HomeMy WebLinkAbout2018-11-27 Rail Agenda PacketCity Council Rail Committee
1
MATERIALS RELATED TO AN ITEM ON THIS AGENDA SUBMITTED TO THE CITY COUNCIL AFTER DISTRIBUTION OF THE AGENDA
PACKET ARE AVAILABLE FOR PUBLIC INSPECTION IN THE CITY CLERK’S OFFICE AT PALO ALTO CITY HALL, 250 HAMILTON AVE.
DURING NORMAL BUSINESS HOURS.
Tuesday, November 27, 2018
Special Meeting
Council Chambers
1:30 PM
Agenda posted according to PAMC Section 2.04.070. Supporting materials are available in
the Council Chambers on the Thursday 12 days preceding the meeting.
PUBLIC COMMENT
Members of the public may speak to agendized items. If you wish to address the Committee on any issue that is on this agenda, please complete a speaker request card located on the table at the entrance to the Council
Chambers/Community Meeting Room, and deliver it to the Clerk prior to discussion of the item. You are not required to give your name on the speaker card in order to speak to the Committee, but it is very helpful. Public comment may be addressed to the full City Council Rail Committee via email at City.Council@cityofpaloalto.org.
Call to Order
Oral Communications
Members of the public may speak to any item NOT on the agenda.
Action Items
1.Project Schedule and Work Plan Update, Including Discussion of the Idea
for Freight Train on Surface and Passenger Train Underground
(Continued From November 14, 2018)
Update on Community Advisory Panel
Update on Interagency Activities
Next Steps and Future Agendas
Adjournment
AMERICANS WITH DISABILITY ACT (ADA) Persons with disabilities who require auxiliary aids or services in using City facilities, services or programs or who
would like information on the City’s compliance with the Americans with Disabilities Act (ADA) of 1990, may contact (650) 329-2550 (Voice) 24 hours in advance.
MEMO
MEMO
……..
RAIL COMMITTEE MEETING
Work Plan Overview
November 14, 2018
2
Work Plan –November
Proposed Meeting Agendas
–CAP Meeting –November 7
•Review Charleston-Meadow Alternatives
•Review evaluation matrix
•Traffic update –data collection
•Pedestrian/bicycle –planned exhibits
–Rail Committee Meeting –November 14
•Review Charleston-Meadow Alternatives
•Review evaluation matrix
•Overview of CAP and stakeholder meetings
–Community Meeting –November 28
•Overview of project need
•Charleston-Meadow Alternatives
–Evaluation matrix
–Construction Costs
•Financing Discussion
Engineering Study Activities
Traffic Data Collection
Stakeholders Meetings
o Santa Clara Valley Water District
o Caltrain
o Safe Routes to School
o TAC Meeting
Develop construction issues and costs
Develop pedestrian/bicycle exhibits
Develop evaluation matrix
Prepare 3D visuals
o Charleston-Meadow
3
Work Plan –December
Proposed Meeting Agenda
–City Council Meeting –December 17
•November Community Meeting Review
•Update on Community Advisory Panel,
Technical Advisory Committee, Stakeholder
Meetings and Interagency Activities
•Grade Separation Alternatives update and
Rail Committee Recommendations
–Tentative CAP and TAC meetings –
December -TBD
Engineering Study Activities
Traffic analysis to evaluate closure at Churchill
Continue evaluating construction issues and
costs
Update alternative exhibits based on feedback
from Community and City Council
Update 3D visuals
Update evaluation matrix
4
Work Plan –January
Proposed Meeting Agenda
–CAP Meeting –January 9, 2019
•Work Plan Update
•Review alternatives for Palo Alto Avenue and
Tunnel within City Limits
•Review traffic analysis for closure at Churchill
–Rail Committee Meeting -TBD
•Work Plan Update
•Review alternatives for Palo Alto and Tunnel
within City Limits
•Review traffic analysis for closure at Churchill
•CAP and TAC meeting overview
–Community Meeting –January 23, 2019
•Review alternatives for Palo Alto and Tunnel
within City Limits
•Review traffic analysis for closure at Churchill
Engineering Study Activities
Complete engineering analysis
Complete traffic analysis
Update exhibits and 3D visuals
Complete construction costs
5
Work Plan –February
Meetings
–City Council Meeting -TBD
•Overview of Community Meeting
•Preferred Alternative
Engineering Study Activities
Prepare final presentation for City Council
meeting
Thank you
……..
RAIL COMMITTEE MEETING
Work Plan Overview
November 14, 2018
2
Work Plan –November
Proposed Meeting Agendas
–CAP Meeting –November 7
•Review Charleston-Meadow Alternatives
•Review evaluation matrix
•Traffic update –data collection
•Pedestrian/bicycle –planned exhibits
–Rail Committee Meeting –November 14
•Review Charleston-Meadow Alternatives
•Review evaluation matrix
•Overview of CAP and stakeholder meetings
–Community Meeting –November 28
•Overview of project need
•Charleston-Meadow Alternatives
–Evaluation matrix
–Construction Costs
•Financing Discussion
Engineering Study Activities
Traffic Data Collection
Stakeholders Meetings
o Santa Clara Valley Water District
o Caltrain
o Safe Routes to School
o TAC Meeting
Develop construction issues and costs
Develop pedestrian/bicycle exhibits
Develop evaluation matrix
Prepare 3D visuals
o Charleston-Meadow
3
Work Plan –December
Proposed Meeting Agenda
–City Council Meeting –December 17
•November Community Meeting Review
•Update on Community Advisory Panel,
Technical Advisory Committee, Stakeholder
Meetings and Interagency Activities
•Grade Separation Alternatives update and
Rail Committee Recommendations
–Tentative CAP and TAC meetings –
December -TBD
Engineering Study Activities
Traffic analysis to evaluate closure at Churchill
Continue evaluating construction issues and
costs
Update alternative exhibits based on feedback
from Community and City Council
Update 3D visuals
Update evaluation matrix
4
Work Plan –January
Proposed Meeting Agenda
–CAP Meeting –January 9, 2019
•Work Plan Update
•Review alternatives for Palo Alto Avenue and
Tunnel within City Limits
•Review traffic analysis for closure at Churchill
–Rail Committee Meeting -TBD
•Work Plan Update
•Review alternatives for Palo Alto and Tunnel
within City Limits
•Review traffic analysis for closure at Churchill
•CAP and TAC meeting overview
–Community Meeting –January 23, 2019
•Review alternatives for Palo Alto and Tunnel
within City Limits
•Review traffic analysis for closure at Churchill
Engineering Study Activities
Complete engineering analysis
Complete traffic analysis
Update exhibits and 3D visuals
Complete construction costs
5
Work Plan –February
Meetings
–City Council Meeting -TBD
•Overview of Community Meeting
•Preferred Alternative
Engineering Study Activities
Prepare final presentation for City Council
meeting
Thank you