HomeMy WebLinkAboutStaff Report 2603-6134CITY OF PALO ALTO
CITY COUNCIL
Special Meeting
Monday, September 28, 2026
Council Chambers & Hybrid
5:30 PM
Agenda Item
14.Direction to advance the Locally Preferred Alternatives for Grade Separation at Churchill
Avenue, Meadow Drive, and Charleston Road crossings to 35% design and
environmental documentation. CEQA Status – Statutorily Exempt. Staff
Presentation, Public Comment
City Council
Staff Report
From: City Manager
Report Type: ACTION ITEMS
Lead Department: Transportation
Meeting Date: September 28, 2026
Report #:2603-6134
TITLE
Direction to advance the Locally Preferred Alternatives for Grade Separation at Churchill Avenue,
Meadow Drive, and Charleston Road crossings to 35% design and environmental documentation. CEQA
Status – Statutorily Exempt.
RECOMMENDATION
Staff recommend that the Council direct proceeding with the 35% design phase and preparation of
environmental documentation for the selected alternatives at the Churchill Avenue, Meadow Drive,
and Charleston Road crossings.
EXECUTIVE SUMMARY
This item seeks approval to continue design plans for the Churchill Avenue Partial Underpass with a
bicycle and pedestrian crossing at Seale Avenue, the Meadow Drive Hybrid, and the Charleston Road
Underpass with a Direct Access Ramp (DAR). Approval would enable proceeding with 35% design and
environmental documentation. Feedback received from both the Rail Committee and City Council will
be considered and incorporated during the early stages of the 35% design phase.
Completion of 15% Design plans established a preliminary project footprint for initiating the
environmental process, identified the primary cost and constructability drivers at each crossing, and
was used to develop an independent cost estimate and preliminary construction schedule for each
delivery scenario. On August 25 and 26, 2026 staff conducted community engagement meetings to
share the 15% design plans and total rough-order-of-magnitude (ROM) project costs at each crossing.
Community feedback received during these meetings is documented in Attachment D.
At the September 8, 2026 Rail Committee meeting, Committee members reviewed the 15% design
concepts, preliminary ROM cost estimates, high-level construction schedules and provided feedback on
total program cost relative to identified funding, how the alternatives were narrowed, wall heights,
and construction period effects at Meadow Drive, and potential property acquisition by crossings.
Committee members also discussed how future decisions on delivery and phasing would be informed
by completion of 35%.
Advancing the alternatives into 35% design will provide additional information to support these future
decisions by refining project costs, schedules, risks, and funding needs, and by identifying
opportunities to phase or sequence implementation in a manner that balances community benefits,
constructability, funding availability, and overall program cost. The City is obligated to advance the
selected grade separation alternatives through the Preliminary Engineering (end of 35% Design) and
Environmental Documentation phase, and this work is fully funded with $20 million in secured external
funds.
BACKGROUND
On December 10 and December 15, 2025, Council directed staff to advance the following alternatives
into 15% Design, with a focus on enhancing safety and access, establishing a preliminary project
footprint for environmental clearance, and minimizing congestion, environmental impacts, and
property impacts:
Churchill Avenue: A Partial Underpass was selected as the Locally Preferred Alternative, with a
partial crossing for motor vehicles at Churchill Avenue, no landscaping strip along Alma Street,
and a pedestrian and bicycle crossing at Seale Avenue/Peers Park with a ramp along Alma
Street. (Consistent with Council direction from November 29, 2021, the Pedestrian and Bicycle
Undercrossing at Churchill remains as the backup alternative and is not being advanced into
preliminary engineering at this time.)
Meadow Drive: A Hybrid Underpass was selected as the preferred alternative, with direction to
evaluate earthen berm and podium options during 15% Design. The Rail Committee reviewed
structural and design considerations for both options on March 10, 2026 and confirmed the
earthen berm with a short bridge over Meadow Drive as the basis of design.
Charleston Road: An Underpass with a Direct Access Ramp (DAR) was selected as the preferred
alternative.
Churchill Avenue Partial Underpass with bicycle and pedestrian crossing at Seale Avenue
Councilmembers have expressed a preference for the Seale Avenue portion of this project to occur in
advance of the Churchill Avenue portion. At Seale Avenue, the bicycle and pedestrian crossing includes
an east ramp along Alma Street that transitions to a tunnel beneath Alma Street and the Caltrain
tracks, terminating in Peers Park and connecting by a west ramp to Castilleja Avenue.
Charleston Road Underpass and Meadow Drive Hybrid Underpass delivered concurrently
Charleston Road Underpass and Meadow Drive Hybrid Underpass delivered sequentially as
back-to-back projects
Charleston Road Underpass Only
Where the track profile must be raised, such as at Meadow Drive, trains cannot remain on the existing
alignment while the permanent improvements are constructed and a temporary shoofly track would
be constructed east of the existing tracks along the southbound portion of Alma Street to maintain rail
service through the work area. The need for a shoofly varies by delivery scenario.
ANALYSIS
15% Design Phase
Churchill Avenue Partial Underpass: The Churchill Ave concept maintains access
across Churchill Avenue with a pedestrian and bicycle bridge adjacent to Caltrain
tracks across the lowered Churchill Avenue roadway. The bridge is anticipated to
include railings and fencing to separate users from the rail corridor and roadway.
Seale Avenue Bicycle and Pedestrian Undercrossing: The Seale Ave concept
provides a 16-foot-wide pedestrian and bicycle path that descends from Seale
Avenue along Alma Street, passes beneath Alma Street and the Caltrain tracks
and emerges in Peers Park, and ramps up to grade at Castilleja Avenue. The tunnel
provides 8 feet of vertical clearance for bicyclists and pedestrians.
Meadow Drive Hybrid Underpass: The Meadow Drive concept would provide a 5-foot
bicycle lane in each direction and 5-foot sidewalks on both sides of Meadow Drive
beneath the rail bridge, reconnecting to existing bicycle facilities at project limits.
Charleston Road Underpass with Direct Access Ramp: The Charleston Road concept
includes a vertically separated pedestrian and bicycle path that would run parallel to
the lowered Charleston Road as it passes beneath Alma Street and the Caltrain
tracks. The path has a minimum clear width of 14 feet through the undercrossing
with at least 8 feet of vertical clearance. The concept also includes an approximately
60-foot pedestrian and bicycle bridge adjacent to the rail bridge that would allow for
bicycle and pedestrian access across Charleston Road.
Connections to the Surrounding Bicycle and Pedestrian Facilities:
The proposed facilities enhance east-west pedestrian and bicycle connections across the
Caltrain corridor and connect to existing facilities at project limits. The Churchill Avenue and
Seale Avenue facilities would connect to the Embarcadero Bike Path and Park Bike
Boulevard and support access to Palo Alto High School and adjacent neighborhoods. At
Meadow Drive, the reconstructed bicycle lanes and sidewalks would connect to existing and
future facilities on East and West Meadow Drive. At Charleston Road, the separated path
and pedestrian and bicycle bridge would connect Charleston Road with Alma Street and
Park Bike Boulevard. These facilities would support access to nearby schools and
neighborhoods destinations. Specific off-site improvements and transitions between the
existing and proposed facilities will be refined.
Cost & Risk: The 15% design phase includes permanent pedestrian and bicycle facilities and
preliminary construction traffic control. Temporary pedestrian and bicycle routes,
accessible detours, barriers, signs, lighting, and other construction-period accommodations
have not been fully defined. Temporary and permanent pedestrian/bicycle access elements
could affect construction staging, property needs, project cost, and construction duration.
Next Step for 35% Design: The 35% design phase will focus on refining the pedestrian and
bicycle facility alignment, accessibility, connections and transitions to existing facilities, as
well as lighting, wayfinding, and other safety features. A traffic study will evaluate
permanent and construction-period pedestrian and bicycle operations, including school
access, temporary closures, detour routes, and options to maintain a usable crossing or
reduce the duration of overlapping closures. The results will inform more detailed
construction phasing and sequencing, access plans, environmental analysis, and updated
cost and schedule information.
Vehicle Access and Circulation
15% Design Objective: Confirm whether each alternative can accommodate safe
pedestrian, bicycle and vehicle movement, and explore methods to maintain pedestrian and
bicycle access during construction. Alma Street is a designated local truck route for its
entire length within the City, which shapes geometric requirements at each crossing.
15% Design Analysis and Findings: Passenger vehicles can generally be accommodated
within the preliminary roadway geometry. However, much of the available stopping and
nighttime headlight sight distance falls below Caltrans criteria, particularly along Alma
Street and at roadway low points. Larger vehicles including semi-trailers, fire apparatus,
school buses, and City garbage trucks require wider turning paths or operational
adjustments at several locations. Recommendations from the analysis include restricting
large vehicles from the Charleston Road Direct Access Ramp, modifying curb and sidewalk
geometry at the upper Alma Street/Charleston Road intersection, installing high visibility
pavement markings, green bike lanes, pedestrian and street lighting. These
recommendations are preliminary and will continue to be evaluated and refined as the
design progresses.
Cost & Risk: The cost estimate developed during the 15% Design phase includes the
principal pedestrian, bicycle and roadway facilities, traffic signals, lighting, pavement
markings, and preliminary construction traffic control. Further geometric changes could
affect retaining walls, bridge elements, utilities, property needs, construction staging, and
project cost.
Next Step for 35% Design: The 35% phase will refine roadway profiles and intersection
geometry, update sight-distance and turning analyses, define vehicle restrictions and traffic
control measures, and advance pedestrian and bicycle facility design. A traffic study will be
completed to evaluate permanent and construction-period operations, including
intersection performance, diversion routes, temporary closures, and emergency, school,
pedestrian, and bicycle access. The results will inform more detailed construction phasing,
detours, access plans, cost estimates, schedule, and environmental analyses.
Utility Identification and Relocation
15% Design Objective: Collect additional information on the existing water, sewer, gas,
electrical, and communication lines to establish a preliminary utility base map and evaluate
potential conflicts with roadway grading, retaining walls, bridges, and excavation.
15% Design Analysis and Findings: Utility records indicate extensive infrastructure at each
crossing. Preliminary concepts for utility relocation include moving utilities into shared
trenches or duct banks, rerouting or lowering individual lines, and protecting certain
facilities in place. The analysis was limited to approximate horizontal locations and utility
depths. Vertical conflicts between utilities were not analyzed during the 15% Design phase.
Cost & Risk: Utility relocation is a significant source of cost and schedule uncertainty. The
estimate includes preliminary relocation quantities, but these cost estimates could be
impacted by unknown utility depths, nonstandard clearance requirements, utility-owner
requirements, and unidentified conflicts. The 24-inch PG&E gas transmission line at
Charleston Road is assumed to remain in place; and any required protection or relocation
of this line will also result in cost and schedule impacts. Responsibility for relocation costs
among the City, Caltrain, and utility owners has not been determined at this stage of the
Project.
Next Step for 35% Design: The 35% Design phase will verify utility locations and depths
through subsurface investigation and potholing, develop a detailed utility conflict matrix,
and refine relocation and protection plans with utility owners. This work will verify
required clearances, as well as preliminary construction sequencing, service interruptions,
property or easement needs and cost responsibility to provide greater clarity on costs
associated with utilities.
Potential Property Acquisition
15% Design Objective: The 15% Design established a preliminary project footprint and
potentially affected parcels using preliminary plans, assessor maps, available right-of-way
records, and limited title information and identified potential property impacts to the level
of detail needed support environmental review and cost estimation. The design aimed to
minimize property impacts while meeting safety, access, constructability, and Caltrain
operating requirements.
15% Design Analysis and Findings: Based on available assessor maps, partial Caltrain right-
of-way information, and limited title reports, the 15% Design preliminarily identifies five
(5) full property acquisitions and 33 additional partial acquisitions of private parcels.
Additional right-of-way from Caltrain may also be required. These findings are preliminary
because a complete boundary survey was not available and the exact limits and types of
property interests have not been established.
Cost & Risk: Final cost estimates will depend on updated project footprints and estimated
extents of permanent acquisition and temporary construction easements. Property
constraints may also affect retaining walls, the temporary shoofly, construction staging and
access, and therefore construction cost and schedule.
Next Step for 35% Design: Property impacts will continue to be evaluated and refined as
design advances. At 15%, the Project identifies the general footprint and potentially
affected properties using preliminary plans, assessor maps, available right-of-way records,
and limited title information. During the 35% Design, additional survey, title, and
engineering information will be used to refine parcel-specific limits, distinguish potential
permanent acquisition and easements from temporary construction easements, and
evaluate design changes that could avoid or reduce impacts. The 35% findings will provide a
more reliable basis for environmental analysis and future coordination with property
owners but will not authorize any real estate acquisition or determine that any specific
property will be acquired. If the Project moves forward following environmental review and
future approvals, some property interests may need to be acquired. Any future acquisition
would require confirmation of the Project and right-of-way needs, compliance with
applicable acquisition procedures, separate funding, and separate authorization. No
construction funding is currently identified or programmed.
Total ROM Project Costs and Preliminary Construction Schedule
Cost estimates become more reliable as design advances and assumptions are replaced by verified
information. The 15% Opinion of Probable Construction Cost is an early-phase estimate. It is
intended to document the current level of design, inform delivery planning, test the
reasonableness of planning-level figures, and focus design efforts during the next phase. It is not
intended to establish a final project budget or serve as the basis for construction funding requests.
Figure 1: Cost Estimate Lifecycle
An independent cost estimator, working separately from the design team, prepared a 15% Opinion
of Probable Construction Cost and a preliminary construction schedule for the project. The cost
estimate was prepared using a design-bid-build procurement assumption for pricing purposes and
reflects how a contractor would price the work based on the current level of design. The estimate
was developed using the available 15% Design and technical materials prepared for this phase,
including the 15% plan sets and supporting technical documentation.
Components of Total ROM Project Cost Ranges
The total ROM project cost ranges include the following major cost categories:
Construction contractor costs, including direct construction costs such as roadway work,
utility work, retaining walls and bridges, jacked boxes, dewatering, track work, rail systems,
overhead contact system (OCS), lighting, power, and landscaping.
Contractor indirect costs, including contractor supervision, staffing, field office
expenses, general and administrative costs, escalation, and contractor fees.
Designer/Engineer of Record costs, including design services needed to advance the
project through subsequent design phases.
Agency costs, including project management, oversight, construction administration,
management, and inspection.
Environmental documentation and permitting, including costs associated with
CEQA/NEPA documentation and required permits.
Trans America Services Inc. (TASI), a third party managing the Caltrain operation as
included in the total project cost assumptions.
Real property and easements, including property acquisition and temporary or
permanent easement needs.
Escalation, reflecting the assumed timing of construction and year-of-expenditure cost
basis.
Project contingency, reflecting uncertainty at the current level of design and the need for
refinement as the project advances.
Costs are developed in 2026 dollars, with escalation applied beginning in 2027 at 5
percent per year using a project midpoint approach
Total ROM project costs are expressed in year-of-expenditure dollars, meaning they
include escalation.
Craft labor rates reflect current Northern California union agreements.
Work within the Caltrain right-of-way is assumed to occur at night, including in
residential areas where night work is assumed to be permissible.
Weekend closures are assumed for temporary rail bridge installation and removal and for
track cutovers.
Productivity inefficiency factors are applied to account for work adjacent to active rail
operations.
Construction is assumed to begin in 2032.
Table 1: Total ROM Project Cost Range and Preliminary Construction Duration
Delivery Scenario Total ROM Project Cost
Range
Preliminary
Construction Duration
$420M – $450M 3-4 Years
$1B - $1.1B 5 Years
$ 1.2B -$1.3B 9 Years
$480M - $530M 4 Years
Primary Cost Drivers of the 15% Estimate
The 15% total ROM project costs is a tool to support decision-making and is based on the current
level of design, supplemented by contractor means-and-methods assumptions and estimating
judgement where information was incomplete.
Design Progression: The 15% estimate includes allowances and contingency for cost
elements that are not fully defined at this stage of design. Allowances were included for
design, potential real estate and easement needs. Contingency was included for other
project-specific risk items. These buffers reflect the preliminary nature of 15% Design and
will be updated as the project advances and additional technical work is completed.
Physical Cost Drivers: Major Cost Drivers include retaining walls and bridges, jacked-box
structures, shoofly and track work, signal and OCS changes, deep excavation and
dewatering, pump stations and drainage, potential ground improvement, and extensive
utility relocation.
Schedule and Market Drivers: Cost and duration are highly dependent on delivery method,
sequencing, construction work windows and flagging, weekend shutdowns, night work,
productivity next to active rail, anticipated start of construction, escalation, and contractor
market conditions.
Key Findings for Charleston Road and Meadow Drive Delivery Scenarios:
The Charleston Road and Meadow Drive delivery scenarios have different implications for
construction duration, access across the Caltrain corridor, and the timing of construction impacts
in the community.
Under the combined delivery scenario, the preliminary construction schedule is approximately 60
months. During that period, closure of Meadow Drive and Charleston Road crossings would overlap
for approximately 26 months. Based on current design and sequencing assumptions, there would
be no open crossing of the Caltrain corridor between Meadow Drive and Charleston Road during
that overlap, with the nearest available crossings at Oregon Expressway and San Antonio Road.
Staff recognizes this as a significant community impact. Exploring design solutions to reduce or
eliminate the overlap is a specific objective of the 35% Design phase, Staff will continue to evaluate
sequencing refinements, including whether the roadway bridge over Alma Street can be
constructed in advance of the railroad work, as discussed at the May 2026 Rail Committee
meeting.
Utilities: Utility profiles have not yet been developed, so utility depths were estimated
using standard assumptions. A 24-inch gas transmission line along Charleston Road is
assumed to remain in place with no associated work. Utility relocation cost responsibility
between the City, Caltrain, and utility owners has not been established.
Potential Property Acquisition: Property impacts will be refined as design advances.
Groundwater and dewatering: No groundwater flow rate data was available at 15%
Design. Dewatering assumptions were developed from geotechnical groundwater
elevations and anticipated excavation depths, and will be refined through additional
geotechnical investigation, groundwater monitoring, and pumping tests.
Ground improvement: Deep soil mixing for soil stabilization beneath the jacked boxes at
Churchill Avenue and Charleston Road, and beneath the mechanically stabilized earth
system at Meadow Drive, may be required but is not included in the current estimate.
Box jacking performance: Limited space for casting and launching the jacked box segments
creates a risk that the box could deviate downward during jacking. Additional ground
improvement or other mitigation may be required, and a separate contingency is
recommended.
Construction sequencing: Cost and duration are sensitive to whether Meadow Drive and
Charleston Road are delivered together or separately, and to the sequencing of roadway and
railroad work within each scenario.
Railroad work windows and flagging: Track access, weekend shutdown availability, and
flagging requirements will be determined with Caltrain. Flagging is carried as a separate
allowance rather than in the base estimate.
Escalation and construction start year: Escalation is applied based on an assumed
construction start. A later start increases cost. Construction start depends on funding
availability.
As the project advances into 35% Design, staff will continue to refine the total ROM project cost
ranges and preliminary construction schedules, particularly as key assumptions are confirmed or
updated. Future updates will incorporate more detailed information on construction sequencing,
rail service requirements, utility conflicts, property needs, permitting requirements, market
conditions, and other design refinements that affect project cost and schedule.
Components of Total ROM Project Cost Ranges
The total ROM project cost ranges include the following major cost categories:
Construction contractor costs, including direct construction costs such as roadway work,
utility work, retaining walls and bridges, jacked boxes, dewatering, track work, rail systems,
overhead contact system (OCS), lighting, power, and landscaping.
Contractor indirect costs, including contractor supervision, staffing, field office
expenses, general and administrative costs, escalation, and contractor fees.
Designer/Engineer of Record costs, including design services needed to advance the
project through subsequent design phases.
Agency costs, including project management, oversight, construction administration,
management, and inspection.
Environmental documentation and permitting, including costs associated with
CEQA/NEPA documentation and required permits.
Trans America Services Inc. (TASI), a third party managing the Caltrain operation as
included in the total project cost assumptions.
Real property and easements, including property acquisition and temporary or
permanent easement needs.
Escalation, reflecting the assumed timing of construction and year-of-expenditure cost
basis.
Project contingency, reflecting uncertainty at the current level of design and the need for
refinement as the project advances.
Key Estimate Assumptions
The total ROM project costs were developed using the following key assumptions:
Costs are developed in 2026 dollars, with escalation applied beginning in 2027 at 5
percent per year using a project midpoint approach
Total ROM project costs are expressed in year-of-expenditure dollars, meaning they
include escalation.
Craft labor rates reflect current Northern California union agreements.
Work within the Caltrain right-of-way is assumed to occur at night, including in
residential areas where night work is assumed to be permissible.
Weekend closures are assumed for temporary rail bridge installation and removal and for
track cutovers.
Productivity inefficiency factors are applied to account for work adjacent to active rail
operations.
Construction is assumed to begin in 2032.
The estimate corresponds to an approximate Association for the Advancement of Cost Engineering
(AACE) Class 3 estimate.
The table below summarizes the total ROM project cost ranges and preliminary construction durations
for each delivery scenario.
Table 1: Total ROM Project Cost Range and Preliminary Construction Duration
Delivery Scenario
Total ROM Project
Cost Range
Preliminary
Construction Duration
Churchill Avenue Partial Underpass with
bicycle and pedestrian crossing at Seale
Avenue
$420M – $450M 3-4 Years
Charleston Road Underpass and
Meadow Drive Hybrid delivered
concurrently
$1B - $1.1B 5 Years
Charleston Road Underpass and
Meadow Drive Hybrid delivered
sequentially as back-to-back projects
$ 1.2B -$1.3B 9 Years
Charleston Road Underpass constructed
on its own $480M - $530M 4 Years
Primary Cost Drivers of the 15% Estimate
The 15% total ROM project costs is a tool to support decision-making and is based on the current
level of design, supplemented by contractor means-and-methods assumptions and estimating
judgement where information was incomplete.
Design Progression: The 15% estimate includes allowances and contingency for cost
elements that are not fully defined at this stage of design. Allowances were included for
design, potential real estate and easement needs. Contingency was included for other
project-specific risk items. These buffers reflect the preliminary nature of 15% Design and
will be updated as the project advances and additional technical work is completed.
Physical Cost Drivers: Major Cost Drivers include retaining walls and bridges, jacked-box
structures, shoofly and track work, signal and OCS changes, deep excavation and
dewatering, pump stations and drainage, potential ground improvement, and extensive
utility relocation.
Schedule and Market Drivers: Cost and duration are highly dependent on delivery method,
sequencing, construction work windows and flagging, weekend shutdowns, night work,
productivity next to active rail, anticipated start of construction, escalation, and contractor
market conditions.
Key Findings for Charleston Road and Meadow Drive Delivery Scenarios:
The Charleston Road and Meadow Drive delivery scenarios have different implications for
construction duration, access across the Caltrain corridor, and the timing of construction impacts
in the community.
Under the combined delivery scenario, the preliminary construction schedule is approximately 60
months. During that period, closure of Meadow Drive and Charleston Road crossings would overlap
for approximately 26 months. Based on current design and sequencing assumptions, there would
be no open crossing of the Caltrain corridor between Meadow Drive and Charleston Road during
that overlap, with the nearest available crossings at Oregon Expressway and San Antonio Road.
Staff recognizes this as a significant community impact. Exploring design solutions to reduce or
eliminate the overlap is a specific objective of the 35% Design phase, Staff will continue evaluate
sequencing refinements, including whether the roadway bridge over Alma Street can be
constructed in advance of the railroad work, as discussed at the May 2026 Rail Committee
meeting.
Under separate delivery, the preliminary construction schedule is approximately 92 months. This
approach would keep at least one crossing open throughout construction, but it would extend the
overall period of construction activity compared to the combined delivery scenario. Charleston
Road would also remain subject to construction restrictions for approximately 52 months during
the later Meadow Drive work. Separate delivery would also be expected to increase overall cost by
duplicating scopes of work, including roadway removals and improvements, fencing, signage and
striping, landscaping, and trackwork, and by extending indirect costs for both the contractor and
the City.
Utilities: Utility profiles have not yet been developed, so utility depths were estimated
using standard assumptions. A 24-inch gas transmission line along Charleston Road is
assumed to remain in place with no associated work. Utility relocation cost responsibility
between the City, Caltrain, and utility owners has not been established.
Potential Property Acquisition: Property impacts will be refined as design advances.
Groundwater and dewatering: No groundwater flow rate data was available at 15%
Design. Dewatering assumptions were developed from geotechnical groundwater
elevations and anticipated excavation depths, and will be refined through additional
geotechnical investigation, groundwater monitoring, and pumping tests.
Ground improvement: Deep soil mixing for soil stabilization beneath the jacked boxes at
Churchill Avenue and Charleston Road, and beneath the mechanically stabilized earth
system at Meadow Drive, may be required but is not included in the current estimate.
Box jacking performance: Limited space for casting and launching the jacked box segments
creates a risk that the box could deviate downward during jacking. Additional ground
improvement or other mitigation may be required, and a separate contingency is
recommended.
Construction sequencing: Cost and duration are sensitive to whether Meadow Drive and
Charleston Road are delivered together or separately, and to the sequencing of roadway and
railroad work within each scenario.
Railroad work windows and flagging: Track access, weekend shutdown availability, and
flagging requirements will be determined with Caltrain. Flagging is carried as a separate
allowance rather than in the base estimate.
Escalation and construction start year: Escalation is applied based on an assumed
construction start. A later start increases cost. Construction start depends on funding
availability.
ranges and preliminary construction schedules, particularly as key assumptions are confirmed or
updated. Future updates will incorporate more detailed information on construction sequencing,
rail service requirements, utility conflicts, property needs, permitting requirements, market
conditions, and other design refinements that affect project cost and schedule.
Table 2: Total ROM Program Delivery Cost Estimates
Program Delivery Scenario Total Program Cost
Churchill Avenue plus Meadow Drive and Charleston Road
concurrently
Churchill Avenue plus Meadow Drive and Charleston Road
sequentially
FISCAL/RESOURCE IMPACT
Environmental Documentation phase. Therefore, this item has no new fiscal impact.
Funding Sources Awarded &
Allocated
Awarded &
Unallocated Unawarded
$6 M --
$14 M -$350 M
-$23 M -
$9 M -$30 M
$432 M
STAKEHOLDER ENGAGEMENT
2026. The community engagement summary is included in Attachment E. The CSTSC briefing focused
on access routes serving Palo Alto High School and other Palo Alto Unified School District schools. The
PABAC briefing focused on planned pedestrian and bicycle infrastructure and routes at the crossings
and regional connections within Palo Alto.
Attachment D. Staff will incorporate Rail Committee
feedback, along with City Council feedback received on September 28, 2026, during the early stages of
the 35% Design phase.
ENVIRONMENTAL REVIEW
ATTACHMENTS
Attachment E: Community Engagement Summary
APPROVED BY:
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Churchill Avenue - Partial Underpass
Upper Alma St
Ch
u
r
c
h
i
l
l
A
v
e
Ch
u
r
c
h
i
l
l
A
v
e
Ke
l
l
o
g
g
A
v
e
Ke
l
l
o
g
g
A
v
e
Co
l
e
r
i
d
g
e
A
v
e
Co
l
e
r
i
d
g
e
A
v
e
Ch
u
r
c
h
i
l
l
A
v
e
Ch
u
r
c
h
i
l
l
A
v
e
Lower Alma St
LEGEND
Preliminary Project Footprint
Caltrain Right-of-Way
Bicycle and Pedestrian Routes
from the Seale Ave Underpass
Access and Connectivity
NOR
T
H
80
Graphic Scale in Feet
160 3200
Retaining walls
Connection to
Embarcadero Bike Path
Retaining walls
Bridge for railroad tracks
Bicycle and
pedestrian bridge One northbound through lane to intersection of
Lower Alma St and Churchill Ave (west leg)
One-way through traffic
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Churchill Avenue - Partial Underpass Rendering
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Seale Avenue - Bicycle and Pedestrian Undercrossing
Alma StAlma St
Se
a
l
e
A
v
e
Se
a
l
e
A
v
e
Te
n
n
y
s
o
n
A
v
e
Te
n
n
y
s
o
n
A
v
e
Ri
n
c
o
n
d
a
A
v
e
Ri
n
c
o
n
d
a
A
v
e
Par
k
B
l
v
d
Par
k
B
l
v
d
LEGEND
Preliminary Project Footprint
Caltrain Right-of-Way
Bicycle and Pedestrian Routes
from the Seale Ave Underpass
Access and Connectivity
NOR
T
H
80
Graphic Scale in Feet
160 3200
PEERS PARKPEERS PARK
Retaining walls
Retaining wallsDriveway
access
maintained
Bicycle and pedestrian
connection under Alma
Street and railroad tracks
Bicycle and pedestrian
ramp to/from crossing
Bicycle and pedestrian
ramp to/from crossing
Bicycle and pedestrian connection to
Palo Alto High School from Peers Park
Alma St travel lanes shifted
west to accommodate ramp
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Seale Avenue - Bicycle and Pedestrian Undercrossing Rendering
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Meadow Drive - Hybrid
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Meadow Drive - Hybrid Rendering
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Charleston Road - Underpass with Direct Access Ramp
City of Palo Alto Project for Grade Separation:
Churchill Avenue | Meadow Drive | Charleston Road Funded by:
Charleston Road - Underpass with Direct Access Ramp Rendering
Comment # Comment Project Team Respons Comment Sourc Associated Concept Community Themes
1
Has projected usage of the Seale Avenue bicycle and pedestrian
undercrossing been studied? Use by Palo Alto High School students
may be limited because California Avenue is nearby and students
north of Seale Avenue tend to cross at Embarcadero Road.
Projected usage of the Seale Avenue bicycle and pedestrian undercrossing was not forecasted during the 15% Design
phase, which focused on confirming safe pedestrian and bicycle accommodation, establishing a preliminary project
footprint, and maintaining access during construction. The crossing was directed by City Council in December 2025 as
part of the Churchill Avenue Partial Underpass alternative to provide a grade separated connection between the
neighborhoods east of Alma Street and Peers Park. A traffic study during 35% Design will evaluate permanent and
construction period operations, including school, pedestrian, and bicycle access. Staff briefed the Community Safety and
Traffic Safety Committee on August 27, 2026 regarding access routes serving Palo Alto High School and other district
schools.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Bicycle, Pedestrian, and School Access
2
How would the project change student and parent traffic on East
Meadow Drive, where residents already live with it, or would
conditions remain similar to today?
The project team recognizes that East Meadow Drive serves students, families, and nearby residents. As a part of project
development, traffic operations and circulation are being evaluated to understand how each concept could affect local
travel patterns including school-related traffic.Community Meeting Meadow Drive Hybrid Bicycle, Pedestrian, and School Access
3
If construction temporarily makes a residence uninhabitable, what
relocation assistance, comparable housing, and moving-cost support
may be available?
Information shown about potential right-of-way needs is for planning purposes only. The project has not received
environmental clearance, and is not substantially funded for construction; therefore, is not approved for
implementation. Nothing at this stage authorizes or commits to any property acquisition or temporary easement. If the
project advances and funding is identified, defined state and federal processes apply, including the Uniform Relocation
Assistance and Real Property Acquisition Policies Act. Those processes govern questions about assistance and
comparable housing, and they apply only once a project is approved and substantially funded. During 35% Design there
will be opportunities for the City and Caltrain to provide additional information to the community on how these
processes work.Community Meeting Not Concept Specific
Construction Considerations
Housing Assistance
4
Why does the current cost estimate for the Meadow Drive Hybrid
appear higher than the Charleston Road Underpass, and what
changed from earlier estimates, when the hybrid was much less
expensive?
The earlier figures were planning-level, construction-only estimates that had not been vetted or validated, and they
reflected a different set of concepts, including a combined Meadow Drive and Charleston Road underpass option that is
not part of the current scope. The 15% figures are total project costs in year-of-expenditure dollars, adding design,
agency costs, environmental documentation and permitting, real property and easements, escalation, and contingency,
which accounts for much of the apparent increase. The two delivery scenarios also cover different amounts of work. The
Meadow Drive Hybrid scenario grade separates both Meadow Drive and Charleston Road, while the Charleston Road
Underpass scenario grade separates Charleston Road only. Estimates will continue to be refined as design advances and
do not establish a project budget.Community Meeting
Meadow Drive Hybrid; Charleston Road Underpass - Direct
Access Ramp Total Project Cost Estimate
5
Would the proposed grade separation concepts improve conditions
compared with the existing crossings?
The proposed grade separation concepts are intended to eliminate at-grade conflicts between trains and roadway users,
which can improve safety, reduce delays caused by train crossings, and enhance connectivity across the rail corridor. Community Meeting All concepts Design Elements and Development
6
Why are different grade-separation concepts proposed for Charleston
Road and Meadow Drive?
City Council selected a different concept at each location in December 2025: an Underpass with a Direct Access Ramp at
Charleston Road and a Hybrid Underpass at Meadow Drive. The two sites have different utility, right-of-way, drainage,
and construction conditions, and the amount of vertical change needed differs. In the combined delivery scenario, the
tracks would be raised about 16 feet at Meadow Drive and about 4.5 feet at Charleston Road, and the roadway would
be lowered about 7 feet at Meadow Drive and about [20] feet at Charleston Road. Council also recognized that findings
at one crossing do not always transfer to the other.Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Design Elements and Development
7
Kellogg Avenue and Alma Street are already gridlocked from Palo Alto
High School and Castilleja traffic, and the project would add further
difficulty and gridlock. Consider closing Kellogg Avenue, and possibly
Churchill Avenue and Coleridge Avenue, as was done in College
Terrace.
A traffic operations analysis has already been completed for the project. It evaluated Churchill Avenue, Meadow Drive,
Charleston Road, Alma Street, and adjacent intersections under existing and future conditions, including level of service
and queuing, to compare how each concept would affect nearby intersections and local street traffic. Traffic conditions
during construction, including access, detours, and operations on surrounding streets, will be evaluated as the design
advances. Suggested changes to local streets, such as closures or turn restrictions, would be considered separately from
the grade separation design and would require City action and further community input. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Construction Considerations
8
What did the near-term safety improvements presented by Caltrain
cost, and how are they being paid for?
The near-term safety improvements presented at the meeting are being delivered by Caltrain separately from the grade
separation project and are not funded through the grade separation project. Along the Alma Street corridor at Churchill
Avenue, Meadow Drive, and Charleston Road, Caltrain has installed delineators, solar markers, pavement markings, and
updated striping, and has implemented anti-trespass panel and Rail Sentry safety pilots. Cost and funding details for that
work are maintained by Caltrain and can be confirmed with Caltrain staff. The City is separately advancing near-term
safety improvements at the Alma Street and Charleston Road crossing through the federal Section 130 program
administered by the California Department of Transportation (Caltrans). Caltrans is providing $700,000 for the design
phase, the identified improvements were determined to be fully eligible for Section 130 funding, and the City will
request additional Section 130 funds for construction once construction documents and an engineer's estimate are
complete.Community Meeting Not Concept Specific
Design Elements and Development;
Total Project Cost Estimate
9
Neighbors near Alma Street and Park Boulevard already experience
train horn blasts every day at 96 to 110 decibels. How would the
project protect them from noise if trains are shifted onto temporary
tracks along Alma Street for five to ten years?
Noise, vibration, air quality, traffic, and access are among the topics that will be studied through the environmental
review under the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA),
beginning in fall 2026. A temporary track, called a shoofly, would only be needed where the track profile is raised. It
would be removed after construction and the corridor restored. For high-level estimating purposes, the cost estimate
assumes work within the Caltrain right-of-way occurs during off-peak periods, with weekend closures for certain
activities such as track cutovers. No work windows are approved. Construction work windows, flagging requirements,
and weekend shutdown availability will be determined with Caltrain as design advances. Specific noise levels, work
hours, and measures have not been established and will come from the environmental review and later design phases. Community Meeting Not Concept Specific
Design Elements and Development;
Construction Considerations
10
How is flooding risk being evaluated for the proposed underpasses?
Oregon Expressway floods when it rains.
Each underpass would have a stormwater pump station. At the 15% Design level, pumps are sized for a 50-year storm,
with a 100-year check to evaluate backup, surcharge, and flooding conditions. Each pump station includes a standby
pump so it can keep operating during maintenance or a pump failure. Inlets and catch basins are spaced to capture a 10-
year storm while keeping a travel lane clear of water. During 35% Design, the team will confirm that the City's
downstream storm drain system can receive the pumped flows, and will further evaluate how the Churchill Avenue and
Seale Avenue pump stations interact, since the current layout makes them dependent on one another. Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
11
How will the proposed design at Charleston Road address the risk of
bicyclists traveling in the wrong direction?
The project team is evaluating how all users, including bicyclists, will navigate proposed improvements. Design elements
such as signage, markings, and intersection configuration will be reviewed to help minimize confusion and support safe
bicycle travel.Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
12
Are the renderings shown of the Charleston Road Underpass in the
correct orientation?
The rendering of the Charleston Road Underpass is an aerial view looking southeast along the corridor, not a north-up
map. From that viewpoint, Alma Street and the tracks appear on the opposite sides from how they would read on a plan
view, which can make the orientation look reversed. Renderings are simplified visualizations and may not show every
existing feature in exact detail, but the orientation shown is correct for that viewpoint. Community Meeting Charleston Road Underpass - Direct Access Ramp Design Elements and Development
13
What is the length of the temporary tracks, and how would
electrified trains be handled on them? The term shoofly is not
understood by the public, materials should state plainly that trains
would run along Alma Street, reducing it to two lanes, approximately
50 feet from homes.
The temporary track would be approximately 6,500 feet long and would shift approximately 50 feet towards Alma
Street. Supporting infrastructure for the rails would cause traffic impacts on Alma Street for 5,500 feet and may extend
up to 37 feet into the roadway.Community Meeting Not Concept Specific Construction Considerations
14
How do the proposed grade-separation concepts compare with a
viaduct alternative in cost, construction duration, property impacts,
flooding risk, and tree removal?
A viaduct is not among the concepts being carried through this phase. Alternatives were screened earlier through the
Connecting Palo Alto effort and the Rail Crossing Community Advisory Committee, and City Council selected the current
alternatives in December 2025. Because a viaduct was not advanced, the 15% Design did not develop cost, schedule,
property, drainage, or tree information for that option, so a side-by-side comparison is not available. Tree removal,
drainage, and property effects for the selected concepts will be developed further during 35% Design and studied in the
environmental review.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing;
Meadow Drive Hybrid; Charleston Road Underpass - Direct
Access Ramp
Design Elements and Development;
Total Project Cost Estimate;
Construction Considerations
15
What is the completed length of each grade separation, so that total
project cost per mile can be compared across the three locations?
Separately, at the Seale Avenue and Peers Park bicycle and pedestrian
crossing, has an alignment farther from the northwest edge of the
park been considered to avoid removing trees?
Project limits differ at each crossing and are shown on the 15% Design plan exhibits posted on the project website. The
estimate was not developed on a cost-per-mile basis. It is a total project cost estimate of the specific work at each
location, prepared by an independent cost estimator using the 15% plans and supporting technical documentation, and
corresponds to an approximate AACE Class 3 estimate. The amount of structure, utility, drainage, and rail work varies
substantially between crossings, so a per-mile figure would not describe those differences. On the Seale Avenue
alignment, the ramp rises through private property and the north edge of Peers Park to reach Castilleja Avenue.
Alignment refinements, including tree effects, will be evaluated during 35% Design and in the environmental review. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing
Design Elements and Development;
Total Project Cost Estimate
16
Do the cost estimates include long term operation and maintenance
of the pumps required to prevent flooding in the lowered roadway
sections?
Cost estimates do not contain operations and maintenance costs. Costs for pump infrastructure are included in the
estimate. Community Meeting Not Concept Specific
Design Elements and Development;
Total Project Cost Estimate
17
Where can the public find current Caltrain ridership data and what is
the outlook for Caltrain over the next 50 years?
Current ridership reports, bicycle planning documents, and information about bicycle access on Caltrain can be found on
Caltrain's official website. Community members may also contact Caltrain directly for the most up-to-date information
regarding ridership and bicycle-related programs.Community Meeting Not Concept Specific
Bicycle, Pedestrian, and School Access;
Design Elements and Development
18
How are long term changes in travel behavior being considered,
including remote work, commuting by car one or two days per week,
and the growth of ride hailing services, e-bikes, and e-scooters?
The previous traffic analysis forecasted future traffic volumes based on historical traffic patterns, input from the City,
and planned future developments. Those forecasts were used to compare how each concept would perform under
existing and future conditions.Community Meeting Not Concept Specific Design Elements and Development
19
What does the future look like under scenario planning, and will
Caltrain fares continue to be subsidized at approximately 70 percent?
The grade separation alternatives are developed to accommodate future conditions along the corridor, including
increased Caltrain service and longer gate downtimes, so that the crossings continue to function as rail service grows.
Caltrain fares, fare policy, and operating subsidy are set by Caltrain and are outside the scope of this project. Fare
information is available on the Caltrain website at caltrain.com. Community Meeting Not Concept Specific
Design Elements and Development;
Total Project Cost Estimate
20
The Charleston Road and Meadow Drive project extents measure
6,500 feet, or 1.23 miles. On that basis the cost per mile, plus long
term maintenance, far exceeds comparable viaducts, including high
speed rail projects, which have been estimated at approximately
$200 million per mile. The assertion that viaducts are much more
expensive is disputed. Please cite the sources supporting that
assertion.
The estimate is not a cost per mile. It was prepared by an independent cost estimator working separately from the
design team, using the 15% plans and supporting technical documentation, and it prices the specific work at Charleston
Road and Meadow Drive. That work includes a temporary shoofly track, retaining walls and bridges, jacked box
structures, deep excavation and dewatering, pump stations and drainage, signal and overhead contact system changes,
extensive utility relocation, and work next to an active electrified railroad. It corresponds to an approximate AACE
(Association for the Advancement of Cost Engineering International) Class 3 estimate. Costs are in 2026 dollars,
escalated beginning in 2027 at [4] percent per year, with construction assumed to begin in 2032. The project has not
prepared a cost comparison with viaduct projects, and no such comparison was developed as part of the 15% Design.
The assumptions, quantities, and unit costs behind the estimate are documented in the Basis of Estimate prepared by
the independent cost estimator.Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp
Design Elements and Development;
Total Project Cost Estimate
21
The design should serve the next 100 years. Build it correctly now and
pay the current cost rather than fixing it 20 years from now.
The project team is evaluating how each concept would perform over the long term, including factors such as safety,
maintenance, operational efficiency, infrastructure lifespan, and adaptability to future transportation needs. Community Meeting Not Concept Specific
Design Elements and Development;
Total Project Cost Estimate
22
At Meadow Drive, how does raising the track profile benefit the City
given the project cost and the effects on adjacent neighborhoods, and
why was it selected as the preferred alternative?
At Meadow Drive, the concept raises the tracks by up to about 16 feet and lowers the roadway by about 7 feet, rather
than raising the tracks the full height needed for clearance. Visual character, noise, air quality, traffic, and access will be
studied in the environmental review under CEQA and NEPA, beginning in fall 2026. Urban design elements have not
been designed and will be developed during 35% Design with further community input. Community Meeting Meadow Drive Hybrid Design Elements and Development
23
Grade separation would intentionally restrict access to the rail
corridor. How does the project address youth suicide prevention,
effects on property values and land use, noise, and pedestrian access?
Grade separation removes the at-grade crossings and creates a sealed corridor at these locations, eliminating pedestrian,
bicycle, and vehicle access onto the railroad tracks. That separation is the primary safety benefit of the project, reducing
conflicts between trains and people and reducing opportunities for unauthorized access to the corridor. Caltrain is also
advancing near-term safety measures along the corridor, including anti-trespass panel and Rail Sentry pilots, separate
from the grade separation project. Access across the corridor would be maintained through the grade separated
crossings, and dedicated bicycle and pedestrian facilities are included at each location. Noise, land use, and pedestrian
access will be evaluated through environmental review under the California Environmental Quality Act (CEQA) and the
National Environmental Policy Act (NEPA), beginning in fall 2026. Community Meeting Not Concept Specific
Bicycle, Pedestrian, and School Access;
Design Elements and Development
24
What improvements are proposed for northbound Alma Street near
Embarcadero Road, where the road currently narrows from two lanes
to one?
The grade separation project covers Churchill Avenue, Meadow Drive, and Charleston Road. The Churchill Avenue
alternative includes the bicycle and pedestrian crossing at Seale Avenue using the Alma Street ramp as part of that
design. Northbound Alma Street near Embarcadero Road is outside the project limits and is not part of this design work.
The Churchill Avenue bicycle and pedestrian concept does connect to the Embarcadero Bike Path. The 35% Design traffic
analysis will evaluate how traffic moves to and from the project area, which can identify effects on nearby streets. Community Meeting Not Concept Specific
Design Elements and Development;
Construction Considerations
25
How would the revised Direct Access Ramp affect setbacks along East
Charleston Road? Reduced front yards would have an impact on our
safety from traffic, environmental exposure, and resale value.
The 15% Design established a preliminary project footprint and identified potential property needs to support
environmental review and cost estimating. The design was developed to reduce property impacts while meeting safety,
access, constructability, and Caltrain operating requirements. These findings are preliminary. During 35% Design,
additional survey, title, and engineering information will refine parcel-specific limits, distinguish permanent needs from
temporary construction easements, and evaluate design changes that could avoid or reduce impacts. Community Meeting Charleston Road Underpass - Direct Access Ramp Design Elements and Development
26
Would a U-turn at Charleston Road and Mumford Place include traffic
control measures appropriate for a school route?
Traffic control at individual intersections and turnarounds has not been established at the 15% Design level. The 35%
Design traffic analysis will evaluate intersection performance, turning movements, and emergency, school, pedestrian,
and bicycle access. Signal needs and other traffic control measures would be determined through that analysis and in
coordination with City Transportation staff.Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
27
How would construction impacts on Charleston Road residents be
evaluated and mitigated?
Construction effects, including noise, vibration, air quality, traffic, and access, will be studied through the environmental
review under CEQA and NEPA, beginning in fall 2026. Construction sequencing and access will continue to be developed
as the design advances. Measures to address construction effects would be identified through that work. Community Meeting Charleston Road Underpass - Direct Access Ramp Construction Considerations
28
How do the Charleston Road and Meadow Drive concepts compare
with the elevated-track and street-underpass design in San Carlos?
A comparison with the San Carlos grade separation was not prepared as part of the 15% Design. The Meadow Drive
concept uses a similar general approach: the tracks would be raised on an embankment supported by retaining walls
with a bridge over the roadway, and the roadway would be lowered to meet the required clearance. At Meadow Drive,
the tracks would be raised by up to about 16 feet and the roadway lowered by about 7 feet. The height, wall design, and
street layout at any location are shaped by the utilities, right-of-way, drainage, and rail operating conditions at that site. Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Design Elements and Development
29
How high are the tracks elevated in San Carlos relative to cross street
grade, and how high can the tracks feasibly be raised at Meadow
Drive and Charleston Road?
In the current concepts, the tracks would be raised by up to about 16 feet at Meadow Drive. In the scenario where
Meadow Drive and Charleston Road are built together, the tracks at Charleston Road would be raised by about 4.5 feet.
How much the track can be raised is governed by Caltrain design criteria for track grades, the clearance required over
the roadway, the corridor length available to return the tracks to existing grade, and effects on adjacent properties.
Track elevations in San Carlos were not reviewed as part of this work. Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Design Elements and Development
30
Would cyclists and e-bike riders, who travel faster than other cyclists
and pedestrians, be able to travel with vehicles at Meadow Drive and
Charleston Road?
The 15% Design provides separated bicycle and pedestrian facilities at both crossings, including protected bicycle lanes
at Meadow Drive and a bicycle and pedestrian bridge over the roadway at Charleston Road. Whether riders use those
facilities or the roadway, and any restrictions on where e-bikes may operate, are governed by City policy and state law
rather than by this project's design. Facility widths, transitions, and how riders traveling at different speeds are
separated from people walking will continue to be refined during 35% Design. Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
31
Will the eastbound Alma Street–Oregon Expressway slip lane be
evaluated for safety and access improvements?
That slip lane is outside the limits of the grade separation project and is not part of this design work. Traffic operations
in and around the project area during construction will be evaluated as the design advances, which can identify effects
on nearby streets and intersections.Community Meeting Not Concept Specific
Bicycle, Pedestrian, and School Access;
Design Elements and Development
32
What are the two reasons that Charleston Road and Meadow Drive
are not both hybrid concepts with raised track at each location? A
short answer is requested.
City Council selected a different concept at each location in December 2025, following alternatives evaluation and
community input at each crossing: a Hybrid Underpass at Meadow Drive and an Underpass with a Direct Access Ramp at
Charleston Road. The site conditions also differ, including utilities, right-of-way width, drainage, and how much the track
profile would need to be raised, which is why the same solution does not apply equally at both crossings. Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Design Elements and Development
33
Would the temporary tracks affect northbound and southbound
traffic on Alma Street, and would that effect last the entire nine year
construction duration of the combined Charleston Road and Meadow
Drive scenario?
The temporary track, called a shoofly, would reduce Alma Street to one lane in each direction where it is in place. Traffic
conditions during construction, including the duration and extent of lane reductions on Alma Street, will be analyzed
during 35% Design, and construction phasing and sequencing will continue to be refined. Community Meeting
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Construction Considerations
34
How would the proposed designs affect potential future Caltrain
improvements, including possible undergrounding of the tracks?
The project team is coordinating with Caltrain to understand how the proposed concepts may interact with future rail
corridor improvements. Future opportunities and constraints will be considered as part of the ongoing planning and
evaluation process.Community Meeting Not Concept Specific Design Elements and Development
35
How would the Churchill Avenue concept affect signalized access
from Old Palo Alto to southbound Alma Street?
In the current Churchill Avenue concept, part of Alma Street would be lowered along with Churchill Avenue, creating a
signalized intersection at the lower level where left and right turns between Churchill Avenue and Alma Street are
provided. One outer lane on the north side of Alma Street would remain at its existing elevation and continue to connect
with nearby cross streets. How left turns from neighborhood streets onto southbound Alma Street would operate has
not been resolved at the 15% Design level and will be evaluated as the design advances. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
36
Could another location for a specialized location provide a signalized
southbound connection to Alma Street if access changes occur?
Neighborhood access and circulation around Churchill Avenue will continue to be evaluated as the design advances,
including where turns are provided and how traffic would redistribute if access changes. A new signalized connection at
another location would need to be evaluated for traffic operations, safety, visibility, and cost, and would involve City
Transportation staff.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
37
How has the preliminary project cost estimate changed, and what
factors could cause future cost increases?
The project cost will continue to be refined as engineering design advances and additional information becomes
available. Factors such as design development, construction costs, utility relocations, utility relocations, right-of-way
needs, environmental requirements, and market conditions can all affect future project costs. Community Meeting Not Concept Specific
Total Project Coast Estimate; Construction
Considerations
38
Could the proposed bicycle and pedestrian switchback ramp be
redesigned to improve convenience and expected use?
The project team is evaluating bicycle and pedestrian access as part of the design process and is considering community
feedback on ramp design, convenience, and usability. Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
39
Will the proposed path provide enough space for faster e-bikes to
pass pedestrians and people using mobility devices safely?
The project team is evaluating bicycle and pedestrian facilities to support safe access and shared use by people with a
range of travel speeds and mobility needs. Path widths, accessibility requirements, and user comfort are being
considered as part of the design process.Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
40
Would a wider sidewalk and a landscape buffer improve pedestrian
and bicycle safety and comfort near Alma Street and East Charleston
Road?
Sidewalk widths, buffers, and other pedestrian and bicycle details shown in the 15% Design are preliminary and will be
advanced during 35% Design. At Churchill Avenue, City Council directed the team in December 2025 to advance the
Partial Underpass without a landscaping strip along Alma Street. Available width along Alma Street is constrained by the
lowered roadway, retaining walls, utilities, and property limits. Community Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
41
Could the West Meadow Drive crossing prioritize bicycle and
pedestrian access if the benefit to automobile traffic is limited?
City Council selected the Meadow Drive Hybrid Underpass in December 2025 to advance into design, which keeps the
crossing open to vehicles as well as people walking and biking. The concept also removed the slip lane to improve bicycle
safety and includes protected bicycle lanes. Changing the crossing to bicycle and pedestrian use only would be a change
in direction that City Council would need to make. This comment will be included in the community input summary
provided to the Rail Committee and City Council.Community Meeting Meadow Drive Hybrid
Bicycle, Pedestrian, and School Access;
Design Elements and Development
42
What property and setback impacts are anticipated near East
Charleston Road and Mumford Place?
Currently there are no permanent property easements or setbacks anticipated near East Charleston Road and Mumford
Place. There may be potential temporary construction easements needed for this location. Community Meeting Charleston Road Underpass - Direct Access Ramp Design Elements and Development
43
Where would construction staging occur near East Charleston Road
and Mumford Place, and how could it affect nearby properties?
Construction staging areas have not been established at the 15% Design level. Staging locations, work hours, haul routes,
and setbacks from homes and streets would be developed in later design phases and evaluated in the environmental
review under the California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA),
beginning in fall 2026.Community Meeting Charleston Road Direct Access Ramp Construction Considerations
44
How would the Churchill Avenue concept affect traffic, left turns,
sight distance, and queuing in Old Palo Alto?
The 15% Design evaluated how far ahead a driver can see and how vehicles turn at each crossing. At Churchill Avenue,
nothing structural blocks the view, but the available sight distance generally falls short of Caltrans Highway Design
Manual criteria, primarily because the roadway dips down under the tracks. Preliminary recommendations were
identified for further study, including visibility, lighting, and intersection control measures. Intersection performance,
queuing, left turn movements, and effects on surrounding streets in Old Palo Alto have not been analyzed at this stage
and will be evaluated during 35% Design as the geometry is refined. Understood on the note going forward. I will keep
the comment answered and apply your direction without restating what changed unless something in it creates a real
risk Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
45 Is closure of the Churchill Avenue crossing being considered?
The alternatives currently under consideration maintain access across the rail corridor at the Churchill area, including
vehicle, pedestrian, and bicycle connections. The project team is continuing to evaluate how best to provide safe access
for all users.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Construction Considerations
46
How would closing Churchill Avenue affect local connectivity, and
what options would preserve crossing access?
The alternatives currently under consideration maintain access across the rail corridor at the Churchill area, including
vehicle, pedestrian, and bicycle connections. The project team is continuing to evaluate how best to provide safe access
for all users.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Bicycle, Pedestrian, and School Access
47
What protective barriers or other safety features are proposed for the
pedestrian bridge near Palo Alto High School?
Comment noted. Barrier heights, railings, fencing, and other safety features for bicycle and pedestrian structures will be
developed as the design advances,Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip
Bicycle, Pedestrian, and School Access;
Design Elements and Development
48
Why is the proposed shoulder near Churchill Avenue longer than at
Charleston Road, and could its dimensions be adjusted to provide
more lane space?
The project proposes shoulders in the Churchill and Charleston underpasses both are proposed to be 8 feet. The project
will continue to evaluate lane widths at these locations to conform with all necessary standards. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
49
How would the project maintain a signalized option for left turns
from Old Palo Alto to southbound Alma Street?
Under the Churchill Avenue concept, a signalized intersection would remain at Churchill Avenue and Alma Street at the
lowered level, with left and right turns provided between the two streets. How left turns from other Old Palo Alto
streets onto southbound Alma Street would operate has not been determined at the 15% Design level. Neighborhood
access, turns, and how traffic would redistribute will be evaluated as the design advances. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
50
How would the concept affect left-turn operations, sight distance,
and vehicle queuing?
The 15% Design evaluated how far ahead a driver can see and how vehicles turn at each crossing. Available sight
distance generally falls short of Caltrans Highway Design Manual criteria, largely because the roadways dip down under
the tracks, and at the Charleston Road Direct Access Ramp the bridge supports and retaining walls block the view at the
corner. Preliminary recommendations were identified for further study, including visibility, lighting, intersection control,
and restricting wide vehicles from the Direct Access Ramp. A traffic analysis evaluating intersection operations and
vehicle queuing, including left turn movements, under existing and future conditions was presented to City Council in
December 2025. Those results will be updated during 35% Design as the geometry and intersection configurations are
refined.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
51
How would the project maintain a convenient walking route for
families traveling between Southgate and destinations near Churchill
Avenue and Walter Hays Elementary School?
Providing safe pedestrian access is an important consideration in the project. The project team is evaluating how each
concept would affect walking routes, connectivity, and access to nearby destinations, including schools, parks and
neighborhoods.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Bicycle, Pedestrian, and School Access
52
How would the Seale Avenue concept address conflicts between
bicyclists exiting the underpass and vehicles turning from Alma
Street?
Conflict points where people on bikes leave the crossing and meet turning vehicles have not been resolved at the 15%
Design level. The 35% phase will advance pedestrian and bicycle facility design and update visibility and turning
analyses.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing
Bicycle, Pedestrian, and School Access;
Design Elements and Development
53
Should left-turn movements from Alma Street onto Seale Avenue be
restricted or redesigned?
Conflict points where people on bikes leave the crossing and meet turning vehicles have not been resolved at the 15%
Design level. The 35% phase will advance pedestrian and bicycle facility design and update visibility and turning
analyses.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing
Bicycle, Pedestrian, and School Access;
Design Elements and Development
54
How will the project explain what people experience today and how
conditions would change under each concept?
The project will use visualizations, renderings, maps, and other outreach materials to help people understand current
conditions and compare how each concept could affect their daily travel experience, access, safety, and connectivity. Community Meeting Design Elements and Development
55
Could the project cause more Palo Alto High School students to drive
via Embarcadero Road, and how would that potential effect be
evaluated?
Comment noted for consideration. Potential changes in travel patterns and routes near Palo Alto High School will be
considered as the traffic analysis is updated during 35% Design Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Bicycle, Pedestrian, and School Access
56
How would drivers safely enter or cross traffic where there is no
signalized gap?
Traffic operations were analyzed at the study intersections identified for the project, and those results were presented
to City Council in December 2025. The unsignalized side street connections along Alma Street in this area were not part
of that analysis. Access and turning movements at these locations will be evaluated as the design advances. If that work
identifies a need, options such as signal changes, turn restrictions, or other traffic control measures would be evaluated
with City Transportation staff.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
57
Should closures or other measures be considered at Kellogg Avenue,
Churchill Avenue, and Coleridge Avenue to reduce cut-through
traffic?
Changes to traffic on neighborhood streets will be evaluated as the design advances, including how traffic redistributes
once the crossing configuration changes and which nearby residential streets drivers may shift to. Street closures and
traffic calming measures are City decisions that would involve City Transportation staff and neighborhood input, and are
not part of the current design work.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
58
How would the intersection protect bicyclists from conflicts with
vehicles turning onto Alma Street?
The project team is evaluating intersection and roadway features that can help reduce conflicts between people
bicycling and turning vehicles.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing
Bicycle, Pedestrian, and School Access;
Design Elements and Development
59
How could the project support a long-term plan to make Alma Street
safer and more comfortable for all users?
The project is evaluating opportunities to improve safety, connectivity, and accessibility for everyone who uses Alma
Street, including pedestrians, bicyclists, transit riders, motorists, and emergency responders. By reducing conflicts at rail
crossings, the project could help support broader long-term community goals for a safer, more connected, and more
comfortable transportation corridor.Community Meeting Not Concept Specific
Bicycle, Pedestrian, and School Access;
Design Elements and Development
60
How would the 15 percent design concepts accommodate emergency
response, including access through tunnels and along entrances and
ramps?
Emergency access was evaluated as part of the 15% Design. Turns were tested using several vehicle types, including a
City fire truck, a school bus, a semi-trailer, and a garbage truck. Passenger vehicles can generally be accommodated
within the proposed street layout, while larger vehicles including fire apparatus require wider turning paths or
operational adjustments at several locations. Preliminary recommendations include restricting wide vehicles from the
Charleston Road Direct Access Ramp and modifying curb and sidewalk geometry at the upper Alma Street and
Charleston Road intersection. Emergency access will continue to be evaluated as the design advances, for both the
completed condition and during construction.Community Meeting Not Concept Specific Design Elements and Development
61
Has the project considered a corridor-wide grade separation solution,
such as a rail viaduct, to improve long-term connectivity, creating
additional crossing opportunities, and support future growth?
A corridor-length viaduct is not among the concepts being carried through this phase. Alternatives were screened earlier
through the Connecting Palo Alto effort and the Rail Crossing Community Advisory Committee, and City Council selected
the current alternatives in December 2025 for Churchill Avenue, Meadow Drive, and Charleston Road. Project Website
Churchill Avenue - Partial Underpass without Landscape
Strip;
Seale Ave - Bicycle and Pedestrian Undercrossing;
Meadow Drive Hybrid;
Charleston Road Underpass - Direct Access Ramp Design Elements and Development
62 Why is the Palo Alto Avenue Crossing not included in the project?
Palo Alto Avenue was one of four crossings studied under Connecting Palo Alto. City Council directed staff to pause
design at that crossing, and the current project covers Churchill Avenue, Meadow Drive, and Charleston Road. Project Website Not Concept Specific Design Elements and Development
63
How does the project address safety concerns related to unauthorized
access to the rail corridor?
The project is intended to improve safety by reducing conflicts between trains, vehicles, bicyclists, and pedestrians at
existing crossings. 35% design will continue to incorporate safety features consistent with applicable railroad, roadway,
and pedestrian design standards.Community Meeting Not Concept Specific Design Elements and Development
64
How are station access and elevation changes considered when rail or
roadway grades are modified?
There are no Caltrain stations within the project limits at Churchill Avenue, Meadow Drive, or Charleston Road, so the
alternatives do not change station access or platform elevations. Rail and roadway grade changes are evaluated as part
of the engineering design to maintain access, meet applicable design standards, and provide connections between the
roadway, bicycle, and pedestrian facilities at each crossing. These elevations will be refined as the design advances. Community Meeting Not Concept Specific
Design Elements and Development;
Construction Considerations
65
What is the estimated cost of the Seale Avenue bicycle and
pedestrian crossing?
The Seale Avenue bicycle and pedestrian crossing is currently included as part of the broader project cost estimate.
Project costs have not yet been finalized but may be refined as project development continues. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Total Project Cost Estimate
66
How will future decisions regarding project costs, funding, and
implementation be made?
Current cost estimates are preliminary and will continue to be refined as design advances. Future decisions regarding
implementation will be made by the City Council based on project costs, funding availability, environmental review , and
other project considerations.Community Meeting Not Concept Specific Total Project Cost Estimate
67
How could the project affect traffic operations on Oregon
Expressway, San Antonio Road, and surrounding roadways?
Potential traffic impacts, including those during construction, will continue to be evaluated through analysis and
coordination with the City. Findings will help identify appropriate traffic management and mitigation measures. Community Meeting Not Concept Specific Design Elements and Development
68
What engineering and design considerations influenced the
recommended concept at Charleston Road?
City Council selected the Charleston Road Underpass with a Direct Access Ramp in December 2025 following alternatives
screening, technical evaluation, and public input, and directed that the 15% Design phase focus on enhancing safety and
access while minimizing congestion, environmental impacts, and property impacts. Reducing potential property impacts
was one of several considerations in carrying this concept forward, along with traffic operations, bicycle and pedestrian
access, constructability, and cost. The 15% Design advanced that direction by refining the roadway profile, retaining wall
and structure configuration, utility relocations, and the Direct Access Ramp layout to fit the improvements within the
available corridor. These elements will continue to be refined during 35% Design. Community Meeting Charleston Road Underpass - Direct Access Ramp Design Elements and Development
69
Could alternative bicycle and pedestrian access connections near
Churchill Avenue and Kellogg Avenue be considered?
Alternative bicycle and pedestrian connections were evaluated during previous phases of project development. In
December 2025, City Council selected the Churchill Avenue Partial Underpass without a landscaping strip, together with
a bicycle and pedestrian crossing at Seale Avenue using the Alma Street ramp, with attention to bicycle safety on the
east side. The Seale Avenue crossing is the connection being carried forward as part of the Churchill Avenue alternative.
The current concept reflects engineering constraints, property considerations, grades, and overall project footprint
requirements. The Seale Avenue crossing is shown at a preliminary level and will be refined during 35% Design. Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Design Elements and Development
70
How will student safety and bicycle/pedestrian access be maintained
during construction?
Maintaining safe access for bicyclists, pedestrians, and students will be an important consideration during construction
phase planning. Temporary routes and traffic control measures will be developed to support safe travel during
construction activities.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Bicycle, Pedestrian, and School Access
71
Why are different design approaches proposed at Meadow Drive and
Charleston Road?
Although the crossings appear similar, each location has unique engineering conditions, railroad operational constraints,
and roadway characteristics that influence the recommended design approach. Community Meeting
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid
Design Elements and Development;
Construction Considerations
72
How will project benefits and performance improvements be
evaluated relative to existing conditions?
A traffic analysis comparing existing and future conditions was presented to City Council in December 2025, evaluating
intersection operations and vehicle queuing at the study intersections. Those results, along with engineering evaluations
of safety, access, and mobility, are how project performance is compared against current conditions. A traffic analysis of
impacts during construction will also be completed during 35%, examining how access, detours, and operations on
surrounding streets would be affected while the work is underway. Both the operational and construction period
analyses will be updated during 35% Design as the design is refined. Community Meeting Not Concept Specific
Design Elements and Development;
Construction Considerations
73 What factors contributed to changes in the project cost estimates?
Updated cost estimates include additional information developed through the design process, including construction
costs, railroad coordination, risk, and other factors not reflected in earlier planning-level estimates. Community Meeting Charleston Road Underpass - Direct Access Ramp Total Project Cost Estimate
74
How could bicycle and pedestrian access change at East Meadow
Drive?
The proposed design would remove conflicts with rail operations while providing bicycle and pedestrian facilities
intended to improve connectivity and safety for users Community Meeting Meadow Drive Hybrid
Bicycle, Pedestrian, and School Access;
Design Elements and Development
75
What are temporary bypass rail tracks ("shoofly tracks") and how
could they be used during construction?
Temporary bypass rail tracks, commonly referred to as shoofly tracks, may be used to maintain rail service while
construction activities occur on or near the existing tracks. Community Meeting Not Concept Specific Design Elements and Development
76
Could bicycle and pedestrian improvements be funded or
implemented separately from other project elements?
Opportunities for alternative project packaging, sequencing, and funding approaches may continue to be evaluated as
the project advances and funding strategies are refined. Community Meeting Not Concept Specific Bicycle, Pedestrian, and School Access
77
How has the project considered minimizing impacts to mature trees
and park resources within Peers Park?
Comment noted. Effects on trees and park resources near the project area will be evaluated as the design advances and
through environmental review under the California Environmental Quality Act (CEQA) and the National Environmental
Policy Act (NEPA), beginning in fall 2026.Community Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Design Elements and Development
78
How would temporary bypass rail tracks be incorporated into the
project area, and how could they affect future roadway
improvements at Charleston Road?
Temporary bypass rail tracks would be used to maintain rail service during construction. Specific track locations and
construction staging will continue to be refined as design advances. PABAC Meeting Charleston Road Underpass - Direct Access Ramp
Design Elements and Development;
Construction Considerations
79
How will bicycle and pedestrian access and crossing movements be
accommodated at Charleston Road during construction and in the
completed project?
Bicycle and pedestrian access will continue to be evaluated through future design phases with a focus on maintaining
safe access during construction and improving connectivity in the completed project. PABAC Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Construction Considerations
80
How will pedestrian and bicycle detour routes be evaluated and
incorporated into future construction planning?
Construction phasing and detour planning will be developed during future design phases and will include consideration
of pedestrian and bicycle needs.PABAC Meeting Not Concept Specific
Design Elements and Development;
Construction Considerations
81
What is the expected extent and profile of the proposed
embankment associated with the Meadow Drive Hybrid concept?
The preliminary embankment limits shown in the 15% design are subject to refinement as engineering and
environmental review continue. Additional design details will be developed during future project phases. PABAC Meeting Meadow Drive Hybrid Design Elements and Development
82
How does the proposed bicycle and pedestrian ramp configuration at
Charleston Road support project goals related to walking, bicycling,
and multimodal connectivity?
The proposed configuration is intended to maintain bicycle and pedestrian connectivity across the corridor while
working within the project design constraints at this location, including the lowered roadway profile, retaining walls,
structure, and utilities. The ramp layout also reflects City Council direction to minimize property impacts, which limits
the width available for the bicycle and pedestrian facilities. Opportunities to refine bicycle and pedestrian access,
including path widths, ramp grades, and transitions, will continue to be evaluated during 35% Design. PABAC Meeting Charleston Road Underpass - Direct Access Ramp
Bicycle, Pedestrian, and School Access;
Design Elements and Development
83
A community member submitted a handout evaluating the project
against four criteria: neighborhood protection, design feasibility and
budget, the City's capacity to deliver, and holistic regional analysis.
The handout states that protecting residents near the rail corridor
should be a prime design criterion rather than mitigation applied
after a design is selected, and that available funding should not
determine the structure before the City defines the best outcome. It
raises concerns about the City's capacity to deliver a program of this
scale and requests that the project not advance until each of these
issues has a defensible answer.
Comment noted for consideration. The 15% Design phase was directed by City Council in December 2025 with a focus on
enhancing safety and access while minimizing congestion, environmental impacts, and property impacts, and the issues
raised will continue to be considered as the project advances through 35% Design and environmental review. Community Meeting All concepts
Bicycle, Pedestrian, and School Access;
Design Elements and Development; Total
Project Cost Estimate; Construction
Considerations
84
A community member submitted a handout asking the City's position
on undergrounding Caltrain and converting the Palo Alto Baylands
into parks and nature preserves. The handout raises concerns about
rider and pedestrian safety, including platform boarding conditions
and an injury the commenter experienced, and states that street level
tracks in populated areas present ongoing safety risks that current
measures at crossings do not adequately address.
Comment noted. Undergrounding the rail corridor is not among the alternatives City Council selected for this phase, and
station platform conditions and Baylands land use are outside the scope of this project. Community Meeting All concepts
Bicycle, Pedestrian, and School Access;
Design Elements and Development
85
A community member presented a slide deck illustrating the Meadow
Drive Hybrid at a street level view, including the temporary track
along Alma Street during construction and the permanent raised
track condition. The recorded presentation states that the technical
drawings do not convey what construction and the finished condition
would mean for people living beside the corridor, and asks that the
Meadow Drive Underpass receive further refinement so it can be
compared directly with the Hybrid before the Hybrid alone advances.
The comment proposes a capped 90 to 120 day review of the
underpass, subject to written responses from the involved agencies.
City Council selected the Meadow Drive Hybrid in December 2025 following alternatives screening, technical evaluation,
and public input. A Meadow Drive underpass was evaluated at a high level for the November and December 2025
Council meetings, including circulation, constructability, and property impacts. The Hybrid was carried forward in part
because it reduced potential property impacts and avoided the full acquisitions identified in that evaluation. The current
grant funding supports advancing the alternatives Council selected through 15% and 35% Design. An underpass at
Meadow Drive is not among those alternatives and is not funded for advancement in this phase. Bringing it to a
comparable level of detail would require additional funding and time. City Council could direct that work at a future
date using other funding sources. The project team acknowledges the request for information at a street level rather
than an aerial view. Staff will provide additional explanation of how the alternatives were narrowed, along with more
specific information on the Meadow Drive Hybrid, including wall height and construction duration. Visual character,
along with noise, vibration, air quality, traffic, and access, will be studied through environmental review under the
California Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA), beginning in fall 2026.
Urban design elements have not been designed and will be developed during 35% Design with further community input.
This comment, the submitted materials, and the proposed motion will be documented and provided to the Rail
Committee and City Council for consideration.Rail Committee Meadow Drive Hybrid
Bicycle, Pedestrian, and School Access;
Construction Considerations
86
A community member stated that the project materials have not
explained what the alternatives would mean at a human scale, either
during construction or in the permanent condition, and asked how
public feedback has changed the proposals or why suggested changes
were declined. The comment notes that Churchill Avenue and
Charleston Road concepts were visibly improved through that
process, questions whether the Meadow Drive Underpass was fairly
represented before it was set aside, asks whether box jacking was
considered at Meadow Drive, and expresses concern that available
budget and schedule are driving the design.
Community input has changed the concepts at several points in the process. Examples include the removal of the
roundabout at the Charleston Road crossing and Council direction in December 2025 to advance the Churchill Avenue
Partial Underpass without a landscaping strip along Alma Street. Staff will continue to report how comments were
considered, including where a suggested change was not carried forward and why. A Meadow Drive underpass was
evaluated at a high level for the November and December 2025 Council meetings, including circulation, constructability,
and property impacts, and the Hybrid was carried forward in part because it reduced potential property impacts. That
evaluation was not advanced to a level that assessed specific construction methods, including whether box jacking could
be used at Meadow Drive. Doing so would require design work to a comparable level of detail, along with additional
funding and time. On budget and schedule: the rough order-of-magnitude figures presented at 15% Design are a
planning tool, not a project budget or a construction funding request. The current $20 million funds preliminary
engineering and environmental documentation only, and no construction funding has been identified. Construction
period effects and permanent effects, including noise, vibration, air quality, traffic, access, and visual character, will be
studied through environmental review under the California Environmental Quality Act (CEQA) and the National
Environmental Policy Act (NEPA), beginning in fall 2026. This comment will be documented and provided to the Rail
Committee and City Council as project development continues. Rail Committee Meadow Drive Hybrid Design Elements and Development
87
A community member proposed a different delivery approach for the
corridor, suggesting that the private sector take over the full
alignment and construct a viaduct, which the comment states would
avoid temporary tracks, avoid lane reductions on Alma Street,
shorten construction duration, and cost less than the current
concepts. The comment also stated that relocating passing tracks
elsewhere on the Peninsula would remove the need for additional
track capacity near Palo Alto, and noted difficulty accessing the
meeting transcript and presentation.
A viaduct is not among the concepts being carried through this phase. Corridor concepts were narrowed through the
Connecting Palo Alto alternatives screening and subsequent Rail Committee and City Council direction, and Council
selected the current alternatives in December 2025. The 15% Design advances those alternatives. Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid
Bicycle, Pedestrian, and School Access;
Construction Considerations
88
A community member asked that a rail viaduct be reconsidered,
stating that it would avoid the pump stations and lowered roadways
associated with the current concepts, avoid conflicts with the 24 inch
gas transmission line, remove the need for bicycle and pedestrian
ramps by keeping crossings at grade, avoid a long retaining wall
through the neighborhood, and avoid the need for a temporary track.
The comment also stated that the 15% cost estimates are
substantially higher than earlier figures, and questioned why the City
would fund elements that serve Caltrain operations.
The project team recognizes community concerns regarding project cost, stormwater infrastructure, utility relocations,
temporary rail operations, construction impacts, property impacts, and long-term community effects. The current
concepts include infrastructure such as pump stations, utility relocations, temporary rail facilities where required, and
modifications to bicycle, pedestrian, and roadway facilities that are being refined as design advances. These topics will
continue to be evaluated through 35% Design and environmental review under CEQA and NEPA. Rail Committee Charleston Road Underpass - Direct Access Ramp
Design Elements and Development; Total
Project Cost Estimate
89
The total ROM project cost estimate is presented in 2026 dollars.
Why were costs not projected forward instead, and does the
escalation approach fully account for future inflation? Confirmation
was also requested of the assumed construction start date, the
combined cost of delivering all three crossings, and the amount of
funding secured to date.
The independent cost estimator priced the work using current market conditions in 2026 dollars. Escalation is then
applied beginning in 2027 at 5 percent per year to the midpoint of construction. The total ROM project costs presented
in Table 1 are expressed in year of expenditure dollars, meaning escalation is already included. Total ROM project costs
are presented by delivery scenario rather than as a single combined figure, because cost and duration at Meadow Drive
and Charleston Road depend on whether the two crossings are delivered concurrently or sequentially. Table 1 shows the
range and preliminary construction duration for each scenario. Rail Committee Not Concept Specific Total Project Cost Estimate
90
Requested a high level summary of the community feedback received
at the August 2026 community meetings, including input from the
Palo Alto Bicycle and Pedestrian Advisory Committee (PABAC) and
comments related to safe routes to school.
Community input fell into three main areas. The first was the alternatives themselves, including questions about bicycle
and pedestrian facilities and roadway configuration, and how the current designs were arrived at. The second was
construction period effects, including potential property impacts and the location of the shoofly track. The third was the
total ROM project cost estimate and how it was developed. PABAC input focused on the bicycle and pedestrian
connection between the west and east sides of the tracks, including the switchback ramp on the west side of Charleston
Road. The roll plots shared at the community meetings are posted on the project website, along with the larger format
exhibits.Rail Committee Not Concept Specific Bicycle, Pedestrian, and School Access
91
The staff report identifies five potential full property acquisitions and
33 partial acquisitions at the 15 percent level, but only three
appeared on the exhibit, all at Charleston Road. Where are the
remaining two? Separately, given community concern about the
retaining wall associated with the Meadow Drive Hybrid, a reminder
was requested of why the Hybrid was carried forward at Meadow
Drive rather than an underpass.
The two additional potential full acquisitions are located on the south side of Charleston Road and are within the
preliminary project footprint. Design work is ongoing to determine whether they would be directly impacted, so they are
identified as potential and are included within the five reported. Several factors supported carrying the Hybrid forward
at Meadow Drive. An underpass at Meadow Drive would require two ramps providing access to and from Alma Street
north of the crossing, one of which would come close to the adjacent shopping center. It would also result in
substantially greater property impacts, including direct impacts to multifamily residential buildings in the northeast
quadrant of the intersection. The Hybrid also responded to direction to improve conditions for bicyclists, particularly
students traveling to schools on both sides of the corridor, by providing a more protected crossing at Meadow Drive. Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid Design Elements and Development
92
Was the 15 percent design finding on increased property acquisition
needs describing all three crossings or Charleston Road specifically?
Charleston Road was selected in part because it carried lower
property acquisition needs, so clarification was requested on whether
the findings show more property acquisition than was expected
entering the phase.
The finding is stated across all three crossings collectively. Future reporting can present property acquisition information
by crossing. Property acquisition needs at Charleston Road are lower than under the earlier design, which included a
roundabout and other features that drove higher acquisition needs. The Direct Access Ramp (DAR) was developed at the
direction of the Rail Committee and City Council to reduce those impacts on the east side. Options on the west side
remain more constrained by available right of way. Potential acquisition needs identified at 15 percent are higher than
anticipated at the start of the phase, driven largely by utility conflicts and the space available within the corridor. Staff is
coordinating with the City's Utilities Department this fall on potential utility rerouting, and property needs will be
refined during 35 percent design.Rail Committee Charleston Road Underpass - Direct Access Ramp Design Elements and Development
93
What are the dimensions of the shared use path on the switchback
ramp at Charleston Road, given that some bicyclists may choose to
remain on the roadway instead? Has a stairway been considered at
the ramp locations closest to the tracks? Separately, could the South
Palo Alto bikeway undercrossing near Matadero Creek be constructed
before construction begins at Meadow Drive or Charleston Road, so
that a crossing option is available for people walking and bicycling
during construction?
The shared use path is 14 feet wide, with five feet in each direction for bicyclists and four feet for pedestrians. A
stairway at the ramp locations closest to the tracks has not been evaluated and has been added to the list of items to
study during 35 percent design. A staircase closer to Park Boulevard has been under consideration. The location that
works best will be determined through further design, with ramp grades retained for accessibility. The South Palo Alto
bikeway undercrossing near Matadero Creek is being planned and pursued for funding concurrently with this project. Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid Bicycle, Pedestrian, and School Access
94
Requested that the South Palo Alto bikeway undercrossing near
Matadero Creek be shown in the City Council presentation and
reflected in the construction period traffic discussion, so that the
public and City Council understand that both projects are advancing
and that the undercrossing is intended to be in place before
construction begins.
The scope of the traffic study includes the bicycle pathway and evaluates how it would function under both conditions.
Preliminary analysis was completed in advance of the December 2025 City Council meeting and can be provided to the
Committee again. Staff will reference the South Palo Alto bikeway undercrossing in the City Council presentation and in
the discussion of construction period circulation.Rail Committee Not Concept Specific
Design Elements and Development;
Construction Considerations
95
What is the preliminary level of service at Charleston Road with the
Underpass and Direct Access Ramp, compared with existing
conditions and with future projected growth if the project were not
built?
Intersection analysis completed in advance of the December 2025 City Council meeting remains part of the public record
and can be provided to the Committee again. Results showed improved operations in all conditions compared with
existing conditions. In the morning peak at Charleston Road, average delay is approximately 1.5 minutes per vehicle
under existing conditions and approximately half a minute with the Underpass and Direct Access Ramp. Under 2040
conditions without the project, delay increases to approximately three minutes per vehicle, compared with
approximately half a minute with the project. In the afternoon peak, existing delay is approximately three minutes per
vehicle, increasing to approximately six minutes in 2040 without the project, compared with approximately half a
minute with the project.Rail Committee Charleston Road Underpass - Direct Access Ramp Design Elements and Development
96
Does the 2040 no build scenario assume a specific number of trains
per hour? The adopted Caltrain service vision covers a broad range, so
clarification was requested on which assumption was used and
whether it reflects the upper limit.
The 2040 analysis is based on the adopted Caltrain service vision. Preliminary review indicates the analysis considered
six and eight trains per hour and did not assume high speed rail service. Staff will confirm the specific assumption used
and report back to the Committee.Rail Committee Not Concept Specific Design Elements and Development
97
Why does the width of the raised track section at Meadow Drive
extend to the edge of Alma Street? Is that driven by a potential
future passing track, by maintenance access, or by both?
Retaining walls at Meadow Drive are located at or offset from the Caltrain right of way line so that Caltrain can continue
to use and maintain its right of way. The width supports maintenance access and preserves the ability to accommodate
an additional track in the future if one is pursued. The four track segment previously analyzed and presented to the Rail
Committee is located north of Meadow Drive, between Meadow Drive and Churchill Avenue. Wall placement and
setbacks will be discussed further with Caltrain during 35 percent design. Rail Committee Meadow Drive Hybrid Design Elements and Development
98
Raised the relationship between Caltrain's requirement for
maintenance access along the raised track section at Meadow Drive
and Caltrain's policies supporting grade separations. A comparable
raised track section in San Carlos does not include this feature, and
the requirement adds cost. This has been raised with Caltrain and a
request has been made that it be brought to the Caltrain board to
reconcile the design, technical, and operating standards.
The 15 percent design applied current Caltrain standards in order to establish a preliminary project footprint and
identify the associated tradeoffs. Along Alma Street the retaining wall is placed close to the right of way line, with a
small setback for maintenance. On the west side it is set back approximately 10 feet from the fence line to allow
maintenance vehicle access. Electrified rail also carries clearance requirements for safe maintenance of overhead
systems. Grade separations built 20 to 30 years ago were designed under different requirements, so direct comparison
with those structures has limits. The bridge at Meadow Drive is sized to carry two tracks along with maintenance access
and emergency egress for passengers if a train is disabled. Wall placement, setbacks, and where flexibility may exist are
appropriate topics for coordination with Caltrain during 35 percent design. Staff will continue that discussion with
Caltrain as design advances.Rail Committee Meadow Drive Hybrid Design Elements and Development
99
Noted that Caltrain is re-examining the tension between its policy
support for grade separations and its right of way access policies. At
Middle Avenue in Menlo Park, a change in Caltrain's position on use
of the right of way for a bicycle and pedestrian undercrossing
significantly increased that project's cost. Caltrain's board is expected
to discuss the policy in the coming months and the outcome is not
settled.
Design decisions on this project have been driven by technical requirements. At Charleston Road, evaluation of the
Direct Access Ramp included limited encroachment into Caltrain right of way, which supported the feasibility of the
grade separation at that location. Some flexibility exists at Charleston Road. Meadow Drive will require further
discussion with Caltrain on what flexibility may be available from a technical standpoint. Staff will track the Caltrain
policy discussion and report back on any outcome that affects the project. Rail Committee Not Concept Specific Design Elements and Development
100
If the maintenance access along the raised track section is required
for Caltrain operations and maintenance rather than for the grade
separation itself, whose responsibility is it to fund? The traditional
division of cost responsibility between Caltrain and cities is less clear
in this case.
Cost responsibility for elements associated with Caltrain right of way use is expected to be part of the coordination
during 35 percent design. Caltrain has full use of its right of way at this location today. The question to be resolved is the
extent to which the grade separation drives the need to relocate the retaining wall to the right of way line so that
Caltrain retains that use in the future. Staff will address cost responsibility with Caltrain as part of 35 percent design and
report back to the Committee.Rail Committee Not Concept Specific Total Project Cost Estimate
101
Noted that the 25th Avenue grade separation in San Mateo was built
in anticipation of electrification and does not include a comparable
maintenance access area, and that further review of that project may
offer lessons on operations and maintenance. Clarification was also
requested on the funding available through final design, including
whether the Transit and Intercity Rail Capital Program (TIRCP)
funding is an award or a grant at risk, the amount available from VTA
Measure B, and the potential use of City of Palo Alto capital funds.
Staff can review the 25th Avenue grade separation in San Mateo and report back on relevant lessons learned. The TIRCP
funding is a state grant with an expiring timeline. Staff is working with the state to extend that timeline. The Preliminary
Engineering and Environmental Documentation phase is fully funded with $20 million in secured external funds.
Amounts identified beyond that phase, including the VTA Measure B grade separation program share and City of Palo
Alto capital funds, are planning level figures that will be refined as VTA updates its sales tax projections. Additional
Measure B grade separation funding may be available depending on final project cost. No construction funding is
currently identified or programmed.Rail Committee Not Concept Specific Total Project Cost Estimate
102
Given the overall cost of all three crossings, the City should consider
intentionally limiting the number of grade separations it advances.
Churchill Avenue has already been deprioritized and could be formally
placed on pause. The 15 percent findings indicate that lower property
acquisition was a key reason the Hybrid was selected at Meadow
Drive, and that advantage now appears reduced, so an underpass at
Meadow Drive warrants further examination. If Charleston Road
were advanced on its own, the construction duration and cost appear
closer to the funding identified to date. Focusing on Charleston Road,
together with the South Palo Alto bikeway undercrossing, would
reduce staff time and cost while still delivering a grade separation.
More detailed information broken out by individual crossing would
support that discussion.
The current grant agreements fund advancement of all three alternatives through 35 percent design and environmental
documentation. Decisions on prioritization, sequencing, and construction packaging would be made by City Council
following completion of that phase. The 15 percent findings identify higher potential property acquisition needs across
all three crossings, driven largely by utility conflicts rather than by conditions at a single crossing. Staff can present
property and cost information by crossing in future reporting. Table 1 presents total ROM project cost ranges and
preliminary construction durations for each delivery scenario, including Charleston Road constructed on its own at
approximately 48 months. These figures are planning level and will be refined during 35 percent design. Rail Committee All concepts Total Project Cost Estimate
103
If only one crossing can be advanced, or if the crossings are
sequenced, why would Charleston Road be first? Clarification was
also requested on how realistically the City can partner with county,
state, and federal agencies to secure funding at the scale required for
all three crossings, and how cities generally approach that level of
funding uncertainty.
Completing 35 percent design and environmental documentation is the point at which additional federal and state
construction and final design funding sources become available to the project. The current grants fund the work through
35 percent design for all three crossings, with no commitment beyond that point. City Council would decide at that stage
whether and how to proceed, including prioritization among crossings. Charleston Road carries the highest traffic
volume of the three crossings, which is one factor in prioritization. A full evaluation of prioritization factors would be
brought to City Council following completion of 35 percent design. Caltrain is also working with corridor cities on a
programmatic corridor funding strategy. Corridor wide approaches of this kind have supported successful funding for
grade separation programs in other regions.Rail Committee Charleston Road Underpass - Direct Access Ramp Design Elements and Development
104
Is constructability also a constraint at Meadow Drive relative to
Charleston Road?
Meadow Drive presents additional constructability challenges. Alma Street is constrained at that location, larger
structures are present on the east side, and utility conflicts along Meadow Drive would affect an underpass. These
factors would need to be addressed in any further evaluation of an underpass at that location. Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid
Design Elements and Development;
Construction Considerations
105
The Jed Foundation has recommended grade separating all four Palo
Alto crossings as a means restriction measure, including Palo Alto
Avenue, for which no planning has been undertaken. Concern was
raised that a program of that scale would cost approximately $2
billion, is unlikely to be funded, and could take two decades, and that
presenting it as a near term option is not realistic. At grade safety
measures have been implemented and are combined with crossing
guards funded jointly by the City and the school district, and
questions have been raised about the long term sustainability of that
funding. Grade separation reduces risk at the crossings but does not
address station areas, which account for an increasing share of
incidents along the corridor. Charleston Road, together with the
bicycle and pedestrian undercrossing near Matadero Creek, is
anticipated as a likely priority, with a City Council decision expected
following completion of 35 percent design.
This project advances the three remaining at grade crossings identified through prior alternatives screening and City
Council direction. Palo Alto Avenue is not within the current project scope. Adding a crossing would require City Council
action, additional funding, and a separate planning and environmental process. Grade separation eliminates conflicts
between trains and roadway users at the crossings themselves. Safety within station areas and along other portions of
the corridor is under Caltrain's jurisdiction and is addressed through separate Caltrain programs. Decisions on how many
crossings advance into final design and construction would be made by City Council following completion of 35 percent
design and environmental documentation, informed by cost, schedule, funding availability, and construction effects. Rail Committee Not Concept Specific Total Project Cost Estimate
106
Requested a more thorough understanding of Caltrain's specific rights
compared with its inferred rights. Clarification was also requested on
vertical clearance at the underpasses, which in earlier work exceeded
clearances at existing undercrossings and affected both design and
cost. What is the existing clearance at Oregon Expressway and
Embarcadero Road, and is the clearance requirement based on
concern about vehicles colliding with the bridge structure?
Vertical clearance for the underpasses follows Caltrans design requirements, which are 16 and a half feet without a
variance and 15 and a half feet with a variance. The 15 percent design used 16 and a half feet in order to establish a
conservative preliminary footprint. During 35 percent design, staff will evaluate reducing the clearance to 15 and a half
feet with a sacrificial beam. Clearances at the existing Oregon Expressway and Embarcadero Road undercrossings are
lower. Those structures were built under earlier standards and different vehicle conditions. Clearance requirements have
increased in response to vehicle collisions with rail bridges elsewhere. Because state and federal grant funds are
involved, funding agency review requirements also apply and will be reflected in the design. Staff will continue
coordination with Caltrain on which requirements are fixed and where flexibility may exist. Rail Committee Not Concept Specific Construction Considerations
107
Requested a clearer understanding of which Caltrain requirements
are necessary and which are preferences as the project advances.
Several items were offered for future consideration rather than for
decision at this time: potential signals on Alma Street between
Meadow Drive and Churchill Avenue, and what role they might play
in these projects or in reducing speeds on Alma Street; and, if
Churchill Avenue is placed on indefinite hold, options for improving
bicycle and pedestrian crossing in that area, including a bicycle only
undercrossing on the north side of California Avenue at lower cost
than a new combined facility, with the existing undercrossing
retained for pedestrians. The focus on geotechnical and utility risk in
the 15 percent work was commended. It was also noted that state
growth projections have been revised downward from the forecasts
that informed earlier assumptions about future train and vehicle
volumes, which changes long term expectations for how many grade
separations will be needed along the corridor.
Staff will continue to work with Caltrain during 35 percent design to distinguish requirements from preferences, and will
report back on items where flexibility may exist. Signals on Alma Street and a bicycle only undercrossing near California
Avenue are outside the scope of the current project. Staff can carry these forward as items for future consideration
through the City's separate transportation planning and capital programming processes. Geotechnical and utility
investigation will continue during 35 percent design, including subsurface utility exploration beginning in October 2026
and coordination with the City's Utilities Department. Travel demand and rail service assumptions used in the analysis
will be reviewed during 35 percent design and environmental documentation as updated regional and state projections
become available.Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid Design Elements and Development
108
Does the Committee need to give direction so that an underpass at
Meadow Drive receives full consideration during 35 percent design?
Concern was raised that the alternative discussed by members of the
public would not be available for a recommendation after 35 percent
design because it was not advanced through 15 percent design.
Clarification was requested on whether that option would remain
available at the conclusion of 35 percent design.
The current grant funding supports advancing the alternatives selected by City Council in December 2025 through 15
percent and 35 percent design. An underpass at Meadow Drive is not among those alternatives and is not funded for
advancement in this phase. An underpass at Meadow Drive was evaluated at a high level for the November and
December 2025 City Council meetings, including circulation, constructability, and property impacts. Advancing it further
would require additional funding and time, including design work to a comparable level of detail before a decision could
be made. City Council could direct that work at a future date using other funding sources. Staff will provide additional
explanation of why the alternatives were narrowed and will provide more specific information on the concerns raised
about the Meadow Drive Hybrid, including wall height and construction duration. One clarification on duration:
Charleston Road and Meadow Drive delivered concurrently are estimated at approximately 5 years, and delivered
sequentially at approximately 9 years. These are alternative scenarios rather than a combined duration. Rail Committee Meadow Drive Hybrid Design Elements and Development
109
Do the property impacts presented cover Charleston Road only, or all
three crossings? Are there no full property acquisitions associated
with the Meadow Drive Hybrid, and are there full acquisitions
associated with the Charleston Road Underpass? Would an underpass
at Meadow Drive require full acquisitions, given the multifamily
housing and larger buildings at that location?
Potential property impacts have been identified at all three crossings, not just at Charleston Road.
At Meadow Drive, the Hybrid does not include any full acquisitions. It includes two partial acquisitions to accommodate
pedestrian facilities on the west side, and full acquisitions were avoided on the east side. The Charleston Road
Underpass does include potential full acquisitions. Based on the high level evaluation prepared for City Council in
November and December 2025, an underpass at Meadow Drive would require full acquisitions. That alternative was not
advanced through 15% Design, so the extent has not been refined. The expectation of fewer property impacts was one
reason the Hybrid was carried forward at Meadow Drive, and it remains one of the principal tradeoffs between
alternatives at that location. Information shown about potential right of way needs is for planning purposes. No
property acquisition is authorized at this stage. Any future acquisition would require project approval, confirmation of
right of way needs, compliance with applicable acquisition procedures, separate funding, and separate authorization. Rail Committee
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid Design Elements and Development
110
The concerns being raised about the Meadow Drive Hybrid are valid,
and the Committee has also heard consistently from community
members who favor a viaduct, which is not among the alternatives
being advanced. Having completed 15 percent design, the decision at
Meadow Drive is effectively set for this phase, though a different
alternative could be considered in the future. Rather than simply
stating that, the project should proactively explain to the public what
the reasons for narrowing were, including for the viaduct, and
whether those reasons still hold.
Alternatives at each crossing were narrowed through the Connecting Palo Alto screening process, the Rail Crossing
Community Advisory Committee (XCAP), and successive Rail Committee and City Council direction. Refinement of
roadway and track geometry prior to 15 percent design produced the Hybrid at Meadow Drive by identifying a track
elevation that avoided full acquisitions and reduced permanent impacts. Staff will provide historical context on how the
alternatives were narrowed, including the reasons a viaduct was not carried forward, in materials for the September 28,
2026 City Council meeting and in ongoing public engagement. Construction period effects will be a focus of 35 percent
design and environmental documentation. If the information developed during that phase does not adequately address
the concerns raised, City Council would have the opportunity to revisit its direction at that time. Rail Committee Meadow Drive Hybrid Design Elements and Development
111
Could Alma Street be permanently reduced to one travel lane in each
direction between San Antonio Road and East Meadow Drive, with
dedicated turn lanes at key intersections and space for bicycle
facilities?
The project teams is evaluating opportunities to improve safety, connectivity, and accessibility for all users of the
corridor users of the corridor, including pedestrians, bicyclists, transit riders, and motorists. The current grade separation
concepts focus on improving safety and mobility at rail crossings while maintaining roadway operations and access.
Community input regarding multimodal improvements and Complete Streets elements along Alma Street will be
documented and considered as project design advances. Project Website Meadow Drive Hybrid Bicycle, Pedestrian, and School Access
112
Will bicyclists be permitted to ride within the vehicle travel lanes on
Charleston Road rather than use the shared pedestrian and bicycle
facilities?
The project team is evaluating how all users, including bicyclists, will navigate proposed improvements at Charleston
Road. Bicycle and pedestrian facilities shown in 15 percent design are preliminary and will continue to be refined during
35 percent design. The project team is exploring how bicycle movements could be accomodated both within dedicated
facilities and along the roadway, while considering safety, accessibility, traffic operations, utility constraints, and
connectivity. Any restrictions, requirements, or operational guidance for bicyclists would be determined during future
design phases and in coordination with applicable transportation agencies and regulations. Project Website Charleston Road Underpass - Direct Access Ramp Bicycle, Pedestrian, and School Access
113
What improvements are planned at the Embarcadero intersection to
improve bicycle and pedestrian access for students and residents
north of Churchill Avenue?
Improvements at the Embarcadero are being implemented through a separate project. Improvements on the north side
are largely complete, with remaining beacon-related electrical components still pending installation. Improvements on
the south side are anticipated to occur before implementation of the grade separation project. The project is intended to
improve bicycle and pedestrian access and safety for users traveling north of Churchill Avenue CSTC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Bicycle, Pedestrian, and School Access
114
What is the anticipated construction sequencing for the Charleston
Road, East Meadow Drive, and related crossing projects?
Construction sequencing has not been finalized. The City is evaluating whether the Charleston Road and Meadow Drive
improvements would be delivered concurrently, sequentially, or as separate projects. Final sequencing will depend on
project readiness, available funding, environmental review, and City Council direction. CSTC Meeting
Charleston Road Underpass - Direct Access Ramp; Meadow
Drive Hybrid Design Elements and Development
115
Has an implementation priority been established for the planned
crossings and roadway improvements?
No final implementation sequence has been established. Charleston Road has been identified as a priority corridor due
to its transportation role and traffic volumes; however, decisions regarding implementation order, project packaging,
and funding priorities will be determined by City Council as project development progresses. CSTC Meeting Not Concept Specific Design Elements and Development
116
Could the bicycle and pedestrian underpass at Churchill Avenue be
advanced ahead of other Churchill-area improvements?
The project team has indicated that advancing bicycle and pedestrian improvements earlier in the implementation
process may be considered where feasible. Final project phasing will continue to be evaluated during future design
phases based on funding, constructability, access needs, and coordination with related improvements. CSTC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip Bicycle, Pedestrian, and School Access
117
What grade is anticipated for the proposed bicycle and pedestrian
underpass at Seale Avenue?
The proposed Seale Avenue bicycle and pedestrian underpass is being designed to meet applicable accessibility
requirements, including ADA standards. Specific grades, slopes, and geometric details will continue to be refined during
future design phases.CSTC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Design Elements and Development
118
What lighting, overhead coverage, and safety features are anticipated
for the proposed underpass at Seale Avenue?
Lighting, overhead coverage, visibility treatments, and other safety features have not yet been finalized. These elements
will be evaluated and refined during future design phases as the project advances beyond the preliminary 15% Design
level.CSTC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Design Elements and Development
119
How will the project address soil stability and structural safety near
the proposed underpass at Seale Avenue?
Geotechnical investigations and engineering analyses will continue as design advances. Proposed retaining structures,
foundation systems, and soil stabilization measures will be designed to meet applicable engineering standards and
maintain long-term structural stability and safety.CSTC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip, Including Seale Ave Bicycle and Pedestrian
Undercrossing Design Elements and Development
120
What potential impacts could construction have on nearby school
activities, including noise and vibration?
Potential construction impacts, including noise, vibration, traffic, air quality, access, and effects on nearby schools and
neighborhoods, will be evaluated during environmental review under CEQA and NEPA. Appropriate mitigation measures
will be identified and considered as project planning and design progress. CSTC Meeting Not Concept Specific Construction Considerations
121
How will bicycle and pedestrian family dimensions, turning
movements, and project risks be further defined as design advances?
Facility widths, turning radii, user circulation patterns, utility constraints, and other project risks will continue to be
refined during the 35% Design phase. Additional engineering analysis, utility investigations, and stakeholder
coordination will provide more detailed information to support future design decisions and project evaluation. PABAC Meeting Not Concept Specific Design Elements and Development
122
Could the Seale Avenue bicycle and pedestrian crossing be
constructed before Churchill Avenue, and how was the proposed
tunnel length determined.
The project team has indicated that Seale Avenue may need to be completed before Churchill Avenue can be fully closed
in order to maintain bicycle and pedestrian connectivity, particularly for school access. The proposed tunnel length is
driven by engineering requirements, including track clearance, tunnel depth, accessibility standards, and the distance
needed to safely return users to grade. Opportunities for refinement will continue to be evaluated during future design
phases.PABAC Meeting
Churchill Avenue - Partial Underpass without Landscape
Strip; Seale Ave - Bicycle and Pedestrian Undercrossing Design Elements and Development
123
A community member expressed opposition to the Meadow Drive
Hybrid, citing the height of the wall facing the Fairmeadow and Park
Boulevard neighborhoods, a minimum of five years of temporary
track along Alma Street, reduced lanes on Alma Street, and the
resulting congestion, air quality, and noise effects.
The project team recognizes that wall height, construction duration, and conditions along Alma Street are significant
concerns for the Fairmeadow and Park Boulevard neighborhoods. City Council selected the Meadow Drive Hybrid in
December 2025, and the earthen berm with a short bridge over Meadow Drive was confirmed as the basis of design
following the March 2026 Rail Committee study session. Under the 15% Design, the track profile at Meadow Drive
would be raised by up to approximately 16 feet and the roadway lowered by approximately 7 feet, with the tracks
supported on embankment behind retaining walls. Wall heights, setbacks, and visual character are preliminary at this
level of design, and staff will provide more specific information on wall height as design advances. A temporary track,
called a shoofly, is required where the track profile is raised. Under the combined delivery scenario it would be built east
of the existing tracks along Alma Street, beginning north of Meadow Drive and ending south of Charleston Road, and
would reduce Alma Street to one lane in each direction for the duration of construction. The preliminary construction
duration is approximately 60 months for combined delivery and approximately 92 months if the two crossings are
delivered sequentially. After construction, the shoofly would be removed and the corridor restored. Noise, vibration, air
quality, traffic, access, and visual effects will be studied through environmental review under the California
Environmental Quality Act (CEQA) and the National Environmental Policy Act (NEPA), beginning in fall 2026. Reducing
construction period impacts, including the overlap of crossing closures, is a specific objective of the 35% Design phase.
This comment and the linked video will be documented and provided to the Rail Committee and City Council for
consideration.Project Website
City of Palo Alto
Grade Separation Project
Churchill Avenue, Meadow Drive,
and Charleston Road
Palo Alto Engagement Summary
September 28, 2026
Engagement Informing Council Direction #2
Rail Committee
Total Project Cost Estimate
and schedule; community
meeting feedback
AUGUST OCTOBER15101520253051015202530
9/8
CSTSC
Safe access routes for
Palo Alto HS & other
PAUSD schools
8/20
Community Meetings
15% design overview; Total Project Cost Estimate
and schedule; community feedback opportunities;
what will continue to be refined
8/25 & 8/26
PABAC
Planned
pedestrian/bike
considerations
9/3
City Council
Concurrence on concepts to
advance into 35% design and
environmental documentation
9/28
2
Community Outreach Methods
3
984 Mailers sent to residents/owners
Social Media Blast Promoted project via Palo Alto Weekly
7 Lawn Signs placed
Email blasts to project
website subscriber list
Meeting Format
2 Meetings
68 attendees for both meetings
Comment Input Process
100+ Comments
Comments and responses logged in the
project comment tracker
Community meeting materials posted to
the project website
Community Meeting Recap
4
Key Topics Discussed
Bicycle,
Pedestrian, and
School Access
Design Elements
and Development
Total Project
Cost Estimate
Construction
Considerations
5
Neighborhood and Residential Effects: Respondents expressed concern about the day-to-day impacts of
construction on households near the corridor, including noise, environmental exposure, and what support would be
available if a residence could not be occupied during construction.
Flooding, Trees, and Environmental Considerations: Respondents asked how flooding risk would be evaluated
in lowered roadway sections and whether long term pump operation and maintenance is accounted for.
Respondents also asked that mature trees and park resources, particularly at Peers Park, be protected as the
design advances.
Corridor Wide and Long-Term Considerations: Respondents asked the project to consider the corridor as a
whole, including the South Palo Alto bicycle and pedestrian crossing, inclusion of the Palo Alto Avenue crossing,
compatibility with potential future Caltrain improvements, and long-term rail safety and corridor access.
Project Delivery, Funding, and Communication: Respondents raised questions about the City's capacity to
deliver a program of this size, whether bicycle and pedestrian elements could be funded separately, and asked for
clearer explanation of how conditions would change. Operational questions were also raised regarding emergency
response access and Alma Street conditions beyond the crossings.
Additional Topics Heard From Community
6
Palo
Alto
High
School
Churchill Ave – Partial Underpass
7
Alma Street and Churchill Avenue Intersection: Respondents shared input on turn movements to and
from southbound Alma Street, the availability of signalized connections, and how sight distance and
queuing at the intersection are being evaluated.
Neighborhood Street Circulation: Respondents shared input on traffic conditions on surrounding
neighborhood streets, including cut through traffic near Palo Alto High School and the role Churchill
Avenue plays in connecting neighborhoods across the corridor.
Bicycle, Pedestrian, and School Access: Respondents shared input on walking and bicycling routes
serving Palo Alto High School and Walter Hays Elementary School, including route directness, safety
features on the pedestrian bridge, and the possibility that route changes could influence how students
and families choose to travel.
Construction Considerations: Respondents raised questions about how bicycle, pedestrian, and
student access would be considered during the construction period.
Churchill – Community Key Takeaways
8
Seale Ave – Bicycle and Pedestrian Undercrossing
9
West Ramp
to/from
Undercrossing
East Ramp
to/from
Undercrossing
Peers Park
Expected Use and Route Directness: Respondents shared input on how the undercrossing would be
used, including its location relative to existing crossings at California Avenue and Embarcadero Road, and
how route directness could influence travel choices for nearby households and students.
Intersection Conditions at Alma Street: Respondents shared input on the interaction between people
bicycling exiting the undercrossing and turning vehicles at Alma Street, including sightlines, separation,
and turn movements at the intersection.
Peers Park: Respondents shared input on the alignment of the undercrossing along the northwest edge
of Peers Park, including whether an alignment farther from that edge was considered.
Total Project Cost Estimate: Respondents asked about the estimated cost of the Seale Avenue bicycle
and pedestrian crossing as a distinct element of the project.
Seale – Community Key Takeaways
10
11
Meadow Drive – Hybrid
Design Elements and Development: Respondents shared input on why the hybrid configuration is
proposed at Meadow Drive, how it differs from the approach at Charleston Road, and how it compares
with grade separations elsewhere along the corridor.
Aesthetics and Visual Effects: Respondents shared input on the appearance of the retaining wall along
the raised track, including its height, continuity, and how it would be experienced from adjacent streets
and homes.
Bicycle, Pedestrian, and School Access: Respondents shared input on walking and bicycling
conditions at East Meadow Drive, including how the crossing experience could change, how people
traveling at different speeds would share space, and how student and parent travel patterns are being
considered.
Construction Considerations: Respondents raised questions about the temporary tracks, including their
potential effect on travel along Alma Street and the duration of those conditions.
Meadow – Community Key Takeaways
12
13
Charleston Road – Underpass
Bicycle, Pedestrian, and School Access: Respondents shared input on the proposed bicycle and
pedestrian facilities, including the switchback ramp configuration, path width where people biking and
walking share space, directional travel, and sidewalk and buffer conditions near Alma Street.
Design Elements and Development: Respondents shared input on the engineering and design
considerations that shaped the Charleston Road alternative, including the intersection configuration at
Alma Street and how drainage in the lowered roadway is being studied.
Potential Property Effects: Respondents asked how close the direct access ramp would come to homes
along East Charleston Road, with front yard depth and proximity to traffic raised as concerns.
Construction Considerations: Respondents shared input on potential construction staging near East
Charleston Road and Mumford Place, and on how potential effects on nearby residents are being
considered as the design advances.
Charleston – Community Key Takeaways
14
Bicycle and Pedestrian Access to Schools: Committee members provided input on walking and
bicycling routes serving students, including conditions at the Embarcadero Road intersection for students
north of Churchill Avenue who are less likely to travel south to the proposed Seale Avenue crossing.
Sequencing and Delivery: Committee members provided input on how the crossings would be
sequenced, including the relationship between the grade separations and the South Palo Alto Bicycle and
Pedestrian Connectivity Project and whether the Seale Avenue undercrossing could be advanced ahead
of Churchill Avenue.
Seale Avenue Undercrossing Design Elements: Committee members provided input on the design of
the undercrossing, including grade and accessibility, the extent of tunnel enclosure, and lighting and
safety features to be developed in later design phases.
Construction Effects Near Schools: Committee members provided input on construction period
conditions adjacent to school property, including ground stability near the field area at Churchill Avenue
and potential vibration and noise effects on class time.
CSTSC Feedback
15
Bicycle and Pedestrian Facility Detail: Committee members requested more specific information on how the facilities
would function, including path widths, turning radii, and a walkthrough of the route a person would take by direction and
by mode.
Charleston Road Access and Connectivity: Committee members expressed concern that the switchback ramp is
indirect, lacks a pedestrian stair option, and would likely lead most cyclists to remain in the roadway. Members also
asked how cyclists traveling east would cross Charleston Road and noted that the configuration should be tested
against adopted City goals for walking, bicycling, and reduced vehicle miles traveled.
Alma Street Corridor Treatment: Committee members stated that where the project substantially changes Alma
Street, the corridor should be treated as a complete street, with adequate sidewalk width and a buffer separating people
walking and bicycling from traffic.
Information Requested Before Advancing: Committee members asked for additional detail ahead of the Council item,
including where pedestrian and bicycle detour routes would go during construction, resolution of risks still identified as
undefined, drawings showing the extent of the raised track profile at Meadow Drive, and whether the Seale Avenue
undercrossing could be delivered ahead of Churchill Avenue.
PABAC Feedback
16
Project Scale and Funding Reality: Committee members discussed the gap between the estimated
total project cost for all three crossings and the funding currently identified and indicated a likely
narrowing of crossing focus.
Meadow Drive Alternative and Public Explanation: Committee members asked the project team to
restate why the hybrid was carried forward at Meadow Drive rather than the underpass and requested the
wall height profile with greater specificity on where effects occur. Members emphasized that the reasons
for narrowing the range of alternatives need to be explained more clearly to the public.
Charleston Road Priority and Refinements: Committee members identified Charleston Road as the
likely near-term priority given traffic volumes, and discussed preliminary level of service results across
existing, project, and future no build conditions.
Right of Way Requirements and Cost Responsibility: Committee members asked why the retaining
wall at Meadow Drive extends to the edge of Alma Street.
Rail Committee Feedback
17
City of Palo Alto
Grade Separation Project
Churchill Avenue, Meadow Drive,
and Charleston Road
City Council
September 28, 2026
Presenters: Jessica Dai, Edgar Torres, and Whitney DiGiantommaso
City Council Direction #2
2
Direction to advance selected concepts to 35% design and environmental documentation.
GRADE
SEPARATION
APPROACH
CROSSING Charleston Road
UNDERPASS
Direct Access Ramp
PARTIAL UNDERPASS
Churchill Avenue
without Landscape Strip
Includes Seale Avenue
Bike/Ped Crossing
Meadow Drive
HYBRID
Elevated rail bridge
Project Area
Downtown
Palo Alto
Current Project Phase
4
2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Preliminary Engineering and Environmental
35% Design and Environmental 15% DesignConcept Development
and Refinement
City Council Direction #2:
Direction to advance to 35%
Design and Environmental
Documentation
City Council Direction #1:
Identified alternatives to
advance to 15% Design
Completed 35% Design and
Environmental Documentation
#1 #2
We are here
Direction from City Council
GRADE
SEPARATION
APPROACH
CROSSING Charleston Road
UNDERPASS
Direct Access
Ramp
PARTIAL
UNDERPASS
Churchill Avenue
Vehicle Crossing
(without Landscape Strip)
Bike/Ped Crossing
(Seale – Alma
Street Ramp)
Meadow Drive & Charleston Road
HYBRID
Elevated rail
bridge
UNDERPASS
Direct Access
Ramp
5
Major Drivers at each Crossing informed Council
Churchill Avenue
Partial Underpass without landscape
strip, Alma Street Ramp at Seale Avenue
Major Driver
Potential property impacts
Prioritized reducing potential property
impacts along Alma Street, as traffic
operations did not differ between the two
options.
Tradeoff
No landscape buffer between the curb
and the sidewalk along Alma Street.
Meadow Drive
Hybrid
Major Driver
Potential property impacts and
bicycle/pedestrian accessibility
Avoided the potential full residential
acquisitions the Underpass option
required while preserving every turning
movement at the intersection.
Tradeoff
A raised track profile and retaining wall
adjacent to a segment along Alma
Street.
Charleston Road
Underpass with Direct Access Ramp
Major Driver
Potential property impacts and
direct traffic access
Reduced potential property acquisitions
east of the tracks while providing more
direct traffic access at the intersection.
Tradeoff
Restricted movements between Park
Boulevard and Charleston Road.
6
South Palo Alto Bicycle and Pedestrian Connectivity Project
7
Downtown
Palo Alto
South Palo Alto Bicycle and
Pedestrian Connectivity Project
Evaluating two design alternatives for a new
grade-separated bicycle and pedestrian rail
crossing near El Dorado Avenue.
Project Status: Planning and Conceptual Design
Funded Through: 15% Design (City funds)Alternative 2 Alternative 1
P
a
g
e
M
i
l
l
R
d
C
h
u
r
c
h
i
l
l
A
v
e
S
e
a
l
e
A
v
e
Alma StU
n
i
v
e
r
s
i
t
y
A
v
e
15% Design Findings and Next Steps
8
Key Design Element 15% Design Findings 35% Design Will Provide
Track
•Churchill Avenue tracks remain at existing
elevation.
•Track profile raised at Meadow Drive and
Charleston Road (when delivered together)
•Refined vertical and horizontal alignment,
shoofly design, and confirmation of track profile
under each delivery scenario
Project Footprint •Developed preliminary project footprint for
environmental studies •Established project footprint for approvals
Roadway and Drainage
•Established roadway profiles and preliminary
drainage, including pump stations at each
depressed crossing
•Refined profiles and geometry, plus a traffic
study of construction-period and permanent
operations
Structural and Geotechnical
•Established structural approach at each
crossing, including retaining wall systems and
box structures.
•Site-specific geotechnical investigation of soil,
groundwater, and settlement risk
Utilities •Developed preliminary utility base map and
conflict matrix from records research
•Verified locations and depths through subsurface
investigation and potholing, a detailed conflict
matrix, and refined relocation plans
Palo
Alto
High
School
Churchill Ave – Partial Underpass
9
•No modifications to track
•Roadway lowered approximately 22 feet
via a concrete box under the tracks
•Constructed by box jacking
Seale Ave – Bicycle and Pedestrian Undercrossing
10
West Ramp
to/from
Undercrossing
East Ramp
to/from
Undercrossing
Peers Park
•Tunnel extended approximately 65 feet west into Peers
Park, where retained soil depth reaches up to 18 feet
•Ramp end retaining wall lengths reduced by 14 feet at each
end
•Constructed by box jacking
11
Meadow Drive – Hybrid
•Meadow Dr and Charleston Rd combined
delivery will result in tracks raised
•Track raised approximately 7 feet
•Temporary track required to maintain
rail service during construction
12
Charleston Road – Underpass
•If Charleston Rd constructed alone:
•No modifications to track
•Charleston Road lowered 24 feet
•Constructed by box jacking
•Roadway and path raised on
cantilever slabs to avoid the existing
gas transmission line
•1.1 Mile Track Shoofly (Temporary Tracks)
•~4700’ Encroachment into Alma Street
Shoofly (Temporary Tracks for Construction)
13
1.1 Mile (Temporary Tracks)
~4,700’ Length of Encroachment along Alma Street
Delivery Scenarios Evaluated
14
CHURCHILL
AVENUE
CROSSING
Charleston Road
+
Meadow Drive
Charleston Road
Meadow Drive
Charleston Road MEADOW AND
CHARLESTON
CROSSING
Churchill Avenue
with Seale Avenue
Concurrently Sequentially
Total Project Cost Estimate Life Cycle
15
Concept Design
Purpose of the Estimate
Schedule
High-level schedule estimate
Preliminary Design &
Environmental Review
Schedule
Preliminary schedule
Design Development
Schedule
Revised schedule
Final Design &
Construction Documents
Schedule
Project baseline schedule
Support concept due diligence
and inform early decisions
Purpose of the Estimate
Support environmental review
and funding plan
Purpose of the Estimate
Support procurement, and
contract packaging
Purpose of the Estimate
Establish construction budget
Final
Design
35%
Design
65%
Design
15%
Design
Cost Estimate Cost Estimate Cost Estimate Cost Estimate
Rough Order of Magnitude (ROM)Preliminary Detailed Project baseline budget
WE ARE
HERE
LATE
2027
Risk Associated with Costs*
16
35%
Design +
Environmental
65%
Design
Construction
Documents
✓Risks Addressed/Mitigated
Stable project footprint identified
!Risks Remaining
Delivery method not confirmed
Unknown utilities
Potential property impacts not confirmed
Soil and groundwater undefined
Construction sequencing uncertainty
Schedule and funding uncertainty
✓Risks Addressed/Mitigated
Delivery method
Project footprint refined
!Risks Remaining
Utility relocations
Potential property acquisition
Railroad work windows
Construction staging
✓Risks Addressed/Mitigated
Utilities located
Soil investigated
Potential property acquisitions appraised
!Risks Remaining
Market conditions
Regulatory approvals
Long-lead time materials
✓Risks Addressed/Mitigated
Scope finalized
Utility design complete
Potential property acquired
Railroad windows confirmed
!Risks Remaining
Unforeseen conditions
Price increases before award
Range of Estimate
Improves with
Design
*Typical risks shown; not inclusive of all potential risks
15%
Current Design
Phase
1.Construction Contractor Cost (Direct & Indirect)
•Permitting and Utilities
2.Designer/Engineer of Record Costs
3.Agency Costs
•Project Management and Oversight
•Environmental Documentation and Permitting
•TASI
•Construction Administration, Management, and Inspections
4.Real Property and Easements
5.Escalation (Cost of Time)
6.Project Contingency (Unallocated & Allocated)
Total Project Cost Estimate – Buildup
17
Construction Contractor Cost (Direct & Indirect)•Permitting and Utilities Designer/Engineer of Record Costs Agency Costs•Project Management and Oversight•Environmental Documentation and Permitting•TASI•Construction Administration, Management, and Inspections Real Property and Easements Escalation (Cost of Time)Project Contingency (Unallocated & Allocated)
Construction Contractor Cost
(Direct & Indirect)
•Permitting and Utilities
Designer/Engineer of Record Costs
Agency Costs
(Caltrain, City, etc.)
Real Property and Easements
Escalation
(Cost of Time)
Project Contingency
(Unallocated & Allocated)
•Project Management and
Oversight
•Environmental Documentation
and Permitting
•TASI
•Construction Administration,
Management,
and Inspections
Total Project Cost Estimates
18
Charleston Road +
Meadow Drive
Charleston
Road
Meadow
Drive
Charleston Road
Costs and durations are preliminary in nature and represent rough order -of-magnitude
estimates that will be further refined during future phases of design.
Delivery Scenario
Estimate Year
(Year of Dollar)2026
Estimated
Construction Start 2032
High -Level
Construction Duration 3 – 4 years 5 years 9 years 4 years
Total Project Cost
Estimate
(Year of Expenditure)
$420M – 450M $1B – 1.1B $1.2B – 1.3B $480M – 530M
Churchill Avenue
with Seale Avenue
Meetings Held
CSTSC – 8/20
Community Meeting #1 – 8/25
Community Meeting #2 – 8/26
PABAC – 9/3
Rail Committee – 9/8
City Council – 9/28
Key Topics Discussed
Bicycle, Pedestrian, and School Access
Design Elements and Development
Total Project Cost Estimate
Construction Considerations
What we are doing next
Comments and project team responses logged in the project comment tracker
Community meeting materials posted to the project website
Engagement Recap
19
Engagement Feedback
20
CSTSC
August 20
•Walking and bicycling
routes serving students
•Construction effects near
school and property
•Sequencing with the
South Palo Alto Project
Community Meetings
August 25 & 26
PABAC
September 3
Rail Committee
September 8
•Total project cost
estimate and schedule
•Bicycle, pedestrian and,
and school access
•Construction effects near
homes
•Charleston Road ramp
configuration
•Pedestrian and bicycle
detour routes during
construction
•Project cost relative to
funding currently
identified
•Clearer public
explanation of how
alternatives were
narrowed
21
Project Phase Funding Sources
Planning & Conceptual
Design $5M
15% Design
$20M
35% Design
Final Design
Construction
Anticipated Funding Sources
FRA Rail Crossing Elimination Grant
VTA Measure B Grade Separation Fund
$23.79M$9M State TIRCP Award
City
Measure K
Phases fully funded
Funding
Strategy to be
Determined
Findings from design process
will inform future City Council
decisions surrounding
prioritization, phasing, and
implementation strategy
City Capital
Funds
VTA Measure B Local
Streets & Roads Fund
Potential Unallocated Funding:
City Measure K: $5M – $30M
VTA Measure B: $325 – $350M
❑3D visualizations of each crossing
❑Technical studies including construction traffic analysis,
noise, air quality, biology, cultural resources, and related
studies completed
❑Refined project footprint
❑CEQA and NEPA environmental documentation
❑Construction sequencing and closure duration
❑Updated cost estimates and schedules
22
Design and Environmental
Documentation
35%
Design Next Steps
City Council Direction #2
23
Direction to advance selected concepts to 35% design and environmental documentation.
GRADE
SEPARATION
APPROACH
CROSSING Charleston Road
UNDERPASS
Direct Access Ramp
PARTIAL UNDERPASS
Churchill Avenue
without Landscape Strip
Includes Seale Avenue
Bike/Ped Crossing
Meadow Drive
HYBRID
Elevated rail bridge
From:Melinda McGee
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Saturday, September 26, 2026 1:18:55 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require temporary shoofly tracks for
at least five years. Please don’t spend more money and time in advancing a bad option. It’s better to leave Meadow
crossing as is with full safety measures than spend a half a billion on a destructive plan that will ruin our
neighborhoods. Running trains on Alma for a minimum of 5 years during construction is a really stupid idea!
Please advance the East Meadow Underpass to the next design stage or don’t advance a plan at all. Box jacking
eliminates the need for shoofly tracks and avoids building a 1.22-mile concrete berm and wall that is taller than the
Berlin Wall in places.
Thank you for considering my views.
Melinda McGee
Fairmeadow
From:samantha nguyen
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Saturday, September 26, 2026 3:15:20 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require temporary shoofly tracks for
at least five years.
Please advance the East Meadow Underpass to the next design stage. Box jacking eliminates the need for shoofly
tracks and avoids building a 1.22-mile concrete berm and wall that is taller than the Berlin Wall in places.
Thank you for considering my views.
Thanks,
Thang Nguyen
Sent from my iPhone
From:Shifa Xu
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 7:06:52 AM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require
temporary shoofly tracks for at least five years. Please advance the East Meadow Underpass to
the next design stage. Box jacking eliminates the need for shoofly tracks and avoids building a
1.22-mile concrete berm and wall that is taller than the Berlin Wall in places.
Thank you for considering my views.
Shifa
This message needs your attention
This is a personal email address.
Mark Safe Report
Powered by Mimecast
From:Mar Carpanelli
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 7:14:34 AM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require
temporary shoofly tracks for at least five years.
Please advance the East Meadow Underpass to the next design stage. Box jacking eliminates
the need for shoofly tracks and avoids building a 1.22-mile concrete berm and wall that is
taller than the Berlin Wall in places.
Thank you for considering my views.
Mar Carpanelli
This message needs your attention
This is a personal email address.
Mark Safe Report
Powered by Mimecast
From:Sergey Firsov
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs. Same money
Date:Sunday, September 27, 2026 11:52:26 AM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs
to the next stage of engineering (35% design). Thank you for considering my views.
Regards
Sergey Firsov
+1 (650) 210-6804
This message needs your attention
This is a personal email address.
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:Marina Egorova
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 12:10:02 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Marina Egorova
4226 Ponce Dr. Palo Alto, 94306
From:Pengfei Wang
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 12:26:35 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council, Please vote NO on advancing the Hybrid at East Meadow. Please advance
Underpass designs to the next stage of engineering (35% design). Thank you for considering
my views. [Your name]
This message needs your attention
This is a personal email address.
This is their first email to your company.
Mark Safe Report
Powered by Mimecast
From:Ashrita C
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 12:41:57 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Regards,
Ashrita
From:Joe Pearson
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 12:50:17 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
[Your name]
Sent from my iPhone
From:Kassandra Garcia
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 12:53:49 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Kassandra Garcia
94301
From:Ola Koumrian
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 1:20:27 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Better leave it as is than erect a monstrocity
Thank you for considering my views.
Olga and Todd Koumrian
3107 Stelling
From:mike@mikeforster.net
To:Council, City; Transportation
Subject:Suspend grade separations consulting expenditures, and reconsider the viaducts approach
Date:Sunday, September 27, 2026 1:54:16 PM
Attachments:Palo Alto - Caltrain Viaduct Grade Separations - Mike Forster v15.pdf
Importance:High
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
!
(This Letter to the Editor appeared in the Palo Alto Daily Post, August 31,
2026, page 6; and was sent to the City Council and Transportation Department
on September 2, 2026.
This message adds the attachment, "Viaducts Grade Separations for Palo Alto",
updated with the August 2026 15% design costs and timeframes, reorganized,
and with tables of contents.)
Our Palo Alto City Council should immediately suspend expenditures to
consultants regarding grade crossings, and then reconsider viaducts.
Caltrain has announced that without the half-percent sales tax measure in
November, they will have to cut back or even eliminate service entirely. A
recent California High-Speed Rail Authority budget indicates that the Gilroy to
San Jose section is as yet an unresolved multi-billion dollar project. So, the
primary driver of grade separations, increased rail traffic, might never happen.
In the opinion of a recent Palo Alto City Council member, funding for
the $1.5 billion project would not occur in the foreseeable future.
Altogether, any further expenditures on consultants may be totally
wasted for a project that may never occur, and should be suspended until at
least 2027.
If and when design work would restart, the viaducts option should be
reconsidered at the top of the list. Viaducts will: be much less expensive; be
less disruptive during construction; less risky in terms of cost and schedule;
avoid property acquisitions; maintain current good vehicle traffic flow avoid
flood risk; and avoid underground utility relocations.
This message could be suspicious
Similar name as someone you've contacted.
Mark Safe Report
Mike Forster
Palo Alto
--
You received this message because you are subscribed to the Google Groups
"ReconnectPaloAlto" group.
To unsubscribe from this group and stop receiving emails from it, send an email to
reconnectpaloalto+unsubscribe@googlegroups.com.
To view this discussion visit
https://groups.google.com/d/msgid/reconnectpaloalto/07e101dd3aea%2484c0d090%
248e4271b0%24%40mikeforster.net.
From:Chengzhong Wu
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 1:58:48 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council, Please vote NO on advancing the Hybrid at East Meadow. Please advance
Underpass designs to the next stage of engineering (35% design). Thank you for considering
my views.
Cheng
This message needs your attention
This is a personal email address.
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:Robin Tu
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 3:28:15 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs
to the next stage of engineering (35% design).
Thank you for considering my views.
Robin Tu
- On the move
This message needs your attention
This is a personal email address.
Mark Safe Report
Powered by Mimecast
From:Pat Lee
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 4:56:17 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Pat
Sent from my iPhone
From:Jim Stauffer
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 5:51:12 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require
temporary shoofly tracks for at least five years and would make living and travel
intolerable for nearby residents.
Please advance the East Meadow Underpass to the next design stage. Box jacking eliminates
the need for shoofly tracks and avoids building a 1.22-mile concrete berm and wall that is
taller than the Berlin Wall in places.
Thank you for considering my views.
Jim Stauffer
Fairmeadow
This message needs your attention
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:Anya Mahan
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 6:26:39 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs
to the next stage of engineering (35% design).
Thank you for considering my views.
Anya Mahan (Fairmeadow)
Best Regards,
Anya Mahan
This message needs your attention
This is a personal email address.
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:Charlie
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 6:32:30 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
!
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Chengdi Sheng
Yahoo Mail: Search, Organize, Conquer
This message could be suspicious
Similar name as someone you've contacted.
No employee in your company has ever replied to this person.
This is a personal email address.
Mark Safe Report
From:MAO-HONG
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 7:28:00 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council, Please vote NO on advancing the Hybrid at East Meadow. Please advance
Underpass designs to the next stage of engineering (35% design). Thank you for considering
my views.
Hong Mao
3741
This message needs your attention
This is a personal email address.
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:BYUNG
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Sunday, September 27, 2026 8:45:07 PM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs to the next stage of
engineering (35% design).
Thank you for considering my views.
Byung Ahn
Sent from my iPhone
From:Brian Kilgore
To:Burt, Patrick; Lauing, Ed; Lythcott-Haims, Julie
Cc:Council, City; Shikada, Ed; Lo, Ria
Subject:East Meadow - grade separation
Date:Sunday, September 27, 2026 9:44:46 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear Rail Committee,
I still disagree with advancing the hybrid crossing at East Meadow. It's basically 80 percent, or
so, in height compared to the viaduct option which the community resoundly rejected shortly
after the CA High Speed Rail Authority announced their plans to elevate the tracks through
most of not all of the city.
The Hybrid would mean an estimated 5 to 9 years of shoofly construction, with temporary
Caltrain tracks, operating trains and catenary on Alma Street while Alma is reduced to one
traffic lane in each direction. It would then leave a permanent raised railroad and wall
condition along Alma.
The Underpass may avoid these impacts. Before Palo Alto makes this long-term commitment,
please give the Underpass the engineering development needed for a fair comparison.
Please advance the Underpass at East Meadow.
Thank you.
This message needs your attention
This is a personal email address.
Mark Safe Report
Powered by Mimecast
From:Jl
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Monday, September 28, 2026 5:32:10 AM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require temporary shoofly tracks for
at least five years.
Please advance the East Meadow Underpass to the next design stage. Box jacking eliminates the need for shoofly
tracks and avoids building a 1.22-mile concrete berm and wall that is taller than the Berlin Wall in places.
Thank you for considering my views.
Jennifer Landesmann
From:Peter Streiff
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Monday, September 28, 2026 9:39:00 AM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
i
Dear City Council,
Please vote NO on advancing the Hybrid at East Meadow. Please advance Underpass designs
to the next stage of engineering (35% design).
Thank you for considering my views.
Peter Streiff
peter.streiff@gmail.com
This message needs your attention
This is a personal email address.
This is their first mail to some recipients.
Mark Safe Report
Powered by Mimecast
From:Hing Sham
To:Council, City
Cc:Burt, Patrick; Lauing, Ed; Lu, George; Lythcott-Haims, Julie; Reckdahl, Keith; Stone, Greer; Veenker, Vicki;
bgh@matteoni.com; brynachangPTC@gmail.com; ptc@caritempleton.com; ptc@allenakin.com;
kevinji2021@gmail.com; Planning Commission; Architectural Review Board; Lo, Ria; Shikada, Ed
Subject:East Meadow: No Hybrid. Advance Underpass designs.
Date:Monday, September 28, 2026 10:14:21 AM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking
on links.
Dear City Council,
Please vote NO on advancing the East Meadow Hybrid. Its construction would require temporary shoofly tracks for
at least five years.
Please advance the East Meadow Underpass to the next design stage. Box jacking eliminates the need for shoofly
tracks and avoids building a 1.22-mile concrete berm and wall that is taller than the Berlin Wall in places.
Thank you for considering my views.
[YourHing Sham name]
Sent from Hing's iPad