HomeMy WebLinkAbout0564.093.. November 4, 1993 THE HONORABLE CITY COUNCIL P~lo Alto, California .' Agreement with Varian Associates -Amendment Nor 1 Members of the Council: RePOrt in "rie! 3 • This report recommends that the city Coun~il approve and authorize the Mayor to execute the attaohed Amendment No. 1 to the Agreement by and between the City of Palo Alto and varian Associates., Inc~ The amendment allows Varian to convert sOlIe additional 4~16JcV equipment to 12.47kV under 'the terms of the aqreementl which will improve Varian and the City's electrical systems. Tbe amendment also contains some clarifications to the revenue aeterinq requirements and the service start date. Background On December 12, 1991, council approved an aqre~ent (CKR:549:91) with Varian Associates which authorized the City to install additional 12.47kV capacity at the Hansen way Substation. The new capacity was intended to serve a new test faGility {Test Set), that Varian was constructinq under It Department of Energy {DOE) contract. Varian has reimbur&ed the city under the terms of the agreement for all expenses to date for the installation. Varian is currently 3waitinq reimbursement from the Electric Utility under the agreement, which is based on the quantity of electric energy consumed by the Test Set~ On March 22, 1993, Varian noti~ied staff that its DOE funding had been delayed for the Test Set project and expressed concern that CIIIU 5 64 • 93 o Varian ftiqht not be able to obtain its entire reimburs~ment4 Varian requested that the City postpone the start date of the reimbursement for two years, in an effort to quarantee that the electric energy will be used as planned and a full reimburse.ent would be pos&ible. Statf did not want to extend the contract beyond the tive year interval since all accounting for the reimburs~t formula is done manually. Staff also recognizes the difficulty with the DOE funding and the need to work with Varian to retain a valuable business. For these reasons, staff began lookinq tor other ways to utilize the spare 12.47kV capacity and requested Varian to consider connecting additional electric loads to the new capacity. While Varian has no new electric loads, it does have significant existinq loads which are presently served frem the City's older 4.16kV system. Some of the City's old 4.16kV equipment, which serves Varian, is quickly approaching the end of its QQsign lite and needs to be retired. Staff realizes it would be in the best interest of both t.~e City and Varian, if Varian would convert some of its electric loads from the old system to the new l2.47kV system. This would enable the City to reduce Its maintenance costs and the inherent risk of failure of the old equipment, and it would allow Varian some reimbursement on their investment of new electrical equipment. To accomplish this~ varian must convert some equipment to the new 12.47kV system at its own expense. Staff is confident that Varian and staff can agree on the conversion plans so as to maximi~e benefits to both parties. Staff proposes to allow approved newly converted loads to be used in the reimbursement formula, ~r.der th~ terms of the agreement. Tbe attached amendment will expand the reimbursement formula to allow this. The amendment also clarifies the start date and .etering requirements for the reimbursement formula. Funding Varian ~ill fund all voltage conversion expenditures on their site4 Tbe City will SUPPOlt the voltaqe conversion effort with associated service cabling and connections. Fundin~ for miscellaneous city work will be from the Capital Improvement Program annual major project, Electric Meters and Service5. Environmental This project is an eXisting one under CEQA and therefore, is categorically exempt from any requirements. pezm-endation Staff r~oommend& that the city Council approve and authorize the Mayor to execute the attached Amendment No.1 to the Aqreement between the City of Palo Alto and Varian Associates, Inc. Respectfully submitted, lWtJ\tu. \.j ,~J (I MIC!I.~L D. BEAIlLAND E~l~ct~~ering ~anaqer E J. KRIZEK Di ector of Utilities ~i'it,~/ BERIIARD M. STROJNY Assistant City Manager Related CMR: CMR:549:91 Aqr ... ent with Varian Associate. Attacbaents: Aaendment No. 1 Aqreement CI010564'U . - .. AKENDMENT NO. 1 TO AGREEMENT e E'TWEEU CITY OF PALO ALTO AND VARIAN ASSOCIATES. IN'C. This Arr.cndrnent No+ 1 to Agreement, dated 1993, is entered into by and bet'wro'ee.n the City of Palo Altc, a chartered city and a municipal corporatiGn ("City") a:1d Varian Associates, Inc., a Delaware corporation, witr-~ offices at 3100 Hansen Way. Palo Alto , Califo:rnia (-Varian"). WHEREAS, the parties have entered into an agreement, dat~d January 16. 1992; and WHEREAS. the parties wish to amend thi~ agreement as set forth herein; NOW. THEREFORE. in consideration of the covenants, terms. and conditions set forth herein, the parties agree: .5...ECTION 1. The partie.s hereby incorporate by reference the letter of September 23. 1991 <attached hereto as ·Exhibit A"l. under which City has agreed to use the meters of Varian to determine electric usage credits under this Agreement under the terms and conditions set forth in such letter~ and the letter of Varian responding to the City's letter of September 23. 1991 {attached hereto as "Exhibt,t: B-). The two letters are intended to modify the terms of the last sentence of Seccian 1{a). paragraph two. SECTION 2. The first sentence of Section 2(e) is hereby modified to read as fallows: follows: "One year after said service begins and annually thereafter, City shall pay to varian twenty percent (20t) of the g:ross annual revenue received by City from the sale of electric po~er for the new Test Set and/or othe~ electric power loads mutually agreed upon by the parties, includir.g electric power loads resulting from the shifting of power loads from varian'S 4 KV power system to the new Test Set l2 KV system .• SECTION 3. Section 4. (c) is hereby added to read as -For the purposes of this Agreement, the tenn "date of init.ial operation" and the date by which service is deemed to begin shall be deemed to have conunenced on January 1, 1993." 1 , ,;.. • IN WITNESS WHEREOF, the parties have executed this Amendment No. 1 to Agreemenr in Palo Alto on the dar,e first above stated. Cit), Clerk APPROVED AS TO FORM, Senior ASs--e-:--city ]J.ttorney c-c-::-:::--=--===---_ Director of Finance Risk Manage r AP PROVED AS TO CONTENT, Director of Utilities CITY OF PALO Jl.LTO Mayo.! Taxpayer Identification No. 94-23S9J45~ ________ _ 2 · - September 23, 1991 Mr. Ha~iano castillo varian Associates 611 Hansen Way P a BOX ICl250' i'AL:J .... LiD. ("'Ulor.r,jA S',OOJ Palo Alto, Ca. 94303-0883 Subject: Variants New Test set Load -Metering Dear Mario, During our meeting on september 17t.h, you nentioneci. that you did not provide any metering space for the City to inst.all metering equipment. As you knm,,', the City needs to measure energy consu11lption .by the new Test Set in order to determine Variants annual credit under the Agreement being finali~ed. We understand that Varian would rather use the Varian watthour dem.>:lnd :meter currently e.}(isting in the feeder break~r cotlpartment (to be desiqrlated D33). We understand that the D3) feeder will be dedicated to the ne~ Test Set. We can allow the existing meter to be used if Varian agrees to the following; 1. Before varian installs the new 12.47kV potential transformers to replace the 4; .16kV units, please Iilake arrangeme:.ts to give the new PT's to the City's metering department for testing. The city reserves the ri9h~ to test and re-test any of the associated metering transforlll.ers at any time. Any outages required for testing 'Will only be done .... ith prior notification of Varian. 2. Va.rian shall allow the City metering department to test, calibrate, and seal Varian's t ..... a we.stir.~hc'...!~e '":.'"a-t.thOL<I derr.a..!"'ld m~ters located in feeders D]2 2.nd DJ]. The City will aI:;o install metering name tags like ~e do for our revenue ~eters. At the end of the five year contract, the city will remove the na~e tags and seals. 3. Varian shall pt"ovide key access to each of the meter locdtions for periodic checking and meter rt'!adings. As an c.lternate, Varian can install windows in the outer doors of feeders D32 and D33 to aIlo...,. the City to read the meters. 'The city .... ill not reset the demand registers on Varian's meters • .:.. Varian ""ill take month 1 '.!r readings of the t ... ,o meters (both peak KW 2nd .KWH) and send :,le readings tc the City. The City ..... ill cross check the Varian :meter readings ...:ith the city revenue DictE"r readings for accuracy. Varian .. ,rill read the meters and re.5~t the demand registers ,.dthin one day of the City!!:; meter EXHIBIT A reacHng of the City's meters. If th~ Varian metE>rs do not check against the City l":1ete.c 'Within 2%, the city has the option of ~stimCl.ti!lg the Test Set Load~ The City , ... ill annually tata I the meter read i ngs for: the test set and compute the dollar credit to Varian and issue such credit. 5. The City ..... ill have the right at any time to inst::-:l (at the city rs expense) a !..oad Profile Record.er with remote phone date; link to allow recording and analysis of the Test Load. I trust this is satisfactory. concerns, please contact :m~. If p]edse notify us in writing 50 agreement in our file. Regards l ~~-f~~ sam Zuccaro Sr. Por,,'er Eng ineer If you Varian .... e can have any questions or agrees 'With this plan l retain a copy of your ce. Mike Beanlanc, Electrical Engineering Manager Donna Hilden l Sr. Power Engineer Charles Randall, Metering supervisor l,a!."ry LaRosa, Lead Utility Servicepel..·son Tom Habashi, Sr. Power Engineer -Energy Planning Saul Gold, varian '" .... '-. , @ I,.·~! & 1200A'~P @\CW A"C r t.>-'3~) '~C,T." (® . ~@(Cj~~ii) 15KVA CPT ,.7j\ \~'3 il COMP'T,® ~ __ I -/-" L"'" 0~(mA ~ 'LAS f -, '~~,;I' ,- (? .. --><=,. .•. FRONT fuvAT/~" ' _-1Jffr>'~Y~(T W!?lI!!/',('f'£'xJF J)",&-'?l [) I C' " " fi:, ~ far ~C:C'u..r'(lt.e" T L., mNER C,1.5 . ;2CI'.1, PfIL. 1!'i~:VA CPT 1 ~ VA 1<iAl--\ ~ ~ "-6;0'~'1 .• 1-t':I-YI,.NNEL e..' 0" A ® PQ' .. ,ER r ,\1~",rf ./ -''{--I '.-I' ; ..... 1 "T L ..... '\11(, __ ' J . -t' ,,-x.., ,. "'~ :"'" 'f' ~;!'8 ( , --' FOHER CI IIlCl)M ,,~, ~)·7tr:j.!,:: "!i~'-"I' , /," .: ~ • '-\;~' d ., ',,,,";: :' ,,' '(C. ".' . ..,; ~~,!;>Jl. "', _'_ ->" ~';~Jt~ ~'l;' Ii,. ,J 'c" "\.:. '; "' .. '~ , / / varian@ ~~HISIT B City of Palo Alto Ut.ilities Department P. o~ Box 10250 Palo Alto, California 94303 November 19, 1991 Subject: Varian's New Test Set Metering at Existing "on Lineup Att2nticn: Mr. Sam Zuccaro Dear Sam, The following is an item by item description of Varian's response to your letter dated september 2], 1991. Item 1. New 12.47kV·potential transformers should be forwarded to CPA for testing. ACTION: PT's have been forwarded to Ken Schwab of your Metering Department and have been tested/calibrated~ Item ~. City reserves the right to retest any of the metering trans­ formers at any time. RESPONSE: We understand that varian will be given ample prior notification in order to coordinate shut down of equipment with the Building occupants. Item 2. Existing Westinghouse watthour demand calibration and installation of tags. at the end of the five year contract. meters require testir.g Tags will be removed RESPONSE: Meters will be removed at the completion of the 12kV upgrade for the switchgear and ~il1 be "forwarded to you for testing and calibration. Item 3. Keyed access shall be provided to each meter location. RESPONSE: switchgear pad is present.ly locked but does have a se~arate access for CPA entry. Meters are now accessible via switchgear doors ~hich are presently unlocked. We will work yith the City to assure con­ trolled access to the meters. EXliIBIr 3 Vilro.aoA5s.o..o(':JI'''';,1I1e 3100 !-bn",c" WJ)' P,O eo_ 10800 Palo I\Jlo,C3h1orn;:J g~:;O"-{l68J li S A .<lISP''':]:) 4000 T!l'h,'" :J.1-b47G • Item 4. varian@ Monthly readings for the lva meters shall be read b)' Varian and forwarded to the CitY4 Reading and resetting of meters shall be coordinated 'With t.he city. RESPONSE: Varian will read and reset the meters as requested. Item 5. city may install a Load Profile Recorder vith remote phone data link. RESPONSE: Varian 'Will cooperate in any effort required .by the city to install the Load Profile. Please call me if you have any additional questions. Our plan is to begin work on the s'Witchgear Thursday December 26 and to complete upgrade of the switchgear no later than Sunday December 29, 1991. We look forward to working with you in determining all of the interfacing required by the City of Palo Alto an"a. ourselves to successfully complete this project. cc: M. Johnson wa M. McCoy va s. Gold wa RespecTfully Yours ~ ... ~ ... tf?~~ Mariano C. Castillo P.E. V".l,lr'lA:l:k.ICi..'I,:s.I,1C 3:00 Han:;en W.:Jy P 0 OO~ 1000'J P .. I<,l AJIO.Calor"'I);,' 94JO.1 O{JtlJ U S 1\ '11514:)3-'000 T d •. :~ lo1-D<\ 7(; December ~2, ~991 THE HO~ORABLE CITY COt~CIL Palo Alto, CalifoLnia AgreeIr'.gnt with Varian Associates Members of the Council: Report in Brief 6 This report recommends that Council approve and authorize the Mayor to execute the attached agreement by and between the City o~ Palo Alto and Varian Associates, Inc., allowing the City to design and install n~w elect~ic substation e~~ipment for serving power to a new Varian Associates electric load. Discussion In A~qust 1988, varian Associates met with Utilities staff to request an increase in electric power capacity to serve a new 6 Meqawatt (6,000,000 wattJ test facility. At that time, Varian wanted the new facility to be ready in late fall of 1990. staff estimated the project cost at $750,000 to design and install the necessary electric power distribution equipment to serve Varian's new facilitY4 Staff determined that the energy consumption of the new test facility was somewhat speculative; and therefore, the project cost may not be economically justified, as discussed under Uti~ity Rule and Regulation 17~ Varian agreed to reimburse the City for its expenses, provided Varian could reco'\~er some of the cost depending on enerqy consumption and subsequent associated revenue to oe received by the City. On August 3, 1989, Council approved a preliminary Reimbursement Agreement vith varian Associates (ref. CMR:4CO:9) that allowed staff to begin enqineering and purchasing lonq leadtime electrical equipment. To date, staff has purchased and received about $400,000 worth of equipment needed for this project. Varian bas reimbursed the City in accoraance with the Preliminary Agreement. Since the preliminary Agreement was approved, staff bas been negotiating the terms of the attached Agreement with Varian. Due to the long negotiation process with varian (two years), staff revised the estimated cost of the project to $820,OOQ~OO to CKR,:549:91 . .. o AGREEME}II"T This Ag=eement is made at Palo Alto, california, on the day of 1991 by and bebleel"'. the CITY OF PALO ALro:-:i municipal corporation~ hereinaft.er called nCity!1~ and VARIAN ASSOCIATES. INC .• a Delaware corpor-ation, with offices at 3100 Hansen way, Palo Alto r California, hereinafter called ItVarian"; ~ I T N E SSE T R, WHEREAS, Varian desires an increase in t~e electrical power provided to its business located at 3100 Hansen 'Nay, Palo Alto, california~ and WHEREAS, City's Electrical Engineering Manager has determined that vari3.n r~quires additicnal transforZler capacity and that Varia.n's requi::-ement is of sUfficiel"'.t :::=agnitllde that it would impair the abil i ty of the present. sy:$t.e~ tc serve the nor:nal load and that the requirements a!'".a of '.,ince!"tain permanency; and ~~EREAS, City has no assurance at the present time requisite capital expenditure foe said transformer increase vill provide an adequate return to City investment: and that the capacity on its WHEREAS, varian is willing to advance to City the. Cityrs actual cost incurred in providing additional transformer capacity provided that Varian may recover o','er a period of years the difference in cost advanced by i":. :;:; Ci::y and. the co,;t of the standard installa.tion pursuant to Rule and Regulation 20 of city's Utility Rules and Requlations, eifec":.ive July II, 1988, a copy of .hic:h is attached hereto and incoryorated herein by "this reference (gRu~e 20 a ); and WHEREAS, the parties inLend that th~ cost of the improvements to be made under this Agreer::ent -... ill not exceed Eight Hundred T'",oienty Thousand Dollars ($82{) I 000) 'i.rithout prier nati Eicat ion to Varian; NOW, THEREFOPJg, in consideration of the mutual understandings and covenants provided in this Agr~e~ent, the parties hereto agree as follows: a. G~neral. In order to serve the Varian Te3t Set Load to be located in Varian Bui,ldinq 4 (referred to hereinafter as the "Test Set"), City will add the new substation capacity at the Hansen Way S~bstation as described below (referred to hereinafter as the -Project-) ~ City presently does not have e:nough physical space at the Hansen Way Substation to add this new capacity without modifying the Substation layout~ To create space, City must first remove transformers i{W-3 and HW-~ and associated equipment now 1 .-,,- -~$<-~ d. varian rnstall.~...t....i,.91l_PeSOons_~.p.lJ_i tips. Varian -";ill pr-ovide design and construct iO:1 senriceE for a:1y work needed on Variants proper~YI as deemed necessary by City an~ Varian fer the Project. varian ..... ill allolJ City to make the necessary power interruptions to accompl is.h th~ Project but such inter=-uptions will be coordinated as reasonably possible with Varian to avoid disruption of 'l'~arianr:5 manufact:uring capa.bilit.ies~ -larian viII make all changes on Varian's po' .... er dist!"ibl!tion system to allow the Building 4 service to accept 12.47 kilovolts. All e:dstinq electric load originally serll'ed from the 3'..lil·jing 4 service -will remain on this service. All CO:1strucc:.ion by Var ian ..,-ill be subject to approval by the City Building Department~ Varian will provide cutouts in the i!".strument panel for Varian I s feeder breaker-serving the new Test Set to allow City ~o i~stall its me~e~ing equipment~ Varian will furnish new rela~~ coordination curves and settings to the City Utilities Department for approval. a. Subject to the provlslons of S~c~ion 2.b. below, Varian shall pay to City the total actual ::j'J5~alled c~s't:. fvr all 'Work accomplished by City under the Prcject, as sumffi~rized in Sections l.a~, b. and c. above. b~ The estimated cost:.s -:~r -=.he -.... ork to be performed by City under Section 2.a. a~ove is: Material--Four Hundred Ninety Thousand Dollars ($490,000. GO); La.bcr--Three Hundred Thirty Thousand Dollars ($330,000.00); T~tal--Eight Hundred Twenty . Thousand Dollars ($8.20,000.00). NC::'·.,Iithstanclinq the foregoing, prior written notification .. ill be provided by City to Varian's Director of Facilities beforE: exceeding thi$ total arnount~ c. City 'IoIil! bill \tar-ian at pe~iodic interva.ls, no less than on a quarterly basis, during the progress af -:he · .... ork for costs actually incurred and paid by Ci~y under the Proje~~~ Evidence of such payments by City shall be fUrnished .. ith invoices submitted. payments to City · ... ill be made oy Va~ian on a net: basis -within thirty (30) days following Var-ian I s receipt of invoices. d~ City agrees to protact l indemnify~ d-Qfend and hold ha~less Varian from and against that portion of an~l and all claims, liabilities (including reasonable at~orneys' fees and legal costs) or causes of action, of whatsoever nature including I 'Without limitation l any mechanics lien claims asserted against Varian or its employees caused by or resulting frem Cit-y's actions or inactions in its performance of this Agre~~ent. varian agrees to protect~ inde!r'.nify, defend and hold harmless City from and against that portion of any and all claims, liabilities (including reasonable attorneys' tees and legal costs) or causes of acticn l of whatso~ver nature i~cluding, without limitation, any mechanics lien claims asserted against city or its employees caused by or resultinq from varian's acticns or inactions in its performance of this Aqreement~ In the event of any conflict between the previsions of this paragraph and Rule 20 1 attached hereto I the prOVisions of Rule 20 shall govern. J 91 I1 0.5 bck CXT.!ID51 o city shall insure that no discrirr.ination shall be maae in the employment or persons to perton ·,.,Ot:"k put'suant to t:his Aqree:uent because of race, color, naticnal or-igin, ancestry, age, veteran status or religior. of such persons. In connection 1o,'ith the Projact city shall require its contractor and any subcontractor to meet all requirements of the Palo Al to Munic ipal code pertaining to nondiscrimination in employment and to complete and submit TlCompliance Report-Nondiscriminat.ion Provisions of City of Palo Alto Contracts n en a for.rn furnished by City. s. TERMTNATrc.m. Varian shall have the right to ter~inate i~s obligations to make payments to City under thls Agreement on thirty PO} days written notice to City; pravide-1, hcwever, that Varian shall remain fully obligated tc pay City fer all reasonable expenses incurred, com'l" . .ltted or encumbered by Cit"f to t.::-J.e date of such notice and for all reasonable eXFJenses inctlrred, committed or encumbered l"i City as a result cf such t€.r:ninat.icn. Such expenses shall incll"je, bl.l': not. be limited to, t'"est.ot'"ation of t.he Hansen Way Substation site and any related a.c:acen~ City p~oper~y to its fully operational condition as determined by Ci~y" 9. rNTEGP~TIO~; AME~DMENT" This docu~ent represents the e~ti=e and int.egrated ~~reement between city and Varian and su~ersedes all prior negotiations, representations and agreements, e1 :.he.:-...... r.l tten or oral. This document may be amended only by wri~~en ins~rurne~t, signed by both City and Varian~ 10. GOVERNING LAW. This Agreement shall be gover:1Ed by t:."::e 1 a" .. 's cf the St:ate of California. IN WITNESS THEREOF, the parties hereto have caused this Agreement to be exeCLlted the day and year first above written. ATTEST, CITY OF PALO ALTO: City Clerk By : ~M"a"')"" o"r'-- Assistant City Attorney VARIAN p,pSOCIA;lS-;x. INC. ~~ ! ts: II'1l' VkE PresilBlt and Gerenl i'\lna!Er APPROVED AS TO FORM: Taxpayer ID No; 94-2JS9J45 5 • j t. SPECIAL POWER SERVICE REQUIRElIENTS: 1. General. SPECIAL ELECTRIC UTILITY REGULATIONS RULE AND REGULATION 20 Where a customer desires vOltage control lJIIithin unusually close limits. the City may requfre the C:Jstomer to provide at his own expense SUCft spedal IJr additional equ;pme!lt as is required. 2. Nonstandard or [xcesshe C~.st~mer Requirernt!!'1ts: Normal1y~ the City ..,ill insta11 'jine and/or transformer capa..::ity to provide a reasonable marSiI1 for future grewt!'!. Howelr'er. if tne customer r-equires a rIOnstandar-d voltaae. or ex;:o::ss line and/or trans­ former capacity be-::ause o'f compara:lvely large loads of shOrt duration~ or unusually close voltage roegul-ltion. or .,is:h temperature liquid filled transformers, or sc~arate transformers t3 serve Jow-r~venue Joad~ slJch as X-raj mact'lines. we"id~f"'s. etc., the~ tne customer-shail pay t.'le City an amount equal to tne difference in COSi: bet'Jrle~n tne insta11ation reQuir-e{j by t.1e cwstomer a:'J!j t.'h.: standar:J installation. If a customer's ~oad is cf sufficient magnituoe t!'lat it impairs the ability of the sySi:!!lI to s~rvt normal load in the opinion of the o,ief £iectr'icil Ellgine2r, tne cus~omer may be reQliire-d to impose h'fs peak: loads aurin9 "afT-peak." hours of the City's e1:2ctri~.aT syst!:'"" or ta.it.e servi ce from th~ Ci ty '5 60-ki1 ova it sy stem, or both. B. PROTECTIVE DEVICES: L It s,'1.a11 !le the applicant's r~spC)nsibi1ity 'to furnisn. instail, inspect and k:e-ep in good and safe condition at his o~n risk and. e!(pense~ all appropriat~ pret.ect!v! d!vices QT any kind or cnarac-:er .... M'fcil may be reqt.iired to properly protect the applicant's facility. He IJtility sMall net be responsitlie for any 'loss or damage occas:oned or caused by the negl1gence. or II'rongful act of the appT icant or of any of I'd s agent~~ empioye!s or ljc2~se~s in omittin;. inst!11jng. maintaining. using, operating or interferiI19 witl'l any such protectiye devices. 2. It shall be the appnca1"lt's responsibility to lns .... al1 apprc'Yed protec­ tive devices as may be necessary to coordinate proper1y "'ith the Utility's protective devices to avoid e;c;posing ot.her cust.omers to unnecessdry ser~ice interruptions. a. Applicants who reot;lue-s .. primary voltage service sl'1al1 install circuit breakers witn ~ver--:Ul"rent and ground fault reiays. CITY. OF PALO ALTO UTILITIES Issued by the City Cr .nc1 1 Supersedes Sheet No. J9a date-oj 7-j-83 Effect.ive 7·11-88 Sh •• t No.20-1 t'""'\ ~ SPECIAl ELECTRIC UTILITY RE6UUTlQHS RULE AND REGULATION 20 (Continued) c.'" JNTERfERE~CE WITH S£RYICE: ,. ,. Genera 1 T'1e Util ity reser'l'es the right to refuse to serve r.ew loads or to n.ntinue tD supply existing loads of a s;z.~ or character-that m!)I be t ~"..rimental to !ne Utility's operation or to the service of its customers. Any customer "'00 operates or plans to operate any equipment such as, C.ut not 1 imited to pumps, WE'lders. saw mit 1 apparatus, furnaces. compressors or other eQu;pmer:t ... here the use af e1ectncity is intermittent. causes intolerable · .. oitage flJJctuations, or otltendSt: causes intolentlie servi.:'! interference, must r'"C?:!Sonably jimit suei) inter ferenee or re s!.ri c t the use 0 f sllch eQui ~mer:t upon reque 5t. ~y the Utility. The customer is re~uired. either to provide and pay for wh~t:!ver correct'fve ~asures aie necessary to 1 imit the 1nt~;fer;nce t'O a le ... ~l established by tn! Utility as' reasonable. or avolo tne us.: of such eq.uipment~ 'Wi'letr.er or not the equ1j:iment has prE-Vl0lJsTy cause'1 interference!. 2. ;-.armful Wave Form Customers shal1 .,ot operat.e equi.;:ment :nat superimposes a current of any f~eQuency or wave form upon the Util 1ty' s system. or draws curre!"lt from the Utility's system of a harmfui 'Wa've form. which C3IJSeS interference-with the Utility opentions. or the service to o:;her customers, 01'" inductive Tn:erferencf' to communication raciiit:";es. J. Customer's Resporlsibil ity Any customer causi ng servic! interfeorenc!: to othe!"s must dil i gent1y purs~e and taxe timely corrective action after being given notice and a reasonab1e time to do so by tne Utility. If the cus-::omer does not ta~e timely correct1ve action, or continues to operate tl'1e equ"ipmerlt ca.us1ng the interference without restriction or limit. the Utility may. without TiabiTity, af:er ~; .... in9 5 days written notice to customer, either insta11 and activa.te c.ontrol devices on its facilitif!s that will eln Of PAlO ALTll lITILlTlES [s.s~ed by tile City Council Supersedes Sheet No+ 41 dated ID-l-S4 Effe<:ti ~e 7-1-83 Sheet No. 20-3 .~. ) ~ Sl'ffiAL ELECTRIC UTIUT'r REGULATIONS RULE AND REGULATION 20 (Continued) TABLE 1 NORMAl i'lAXIMIII AllOWABLE IWTOR STARTING ClJAAEIITS ALTERIIA T1NG-tURREIIT MOTORS Single-Phase Voltage Rated HP Gutput Motor Rating (Service Voltace) 208v 1240.) Thre-e-Phase VoTtage Motor Rating {Service Voltaae Z08v ~ 480, 2 3 5 46 amps 40 amps 69 60 115 100 69 amps 102 50 amps 30 amps 88 44 7 1/2 10 127 110 ll3 163 115 58 141 71 15 227 197 99 20 ··188 250 125 25 351 304 15Z 30 415 360 180 40 4J8 380 190 50 462 400 200 60 140 75 lOO 100 400 Over 100 -SEe Note 3. iable 1 Notes: L See Sect-ion C.4 f\1r detalls 011 tne use of this table. 2. Motor starting curr!nt is jefined as the st~ady state curre~t taken from the supply lir.e with tne motor r~tor or rotors locKed, with a11 other power consuming components. inel uding a current-reducing starter. j fused. connec::ted in the starting position, and ...-ith rated vol tage and frequency .ppl ied. 3. The applicant shall consult the Utility fOr" design criteria lrlTormation for selecting suitable starting equipment for three-Dnase !-c motors not shown on Table 1, and for motors that opera.te at higher vol tage ratings. CITT OF PALO ALTO UTILITIES Issued by the City Council Supersedes Sheet No. 43 dated 10-1-54 Hfect7ve 7-1-83 Sheet No. 10-5 \ ~CIAl ELECTRIC UTiliTY RE6UUTlONS RULE A~n R£GilLUiON 20 (Contin,.o) 2. Special facilities are; (a) fadlfties r~quested by an !pplic<!nt w!1icn are in addition to or in substitut'ion for standard fa<:il1ties whicb the Utiiity 'WOuld noneall), pro~iae for delivery of sen ice at one po;nt~ thrOLigh one l*eter. at one voltage class under its rat! sched~Tes. or {b) a pro:; rata pOr"'tlon cf the f.!ci1ities requested by an appl ieant. fer the sele use of sue" applicant, .,.nich would not normally be ailocated for such soTe use. Unless otheno'ise pro .... ided by ttle UtlJity's rate sc.';edules. special facilities wilT be installed. owned and maintained ~y the Utility as an accorrrnodatior. to the appltcant only if acce~t1!cle for operation by the l1tllity and tile reTiabflity of service to the Utility's other customers is not impaire-j. cln OF PAlO AI. TO UTILITIES Jssued by the City Council Effective 7-1-83 Driginal She~t Nc. 20-7 .:/ .~ .... C!L COMMUNICATIONS (Continued) John Frances caruso, 101 El Ca.rmela Avenue, spoke regarding a request to Council to review the negligence of the Palo Alto Police Department. He was falsely arrested. Edmund Po'Wer~ 2254 Dartmouth, spoke regarding civic responsi~ility. Bazry Boulton, 535 Everett A'Ien'J.e, 4203, spOKe regarding support fo~ a public meeting on the T2010 Transportation Plar.. Bob Moss, 4010 Orme Street, spoke regarding ~ th~nks to outgoing council Members. APPROVAL OF MI~~TES septamber 9, 1991: Faz~ino/Kecovn, as submitted, MOTION PASSED 9-0. CONSENT CALENDAR Ilt1l.S will be VQfed OIl in one moliOJI UJr/~l lCllOo,Jed from '/rr calcrdar ,;.-'" a C)lIJlcir .~(e'mDt'r. Mccown/Cobb -Approve COnsent Calendar J -9 and 11 -1J, with Item 10 removed by a Council Member to become lSA. J. contract with Modern Office Machines tor Rental and Mainte­ nance of Photocopiers .t. RESOLUTION' 105J entitled IlRLSOLUTION OF THE COUNCIL OF THE CITY OF PALO ALTO APPROVING AND AUTHORIZI/iG THE MAYOR TO EXECUTE THE MEMORANDUM OF UNDERSTANDIIIG REGARDING URBAN WATER CONSERVATIoN IN CALIFORNIA" Memorandum of Understanding Regarding Urban Conservation in California 5. RESOLUTION" 7054 entitled "RESOLUTION OF THE COUNCIL OF THE CITY OF PALO ALTO DETERMINING PROPERTIES ELECTING TO ?;'Y COST OVER A PERIOD OF YEARS, DETERMINING AND CLASSIFYI/iG GlfPArD ASSESSMENTS, AND FUNDING LOANS TO PROPERTY OWNERS FROM THE ELECTRIC SYSTEM IMPROVEMENT" RESERVE: UNDERGROU~D UTILITIES CONVERSION UNDERGROUND UTILI~Y ASSESSMENT DISTRICT JJ 6. Agreement with Varian ~sociate5 re New Electric SUbstation Equipment 7. Policy and Services committee recom.'llends to city Council approval of consultant Agreement with uribe , Associates for Assistance with Vehicle Service Facilities Pollution Preven­ tion Program Professional Engineering Consultant Services Agreement by and between the city of Palo Alto and Uribe & Associates 2 12/16/91 o CALENDAR {ContinoJ:ed~ 8 ~ RESgJ,.;JTICN 7055 entitled IrRESOLUTION Of" THE CCUNCIL OF THE CITY OF PALO ALTO APPROVING THE C1TY IS PARTICIPATIOU IN THE SANTA cLAR.A COUNTY MORTGAGE CREDIT CERTIFICAT!: PROGRAM" cooperative J~.greement 8et· .... epn county of Santa Clara and City of Palo Alto cspcsit Certificate Fo~ 9. RESQf,JJTION 7056 entitled "FtESOLUTION OF THE COUNCIL OF THE C!TY OF PALO ALTO EXPRESSnlG /l.PPR£CL~TION TO EUGENE ANTONE. PROIET'l'1 UPON HIS RETIREMENT>! ~O. ORDIN~ ..... ~CE Of THE COUNCIL uF T:iE CIT! OF P.Il,.LO ALTO )._~ENDING 'tHE. Bt]DG£:"T fOR F!SCAL YEAR 1991-92 TO ESTABLISH A NEW CAPITAL IMPROVEMENT PROJECT N04 1921'2 IIBRYAN'T STREET BIC'lCU BOULEVARD EXTENSION" IN THE' STREET IMP!iOVEMENT FUN~" Item removed to become laA. 11. ORDBiA.J. ..... C; ______ 4.ruU entitled rtORDINANCE OF THE COl:/'lCIL or THE CITY OF PALO ALTO AMENDING SECTION lR. {is. 040 OF THE PALO ALTO MUNICIP_~L CODE (THE ZDNI.'~G ~..A?) BY A.MEN'DI~lG THE EXISTING PUNNED COMMUNITY ZONING DESIGNATIC!'4 OF THE PROPERTY moWN AS 251 UNIVERSITY AVENUE TO DELETE: THE REQU:::REME:olT FOR GROUND F.LOOR RETAIL USE" {1st Reading 12/02/91, Passe.d 9-0) 12. ~ma/East Meadow/East Charleston Intersection Improvements - CIF 1907) RESOLUTION' 7057 entitled "RESOLUTION OF THE COUNCIL OF THE CI~,{ OF PALO ALTO APPROVING kND AUTHORIZING EXECL~ION OF AN AGREEMENT BETWEEN THE CITY OF PAW ALTO AND THE COUNTY OF Sl\l:TA CL.ARA. TRANSIt' DISTRICT FOR COST SHARING FOR THE AL'!A ~TREET BUS STOP DUCKOUT AT MEADOW DRIVE" AJreement bet-"'een the City of Palo Alta and County of Santa ,lara Transit District for Cost Sharing for the Airea street EJS Stop Duckout at Meadow Driv~ RESOLUTIO/l1 7058. entitled "RESOLUTION of THE COU}lCIL OF THE CITY OF PALO ALTO AP'PROVING AND AUTHORIZING EXECUTION OF PROGRAM SUPPLEMENT NOS. 00] AND 004 TO LOCAL AGENCY-STATE' AGREEMENT FOR FEDEEL~L AID PROJECTS NO~ 04-5100" Cal trans program Supplement No~ 00] ~altrans Program Supplement No. 004 13. Prop?sec study re Reflective Noise from Soundwalls .oT~O. PASSE~ 9-0~ 3 12/16/91 •