HomeMy WebLinkAbout0464.091j • ((D. . . ... '~ " ,.:{ """ -".1, "I October 17, 1991 THE HONORABLE CITY OOUNC1L Palo Alto, California ,- 7 Contract for wastewater Col1ecti~n Sy~~m Augmentation Project Phase I Members of the Council: Report in Brief This report requests that Council a.ard a contract in the amount of $273,372. to EMSCO of San Francisco for waste'Water collection system augmentation on Kinglsey Avenue~ from Webster street to Middlefield Road; the intersection of Channing AvenUe and Lincoln Avenue; the intersection of Channin~ Avenue and Ne~ell Road; st. Francis Drive, from Embarca~ero Road to Channing Avenue; and Fabian Way at East Meadow Drive. In addition, staff recommends that Council authorize the city Manager or his designee to execute one or more change orders to the contract with EMSCO of San Francisco for additional related but unforeseen work. The value of these change orders shall not exceed $27,337. Funds for this project have been carried forward from the FY 91/92 Capital Improvement Program budget for wastewater collection syst~m augmentation. Backgroyn d In 1989, Camp Dresser' McKee completed a master plan study of Palo Alto's entire sanitary sewer collection system. This study took into account the groundwater infiltration and rainfall-dependent infiltration/inflow studies conducted in 1982 by CH2M HilL The master plan study indicated certair! facilities are in need of capacity relief, to handle increased use and peak wastewater flow, and recommended improvements to correct these deficiencies. The proposed project is part of this augmentation work. Prgject nescription The proposed project ~ill install 1,637 linear feet of new ~astewater mains in various locations throughout the City, as shown on the attached map. CKR:464:91 / o Bid Eyaluation The project was sent out for competitive bid. Bids ~e~e received frOID six qualified bidders on September 24, 1991, as indicated on the at~ached bid summary. The bids rang~d from a low of $273,312 ~o a high of $417,198. The estimat~ of our engineer was $396,343.50 The lowest r~sponsible bidd~r was EMSCO of San Francisco~ Statf finds the low bidder to be qualified to perform the work. ~ommend3tion Staff recommends that Council: 1. Authorize the Mayor to executa a con~ract with EMSCO of San Francis-co, in tl1e e.mount of $213~ 172 for the Waste'Jater Collection system Augmentation project Phase I; and 2. Authorize the city Manager or his designee to negotiate and execute one or more change orders to the constructin contract with EMSCO of San Frarlcisco, the value of which change orders shall not exceed $27,3~7. Attachments: Project Map Bid Summary contract CXR:464: 91 • ______ ' ........ ·a _____ _ NOTICE INVITlNG SEAlED BIDS· PART II Page 23 CONTRACT nilS AGREEMENT is mada a'ld entered into, in duprlCate, !his day of ;;:::=:-~_~ 19_, by and between the City of Palo Alto, California, her.lnafter called 'CITY", and ___ ~, hereinafler caned 'Contracta(', whOse Taxpayer Identification Number is: WITNESSETH: Fer and in consideration of their mutual covenants, tr.e parties hereto agree as follows: 1. Contractor shan do an the work and furnish an the materials necessary to COI'l$truct and complete in a good, worl<rnanlike and substantial manner, and 10 the satisfacOOn of toe CITY, the fonowing: 2. Tnls Contract shan consist cf the followng documents on file with the City Clerk, a~ of which are incorporated herein and made a part hereof by reference thereto: s. This Contract b. Notice inviting Sealed Bids c. Accepted Bid d. Standard Specifications dated 1972, as amended, or as superseded by other documents Wlcorporated herein. e. Technical Specifications -Special Provisions f. Certifioate of Insu<ance g. Performance Bond h. labor and Materials Bond L Affirmative ActiOf'. Guidennes and Compn ar.ce Report j. Any arid an Supplemental agreements wh ich am end or exlend the work contemplated end whi ch may be required to complete the work in a substantial and acceptable manner. t Plans. 3. In consideration 01 such work, CITY shan pay Contractor the amount specified in his bid in the manner provided in said Standard Specifications dated 1972, as ame~ded. 4. Concurrently with the execution of this Contract, Contractor shan provide CITY with the Contractor's Labor and Materials and Faithful Performance Bonds and certificates of insu<ance, incIudng any workers' compensation insurance required by the laws of the State of CaI~omia or otherwise required in said specifications. 5. This Contract shan not be assigned by Contractor. City 01 P. Alto. C~T \ II't' • ~TICE INVITING SEA1Q BIDS· PART II o Page 24 CONTRACT (Co<1tinusd) 6. AI claims by ConIrac\of regarding extra work. charges, claiay or other olSputes arising cui of the ConIracI must be submitted 10 CiTY in writing within len (10) working days after !he dairn arose, dfJsc:ibirlg in cIetaI the nature and value of the disputed wor1< or claim. 7. ConIrac\of hereby agrees 10 indemnity, defend and hold harmless CiTY, its officers, agents, and employees from any and all demands, claims or flabffity 01 any nalUre, caused by or arising out of Conlractor's, its officers', agents', or employees' negfigent 0Icts, errors, or omissions, or wmfu! misconduct, or conduct for which the law imposes sbict fiabnity on ConlractOr in the periorm&nee or fSl1",e to periorm this contract. 8. This Conlract represents the entire agreement between L~e parties with respect to L'1e purchase and saie of the equipment, matenals. or suppnes or payment for services which may be the subject of this Conlract. All prior agreements, representations, statements, negotiatiOl",s and undertaJdngs whether oral or written are superseded hereby, 9. No payment, partial payment, acceptance. or partial acceptance by CITY shan operate as waiver on the part of CiTY of any of its rights under this C'.onlract. , O. ConlractOr agrees to permit Cf1Y to aOOr!, at any reasonable time during the term of thls Contract and for three (3) years thereafter, Conlractor's records pertaining to matters 'covered by this Contract. Conlractor funher agrees to maintain sucn records for at leas! three (3) years after the term of this Conlract. UII WITNESS WHEREOF, the parties have set Iheir hands an on the day and year first above written. ATTEST: Cf1Y OF PALO ALTO, CAUFORNIA City Clorl< By: Mayor APPROVED: CONTRACTOR City Manager By: Tille: O~ector of Utilities Taxpayer 1.0. # Director of Flflance APPROVED AS TO FORM: Risl< Manager C!Iy Attorney c.t., on P'" "'D: eONT~c.T P~'4 CITY OF PALO ALTO WASTEWATER COLLECTION SYSTEM AUGMENTATION PROJECT PHASE I COMPLETION TIME -90 CALENDAR DAYS PACIFIC UNOEAGRU CONST.INC. ---,--_.-0t __ .....,-,-. .",.-. ... ,.-_~--.. 'It , CASEY MCNAA4ARA. & SMAllM~'f 110 ESTIMATE UNIT tOTAL UNIT TOTAL I U' .... DESCRIPtION OUANTfTV ""ICE eo,T PR'CE COST PRI( . ,: ~ f , 1 • \ • , DSOflNST.II.lLATION OF SHORING , lS 15000.0 15000.0 5066.00 '_00 2 SCHEDULE 1, RELIEf SEWER .. 647 IF 150.0 91050.0 75.00 ... es25.00 , SctiEDUlE 1, CHVERSION H 7 IF 128.0 ."6,0 300,00 I 2100,00 • SCHEDULE " OlVERSION I I 55 LF ~09,0 5995,0 190.00 10450.00 5 SCHEDULE 1, DIVERSION J 570 LF 196.0 l~1720,O 1"°,00 79800.00 6 SCHEDuLE 3, RELIeF SEWER 2 ) 35E1 LF 250,0 89500.0 UlO.OO 64«0,00 • Vf.:fl,lOCATE. & R(CONN, lATEAAl 18 EA 1500.0 27000,0 505(1,00 10060.')0 • INSTALL NEW MANHOLES 15 EA 3006 4!':Q90,1j I 3200 49000.00 KENNEllY CONSTRUe f> & J UT1l1TY CO. 810 -- -------wsnMATEj -u1fT-. TOTAL UNIT r TOTAl ru ' ITEM DESCRIPTION IQUAP4TITY P~ICE COST PRICE: COST 1=:DSGfINSTAlLATlQN OF SHORING " I LS ~soOO.oo 500(1,00 5/)12 5fi'-ioo 2 SCHEDULE f, REllEr: SEWER 4 ! &41 LF 120.00 17640,00 13(1 64110.00 3 SCHEDULE 1, [)fIIE~SION H 1 LF 200,00 , .. 00.00 190 1330.00 4 SCHEDULE " DIVERSION I I 56 IF 200.00 1HIOO.ca 190 10450,00 5 SCHE~ULE " (ltVEASION J 570 IF 220.00 125400,00 230 131100,00 G ISCHEOULE 3, AF.t.lEF SEWeA 2 359 L,F 0'00.00 11600.00 251 898.S8.oo II" 8 ,',VEA.,LOC"TE, & ~ECONN. LAY~R"L 18 E"', 1200.00 I 3600.00 I 313[ 56.34,00 J 9 I'NST"LlN£:WMANHOLES ! 15 EA 8000 1'20000.00 I: 3366 50790,00 1 ~.~EAN & VIDEO NEW S"":I. SEWERS 1~37 IF I 1 1637 ~oti.~~_~2.50 ) 11411,277,00 1383,176.50 I " L_~.,,_., " ·r. '. '~;,i!",,",: .. \- "XX 65 .00 300 I ,55 1<' I 500 3500 54995,00 .. 63400.00 llJ5.00 67935.00 3500,00 200 1.00.00 110.00 16500.00 .. 5300,00 150.00 9405(1,00 '.2 1().3741j,OO 100,00 50478,00 '80 6«<10,00 190.00 9000,00 '000 18000.00 J1lO,oo 52500.00 2900 .3500.00 2OC<J 810SUMMARV CITY OF PALO ALTO WASTEWATER GOlLECTION SYSTfM AUGMENTAT10N PROJEC.T PHASE I CITY OF PAlO AnD ESTI~ATE EMSCO OF SAN FAA (low B~ ... > PACIfiC UNQEAGAOUND CONSTRUcnON CASEY CONSTRUCTION MCNAMARA & SMALLMAN P & J UTILITY CO, KENNElLY CON~UCTION 396,343,50 273.372.00 295,9304.00 31)7,331.50 309.1';12.00 383,176.50 "'7,217.00 f ! I I I .~'