June 21. 1990
THE HONORABLE CITY COUNCIL
Palo Alto, Calitornia
6
Contract for Installation and Removal of utility Poles Along Rear
LOt Easements
Members of the Council:
This report requests that council award a contract in the amount
of $166,073 to sturgeon Electric Company Inc. for installation
and removal of 54 utility poles along rear lot easements. In
addition, staff recommends that council authorize the City
xanager or his designee to execute one or more change orders to
the ~'tract with Sturgeon Electric Company Inc. tor additional
related but unforeseen work. The total value of the change
orders shall not exceed $20,000. Funds for this project are
a~ailable in the FY 1989-90 Capital Improvement program, Electric
FUnd ·OVerhead Extensions and Replacements-.
Background
There are approximately 8~~ ~tility poles in the City. Abcut
balf of them are along rear lot easements, with those remaining
located along the street riqht-of-way_ with an average life of
30 to '0 years~ the city needs to replace a minimum of 2C~ poles
annually. The City 's crews are unable to replace 20'0 poles
during a fiscal year, because of other capital Improvement
projects and regular and unscheduled maintenance work. Because
of this, the poles that have not: been replaced at the end of the
fiscal year by City crews are replaced by contractors. Since
replacing utility poles along rear lot easements is difficult and
time-~suming, these poles are replaced using contract services
in order to more effectively use City crews elsewhere.
en",,,.
L
•
~ ..... ;. ·::···········:.·.'·1 ."
'. -' . ','
,
I " .... '
. ,
~
S
" ,
t :
."
I .
o o
Project Description
This project involves setting 54 new poles adjacent to existing
poles, transferring all electrical attachments and services to
the new poles, topping off the old poles above th-e telephone and
cable TV lines and restorinq and cleaning up the project site.
All of this ~ork vill be done with the lines energized, causing
ainimal interruption to the customers. The ~aterialS for the
project vill be furnished by the city.
Tbe old poles are removed by Pacific Bell once their facilities
have been transferred to the new poles. Typically, the old poles
are removed within three to six months after completion of the
project.
Bid Evaluation
Staff requested proposals from seven contractors and received the
following five bids on Hay 29, 1990:
Contractor
Sturqeon Electric Company, Inc.
Contra Costa Electric, Inc~
Vanalt Company_ Inc~
W.F. Anderson Electric, Inc~
R.C. Hughes Corporation
AmoUnt
$166,073
171,540
191,902
1.93,670-
396,428
The engineer's estimate for the project was $leO~OOO. As a Joint
Pole owner. Pacific Bell will be required to pay $40,140# based
on the Joint Pole Agreement between the City and Pacific Bell.
l'Unding
Funds for this project are available in the FY 1989-90 Capital
Zmprovement Proqram, Electric Fund ·Overhead ExtensIons and
Replacements-.
cloun"a
~~,'~I ••• ".r:"'--"''''-''~~~-.. :s,;.._~ __ " "-.---"''';;'-.
-', -, -.
-
.-:
•
.-.... -
"::'" ,---_.
. .. ~
ReCQ"J'endatlons
staff recommends that council:
1) Execute a contract with sturgeon Electric Company Inc. in
the amount of $166,013 for the installation and removal of
54 utility poles; and
2) Authorize the city Manager or his designee to negotiate and
execute one or BOre change orders to the contract with
sturqeon Electric Company Inc. the value of which shall not
exceed $20,000.
Respectfully 5ubmitted~
X2.-, l:l, (D s-6:. ,j
LARRY W. STARR
Manager Electrical Engineering
am.37f ••
•
-, ~-
,
•
•
\
o o
. ;,~::",'
.\~/ .. t
a
~I~ r ~~~~~~~r+~r+~A~~~rT~,,~~_, ~
v-L
--.' .
,
o o
THIS AGREEMENT is made and entered into. in Quplicate. this ____ _
____ day of :-::~-::--;:-::::::-=' 19 ___ • by and bet,*"een the City of Palo
~to, california. hereinafter called ·CITY-, and
:;;-:=:-:-::-::-=-~"-::::-;:7.;-;-=-;:-;:-::-:=-,;;::~;here1nafter called IIIICon'tractor-. ,*"hose Taxpayer Identification Number is: ________________________________ ~
For and in consi~eration of their mutual covenants. the parties
hereto agree as tollows:
•
1. Contractor sball do all the work and furnish all the materials necessary
to construct and complete in a good. workmanlike and substantial manner,
and to the satisfacticn of the
city of Palo Alto. the following:
2. This contract shall consist of the follo~ing documents on file with the
City clerk, all of which are incorporated herein and made a part hereof
by reference thereto:
• a.
b.
c.
d.
e.
f.
9·
h.
1-
j.
This contract
Notice Inviting Sealed Proposals
Accep,ted Proposal
standard Specifications dated 1972. as amended. or as
superseded by c~her documents incorporated herein.
General Provisions
Technical SpecificatIons --special Provisions
certificate of Insurance
Performance ~~
Affirmative Action Guidelines and Compliance Report
Any and a11 supplemental agreements which amend or extend
the work contemplated and vhich may be required to complete
the work in a substantial and acceptable manner.
3. In consideration of such 'Work. CITY" shall pay Contractor the amount
specified in his bid in the manner provided in said standard
Specifications dated 1972. as amended.
4. Concurrently with the execution of this contract ... Contractor shall
provide CITY with the Cootractor's Labor and Material and Faithful
Perfor.mance Bonds and certificates of insurance. including any workers·
compensation insurance required by the laws of the state of California
or otherwise required in said specIfications.
5. This contract shall not be assigned by Contractor.
.-"-
\~-.
~:;-'tl.
'"
•
•
. --,
\
..
o o
CONTRACT {Co-ntinued)
6. All claims by contractor regarding extra work~ Charges, delay o~ other
disputes arising out of the Contract must be submitted to CITY in
writing within ten (lO) workir~ days after the claim arose, describing
in detail the nature and value of the disputed work or claim.
1.
8.
9.
•
contractor hereby agrees to indemnify, defe~ and hold harmless CITY~
its officers, agents, and e~ployees from any and all demands~ claims or
liability of any nature. ca~sed by or arising out of Contractor's~ its
officers', agents', or employees' negligent acts, errors, or omissicns,
or willful misconduct, or co-nduct for which the law imposes strict
liability on Contractor in the performance or failure to perform this
Agreement.
This Agreement represents the entire Agreement bet\ll'een the parties 1.rith
respect. t.o the purcbase and sale of the equipment.. materials, or
supplies or payment for senrices "ihich may be the subject of this
Contract. All prior egreements l representation~. statements, negotia
tions and undertakings whether oral or written are superseded hereby.
No paymentl partial payment I acceptance l or partial acceptance by City
shall operate as ~aiver on the part of City of any of its rights under
this contract.
10. Contractor agrees to permit CITY to audit, at any reasonable time during
the term of this Agreement and for three {3j )ears thereafter~
ContractorPs ~ecords pertaining to matters covered by this Agreement.
Contractor further agrees to maintain such records for at least three
(3) years after the term of this Agreement.
IN WITNESS WHEREOF I the Parties have set their bands all on the day and year
first above written.
Al'rEST, CITY OF PALO ALTO, CALIFORNIA
By: ______ _
City Clerk Mayor
APPROVED: CONTRACTOR
City Manager ~:~-----------------Title: ---
{Department Head] Taxpayer I.D.', ___________ __
APPFOVED AS '1'0 FORM:
Director of Finance
Risk Manager City Attorney
City or Palo "Lto: COlrfTRAC1' '-~h!l
.-;
.~, •. ;.
;;~---<.
'-<-
","". 2f'j