HomeMy WebLinkAboutStaff Report 2512-56383.Fiscal Year 2026 Mid-Year Electric Grid Modernization Update (DISCUSSION 7:35 PM –
8:35 PM) Staff: Terry Crowley Presentation
Item No. 3. Page 1 of 7
Utilities Advisory Commission
Staff Report
From: Alan Kurotori, Director Utilities
Lead Department: Utilities
Meeting Date: January 7, 2026
Report #: 2512-5638
TITLE
Fiscal Year 2026 Mid-Year Electric Grid Modernization Update
RECOMMENDATION
This staff report and presentation are for discussion purposes only; no commission action is
requested at this time.
EXECUTIVE SUMMARY
Palo Alto’s Electric Grid Modernization Project (Grid-Mod) was developed to improve the City’s
electric grid in anticipation of building and transportation electrification and to improve system
reliability. Palo Alto’s electric grid can be characterized as an efficient but aged system that has,
in large part, reached the end of its useful life. Some in-service equipment was originally
installed in the mid 1950’s and has served the City well over those 70+ years. However, due to
both the age of the electric system and increased electrical loads from electrification, the City’s
grid must be reconstructed and modernized to serve these higher loads while maintaining
system reliability.
To prepare for Palo Alto’s increased electric demands, it will be more cost effective to
modernize through the incorporation of newer technologies, implementation of current and
emerging utility best practices, and prepare for higher adoption rates of self-generation and
energy storage at the time of replacing legacy system components. However, the age and size
of Palo Alto’s system requires a large financial commitment two to three times historical
funding levels, over many years to fully support electrification within the residential sector. The
initial estimate for Grid-Mod was approximately $300 million over a five-year period. Current
staff estimates, with 12kV distribution upgrades (local transformers and secondary) paced to
match customer participation, reach $342 million (present value) between FY2026 and FY2034.
If all 12kV distribution upgrades are completed before FY2034 staff estimated costs for Grid-
Mod through FY2034 are $443million (present value).
Item No. 3. Page 2 of 7
PROJECT DESCRIPTION
With the intent to increase system capacity to meet forecasted electrification loads and
improve overall system reliability, Grid-Mod will touch the City’s sub-transmission, electrical
substations, and distribution systems. Each of these system components make up the City’s
electrical “Grid” and each are necessary to distribute power from the City’s interconnection
with PG&E’s transmission system to City customers. To achieve the project goal of supplying
building and transportation electrification loads from a clean, reliable, and affordable energy
source, each of these system components require reconstruction to increase system capacity
and reliability. Specific near-term areas of focus and rough cost estimates (excluding inflation)
include:
Reconductor roughly 3 miles of overhead sub-transmission; $4.6 million
Conversion of legacy 4kV distribution systems to 12kV, roughly 2,900 customers; $32.4
million
Reconstruction of four Substations, at East Meadow, Hopkins, Adobe Creek and
Colorado; $96.0 million
Reconstruction of 115kV and 60kV components of Colorado Substation; $40.7 million
Upgrading of existing 12kV distribution systems; $243.6 million
Strengthening 12kV feeder ties to improve reliability and capacity; $25.2 million
It’s important to note that this work is in addition to ongoing capital improvements such as
replacement of aging wood poles, replacement of damaged, aged or failed equipment, and
upgrades necessary for new or redeveloped parcels. The routine and ongoing capital
replacement work will require continued funding to maintain system reliability.
In 2020, the City set a goal to reduce GHG emissions 80 percent below 1990 levels by 2030
(80x30 goal). A 2020 analysis1 indicated that to meet the 80x30 goal, the City would need,
among other things, to electrify all single-family homes by replacing natural gas equipment with
efficient electric appliances and providing for electric vehicle charging. The 2020 analysis
estimated peak demands from single-family dwellings at 8.5kW without consideration of home
EV charging. When including a single, level-2 EV charger, customer peak demands could rise to
19.5kW. Compared to historical average peak demands of 1 to 2kW, residential electrification
represents a significant new demand on CPAU’s distribution system. Due to the higher
expected demands, Palo Alto’s electric system requires extensive upgrades to increase capacity
while replacing aging equipment to improve system reliability.
To support electrification of Palo Alto’s residential sector and rebuild the electric distribution
system, the City Council adopted the F2025–2029 Capital Budget including an electric capital
improvement budget of roughly $300 million for Grid-Mod projects. In FY2025 CPAU began
1 City of Palo Alto (2020), Preliminary Analysis of the Utility Costs & Staffing Impact to Electrify All Single-Family
Residences in Palo Alto
Item No. 3. Page 3 of 7
work within the initial Grid-Mod pilot area. Completed in mid-2025, this pilot area upgraded the
distribution system for roughly 900 homes at cost of roughly $10 million. At the same time,
CPAU engineering staff began the planning process to replace and upgrade Colorado
substation’s 60kV breakers, 115kV/60kV bank, eliminate legacy 4kV distribution systems, and
other work related to aged facilities.
ANALYSIS
Item No. 3. Page 4 of 7
flexibility from engineering and construction but is customer focused and provides the
opportunity to delay costly system upgrades until electric customers are ready to replace gas
appliances or install EV chargers. Additionally, the “when and where” approach allows
engineering staff to improve reliability by advancing the replacement of overload transformers
under the Grid-Mod Project.
Item No. 3. Page 5 of 7
Upgrading Sub-Transmission Systems to Improve Reliability
Table:1 – General timelines for key Grid-Mod Projects in support of electrification alongside estimated
project costs adjusted for inflation.
Item No. 3. Page 6 of 7
To fully implement a “When and Where” approach to the 12kV distribution system, staff is
recommending planning for a longer reconstruction timeline. This approach allows CPAU
electric engineering staff to focus on accelerating critical system rebuilds, such as the 4kV
system, sub-transmission, and the Colorado substation which have a greater impact on overall
system reliability. Additionally, employing the “When and Where” approach to the 12kV
distribution rebuild could allow increased revenues from electrification to fund upgrades,
softening future rate increases.
Table:2 - General timelines for key Grid-Mod Projects with 12kV upgrades spread out over a longer
period but tied directly to residential customers speed to install efficient electric appliances. Estimated
project costs adjusted for inflation.
FISCAL/RESOURCE IMPACT
Project Description FY2026 FY2027 FY2028 FY2029 FY2030 FY2031 FY2032 FY2033 FY2034
Sub-Transmission Reconductor
4kV Substation Conversions
Colorado Substation Upgrades
Adobe Creek Substation Upgrades
Colorado 12kV Substation Upgrades
4kV Distribution Conversions
Grid-Mod 12kV Distribution Upgrades
Grid-Mod Estimate Costs w/ inflation
($ Millions)$15.65 $34.75 $62.56 $27.39 $15.77 $59.89 $54.04 $58.80 $62.11
Item No. 3. Page 7 of 7
planning horizon, estimated costs through FY2034 are just under $425 million. Through early
planning and design phases, CPAU engineering staff will continue to refine and update project
scopes and related cost estimates. Staff will endeavor to reduce project timelines and costs,
while maintaining the overarching project goals.
STAKEHOLDER ENGAGEMENT
ENVIRONMENTAL REVIEW
ALTERNATIVE ACTIONS
AUTHOR/TITLE:
January 7, 2026 PaloAlto.gov
Grid-Modernization Update
Fiscal Year 2026 Mid-Year
Presenters:
Terry Crowley
TITLE 40 FONT BOLD
Subtitle 32 font
Grid Modernization Background
•The Grid Modernization (Grid Mod) project replaces existing electric utility facilities
to improve system reliability while preparing to meet the demands of electrification.
•Historically residential dwellings average demands between 1 to 2 kilowatts (kW),
under electrification these peak demands could increase to range between 8.5 to
19.5kW
•In FY2025 Grid Mod completed a pilot area increased capacity for roughly 900
homes.
•Cost to complete the pilot was $10 million or roughly $11,000 per dwelling.
•Future work includes reconstructing legacy 4-kilovolt systems, upgrading sub-
transmission capacity, strengthen feeder ties between substations, and modernizing
the Colorado Substation
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
The projects below are focused Grid-Modernization efforts with present-dollar rough
cost estimates:
•Reconductor roughly 3 miles of overhead 60kV sub-transmission; $4.6 million
•Convert 4kV distribution systems to 12kV, roughly 2,900 customers; $32.4 million
•Reconstruction of four Substations: East Meadow, Hopkins, Adobe Creek and Colorado;
$96.0 million
•Reconstruction of 115kV and 60kV components of Colorado Substation; $40.7 million
•Upgrade existing 12kV distribution systems; $243.6 million
•Strengthening 12kV feeder ties to improve reliability and capacity; $25.2 million
Projects and project budgets are subject to the FY2027 budget adoption
Ongoing capital improvement work (pole replacements, replacement of failed
equipment, etc.) will continue to need additional funding.
Key Grid Modernization Projects
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
The 60kV sub-transmission system provides a networked system
across the city to increase system reliability.
•Planning to reconductor roughly 3 miles of overhead 60 kV
sub-transmission; $4.6 million
•Work will mitigate conductor overloads under certain
system outages
•Not originally identified within the Grid-Mod Project
•Expecting to complete work by end of FY2028
Sub-Transmission System
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
The City operates an aging 4kV system serving roughly 2,900
customers.
•Convert 4kV distribution systems to 12kV: $32.4 million
•Current system is an island, without redundancy from
adjacent substations or circuits
•System includes two 4kV substations constructed in the
1950s and 1960s
•Conversion/reconstruction will allow ability to serve
future electrification energy needs
•Distribution work is planned to be complete by end of
FY2028, substations by FY2034
Convert 4kV Systems
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
Reconstruct of four 60/12kV substations to increase capacity
and improve reliability.
•Reconstruction of four Substations, at East Meadow,
Hopkins, Adobe Creek and Colorado: $96.0 million
•Both Hopkins and East Meadow are 4kV substations
operating on 60 to 70-year-old equipment. Once
complete these stations provide redundancy and added
reliability to Adobe Creek and Colorado Substations
•Adobe Creek and Colorado Substation were constructed
in the 1970s and show signs of age and limited capacity
•Due to long material delivery times, work is planned to
be complete between FY2031 and FY2034
Substation Reconstruction
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
Reconstruct and replace major equipment in Colorado Substation.
•Reconstruction of 115kV and 60kV components of Colorado
Substation: $40.7 million
•Combined projects will upgrade substation property, replace
a 115/60kV bank, and reconstruct the 60kV bus
•Equipment targeted for replacement was originally installed
in the 1970s
•Implementation of current utility designs is expected to
improve reliability twofold
•Due to long material delivery times, work is planned to be
complete between FY2028 and FY2031.
Colorado 115 and 60kV
Improvements
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
Reconstruct 12kV Distribution System for electrification and
improved system reliability.
•Upgrade existing 12kV distribution systems: $243.6
million and strengthening 12kV feeder ties: $25.2 million
•Strengthen circuit ties between substations increasing
reliability and allowing clearances for maintenance and
reconstruction
•Upgrading 12kV distribution components (transformers,
wires) for future electrification loads
•Primary focus of work is to strengthen feeder ties first,
then replace transformers as customers electrify
•Work is expected to be ongoing and last beyond FY2034
12kV Distribution
Improvements
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
•Focusing on meeting electrification demands “when and
where” it appears. Will require flexibility and responsiveness
from engineering and operations
•Use AMI data to identify overload transformers and
implement Grid-Mod upgrades while addressing the overload
situations
•Reduce residential EV charging demands through plug-sharing
devices. This limits overall build and customer costs
•Customers with energy demands larger than the expected
system average will fund their system upgrades that exceed
the standard grid-mod build
12kV Distribution
Improvements (cont.)
PaloAlto.gov
TITLE 40 FONT BOLD
Subtitle 32 font
Pacing reconstruction of the 12kV system to match customer adoption defers $117
million in debt financing within the next five years.
Forecasted Costs & Timeline
PaloAlto.gov
Sub-Transmission Reconductor
4kV Substation Conversions
Colorado Substation Upgrades
Adobe Creek Substation Upgrades
Colorado 12kV Substation Upgrades
4kV Distribution Conversions
Grid-Mod 12kV Distribution Upgrades
$15.65 $34.75 $62.56 $27.39 $15.77 $59.89 $54.04 $58.80 $62.11
Considerations
11
•Implement of staff’s recommended strategic approach to the 12kV distribution system.
•Whether customers with larger demands should pay for upgrades beyond an assumed
19.5kW peak (staff’s recommendation).
•Other Commission concerns.