HomeMy WebLinkAboutStaff Report 2507-4989CITY OF PALO ALTO
CITY COUNCIL
Monday, September 15, 2025
Council Chambers & Hybrid
5:30 PM
Agenda Item
B.Accessory Dwelling Unit (ADU) – 2025 Quarter 2 (April– June 2025) Report
City Council
Staff Report
From: City Manager
Report Type: INFORMATION REPORTS
Lead Department: Planning and Development Services
Meeting Date: September 15, 2025
Report #:2507-4989
TITLE
Accessory Dwelling Unit (ADU) – 2025 Quarter 2 (April– June 2025) Report
RECOMMENDATION
This is an informational report, and no action is required.
ANALYSIS
This report transmits information related to application activity for accessory dwelling units
(ADU), including junior accessory dwelling units (JADU), for the second quarter of calendar year
2025. Since 2015, the City has received 887 ADU/JADU building permit applications and issued
690 building permits. Since the beginning of the Housing Element cycle in 2023, 243 ADUs and
73 JADUs have been permitted which is on pace to exceed the expected ADU production from
this Housing Element; for an average of 126 units per year.
In the first half of 2025, the City received 87 new applications, issued 63 ADU permits, and
provided an approved Final Inspection on 80 ADU/JADU permits. The ADU sizes of open
applications in this period range from 176 to 1,000 square feet, with an average size of 570
square feet. Approximately 38% of applications are located north of Oregon Expressway, and
62% are located south of Oregon Expressway. Since 2017, the majority of ADU/JADU permits
relative to the Oregon Expressway has shifted between north and south from year to year.
Further details can be found on Table 1 of the following page.
Table 1: Summary of ADU Permits from 2015-2025
Category 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
2025
(Q1-Q2)
New ADU Applications Filed1 10 9 28 55 75 78 136 151 122 136 87
Permits: Ready to Issue (City
Approved)2 8 5 12 39 62 46 112 127 135 131 64
Permits: Issued (Permit Obtained)3 8 5 12 36 62 43 89 120 125 128 63
Permits: Final Inspection Approved4 3 4 9 12 33 46 37 62 101 105 80
Permits Expired 1 1 1 6 2
Detached ADUs (Submitted)5 20 35 52 52 80 80 48 53 36
Detached ADUs (Issued)5 8 24 41 33 55 64 57 48 20
Attached ADUs (Submitted)6 8 20 23 20 56 44 43 47 30
Attached ADUs (Issued)6 4 11 21 9 34 32 40 52 21
Junior ADUs (Submitted)7 1 1 1 25 27 31 36 21
Junior ADUs (Issued)7 1 1 1 9 24 28 24 22
Average Application Processing
Time (Days Including Weekends)8 127 214 118 183 135 197 162 193 187 193 188
Average Construction Time (Days
Including Weekends)9 578 751 330 287 173 262 455 431 496 519 459
City Impact Fees Collected for New
ADUs10 $451,514 $402,012 $198,962 $44,057 $139,592 $540,453 $487,322 $498,101 $310,952
ADU Size Smallest 150 SF 159 SF 220 SF 208 SF 178 SF 192 SF 227 SF 165 SF 176 SF
ADU Size Largest 900 SF 900 SF 1,031 SF 1,000 SF 1,218 SF 2,217 SF 1,000 SF 1,000 SF 1,000 SF
Average ADU Size 470 SF 469 SF 383 SF 518 SF 550 SF 589 SF 571 SF 558 SF 570 SF
North 46%49%52%55%49%52%41%44%38%ADU Location Relative
to Oregon Expressway South 54%51%48%45%51%48%59%56%62%
Source: City of Palo Alto Accela Data January 2015 through June 2025
Notes:
1. Any ADU/JADU Application SUBMITTED for the year
2. Any ADU/JADU application Permit 'READY TO Issue' for the year (regardless of when it was submitted)
3. Any ADU/JADU Permit ISSUED for the year (regardless of when it was submitted)
4. Any ADU/JADU Permit receiving a Final Inspection (Ready to Occupy) for the year, regardless of when the application was submitted. Years 2015-2017 data point not available.
Table 1: Summary of ADU Permits from 2015-2025
5. Any Detached ADU Permit Application submitted for the year/Any Detached ADU Permit Issued for the year, regardless of when the application was submitted. Years 2015-2016 data point not available.
6. Any Attached ADU Permit Application submitted for the year/Any Attached ADU Permit Issued for the year, regardless of when the application was submitted. Years 2015-2016 data point not available.
7. Any JADU Permit Application submitted for the year/Any JADU Permit Issued for the year, regardless of when the application was submitted. Years 2015-2016 data point not available.
8. Average number of days from permit application submittal to when permit is approved and ready to issue. This average includes weekends and days application is pending due to applicant preparation
of resubmittal or additional information from applicant.
9. Average number of days from permit issued to final inspection completed. This average includes weekends and days staff is waiting for applicant to schedule the next required inspection; it also includes
time related to the construction of a primary residence when the J/ADU is built at the same time.
10. Impact Fees collected for ADU’s permitted for the year. Years 2015-2016 data point not available.
FISCAL/RESOURCE IMPACT
This action has no fiscal impact.
ATTACHMENTS
Attachment A: Q2 2025 ADU Location Data Table
APPROVED BY: Jonathan Lait, Planning and Development Services Director
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
# of
Apps
1
Dwelling
Type
JADU
Project
Location
South
Zoning
District
R-1
Date
Filed
1/7/25
Application
Status
Pending
Structure
of Space
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage ADU Size
200x
Resubmittal
2
3
4
5
6
7
ADU
ADU
JADU
JADU
ADU
ADU
South
North
South
North
South
North
R-1
(8000)
R-1
1/10/25
1/13/25
1/14/25
1/27/25
1/28/25
1/28/25
Permit
Issued
Permit
Issued
Permit
x
x
x
x
x
x
2
1
1
1
1
2
728
517
493
265
558
944
R-1 (S)
R-1
x
x
Issued
Pending
Resubmittal
Permit
Issued
Pending
Resubmittal
R-1
(7000)
R-1
8 ADU North R-1 1/30/25 Pending
Resubmittal
x 1 647
9 ADU
ADU
South
North
R-1
(8000)
R-1
1/30/25
2/3/25
Pending
Resubmittal
Pending
x
x
2
1
800
71810
(10000)Resubmittal
11
12
13
ADU
JADU
ADU
North
North
South
R-1 (S)2/4/25
2/5/25
2/6/25
Incomplete x 2
1
2
799
286
745
R-1 Permit
Issued
Pending
Resubmittal
x
R-1 x
x
x
x14
15
ADU South
South
R-1
R-1
2/10/25
2/11/25
Pending
Resubmittal
1
0
825
389JADUPermit
Issued
x
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
Structure
of Space
# of
Apps
16
Dwelling
Type
ADU
Project
Location
North
Zoning
District
R-1
Date
Filed
2/11/25
Application
Status
Pending
# of
Bdrms
0
Attached Detached Attached Detached
x
Garage
x
ADU Size
787
(10000)Resubmittal
17 ADU South RM-15 2/12/25 Pending x 2 680
Resubmittal
18
19
ADU South
North
R-1
R-1
2/12/25
2/18/25
Pending
Resubmittal
x 1
0
560
246JADUPendingx
Resubmittal
20
21
ADU North
South
R-1
R-1
2/18/25
2/20/25
Pending
Resubmittal
x 1
0
430
293JADUPermit
Issued
x x
x22JADUSouthR-1
R-1
2/20/25 Pending
Resubmittal
x 0 230
23
24
ADU
ADU
South
South
2/20/25
2/20/25
In Plan
Check
Pending
Resubmittal
x
x
2
2
400
781R-1
(8000)
25 ADU South R-1 2/21/25 Permit
Issued
x 1 545
26
27
28
ADU
JADU
ADU
North
South
South
R-1
R-1
R-1
2/24/25
2/25/25
2/25/25
Permit
Issued
In Plan
Check
In Plan
Check
x
x
x
1
1
1
748
499
748
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
Structure# of
Apps
29
Dwelling
Type
ADU
Project
Location
North
Zoning
District
R-1
Date
Filed
3/5/25
Application
Status
Pending
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage
x
of Space ADU Size
453
Resubmittal
30
31
32
JADU
ADU
ADU
South
South
North
R-1 (S)
R-1
3/11/25
3/13/25
3/17/25
Permit
Issued
Permit
x x 1
1
0
395
796
403
x
Issued
R-1 Pending
Resubmittal
x x
33
34
ADU North
South
R-1
R-1
3/18/25
3/19/25
Pending
Resubmittal
x
x
0
0
936
288JADUIn Plan
Check
35 ADU South R-1 (8000)3/19/25 Pending
Resubmittal
x 2 998
36
37
ADU
ADU
North
South
R-1 3/19/25
3/20/25
In Plan
Check
Pending
Resubmittal
x
x
1
1
800
527R-1 (8000)
38
39
ADU
ADU
South
South
R-1 3/25/25
3/27/25
Pending
Resubmittal
x x 1
1
423
749R-1
(8000)(S)
Permit
Issued
x
40
41
42
ADU
JADU
JADU
North
South
North
R-1 3/27/25
3/31/25
3/31/25
Pending
Resubmittal
x
x
x
1
1
1
667
420
407
R-1 Pending
Resubmittal
x
R-1
(10000)
In Plan
Check
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
# of
Apps
43
Dwelling
Type
ADU
Project
Location
South
Zoning
District
R-1
Date
Filed
3/31/25
Application
Status
Pending
Structure
of Space
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage ADU Size
308x
Resubmittal
44 ADU South R-1 4/3/25 Pending x 1 494
Resubmittal
45
46
47
48
ADU
ADU
ADU
ADU
South
North
South
North
R-1
R-1
R-1
R-1
4/4/25
4/7/25
4/8/25
4/8/25
In Plan
Check
In Plan
x
x
x
x
1
1
2
1
494
360
653
751
Check
Pending
Resubmittal
Pending
Resubmittal
x
49
50
ADU
ADU
South
South
R-1 4/9/25 Pending
Resubmittal
x
x
2
2
700
649R-1
(8000)
4/10/25 In Plan
Check
51
52
53
54
JADU
JADU
ADU
ADU
North
South
North
South
R-1
R-1
R-1
R-1
4/11/25
4/15/25
4/16/25
4/17/25
Pending
Resubmittal
x
x
x
x
1
1
1
1
457
176
408
748
Pending
Resubmittal
Pending
Resubmittal
x
Pending
Resubmittal
55 JADU South R-1 4/18/25 Pending
Resubmittal
x 1 468
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
Structure# of
Apps
56
Dwelling
Type
ADU
Project
Location
South
Zoning
District
R-1
Date
Filed
4/23/25
Application
Status
In Plan
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage
x
of Space ADU Size
794
Check
57
58
ADU North
South
R-1 4/24/25
4/28/25
Pending
Resubmittal
Pending
Resubmittal
x 2
1
924
390JADUR-1
(7000)
x x
x59
60
ADU
ADU
South
South
R-1
R-1
4/28/25
4/29/25
Pending
Resubmittal
x 1
1
495
711Pendingx
Resubmittal
61
62
63
ADU
JADU
ADU
South
North
North
R-1
R-1
R-1
4/29/25
5/1/25
5/1/25
Pending
Resubmittal
Pending
Resubmittal
Pending
x
x
x
1
0
2
698
401
749
x
Resubmittal
64
65
ADU
ADU
South
South
R-1 5/7/25 Pending
Resubmittal
x 1
2
747
832RM-30 5/13/25 Pending x x
Resubmittal
66
67
ADU
ADU
North
North
R-1
(10000)
R-1
5/14/25
5/15/25
Incomplete x
x
2
2
1,000
650Pending
Resubmittal
68 ADU South R-1 (S)5/15/25 In Plan
Check
x 1 496
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
# of
Apps
69
Dwelling
Type
JADU
Project
Location
South
Zoning
District
R-1
Date
Filed
5/19/25
Application
Status
Pending
Structure
of Space
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage ADU Size
498
Resubmittal
70
71
ADU
ADU
South
South
R-1
R-1
5/21/25
5/21/25
Pending
Resubmittal
x 1
1
295
295Pending
Resubmittal
x
72
73
ADU
ADU
South
South
R-1
R-1
5/23/25
5/27/25
In Plan
Check
Pending
Resubmittal
x x 0
1
590
716x
x74
75
ADU
ADU
North
North
R-1
R-1
5/28/25
5/28/25
Pending
Resubmittal
2
1
794
273Pendingx
Resubmittal
76
77
78
JADU
ADU
ADU
North
South
South
R-1
R-1
5/29/25
6/3/25
6/5/25
In Plan
Check
In Plan
x
x
x
1
2
1
326
749
540
Check
Pending
Resubmittal
R-1
(8000)(S)
79
80
ADU
ADU
North
South
R-1 6/9/25 In Plan
Check
In Plan
Check
x
x
1
1
559
459R-1 (7000)6/11/25
81
82
ADU South
North
R-1
R-1
6/13/25
6/19/25
In Plan
Check
Pending
Resubmittal
x x 1
1
402
225JADUxx
Q1-Q2 2025 ADU/JADUs Submitted New Construction Conversion Type of Conversion
Other
Acc.
# of
Apps
83
Dwelling
Type
ADU
Project
Location
North
Zoning
District
R-1
Date
Filed
6/23/25
Application
Status
Pending
Structure
of Space
# of
Bdrms
1
Attached Detached Attached Detached
x
Garage
x
ADU Size
341
Resubmittal
84 ADU South R-1
(8000)
6/24/25 In Plan
Check
x x 1 749
85
86
ADU
ADU
South
North
R-1 6/24/25
6/26/25
In Plan
Check
x 0
1
749
540R-1 Pending
Resubmittal
x
87 ADU South RE 6/30/25 In Plan
Check
x 1 795