Loading...
HomeMy WebLinkAboutStaff Report 2505-4733CITY OF PALO ALTO CITY COUNCIL Special Meeting Monday, August 11, 2025 Council Chambers & Hybrid 5:30 PM     Agenda Item     10.Approval of Increase of Construction Contingency for Contract No. C24189237 with SAK Construction, LCC in the amount of $1,800,000, Funded by the Wastewater Treatment Enterprise Fund for the Joint Intercepting Sewer Rehabilitation (Phase 1) Project (WQ 24000), and Approval of a Budget Amendment in the Wastewater Treatment Fund; CEQA Status - Exempt under CEQA Guidelines Section 15301 (Repairs to Existing Facilities) City Council Staff Report From: City Manager Report Type: CONSENT CALENDAR Lead Department: Public Works Meeting Date: August 11, 2025 Report #:2505-4733 TITLE Approval of Increase of Construction Contingency for Contract No. C24189237 with SAK Construction, LCC in the amount of $1,800,000, Funded by the Wastewater Treatment Enterprise Fund for the Joint Intercepting Sewer Rehabilitation (Phase 1) Project (WQ 24000), and Approval of a Budget Amendment in the Wastewater Treatment Fund; CEQA Status - Exempt under CEQA Guidelines Section 15301 (Repairs to Existing Facilities) RECOMMENDATION Staff recommends that the City Council: 1. Approve an increase of construction contingency for Contract No. C24189237 with SAK Construction, LCC in an amount not to exceed $1,800,000 for a total contract contingency amount not to exceed $2,534,770; and 2. Approve an amendment to the Fiscal Year 2026 Adopted Capital Budget Appropriation for the Wastewater Treatment Fund (requires a 2/3 majority vote) by: a. Increasing the Joint Intercepting Sewer Rehabilitation (Phase 1) project (WQ-24000) appropriation by $700,000; and b. Decreasing the Wastewater Treatment Fund balance by $700,000. EXECUTIVE SUMMARY The Joint Intercepting Sewer Rehabilitation (Phase 1) Project will install a structural liner in a critical 72-inch sewer pipeline that conveys over half the influent flow to the Regional Water Quality Control Plant (RWQCP). The City awarded a $8.1 million construction contract to SAK Construction, LLC in December 2023, including a 10% construction contingency. During construction, significant unforeseen site conditions, contractor schedule and sequencing challenges, and necessary design clarifications required change orders that have nearly exhausted the original contingency. While the main pipe rehabilitation work is complete, further work including bypass rerouting, manhole modifications, and structural evaluation of a major junction structure necessitates an increase to the construction contingency. Staff recommends increasing the contingency by $1,800,000. If the contingency is fully utilized, the total contract not-to-exceed amount would be $9,882,470. Cost-sharing among RWQCP partner agencies will be reconciled based on final expenditures. BACKGROUND The Joint Intercepting Sewer Rehabilitation (Phase 1) Project rehabilitates 2,364 linear feet of deteriorated 72-inch diameter concrete sewer pipe using cured-in-place pipe (CIPP) lining, addressing extensive corrosion in a critical section of the Joint Intercepting Sewer (JIS) system leading to the RWQCP. This section of the JIS conveys most of the wastewater flow from Mountain View, Los Altos, Los Altos Hills, and Palo Alto to the RWQCP. There are other sewers leading to the RWQCP, but these are maintained by the Utilities Department, Stanford University, and the East Palo Alto Sanitary District and not included in the scope of this Project. City Council awarded the design contract for the Project to Jacobs Engineering Group, Inc. on May 16, 2022, and the design was completed in August 2023.1 On December 11, 2023, City Council approved a funding agreement with partners, a construction contract with SAK Construction, LLC (SAK) for a base amount of $7,347,700 and a 10% contingency of $734,770, for a total not-to-exceed amount of $8,082,470, as well as an amendment to the construction management services contract with Tanner Pacific, Inc.2 Construction began in winter 2024 but encountered delays due to unforeseen site conditions, including difficult access and obstructions not visible during pre-construction investigations, as well as contractor schedule and sequencing challenges. These delays pushed field construction activities into the 2025 dry season. On June 9, 2025, Council approved amendments to related contracts for Jacobs Engineering Group, Inc., Tanner Pacific, Inc., and Carollo Engineers, Inc. to support continued engineering and construction management services through the extended schedule.3 ANALYSIS While the primary pipe rehabilitation (CIPP lining) was successfully completed, during the initial phases of construction, there were project delays due to unforeseen site conditions, as well as 1 City Council, May 16 2022; Consent Item #7; SR #14164, https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=81838 2 City Council, December 11, 2023; Consent Item #2; SR #2308-1879, https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=82522 3 City Council, June 9, 2025; Consent Item #11; SR #2504-4519, https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=83447 contractor schedule and sequencing challenges. These delays pushed field construction activities into the 2025 dry season. Additional unforeseen work became necessary, including: Excavation and backfill to construct pump pads at two additional locations Landfill cap material import and placement after landfill waste discovered during excavations Replacement of a manhole base deemed structurally unsuitable Modifications to existing manholes to accommodate liner transitions Addressing complications with the bypass pumping system due to higher-than- anticipated flow variability. Isolation and structural evaluation of a critical junction box (JB-0), which was previously inaccessible Additional temporary bypass rerouting to enable safe inspection of JB-0 and repair FISCAL/RESOURCE IMPACT project (WQ-24000) by $700,000 (there is currently $1.1 million available in the project), from $12.4 million to $13.1 million. STAKEHOLDER ENGAGEMENT Project notices and updates have been shared with the Parks and Recreation Commission and through City newsletters, with staff responding to public inquiries and keeping stakeholders informed throughout key milestones. On February 25, 2025, staff briefed the Parks and Recreation Commission (PRC) on construction progress and on Byxbee Park Western Trail Temporary Closure from 3/30/2025 to 11/30/2025 for the Sewer Pipe Rehabilitation.4 On July 22, 2025, staff provided an update to the PRC during the Departmental Report. ENVIRONMENTAL REVIEW ATTACHMENTS APPROVED BY: 4 Parks and Recreation Commission, February 25, 2025; Agenda Item #3; SR# 2502-4115, https://cityofpaloalto.primegov.com/Portal/Meeting?meetingTemplateId=16875 Le g e n d ±Condition Assessment Figur e E x p o r t e d : 7 / 2 9 / 2 0 2 0 B y : k b r a d l e y U s i n g : \ \ w o o d a r d c u r r a n . n e t \ s h a r e d \ P r o j e c t s \ R M C \ S J \ 0 3 8 - 0 1 4 P a l o A l t o R W Q C P P r o g r a m M a n a g e m e n t \ B . P r o g r a m M a n a g e m e n t \ 7 . O t h e r P r o j e c t s \ 7 2 I n c h C o n d A s s e m t \ C A \ M a p s \ P a l o A l t o _ 7 2 I n c h . m x d Project #: 0038014.01Map Created: July 2020 0 0.1 0.20.05 Miles Third Party GIS Disclaim er: This m ap is for reference and graphical purposes only and should not be relied upon by third parties for any legal decisions. Any reliance upon the m ap or data contained herein shall be at the users’ sole risk . Data Sources: !Manholes and Structures Future Phase 1 REGIONAL WATER QUALITY CONTROL PLANT REGIONAL WATER QUALITY CONTROL PLANT FLOWFLOW FIGURE 7: RECOMMENDED PROJECT PRIORITIZATION 21 Palo AltoTrunk Sewer Trunk Sewer Interceptor Attachment A: SITE MAP This Projec t Attachment B ‐ Partner Agencies Cost Share Summary for Construction Phase Table B‐1: Project Costs during Construction (Less Bypass Pumping Inside The Plant) Estimated Cost at Time of Estimated Cost June 2025 Current EstimatedAgencyFixed Cost Share %Construction Award December 2023 City of Mountain View of Palo Alto of Los Altos of Los Altos Hills Subtotal: 62.50%$4,398,734 $4,808,985 $4,808,985 100.00%$7,037,975 $7,694,376 $7,694,376 Table B‐2: Cost for Bypass Pumping during Construction inside The Plant Cost at Time of Estimated Cost June 2025 Current EstimatedAgencyEstimated Cost Share %*Construction Award December 2023 City of Mountain View of Palo Alto 39.31%$760,885 $799,365 $1,507,000 City of Los Altos Town of Los Altos Hills Palo Alto Sanitary District University Subtotal: 5.56%$104,904 $122,736 $1,896,996 $113,062 $129,127 $2,033,489 $213,000 $243,000 $3,833,000 6.35% 100.00% * Estimate only based on FY2025 cost share (actual cost share will be determined after project completion based on wastewater flows and strength by each partner in 2024, 2025, and 2026). ** Includes additional contingency of $1.8 M Table B‐3: Not‐to‐Exceed Cost for Partners during Construction (Sum of Table B‐1 and B‐2) Estimated Total Cost at Time Estimated Total Cost Current EstimatedAgencyOverall Project Cost Share %of Construction Award December 2023 in June 2025 Total Cost City of Mountain View of Palo Alto 54.79%$5,159,619 $5,608,349 $6,316,000 City of Los Altos Town of Los Altos Hills Palo Alto Sanitary District University Total, Not‐to‐Exceed: 1.85%$104,904 $113,062 $213,000 2.11%$122,736 $129,127 $243,000 100.00%$8,934,970 $9,727,865 $11,528,000