HomeMy WebLinkAboutStaff Report 2502-4186CITY OF PALO ALTO CITY COUNCIL Monday, April 14, 2025 Council Chambers & Hybrid 5:30 PM     Agenda Item     5.Approval of Amendment No. 2 via Change Order No. 2 to Contract Number C22183580 with MP Nexlevel of California, Inc. in the Amount of $4,000,000 for a Total Not-to-Exceed Amount of $15,347,390, and Extending the Three-Year Term of the Contract for an Additional Four Months Through August 31, 2025 to Provide Substructure and Utility Trenching Construction Services for the Foothills Rebuild Wildfire Mitigation and Grid Modernization for Electrification Projects; CEQA Status: the Foothills Rebuild and Grid Modernization Project are Exempt Under CEQA Guidelines Sections 15302, 15303 and 15183 6 5 7 1 City Council Staff Report From: City Manager Report Type: CONSENT CALENDAR Lead Department: Utilities Meeting Date: April 14, 2025 Report #:2502-4186 TITLE Approval of Amendment No. 2 via Change Order No. 2 to Contract Number C22183580 with MP Nexlevel of California, Inc. in the Amount of $4,000,000 for a Total Not-to-Exceed Amount of $15,347,390, and Extending the Three-Year Term of the Contract for an Additional Four Months Through August 31, 2025 to Provide Substructure and Utility Trenching Construction Services for the Foothills Rebuild Wildfire Mitigation and Grid Modernization for Electrification Projects; CEQA Status: the Foothills Rebuild and Grid Modernization Project are Exempt Under CEQA Guidelines Sections 15302, 15303 and 15183 RECOMMENDATION Staff recommends that City Council approve and authorize the City Manager or their designee to execute Change Order No. 2 to contract C22183580 with MP Nexlevel (Attachment A) for substructure installations, utility trenching, and conduit installations in support of the Foothills Rebuild and Grid Modernization projects, in an amount not-to-exceed $4,000,000, for a revised total contract amount of $15,347,390 and extending the term of the contract to August 31, 2025 for a total of three years and four months. BACKGROUND The City contracts substructure and trenching construction services because the amount of work varies year over year and use of contracted services allows for the most efficient and cost- effective use of resources for this variable timing. In 2022, MP Nexlevel was deemed the lowest responsible bidder of a competitive solicitation for utility trench and substructure installation (Staff Report 139531). The performance and quality of work delivered by MP Nexlevel has been satisfactory over the years. As part of the task order completion process, MP Nexlevel’s work is inspected and signed off by internal staff. The original Task Order Construction Contract C22183580 with MP Nexlevel of California, Inc., was approved by Council March 21, 2022 in the amount of $8,815,809 for Trenching and Substructure Installation and Materials and a contingency amount of $881,581, for a total not-to-exceed amount of $9,697,390 over three 1 City Council, March 21, 2022: Staff Report #13953 https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=81767 6 5 7 1 years through April 30, 2025. For customer-related work, trenching and substructure work are reimbursed by the customers through the customer connection charges. Since FY 2023, the City has been reimbursed $4.5 million from customers for new service connections. 2). MP Nexlevel will install, lash, splice and test approximately 59,500 feet of fiber optic cable; build underground laterals and pad mounts for fiber distribution cabinets; and build a concrete pad to support the fiber hut and emergency generator including electric wiring, lighting, HVAC and security fencing. The FTTP pilot will inform the City the best mix of insource (internal staff) and outsource (contractors) staffing to construct and operate the new municipal Palo Alto fiber internet business. Change order #1 covers the FTTP Phase 1 pilot area only. Once the pilot area is complete and can inform the requirements for a competitive solicitation, staff will be requesting competitive bids for construction of the remainder of the FTTP Phase 1 scope. ANALYSIS 3 Plan, the Utilities Department is undergrounding eleven miles of overhead electric lines in the Foothills area. This project involves installing substructure work, including boxes for electric and fiber lines; removing electric lines and fiber lines from overhead poles; and installing padmount equipment where possible. Given the number of miles of undergrounding and steep terrain in the foothills, the project was divided into five phases over three years (FY 2022 – FY 2025). As of February 2025, three of five phases have been completed and the remaining two phases are underway with a planned project completion of June 30, 2025. 4 map, the Foothills region is a mix of high and very high hazard zones. The City’s goal is to complete the Foothills Rebuild project by the end of Fiscal Year 2025 and before wildfire season begins. Over the past three years, the City has spent approximately $6.3 million for substructure work, trenching, and conduit installation through the MP Nexlevel contract. Staff estimates an 2 City Council, October 7, 2024: Staff Report #2408-3368 https://cityofpaloalto.primegov.com/Portal/viewer?id=0&type=7&uid=1136b122-5ea9-447e-8a85-48c161ef99d4 3 Wildfire Mitigation Plan https://www.cityofpaloalto.org/files/assets/public/v/1/utilities/safety-information/cpau- wildfire-mitigation-plan-2024-update.pdf 4 Fire Hazard Severity Zone https://experience.arcgis.com/experience/6a9cb66bb1824cd98756812af41292a0 6 5 7 1 additional $3 million is required in the contract to complete the remaining undergrounding phases. FISCAL/RESOURCE IMPACT STAKEHOLDER ENGAGEMENT 5 and Grid Modernization for Electrification webpage6. ENVIRONMENTAL REVIEW 5Utilities Wildfire Mitigation webpage https://www.cityofpaloalto.org/Departments/Utilities/Utilities-Services- Safety/Safety/Utilities-Wildfire-Mitigation 6Grid Modernization for Electrification webpage https://www.cityofpaloalto.org/Departments/Utilities/Utilities- Services-Safety/Utilities-Projects/Grid-Modernization-for-Electrification 6 5 7 1 modernization project, section 15183 (projects consistent with a general plan, community plan, or zoning) since it is consistent with the Environmental Impact Report (EIR) Addendum to the City of Palo Alto Comprehensive Plan Final Environmental Impact Report Council approved on June 5, 2023. ATTACHMENTS APPROVED BY: CONTRACT CHANGE ORDER CITY OF PALO ALTO DEPARTMENT: ELECTRIC UTILITIES OPERATIONS _____________________________ Project Contract Change Order # Project Title: Foothills Rebuild Project No.: EL-21001 Contract Number: C22183580 Date: 2/20/25 Contractor: MP Nexlevel of California, Inc. Change Order No.: 2 Description of Change Order Background Information: The original contract C22183580 was approved by Council on March 21, 2022 under staff report ID 13953. The original term of the contract was an annual not-to-exceed amount of $9,697,390 for a total three-year not-to-exceed amount from June 15, 2022 through April 30, 2025. https:// recordsportal.paloalto.gov/WebLink/DocView.aspx?id=81767&dbid=0&repo=PaloAlto Change order #1 was approved by Council on October 7, 2024 under staff report ID 2408-3368. $1.65 million was added to the MP Nexlevel (MPNL) contract to perform substructure work for the new fiber hut and fiber construction for the fiber-to-the-premises (FTTP) pilot. With the FTTP amendment, the revised not-to-exceed amount is $11,347,390. Staff Report 2408-3368 As of Feb 19, 2025, there is approximately $1,400,000 remaining in the contract. Utilities will be issuing a new RFP for substructure work in March 2025. It will take approximately 4-6 months to award the new contract including Council’s approval. A change order is required for MPNL to maintain business continuity and accelerate the Foothills Undergrounding project until a new contract is in place. The average monthly MPNL billing rate is approximately $450,000 for up to three crews. Staff may request for a fourth crew at times depending on the number of projects that are occurring concurrently. Change Order Justification: The City does not possess the staffing resources to provide substructure, trenching services and fiber installation because the amount of work varies year over year. These services have been contracted out for approximately 30 years and are required to complete CIP and customer connections in a timely and cost-effective manner. The City has been contracting with MP Nexlevel for over the past 10 years for substructure installations, utility trenching, and fiber conduit installations Staff recommends increasing the task order construction contract by $4,000,000 to accelerate undergrounding of critical areas deemed as high fire threat in the foothills before fire season begins (2024 Wildfire Mitigation Plan). In addition, staff needs additional funding to complete the pilot for electric gird modernization and new customer connection projects (i.e. Hoover School). Staff also recommends extending the duration of the contract by four months from April 2025 to August 2025 until a new contract is in place. Staff will be issuing a new competitive bid for substructure and trenching construction in March 2025 with anticipation of a new contract award in August 2025 (post-Council break). This change order will bridge the gap between April through August 2025. When the new contract is awarded, all remaining funds in the existing contract will be disencumbered and returned to reserves. Docusign Envelope ID: 23AB0BDA-C1C4-45E2-9520-72E52BEEAF18 Description of Work to be Performed: Contractor will provide ongoing and scheduled substructure construction work for the following CIP projects:  Foothills Undergrounding (EL-21001) ~ $3.1M  Grid Modernization (EL-24000) ~$0.6M  Customer Connections (EL-89038) ~0.3M Incorporates Field Order Number(s): Bid items 1 – 34 Cost Time This Change Order will:  No cost change: N/A X Increase cost by $ 4,000,000  Decrease cost by $ N/A This Change Order will: X Increase time by __123__ days o _0_ days Excusable Delay o _0_ days Compensable Delay  Decrease time by ____ days The date of completion as of this Change Order is: August 31, 2025_______________________________ G/L account number (s): 40030200 / 31650 Basis for change in cost:  Unit price(s)  Lump sum X Time and Materials  Compensation for Compensable Delay  Other: Docusign Envelope ID: 23AB0BDA-C1C4-45E2-9520-72E52BEEAF18 Contract Change Order – continued CONTRACTOR CERTIFICATION: By signing below, Contractor agrees that this Change Order constitutes full resolution, settlement, accord and satisfaction with respect to any and all pending or future Claims for cost and extensions of time that were asserted, or that could have been asserted, in connection with the Work covered by this Change Order, as more fully set forth in Article 7 of the Contract General Conditions. FAILURE TO EXECUTE: If Contractor fails to promptly execute this Change Order after it has been submitted for Contractor’s signature, the City may unilaterally approve this Change Order as set forth in Article 7 of the Contract General Conditions. Contractor may dispute the terms of a unilaterally-approved Change Order, in whole or in part, by submitting a Claim in accordance with the Dispute Resolution Procedures set forth herein within fourteen (14) days after the Change Order is approved by the City. If Contractor fails to submit a Claim within that 14-day period, with respect to all or part of the unilaterally-approved Change Order, those portions of the Change Order which have not been disputed by timely submission of a Claim shall be deemed to have the same effect as if the Change Order was fully executed by both parties as set forth above. Accepted for Contractor: Accepted for City of Palo Alto: By: By: Title: Title: Date: Date: PC O N o . AS I FO CO R CO Description Amount Reason for Change 1 Foreman $795,302 Foothills Underground/Grid Mod 2 Laborer $1,526,280 Foothills Underground/Grid Mod 3 Equipment Operator $66,989 Foothills Underground/Grid Mod 4 Truck Driver Class A $44,520 Foothills Underground/Grid Mod 5 Qualified journeyman worker to perform conduit intercepts in an energized duct bank $10,501 Foothills Underground/Grid Mod 6 Concrete Finisher $47,461 Foothills Underground/Grid Mod 7 Core Driller with operator $7,805 Foothills Underground/Grid Mod 8 Concrete Saw with operator $7,141 Foothills Underground/Grid Mod 9 Foreman’s Truck $68,880 Foothills Underground/Grid Mod 10 Crew truck, with Hand Tools, and Gas-Powered Cutoff Saw $103,320 Foothills Underground/Grid Mod 11 Compressor and Jackhammer $2,115 Foothills Underground/Grid Mod 12 Backhoe $19,389 Foothills Underground/Grid Mod 13 Ramhoe $7,939 Foothills Underground/Grid Mod 14 Bobtail Truck $179,760 Foothills Underground/Grid Mod 15 End-Dump Truck $242,549 Foothills Underground/Grid Mod Scope of Work Docusign Envelope ID: 23AB0BDA-C1C4-45E2-9520-72E52BEEAF18 3/31/2025 Robbi Pribyl President 16 10-wheel Dump Truck $35,280 Foothills Underground/Grid Mod 17 Boom Truck with Flatbed $3,528 Foothills Underground/Grid Mod 18 Directional Boring Rig $9,869 Foothills Underground/Grid Mod 19 Arrow Board $355 Foothills Underground/Grid Mod 20 Vac Trailer – 800 Gallons $28,224 Foothills Underground/Grid Mod 21 Mini Excavator $61,600 Foothills Underground/Grid Mod 22 Bobcat Skid-Steer $2,829 Foothills Underground/Grid Mod 23 Equipment Trailer $15,960 Foothills Underground/Grid Mod 24 A/C Roller $2,296 Foothills Underground/Grid Mod 25 Estimator $14,981 Foothills Underground/Grid Mod 26 3-5 Yard Dump Truck $3,877 Foothills Underground/Grid Mod 29 Box Shoring $5,733 Foothills Underground/Grid Mod 30 Message Board $3,613 Foothills Underground/Grid Mod 31 Pipe Fusing (100') $14,280 Foothills Underground/Grid Mod 32 Pipe Grouting $111,301 Foothills Underground/Grid Mod 33 2200 Gallon Vacuum Truck $397,419 Foothills Underground/Grid Mod 34 Large Bore Rig $158,901 Foothills Underground/Grid Mod Total for this Change Order $4,000,000 Docusign Envelope ID: 23AB0BDA-C1C4-45E2-9520-72E52BEEAF18 Document Preparation By: Dave Yuan Title: Utilities Strategic Business Manager Date: March 27, 2025 City Approval – Division Head Signature required on all Change Orders By : Title : Jorge Silva Interim Assistant Director, Electric Engineering and Operations Date: City Approval – Department Head Signature required when any individual Change Order exceeds $10,000. By: Title: Kiely Nose Interim Director of Utilities Date: Contract Change Order – continued Summary of Amounts Payable Under Contract (For Internal Purposes Only) Original Contract Sum: $ 9,697,390.00 Previous Change Orders $ 1,650,000.00 This Change Order $ 4,000,000.00 Revised Contract Sum: $ 15,347,390.00 Compare to: Original Contract Authorization: $ 8,815,809.00 Contingency: 881,581.00 Contract Amendment Authorizations $ 1,500,000.00 Contingency added: 150,000.00 Contingency Authorizations: $ 1,031,581.00 Used to date (0.00) Total Authorized Funding: $ 11,347,390.00 Balance remaining 1,408,953.00 Change Orders shall not be initiated for Council-approved contracts if the revised Contract Sum exceeds the total authorized funding amount. Docusign Envelope ID: 23AB0BDA-C1C4-45E2-9520-72E52BEEAF18