Loading...
HomeMy WebLinkAboutStaff Report 2405-3043CITY OF PALO ALTO CITY COUNCIL Special Meeting Monday, December 16, 2024 Council Chambers & Hybrid 5:30 PM     Agenda Item     28.Semiannual Update on the Status of Capital Improvement Program Projects; CEQA Status – Not a Project City Council Staff Report From: City Manager Report Type: INFORMATION REPORTS Lead Department: Public Works Meeting Date: December 16, 2024 Report #:2405-3043 TITLE Semiannual Update on the Status of Capital Improvement Program Projects; CEQA Status – Not a Project RECOMMENDATION This report is provided for information only and requires no Council action. EXECUTIVE SUMMARY The City Council and Palo Alto community can be proud of the City’s capital improvement program (CIP). The CIP represents major investments in infrastructure functionality and sustainability, funded largely through the 2014 Council Infrastructure Plan as well as utility rates and various other sources. The 2024-2028 five-year CIP totaled $1.2 billion for 209 projects as reviewed by the Council in its adoption of the FY 2024 Capital Budget. Since July 2016, the City of Palo Alto has completed 101 individual community-serving projects totaling over $406 million in improvements. A summary of all completed CIP projects is provided at the end of Attachment A. The CIP also represents a major effort for much of the City workforce. The following table summarizes the status of all projects for the six-month period of January to June 2024. One Time CIP's CIP Workgroup Recurring CIPs Pre-Design Design Procurement Construction Completed Airport 0 0 3 2 1 0 Buildings and Facilities 10 4 10 0 11 0 Electric 9 2 10 0 6 0 Fiber Optic 2 0 2 0 0 0 Gas 4 0 1 0 1 0 Parks and Open Space 9 5 5 0 5 1 Stormwater Management 2 0 3 0 3 0 Streets and Sidewalks 8 0 3 0 0 0 Traffic and Transportation 5 1 5 1 2 1 Wastewater Collection 4 0 0 0 0 1 Wastewater Treatment 1 2 3 0 3 1 Water 7 1 1 0 2 1 Subtotals 61 15 46 3 34 5 Totals 164 BACKGROUND This report provides Council with an update on the status of capital improvement program (CIP) projects, with detailed and useful information for the Council and public regarding general fund and enterprise fund projects that appear on Council agendas and will be visible throughout the community. The report does not include Internal Service Funds projects (Information Technology and Vehicle). ANALYSIS Project Update Organization The City of Palo Alto has a robust capital improvement program, and many individual projects are in progress at any given time. The 2024-2028 five-year CIP totaled $1.2 billion for 209 projects as reviewed by the Council as part of the adoption of the FY 2024 Capital Budget. The attached CIP project tables are intended to provide Council with a quick overview of each project, including budgetary information, the anticipated completion date, a brief description of the project scope, the status of the project, and upcoming activities including Council actions. Also included in the report is a list of all completed projects since the introduction of the Infrastructure Management System. Major/Significant Projects Summary The 2014 Council Infrastructure Plan is a major focus of staff’s capital improvement program efforts and ties to several 2024 City Council Priorities and related objectives. The following table details the Total Project Budget and Total Actual Expenses through June 30, 2024, for the Infrastructure Plan projects. Please note that the project updates in the Council Infrastructure Plan table are current as of the publication of this report, while the attached comprehensive project updates include June 30, 2024 status information. Council Infrastructure Plan Projects CIP Number Project Update Total Project Budget Total Actual Expenses* New Public Safety Building PE-15001 Construction is finishing up with completion expected in winter 2025. Phased staff move-in is expected in January 2025, following December 2024 issuance of a Temporary Certificate of Occupancy. $118,137,997 $113,275,793 Bicycle and Pedestrian Transportation Implementation Plan PL-04010 This project funds the Bicycle and Pedestrian Transportation Plan Update, which has kicked off recently and is slated to take approximately 18 months to complete. This project also funds the implementation of various bicycle and pedestrian projects. $15,293,904 $211,611 New Downtown Parking Garage PE-15007 Council directed staff to look at the feasibility of partnering with a private entity to develop new parking using downtown in-lieu parking fees in conjunction with housing or other uses, including the use of City surface lots or privately held parcels. Council gave direction to staff in December 2023 to advance the project in conjunction with advancement of affordable housing in the Downtown area. A design contract for the garage was approved on Council’s December 2, 2024 consent agenda. $7,488,918 $1,440,311 New California Avenue Area Parking Garage PE-18000 Completed (final punch list items in progress)$50,213,486 $49,442,821 Charleston Arastradero Corridor Project PE-13011 Completed $20,645,491 $20,645,491 Fire Station 3 Replacement PE-15003 Completed $10,598,580 $10,598,580 Highway 101 Pedestrian/Bicycle Overpass Project PE-11011 Completed $23,734,218 $23,734,218 Fire Station 4 Replacement PE-18004 Project is going through building permit review. Staff is completed a pre-qualification process, with construction bidding anticipated in early 2025. $15,329,846 $1,860,907 Byxbee Park Completion PE-18006 On hold pending completion of Baylands Comprehensive Conservation Plan. $3,699,189 $368,192 Downtown Automated Parking Guidance Systems PL-15002 Council approved a design build contract in May 2023. Construction is underway and expected to be completed in spring 2025. $5,197,833 $1,658,417 *Total actual expenses through June 30, 2024 Current Council Infrastructure Plan project schedules can be found at https://www.infrastructure.cityofpaloalto.org/ Key considerations for the information presented in the project update tables include: •Project status information is current as of June 30, 2024. •The individual project tables align with the Capital Improvement Fund categories in the Fiscal Year 2024-2028 capital budget: Buildings and Facilities, Parks and Open Space, Streets and Sidewalks, and Traffic and Transportation. •Enterprise Fund projects follow the order of their respective Fund in the capital budget. •Department Technology Upgrades and Improvements projects and Cubberley Property Infrastructure Fund projects are included in the Buildings and Facilities table. •Additional project information is available in the Fiscal Year 2024-2028 capital budget. •Each project table is divided into a section for one-time projects and a section for recurring projects that have ongoing annual funding. •Budgetary figures include staff oversight costs for projects to which staff costs have been allocated. •The table of completed projects, located at the end of Attachment A, provides a summary of all CIP projects completed since the Biannual CIP updates to council began in 2016. Completed Projects There were five completed one-time projects in the second half of Fiscal Year 2024 (January through June 2024). •Baylands Nature Preserve Entrance Gate (OS-24000) •Charleston Arastradero Corridor Project (PE-13011) •Wastewater Collection System Rehabilitation Augmentation Project 31 (WC-19001) •Primary Sedimentation Tank Rehabilitation (WQ-14003) •Water Regulation Station Improvements (WS-07000) One-time projects do not include the significant amount of annual work completed under ongoing recurring projects, such as streets and sidewalks repairs, parking lot maintenance, roofing replacements, and regular maintenance of Utilities assets. Below are some photos of completed projects: Charleston Arastradero Corridor Project (PE-13011) Primary Sedimentation Tank Rehabilitation (WQ-14003) Wastewater Collection System Rehabilitation Augmentation Project 31 (WC-19001) One-Time Projects Under Construction The 34 projects that are currently underway include the following: Capital Improvement Fund (general fund): • Baylands Boardwalk Piling Repair (PE-24000) •Boulware Park Improvements (PE-17005) •Cameron Park Improvements (PG-14002) •Churchill Avenue/Alma Street Railroad Crossing Safety Improvements (PL-20000) •City Facilities Assessment and Record Plan Management System (PE-20002) •Civic Center Fire Life Safety Upgrades (PE-18016) •Civic Center Waterproofing Study and Repairs (PE-15020) •Cubberley Field Restroom (CB-17002) •Downtown Automated Parking Guidance Systems, Access Controls & Revenue Collection Equipment (PL-15002) •Homekey Facilities (PE-24005) •JMZ Renovation (AC-18001) •Library Automated Material Handling (LB-21000) •Lucie Stern Community Theatre Stage Rigging System Refurbishment (AC-24000) •New Public Safety Building (PE-15001) •Performing Arts Venues Seat Replacement (AC-18000) •Ramos Park Improvements (PG-14000) •Rinconada Park Improvements (PE-08001) •Roth Building Rehabilitation Phase 1 (PF-23001) Airport Fund: • Airport Layout Plan (AP-21000) Electric Fund: • Colorado Distribution Feeder Outlet Replacement (EL-22002) •Inter Substation Line Protection Relay (EL-17005) •Foothills Rebuild Fire Mitigation (EL-21001) •Hanover Substation Improvement (EL-24001) •Smart Grid Technology Installation (EL-11014) •Substation Physical Security (EL-16003) Gas Fund: •Gas Main Replacement Project 24 (GS-14003) Stormwater Management Fund: • East Meadow Drive System Upgrades (SD-22000) • East Meadow Circle Connection to Adobe Creek Pump Station (SD-26000) • Trash Capture Device Installation (SD-22002) Wastewater Treatment Fund: • Joint Intercepting Sewer Rehabilitation (Phase 1) (WQ-24000) • Plant Master Plan (WQ-10001) • Secondary Treatment Upgrades (WQ-19001) Water Fund: •Water Main Replacement Project 29(WS-15002) •Water Tank Seismic System Upgrades (WS-09000) As described above for completed projects, the list of projects under construction does not include work currently being conducted under recurring CIP projects. Below are some photos of projects under construction: New Public Safety Building (PE-15001) Capital Improvements of Note Implemented by Other Agencies El Camino Real: El Camino Real (State Highway 82) is maintained by Caltrans. Pavement Condition Index scores for El Camino Real are significantly lower than the average for Palo Alto streets. Staff has been communicating with Caltrans about the plans to repave El Camino Real in Mountain View, Los Altos, and Palo Alto. Related work to address ADA updates/shoulder and sidewalk work at different points along El Camino Real has been completed with temporary parking and shoulder closures in effect. Roadway repaving construction began in early September 2024 and is anticipated to be completed in early 2025. FISCAL/RESOURCE IMPACT Funding for the projects discussed in this report was appropriated in the Fiscal Year 2024 Adopted Capital Budget and reviewed for the 2024-2028 Five-Year CIP. STAKEHOLDER ENGAGEMENT This report was coordinated with internal City staff in the Administrative Services, Community Services, Office of Transportation, Public Works, and Utilities Departments. Stakeholder engagement is conducted separately for each project. ENVIRONMENTAL REVIEW This report is exempt from the California Environmental Quality Act (CEQA) as it is an informational report to Council. CEQA compliance is reviewed separately for each capital project. ATTACHMENTS Attachment A: Semiannual Update on the Status of Capital Improvement Program Projects APPROVED BY: Brad Eggleston, Director Public Works/City Engineer ATTACHMENT A Semiannual Update on the Status of Capital Improvement Program Projects Capital Improvement Fund CIP Projects  Buildings and Facilities Projects  Parks and Open Space Projects  Streets and Sidewalks Projects  Traffic and Transportation Projects Enterprise Fund CIP Projects  Airport Projects  Electric Projects  Fiber Optics Projects  Gas Projects  Stormwater Management Projects  Wastewater Collection Projects  Wastewater Treatment Projects  Water Projects List of Completed Projects Buildings and Facilities Projects Status as of June 2024 One‐Time Projects Animal Shelter Renovation (PE‐19002) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $2,921,108 $5,981,221 Public Works Design TBD Project Status: This project installs interim facility improvements to the Animal Shelter that accompany the agreement for operation of the shelter by Pets In Need (PIN) approved by City Council in November 2018. The medical area upgrades and the modular office building are complete. The new kennel addition has been submitted for building permit. Project was placed on hold following receipt of PIN’s letter providing one‐year notification of termination of the agreement between PIN and the City. Public Works and Community Service Department staff are reviewing the project while negotiations continue on a new agreement. A new five‐year agreement was approved by Council in March 2024. Discussions with PIN and City staff regarding capital projects will start in summer 2024.City Baylands Boardwalk Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Piling Repair $182,854 $276,461 Public Works Construction Winter 2025 (PE‐24000)Project Status: This project provides funding for the identification and implementation of a long‐term solution to damage caused by aquatic borers to The Lucy Evans Baylands Interpretive Center’s boardwalk. The project received permits from the San Francisco Bay Regional Water Quality Control Board, Bay Conservation and Development Commission, United States Fish and Wildlife Services, and United States Army Corps of Engineers. The project was issued to bid in April 2024 and Council approved a construction contract in June 2024. Due to the biological restrictions, project construction will occur outside of the Ridgeway’s rail nesting season between September 1, 2024 and January 31, 2025. City Facilities Assessment and Record Plan Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $288,961 $333,134 Public Works Construction Summer 2024 Project Status: The Kitchell Report in 2008 summarized the last City‐wide facility condition assessment. A new facility condition assessment is warranted per the City’s APWA reaccreditation requirements. All City facilities will Buildings and Facilities Projects – Page 1 of 12 Buildings and Facilities Projects Status as of June 2024 Management System (PE‐20002) be assessed to bring current the “catch‐up” and “keep up” costs. In addition, an electrification assessment will be included to help the City reach its sustainability goals for 2030. Council awarded the contract in April 2022. All City facilities have been assessed for the Condition and Electrification assessments. The data is currently being evaluated in the new Capital Predictor software to generate reports detailing the current “catch‐up” and “keep up” costs, while staff continues to evaluate the draft reports. A detailed list of buildings for electrification is being analyzed to determine prioritization for replacements. The project is 98% complete and staff are evaluating the final reports. An Electronic Records Management System will be implemented through TE‐13004 utilizing Laserfiche as the sole repository for Public Works. City Hall Space Planning Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $52,615 $650,907 Public Works Design Winter 2024 (PE‐19000)Project Status: This project involves space planning to determine future workgroup space needs and programming for the City Hall office building focused primarily on the areas that will be vacated once the new Public Safety Building is complete and occupied. The project will include preliminary design of the space following the initial feasibility phase. Staff anticipates entering into a contract for initial space planning services in fall 2024. Civic Center Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Electrical Upgrade & EV Charger Installation $656,289 $2,141,929 Public Works Design Spring 2025 Project Status: This project installed EV chargers in existing downtown garages and will replace the aging Civic Center electrical switchgear and motor control centers. EV charger construction at the Civic Center, Bryant Street garage and Webster Street garage was completed in December 2021. A contract was awarded in June 2021 for the design of the Civic Center switchgear replacement and is currently at the 90 percent design stage. Lead times on switch gear are now taking 12 months, so the project completion date has been extended. The structural analysis design of the switchgear area and its permit set were completed in winter 2024. (PE‐17010) Buildings and Facilities Projects – Page 2 of 12 Buildings and Facilities Projects Status as of June 2024 Civic Center Fire Life Safety Upgrades Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $904,269 $1,031,443 Public Works Construction Fall 2024 (PE‐18016)Project Status: This project will assess, update, and replace the Civic Center fire alarm system. The fire life safety system is approaching the end of its useful life. The fire alarm panel and associated equipment need an upgrade to meet current code requirements. The award of a design‐build contract was approved by Council in June 2021. Construction in the main tower areas is nearly complete. The ground floor and the garage levels are yet to be completed. The project completion date has been extended to fall 2024 due to ongoing testing issues. Civic Center Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Waterproofing Study and Repairs (PE‐15020) $798,460 $1,153,021 Public Works Construction Fall 2025 Project Status: This project includes a condition assessment of the Civic Center plaza deck structural system. In 2016, RDH Building Science, Inc. determined that the expansion joint on the plaza could be repaired and that replacing the waterproof coatings on the inside of the plaza perimeter planter boxes was needed. Repair of the waterproofing joint in front of City Hall was completed in winter 2023. Staff will start procurement for a design contract in fall 2024 focused on the repair of the perimeter planter boxes. Cubberley Gym Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion HVAC Replacement $0 (CB‐24000) $809,297 Public Works Design Spring 2026 Project Status: The existing heating system in Cubberley Gyms A & B is original to the building, which was constructed in the mid‐1950s. The system is currently not functioning because multiple leaks have developed in the steel hot water piping, which is in the walls and under the floor. These leaks contributed (in addition to a domestic water main supply leak) to significant water damage in the walls, floors, and crawl spaces of the gyms. Asbestos and mold were remediated from the under‐floor crawl space. All the old heating units and piping were removed from the ceilings in both gyms. The next step is to hire a consultant to create design drawings for a new heating system. Due to staff workload constraints, design will begin in early FY 2025. Buildings and Facilities Projects – Page 3 of 12 Buildings and Facilities Projects Status as of June 2024 Electrification of City Facilities (PE‐24001) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $204,162 $1,017,599 Public Works Pre‐Design Fall 2030 Project Status: This project will evaluate feasibility, prepare designs, and implement construction for the electrification of fossil fuel consuming building systems in coordination with the Building Systems Improvements project (PF‐01003). The City Facility Electrification assessment report will act as a workplan to implement the electrification of City facilities. An RFP for an on‐call task order consultant for all City facilities requiring electrification will be issued in fall 2024. Facilities will be electrified in order by priorities set by the Electrification Assessment to facilitate reaching the S/CAP goals. Fire Station 4 Replacement (PE‐18004) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,860,907 $15,329,842 Public Works Design Winter 2026 Project Status: This project will replace Fire Station #4 at the corner of Middlefield Road and East Meadow Drive. The design consultant has completed design development and received Planning approval for the project in November 2023. A construction management contract was awarded in December 2023. Project has been submitted for building permit review, and Architect is preparing resubmittal. CityStaff is preparing to solicit for pre‐qualification bids later this summer with a construction bid anticipated in fall 2024. City will submit the temporary station project for building permit review in summer 2024. Fire Training Facility Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Replacement $459 $55,293 Fire Department Pre‐Design Summer 2026 (FD‐24000)Project Status: This project will identify an appropriate site and construct a new fire training facility in Palo Alto. This will be the first City‐owned and City‐maintained permanent fire training facility, and it will allow training to be conducted within City limits and therefore reduce the downtime associated with the need for staff to travel for training and when responding to calls. Buildings and Facilities Projects – Page 4 of 12 Buildings and Facilities Projects Status as of June 2024 Homekey Facilities Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion (PE‐24005)$2,218,979 $4,500,000 Public Works Construction Spring 2025 Project Status: This project involves relocating the City of Palo Alto (City) GreenWaste facility from its current site on one portion of 1237 San Antonio Road to the rear portion of the same site as a result of adding the Homekey Palo Alto interim housing shelter. Homekey Palo Alto will be operated by LifeMoves who will provide intensive, customized case management for clients including counseling, employment and housing search services with the goal of paving a dignified path to self‐sufficiency. Devcon Construction began construction in October 2023. Site excavation, grading and underground utility infrastructure work has been completed. Building utilities, curb pouring, concrete form work and rebar placement for the building foundation is currently in progress. Construction is anticipated to be completed in early 2025. JMZ Renovation Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion (AC‐18001)$4,172,284 $4,966,603 Community Services Construction Summer 2025 Project Status: This project provides for the temporary relocation of the Junior Museum and Zoo and the construction of a new facility and exhibits. The California Dinosaur Garden exhibit, which is partially funded by a reimbursable federal grant, was opened with a special ribbon cutting ceremony in October 2023. Funds associated with the grant are expended against the project until reimbursements are made. Reimbursement has been submitted and expected in the first quarter of FY 2025. A portion of the CIP was extended through FY 2025 to complete the list of remediations and equipment not purchased in FY 2024 due to staffing shortages. Completion is expected in July 2025. Library Automated Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Material Handling $205,811 $1,085,100 Public Works Construction Winter 2025 (LB‐21000)Project Status: This project is to provide the design and construction of three new Automated Material Handling (AMH) Systems for the College Terrace, Children’s, and Downtown Libraries. Due to space constraints and limited functionality, only the Children’s Library installation will be proceeding. AMH systems efficiently sort returned Buildings and Facilities Projects – Page 5 of 12 Buildings and Facilities Projects Status as of June 2024 library materials based on the Radio Frequency Identification Devices (RFID) on the materials. Building permit has been issued. Project will be out to bid in summer 2024, and construction contract award is anticipated for fall 2024. Lucie Stern Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Community Theatre $28,548 $2,756,854 Public Works Pre‐Design Fall 2026 Mechanical Equipment Replacement (PE‐24002) Project Status: This project will upgrade and replace the Heating Ventilation and Air Conditioning (HVAC) system at the Lucie Stern Community Theatre. As a first step, the project will include a detailed feasibility study to determine if natural gas‐powered equipment in the facility can be electrified per the recommended results of the City‐wide electrification assessment. Lucie Stern Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Community Theatre $0 $221,169 Community Services Pre‐Design Fall 2026 Fire Curtain (AC‐24001) Project Status: This project will replace the fire curtain and its associated rigging at the Lucie Stern Community Theatre. The fire curtain work will be coordinated with the Theatrical and House Lighting System Replacement Project (PE‐24003). Lucie Stern Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Community Theatre $0 $116,113 Community Services Construction Summer 2024 Stage Project Status: This project will refurbish the most heavily used components of the stage rigging system at the Lucie Stern Community Theatre. The construction contract was approved by City Council on June 3, 2024. Work is scheduled to start in July 2024. Rigging System Refurbishment (AC‐24000) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $21,177 $372,252 Public Works Design Fall 2026 Buildings and Facilities Projects – Page 6 of 12 Buildings and Facilities Projects Status as of June 2024 Lucie Stern Community Theatre back‐stage work areas, the performance stage, and audience areas. The design of the new system is complete Theatrical and bid ready. The timing of this project will coincide with the Community Theatre Mechanical Equipment Project Status: This project will upgrade and replace lighting systems at the Lucie Stern Community Theatre for and House Lighting Replacement (PE‐24002). System Replacement (PE‐24003) Mitchell Park Library Repair (PE‐24006) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $15,083 $250,000 Public Works Design Spring 2025 Project Status: This project will repair the damage caused by a vehicular accident in January 2023. A vehicle ran into the north wall of the Mitchell Park Library near the center of the building. The car impacted an area of the stone cladding on cold‐formed steel studs, causing the cladding to fall from the wall and the wall to bulge into the building’s interior. Architectural and structural survey and reports were completed. The stone cladding wall requires replacement, but the structural steel frame was not damaged. The design contract is being finalized with Purchasing. Construction to repair the wall is estimated to begin in late fall 2024. Municipal Service Center Lighting, Mechanical, and Electrical Improvements (PF‐16006) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,195,776 $8,786,825 Public Works Design Spring 2026 Project Status: This project replaces original mechanical, electrical, and lighting systems installed in 1966. It also includes design and construction for office renovations for the Zero Waste group. The design is 100% complete and the planning permit was approved in spring 2024. The project should be out to bid in the first half of FY 2025. New Downtown Parking Garage Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,440,311 $7,488,904 Public Works Design TBD Buildings and Facilities Projects – Page 7 of 12 Buildings and Facilities Projects Status as of June 2024 (PE‐15007)Project Status: This project was intended to provide a new parking structure in the University Avenue commercial area at existing Parking Lot D at the corner of Hamilton Avenue and Waverley Street. As part of the FY 2021 budget strategy, all Capital Improvement Fund funding has been removed and only the downtown parking in‐lieu fee funding remains for this project. In December 2021, Council directed staff to look at the feasibility of partnering with a private entity to develop new parking using downtown in‐lieu parking fees in conjunction with housing or other uses, including the use of City surface lots or privately held parcels. A Request for Information was issued in December 2022 and staff reviewed proposals and held interviews in May 2023. Council gave direction to staff in December 2023 to advance the project in conjunction with advancement of affordable housing in the Downtown area. New Public Safety Building Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $113,275,793 $ 118,137,971 Public Works Construction Summer 2024 (PE‐15001)Project Status: This project will provide a new, modern Public Safety Building (PSB) that will meet essential services standards and the current and future needs of the public safety departments. The PSB and new garage in the California Avenue business district are now an integrated project and both are part of the 2014 Council Infrastructure Plan. Construction on the PSB started in March 2021 and will continue into summer 2024. Permanent power was completed in September 2023. The communications monopole was installed in October 2023. The Tier 4 emergency generator has been started up. Sitework, landscape and the building exterior is nearly complete. Remaining construction activities and City fixtures, furniture and equipment are progressing on a schedule to allow public safety departments a phased move‐in to the new building starting in September 2024. Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $663,022 $1,247,566 Public Works Construction September 2024 Buildings and Facilities Projects – Page 8 of 12 Buildings and Facilities Projects Status as of June 2024 Performing Arts Venues Seat Replacement (AC‐18000) Project Status: This project will replace all the seats in the Community and Children’s Theatres. Staff hired a consultant to design the seat replacements and ADA upgrades for the Children’s Theatre portion of the project. The Children’s Theatre seats replacement was completed in November 2022. A contract for the design of the Community Theatre was issued in June 2023. Council approved a construction contract on April 22, 2024, with project completion expected in fall 2024. Rinconada Pool Family Changing Room Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $34,922 $1,544,303 Public Works Design Spring 2025 Project Status: The project will construct a gender‐neutral restroom and family changing facility that is compliant with the Americans With Disabilities Act (ADA) at the Rinconada Pool. The facility will include two separate rooms, each consisting of a toilet, sink, shower, and child/adult changing station. The facility will provide community members who have special needs, and individuals who require privacy, an accessible space for changing and personal hygiene. A design contract is currently being prepared. (PE‐24004) Roth Building Rehabilitation Phase 1 Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $6,927,119 $11,848,825 Public Works Construction Fall 2024 Project Status: This project provides funding for Phase 1 of the rehabilitation and build‐out of the Roth Building facility. Phase I will make the building suitable for occupancy, also known as a “warm shell.” Phase II of the rehabilitation includes the interior build‐out of the museum and exhibits, readying the facility to welcome visitors, and will be funded by the Palo Alto History Museum (PAHM). A Tenant Work Letter was approved by Council in April 2023 and construction is underway including underground utilities, roof, demolition, and abatement. The project is currently 50% complete. (PF‐23001) Recurring Projects Buildings and Facilities Projects – Page 9 of 12 Buildings and Facilities Projects Status as of June 2024 Americans With Disabilities Act Compliance Prior Year Actuals $0 Current Year Budget $884,677 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project provides accessibility upgrades to City facilities and equipment. It includes continued funding for improvements such as path of travel, restrooms, drinking fountains, and counters. An updated ADA Transition Plan was adopted by Council in June 2021. Staff is waiting to solicit for new software that will allow staff to identify and log new barriers, track grievances from the public, and update the ADA Transition Plan Report. (PF‐93009) Building Systems Prior Year Actuals Current Year Budget $932,317 Implementing Department Project Phase Project Completion Public Works N/A RecurringImprovements$77,759 (PF‐01003)Project Status: This project provides electrical, mechanical, plumbing, structural, and security upgrades for City facilities. Construction for the Lucie Stern Community Theatre Automated Logic Controls Upgrade project started in June 2024 and is scheduled to be completed in summer 2024. City Facility Parking Lot Maintenance (PE‐09003) Prior Year Actuals $0 Current Year Budget $385,941 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project repairs, resurfaces, or reconstructs parking lots and walkways at various City facilities, including restriping and signage. The FY 2024 Overlay Project was awarded by Council in March 2024, and includes the resurfacing of Hopkins Newell Tennis Court Parking Lot, Cubberley Community Center West and South‐East lots and Foothills Nature Preserve Water Tower Lots 1 & 2. All parking lot paving work was completed in the second half of FY 2024 with the exception of Cubberley Community Center which is expected to be completed in summer 2024. Cubberley Repairs Prior Years Actuals (CB‐17001) $309,506 Current Year Budget $201,107 Implementing Department Project Phase Project Completion Public Works N/A Recurring Buildings and Facilities Projects – Page 10 of 12 Buildings and Facilities Projects Status as of June 2024 Project Status: This project is for general maintenance needs of the Cubberley campus. Gym B is scheduled for floor sanding, game line repainting, and refinishing in July 2024. One third of the hardwood flooring and subflooring has been removed in Gym A due to water damage. A solicitation to replace the flooring is targeted for fall 2024. Cubberley Roof Replacements (CB‐16002) Prior Year Actuals $27,039 Current Year Budget $2,835,922 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project replaces existing roofs at Cubberley Community Center. Bid documents are with Purchasing for the Pavilion flat roof and staff are targeting early fall 2024 for construction. Electric Charger Infrastructure Installation Prior Year Actuals $63,243 Current Year Budget $307,519 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project designs and installs electric vehicle chargers at various City facilities. The primary use of the electric vehicle chargers will be for City fleet vehicles. The design to install six new chargers on Level C of the City Hall parking garage is underway. A contractor has been selected for this project and construction is scheduled to start in July 2024. (PF‐23000) Facility Interior Finishes Prior Year Actuals $83,323 Current Year Budget $735,167 Implementing Department Project Phase Project Completion Public Works N/A Recurring Replacement (PF‐02022) Project Status: This project improves the interior finishes of City facilities, including flooring, walls, cabinets, paint, lighting, ceiling tiles, soundproofing, and fixed office furniture, doors, windows, and associated fire/life safety, mechanical, electrical and plumbing code compliance requirements. Design of modifications to the Revenue Collections office area on Level G has restarted and is anticipated to be in construction in winter 2024. New carpet has been selected for the Children’s Library with work scheduled for early 2025. Police Video Recording Prior Years Actuals $10,751 Current Year Budget Implementing Department Project Phase Project Completion $132,700 Police Department N/A Recurring Buildings and Facilities Projects – Page 11 of 12 Buildings and Facilities Projects Status as of June 2024 Systems Replacement (PD‐20000) Project Status: This project maintains the Palo Alto Police Department video recording systems used to record events in the field with up to five in‐car cameras as well as body‐worn cameras (BWC). In FY 2024, the City solicited for a new vendor to include the in‐car and BWC systems and newly added fixed interrogation systems in the PSB. A vendor was selected and the transition is anticipated to begin in fall 2025. Roofing Replacement (PF‐00006) Prior Year Actuals $447,681 Current Year Budget $2,022,410 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project replaces existing roofs at City facilities that have outlived their useful lifespans. The Animal Shelter roof recoating has been delayed due to roof modifications required for the proposed kennel remodel. Phase 2 of the Lucie Stern Community Center roof replacement project is scheduled to begin by fall 2024. University Avenue Prior Year Actuals Current Year Budget $149,318 Implementing Department Project Phase Project Completion Public Works N/A RecurringParking$0 Improvements (PF‐14003) Project Status: This project maintains parking lots and parking structures within the University Avenue Downtown Business Parking District. There is no work planned for parking improvements in the second half of FY 2024. Buildings and Facilities Projects – Page 12 of 12 Parks and Open Space Projects Status as of June 2024 One‐Time Projects Baylands Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Comprehensive $386,401 $434,059 Community Services Design Spring 2025 Conservation Plan (PG‐17000) Project Status: This project provides funding for a conservation plan that will examine the native vegetation, wildlife habitat resources, and wildlife‐appropriate public access for the entire Baylands, including Byxbee Park. This plan will provide needed information on best areas to maintain wildlife habitat and appropriate areas to develop trails or other recreation amenities; provide a design overlay for appropriate types and locations of public art in the Baylands; and design interpretive messaging throughout the Baylands. The plan seeks to optimize opportunities for low impact recreation ensuring that these are compatible with the Baylands Master Plan direction for passive use of the nature preserve. The Conservation Plan will also provide input to the Byxbee Park Completion project. The Parks and Recreation Commission has created an Ad Hoc Committee to work with staff on this project. The next steps are to review the draft plan to identify gaps and highlight where updates are required. Baylands Nature Preserve $14,866 Prior Years Actuals Total Project Budget Implementing Department $132,701 Community Services Project Phase Project Completion Completed Spring 2024 Entrance Gate (OS‐24000) Project Status: This project installed a new automated gate at the Baylands Nature Preserve main entrance. The existing gate was manually opened and closed by staff each day for public access. The scope of work included an electrical transformer, trenching, wiring, and gate automation equipment. The project was substantially completed in June 2024. Boulware Park Improvements (PE‐17005) Prior Years Actuals Total Project Budget Implementing Department $2,937,729 $6,261,627 Public Works Project Status: This park renovation project was initially planned in FY 2018 but was postponed due to project priorities and potential purchase of the adjacent AT&T lot located at 3350 Birch Street. In fall 2019, the lot was purchased by the City. In response to the purchase, the City utilized the funding for the initial renovation project for preliminary design and outreach for both the existing park and the newly purchased park land. A Park Improvement Ordinance for Project Phase Project Completion Construction Fall 2024 Parks and Open Space Projects – Page 1 of 9 Parks and Open Space Projects Status as of June 2024 the improvements was adopted by the City Council in October 2021. A construction contract was awarded in June 2023 and the project construction began in August 2023. Current site work is 50% complete and all underground utilities have been installed. The project is scheduled to be completed by fall 2024. Byxbee Park Completion (PE‐18006) Prior Years Actuals Total Project Budget Implementing Department $368,192 $3,699,189 Public Works Project Phase Project Completion Pre‐Design Summer 2026 Project Status: This project allows for the remaining improvements to Byxbee Park that follow the completion of the landfill capping work. The Baylands Comprehensive Conservation Plan (BCCP), which is currently undergoing CEQA analysis, will include recommendations on the scope of the Byxbee Park project. The BCCP and the conceptual plan for Byxbee Park need additional outreach and review. The project has been moved to FY 2025 due to staffing constraints and pending the Baylands Comprehensive Conservation Plan. Cameron Park Improvements (PG‐14002) Prior Years Actuals Total Project Budget Implementing Department $205,627 $538,898 Community Services Project Phase Project Completion Construction Summer 2024 Project Status: This project upgrades and renovates safety and accessibility features at Cameron Park with a primary focus on the park playground. A park improvement ordinance was approved by Council in February 2021. Bids were opened in June 2023. The construction contract was awarded by Council in September 2023. Construction began in June 2024 with an estimated completion in August 2024. Cubberley Field Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Construction Fall 2024Restroom$776,349 $1,398,526 Public Works (CB‐17002)Project Status: This project will install a new restroom in the sports field area of the Cubberley Community Center. Design for the project started in fall 2018 along with public outreach. Staff assessed the feasibility of on‐site utilities connection and reviewed design and specifications of a prefabricated restroom building to incorporate in the final design for ARB review. Staff conducted outreach meetings and coordination for the potential location of the proposed restroom. In June 2023, Council approved a purchase order with the Public Restroom Company for a four‐stall Parks and Open Space Projects – Page 2 of 9 Parks and Open Space Projects Status as of June 2024 prefabricated restroom building. The Public Restroom Company obtained the state of California approval of the building design and City’s building permit was received in April 2024. The IFB for construction occurred in June 2024. Council award of construction for site work is anticipated in September 2024. The project is anticipated to be completed by fall 2024. El Camino Park Turf Prior Years Actuals Total Project Budget Implementing Department $ 40,000 $931,121 Community Services Project Phase Project Completion Design Summer 2025 Replacement (PG‐24000) Project Status: This project has been paused and City Council has provided direction to use this CIP funding to complete a comprehensive study to compare synthetic turf fields to natural grass fields assessing: environmental and health impacts, field utilization capacity, and capital and operating costs required for both types of fields. Foothills Nature Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Pre‐Design Summer 2025Preserve$0 $255,427 Public Works Boronda Lake Dock Replacement (OS‐18000) Project Status: This project is a refurbishment of the existing dock. The current condition of the dock is declining and now requires a complete replacement of the dock with new decking, ramp, floats, and pilings. Staff is examining if CEQA permitting would be required for this project. Foothills Nature Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Design Spring 2025Preserve Dam Seepage $42,170 $88,591 Public Works Project Status: This project will study a location of historic seepage from the Foothills Nature Preserve Dam at the sharp bend in the road on the face of the dam and will locate and investigate the pipe and trench backfill material. The seepage is very minor, but it appears to be slowly worsening. The source of the seepage is suspected to be the trench backfill around the pipe that returns shallow groundwater to Boronda Lake. Staff continues to monitor and investigate the seepage per the Department of Water Resources Division of Safety of Dams (DSOD) inspections and recommendations. Staff completed camera inspections of the underdrain pipes to identify potential obstructions and Investigation and Repairs (PE‐20000) Parks and Open Space Projects – Page 3 of 9 Parks and Open Space Projects Status as of June 2024 leakage issues. Per the DSOD recommendations, staff is in the process of hiring a hydraulic engineering firm to design and install a weir to quantify and analyze the seepage flows. Foothills Nature Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Design Summer 2028Preserve$246,859 $3,632,918 Public Works Improvements (PE‐21000) Project Status: This project will repair the bridge to Sunfish Island, complete the design and permitting to replace the footbridge in Los Trancos Valley, replace the grade control structures along Buckeye Creek, provide new split rail fencing to protect sensitive areas, new pedestrian pathways to keep park visitors safe while walking along the park road, and improvements to some of the existing parking areas to make them safer and more efficient. Staff completed a concept plan design and initiated the minor Architectural Review Board process for the pathways, fencing and parking improvements in winter 2024. The repair of Sunfish Island Bridge was completed in March 2024 separately from the larger scope of work under ARB review. Council awarded a professional services contract for additional outreach, a detailed design and bid package preparation for pathways, fencing and parking improvements in spring 2024. The replacement of the footbridge in Los Trancos Valley and the grade control structures along Buckeye Creek have been moved to FY 2027 and FY 2028 due to staffing constraints. Golf Course Net Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Pre‐Design Summer 2026and Artificial Turf $0 $932,167 Community Services Project Status: This project will remove and replace the golf course driving range netting and synthetic turf. This project is being delayed as additional ball retention needs are being assessed throughout the golf course and development of a potential long‐term partnership with the First Tee of Silicon Valley for driving range and practice facility improvements is under consideration. Replacement (PG‐18000) Peers Park Improvements Prior Years Actuals Total Project Budget Implementing Department $0 $293,050 Community Services Project Phase Project Completion Pre‐Design Summer 2028 Parks and Open Space Projects – Page 4 of 9 Parks and Open Space Projects Status as of June 2024 (PG‐14001)Project Status: This project will upgrade and renovate the irrigation system and turf, repair playground surfacing, replace dog park surfacing, and upgrade drinking fountains. This project has been pushed out to FY 2028 due to a reprioritization of Parks projects to address overall funds availability and CIP projects with more urgent needs. Ramos Park Improvements (PG‐14000) Prior Years Actuals Total Project Budget Implementing Department $279,354 $935,035 Community Services Project Status: This project replaces the playground equipment at Ramos Park. Council awarded a cooperative agreement with Ross Recreation in June 2024 to replace and install the playground equipment for both Ramos Park and Robles Park. Work is anticipated to be completed by spring 2025. Project Phase Project Completion Construction Spring 2025 Rinconada Park Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Construction Summer 2024Improvements$5,447,216 $9,979,716 Public Works (PE‐08001)Project Status: This project provides upgrades to safety, site amenities, playground facilities, a new restroom, irrigation, drainage, and ADA accessibility improvements at Rinconada Park. These improvements were identified in the Rinconada Long Range Plan (LRP). Phase 1 park improvements to the western half of the park were completed in spring 2022. A new restroom that was removed from the Phase 1 park improvements in FY 2022 is currently in design. In April 2023, Council approved a purchase order with the Public Restroom Company for a two‐stall prefabricated restroom building. Staff completed design and obtained a building permit for site work and restroom. On December 18, 2023, Council awarded a construction contract for restroom site work. The Public Restroom Company installed the restroom building on site in June 2024. Remaining site work and utilities connections would be completed by the City’s site work contractor. All work related to the new restroom is anticipated to be completed by July 2024. According to the LRP, future improvement phases will include improvements to the eastern half of the park by FY 2028 including pathway improvements, ADA upgrades, planting, irrigation, lighting, and site furnishings. Parks and Open Space Projects – Page 5 of 9 Parks and Open Space Projects Status as of June 2024 Robles Park Improvements (PE‐18015) Prior Years Actuals Total Project Budget Implementing Department $161,765 $507,817 Public Works Project Phase Project Completion Design Winter 2025 Project Status: This project will replace playground equipment. A community meeting was held in September 2023 with an additional community meeting conducted in March 2024 to obtain community input. Staff continues to work with the playground manufacturer, Ross Recreation to provide design for playground equipment under a cooperative agreement for both Robles Park and Ramos Park. Upon community buy‐in and staff’s review, the playground fabrication should be completed within six months for installation by winter 2025. Recurring Projects Art in Public Spaces Prior Year Actuals Current Year Budget Implementing Department Project Phase $189,175 $1,704,337 Community Services N/A Project Completion Recurring (AC‐86017)Project Status: This project provides the ongoing temporary and permanent artworks throughout the City. The second half of the FY 2024 budget is supporting three new artworks installed at the Public Safety Building, a new mural at Cubberley, artwork at Fire Stations 4 and 5, and three murals downtown. Twenty utility box projects are in design to be painted throughout the City. Projects in process include the ongoing King Artist‐in‐Residence with artist Alma Landeta, including the development of temporary artwork for King Plaza, and artwork for Boulware Park. Athletic Courts Resurfacing (PG‐06001) Prior Year Actuals Current Year Budget Implementing Department Project Phase $22,294 $525,348 Community Services N/A Project Status: This project repairs and resurfaces athletic courts in various Palo Alto parks. Staff is currently working with Purchasing to bid for the reconfiguration and resurfacing of the Greer Park basketball courts and estimated for construction to start in fall 2024. The Terman Park and Fletcher Middle School basketball courts were resurfaced in spring 2024. Project Completion Recurring Parks and Open Space Projects – Page 6 of 9 Parks and Open Space Projects Status as of June 2024 Benches, Signage, Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Walkways, Perimeter Landscaping (PG‐06003) $513,204 $440,938 Community Services N/A Recurring Project Status: This project restores and replaces existing benches, signage, fencing, walkways, and landscaping at various City facilities. The Golf Course fence extension in the youth practice area was completed in winter 2024. The regrading and restoration of the Hoover Park perimeter decomposed granite pathways, the Greer Park Skatepark parking analysis was completed, the pickleball picnic site improvements at Mitchell Park which included the installation of bike racks, tree grates, and waste receptacles were all completed in spring 2024. The Mitchell Park directory signage design was completed in spring 2024, and the fabrication and installation are estimated for completion in summer 2024. Dog Park Prior Year Actuals Current Year Budget Implementing Department Project Phase $30,278 $325,671 Community Services N/A Project Completion RecurringInstallation and Renovation (PG‐18001) Project Status: This project enables construction of dog parks at various City parks and facilities for constructing new or renovating existing dog parks. A new dog park will be added with the Boulware Park expansion project for which construction started in summer 2023. Council approved a Park Improvement Ordinance in September 2022 for expansion of the Mitchell Park Dog Park. Mitchell Dog Park installation and expansion will begin in July 2024 and be completed by October 2024. Off‐Road Pathway Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Resurfacing and Repair (OS‐09001) $22,075 $267,876 Public Works N/A Recurring Project Status: This project resurfaces failing and broken pathways within the City. Pathways are chosen based on inspections and resident requests. This project included discussion of the conceptual repair design and permitting approach with the relevant regulatory agencies that would allow for repairs to the existing Baylands Boardwalk pilings. No pathway work was done in the second half of FY 2024. Parks and Open Space Projects – Page 7 of 9 Parks and Open Space Projects Status as of June 2024 Open Space Lakes Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion and Pond $27,900 $91,855 Community Services N/A Recurring Maintenance (OS‐00002) Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat and recreational safety and to meet State Division of Safety of Dams requirements. Year three of an existing three‐ year maintenance contract for removal of aquatic vegetation in Boronda Lake was completed in spring 2024. A new three‐year contract awarded in spring 2024 will begin in FY 2025. Open Space Trails Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion and Amenities $360,820 $276,462 Community Services N/A Recurring (OS‐00001)Project Status: This project restores unpaved trails, fences, picnic areas, and campgrounds at Foothills, Baylands, and Pearson‐Arastradero Nature Preserves. Work performed in winter 2024 included the reconstruction of five miles of the Panorama trail at the Foothills Nature Preserve. Work performed in spring 2024 included sixty acres of firebreak maintenance at Trappers Fire Road, Pony Tracks Fire Road, Charlie Brown Fire Road maintenance of twenty‐five miles of trail tread, and maintenance of twenty‐five miles of trailside vegetation in the Foothills Nature Preserve. In spring 2024, the reconstruction of the Meadowlark trail was completed at the Arastradero Preserve. Parks and Open Space Emergency Repairs Prior Year Actuals Current Year Budget Implementing Department Project Phase $192,025 $367,187 Community Services N/A Project Completion Recurring Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park amenities, and play equipment in the event of storms, fire, vandalism or structural failures. In winter 2024, the replacement of two culverts along Las Trampas Valley Road within Foothills Nature Preserve were completed. In winter 2024, emergency repairs to chain link fencing was completed at the Cubberley Community Center tennis court perimeter fencing, and to the Mitchell Park tennis court perimeter fencing due to damage caused by winter storms. In spring 2024 the Robles Park picnic area were completed due to fire damage. The Robles Park repairs project included the removal and disposal of fire damaged equipment and repairs to the wooden picnic arbor and wooden picnic table. (PG‐09002) Parks and Open Space Projects – Page 8 of 9 Parks and Open Space Projects Status as of June 2024 Park Restroom Installation Prior Years Actuals Current Year Budget Implementing Department Project Phase $485,995 $893,846 Community Services N/A Project Completion Recurring (PG‐19000)Project Status: This project installs new restrooms at City parks that currently do not have restroom facilities. City Council approved a Park Improvement Ordinance for Ramos Park. In April 2023, Council approved a purchase order with the Public Restroom Company for a two‐stall prefabricated restroom building at Ramos Park. Staff completed design and obtained a building permit for site work and restroom. On December 18, 2023, Council awarded a construction contract for restroom site work. The Public Restroom Company installed the restroom building on site in June 2024. Remaining site work and utilities connections will be completed by the City’s site work contractor in July 2024. Parks and Open Space Projects – Page 9 of 9 Streets and Sidewalks Projects Status as of June 2024 One‐Time Projects California Avenue Prior Years Actuals District Gateway $26,943 Total Project Budget $150,321 Implementing Department Project Phase Project Completion Public Works Design Summer 2025 Signs (PE‐17004) Project Status: This project includes the design and replacement of two existing gateway signs for the California Avenue business district. Initial public outreach was completed in winter 2021. The California Avenue District Gateway Signs project is in the next phase of improvements following the California Avenue Streetscape update and near‐term improvements. The signage is anticipated to be replaced in fall 2024. Newell Road San Prior Years Actuals $3,957,812 Total Project Budget $23,204,651 Implementing Department Project Phase Project Completion Public Works Design Spring 2026 Francisquito Creek Bridge Replacement (PE‐12011) Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500 cubic feet per second, and to improve safety for vehicular, bicycle, and pedestrian traffic. The project is being closely coordinated with the City of East Palo Alto, Valley Water, and San Francisquito Creek Joint Powers Authority (SFCJPA). In the second half of FY 2024, staff acquired the eight easements needed to complete the project and obtained a permit from Regional Water Quality Control Board and a draft permit from California Department of Fish and Wildlife along with encroachment permits from East Palo Alto and Santa Clara Valley Water District. Staff and consultants worked with PG&E, Comcast, AT&T, City of East Palo Alto Water and City of Palo Alto Utilities on the Utility Relocation letters needed for Caltrans’ review and approval. The right‐of‐way acquisition and permitting is anticipated to be completed by the end of summer 2024. Staff also submitted a request to Caltrans to authorize the start of the construction phase with the current construction funding that was approved previously. Once approved, staff will solicit bids for construction in fall 2024 with construction to follow. Prior Years Actuals $8,799 Total Project Budget $276,384 Implementing Department Project Phase Project Completion Public Works Design Fall 2025 Streets and Sidewalks Projects – Page 1 of 5 Streets and Sidewalks Projects Status as of June 2024 Street Lights Condition Assessment (PE‐13014) Project Status: This project will assess the condition of the City’s streetlight system. The assessment will include an inventory of the entire lighting system, including age and condition of conduit, wiring, streetlight poles, foundations, luminaires, and lighting coverage. The project will also determine the inspection, maintenance, repair, and rehabilitation necessary to prolong the life of the City’s streetlight system. This project has been moved to FY 2025 due to staffing constraints. Recurring Projects City Bridge Improvements (PE‐20001) Prior Year Actuals Current Year Budget $200,258 $786,919 Implementing Department Project Phase Project Completion Public Works N/A Recurring Project Status: This project includes bridge inspections, maintenance, repair, and an improvement program over the next five years. This program will include on‐going inspections to report physical changes to the structures, recommendations for work to be done, and additional information to meet functional and structural standards in accordance with industry standards. Staff hired an on‐call structural engineering firm to assist with the bridge inspection and repair program. Staff completed design and bidding for repairs of six bridges identified for repairs in winter 2023. Due to the lack of competitive bids, staff rebid the project in December 2023. A construction contract was awarded by Council in March 2024. Bridge repair work is anticipated to begin in late summer 2024. Staff and City’s consultant continue to make progress on recurring inspections of City bridge structures. Curb and Gutter Repairs Prior Year Actuals Current Year Budget $1,519 $241,020 Implementing Department Public Works Project Phase Project Completion N/A Recurring (PO‐12001)Project Status: This project repairs curbs and gutters uplifted by tree roots. Funding for FY 2023 has been carried over into FY 2024 for a larger curb and gutter repairs project. The project will focus on Downtown North and University South neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middlefield Road) in addition to addressing hot spot locations from 311 requests. Approximately 2,136 linear feet of curbs and gutters are included Streets and Sidewalks Projects – Page 2 of 5 Streets and Sidewalks Projects Status as of June 2024 in the FY 2024 Sidewalk Repair ADA Improvement Project. Council approved the construction contract on June 10, 2024 and a Notice to Proceed with construction is planned for July 2024. San Francisquito Creek Joint Powers Authority Ongoing Creek Projects Prior Year Actuals Current Year Budget $108,514 $119,374 Implementing Department Public Works Project Phase Project Completion N/A Recurring Project Status: This project provides funding for studies and completion of the design for the San Francisquito Creek Joint Powers Authority (JPA) upstream project including channel widening and Continuing Authority Program Section 205 (CAP 205) study. The project design is temporarily on hold due to the recent significant storm events and flooding that occurred on December 31, 2022. The JPA and Valley Water are re‐evaluating the creek capacity and hydraulic limitations of the channel to determine how to proceed with the design. In FY 2024 JPA awarded a contract with WRA Environmental Consultants to analyze the creek hydraulics and the improvement alternatives that could reduce flooding. The Master Service Agreement includes design and implementation of Reach 2 project elements. (PE‐22000) Sidewalk Repairs Prior Year Actuals Current Year Budget Implementing Department Public Works Project Phase Project Completion N/A Recurring(PO‐89003)$1,265,080 $2,515,608 Project Status: This project repairs and replaces broken and uplifted sidewalks. The program completed all twenty‐ three sidewalk districts in 2017, a 30‐year (1986–2017) sidewalk repair district cycle. Council approved a sidewalk assessment contract in November 2017 to evaluate the sidewalk program and assess potential improvements to the current district‐based program. Funding for FY 2023 has been carried over into FY 2024 for a larger sidewalk project. The Project will focus on sidewalk repairs (PO‐89003) and curb and gutter repairs (PO‐12001) in the Downtown Professorville neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middlefield Road). Council approved the construction contract on June 10, 2024 and a Notice to Proceed with construction is planned for July 2024. The Project aims to replace approximately 18,468 square feet of concrete sidewalk, 3,759 square feet of driveways, install eighty‐four new curb ramps, and retrofit thirty‐three existing curb ramps with truncated domes to conform to the Americans with Disabilities Act (ADA). Sign Reflectivity Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Streets and Sidewalks Projects – Page 3 of 5 Streets and Sidewalks Projects Status as of June 2024 Upgrade $6,692 $81,330 Public Works N/A Recurring (PO‐11000)Project Status: This project includes the annual inventorying, upgrading and maintaining of all traffic signs. A list of signs not meeting the minimum requirement is derived from MUTCD approved Nighttime Visual Inspection surveys. Due to staffing constraints, there were no signs identified for reflectivity replacement in the first half of FY 2024, but 472 signs were identified for reflectivity replacement in the second half of FY 2024. Sixty‐seven signs were replaced through the end of FY 2024 and the remaining 405 signs are scheduled for replacement during FY 2025. Street Light Improvements (PO‐05054) Prior Year Actuals Current Year Budget $210,264 $512,047 Project Status: This project replaces streetlights, including poles, pole foundations, luminaires and wiring as needed to restore or improve street lighting. In the second half of FY 2024, there were 4 knockdown locations with 6 completed repairs and 11 are still in progress to be completed in FY 2025. Implementing Department Public Works Project Phase Project Completion N/A Recurring Street Maintenance (PE‐86070) Prior Year Actuals Current Year Budget $3,892,921 $7,126,112 Implementing Department Public Works Project Phase Project Completion N/A Recurring Project Status: Street Maintenance Projects include the annual resurfacing, micro‐seal, crack seal, and reconstruction of various city streets. These projects fund the street maintenance work that supports Council’s adopted goal of achieving a citywide average pavement condition index (PCI) score of 85, representing very good or excellent conditions. The FY 2024 Street Resurfacing Project under construction will replace 10,149 square feet of sidewalk, 3,371 square feet of driveway, 2,280 linear feet of curb and gutter, construct 37 new ADA curb ramps, and will place 9,844 tons of asphalt concrete overlay, 36 blue markers, 384 thermoplastic legends, and 39,615 LF of thermoplastic striping on the streets of Palo Alto. The FY 2024 Streets Preventive Maintenance Project simultaneously under construction will micro‐surface 14.23 lane miles of streets, replace 12,425 LF of thermoplastic striping, 256 thermoplastic legends, and 77 blue markers. This will help maintain and improve the City’s Pavement Condition Index (PCI) beyond its average of 84 and will address many streets whose PCI scores fall below the City’s minimum goal of 60. Streets and Sidewalks Projects – Page 4 of 5 Streets and Sidewalks Projects Status as of June 2024 Thermoplastic Lane Marking and Striping (PO‐11001) Prior Year Actuals Current Year Budget $0 $235,939 Project Status: This project maintains the thermoplastic markings on roadways. Thermoplastic lane marking and striping is incorporated into annual Pavement Preventive Maintenance Projects. The FY 2024 Streets Preventive Maintenance Project (PE‐86070) is currently under construction and includes the installation of approximately 60 new thermoplastic markings and 14,000 linear feet of thermoplastic striping to be installed in FY 2025. Implementing Department Public Works Project Phase Project Completion N/A Recurring Streets and Sidewalks Projects – Page 5 of 5 Traffic and Transportation Projects Status as of June 2024 One‐Time Projects California Avenue Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Streetscape Update (PL‐23000) $84,054 $121,584 City Managers’ Office Design Fall 2024 Project Status: The project provides funding for interim changes to the street and for necessary CEQA analysis for the future configuration of the street. Staff anticipates that this work will occur in the fall 2024 and be brought before the City Council for discussion later in 2024. Charleston Prior Years Actuals $20,645,491 Total Project Budget Implementing Department Project Phase Project Completion $20,788,951 Public Works Completed Spring 2024Arastradero Corridor Project (PE‐13011) Project Status: This project is part of the 2014 Council Infrastructure Plan. The Charleston Arastradero Corridor was reconfigured to provide new landscaped median islands, bulb outs, enhanced bike lanes, traffic signal improvements, and new street trees to complement the new lane configurations that were approved for permanent retention. Phase 1 (Arastradero Road between Foothill Expressway to Clemo Avenue) and Phase 2 (Charleston Road from Alma Street to Middlefield Road) were completed in 2020. Phase 3 (Arastradero Road from Los Palos Avenue to El Camino Real, Charleston Road from El Camino Real to Alma Street and from Middlefield Road to San Antonio Road) was approved by Council in June 2021. All major construction activities of Phase 3 were completed in spring 2024. Paving and striping of the El Camino Real intersection was completed in April 2024 and the Wilkie Way and West Charleston Road intersection signal switchover was completed in May 2024. In total, this project paved 4.8 lane miles, replaced 18,500 square feet of concrete sidewalk, constructed forty‐eight curb ramps, installed 5,500 linear feet of concrete curbs, and planted 12,700 square feet of landscaping. New striping was installed throughout the corridor which included 39,000 linear feet of thermoplastic striping, 11,600 square feet of green thermoplastic for bike lanes, and 450 pavement markers. Prior Years Actuals $418,211 Total Project Budget Implementing Department Project Phase Project Completion $3,789,671 Public Works Design Winter 2026 Traffic and Transportation Projects – Page 1 of 8 Traffic and Transportation Projects Status as of June 2024 Churchill Avenue Project Status: This project includes planning, design and construction of a shared‐use path along the north side of Enhanced Bikeway (PL‐14000) Churchill Avenue between the existing shared‐use path at Castilleja Avenue and the Stanford Perimeter Trail. It also includes intersection improvements at Churchill Avenue and El Camino Real, which will include a new dedicated westbound right‐turn lane. PAUSD approved the easements required for the project in August 2023. Staff has worked with Caltrans for re‐issuance of the encroachment permit and received approval in June 2024. The project is anticipated to bid in late summer 2024 and construction is anticipated to be completed by winter 2026. Churchill Avenue Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $196,086,259 Office of Transportation Design Spring 2029Rail Grade Separation and Safety $21,018 Project Status: This project provides for the planning, design, and construction of the grade separation at the existing at‐grade crossing on Churchill Avenue in the Caltrain Rail Corridor. The project will provide improvements to accommodate bicycles, pedestrians, and vehicular movement at the crossing. After reviewing various studies and refinements to the alternatives, the Rail Committee recommended proceeding with a Partial Underpass Alternative with Bicycle and Pedestrian crossing at Seale Avenue. On June 10, 2024 the City Council selected the Churchill Underpass with Ped/bike crossing at Seale Avenue. The funding agreement with the Federal Railroad Administration was approved by City Council on June 17, 2024. Staff is collaborating with Caltrain and the Valley Transportation Agency to develop a cooperative agreement for the Preliminary Engineering and Environmental Documentation phase and funding from Measure B Grade Separation funds. The City is also working with State representatives to preserve the CalSTA, Transit, and Intercity Capital Program funding awarded for the project, which is currently being reconsidered for reduction in the Governor’s budget. Improvements Main (PL‐24001) Churchill Avenue Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $9,690,252 Public Works Construction Fall 2024Alma Street Railroad Crossing Safety $1,804,194 Project Status: This project is a railroad crossing improvement project to enhance safety at the intersection of Churchill Avenue and Alma Street. The design includes traffic signal modifications, street lighting improvements, roadway resurfacing, sidewalk realignment, drainage improvements, utility relocations, signage, and striping. StaffImprovements (PL‐20000) Traffic and Transportation Projects – Page 2 of 8 Traffic and Transportation Projects Status as of June 2024 is coordinating with Caltrain, Caltrans, and California Public Utilities Commission (CPUC). CPUC approved General Order 88‐B for the project in November 2022 and authorized the City to move forward with construction. Council approved the construction contract in June 2023 and construction started in summer 2023. The equipment has been ordered, while the contractor has been waiting for a Caltrain flagman for the specific work around the train track areas. All work is expected to be completed in fall 2024. Downtown Automated Parking Prior Years Actuals $1,658,417 Total Project Budget Implementing Department Project Phase Project Completion $5,197,828 Public Works Construction Spring 2025 Project Status: This project includes design and installation of new downtown parking guidance systems, access controls, and revenue collection equipment that will be coordinated with both the Downtown Parking Wayfinding, PL‐15004 project and the 2016 Downtown Parking Management. Staff contracted with Dixon Resources for additional management support in design and procurement for the system installation in the Downtown garages on University Avenue. The Downtown Automated Parking Guidance Systems design‐build construction contract was approved by Council in May 2023. Fiber connections were installed at Lot S/L and Lot R in January 2024. Building permits for the interior garage work for Lot R, Lot S/L, Lot W/C, and Civic Center parking garages have been approved. Staff is working towards obtaining permits for the exterior garage signage. Construction is anticipated to start July 2024 with estimated completion by spring 2025. Guidance Systems, Access Controls & Revenue Collection Equipment (PL‐15002) Prior Years Actuals $42,055 Total Project Budget Implementing Department Project Phase Project Completion $396,395,198 Office of Transportation Design Spring 2028 Traffic and Transportation Projects – Page 3 of 8 Traffic and Transportation Projects Status as of June 2024 Meadow Project Status: This project provides for the planning, design, and construction of the grade separations at the Drive/Charleston existing at grade crossings on Meadow Drive and Charleston Road in the Caltrain Rail Corridor. The project will Road Rail Grade Separation and Safety Improvements (PL‐24000) provide improvements to accommodate bicycles, pedestrians, and vehicular movement at the crossings. After reviewing various studies and refinements to the alternatives, the Rail Committee recommended proceeding to advance two alternatives, the Hybrid and Underpass Alternatives, into the early phase of Preliminary Engineering and Environmental Documentation. The committee also recommended refining these alternatives to reduce right‐ of‐way impacts and improve bicycle and pedestrian facilities. The City Council after reviewing directed staff to advance these alternatives into Preliminary Engineering and Environmental phase on June 10 and June 18 City Council Meetings. The funding agreement with the Federal Railroad Administration was approved by City Council on June 17, 2024. Staff is collaborating with Caltrain and the Valley Transportation Agency to develop a cooperative agreement for the Preliminary Engineering and Environmental Documentation phase and funding from Measure B Grade Separation funds. The City is also working with State representatives to preserve the CalSTA, Transit, and Intercity Capital Program funding awarded for the project, which is currently being reconsidered for reduction in the Governor’s budget. Parking Management and $292,811 Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $627,247 Office of Transportation Procurement Spring 2025 System Implementation (PL‐16002) Project Status: This project provides funding for the design and installation of the Comprehensive Parking Permit and Citation Management System. The all‐inclusive system is a tool staff will utilize in the management of parking permits for eight parking permit programs and associated on and off‐street parking citations. An RFP to solicit another vendor was issued the last week of June 2024. Railroad Grade Separation and Prior Years Actuals $4,501,430 Total Project Budget Implementing Department Project Phase Project Completion $12,238,838 Office of Transportation Pre‐Design Fall 2025 Traffic and Transportation Projects – Page 4 of 8 Traffic and Transportation Projects Status as of June 2024 Safety Improvements (PL‐17001) Project Status: This project is a community‐based process to advance the railroad grade crossing circulation study and context sensitive solutions study envisioned by the City Council for the Palo Alto Avenue crossing. It will also fund the preparation of a Project Study Report and environmental analysis that will be required for the City to realize its goals of advancing grade separations. The project will perform preliminary engineering design, conduct project related studies, and prepare environmental documents for the improvements. This project is currently on hold. City is considering quiet zone implementation for interim conditions and staff will initiate the conceptual plan development for grade separation at this crossing in late 2024. University Ave Streetscape Update Prior Years Actuals $461,353 Total Project Budget Implementing Department Project Phase Project Completion $175,000 Public Works Design Winter 2025 Project Status: This project includes a study to reconfigure University Avenue between Alma Street and Middlefield Road to adapt the public realm to maximize pedestrian and bicycle use, reduce congestion, and enhance the retail environment/economic activity, while maintaining two‐way vehicular access, parking opportunities, delivery and loading zones, ride share spaces, and other amenities including performance space. Council awarded a professional services contract for CSW/Stuber‐Stroeh Engineering in February 2022. The project uses a phased approach with Phase 1 consisting of public outreach, conceptual design, preliminary environmental studies, and financial assessment. A preferred plan will be developed in Phase 1 based on community and stakeholders’ input. Upon completion of Phase 1 assessment and Council’s review of the community preferred plan, future phases including design, environmental assessment, bidding, and construction will be developed. Staff presented an alternatives analysis and a preferred streetscape concept plan to Council on December 18, 2023. Council did not approve the plan and directed staff to identify additional concept alternatives for Council discussion. Staff conducted two meetings with the Retail Committee and received input from Council on June 3, 2024. In summer 2024, staff will continue with stakeholder engagement, refining concepts and cost estimates. Staff is planning to present the preferred concept to Council in September 2024 to conclude Phase 1. Staff will proceed with Phase 2 of the project consisting of preliminary design and environmental assessment upon Council approval of the preferred concept alternative. (PE‐21004) Traffic and Transportation Projects – Page 5 of 8 Traffic and Transportation Projects Status as of June 2024 Recurring Projects Bicycle and Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Pedestrian $211,611 $2,434,852 Office of Transportation N/A RecurringTransportation Plan Implementation (PL‐04010) Project Status: This project funds the Bicycle and Pedestrian Transportation Plan Update effort, which kicked off in fall 2023 and is scheduled to be completed in approximately 24 months (summer/fall 2025). This project also funds the implementation of various individual bicycle and pedestrian projects, such as the design and construction of bicycle boulevards, enhanced bikeways, shared‐paths, bicycle parking, pedestrian improvements, and quick‐build implementation of the City’s existing 2012 Bicycle and Pedestrian Transportation Plan. This project funds infrastructure projects like the Embarcadero Road Improvements Projects and the Charleston/Arastradero Corridor Improvements Project. Parking District Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Implementation $0 $163,900 Office of Transportation N/A Recurring (PL‐15003)Project Status: This project introduces additional parking permit programs throughout the city. One aspect of this project is to update City Council‐approved Residential Preferential Parking (RPP) ordinance language to establish uniform and streamlined procedures and processes to implement RPP districts through the process outlined in Municipal Code 10.50. Safe Routes to School Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $77,826 $969,106 Office of Transportation N/A Recurring (PL‐00026)Project Status: This project enables the City’s Safe Routes to School program, including school commute planning, encouragement activities, and capital improvements along local and collector streets that may be impacted by school commute activities. The capital improvements include traffic calming devices, enhanced crosswalks, and improved signage along suggested safe routes to school. The community engagement and planning process for the construction of the South Palo Alto Bikeways project began in FY 2021. The project will implement buffered or protected bike lanes on East Meadow Drive from Alma Way to Fabian Way, Fabian Way from East Meadow Traffic and Transportation Projects – Page 6 of 8 Traffic and Transportation Projects Status as of June 2024 Drive to East Charleston Road, and widen and repave the Waverley Avenue Bike Path between East Meadow Drive and Charleston Road. Staff was notified of the award of a “Safe Streets for All” grant in spring 2024 to pilot the South Palo Alto Bikeways concept plans on East Meadow Drive and Fabian Way. This fund will support the demonstration project local match and pre‐grant activities in FY 2025. In FY 2024, this project funded education to improve school access and safety. In addition, this project supported a secondary school needs assessment to identify middle and high school education and encouragement programs and to query the Safe Routes Partnership for the resources to support these programs. Traffic Signal and Intelligent Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $223,813 $1,451,217 Office of Transportation N/A Recurring Transportation Systems (PL‐05030) Project Status: This project includes design and construction of traffic signals, traffic signal communications networks, detection, and data projects for transportation use, and maintenance of the City’s traffic signal central management system. The project includes the replacement of traffic signal controllers and cabinets, video detection systems, accessible pedestrian buttons, and related field equipment. Design for traffic signal safety and operational improvements at the intersection of San Antonio Road and Charleston Road is nearing 100% completion. Staff is finalizing the plans and will be preparing bid documents for construction to be released in fall 2024, with construction anticipated to begin in spring 2025. Staff is in the procurement process to update the Centralized Traffic Management system servers to improve operational functions and system security. An IFB for the Quarry Road Traffic Signal and Intelligent Transportation System upgrade project is anticipated for summer 2024. Staff continually provides traffic signal modifications, installations, and upgrades throughout the City. Transportation and Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Parking $309,114 $914,692 Office of Transportation N/A Recurring Improvements (PL‐12000) Project Status: This project implements miscellaneous parking and transportation related improvements including neighborhood traffic calming, neighborhood traffic studies, minor striping and signs installation, and parking improvements. This project also funds the development of grant proposals used to procure funding for future Traffic and Transportation Projects – Page 7 of 8 Traffic and Transportation Projects Status as of June 2024 projects. For the traffic calming project in the Crescent Park neighborhood, City Council approved proceeding with the design of permanent improvements in November 2023. Staff has procured the services of the consultant to design improvements and conduct community outreach. In addition, staff also initiated an Engineering and Traffic Survey for select roadway segments to study prevailing speeds and review traffic conditions in order to establish and/or certify posted speed limits. Staff is also working on the quiet zone project for all railroad crossings along the Caltrain corridor. A quiet zone study was performed for the Palo Alto Avenue and Alma Street crossing in collaboration with City of Menlo Park in 2022. Staff has retained the services of the consultant to design final improvements at this crossing. The design plans are currently at 70% and are being reviewed by CPUC, Caltrain and FRA for feedback and comments that will be incorporated to develop final PS&E and procure necessary permits. In addition, staff procured the services of the consultant to conduct a study for evaluation of quiet zones at the other three crossings of Churchill Avenue, Meadow Drive, and Charleston Road. The $200K Safe Streets for All (SS4A) Safety Action Plan is funded via this project but will be reimbursed up to $160K by a federal grant. The plan will target eliminating traffic deaths and life‐changing injuries on local streets. Traffic and Transportation Projects – Page 8 of 8 Airport Projects Status as of June 2024 One‐Time Projects Airport Access Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Road $0 $3,754,870 Public Works Design Summer 2027 Reconstruction (AP‐24000) Project Status: This project is for the design and reconstruction of the pavement on Embarcadero Way, which is the main access road for airport businesses and the Air Traffic Control Tower at the Airport. The Airport did not receive FAA funding for this project and the project is currently on hold. Airport Layout Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Plan $1,179,551 $967,100 Public Works Construction Summer 2025 (AP‐21000)Project Status: This project provides updates to the Airport Layout Plan, also known as the Long Range Facilities and Sustainability Plan, including a narrative report and environmental study. The Airport received funding for a Phase I portion of this project in fall 2020. The airport conducted five public meetings for the project, and additional meetings are currently being planned for this project. Phase I is approximately 95% complete, and Phase II is approximately 75% complete. Airport Parking Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Lot Electric Vehicle Charger Installation (AP‐24001) $0 $28,994 Public Works Design Summer 2026 Project Status: This project will install electric vehicle charging stations in the Airport customer parking lot. The Airport is currently unable to offer electric vehicle charging to its customers, but there is increasing demand for vehicle charging capability from Airport tenants. This project has been delayed as the Airport explores further funding options. Airport Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Temporary $947 $411,105 Public Works Procurement Winter 2025 Airport Projects – Page 1 of 2 Airport Projects Status as of June 2024 Office Buildings (AP‐22001) Project Status: This project provides funding for the installation and Furniture, Fixtures, & Equipment (FF&E) of existing temporary modular buildings at the airport to provide adequate office space for airport staff as well as terminal space for the public. This project has been delayed while the Airport explores further funding options. Airport Zero Emission Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $192,546 $369,008 Public Works Procurement Summer 2024 Vehicle Fleet Replacement Program Project Status: The Airport vehicle fleet will be replaced by three zero emissions vehicles (ZEV), to be supported by three electric charging stations. The van is used for the transportation of airport guests and passengers and improves safety by minimizing foot traffic on the airport apron. The truck is used as a maintenance, first response, and operations vehicle. The ZEV fleet will include one passenger vehicle and two trucks. FAA funding was received in fall 2023, for the fleet replacement. The Airport issued an RFP in May 2024 and received a bid for a truck. It is expected the vehicle will meet all the FAA Buy America requirements. (AP‐23000) Automated Weather Observation System (AWOS) AP‐19000 Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $43,677 $514,109 Public Works Design Summer 2025 Project Status: This project provides a new weather information system to be installed at the Palo Alto Airport. The Airport has applied for FAA funding, and is waiting for the grant agreement to start design. The Airport received a bid for the project and is submitting a grant application to the FAA. It is anticipated that funding for the project will be received in fall 2024. Recurring Projects 2024‐2028 – Airport Capital Improvements Program Projects: There are no recurring projects scheduled at this time. Airport Projects – Page 2 of 2 Electric Fund Projects Status as of June 2024 One‐Time Projects 115 kV Electric Intertie Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $742,639 $1,801,190 Utilities Pre‐Design Summer 2027 (EL‐06001)Project Status: This project will perform a technical feasibility study to determine the general project requirements to establish a 115 kV electric intertie line and construct a 115/60 kV substation to connect the City's electric system directly to the 115 kV transmission line at an additional location. Staff did not receive California Independent System Operator’s (CAISO) commitment to support this interconnection. Staff has retained the services of a consultant to evaluate the options available to the City. Staff is developing CPAU electric load forecast and proposal for an additional 115 kV transmission line to be submitted in fall 2024 to CAISO for review and acceptance. Coleridge Cowper Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $180,813 $2,680,811 Utilities Design Summer 2025 Tennyson 4/12kV Conversion (EL‐14000) Colorado Project Status: This project converts the primary electric distribution system in the Coleridge Avenue, Cowper Street, Tennyson Avenue area from 4 kV to 12 kV. This individual project will be closed but the scope of work will be covered under the EL‐24000 Grid Modification project. Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Distribution Feeder Outlet Replacement (EL‐22002) $10,576 $400,000 Utilities Construction Fall 2025 Project Status: This project is for the installation of a new underground duct bank and cable at Colorado Substation. The installation will improve reliability for all Colorado circuits. The design was completed in spring 2024 and construction will begin by summer 2025. Council approved the contract in April 2024 and an order for the material has been issued. The construction is delayed due to the procurement of the 12 kV pad‐mount switches. Colorado Power Station Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $4,468,548 $11,536,114 Utilities Design Fall 2027 Electric Fund Projects – Page 1 of 10 Electric Fund Projects Status as of June 2024 Equipment Upgrades (EL‐19001) Project Status: This project is for the upgrades to equipment at the Colorado Power substation. In FY 2022 staff completed the evaluation of existing equipment and will proceed with replacing the COP‐3 115 kV/60 kV transformer bank and the 115 kV breaker. Engineering is continuing to work on the design RFPs and construction IFBs for contract services to complete substation projects. In the meantime, the station service voltage transformer (SSVT1) and the 60 kV Bus 1 & 2 Potential Transformers (PT) have been purchased for the replacement. Colorado Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Substation Site Improvements (EL‐19002) $275,777 $1,425,693 Utilities Design Fall 2025 Project Status: This project will make modifications to the substation driveways and fence to provide adequate ingress and egress for utility vehicles used for maintenance and repair. Staff has prepared an overall master plan for Colorado Substation to include all proposed improvements. Detailed designs for lighting, driveway, fences, walls, and an oil containment improvement have been prepared. The Planning Department approved Utility engineering’s design in May 2024. Engineering staff is currently preparing bid documentation for the construction IFB. Bid opening has been delayed until winter 2025 due to staff changes. East Meadow Circles 4/12kV Conversion Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $367,401 $1,742,527 Utilities Design Spring 2025 Project Status: This project converts the primary electric distribution system in the East Charleston Road, Alma Street, East Meadow Drive, Middlefield Road areas from 4 kV to 12 kV and is challenging because of the configuration of the streets and rear easement facilities. This project has been split into six design and construction phases. Engineering has completed the design and construction for Phase 1. The City’s electrification goals have changed the priority, schedule, and the allocation of staff resources for this CIP project. Engineering design for Phase 2 and 3 is in progress. (EL‐17001) Foothills Rebuild Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion (Fire Mitigation) $8,503,110 $14,999,589 Utilities Construction Fall 2025 Electric Fund Projects – Page 2 of 10 Electric Fund Projects Status as of June 2024 (EL‐21001)Project Status: This project will rebuild the approximately 11 miles of overhead line in Foothills Park, as necessary to mitigate the possibility of wildfire due to overhead electric lines. This could include the utilization of more robust equipment or construction practices, rerouting to avoid vegetation and improve access for inspection and maintenance, or converting the overhead lines to underground where feasible. Two proposals were received for this project and both proposals were rejected because they did not provide an option to underground existing overhead electric lines. Substructure for Phases 1, 2 and 3 is completed while the Phase 4 substructure is currently in construction. Grid Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Modernization $350,153 $300,000,000 Utilities Design Winter 2030 for Electrification Project Status: This project will provide the City with an electric infrastructure adequate to support the City’s goal (EL‐24000)of 100% electrification and 80% carbon emissions reduction by the year 2030. To attain the 100% electrification scenario, the City must maximize use of electric energy and phase out carbon‐based end uses such as natural gas appliances and internal combustion vehicles. The electric system must be updated to meet the needs of electrification, and older components in the distribution infrastructure must be replaced to mitigate chances of overloading the system. Examples of assets to be replaced are distribution and substation transformers, primary/secondary distribution circuits. A Pilot area was designated and engineering staff in conjunction with a consultant have completed the distribution system design for the Pilot area, with a handful of power poles replaced and installed as initial construction efforts start to take shape. The estimated completion date for the Pilot is December 2024. Starting in FY 2025, this project will incorporate and consolidate the scope of work from the following projects into one CIP: Coleridge Cowper Tennyson 4/12kV Conversion (EL‐14000), Hopkins Substation 4/12 kV Conversion (EL‐20000), Rebuild Underground District 15 (EL‐11003) and Rebuild Underground District 16 (EL‐13003). Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $220,986 $15,000,000 Utilities Construction Fall 2024 Electric Fund Projects – Page 3 of 10 Electric Fund Projects Status as of June 2024 Hanover Project Status: This project proposes to install two 12 kV 50 MVA transformers to replace two 4kV transformers that served 1501 Page Mill Road and make all substation improvements necessary to accommodate the installations. Generally, three to four years are spent on a substation upgrade. However, Tesla is requesting to finish all construction at the substation and energize the new transformers and switchgear by the end of September 2024. Construction work is in progress. Substation Improvement (EL‐24001) Hopkins Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Substation 4/12 kV Conversion (EL‐20000) $0 $2,010,000 Utilities Design Fall 2025 Project Status: This project will convert the distribution system connected to the Hopkins Substation from 4 kV to 12 kV. The future conversion of the Hopkins Substation from 4 kV to 12 kV requires that all the areas currently served at 4 kV from the Hopkins Substation be converted to 12 kV. This project will improve operating flexibility of the system, service reliability, and back‐up to customers in downtown and other adjacent areas. The City’s electrification goals have changed the priority, schedule, and the allocation of staff resources for this CIP project. Staff is working on an RFP for the engineering design for electrification of all overhead circuits. This individual project will be closed and the scope of work will be covered under the EL‐24000 Grid Modification project. Please see EL‐24000 Grid Modernization for Electrification for future updates. Inter‐Substation Line Protection Relay Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $371,146 $1,601,626 Utilities Construction Summer 2027 Project Status: This project replaces the existing HCB pilot wire relays with a new microprocessor line differential protective relay to protect the city’s 60 kV sub‐transmission line sections and equipment from damage due to faults (i.e. short circuits) on the 60 kV line sections. This project is being done in phases, with design and construction happening concurrently on the different phases. Construction of these improvements relies on work completed by other projects to install fiber optic connections. Engineering design for segments Colorado substation to Adobe Creek substation, Park Boulevard substation to Quarry substation, and Maybell substation to Park Boulevard substation is in progress. A test plan is being written to prove the equipment will work as designed. (EL‐17005) Electric Fund Projects – Page 4 of 10 Electric Fund Projects Status as of June 2024 The Quarry to Park substation segment is delayed due to resources and is expected to be completed fall 2024. Park to Maybell segment is still in progress, fiber installation is complete, and completion is expected winter 2025. Rebuild Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Underground District 15 (EL‐11003) $43,348 $1,293,337 Utilities Design Fall 2027 Project Status: This project rebuilds and replaces the underground electric system in Underground District 15, the area bounded by Los Palos Avenue, Glenbrook Drive, Pomona Avenue, and Arastradero Road. This project is in the preliminary stages of engineering design and work will be coordinated with EL‐16000 which is currently rebuilding the electric system along Arastradero Road. Work on this project was delayed due to public input regarding the design of the project. Changes to the Rules and Regulations will require property owners to pay for the differential cost should they want submersible equipment instead of pad mount. This project will fall under the underground scope of work for electrification. Funds will be returned to reserves. Please see EL‐24000 Grid Modernization for Electrification for future updates. Rebuild Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Underground District 16 (EL‐13003) $28,742 $728,735 Utilities Design Spring 2027 Project Status: This project rebuilds and replaces the underground electric system in Underground District 16, the area along Louis Road between Greer Street and Loma Verde Avenue. The engineering design work is complete. The City’s electrification goals have changed the priority, schedule, and the allocation of staff resources for this CIP project. This project will fall under the underground scope of work for electrification. Funds will be returned to reserves. Please see EL‐24000 Grid Modernization for Electrification for future updates. Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,949,767 $2,522,451 Utilities Design Fall 2024 Electric Fund Projects – Page 5 of 10 Electric Fund Projects Status as of June 2024 Rebuild Project Status: This project rebuilds and replaces the underground electric system in Underground District 24, the area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street. The engineering design is in progress and will be completed in winter 2025. Construction will follow in spring 2025. Underground District 24 (EL‐10006) Rebuild Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Underground District 26 (EL‐16000) $36,817 $2,522,451 Utilities Design Spring 2025 Project Status: This project rebuilds and replaces the underground electric system in Underground District 26, the area along Arastradero Road between El Camino Real and Hillview Avenue. This is a four‐phase project. The engineering design is in progress and will be completed by winter 2025. Construction will follow in spring 2025. Smart Grid Technology Installation (EL‐11014) Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $12,805,162 $17,690,005 Utilities Construction Spring 2025 Project Status: Council approved the Advanced Metering Infrastructure (AMI) with Sensus on October 18, 2021. The project includes replacement of 30,000 electric meters and retrofit of 20,800 water and 24,200 gas meters with radio endpoints to transmit meter data to the AMI network. The proof of concept phase including AMI network installation, meter testing, and system integration will occur between January 2022 and August 2023. Full deployment is anticipated to run from September 2023 through April 2025. Substation Breaker Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $1,568,954 $7,368,743 Utilities Pre‐Design Summer 2028 Replacement (EL‐17002) Project Status: This project replaces high voltage circuit breakers that interconnect the nine electric substations and two power switching stations that are reaching the end of their useful life and are now underrated for their use. This project is being done in phases, with design and construction happening concurrently on the different phases. Staff completed the construction on the first phase and is working to procure a multi‐year contract with a contractor to complete the design and replacement of the remaining breakers. Staff is working on the design RFP Electric Fund Projects – Page 6 of 10 Electric Fund Projects Status as of June 2024 and the construction IFB for contract services to complete substation projects. Lead times for circuit breakers are currently at around 18 months. Substation Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Physical Security $3,093,299 $6,895,187 Utilities Construction Winter 2025 (EL‐16003)Project Status: This project installs facilities providing physical protection of electric substations from vandalism and intrusion. A professional services contract was awarded to Burns and McDonnell and the study was completed. Staff continues to implement recommendations from the study each fiscal year. Construction is 90% complete at seven of the nine substations. The Park and Colorado substations are the two remaining substations that need updated security. The engineering design was approved by Planning and staff is now preparing the bid documentation. Recurring Projects Communications Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Utilities N/A RecurringSystem$45,733.$100,000 Improvements (EL‐89031) Project Status: This project installs high frequency coaxial cable, fiber optic cable, and related equipment to provide communications services for traffic signal coordination, telephone links, computer data transmission, and the Electric Supervisory Control and Data Acquisition (SCADA) system. This project is funding a portion of the design phase of an expanded Utilities fiber optic network. The contract for design of this network was approved by Council in June 2020. Staff installed 48F FO Cable between Maybell MB and PBS Park Boulevard substations in Existing Aerial Innerduct for pilot wire relay protection. Electric Fund Projects – Page 7 of 10 Electric Fund Projects Status as of June 2024 Electric Customer Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Connections $2,202,541 $2,700,000 Utilities N/A Recurring (EL‐89028)Project Status: This project installs services, transformers, and meters for new customers; upgrading of existing services; temporary service connections; and overhead and underground extensions for new or existing customers. Projects are in many stages of design and construction to provide temporary and permanent power to residential and commercial customers in Palo Alto. Electric System Improvements (EL‐98003) Prior Year Actuals Current Year Budget $1,567,547 $2,500,000 Project Status: This project consists of various projects that replace deteriorated facilities or install protective devices that improve the Electric Distribution System. Projects are in many stages of development to replace transformers, replace poles, replace overhead wires, and install protective devices to improve service reliability. Implementing Department Project Phase Project Completion Utilities N/A Recurring Electric Utility Geographic Information System Prior Year Actuals Current Year Budget $68,397 $250,000 Implementing Department Project Phase Project Completion Utilities N/A Recurring Project Status: This project enhances the citywide Geographical Information System (GIS). The primary emphasis will be to provide a compatible user interface and estimating software, to edit and update data which will reside in the citywide GIS. This funding is also being used to pay for Utilities Electric Division’s share of cost for the implementation of new city‐wide GIS system (ESRI) led by IT. Utilities and Information Technology staff are also working to assess GIS needs and the transition of the mapping information to ESRI. The migration of the topographic data for Electric is 100% complete, but the migration of metadata is still in process. (EL‐02011) SCADA System Upgrades Prior Year Actuals Current Year Budget $136,591 $220,000 Implementing Department Project Phase Project Completion Utilities N/A Recurring Electric Fund Projects – Page 8 of 10 Electric Fund Projects Status as of June 2024 (EL‐02010)Project Status: This project upgrades the Supervisory Control and Data Acquisition (SCADA) system hardware. Staff completed the upgrade of the servers used for monitoring the utility substations and equipment for 2024. The next hardware and software upgrade is currently in progress at the factory and work will occur in winter 2025 Substation Facility Prior Year Actuals Current Year Budget $29,240 $1,200,000 Implementing Department Project Phase Project Completion Utilities N/A Recurring Improvements (EL‐89044) Project Status: This project makes improvements to facilities at the electric substations in Palo Alto. Staff is working on the replacement of Remote Terminal Units (RTU) at various substations, upgrading gravel and grounding, 60 kV air switches, and reconfiguring steel trusses and associated devices. Engineering is working on design and construction for contract services to complete substation projects. Staff has completed the install for Nexus meters at Hansen Way (22/23) and Colorado (20/21). Design for Hansen Way (20/21) is in progress. Substation Protection Prior Year Actuals Current Year Budget $262,000 $300,000 Implementing Department Project Phase Project Completion Utilities N/A Recurring Improvements (EL‐89038) Project Status: This project makes improvements to equipment used at electric substations to protect the substation equipment and circuits emanating from the substation from damage due to faults (i.e. short circuits) on the electric system. Staff issued a task order with Soudi Consultants to review and revise protection settings and training on the commissioning of Park Boulevard relays. Underground System Rebuild (EL‐16001) Prior Year Actuals Current Year Budget $0 $350,000 Project Status: This project replaces underground electric equipment in areas that were originally installed underground, that are not part of an Underground District. Staff is working to identify areas where the age of the existing cables are a high priority for cable replacement. To date, this includes areas in the Stanford Research Park, Arastradero Road, and along East Bayshore Road. New areas have been identified and progress has been Implementing Department Project Phase Project Completion Utilities N/A Recurring Electric Fund Projects – Page 9 of 10 Electric Fund Projects Status as of June 2024 made on development of the project. Projects are in many stages of development to replace underground transformers, cables, vaults, and to install protective devices to improve service reliability. Wood Pole Replacement (EL‐19004) Prior Year Actuals Current Year Budget $533,613 $1,500,000 Project Status: This project will fund the annual replacement of deteriorated wood power poles. Staff has completed the replacement of forty‐six poles in FY 2024. Implementing Department Project Phase Project Completion Utilities N/A Recurring Electric Fund Projects – Page 10 of 10 Fiber Optics Fund Projects Status as of June 2024 One‐Time Projects Fiber Optic Network System Rebuild (FO‐16000) Prior Years Actuals Total Project Budget $3,232,944 $32,103,876 Implementing Department Project Phase Project Completion Utilities Design Fall 2025 Project Status: This project is for the System Capacity Improvement that rebuilds portions of the "dark" fiber optic network around Palo Alto. In September 2022, Council approved the City’s fiber expansion plan including construction of a new fiber backbone and a phased buildout of a fiber‐to‐the‐premises network. The Fiber Optic Network System Rebuild CIP will be replaced with new Fiber Backbone and Fiber‐to‐the‐Premises (FTTP) CIP’s in FY 2024. Staff has hired a consultant to complete the Fiber Backbone and FTTP conceptual design. The conceptual design has been completed the contract has been amended to complete the design and all provide documentation necessary for procurement of a construction contract. Staff is updating fiber databases and reviewing the current inventory of fiber strands in order to determine what sections of the Fiber Backbone should be upgraded first. Due to the Fiber to the Premises pilot and Wildfire Mitigation project in the Foothills, materials and resources have been reassigned from this project. Staff anticipates restarting this review phase, to be completed by January 2025. As the FTTP pilot expands into Phase I, staff will be designing and constructing the new Fiber Backbone, with an anticipated date to complete phase 1 Fiber Backbone by end of December 2025. Fiber to the Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Utilities Design Winter 2030Premises (FTTP) $53,550 $ 20,000,000 Project Status: This project will build Fiber‐to‐the‐Premises (FTTP) to deliver broadband (high‐speed internet) for homes and businesses in the City of Palo Alto. As the City builds the FO‐16000 ‐ Fiber Optics Network ‐ System Rebuild Staff has divided up the City into smaller sections for a phased approach of the Fiber‐to‐the‐Premises project. Furthermore, Staff has proceeded to combine the Phase 1 Fiber‐to‐the‐Premise design with a Grid Modernization Project covering the same area. Staff is capitalizing on inherent synergies between the two projects, as well as taking advantage of economies of scale deployment that can be realized as a result of combining the two projects. Staff has contracted with an Engineering firm to produce design drawings and specifications. The City is implementing a pilot during Phase 1 of the FTTP project to evaluate various new technologies and to assess various construction (FO‐24000) Fiber Optics Fund Projects – Page 1 of 2 Fiber Optics Fund Projects Status as of June 2024 methodologies to closely align with Grid Modernization and inform on future phases of deployment. FTTP pilot construction is scheduled to begin in September 2024 and customers in the pilot area can be served in February 2025. Recurring Projects Fiber Optics Customer Prior Year Actuals $18,434 Current Year Budget Implementing Department Project Phase Project Completion $251,600 Utilities N/A Recurring Connections (FO‐10000) Project Status: This project enables the installation of fiber optic infrastructure for new service connections. Projects are developed as needed to meet customer requests for leasing of fibers on the Dark Fiber system. There have been five new customer inquiries in the second half of FY 2024. Staff has installed new fiber connection services for the Public Safety Building. Fiber Optics Network System Prior Year Actuals $36,608 Current Year Budget Implementing Department Project Phase Project Completion $561,000 Utilities N/A Recurring Project Status: This project improves the reliability within the fiber optic network system. As part of the City’s Improvements wildfire mitigation plan, this project will add new fiber conduit and substructure in the foothills to support city (FO‐10001)infrastructure and improve telecommunication and connectivity in the open space. In the second half of FY 2024, staff is having discussions with customers in the foothills to see whether they are interested in licensing dark fiber from the City to enhance their residential broadband service in conjunction with a third‐party internet service provider. Fiber conduit installation in the foothills is expected to be completed by early 2025. Fiber Optics Fund Projects – Page 2 of 2 Gas Fund Projects Status as of June 2024 One‐Time Projects Gas Main Replacement $3,929,943 Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Spring 2025$10,063,205 Utilities Construction Project 24 (GS‐14003) Project Status: This project enables the design and construction to replace approximately 20,100 linear feet (which represents 1.9% of the City's Gas distribution main system) of distribution main and 260 gas services constructed mainly of PVC on various streets within the University Park, and Crescent Park neighborhoods. Release of the project for bidding has been delayed, to include the Town & Country Village scope. This project was split into GMR24A and GMR24B. GMR24A (Stanford Shopping Center) was completed spring 2023. GMR24B construction started in winter 2024 and is anticipated to be complete in spring 2025. Gas Main Replacement $15,525 Prior Years Actuals Total Project Budget Implementing Department Project Phase $10,000,000 Utilities Design Project Completion Fall 2026 Project 25 (GS‐15000) Project Status: This Gas Main Replacement (GMR) project replaces approximately 26,000 linear feet (which represents 2.3 percent of the City’s Gas Distribution System) of leaking, inadequately sized, and structurally deficient gas mains and services located on various streets in the neighborhoods of Community Center, Leland Manor, Midtown, and Palo Verde neighborhoods. Staff identified problematic mains and services by researching maintenance and leak histories, analyzing performance of the entire Gas Distribution System, and considering risk ratings of the Distribution Integrity Management Plan. A federal grant application was submitted in August 2023 and the City was awarded $16.5 million in grant funding for this project. Staff is currently completing the Tier 2 Environmental documentation to meet federal grant requirements before it can be released through purchasing for construction bids. The project is on track for construction to begin in summer 2025. Recurring Projects Gas Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Distribution $484,530 $1,005,796 Utilities N/A Recurring Gas Fund Projects – Page 1 of 3 Gas Fund Projects Status as of June 2024 System Project Status: This project enables Gas Distribution System improvements that include increasing distribution system Improvements capacity for load growth, replacing deteriorated capital facilities, reconfiguring and adding to the system to improve (GS‐11002)service reliability, and conducting research related to performance of the gas distribution system or its various components making general improvements to the system. The City must continuously evaluate service reliability needs and make improvements to the system to maintain top level service to City customers and to minimize potential economic losses due to service interruptions. In the second half of FY 2024, City crews completed the replacement of various gas services and valves throughout the system, emergency repairs to Arastradero Creek to backfill an exposed 8 inch gas pipeline, and replacement of pressure transmitting equipment at Scripps Avenue. Gas Prior Year Actuals Current Year Budget Implementing Department $80,226 $100,000 Utilities Project Status: This project purchases polyethylene (PE) fusion equipment and tools, directional boring/locating equipment and tools, and general shop equipment and tools. The equipment needs to be upgraded on an annual basis to safely operate and maintain a natural gas distribution system and to ensure operators’ safety and productivity. In the second half of FY 2024, the purchase of 15 new Sensit gas detectors was completed. Project Phase N/A Project Completion RecurringEquipment and Tools (GS‐13002) Gas Meters and Prior Year Actuals Current Year Budget Implementing Department $365,663 $500,000 Utilities Project Phase N/A Project Completion Recurring Regulators (GS‐80019) Project Status: This project provides replacement of the existing gas meters and regulators annually. The coordination of gas meter and regulator replacements with gas meters identified to be replaced under the AMI contract, which is generally gas meters that are 25 years or older. The gas meter replacement program ensures the accuracy of gas consumption measurement, reduces possible revenue loss due to under‐registered gas, and provides customers with accurate monthly bills. Replacement of aged gas meters and regulators is on‐going. The next major replacement of meters and regulators will be coordinated with Gas Main Replacement Project 24 (GS‐14003) and the Advanced Metering Infrastructure project. Gas Fund Projects – Page 2 of 3 Gas Fund Projects Status as of June 2024 Gas System, Customer Prior Year Actuals Current Year Budget Implementing Department $584,034 $810,900 Utilities Project Phase N/A Project Completion Recurring Connections (GS‐80017) Project Status: This project enables the Gas Distribution System to be extended in order to provide gas service to new customers and augment service to customers with increased natural gas demands. Improvements include new mains, services, valves, regulators, meters, and accessories in order to meet changes in existing customer service demands, and respond to changes in gas service requirements due to new development or redevelopment. This project is funded partially from reimbursements by customers. City crews completed 18 gas service installations, 5 gas service relocations and 14 gas service demolitions in the second half of FY 2024. Gas Fund Projects – Page 3 of 3 Stormwater Management Projects Status as of June 2024 One‐Time Projects Corporation Way System Upgrades and Pump Station (SD‐21000) Prior Years Actuals $340,827 Total Project Budget Implementing Department Project Phase Project Completion $4,146,556 Public Works Design Spring 2026 Project Status: This project incorporates a design of a new small pump station with a twenty‐five cubic feet per second capacity and upgrades 700 linear feet of pipe to thirty inch diameter High Density Polyethylene pipe. The existing system does not have the force needed to discharge storm flows into the Adobe Creek. Adding a pump station in advance of the outfall and upsizing the storm pipe will eliminate the routine flooding along East Bayshore Road and convey runoff from a ten year storm event. Staff secured an easement for the pump station from adjacent property owners. The design consultant addressed the City’s 90% review comments and submitted the final Plans, Specifications and Estimate (PS&E) to staff. The Architectural Review application was approved and the Plans are under review by the Building Department. Concurrently, staff is preparing an IFB for construction. Bids will be solicited in summer 2024 and a construction contract is anticipated to start in fall 2024. East Meadow Drive System Upgrades Prior Years Actuals $440,133 Total Project Budget Implementing Department Project Phase Project Completion $636,405 Public Works Construction Summer 2024 Project Status: This project adds approximately 407 linear feet of new 24‐inch high density polyethylene (HDPE) to be parallel to the existing thirty‐six inch pipe within East Meadow Drive to increase the capacity of the storm drain system. This project includes upsizing manholes based on new pipes and reconnecting laterals from private property and catch basins. A construction contract was awarded in October 2023, and construction began in November 2023. Construction contract closeout is anticipated in August 2024 due to additional storm drain‐pipe replacement locations as part of the Storm Drain Rehab project (SD‐06101). (SD‐22000) East Meadow Circle Prior Years Actuals $333,087 Total Project Budget Implementing Department Project Phase Project Completion $634,016 Public Works Construction Summer 2024 Connection to Adobe Creek Pump Station Project Status: This project will install approximately 600 linear feet of fifteen inch pipe and manholes along East Meadow Circle. The upgraded line will eliminate flooding that occurs within East Meadow Circle when the water level within Barron Creek is higher than the flap‐gate, and flows are not able to drain into the creek. The new fifteen‐ Stormwater Management Projects ‐ Page 1 of 4 Stormwater Management Projects Status as of June 2024 (SD‐26000)inch HDPE line extension allows flows to drain away from Barron Creek and into Adobe Creek, where they can be pumped. The project also includes a small bioretention area to treat low flow runoff within East Meadow Circle before discharging into either creek. A construction contract was awarded in October 2023, and construction began November 2023. Construction contract closeout is anticipated in August 2024 due to additional storm drain‐pipe replacement locations as part of the Storm Drain Rehab project (SD‐06101). Trash Capture Device Prior Years Actuals $762,720 Total Project Budget Implementing Department Project Phase Project Completion $818,837 Public Works Construction Summer 2024 Installation (SD‐22002) Project Status: This project involves design and construction of a large trash capture device (TCD) installed in the planting strip along Embarcadero Road located in front of the Palo Alto Baylands Golf Links parking lot. The TCD will be integrated into a thirty‐six inch storm pipe to capture trash as small as five millimeters from a section of the storm drain system prior to discharging to the San Francisco Bay. The 189‐acre drainage area treated by the TCD consists of 169 acres of commercial and office land use in the City’s jurisdiction and twenty acres in the California Department of Transportation (Caltrans) right‐of‐way. Construction began in summer 2023 and will be completed by summer 2024. West Bayshore Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion $3,058,134 Public Works Design Spring 2026Road Pump Station $424,398 Project Status: This project incorporates design and construction of a new small pump station with fifteen cubic feet per second capacity. Installing a new pump station will allow storm flows to be pumped into the Adobe Barron Creek confluence while adding a pump station in advance of the outfall would eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from a ten year storm event. Staff secured an easement for the pump station from adjacent property owners. The design consultant has submitted the final plans after addressing the City’s comments. The Architectural Review application for the project has been approved and is under review by the Building Department for final permit approval. An IFB for construction is anticipated to be issued in summer 2024. (SD‐20000) Stormwater Management Projects ‐ Page 2 of 4 Stormwater Management Projects Status as of June 2024 West Bayshore Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Road Trunk Line $44,554 $2,542,314 Public Works Design Spring 2026 Improvements (SD‐23000) Project Status: This project replaces approximately 1,400 linear feet of existing fifteen inch diameter pipe with thirty‐six inch High Density Polyethylene pipe. These improvements along with the new West Bayshore Road Pump Station (SD‐20000) will eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from a ten year storm event. Staff secured an easement for the pump station from adjacent property owners. The design consultant has submitted the final plans after addressing the City’s comments. The Architectural Review application for the project has been approved and is under review by the Building Department for final permit approval. An IFB for construction is anticipated to be issued in summer 2024. Recurring Projects Green Stormwater Infrastructure (SD‐22001) Prior Year Actuals $77,092 Current Year Budget Implementing Department Project Phase Project Completion $2,005,559 Public Works N/A Recurring Project Status: This project provides funding for Green Stormwater Infrastructure (GSI) projects and the integration of GSI features in the design and implementation of planned CIP projects supported by other funds. GSI mimics the natural environment to slow, spread, infiltrate, and filter pollutants from stormwater runoff through native or engineered soils or other pervious material rather than discharging it directly into the storm drain system, creeks, and the Bay. Types of GSI include bioretention areas, flow‐through planters, tree wells, and pervious pavement to manage stormwater runoff. The FY 2024 budget is allocated as a match to fund the balance of a GSI project partially funded by the U.S. Environmental Protection Agency and also provided funding for constructing a bioretention area as part of the East Meadow Circle Connection to Adobe Creek pump station project (SD‐26000) in spring 2024. Storm Drainage Prior Year Actuals System $598,188 Current Year Budget Implementing Department Project Phase Project Completion $1,525,681 Public Works N/A Recurring Stormwater Management Projects ‐ Page 3 of 4 Stormwater Management Projects Status as of June 2024 Replacement and Rehabilitation (SD‐06101) Project Status: This project provides for annual replacement and rehabilitation to maintain the integrity of the storm drain system, including deteriorated storm drain piping, manholes, and storm drain inlets. The rehabilitation includes replacement of broken corrugated metal pipe with High Density Polyethylene pipe. Based on the recent pipe failures that occurred in early 2023, staff is proposing to replace storm drain pipes at seven locations (Forest Avenue, Ramona Street, Embarcadero Road, Fielding Drive, Middlefield Road, Newell Road, and Alexis Drive), as part of CIP projects SD‐22000 and SD‐26000. A construction contract was awarded in October 2023 and construction began in November 2023. In the second half of FY 2024, Forest Avenue, Embarcadero Road, Newell Road, and Fielding Drive locations were completed and construction is anticipated to be completed by August 2024 on the remaining locations. Stormwater Management Projects ‐ Page 4 of 4 Wastewater Collection Fund Projects Status as of June 2024 One‐Time Projects Wastewater Collection System Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Spring 2024$7,458,916 $8,635,244 Utilities Completed Rehabilitation Augmentation Project 31 Project Status: This project funded the design and construction of high priority main replacements which reduces inflow of rainfall and groundwater into the collection system. The project replaces approximately 11,000 linear feet (which represents 1.0 percent of the City’s Wastewater Collection System) for El Camino Real from Page Mill Road to Cesano Court, and Page Mill Road from Ramos Way to Ash Street. The project was comprised of mains identified in video inspection work or through maintenance records as structurally deficient and in need of replacement. The work was in Caltrans (El Camino Real) and the County of Santa Clara (Page Mill Road) right‐of‐way. Construction was completed in May 2024. (WC‐19001) Recurring Projects Sewer Lateral/Manhole Rehabilitation and Prior Year Actuals Current Year Budget Implementing Department $850,000 Utilities Project Phase Project Completion $688,486 N/A Recurring Project Status: This project replaces defective sewer laterals, cleanouts, manholes, backwater devices, and equipment to support these activities to maintain the Wastewater Collection System, as well as to comply with the Sanitary Sewer Master Plan (SMP). Information collected during routine annual maintenance activities is used to prioritize work. The continued work performed will also help reducing both sewage blockage and the City's treatment expenses to treat rainwater or groundwater infiltration. A new three year construction contract was approved in FY 2023 to replace problematic sewer laterals. In the second half of FY 2024, seven sewer lateral replacements were completed under this contract. Replacement (WC‐99013) Wastewater Collection Fund Projects – Page 1 of 2 Wastewater Collection Fund Projects Status as of June 2024 Sewer System, Customer Prior Year Actuals $386,388 Current Year Budget Implementing Department $450,000 Utilities Project Phase N/A Project Completion Recurring Connections (WC‐80020) Project Status: This project installs sewer lateral connections and additions or extensions of existing mains to serve new customers and to respond to changes in sewer requirements due to redevelopment. Old existing non‐plastic sewer laterals with condition deficiencies per Utilities Operations’ criteria are required to be replaced in accordance with the latest 2022 WGW Standards. In the second half of FY 2024, seven new lateral connections were performed. Wastewater General Prior Year Actuals $44,679 Current Year Budget Implementing Department $108,941 Utilities Project Phase N/A Project Completion Recurring Equipment and Tools Project Status: This project provides funds to procure new general equipment and new tools. In the second half of FY 2024, no new general equipment or tools was procured. (WC‐13002) Wastewater System Prior Year Actuals $133,144 Current Year Budget Implementing Department $799,501 Utilities Project Phase N/A Project Completion Recurring Improvements (WC‐15002) Project Status: This project implements improvements to the Wastewater Collection System by increasing system capacity for growth, flow monitoring, hydraulic modeling and system analysis, load simulations, asset management analysis and assessment, system inflow/infiltration analysis, and sanitary sewer overflow monitoring and reduction. Part of this project funds the Sewer Master Plan Study, which is evaluating the City’s existing wastewater collection system, flows, and flow patterns to determine system capacity to meet current and future flows and recommend and prioritize capital improvement projects where needed. The consultant contract was approved in November 2023. The consultant started work in December 2023. The project completed flow monitoring in spring 2024 and is currently validating the collection system model network. Wastewater Collection Fund Projects – Page 2 of 2 Wastewater Treatment Fund Projects Status as of June 2024 One‐Time Projects Advanced Water Prior Years Actuals Total Project Budget $2,196,877 $59,974,965 Implementing Department Public Works Project Phase Project Completion Design Spring 2027 Purification Facility (WQ‐19003) Project Status: This project enables the design and construction of an Advanced Water Purification Facility to further improve the quality of the tertiary‐treated recycled water by ultrafiltration followed by reverse osmosis to reduce the level of total dissolved solids. The water reuse partnership agreement with Valley Water and Mountain View provides $16 million in funding from Valley Water for this project. The City has also received grant funding for a portion of the project costs and a State low‐interest loan for the design and construction phases. Mountain View agreed to pay the remainder of the capital costs associated with this project. The design is currently at 100%. The project is in process of receiving a building permit prior to issuing an invitation for bids in fall 2024, while financial agreements with funding agencies are being formalized. Headworks Facility Prior Years Actuals Total Project Budget $184,846 $52,095,872 Implementing Department Public Works Project Phase Project Completion Pre‐Design Spring 2032 Replacement (WQ‐16002) Project Status: This project replaces the existing two outdated influent pump stations and their associated equipment and ancillary systems, including the suction and discharge piping manifolds, valves, electrical and controls system, screening equipment, grit handling equipment, pumps, flow meters and yard piping. A consultant was selected in winter 2024 to perform preliminary and carry out workshops to determine the design criteria. Horizontal Levee Pilot (WQ‐22001) Prior Years Actuals Total Project Budget Implementing Department $156,195 $738,511 Public Works Project Phase Project Completion Design Fall 2029 Project Status: This project consists of the design, permitting, and construction of a horizontal levee pilot system. The system will utilize treated wastewater to create a transitional brackish habitat on the Bayside of a future flood control levee located in the Palo Alto Baylands, adjacent to the Regional Water Quality Control Plant (RWQCP). Information and data collected by this pilot system could support broader implementation of horizontal levees as green infrastructure components in larger flood control levee improvement projects within Palo Alto and beyond. The project Wastewater Treatment Fund Projects – Page 1 of 4 Wastewater Treatment Fund Projects Status as of June 2024 completed design, CEQA review, conducted several stakeholder outreach events, created a project webpage, obtained all construction permits from resource agencies, received a recommendation from the Parks and Recreation Commission, and obtained Council approval of the Park Improvement Ordinance as well as a Cooperative Agreement between project partners. The project is currently onboarding a construction management firm, preparing for required monitoring, and coordinating future community engagement activities including BioBlitz’ and King Tide Walks. The San Francisco Estuary Partnership/Association of Bay Area Governments will be posting the project for solicitation in late 2024. Joint Intercepting Sewer Prior Years Actuals Total Project Budget $103,833 $12,573,488 Project Status: This project will rehabilitate 2,364 linear feet of the 60‐inch and 72‐inch diameter Joint Intercepting Implementing Department Public Works Project Phase Project Completion Construction Fall 2024 Rehabilitation Sewer (JIS) trunk line leading to the Regional Water Quality Control Plant (RWQCP). The entire trunk sewer line, (Phase 1) (WQ‐24000) constructed in 1972, is approximately 9,000 feet long consisting of 13 manholes and junction structures. The JIS conveys raw wastewater mainly from the City of Mountain View, City of Los Altos, Los Altos Hills, and a portion Palo Alto, which accounts for more than half of the RWQCP’s influent flows. A construction contract was awarded in winter 2024. Construction is 20 percent complete and is scheduled to be completed by fall 2024. New Laboratory and Prior Years Actuals Total Project Budget $363,705 $23,979,898 Project Status: This project was originally envisioned to replace the existing plant laboratory and environmental Implementing Department Public Works Project Phase Project Completion Pre‐Design Fall 2030 Environmental services offices. Staff is currently revising space planning assumptions as the City and RWQCP are investigating the Services Building (WQ‐14002) potential acquisition of a property adjoining the RWQCP and have put further design efforts on hold. The original design contract was terminated in March 2021. Solicitation for engaging a new consultant for detailed design will begin after advanced planning and siting analysis are completed as part of the Long‐Range Facilities Plan Update. Recommendations from the Long Range Facilities Plan Update, anticipated to be completed in 2027, will help determine the direction the RWQCP will pursue to address this item. Wastewater Treatment Fund Projects – Page 2 of 4 Wastewater Treatment Fund Projects Status as of June 2024 Outfall Line Construction (WQ‐19000) Prior Years Actuals Total Project Budget $0 $17,923,113 Implementing Department Public Works Project Phase Project Completion Design Summer 2026 Project Status: This project consists of the construction of a new parallel outfall pipe to convey final plant effluent to San Francisco Bay. A re‐design of the pipeline is needed to accommodate a potential future runway shift at Palo Alto Airport. Staff is currently working with the Federal Aviation Administration (FAA) to gain FAA concurrence for the pipeline construction and permanent easements on Airport property. The re‐design is anticipated to begin in fall 2024, moving immediately to construction upon design completion. Plant Master Plan Prior Years Actuals Current Year Budget $5,958,554 $442,587 Implementing Department Public Works Project Phase Project Completion Construction Winter 2028 (WQ‐10001)Project Status: This project enables the ongoing program management support for major capital projects. Current tasks include developing scopes of work, evaluating consultant proposals, coordinating project management activities, pursuing State low‐interest loans for multiple projects, and updating partner agreements. The consultant provides support for coordination of the construction contracts in progress, as well as any tasks and projects associated with the Long‐Range Facilities Plan (LRFP), with a contract that expires in 2028. Primary Prior Years Actuals Total Project Budget $20,449,644 Project Status: This project enabled the design and construction for new protective coatings on each of the four Implementing Department Public Works Project Phase Project Completion Completed Summer 2024Sedimentation $14,653,675 Tank Rehabilitation concrete primary sedimentation tanks, with replacement of worn rotating parts and mechanical and electrical (WQ‐14003)equipment. These tanks were installed in 1972 and the recoating project will extend the concrete life for another thirty years. Construction began in summer 2021. Substantial completion was achieved on June 1, 2024. All remaining work associated with the punch List, including miscellaneous and small deficient contract work should be completed by summer 2024. Wastewater Treatment Fund Projects – Page 3 of 4 Wastewater Treatment Fund Projects Status as of June 2024 Secondary Treatment Upgrades Prior Years Actuals Total Project Budget $76,315,534 $193,317,009 Implementing Department Public Works Project Phase Project Completion Construction Summer2028 Project Status: This project upgrades the Secondary Treatment process at the RWQCP. The existing Secondary Treatment process has two main components, the Fixed Film Reactors (FFR) and the Activated Sludge (AS) Process. This project includes the reconstruction of the AS process, rehabilitation and reconfiguration of the AS Aeration Basins, the elimination of the FFRs, addition of denitrification capabilities, and replacement of equipment beyond its useful life. Construction began in winter 2023 with completion of new denitrification treatment and retirement of the FFR’s is expected in 2028. Construction is still in progress with much of the underground support infrastructure in place. Reconfiguration of the first AS Aeration Basin is anticipated in fall 2024. (WQ‐19001) Recurring Projects Plant Repair, Retrofit and Prior Year Actuals $5,804,943 Current Year Budget Implementing Department Project Phase Project Completion $10,141,002 Public Works N/A Recurring Equipment Replacement (WQ‐19002) Project Status: This project enables the assessment, repair, and retrofit of the RWQCP’s concrete and metal structures; the replacement of necessary equipment and ancillary facilities, including electrical equipment/systems, to maintain treatment reliability and existing infrastructure; and the replacement of large diameter flow meters built into the wastewater treatment system on sewers, pipes, and water lines. The Long Range Facility Plan (LRFP) Update consultant contract, to identify and prioritize repair, retrofit, or replacement of Plant infrastructure and equipment and the timing of such projects, was awarded in spring 2024. The contract will commence in summer 2024. Design of the 12 kV Electrical Loop Upgrade Project was completed in spring 2022. A construction contract for phase 1 was executed in winter 2023, with expected completion in summer 2024. Solicitation for Phase 2 construction will commence in summer 2024. Wastewater Treatment Fund Projects – Page 4 of 4 Water Fund Projects Status as of June 2024 One‐Time Projects Water Main Replacement Project 29 Prior Years Actuals Total Project Budget $3,888,047 $9,307,828 Implementing Department Project Phase Project Completion Utilities Construction Summer 2024 Project Status: This project will fund the design and replacement of structurally deficient water mains and appurtenances. Mains are selected by researching the maintenance history of the system and identifying those that are undersized, corroded, and/or subject to breaks. The project scope includes approximately 7,500 linear feet (which represents 0.6 percent of the City’s Water Distribution System) of mains and services on various streets within the City, including areas in the Evergreen Park and Ventura neighborhoods. Construction started in November 2023. The project is approximately 65% complete and is on target to be completed in August 2024. (WS‐15002) Water Main Replacement Project 30 Prior Years Actuals Total Project Budget $5,371 $9,350,000 Implementing Department Project Phase Project Completion Utilities Design Spring 2026 Project Status: This project will fund the replacement of structurally deficient water mains and appurtenances in Fiscal Year 2026. Mains are selected by researching the maintenance history of the system and identifying those that are undersized, corroded, and subject to breaks. The project scope includes approximately 10,000 linear feet (which represents 0.8 percent of the City’s Water Distribution System) of mains and services on various streets within the City, including areas in Midtown/Midtown West, Palo Verde, and Green Meadow neighborhoods. The design is approximately 30% complete at the end of FY 2024. (WS‐16001) Water Recycling Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion Utilities Pre‐Design Fall 2024Facilities$710,106 $852,674 (WS‐07001)Project Status: This project allows the City to hire a consultant to prepare a business plan, prepare preliminary design, and secure funding options for an expansion of the existing recycled water delivery system in the City. The expansion pipeline is one of several water reuse projects being considered in the Northwest County Recycled Water Strategic Plan. One Water Plan development is underway to evaluate alternative water supplies, define existing and future uncertainties and supply risks, and identify community needs and priorities. Funding contribution from Water Fund Projects – Page 1 of 5 Water Fund Projects Status as of June 2024 the Water Fund to the Recycled Water project has ended and funding for Operations and Maintenance will be reviewed for budget cycle FY 2027. Water Regulation Station Improvements (WS‐07000) Prior Years Actuals Total Project Budget $2,900,163 $2,960,477 Project Status: The project for Water Regulation Station Improvements included seismic upgrades, piping improvements and other various upgrades to increase the structural reliability of two of the City’s turnouts with SFPUC. Work under this project includes Seismic Upgrades of California Avenue and Page Mill Road Turnouts. City Council approved this project and the construction was completed in May 2024. Implementing Department Project Phase Project Completion Utilities Completed Spring 2024 Water Tank Seismic Upgrade $9,944,241 Prior Years Actuals Total Project Budget $26,989,834 Implementing Department Project Phase Project Completion Utilities Construction Fall 2028 and Rehabilitation (WS‐09000) Project Status: This project for Seismic Water System Upgrades includes seismic upgrades at the Montebello, Mayfield, Corte Madera, Park, Boronda, and Dahl Reservoirs in compliance with the American Society of Civil Engineers (ASCE 7) seismic codes. Mayfield Reservoir was seismically retrofitted in 2011. Seismic upgrades of Boronda and Montebello Reservoirs were completed in 2016 and 2018. The new concrete Corte Madera Reservoir was completed in April 2022. The Park Reservoir and Dahl Reservoir Tanks are scheduled next for retrofit or replacement. An Engineering and structural assessment of Park Reservoir was completed in spring 2023, and Dahl Reservoir will be assessed in 2025. The design for Park and Dahl Reservoir is expected to be completed by fall 2025. The retrofit and rehabilitation for both tanks are expected to be completed by the end of 2028. Recurring Projects Water Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Distribution $161,813 $646,029 Utilities N/A Recurring Water Fund Projects – Page 2 of 5 Water Fund Projects Status as of June 2024 System Improvements (WS‐11003) Project Status: This project enables improvements to water distribution system deliverability and reliability. Typical activities include installing restraining joints at critical pipelines and bridge crossings, increasing the size of inadequate facilities, system leakage surveys, network modeling, and fire flow studies or other system improvements as required. Continuous evaluation of system needs and making required improvements is necessary to maintain adequate quantities of quality water, meeting local, state, and federal safe drinking water standards. The Pump Station Painting project to paint the five foothill pump stations was completed in May 2024. Services for a full system leakage survey of the water distribution system will be solicited in 2024 and the work is expected to be completed by the end of 2025. Water, Gas, Wastewater Utility GIS Data (WS‐02014) Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $249,154 $513,400 Utilities N/A Recurring Project Status: This project enables contracts related to Utilities GIS (Geographic Information System) needs. AME database is heavily utilized by Utilities Engineering staff to update the utility information in GIS. The updated information is used by various City staff, such as marking/locating underground utilities to comply with USA (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects; verifying existing underground utilities during construction activities; creating customized utility map books for field crews and on‐call personnel to meet their specific needs. Annual surveying contracts collect GPS points of existing above‐ ground utility features within CIP project areas. The data being collected continues to be used to correct the GIS database. Accurate utility data helps the design to select new pipe alignment to minimize construction conflicts and provides data for additional road feature linework to be corrected in the older GIS/AVEC database via ESRI. Water General Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion Equipment/Tools $0.00 (WS‐13002) $50,000 Utilities N/A Recurring Project Status: This project acquires new equipment and tools, the replacement of existing fusion equipment, and other associated tools. The fusion equipment is used to fuse together pipe joints in the City's water distribution system. Equipment and tools are required to be upgraded on an annual basis to maintain high quality standards Water Fund Projects – Page 3 of 5 Water Fund Projects Status as of June 2024 for the installation of the City's water distribution mains, along with the associated service standards and worker safety and productivity measures. There were no purchases of equipment or tools in the second half of FY 2024. Water Meters Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion (WS‐80015)$2,801,577 $1,599,821 Utilities N/A Recurring Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable. This funding also allows for annual testing and calibration of selected meters to maintain meter accuracy and reliability. During the AMI implementation process, approximately 50% of the meters will be replaced, with a focus on meters more than twenty years old. Staff is currently testing large diameter meter sets. Staff will begin testing a batch of additional meters in the first half of FY 2025. Water Service and Hydrant Replacement (WS‐80014) Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $152,163 $400,000 Utilities N/A Recurring Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goosenecks, and fire hydrant valves and assemblies per the Fire Department’s flow testing, upgrades fire hydrants in main line replacement project areas, replaces damaged fire hydrants, and replaces existing undersized or deteriorated copper water services on an as needed basis. Staff has been working on an extensive valve audit and to date have operated and evaluated approximately 74% of the City’s 6,500 water valves. This project will be increasing work to replace inoperative and leaking valves identified during this audit process. This project will be increasing work to replace inoperative and leaking valves identified during this audit process. In addition, the City will be doing additional work to look for possible lead whips in our distribution system as we continue to comply with the new lead and copper rule revisions (LCRR). Water Fund Projects – Page 4 of 5 Water Fund Projects Status as of June 2024 Water System Customer Connections (WS‐80013) Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $1,187,207 $932,000 Utilities N/A Recurring Project Status: This project allows for improvements that include new main extensions, valves, domestic services, meters on upgraded services, backflow devices, fire services, and fire hydrants. System extensions are required to provide service to new large developments and to serve existing customers requesting expanded service on Development Services projects. A total of 46 water services were installed in the second half of FY 2024. Water System Supply Improvements (WS‐11004) Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion $23,648 $3,617,000 Utilities N/A Recurring Project Status: This project evaluates and improves the City’s water distribution system on an as‐needed basis. This project includes piping modifications, equipment replacements associated with water delivery, supervisory control software upgrades, system modifications for water system quality compliance, conditional assessment of the reliability of transmission mains, and security system installations. The water system includes the connection facilities between the City’s and the San Francisco Public Utility Commission’s pipelines, emergency water wells within the City, pumping stations, water reservoirs, and pipelines. Security cameras will also be added to various tanks, pump stations, and turnouts as part of the Security Cameras project. Staff leased a mobile generator for Foothill pump stations in summer 2024 and purchased generators to be delivered by the summer 2025. Water Fund Projects – Page 5 of 5 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project installed a new automated gate at the Baylands Nature Preserve main entrance. The existing gate was manually opened and closed by staff each day for public access. The scope of work included an electrical transformer, trenching, wiring, and gate automation equipment. The project started June 24, 2024 and reached substantial completion on June 30, 2024. Baylands Nature Preserve Entrance Gate Parks and Open Space Community ServicesOS‐24000 Construction Spring Spring 2024 2024 $ $ 132,701.00 The Charleston Arastradero Corridor was reconfigured to provide new landscaped median islands, bulb outs, enhanced bike lanes, traffic signal improvements, and new street trees to complement the new lane configurations that were approved for permanent retention. Phase 1 (Arastradero Road between Foothill Expressway to Clemo Avenue), Phase 2 (Charleston Road from Alma Street to Middlefield Road) and Phase 3 (Arastradero Road from Los Palos Avenue to El Camino Real, Charleston Road from El Camino Real to Alma Street and from Middlefield Road to San Antonio Road) have all been completed as of spring 2024. Charleston Arastradero Corridor Project Traffic and TransportationPE‐13011 Construction Construction Public Works 20,788,951.00 This project funded the design and construction of high priority main replacement work, which reduces inflow of rainfall and groundwater into the collection system. The project replaced approximately 11,000 linear feet (which represents 1.0 percent of the City's Wastewater Collection System) for El Camino Real from Page Mill Road to Cesano Court, and Page Mill Road from Ramos Way to Ash Street. The project wais comprised of mains identified in video inspection work or through maintenance records as structurally deficient and in need of replacement. The work was in Caltrans (El Camino Real) and the County of Santa Clara (Page Mill Road) right‐of‐way. Construction was completed May 5, 2024. Wastewater Collection WC‐19001 System Rehabilitation Wastewater Collection Utilities Spring 2024 $8,635,244.00 Augmentation Project 31 This project enabled the design and construction for new protective coatings on each of the four concrete primary sedimentation tanks, with replacement of worn rotating parts and mechanical and electrical equipment. These tanks were installed in 1972 and the recoating project will will extend the concrete life for another thirty years. Substantial completion was achieved on June 1, 2024. Primary Sedimentation Tank Rehabilitation Wastewater TreatmentWQ‐14003 WS‐07000 Construction Construction Public Works Spring Spring 2024 2024 $ $ 20,449,644.00 2,960,477.00 This project for Water Regulation Station Improvements included seismic upgrades, piping improvements and other various upgrades to increase the structural reliability of two of the City's turnouts with SFPUC. Work under this project includes Seismic Upgrades of California Avenue and Page Mill Road Turnouts. Structural evaluation for restraining the Page Mill turnout and piping was included in the design. The construction was completed in May 2024. Water Regulation Station Improvements Water Utilities This project incorporated renovations to the Utilities Water Gas Wastewater (WGW) office space at the Municipal Service Center (MSC). The new work area includes a small reception area, a renovated kitchen and printer area, additional offices and cubicles, upgrades to the HVAC system, lighting improvements and fire life safety systems upgrade. Construction was completed in April 2023. Water, Gas, Wastewater Office Remodel Buildings and FacilitiesPE‐19001 Construction Public Works Spring 2023 $1,234,354.00 1 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project provided funding for the replacement of all extrication tools for the Fire Department. Extrication tools, also known as "Jaws of Life", are used to rescue victims of car accidents and other emergencies where the victims are trapped in confined spaces. Equipment was purchased in winter 2023 and the project is complete. Buildings and Facilities Fire DepartmentFD‐22000 Extrication Tool Replacement Procurement Winter Spring Spring 2023 2023 2023 $ $ $ 298,200.00 10,305,619.00 4,656,777.00 This project has replaced approximately 18,600 linear feet (which represents 1.6% of the City's water distribution system) of mains and 265 services on various streets in the City, including areas in the Duveneck, St. Francis, Barron Park and Charleston Meadows neighborhoods. Construction started in April 2022 and the project was substantially completed in spring 2023. Water Main Replacement Project 28WS‐14001 Construction Construction Water Utilities Utilities Airport This project included the design and construction of high priority mains with structural defects that could not be addressed with routine maintenance. The wastewater mains on various streets in the City were replaced with approximately 10,000 linear feet of HDPE sanitary sewer mains and associated laterals in the Ventura, Charleston Meadows, Fair Meadow, and Palo Verde neighborhoods. The project achieved substantial completion in April 2023. Wastewater Collection WC‐17001 System Rehabilitation Wastewater CollectionAugmentation Project 30 This project included the design and reconstruction of the Palo Alto Airport apron. The need to reconstruct the aircraft parking apron is critical to airport safety. Construction Phase I was completed in November 2017. Construction Phase II was completed in winter 2020. Construction on Phase III reached substantial completion in June 2023 Airport Apron ReconstructionAP‐16000 Construction Construction Airport Spring 2023 2022 $ $ 41,563,570.00 857,380.00 This project replace rubberized and synthetic turf surfacing in the playground and replace play Magical Bridge Playground equipment including swings, climbing net, and playhouse. An IFB was issued in November 2021 Parks and Open SpacePE‐21003 Rubber and Synthetic Turf and Council awarded a construction contract in spring 2022. Installation of rubberized and synthetic surfacing, replacement of climbing nets and renovation of the playhouse took place in fall 2022. Project was completed in December 2022. Public Works Fall Resurfacing This project designed and constructed approximately 21,700 linear feet (which represents 1.9% of the City's Gas distribution main system) of distribution main and 320 gas services constructed mainly of PVC material on various streets within the Midtown, Evergreen Park, Ventura, College Terrace, Charleston Terrace, and Research Park neighborhoods. Construction began in winter 2021and was completed in summer 2022 Gas Main Replacement Project 23GS‐13001 FD‐21000 Construction Procurement Gas Utilities Summer Summer 2022 2022 $ $ 7,951,858.00 237,500.00 This project replaced the entire complement of Automated External Defibrillators (AEDs) throughout City facilities and emergency response vehicles, which currently totals 93 AEDs. The RFP process was completed in fall 2021. The new AEDs were purchased and deployed in summer 2022. Automated External Defibrillator Replacement Buildings and Facilities Fire Department 2 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project replaced the existing MSC roofs. The existing asphalt and gravel roofs have reached the end of their useful life and needed to be replaced. The new roofs will meet current cool roofing codes to optimize energy efficiency. Construction was completed in November 2022. Municipal Service Center A, B, & C Roof Replacement Buildings and FacilitiesPF‐17000 Construction Public Works Fall 2022 2022 $ $ 2,013,475.00 1,050,443 This project installed capacitor banks at electric substations and on distribution lines to ensure Northern California Power Association Power Factor requirements are met. Capacitor banks EL‐16002 Capacitor Bank Installation were installed at Hanover Avenue, Hansen Way, Maybell Avenue, and Park Boulevard Substations. The project was substantially completed in June 2022 and will be commissioned and energized in summer 2022. Construction Electric Electric Utilities Spring Facility Relocation for EL‐17007 Caltrain Modernization Project The Utilities Department removed the overhead lines allowing for the installation of the Overhead Catenary System above the rails for the Caltrain Modernization. This project was completed in spring 2022 Construction Construction Utilities Spring Spring 2022 2022 $ $ 3,055,472 4,646,247 This project upgraded safety, site amenities, playground facilities, a new restroom, irrigation, drainage, and ADA accessibility improvements at Rinconada Park. These improvements were identified in the Rinconada Long Range Plan (LRP). Phase 1 of construction started in August 2021 and construction was completed in spring 2022. Rinconada Park Improvement Parks and Open SpacePE‐08001 Public Works This project reconfigured the distribution circuits to the substation transformer at Quarry EL‐14005 Reconfigure Quarry Feeders Substation. Design of QR 27 feeder replacement was completed in spring 2021. Construction Construction Construction Electric Utilities Fall Fall 2021 2021 $ $ 792,034 was completed in December 2021 . This project provided for the relocation of the Junior Museum and Zoo to Cubberley for two years while a new JMZ was being built, tenant improvements to the Cubberley Auditorium and Buildings and Facilities Community ServicesAC‐18001 JMZ Renovation then removal of tenant improvements post‐construction. Construction of the new Junior Museum and Zoo started in June 2018 and was completed in late 2021. The new Junior Museum and Zoo was opened to the public on November 12, 2021. 2,927,870.00 This project included a systems analysis and repaired the water proofing system in the High Street and Bryant Street parking garages. Water proofing repairs were completed in the High Street parking garage. Additional funding was added and the contractor completed waterproofing repairs in the subterranean stairwells in the Bryant Street garage in fall 2021. High and Bryant Street PE‐18002 Garages Waterproofing and Buildings and FacilitiesConstruction Construction Public Works Public Works Fall Fall 2021 2021 $ $ 264,235.00 22,889,453 Repairs As part of the 2014 Council Infrastructure Plan, this project designed and constructed a new pedestrian bridge across Highway 101 at Adobe Creek. Council approved a contract with Granite Construction in November 2019. Construction began in January 2020. The project construction completed on November 20, 2021, with a ribbon‐cutting ceremony and a community celebration. Highway 101 Pedestrian Bicycle Overpass Project Traffic and TransportationPE‐11011 3 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project undergrounded the existing overhead utility systems in the area along the 400 block of West Charleston and El Camino Real. Staff completed cable, equipment installation and 100% of customer service conversions. The construction for the final phase of the project to install two 60 foot tall steel poles and to reconductor the 60 kV sub‐transmission lines was completed in the fall 2021. Underground District 46 CharlestonEL‐12001 Construction Electric Utilities Fall 2021 $3,904,425 This project improved the Pearson Arastradero Preserve parking lot by improving the base rock surfacing, adding drainage, widening the entrance for safety, and new fencing. This new improvement will allow the overflow parking area to be open year round. The work was completed in May 2021. Pearson Arastradero OS‐18001 Preserve Parking lot Parks and Open Space Community ServicesConstruction Study Spring Spring Spring 2021 2021 2021 $ $ $ 170,300 926,792 350,000 Improvement Cubberley Community Center Master Plan This project developed the master plan for future use of the Cubberley Community Center site by the City and Palo Alto Unified School District. Buildings and Facilities Community ServicesCB‐16001 CB‐19001 This project replaced the Building management System(BMS) controls for the pavilion, Theater, Wing I, and Gyms A and B boiler rooms at the Cubberley Community Center. The project included the installation of control points for each building along with controllers, valve and damper actuators. Cubberley Building Management Systems Buildings and FacilitiesConstruction Public Works Fire Ringdown System Replacement This project replaced the current ring down system that provides an audible alert of calls in the fire stations. Ongoing installations started in 2018 and were completed with Fire Station #3. Buildings and FacilitiesFD‐14002 PD‐14000 Construction Construction Fire Departent Spring Winter Spring Winter 2021 2021 2021 2021 $ $ $ $ 400,144 77,569 94,500 146,466 Internal Alarm System Replacement The project replaced the citywide internal alarm system. The alarms at City Hall migrated to this new system in FY 2019, but was completed in early 2021. Buildings and Facilities Police Department Self Contained Breathing FD‐20001 Apparatus (SCBA) Air This project replaced the central air compressor that provides air for the self‐contained breathing apparatus (SCBA) tanks to ensure firefighter safety when entering environments with hazardous Construction air quality. Buildings and Facilities Fire DepartmentCompressor Replacement Airport Electrical Improvements This project replaced the outdated electrical panels for the Palo Alto Airport office rental spaces. Construction was completed in January 2021.AP‐20000 PE‐18000 Construction Construction Airport Public Works Public Works This project built the California Avenue Area Parking Garage, as part of the 2014 Council Infrastructure Plan. The parking garage has 627 parking spaces with 2 basement levels and 4 above grade floors. The garage features an automated parking space guidance system, EV charging stations, bicycle parking, and motorcycle parking. The garage was opened to the public on December 8, 2020. New California Avenue Area Parking Garage Buildings and Facilities Fall Fall 2020 2020 $ $ 50,119,976 187,064 This project updated the individual sleeping quarters in the firehouse to address gender issues and privacy concerns. Fire Station #1 was the only fire station in the City that did not have separate bedrooms to accommodate male and female firefighters. This project was completed in fall 2020. Buildings and FacilitiesPF‐14002 Fire Station 1 Improvements Construction Public Works 4 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project replaced gas services laterals constructed of Acrylonitrile‐butadiene‐styrene (ABS) or Tenite material on various streets. Council approved funding in June 2019. The project replaced 104 ABS and Tenite gas services. The WQCP ABS gas service is assigned to Utility Operations for replacement and the remaining five ABS gas services will be scheduled for replacement once the five‐year moratorium ends on those streets. As of November 2020, this project is complete. Gas ABS/Tenite Replacement ProjectGS‐18000 Construction Gas Utilities Fall Fall 2020 2020 $ $ 2,615,100 2,976,813 This project replaced 1,750 linear feet of storm drain with 48‐inch diameter High Density Polyethylene (HDPE) pipe and associated catch basins, laterals and manholes. In addition to underground work, additional street restoration and concrete work was completed. Work includes resurfacing one full lane on Loma Verde from the beginning to the end of the project limits, replacement of driveways, sidewalk, and 718 linear feet of curb and gutter. The contract was awarded in June 2020, construction work began in August 2020, and was completed in December 2020. Loma Verde Avenue Trunk Line ImprovementsSD‐19000 WS‐19000 Construction Storm Drain Utilities This project is part of the City’s recent Seismic Upgrade and Emergency Water Supply and Storage Projects. The reservoir was drained in 2012 for approximately two years to allow extensive seismic rehabilitation work to be performed and construction of a new pump station. Subsequently hairline cracks were sealed in the reservoir. A geotechnical consultant was hired to Construction evaluate the tank foundation. This study was completed and there were several options identified. Staff has completed the design and construction of the vent screen replacement and crack sealing. Mayfield Reservoir Subgrade and Venting Repair Water Utilities Utilities Utilities Fall Fall Fall 2020 2020 2020 $ $ $ 600,000 3,649,356 4,434,839 This project undergrounded the existing overhead distribution system in the area bounded by Middlefield Road, Homer Avenue, Webster Street, and Addison Avenue. Installation of substructures and utility electric system is completed. Where possible, the overhead electric lines were removed and poles cut down to the level of the communication lines. Underground District 47 EL‐11010 Middlefield, Homer,Construction Electric Webster, Addison This project replaced of 8,972 linear feet of wastewater mains. The sanitary sewer mains, laterals, and manholes to be rehabilitated or replaced in this project are located in the Charleston Meadows neighborhood. Construction started in February 2020 and was suspended for almost 3 months due to COVID‐19 County’s Shelter‐in‐Place Order. The project is complete as of December 2020. Wastewater Collection WC‐16001 System Rehabilitation Augmentation Project 29 Wastewater CollectionConstruction This project modernized the existing elevators at parking Lot J. The project involves upgrading the interior of the elevators, elevator control interface, call buttons, and meeting current ADA standards. Construction started in April 2019. Project is complete except for the State final inspection on the second car. State is behind because of COVID, but the inspection should be done by the end of July 2020. Parking Lot J Elevator Modernization Buildings and FacilitiesPF‐18000 Construction Construction Public Works Public Works Spring Winter 2020 2020 $ $ 781,324 This project replaced the existing Fire Station at Embarcadero Road and Newell Road with a new PE‐15003 Fire Station 3 Replacement structure that meets essential services standards and current program needs. Construction Buildings and Facilities 10,080,258 completed in March 2020. 5 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date This project included the recoating of four steel tanks. Work under this project was included in the Seismic Upgrade of four Steel Tanks and the three Turnout Projects. Once construction started, it was found that the Montebello Reservoir was in very poor condition. Due to escalating Construction costs associated with roof replacement, staff decided to complete construction of the Montebello Reservoir and re‐evaluate the remaining three tanks for replacement. Water Reservoir Coating ImprovementsWS‐08001 Water Utilities Spring 2020 $2,141,172 This project replaced approximately 9,600 linear feet of structurally deficient, aging, or corroded water mains and services along the mains on Sand Hill Road, Oak Creek Drive (5%) and Fulton Avenue. Water Main Replacement ‐ Project 27WS‐13001 Construction Construction Water Utilities Utilities Spring Spring 2020 2020 $ $ 7,786,998 5,665,897 This project enabled the design and construction of a high priority wastewater main and lateral replacement work to reduce inflow of rainfall and ground water into the collection system. The project replaced or rehabbed a total of 7,655 linear feet of wastewater mains located in the Leland Manor/Garland, Midtown West, and Lower Page Mill/Los Altos Hills areas of the City. Wastewater Collection Wastewater CollectionWC‐15001 System Rehabilitation Augmentation Project 28 This project met the growing electric needs of the VA Hospital. Staff has had numerous discussions with VA Hospital on electric load growth at the hospital and anticipated needs from the utility. Much of the cost is reimbursed to the City by the VA Hospital. Staff has prepared preliminary designs for interim solutions and is awaiting additional information from VA to develop long range plans to meet their future needs. VA Hospital ‐ Customer Load RequirementsEL‐17003 Design Electric Utilities Spring 2020 $84,984 This project added electronic security systems at utility sites to protect equipment at electric substations, water pumping plants, reservoirs, and gas stations from intrusion and vandalism. Cameras and detection systems have been installed at nine electric substations, three water stations, and one natural gas station to monitor facilities. Utility Site Security ImprovementsEL‐04012 EL‐11008 Construction Construction Electric Electric Utilities Utilities Spring Spring 2020 2020 $ $ 1,644,681 149,023Rebuild Underground District This project rebuilt and replaced the underground electric system in Underground District 19, the 19 area bounded by Forest Avenue, Waverley Street, Addison Avenue, and Alma Street. This project replaced Self Contained Breathing Apparatus equipment (SCBA) used by firefighters when entering hazardous conditions when responding to fire and hazardous materials incidents. The SCBA provides breathable air for firefighters when entering environments where the atmosphere is immediately dangerous to life or health. The expected service life for SCBAs is 15 years. Self Contained Breathing Apparatus Replacement Buildings and Facilities Fire DepartmentFD‐18000 Purchase Spring 2020 $799,999 6 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Purchase Fund Source Department CMR Date This project replaced the entire complement of twenty cardiac monitors in the Department. Along with other tools needed for patient assessment and airway verification, cardiac monitors assess cardiac activity in patients and provide defibrillation and pacing. Cardiac Monitor Replacement Buildings and Facilities Fire DepartmentFD‐20000 PL‐16001 Spring Fall 2020 2019 $ $ 850,000 Downtown Mobility and Safety Improvements This project included the construction of curb extensions and the installation of new pedestrian signal heads and traffic signal modifications in 2019 as part of the Upgrade Downtown project. Traffic and Transportation Transportation Office ofConstruction 1,819,847 This project replaced the Thermal Imaging Cameras (TICs) on all fire and response vehicles used to help identify the location of victims; assess the source of fires, smoke, and heat; to assist in creating a plan of action. Thermal Imaging Cameras Replacement Buildings and Facilities Fire DepartmentFD‐20002 Purchase Fall 2019 $99,000 Wastewater Collection WC‐11000 System Rehabilitation This project addressed areas that were identified in Wastewater Capital Improvement Project 17 (Cleaning and Video Inspection of the Collection System) as needing rehabilitation. This project was combined with Project 25 and 26(WC‐12001; WC‐13001). Wastewater CollectionConstruction Utilities Utilities Fall Fall Fall 2019 2019 2019 $ $ $ 3,131,595 3,309,998 1,851,708 Augmentation Project 24 Wastewater Collection WC‐13001 System Rehabilitation Augmentation Project 26 This project was combined with Project 24 and 25(WC‐11001; WC‐12001). All new service laterals were installed from the new sewer main to the new sewer cleanouts located in the City’s Construction right‐of‐way. Wastewater Collection Cubberley Track and Field Replacement Parks and Open SpaceCB‐19000 PE‐14018 This project replaced the synthetic turf field, installed an all‐weather track and a fitness area.Construction Public Works Baylands Boardwalk Improvements Buildings and FacilitiesThis project replaced the existing boardwalk with similar alignment and configuration.Construction Construction Public Works Public Works Winter Winter 2019 2019 $ $ 2,123,681 494,818This project improved the Administrative Services Department offices on the fourth floor of City Hall. Buildings and FacilitiesPE‐17009 City Hall Floor 4 Remodel Lucie Stern Buildings PE‐14015 Mechanical and Electrical Upgrades This project replaced and upgraded the mechanical, electrical, and fire/life safety systems at Lucie Stern Children’s Theater, Lucie Stern Community Theater, and Lucie Stern Community Center. Buildings and FacilitiesConstruction Public Works Spring 2019 $6,142,607 Planning and Community Environment Quarry Road Improvements This project included planning, design and construction of bicycle and pedestrian improvements Traffic and TransportationPL‐16000 EL‐17008 Construction Construction Spring Winter 2019 2019 $ $ 5,148,378 499,997 and Transit Center Access along Quarry Road. Utility Control Center Upgrades This project upgraded the Utility Control Center working environment.Electric Gas Utilities Gas Main Replacement Project 22 This project replaced approximately 23,700 linear feet of gas mains and services along University Avenue and other streets in the Downtown North nieghborhood.GS‐12001 Construction Construction Utilities Spring Spring 2019 2019 $ $ 11,658,997 3,211,998 Wastewater Collection WC‐12001 System Rehabilitation /This project was combined with Project 24 and 26 (WC‐11001; WC‐13001) replacing 45,294 linear feet of sanitary sewer mains in university South, Professorville and Old palo Alto neigborhoods. Wastewater Collection Utilities Augmentation Project 25 7 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Construction Construction Construction Fund Source Department Public Works Utilities CMR Date Dewatering and Loadout Facility This project provides funding for the design and construction of the sludge dewatering facility and truck loadout to retire existing dewatering and sewage sludge incinerators. Wastewater TreatmentWQ‐14001 WS‐12001 Spring Spring 2019 2019 2018 $ $ $ 27,497,551 7,506,161 525,000 Water Main Replacement – This project replaced approximately 11,000 linear feet of aging water mains and services which Project 26 Waterincluded water main replacement as part of the Upgrade Downtown Project. This project improved the Planning and Community Environment (PCE) Department offices on the fifth floor of City Hall. Buildings and FacilitiesPE‐17009 City Hall Floor 5 Remodel Public Works Summer Baylands Nature Interpretive This project replaced worn out or non‐functioning exhibits at the Baylands Nature Interpretive Center Exhibit Improvements Center. Buildings and Facilities Community ServicesAC‐14001 PE‐17000 PD‐14000 Construction Construction Construction Summer Summer Summer 2018 2018 2018 $ $ $ 56,000 250,000 78,000 Mitchell Park Adobe Creek Bridge Replacement Parks and Open SpaceThis project replaced the existing bridge over Adobe Creek in Mitchell Park.Public Works PoliceInternal Alarm System Replacement This project replaced the citywide system of panic alarms from various departments and the Council chambers. Buildings and Facilities Maybell 1&2 4/12kV ConversionEL‐14004 GS‐15001 This project converted circuits 1 & 2 at Maybell substation from 4kV to 12kV.Construction Construction Electric Gas Utilities Utilities Fall 2018 2018 $ $ 364,796 150,000Security at City Gas Receiving Stations This project equiped the City’s four Gas Receiving Stations with video surveillance systems.Summer Matadero Creek Storm SD‐13003 Water Pump Station and This project upgraded the capacity to the Matadero Creek Storm Water Pump Station, which serves a low‐lying 1200‐acre area of southeastern Palo Alto.Construction Storm Drain Airport Public Works Summer 2018 $6,685,317 Trunk Line Improvements Wildlife Hazard Management The Wildlife hazard Management Plan identified the specific actions the airport will take toAP‐16002 Study Construction Study Public Works Utilities Summer Winter Spring 2018 2018 2018 $ $ $ 63,415 4,022,455 167,741 Plan mitigate the risk of wildlife strikes on or near the airport. Wastewater Collection WC‐14001 System Rehabilitation This project replaced 16,859 linear feet of sanitary sewer mains of various sizes on various streets. Wastewater CollectionAugmentation Project 27 Buckeye Creek Hydrology Study This project analyzed flooding conditions and recommended flood control structures and drainage and erosion control solutions for the creek located within Foothills Park. Parks and Open SpacePG‐15000 Public Works CalTrain Corridor Video PE‐17004 Management System This project replaced two existing gateway signs in the right‐of‐way for the California Avenue business district. Streets and SidewalksConstruction Public Works Spring 2018 $1,550,000 Installation 8 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Department CMR Date Parking Lot Q Elevator Modernization Buildings and FacilitiesPF‐16003 PE‐13003 This project modernized the existing elevator at Parking Lot Q.Construction Study Public Works Fall Fall Fall Fall Fall Fall 2017 2017 2017 2017 2017 2017 $ $ $ $ $ $ 170,608 627,057Parks, Trails, Open Space, and Recreation Master Plan parks, trails, open space and recreational programs. This master plan provided guidance on the recreation and improvement needs for Palo Alto’s Parks and Open Space Community Services This project developed a plan for short, medium and long range improvements to the regional Parks and Open Space Community ServicesPE‐12003 Rinconada Park Master Plan park including the consideration of pathways, new restrooms and playgrounds, new landscaping,Study 541,355 and revitalization of underutilized areas within the park. The project developed an inventory of all City‐owned bridges and culvert structures, condition assessment, cost estimate for rehabilitation, and recommendation for future inspection frequencies, assessment and improvements. Structural Assessment of City Bridges Buildings and FacilitiesPE‐13012 Study Public Works Utilities 198,529 Wastewater Collection WC‐11000 System Rehabilitation / Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of various sizes, 779 sewer laterals, and 121 sewer manholes. Wastewater CollectionConstruction Construction 3,119,806 3,361,118 Augmentation Project 24 Wastewater Collection WC‐13001 System Rehabilitation / Augmentation Project 26 Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of various sizes, 779 sewer laterals, and 121 sewer manholes. Wastewater Collection Utilities Golf Reconfiguration and PG‐13003 Baylands Athletic Center Improvements This project completed the rehabilitation of the Palo Alto Municipal Golf Course, including a new layout for the course, new prefabricated restroom, new water‐saving turf and irrigation system, and rebranded the course as the Baylands Golf Links. Parks and Open SpaceConstruction Construction Public Works Utilities Fall 2017 2017 2017 $ $ $ 13,675,177 2,364,937 5,445,069 Gas Main Replacement –GS‐11000 WS‐11000 This project combined with GWR 19B & GMR 20 and replaced ABS gas mains and services.Gas Winter Winter Project 21 This project provided installation of approximately 11,869 linear feet of new High Density Polyethylene (HDPE) water mains, 232 new HDPE water services, and 15 new fire hydrants within Construction the City limits. Water Main Replacement – Project 25 Water Utilities The 2015 Water System Master Plan identified present capital improvements and replacement WS‐15004 Water System Master Plan rates required to ensure optimal reliability levels of service to the existing distribution and transmission systems. Study Water Utilities Utilities Utilities Spring Winter Spring 2017 2017 2017 $ $ $ 500,000 1,272,289 696,918 Wastewater Collection WC‐10002 System Rehabilitation / Augmentation Project 23 Combined with Project 22 (WC‐09001). This project replaced and/or rehabilitated approximately 33,497 linear feet of sanitary sewer mains of various sizes, 554 sewer laterals, and 102 sewer manholes. Wastewater CollectionConstruction Construction Street Light System Street EL‐10009 Light System Conversion Project This project converted HPS streetlights to LED and the conversion of approximately 4500 cobrahead streetlight fixtures.Electric 9 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Electric Department Utilities CMR Date Sand Hill / Quarry 12kV InterTieEL‐13006 EL‐15001 This project installed new wire to connect circuits QR‐24 and QR‐27 in the Sand Hill/Quarry area. Construction Winter Winter Fall 2017 2017 2016 2016 2016 $ $ $ $ $ $ $ $ $ $ $ $ 208,648 400,000 1,499,979 94,419 Electric Substation Battery Replacement This project replaced the batteries in all nine of the City's electric substations. This project replaced the synthetic turf at the Stanford/Palo Alto Playing Fields. Construction Construction Construction Construction Construction Construction Construction Construction Construction Construction Construction Electric Utilities Stanford/Palo Alto Playing Parks and Open Space Community ServicesPG‐13001 Fields Soccer Turf Replacement Park Maintenance Shop Remodel This project renovated and remodeled the Parks maintenance shop for safety and efficienciency upgrades. Parks and Open Space Community ServicesPG‐09003 PE‐12017 Summer SummerCity Hall First Floor Renovations This project installed new elevator control panels and replaced the gray‐painted panels inside the elevators. Buildings and Facilities Public Works Public Works Public Works 3,974,963 156,254 889,452 421,126 334,607 440,000 3,247,248 65,000 This project created a temporary main Library to be used while the new one was being constructed. Buildings and FacilitiesPE‐11012 Temporary Main Library The project replaced decking, railings, structural framing members, exterior wood flooring, and cabinetry, restroom reconfiguration, and provided Americans with Disabilities Act (ADA) improvements. Baylands Nature Interpretive Center Facility Improvement Buildings and FacilitiesPE‐15029 Spring Summer Fall 2017 2016 2016 2017 2016 2017 This project improved the children’s playground and included park amenity upgrades such as new playground equipment, a new retaining wall, surfacing and pathway upgrades, planting restoration and irrigation renovations, and replaced of damaged wood benches and the playground perimeter fence. Parks and Open Space Community ServicesPE‐13008 Bowden Park Improvements PE‐13020 Byxbee Park Trails Parks and Open SpaceThis project provided trail and site amenities over the remaining area of the landfill cap.Public Works Public Works Public Works This project improved the Utilities Department administrative offices on the third floor of City Hall. It included new carpet, wall reconfiguration, a kitchenette, cabinets, paint, soundproofing, office furniture, doors, and associated building systems. Buildings and FacilitiesPE‐17002 City Hall Floor 3 Remodel Spring Summer Winter Lucie Stern Buildings PE‐14015 Mechanical and Electrical Upgrades – Phase 1 This project replaced and upgraded the mechanical, electrical, and fire/life safety systems at Lucie Stern Children’s Theater, Lucie Stern Community Theater, and Lucie Stern Community Center. Buildings and Facilities Sarah Wallis Park Improvements This project improved site amenities with new concrete pathways, replaced old furnishings, and upgraded landscape with drought tolerant species. Parks and Open Space Community ServicesPG‐12004 10 List of Completed Projects Season Completed Completed Year Total Project Budget **CIP #Project Name Project Description Project Type Fund Source Airport Department Public Works Public Works Utilities CMR Date This project replaced the perimeter fencing and gates surrounding the Palo Alto Airport boundaries to prevent unauthorized access to the airport runway in accordance with Federal and Construction State standards. AP‐16003 Airport Perimeter Fence Spring Winter Summer Winter Winter 2017 2016 2016 2016 2016 2015 $ $ $ $ $ 2,003,540 7,676,275 149,500 150,000 464,433 Channing Avenue/Lincoln SD‐11101 Avenue Storm Drain Improvements This project installed of 5,800 linear feet of 36‐inch to 60‐inch diameter storm drain along Channing and Lincoln Avenues over three project phases to increase drainage system capacity.Construction Study Storm Drain GasGas Distribution System Model This project included the development, model installation, testing, documentation, and staff training of a natural gas distribution system model.GS‐14004 AC‐14000 Art Center Auditorium Audio, This project replaced outdated audio visual equipment and furnishings following the Visual and Furnishings Buildings and Facilities Community ServicesConstruction Construction Construction auditorium’s use as a temporary library. This project renovated the Rinconada Pool locker room including the changing area, restrooms, and showers in the women's and men's locker rooms. Buildings and FacilitiesPF‐15000 Rinconada Pool Locker Room Public Works This project installed new athletic fields, synthetic turf, field lighting, fencing, a new restroom,Parks and Open Space Community ServicesPE‐13016 El Camino Park Restoration scorekeeper booth and storage buildings, an expanded parking lot, new bike and pedestrian Fall $5,611,122 pathways, landscaping, benches, and other amenities. Notes: ** Final Project Actuals may be different from Total Project Budget amounts Grand Total $406,517,673 11