Loading...
HomeMy WebLinkAboutStaff Report 2308-19562 9 8 6 City Council Staff Report From: City Manager Report Type: INFORMATION REPORTS Lead Department: Public Works Meeting Date: April 22, 2024 Report #:2308-1956 TITLE Semiannual Update on the Status of Capital Improvement Program Projects; CEQA Status – Not a Project RECOMMENDATION This report is provided for information only and requires no Council action. EXECUTIVE SUMMARY The City Council and Palo Alto community can be proud of the City’s capital improvement program (CIP). The CIP represents major investments in infrastructure functionality and sustainability, funded largely through the 2014 Council Infrastructure Plan as well as utility rates and various other sources. The 2024-2028 five-year CIP totaled $1.2 billion for 209 projects as reviewed by the Council in its adoption of the FY 2024 Capital Budget. Since July 2016, the City of Palo Alto has completed 96 individual community-serving projects totaling over $353 million in improvements. A summary of all completed CIP projects is provided at the end of Attachment A. The CIP also represents a major effort for much of the City workforce. The following table summarizes the status of all projects for the six-month period of July to December 2023. 2 9 8 6 One Time CIPCapital Improvement Fund Recurring CIP Pre-Design Design Procurement Construction Completed Buildings and Facilities 10 3 15 0 7 0 Parks and Open Space 9 2 12 0 2 0 Streets and Sidewalks 8 0 3 0 0 0 Traffic and Transportation 5 1 6 2 2 0 Airport 0 0 3 2 1 0 Electric 9 3 10 0 4 0 Fiber Optics 2 0 2 0 0 0 Gas 4 0 1 0 1 0 Stormwater Management 2 0 3 0 3 0 Water 7 1 1 0 3 0 Wastewater Collection 4 0 0 0 1 0 Wastewater Treatment 1 1 4 0 4 0 Subtotals 61 11 60 4 28 0 Total 164 BACKGROUND This report provides Council with an update on the status of capital improvement program (CIP) projects, with detailed and useful information for the Council and public regarding general fund and enterprise fund projects that appear on Council agendas and will be visible throughout the community. The report does not include Internal Service Funds projects (Information Technology and Vehicle). ANALYSIS Project Update Organization The City of Palo Alto has a robust capital improvement program, and many individual projects are in progress at any given time. The 2024-2028 five-year CIP totaled $1.2 billion for 209 projects as reviewed by the Council as part of the adoption of the FY 2024 Capital Budget. The attached CIP project tables are intended to provide Council with a quick overview of each project, including budgetary information, the anticipated completion date, a brief description of the project scope, the status of the project, and upcoming activities including Council actions. Also included in the report is a list of all completed projects since the introduction of the Infrastructure Management System. Major/Significant Projects Summary The 2014 Council Infrastructure Plan is a major focus of staff’s capital improvement program efforts and ties to several 2024 City Council Priorities and related objectives. The following table details the Total Project Budget and Total Actual Expenses through February 26, 2024, for the Infrastructure Plan projects. 2 9 8 6 Council Infrastructure Plan Projects CIP Number Project Update Total Project Budget Total Actual Expenses* New Public Safety Building PE-15001 Construction is underway with completion expected in spring 2024.$118,137,997 $105,703,406 Bicycle and Pedestrian Transportation Implementation Plan PL-04010 This project funds the Bicycle and Pedestrian Transportation Plan Update, which has kicked off recently and is slated to take approximately 18 months to complete. This project also funds the implementation of various bicycle and pedestrian projects. Currently, one of the projects is the Embarcadero Road Improvements Project (from Emerson to High Street), which provides improvements on both the north and south sides of Embarcadero Rd., from Emerson to High Street. Improvements include intersection improvements at Emerson and Kingsley; landscaping, new pedestrian level lighting; and bicycle and pedestrian enhancements. Final Design is currently being completed, and the project will be ready to bid for construction in 2024. $15,293,904 $9,679,699 New Downtown Parking Garage PE-15007 Council directed staff to look at the feasibility of partnering with a private entity to develop new parking using downtown in-lieu parking fees in conjunction with housing or other uses, including the use of City surface lots or privately held parcels. A Request for Information was issued in December 2022 and staff reviewed proposals and held interviews in May 2023. Council gave direction to staff in December 2023 to advance the project in conjunction with advancement of affordable housing in the Downtown area. $7,488,918 $1,440,311 New California Avenue Area Parking Garage PE-18000 Completed $50,213,486 $49,411,201 Charleston Arastradero Corridor Project PE-13011 Phase 1 & 2 improvements are complete. Phase 3 construction is underway with completion expected spring 2024. $20,788,951 $20,112,144 Fire Station 3 Replacement PE-15003 Completed $10,588,654 $10,588,654 Highway 101 Pedestrian/Bicycle Overpass Project PE-11011 Completed $23,718,769 $23,718,769 2 9 8 6 Fire Station 4 Replacement PE-18004 Received Architectural Review Board approval in October. Council approved a construction management contract in December 2023 and 90% construction documents are expected in early 2024. $15,329,846 $1,003,046 Byxbee Park Completion PE-18006 On hold pending completion of Baylands Comprehensive Conservation Plan.$3,699,189 $368,192 Downtown Automated Parking Guidance Systems PL-15002 Council approved a design build contract in May 2023. Design for the four garages started in summer 2023 and construction is expected to be completed in fall 2024. $5,197,833 $1,141,499 The last phases of the Charleston/Arastradero Corridor project and the Public Safety Building project are expected to be completed in spring 2024. Current Infrastructure Plan project schedules can be found at https://www.infrastructure.cityofpaloalto.org/ Key considerations for the information presented in the project update tables include: •Project status information is current as of December 2023. •The individual project tables align with the Capital Improvement Fund categories in the Fiscal Year 2024-2028 capital budget: Buildings and Facilities, Parks and Open Space, Streets and Sidewalks, and Traffic and Transportation. •Enterprise Fund projects follow the order of their respective Fund in the capital budget. •Department Technology Upgrades and Improvements projects and Cubberley Property Infrastructure Fund projects are included in the Buildings and Facilities table. •Additional project information is available in the Fiscal Year 2024-2028 capital budget. •Each project table is divided into a section for one-time projects and a section for recurring projects that have ongoing annual funding. •Budgetary figures include staff oversight costs for projects to which staff costs have been allocated. •The table of completed projects, provides a summary of all CIP projects completed since the Biannual CIP updates to council began in 2016. The data is sorted from most recent to oldest. Completed Projects There were no completed one-time projects in the first half of Fiscal Year 2024 (July through December 2023). One-time projects do not include the significant amount of annual work completed under ongoing recurring projects, such as streets and sidewalks repairs, parking lot maintenance, roofing replacements, and regular maintenance of Utilities assets. 2 9 8 6 One-Time Projects Under Construction The twenty-eight projects that are currently underway include the following: Capital Improvement Fund (general fund): •Boulware Park Improvements (PE-17005) •Cameron Park Improvements (PG-14002) •Charleston-Arastradero Corridor Project (PE-13011) •Churchill Avenue/Alma Street Railroad Crossing Safety Improvements (PL-20000) •City Facilities Assessment and Record Plan Management System (PE-20002) •Civic Center Fire Life Safety Upgrades (PE-18016) •Civic Center Waterproofing Study and Repairs (PE-15020) •Homekey Facilities (PE-24005) •JMZ Renovation (AC-18001) •New Public Safety Building (PE-15001) •Roth Building Rehabilitation Phase 1 (PF-23001) Airport Fund •Airport Layout Plan (AP-21000) Electric Fund •Inter Substation Line Protection Relay (EL-17005) •Foothills Rebuild Fire Mitigation (EL-21001) •Smart Grid Technology Installation (EL-11014) •Substation Physical Security (EL-16003) Gas Fund •Gas Main Replacement Project 24 (GS-14003) Stormwater Management Fund •East Meadow Drive System Upgrades (SD-22000) •East Meadow Circle Connection to Adobe Creek Pump Station (SD-26000) •Trash Capture Device Installation (SD-22002) Wastewater Collection Fund •Wastewater Collection System Rehabilitation Augmentation Project 31 (WC-19001) Wastewater Treatment Fund •Joint Intercepting Sewer Rehabilitation (Phase 1) (WQ-24000) •Plant Master Plan (WQ-10001) •Primary Sedimentation Tank Rehabilitation (WQ-14003) •Secondary Treatment Upgrades (WQ-19001) 2 9 8 6 Water Fund •Water Main Replacement Project 29(WS-15002) •Water Regulation Station Improvements (WS-07000) •Water Tank Seismic System Upgrades (WS-09000) As described above for completed projects, the list of projects under construction does not include work currently being conducted under recurring CIP projects. Below are some photos of projects under construction: New Public Safety Building (PE-15001) 2 9 8 6 Public Safety Building Update The Public Safety Building project made significant progress in the first half of Fiscal Year 2024. Exterior brick, tile, and plaster are almost completed. Permanent power to the building switchgear was completed in September 2023. The communications monopole was installed in October 2023. The roofing was completed. The Tier 4 emergency generator has been installed. 2 9 8 6 Utility tie-ins have been completed. Sitework is in progress on Park Boulevard, Birch Street, Jacaranda Lane, and Sherman Avenue. Interior build out and mechanical, electrical, and plumbing systems are almost complete. Painting and interior finishes installation have begun. The photovoltaic panel system has been completed. The photovoltaic panel system serving the PSB is located on the roof of the 350 Sherman Avenue Garage. As of December 2023, construction is 94% complete and 82% of the project’s construction contingency has been used. Staff continues to coordinate with the City Auditor, Baker Tilly, on the Public Safety Building Construction Audit by providing project documents on a monthly basis. Additionally, a cross- departmental staff team is meeting monthly to review and coordinate construction of the Public Safety Building and other projects in the California Avenue area, with a goal of communicating and mitigating the impacts. Capital Improvements of Note Implemented by Other Agencies El Camino Real: El Camino Real (State Highway 82) is maintained by Caltrans. Pavement Condition Index scores for El Camino Real are significantly lower than the average for Palo Alto streets. Staff has been communicating with Caltrans about the upcoming plans to repave El Camino Real from the Mountain View to Menlo Park borders. Currently, this work is planned to start in late 2024. Related work to address ADA updates/shoulder and sidewalk work at different points along El Camino Real is underway with temporary parking and shoulder closures in effect. Caltrain Electrification: Caltrain is on schedule to provide all-electric train service between San Jose Diridon and San Francisco stations in fall 2024. All foundations, poles, and wires have been installed along the 51-mile corridor and crews are currently testing the infrastructure and trains. Six of the eventual 23 trainsets are currently on Caltrain property, three of which have completed a thousand miles of testing along the Caltrain corridor. The entirety of the new fleet must meet all safety and quality standards prior to the launch of electrified service in Fall 2024. Testing of the trains in the Palo Alto city limits is expected to begin in March 2024. Caltrain work continues requiring partial lane closures of Alma Street to vehicle, bicycle, and pedestrian traffic. The temporary lane closures are required due to trenching and construction equipment and crews entering and exiting the Caltrain right-of-way along Alma Street. FISCAL/RESOURCE IMPACT Funding for the projects discussed in this report was appropriated in the Fiscal Year 2024 Adopted Capital Budget and reviewed for the 2024-2028 Five-Year CIP. STAKEHOLDER ENGAGEMENT This report was coordinated with internal City staff in the Administrative Services, Community Services, Office of Transportation, Public Works, and Utilities Departments. Stakeholder engagement is conducted separately for each project. 2 9 8 6 ENVIRONMENTAL REVIEW This report is exempt from the California Environmental Quality Act (CEQA) as it is an informational report to Council. CEQA compliance is reviewed separately for each capital project. ATTACHMENTS Attachment A: CIP Project Status Updates and Completed Projects List APPROVED BY: Brad Eggleston, Director Public Works/City Engineer Buildings and Facilities Projects Parks and Open Space Projects Streets and Sidewalks Projects Traffic and Transportation Projects Enterprise Fund CIP Projects  Airport Projects Electric Projects Fiber Optics Projects Gas Projects Stormwater Management Projects Wastewater Collection Projects Wastewater Treatment Projects Water Projects List of Completed Projects  ATTACHMENT A  Semiannual Update on the Status of Capital Improvement Program Projects  (This page is a summary outline of Attachment A) Capital Improvement Fund CIP Projects  Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 1 of 11  One‐Time Projects  Animal Shelter  Renovation   (PE‐19002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,920,943 $5,981,221 Public Works Design TBD  Project Status:   This project installs interim facility improvements to the Animal Shelter that accompany the  agreement for operation of the shelter by Pets In Need approved by City Council in November 2018.  The medical  area upgrades and the modular office building are complete.  The new kennel addition has been submitted for  building permit. Project was placed on hold following receipt of Pets In Need's letter providing one‐year  notification of termination of the agreement between Pets In Need and the City. Public Works and Community  Service Department staff are reviewing the project while negotiations continue on a new agreement.  Project  completion is undetermined because the project definition is dependent on the approval of a new agreement  between the City and Pets In Need.    Baylands Boardwalk  Piling Repair  (PE‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $276,461 Public Works Design Winter 2025  Project Status:  This project provides funding for the identification and implementation of a long‐term solution to  damage caused by aquatic borers to The Lucy Evans Baylands Interpretive Center’s boardwalk. The project  permitting and design are in progress. The piling repair project requires permits from the San Francisco Bay  Regional Water Quality Control Board, Bay Conservation and Development Commission, United States Fish and  Wildlife Services, and United States Army Corps of Engineers. Due to the biological restrictions, project  construction will occur outside of the Ridgeway’s rail nesting season between September 1, 2024 and January 31,  2025     City Facilities  Assessment and  Record Plan  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $177,071 $333,134 Public Works Construction Summer 2024  Project Status:  The Kitchell Report in 2008 summarized the last City‐wide facility condition assessment.  A new  facility condition assessment is warranted per the City’s APWA reaccreditation requirements.  All City facilities will  Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 2 of 11  Management  System                (PE‐20002)        be assessed to bring current the “catch‐up” and “keep up” costs.  In addition, an electrification assessment will be  included to help the City reach its sustainability goals for 2030.  Council awarded the contract in April 2022. All City  facilities have been assessed for the Condition and Electrification assessments.   The data is currently being  evaluated in the new Capital Predictor software to generate reports detailing the current “catch‐up” and “keep  up” costs, while staff continues to evaluate the draft reports. A detailed list of buildings for electrification is being  analyzed to determine prioritization for replacements. An Electronic Records Management System will be  implemented through TE‐13004. This project will compile all sources of building documents into a singular  repository. The cooperative agreement for this project will begin in spring 2024.    City Hall Space  Planning  (PE‐19000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $45,701 $650,907 Public Works Design Summer 2025  Project Status:  This project involves space planning to determine future workgroup space needs and programming  for the City Hall office building focused primarily on the areas that will be vacated once the new Public Safety  Building is complete and occupied.  The project will include preliminary design of the space following the initial  feasibility phase. A Request for Proposals (RFP) is being drafted and is expected to be released in summer 2024.    Civic Center  Electrical Upgrade  & EV Charger  Installation  (PE‐17010)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $554,045 $2,141,929 Public Works Design Spring 2025  Project Status: This project installed EV chargers in existing downtown garages and will replace the aging Civic  Center electrical switchgear and motor control centers.  EV charger construction at the Civic Center, Bryant Street  garage and Webster Street garage was completed in December 2021. A contract was awarded in June 2021 for  the design of the Civic Center switchgear replacement and is currently at the 90 percent design stage. Lead times  on switch gear are now taking 12 months, so the project completion date has been extended. The structural  analysis design of the switchgear area and its permit set will be completed in January 2024.      Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 3 of 11  Civic Center Fire  Life Safety  Upgrades   (PE‐18016)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $478,938 $1,031,443 Public Works Construction Spring 2024  Project Status:  This project will assess, update, and replace the Civic Center fire alarm system.  The fire life safety  system is approaching the end of its useful life.  The fire alarm panel and associated equipment need an upgrade  to meet current code requirements.  The award of a design‐build contract was approved by Council in June 2021.  Construction in the main tower areas is nearly complete. The ground floor and the garage levels are yet to be  completed.  The project completion date has been extended to April 30, 2024.    Civic Center  Waterproofing   Study and Repairs  (PE‐15020)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $769,908 $1,153,021 Public Works Construction Summer 2025  Project Status:  This project includes a condition assessment of the Civic Center plaza deck structural system.  In  2016, RDH Building Science, Inc. determined that the expansion joint on the plaza could be repaired and that  replacing the waterproof coatings on the inside of the plaza perimeter planter boxes was needed.  Repair of the  waterproofing joint in front of City Hall was completed in winter 2023. Staff will start procurement for a design  contract in summer 2024 focused on the repair of the perimeter planter boxes.    Cubberley Gym  HVAC Replacement  (CB‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $809,297 Public Works Design Fall 2024  Project Status:   The existing heating system in Cubberley Gyms A & B is original to the building, which was  constructed in the mid‐1950s. The system is currently not functioning because multiple leaks have developed in  the steel hot water piping, which is in the walls and under the floor. These leaks contributed (in addition to a  domestic water main supply leak) to significant water damage in the walls, floors, and crawl spaces of the gyms.  Asbestos and mold were remediated from the under‐floor crawl space.  All the old heating units and piping were  removed from the ceilings in both gyms.  The next step is to hire a consultant to create design drawings for a new  heating system.  Due to staff workload constraints, design will begin in early FY 2025.    Buildings and Facilities Projects Status as of December 2023 Buildings and Facilities Projects – Page 4 of 11  Electrification of  City Facilities  (PE‐24001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $ $1,017,599 Public Works Pre‐Design Fall 2030  Project Status:   This project will evaluate feasibility, prepare designs, and implement construction for the  electrification of fossil fuel consuming building systems in coordination with the Building Systems Improvements  project (PF‐01003). The City Facility Electrification assessment report will act as a workplan to implement the  electrification of City facilities.  Fire Station 4  Replacement  (PE‐18004)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $683,253 $15,329,842 Public Works Design Winter 2026  Project Status:  This project will replace Fire Station #4 at the corner of Middlefield Road and East Meadow Drive.  The design consultant has completed design development and received Planning approval for the project in  November 2023. A construction management contract was awarded in December 2023. Architect will submit for  building permit review in spring 2024.   Fire Training Facility  Replacement  (FD‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $55,293 Fire Department Pre‐Design Summer 2026  Project Status:  This project will identify an appropriate site and construct a new fire training facility in Palo Alto.  This will be the first City‐owned and City‐maintained permanent fire training facility, and it will allow training to  be conducted within City limits and therefore reduce the downtime associated with the need for staff to travel for  training and when responding to calls.  Homekey Facilities  (PE‐24005)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $4,500,000 Public Works Construction Spring 2025  Project Status: This project involves relocating the City of Palo Alto (City) GreenWaste facility from its current site  on one portion of 1237 San Antonio Road to the rear portion of the same site as a result of adding the Homekey  Palo Alto interim housing. Homekey Palo Alto will be operated by LifeMoves who will provide intensive,  Buildings and Facilities Projects Status as of December 2023 Buildings and Facilities Projects – Page 5 of 11  customized case management for clients including counseling, employment and housing search services with the  goal of paving a dignified path to self‐sufficiency. Construction began in October 2023.  JMZ Renovation  (AC‐18001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $3,618,438 $4,966,603 Community Services Construction Spring 2024  Project  Status:  This  project  provides  for  the  temporary  relocation  of  the  Junior  Museum  and  Zoo  and  the  construction of a new  facility  and  exhibits.  The California Dinosaur Garden exhibit, which is partially funded by a reimbursable federal grant, was opened with a special ribbon cutting ceremony in October 2023. Funds  associated  with  the  grant  are  expended  against  the  project until  reimbursements are  made.  All work is  expected to be  completed in FY 2024.  Library Automated  Material Handling  LB‐21000  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $166,947 $1,085,100 Library Design Spring 2024  Project Status:  This project is to provide the design and construction of three new Automated Material Handling  (AMH) Systems for the College Terrace, Children’s, and Downtown Libraries. Due to space constraints and limited  functionality, only the Children’s Library installation will be proceeding. AMH systems efficiently sort returned  library materials based on the Radio Frequency Identification Devices (RFID) on the materials. Project design is  complete, and construction is waiting on permit issuance. Construction is estimated to start in May 2024.  Lucie Stern  Community Theater  Mechanical  Equipment  Replacement  (PE‐24002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $2,756,854 Public Works Pre‐Design Fall 2026  Project Status:  This project will upgrade and replace the Heating Ventilation and Air Conditioning (HVAC) system  at the Lucie Stern Community Theatre. As a first step, the project will include a detailed feasibility study to  determine if natural gas‐powered equipment in the facility can be electrified.  Buildings and Facilities Projects Status as of December 2023 Buildings and Facilities Projects – Page 6 of 11  Lucie Stern  Community Theater  Fire Curtain  (AC‐24001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $221,169 Community Services Design Fall 2024  Project Status:  This project will replace the fire curtain and its associated rigging at the Lucie Stern Community  Theatre.  Lucie Stern  Community Theater  Stage  Rigging System  Refurbishment  (AC‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $116,113 Community Services Design Summer 2024  Project Status:  This project will refurbish the most heavily used components of the stage rigging system at the  Lucie Stern Community Theatre. The scope of work is currently under review by the department.  Lucie Stern  Community Theater  Theatrical  and House Lighting  System  Replacement  (PE‐24003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $372,252 Public Works Design Fall 2024  Project Status:  This project will upgrade and replace lighting systems at the Lucie Stern Community Theatre for  back‐stage  work  areas,  the  performance  stage,  and  audience  areas.  The  project  team  is  in  the process  of  contracting with a consultant to prepare biding documents for a design‐build procurement.  Mitchell Park  Library Repair  (PE‐24006)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $250,000 Public Works Design Summer 2024  Project Status:  This project will design and repair the damage caused by a vehicular accident in January 2023. A  vehicle ran into the north wall of the Mitchell Park Library near the center of the building. The car impacted an  area of the stone cladding on cold‐formed steel studs, causing the cladding to fall from the wall and the wall to  bulge into the building’s interior. Architectural and structural survey and reports were completed. The stone  cladding wall will require replacement, but the structural steel frame was not damaged. A consultant will provide  a proposal to replace the stone cladding wall.  Buildings and Facilities Projects Status as of December 2023 Buildings and Facilities Projects – Page 7 of 11  Municipal Service  Center Lighting,  Mechanical, and  Electrical  Improvements  (PF‐16006)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,149,073 $8,786,825 Public Works Design Fall 2024  Project Status:  This project replaces original mechanical, electrical, and lighting systems installed in 1966.  It also  includes design and construction for office renovations for the Zero Waste group.  The design is 100% complete  and corrections will be submitted to Building Department in January 2024.  New Downtown  Parking Garage  (PE‐15007)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,440,311 $7,488,904 Public Works Design TBD  Project Status: This project was intended to provide a new parking structure in the University Avenue commercial  area at existing Parking Lot D at the corner of Hamilton Avenue and Waverley Street.  As part of the FY 2021 budget  strategy, all Capital Improvement Fund funding has been removed and only the downtown parking in‐lieu fee  funding remains for this project.  In December 2021, Council directed staff to look at the feasibility of partnering  with a private entity to develop new parking using downtown in‐lieu parking fees in conjunction with housing or  other uses, including the use of City surface lots or privately held parcels. A Request for Information was issued in  December 2022 and staff reviewed proposals and held interviews in May 2023. Council gave direction to staff in  December 2023 to advance the project in conjunction with advancement of affordable housing in the Downtown  area.  New Public Safety  Building  (PE‐15001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $105,703,406 $ 118,137,971 Public Works Construction Summer 2024  Project Status: This project will provide a new, modern Public Safety Building (PSB) that will meet essential services  standards and the current and future needs of the public safety departments.  The PSB and new garage in the  California Avenue business district are now an integrated project and both are part of the 2014 Council  Infrastructure Plan.  Construction on the PSB started in March 2021 and will continue into summer 2024.  Exterior  brick, tile, and plaster are   almost  completed. Permanent power was completed in September 2023. The  communications monopole was installed in October 2023.The roofing was completed. The Tier 4 emergency  Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 8 of 11  generator has been installed. Utility tie‐ins have been completed. Sitework is in progress on Park Boulevard, Birch  Street, Jacaranda Lane, and Sherman Avenue. Interior build out and mechanical, electrical, and plumbing systems  are almost complete. Painting and interior finishes installation have begun. The radio antenna contract was  awarded in March 2023. Contracts for communication systems, furniture, fixtures, and equipment were awarded  in June 2023. The photovoltaic panel system has been completed. The photovoltaic panel system serving the PSB  is located on the roof of the 350 Sherman Avenue Garage.     Performing Arts  Venues Seat  Replacement   (AC‐18000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $438,343 $1,247,566 Community Services Design Summer 2024  Project Status:  This project will replace all the seats in the Community and Children’s Theatres.  Staff hired a  consultant to design the seat replacements and ADA upgrades for the Children’s Theater’s portion of the project.   Additional funding was added for FY 2023 to address the Community Theater portion.   The Children’s Theater  seats replacement was completed in November 2022.  A contract for the design of the Community Theater was  issued in June 2023. Construction is scheduled to take place during summer 2024. Plans have been submitted for  plan check and permit approval.      Rinconada Pool  Family Changing  Room  (PE‐24004)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $1,544,303 Public Works Design Spring 2025  Project Status:  The project will construct a gender‐neutral restroom and family changing facility that is compliant  with the Americans With Disabilities Act (ADA) at the Rinconada Pool. The facility will include two separate rooms,  each consisting of a toilet, sink, shower, and child/adult changing station. The facility will provide community  members who have special needs, and individuals who require privacy, an accessible space for changing and  personal hygiene. A design contract is currently being prepared.      Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 9 of 11  Roth Building  Rehabilitation  Phase 1  (PF‐23001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $7,797 $11,848,825 Public Works Construction Fall 2024  Project Status:  This project provides funding for Phase 1 of the rehabilitation and build‐out of the Roth Building  facility. Phase I will make the building suitable for occupancy, also known as a “warm shell.” Phase II of the  rehabilitation includes the interior build‐out of the museum and exhibits, readying the facility to welcome visitors,  and will be funded by the Palo Alto History Museum (PAHM). A Tenant Work Letter was approved by Council in  April 2023 and construction is underway including underground utilities, roof, demolition, and abatement.      Recurring Projects  Americans With  Disabilities Act  Compliance   (PF‐93009)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,342 $884,677 Public Works N/A Recurring  Project Status:  This project provides accessibility upgrades to City facilities and equipment.  It includes continued  funding for improvements such as path of travel, restrooms, drinking fountains, and counters.  An updated ADA  Transition Plan was adopted by Council in June 2021.  Staff is waiting to solicit for new software that will allow staff  to identify and log new barriers, track grievances from the public, and update the ADA Transition Plan Report.    Building Systems  Improvements   (PF‐01003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $735,097 $932,317 Public Works N/A Recurring  Project Status:  This project provides electrical, mechanical, plumbing, structural, and security upgrades for City  facilities.      City Facility  Parking Lot  Maintenance  (PE‐09003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $28,800 $385,941 Public Works N/A Recurring  Project Status:  This project repairs, resurfaces, or reconstructs parking lots and walkways at various City facilities,  including restriping and signage. Work for this project will be included in the FY 2024 Overlay Project, which is  Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 10 of 11  anticipated to be awarded in March. The work includes resurfacing of Hopkins and Newell Tennis Courts Parking  Lot and Foothills Nature Preserve Water Tower Lots 1 & 2.    Cubberley Repairs  (CB‐17001)   Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $7,302 $201,107 Public Works N/A Recurring   Project Status:   This project is for general maintenance needs of the Cubberley campus.  The project to remediate  the asbestos and mold in the crawl space of Gyms A & B was completed at the end of November 2023..   .   The  project to remediate the lead base paint and then paint the ceilings and walls is underway and will be done by the  end of January 2024.  Cubberley Roof  Replacements  (CB‐16002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $553,008 $2,835,922 Public Works N/A Recurring  Project Status:  This project replaces existing roofs at Cubberley Community Center.   Currently in design and pre  bid stage are the Cubberley Pavilion Flat Roof, T1 & T2 Wings, & U‐Wing roofs scheduled for replacement in the  second half of FY 2024.     Electric Charger  Infrastructure  Installation  (PF‐23000)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $307,519 Public Works N/A Recurring  Project Status:  This project designs and installs electric vehicle chargers at various City facilities. The primary use  of the electric vehicle chargers will be for City fleet vehicles.  The design to install six new chargers on Level C of the  City Hall parking garage is underway.  A new charger was installed next to the Cubberley Wing‐V.  Two new chargers  were installed at MSC‐B.    Facility Interior  Finishes  Replacement  (PF‐02022)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $5,172 $735,167 Public Works N/A Recurring  Project Status:  This project improves the interior finishes of City facilities, including flooring, walls, cabinets, paint,  lighting, ceiling tiles, soundproofing, and fixed office furniture, doors, windows, and associated fire/life safety,  Buildings and Facilities Projects               Status as of December 2023  Buildings and Facilities Projects – Page 11 of 11  mechanical, electrical and plumbing code compliance requirements. Design of modifications to the Revenue  Collections office area on Level G has restarted and is anticipated to be in construction in spring 2024.  New carpet  is being selected for the Children’s Library.     Police Video  Recording Systems  Replacement  (PD‐20000)  Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $106,395 $132,700 Police Department N/A Recurring  Project Status:  This project maintains the Palo Alto Police Department video recording systems used to record  events in the field with up to five in‐car cameras as well as body‐worn cameras (BWC).   In‐car units were added to  new vehicles as they came into service in FY 2023. An RFP will be issued in summer 2024 for a solution that has  mobile video for vehicles, body‐worn cameras, and interview room systems. The program will seek to include all  detention facilities in the Public Safety Building which is expected to come online in summer 2024.  The Purchasing  Department received six RFP submissions.  The Police Department will conduct vendor demonstrations from the  top three vendors in January 2024.    Roofing  Replacement   (PF‐00006)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $288,268 $2,022,410 Public Works N/A Recurring  Project Status: This project replaces existing roofs at City facilities that have outlived their useful lifespans.  The  Animal Shelter roof recoating has been delayed due to roof modifications required for the proposed kennel  remodel.  Staff is working on the design for the Peers Park Field House roof replacement.    The Lucie Stern Community Center reroofing project is complete.    University Avenue  Parking  Improvements  (PF‐14003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $31,299 $149,318 Public Works N/A Recurring  Project Status: This project maintains parking lots and parking structures within the University Avenue Downtown  Business Parking District.    Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 1 of 8  One‐Time Projects  Baylands  Comprehensive  Conservation  Plan  (PG‐17000)    Prior Years Actuals    Total Project Budget Implementing Department Project Phase Project Completion  $386,401 434,059 Community Services Design Spring 2025  Project Status: This project provides funding for a conservation plan that will examine the native vegetation, wildlife  habitat resources, and wildlife‐appropriate public access for the entire Baylands, including Byxbee Park. This plan will  provide needed information on best areas to maintain wildlife habitat and appropriate areas to develop trails or other  recreation amenities; provide a design overlay for appropriate types and locations of public art in the Baylands; and  design an interpretive messaging throughout the Baylands. The plan seeks to optimize opportunities for low impact  recreation ensuring that these are compatible with the Baylands Master Plan direction for a passive park and nature  preserve. The Conservation Plan will also provide input to the Byxbee Park Completion project.    Baylands  Nature Preserve  Entrance Gate  (OS‐24000)  Prior Years Actuals    Total Project Budget Implementing Department Project Phase Project Completion  $0 $132,701 Community Services Design Summer 2024  Project Status: This project will install a new automated gate at the Baylands Nature Preserve main entrance. The  existing gate is manually opened and closed by staff each day for public access. The scope of work includes an electrical  transformer, trenching, wiring, and gate automation equipment.     The design work encompasses sourcing for  appropriate equipment and an electrical feed in the open space area.    Boulware Park  Improvements  (PE‐17005)  Prior Years Actuals    Total Project Budget Implementing Department Project Phase Project Completion  $823,665 $6,261,627 Public Works Construction Fall 2024  Project Status: This park renovation project was initially planned in FY 2018 but was postponed due to project priorities  and potential purchase of the adjacent AT&T lot located at 3350 Birch Street.  In fall 2019, the lot was purchased by  the City.  In response to the purchase, the City utilized the funding for the initial renovation project for preliminary  design and outreach for both the existing park and the newly purchased park land.  A Park Improvement Ordinance for  the improvements was adopted by the City Council in October 2021.   A construction contract was awarded in June  2023 and the project construction began in August 2023 and is anticipated to be completed by fall 2024.   Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 2 of 8  Byxbee Park  Completion  (PE‐18006)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $368,192 $3,699,189 Public Works Pre‐Design Summer 2026  Project Status: This project allows for the remaining improvements to Byxbee Park that follow the completion of the  landfill capping work.  The Baylands Comprehensive Conservation Plan (BCCP), which is currently undergoing CEQA  analysis, will include recommendations on the scope of the Byxbee Park project.  The BCCP and the conceptual plan for  Byxbee Park need additional outreach and review.  The project has been moved to FY 2025 due to staffing constraints  and pending the Baylands Comprehensive Conservation Plan.     Cameron Park  Improvements  (PG‐14002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $165,670 $538,898 Community Services Construction Summer 2024  Project Status: This project upgrades and renovates safety and accessibility features at Cameron Park with a primary  focus on the park playground.  A park improvement ordinance was approved by Council in February 2021.  Bids were  opened in June 2023. The construction contract was awarded by Council in September 2023 with anticipated  completion in summer 2024.     Cubberley Field  Restroom   (CB‐17002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $347,845 $1,398,526 Public Works Design Summer 2024  Project Status: This project will install a new restroom in the sports field area of the Cubberley Community Center.   Design for the project started in fall 2018 along with public outreach.  Staff assessed the feasibility of on‐site utilities  connection and reviewed design and specifications of a prefabricated restroom building to incorporate in the final  design for ARB review. Staff conducted outreach meetings and coordination for the potential location of the proposed  restroom.   In June 2023, Council approved a purchase order with the Public Restroom Company for a four‐stall  prefabricated restroom building. The Public Restroom Company is the process of obtaining the state of California  approval of the building design. The project design, bid package, and a building permit will be completed by early 2024.  The project is anticipated to go out to bid in spring 2024 for site preparation and for restroom installation in summer  2024.   Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 3 of 8  El Camino Park  Turf  Replacement  (PG‐24000)    Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $931,121 Community Services Design Spring 2024  Project Status: The project will replace the synthetic turf at the El Camino Park playing field.  Staff is currently working  with a design consultant for preparation of bid documents.    Foothills Nature  Preserve  Boronda Lake  Dock  Replacement  (OS‐18000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $255,427 Public Works Design Fall 2024  Project Status: This project replaces an aged and deteriorating Boronda Lake Dock located in the Foothills Nature  Preserve.  Design for a similar replacement dock is anticipated to be completed in spring 2024 with construction in  fall 2024 after bird nesting season.    Foothills Nature  Preserve Dam  Seepage  Investigation  and Repairs  (PE‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $24,779 $88,591 Public Works Pre‐design Spring 2024  Project Status: This project will study a location of historic seepage from the Foothills Nature Preserve Dam at the  sharp bend in the road on the face of the dam.  The seepage is very minor, but it appears to be slowly worsening.  The  source of the seepage is suspected to be the trench backfill around the pipe that returns shallow groundwater to  Boronda Lake.  This project will locate and investigate the pipe and trench backfill material.  Staff continues to monitor  and investigate the seepage per the Department of Water Resources inspections and recommendations. Staff  completed camera inspections of the underdrain pipes to identify potential obstructions and leakage issues. Depending  on the ongoing investigation, an engineered solution may be required.      Foothills Nature  Preserve  Improvements  (PE‐21000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $698,223 $3,632,918 Public Works Design Summer 2026  Project Status: This project will repair the bridge to Sunfish Island and complete design and permitting to replace the  footbridge in Los Trancos Valley, replace the grade control structures along Buckeye Creek, provide new split rail  fencing to protect sensitive areas, new pedestrian pathways to keep park visitors safe while walking along the park  Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 4 of 8  road, and improvements to some of the existing parking areas to make them safer and more efficient. Staff completed  a concept plan design and initiated the minor Architectural Review Board process.  Staff is proceeding with an RFP to  hire a consultant for the detailed design and bid package preparation. Additionally, a design for the repair of Sunfish  Island bridge has been completed with repair work slated for spring 2024.    Golf Course Net  and Artificial  Turf  Replacement  (PG‐18000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $932,167 Community Services Design Summer 2025  Project Status: This project will remove and replace the golf course driving range netting and synthetic turf.  This project  is being delayed as additional ball retention needs are being assessed throughout the golf course and development of  a potential long term partnership with the First Tee of Silicon Valley for driving range and practice facility improvements  is under consideration along with changes to the layout of the driving range.    Golf  Reconfiguration  and Baylands  Athletic Center  Improvements  (PG‐13003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $14,026,970 $14,584,775 Public Works Design Winter 2029  Project Status: This project provides funding for the renovation of the Municipal Golf Course in accordance with the  Council approved conceptual plan. The project includes less turf, raising the elevation of the course with imported soil,  replacement of the irrigation and drainage systems and space for athletic fields. The project will also fund five years of  required environmental monitoring of the golf course and staff are in communication with State regulatory agencies  to comply with the requirement.    Peers Park  Improvements  (PG‐14001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $293,050 Community Services Design Summer 2025  Project Status: This project will upgrade and renovate the irrigation system and turf at Peers Park. The project will also  repair playground surfacing, replace dog park surfacing, and upgrade drinking fountains.        Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 5 of 8  Ramos Park  Improvements   (PG‐14000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $256,586 $935,037 Community Services Design Summer 2025  Project Status: This project includes safety and accessibility improvements at Ramos Park.  The work includes replacing  the existing park playground, benches, drinking fountains, and resurfacing the basketball court playing surface.  This  project was previously bid but did not move forward at that time.  The Ramos Park project will now be bundled with  Robles Park Improvements and is anticipated  for bid solicitation in spring 2024.    Rinconada Park  Improvements  (PE‐08001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $5,010,174 $9,979,716 Public Works Design Spring 2024  Project Status: This project provides upgrades to safety, site amenities, playground facilities, a new restroom, irrigation,  drainage, and ADA accessibility improvements at Rinconada Park.   These improvements were identified in the  Rinconada Long Range Plan (LRP).  Phase 1 park improvements to the western half of the park were completed in spring  2022. A new restroom that was removed from the Phase 1 park improvements in FY 2022 is currently in design. In April  2023, Council approved a purchase order with the Public Restroom Company for a two‐stall prefabricated restroom  building. Staff completed design and obtained a building permit for site work and restroom. The restroom fabrication  is in progress and installation is anticipated in FY 2024. On December 18, 2023, Council awarded a construction contract  for restroom site work. According to the LRP, future improvement phases will include improvements to the eastern  half of the park by FY 2028 including pathway improvements, ADA upgrades, planting, irrigation, lighting, and site  furnishings.      Robles Park  Improvements  (PE‐18015)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $46,570 $507,817 Public Works Design Summer 2025  Project Status: This project will replace play equipment and resurface two children’s playground areas; repair a  and  replace perimeter fencing, pathways and other site amenities.  A community meeting was held in September 2023 with  an additional community meeting anticipated for 2024.  Construction work is anticipated to occur in summer 2024.    Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 6 of 8    Recurring Projects  Art in Public  Spaces  (AC‐86017)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $246,702 $1,704,337 Community Services N/A Recurring  Project Status: This project provides the ongoing temporary and permanent artworks throughout the City.  The FY  2024 budget supported seven installations for the Code: ART festival downtown and three new murals in the  California Avenue district.  Projects in process include the ongoing King Artist‐in‐Residence including temporary  artwork for King Plaza, artwork for Boulware Park, permanent artworks at the Public Safety Building, artwork at Fire  Station 4, and implementation of the California Avenue Public Art Plan.    Athletic Courts  Resurfacing   (PG‐06001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $88,701 $525,348 Community Services N/A Recurring  Project Status: This project repairs and resurfaces athletic courts in various Palo Alto parks.    The resurfacing of the  Johnson Park basketball court was completed in February 2023. Staff is currently working with a design consultant  for preparation of bid documents for the reconfiguration and resurfacing of the Greer Park basketball courts.    Benches, Signage,  Walkways,  Perimeter  Landscaping   (PG‐06003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $150,643 $440,938 Community Services N/A Recurring  Project Status: This project restores and replaces existing benches, signage, fencing, walkways, and landscaping at  various City facilities. The Lytton Plaza fountain improvement project was completed in fall 2023. A consultant  completed parking analysis for the Greer Park Skatepark in December 2023. A design consultant was hired to prepare  park directory signage for Mitchell Park with an estimated completion of winter 2024.     Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $31,256 $1325,671 Community Services N/A Recurring   Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 7 of 8  Dog Park  Installation and  Renovation   (PG‐18001)  Project Status: This project enables construction of dog parks at various City parks and facilities  for constructing  new or renovating existing dog parks.  A new dog park will be added with the Boulware Park expansion project for  which construction started  in summer 2023.  Council approved a Park Improvement Ordinance in September 2022  for expansion of the Mitchell Park Dog Park.  The solicitation of construction bids is anticipated in winter 2024.    Off‐Road Pathway  Resurfacing and  Repair   (OS‐09001)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $2,742 $267,876 Public Works N/A Recurring  Project Status: This project resurfaces failing and broken pathways within the City.  Pathways are chosen based on  inspections and resident requests. This project included discussion of the conceptual repair design and permitting  approach with the relevant regulatory agencies that would allow for repairs to the existing Baylands Boardwalk  pilings. A permitting strategy was determined to proceed with the repairs.     Open Space Lakes  and Pond  Maintenance   (OS‐00002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $35,931 $91,855 Community Services N/A Recurring  Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat  and recreational safety and to meet State Division of Safety of Dams requirements. Year three of a three‐year  maintenance contract is in place for removal of aquatic vegetation in Boronda Lake. The biannual vegetation removal  from the lake was completed in fall 2023.    Open Space Trails  and Amenities   (OS‐00001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $311,663 $276,462 Community Services N/A Recurring  Project Status: This project restores unpaved trails, fences, picnic areas, and campgrounds at Foothills, Baylands,  and Pearson‐Arastradero Nature Preserves.  Work performed in summer 2023 work included the grading of dirt fire  roads and repair to drainage systems.      Parks and Open Space Projects                Status as of December 2023    Parks and Open Space Projects – Page 8 of 8  Parks and Open  Space Emergency  Repairs   (PG‐09002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $367,541 $367,187 Community Services N/A Recurring  Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park amenities,  and play equipment in the event of storms, fire, vandalism, or structural failure.   In fall 2023, the Mitchell Park net  climber was repaired with a replacement net.     Park Restroom  Installation  (PG‐19000)  Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $6143,533 $893,846 Community Services N/A Recurring  Project Status: This project installs new restrooms at City parks that currently do not have restroom facilities.  The  restrooms may be prefabricated. City Council approved a Park Improvement Ordinance for Ramos Park. In April  2023, Council approved a purchase order with the Public Restroom Company for a two‐stall prefabricated restroom  building. Staff completed design and obtained a building permit for site work and restroom. The restroom fabrication  is in progress and installation is anticipated in FY 2024. On December 18, 2023, Council awarded a construction  contract for restroom site work.      Streets and Sidewalks Projects Status as of December 2023 Streets and Sidewalks Projects – Page 1 of 4  One‐Time Projects  California Avenue  District Gateway  Signs   (PE‐17004)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $26,943 $150,321 Public Works Design Summer 2025  Project  Status:  This  project  includes the   design and  replacement of two existing   gateway  signs for the   California  Avenue  business  district.   Initial  public  outreach  was  completed  in  winter  2021.  The  California  Avenue  District  Gateway Signs project is in the next phase of improvements following the California Avenue Streetscape update and near term improvements.  Newell Road  San  Francisquito  Creek Bridge   Replacement  (PE‐12011)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,803,014 $19,838,852 Public Works Design Spring 2026  Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear  span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500  cubic feet per second, and to improve safety for vehicular, bicycle, and pedestrian traffic.  The project is being closely  coordinated with the City of East Palo Alto, Valley Water, and San Francisquito Creek Joint Powers Authority (SFCJPA).   The 100% design set was completed in February 2023. Specifications and construction cost estimate were submitted  to the City in March 2023. With the revised cost estimate on hand, staff submitted a request to Caltrans for additional  construction funding. The request also includes additional funding for right‐of‐way support and engineering design.  The right‐of‐way appraisal and acquisition work started in January 2023. Staff and consultants are working with the  individual property owners to secure permanent and temporary easements by February 2024. Staff is working with  SFCJPA staff and their consultant on securing regulatory permits for the project by spring 2024. Right‐of‐way  acquisition and permitting is anticipated to be completed by winter 2024, with bidding of the project in spring 2024  and construction to start in summer  2024.  Street Lights  Condition  Assessment  (PE‐13014)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $8,799 $276,384 Public Works Design Fall 2025  Project Status: This project will assess the condition of the City’s streetlight system. The assessment will include an  inventory of the entire lighting system, including age and condition of conduit, wiring, street light poles, foundations,  Streets and Sidewalks Projects                Status as of December 2023    Streets and Sidewalks Projects – Page 2 of 4    luminaires, and lighting coverage. The project will also determine the inspection, maintenance, repair, and  rehabilitation necessary to prolong the life of the City’s streetlight system. This project has been moved to FY 2025  due to staffing constraints.      Recurring Projects  City Bridge  Improvements  (PE‐20001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $210 $786,919 Public Works N/A Recurring  Project Status: This project includes bridge inspections, maintenance, repair, and an improvement program over the  next five years. This program will include on‐going inspections to report physical changes to the structures,  recommendations for work to be done, and additional information to meet functional and structural standards in  accordance with industry standards.   Staff hired an on‐call structural engineering firm to assist with the bridge  inspection and repair program.  Staff completed design and bidding for repairs of six bridges identified for repairs in  winter 2023. Due to the lack of competitive bids, staff plans to rebid the project in December 2023 to begin the repair  work in spring 2024.      Curb and Gutter   Repairs  (PO‐12001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $123,607 $241,020 Public Works N/A Recurring  Project Status: This project repairs curbs and gutters uplifted by tree roots.  Funding for FY 2023 has been carried  over into FY 2024 for a larger curb and gutter repairs project. The project will focus on Downtown North and University  South neighborhoods (Palo Alto Avenue to Embarcadero Road and Alma Street to Middlefield Road) in addition to  addressing hot spot locations from 311 requests.  Project bidding is anticipated early 2024 with construction to start  summer 2024.    Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $96,686 $119,374 Public Works N/A Recurring  Streets and Sidewalks Projects                Status as of December 2023    Streets and Sidewalks Projects – Page 3 of 4    San Francisquito  Creek Joint  Powers  Authority  Ongoing Creek  Projects  (PE‐22000)  Project Status: This project provides funding for studies and completion of the design for the San Francisquito Creek  Joint Powers Authority (JPA) upstream project including channel widening and Continuing Authority Program Section  205 (CAP 205) study.   The project design is temporarily on hold due to the recent significant storm events and flooding  that occurred on December 31, 2022. The JPA and Valley Water are re‐evaluating the creek capacity and hydraulic  limitations of the channel to determine how to proceed with the design.     Sidewalk Repairs  (PO‐89003)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,100,469 $2,515,608 Public Works N/A Recurring  Project Status: This project repairs and replaces broken and uplifted sidewalks.  The program completed all twenty‐ three sidewalk districts in 2017, a 30‐year (1986–2017) sidewalk repair district cycle.  Council approved a sidewalk  assessment contract in November 2017 to evaluate the sidewalk program and assess potential improvements to the  current district‐based program.  Funding for FY 2023 has been carried over into FY 2024 for a larger sidewalk project.  The Project will focus on Downtown North and University South neighborhoods (Palo Alto Avenue to Embarcadero  Road and Alma Street to Middlefield Road). Project bidding is anticipated early 2024 with construction to start  summer 2024.    Sign Reflectivity   Upgrade  (PO‐11000)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,963 $81,330 Public Works N/A Recurring  Project Status:  This project includes the annual inventorying, upgrading and maintaining of all traffic signs.  A list of  signs not meeting the minimum requirement is derived from MUTCD approved Nighttime Visual Inspection surveys.   Due to staffing constraints, there were no signs identified for reflectivity replacement in the first half of FY 2024.     Street Lights   Improvements  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $314,447 $512,047 Public Works N/A Recurring  Streets and Sidewalks Projects                Status as of December 2023    Streets and Sidewalks Projects – Page 4 of 4    (PO‐05054)  Project Status:  This project replaces streetlights, including poles, pole foundations, luminaires and wiring as needed  to restore or improve street lighting.  In the first half of FY 2024, there were 13 knockdown locations with seven  completed repairs and four in progress. Additionally, a project located in the Midtown neighborhood completed 16  pole foundation replacements and repainting of 131 streetlight poles was completed in September 2023.      Street  Maintenance  (PE‐86070)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $2,789,013 $7,126,112 Public Works N/A Recurring  Project Status:  This project includes the annual resurfacing, micro‐seal, crack seal, and reconstruction of various city  streets.  This project funds the street maintenance work that supports Council’s adopted goal of achieving a citywide  average pavement condition index (PCI) score of 85, representing very good or excellent conditions. The FY 2023  Street Resurfacing Project was completed in summer 2023.  The FY 2024 Street Resurfacing Project went out to bid  in December 2023. The project will replace 10,149 square feet of sidewalk, 3,371 square feet of driveway, and 2,280  linear feet of curb and gutter, construct thirty‐seven new ADA curb ramps, and place 9,844 tons of AC overlay on the  streets of Palo Alto.  This will help maintain and improve the City’s Pavement Condition Index (PCI) beyond its average  of 84 and will address many streets whose PCI scores fall below the City’s minimum goal of 60. The FY 2024 Streets  Preventive Maintenance Project will go out to bid early 2024. The project will include micro‐surfacing of sixteen lane‐ miles of streets.    Thermoplastic  Lane Marking  and Striping  (PO‐11001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $235,939 Public Works N/A Recurring  Project Status: This project maintains the thermoplastic markings on roadways.  Thermoplastic lane marking and  striping is incorporated into annual Pavement Preventive Maintenance Projects.  No new thermoplastic markings and  striping were installed during the first half of FY 2024.         Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 1 of 8   One‐Time Projects  California Avenue  Streetscape  Update  (PL‐23000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $13,882 $121,584 Office of Transportation Design Fall 2024  Project Status: The project provides funding for interim changes to the street, and for preliminary community  engagement to help inform an upcoming Request for Proposals in summer 2023 to procure a consultant for an  Alternatives Analysis study of different street configurations and design options. Council approved a consultant  contract at the December 18, 2023 meeting and the consultant’s work will begin in January 2024. Staff will also  continue implementing improvements and activations on the streets through 2024, including more family games,  more public art, new barriers, and continual partnerships for music and mini‐golf.     Charleston  Arastradero  Corridor Project  (PE‐13011)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $19,973,800 $20,788,951 Public Works Construction Winter 2024  Project Status: This project is part of the 2014 Council Infrastructure Plan. It will reconfigure the Charleston  Arastradero Corridor to provide new landscaped median islands, bulb outs, enhanced bike lanes, traffic signal  improvements, and new street trees to complement the new lane configurations that were approved for  permanent retention.  Phase 1 (Arastradero Road between Foothill Expressway to Clemo Avenue) and Phase 2  (Charleston Road from Alma Street to Middlefield Road) were completed in 2020. Phase 3 (Arastradero Road from  Los Palos Avenue to El Camino Real, Charleston Road from El Camino Real to Alma Street and from Middlefield  Road to San Antonio Road) was approved by Council in June 2021.  Construction of Phase 3 is currently paused in  coordination with Utilities’ Sanitary Sewer Replacement 31 Project and Caltrans’ traffic control requirements.  Remaining construction activities include paving operations at the El Camino Real intersection and signal  switchover at the Wilkie Way and West Charleston Road intersection. Construction is anticipated to be completed  by early 2024.    Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $387,453 $3,789,671 Office of Transportation Design Winter 2025  Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 2 of 8  Churchill Avenue  Enhanced  Bikeway  (PL‐14000)  Project Status: This project includes planning, design and construction of a shared‐use path along the north side of  Churchill Avenue between the existing shared‐use path at Castilleja Avenue and the Stanford Perimeter Trail.  It also  includes intersection improvements at Churchill Avenue and El Camino Real, which will include a new dedicated  westbound right‐turn lane.  PAUSD approved the easements required for the project in August 2023. Staff is working  to resolve additional comments received from Caltrain for re‐issuance of the encroachment permit. The project is  anticipated to bid in early 2024 and the construction is anticipated to be completed by winter 2025.       Churchill Avenue  Rail Grade  Separation and  Safety  Improvements  Main  (PL‐24001)  Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $0 $196,086,259 Office of Transportation Design Spring 2029  Project Status: This project provides for the planning, design, and construction of the grade separation at the existing  at‐grade crossing on Churchill Avenue in the Caltrain Rail Corridor. The project will provide improvements to  accommodate bicycles, pedestrians, and vehicular movement at the crossing. In 2021, the City Council selected  partial underpass as the preferred alternative, with closure as a backup alternative. Following feedback from key  stakeholders, staff refined the partial underpass alternative and conducted a preliminary geotechnical study to  assess subsurface conditions, as directed by the Council. These updated and additional studies were concluded in  October 2023. Additionally, the Rail Committee directed staff to conduct further evaluation to align with the  Council's recently adopted Alternative Evaluation Criteria. Staff is collaborating with the project consultant to carry  out additional studies for this update. The City is also in discussions with Caltrain to address comments received on  the conceptual alternatives. Furthermore, the City was granted two awards; $6.0 million from Federal Railroad  Administration for conducting Preliminary Engineering and Environmental Studies at the three crossings of Churchill  Avenue, Meadow Drive, and Charleston Road, and $23.79 million from California State Transportation Agency for  final design at this location. Staff is actively working with granting agencies to execute the necessary agreements  and seeking additional funding from other grant programs.     Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 3 of 8  Churchill Avenue  Alma Street  Railroad Crossing  Safety  Improvements  (PL‐20000)  Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $339,907 $9,690,252 Office of Transportation Construction Spring 2024  Project Status: This project is a railroad crossing improvement project to enhance safety at the intersection of  Churchill Avenue and Alma Street. Design includes traffic signal modifications, street lighting improvements,  roadway resurfacing, sidewalk realignment and/or widening, drainage improvements, utility relocations, signage,  and striping.  Staff is coordinating with Caltrain, Caltrans, and California Public Utilities Commission (CPUC). CPUC  approved General Order 88‐B for the project in November 2022 and authorized the City to move forward with  construction.  Council approved the construction contract in June 2023. Construction started in July 2023 and will be  completed in spring 2024.    Downtown  Automated  Parking   Guidance  Systems, Access  Controls &   Revenue  Collection  Equipment  (PL‐15002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $437,918 $5,197,828 Office of Transportation Design Fall 2024  Project Status:  This project includes design and installation of new downtown parking guidance systems, access  controls, and revenue collection equipment that will be coordinated with both the Downtown Parking Wayfinding,  PL‐15004 project and the 2016 Downtown Parking Management. Staff contracted with Dixon Resources for  additional management support in design and procurement for the system installation in the Downtown garages on  University Avenue.  The Downtown Automated Parking Guidance Systems design‐build construction contract was  approved by Council in May 2023. Design is in progress and construction is expected to be completed in fall 2024.  Emergency  Vehicle Traffic  Signal  Preemption  System Pilot   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $486,422 $683,522   Fire Department Procurement Winter 2024  Project Status:  This project will purchase and implement an emergency vehicle preemption system pilot project.  The system will integrate with the City’s current traffic signal management system and with the City’s computer‐ aided emergency response dispatch system to provide safer and quicker response times for emergency vehicles.   Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 4 of 8  (PL‐19000) This project is a pilot on 25 intersections.  The traffic signal controls software was updated in spring 2020. An RFP  process for a new CAD system will be conducted in FY 2024. The RFP requirements will include the ability to connect  to the Trafficware Signal controls. This project is being sunsetted.     Meadow  Drive/Charleston  Road Rail Grade  Separation and  Safety  Improvements  (PL‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $396,395,198   Office of Transportation Design Spring 2028  Project Status:  This project provides for the planning, design, and construction of the grade separations at the  existing at grade crossings on Meadow Drive and Charleston Road in the Caltrain Rail Corridor. The project will  provide improvements to accommodate bicycles, pedestrians, and vehicular movement at the crossings. In 2021,  the City Council narrowed the alternatives under consideration at these locations to trench, hybrid, and underpass.  Currently, the Rail Committee is reviewing these alternatives to further narrow and select the preferred alternative  (s) for recommendation to the City Council. Following feedback from key stakeholders, City staff refined the  underpass alternatives and conducted a preliminary geotechnical study to assess subsurface conditions, as directed  by the Council. These updated and additional studies were concluded in October 2023. Additionally, the Rail  Committee directed staff to conduct further evaluation to align with the Council's recently adopted Alternative  Evaluation Criteria. Staff is collaborating with the project consultant to carry out additional studies for this update.  The City is also in discussions with Caltrain to address comments received on the conceptual alternatives.  Furthermore, the City was granted $6.0 million from Federal Railroad Administration for conducting Preliminary  Engineering and Environmental Studies at three crossings of Churchill Avenue, Meadow Drive, and Charleston Road.  Staff is actively working with granting agencies to execute the necessary agreements and seeking additional funding  from other grant programs.     Parking  Management and  System  Implementation  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $151,580 $627,247 Office of Transportation Procurement Spring 2024  Project Status:  This project provides funding for the design and installation of the Comprehensive Parking Permit  and Citation Management System. The all‐inclusive system is a tool staff will utilize in the management of parking  Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 5 of 8  (PL‐16002) permits for eight parking permit programs and associated on and off‐street parking citations.  Staff is preparing an  RFP to solicit another vendor.     Railroad Grade  Separation and  Safety  Improvements  (PL‐17001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $3,860,627 $12,238,838 Office of Transportation Pre‐Design Fall 2025  Project Status: This project is a community‐based process to advance the railroad grade crossing circulation study  and context sensitive solutions study envisioned by the City Council for the Palo Alto Avenue crossing.  It will also  fund the preparation of a Project Study Report and environmental analysis that will be required for the City to realize  its goals of advancing grade separations.  The project will perform preliminary engineering design, conduct project  related studies, and prepare environmental documents for the improvements.  This project is currently on hold. City  is considering quiet zone implementation for interim conditions and staff will initiate the conceptual plan  development for grade separation at this crossing in late 2024.     University Ave  Streetscape  Update  (PE‐21004)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $164,146 $175,000 Public Works Design Winter 2024  Project Status: This project includes a study to reconfigure University Avenue between Alma Street and Middlefield  Road to adapt the public realm to maximize pedestrian and bicycle use, reduce congestion, and enhance the retail  environment/economic activity, while maintaining two‐way vehicular access, parking opportunities, delivery and  loading zones, ride share spaces, and other amenities including performance space. Council awarded a professional  services contract for CSW/Stuber‐Stroeh Engineering in February 2022.  The project uses a phased approach with  Phase 1 consisting of public outreach, conceptual design, preliminary environmental studies, and financial  assessment. A preferred plan will be developed in Phase 1 based on community and stakeholders’ input. Upon  completion of Phase 1 assessment and Council’s review of the community preferred plan, future phases including  design, environmental assessment, bidding, and construction will be developed.  Staff concluded the Phase 1  outreach process and concept plans alternatives analysis in fall 2023.  Staff presented the preferred streetscape  concept plan to Council on December 18, 2023   Per Council direction in December 2023, staff is identifying additional  Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 6 of 8  concept alternatives for Council discussion. Staff will proceed with Phase 2 of the project consisting of preliminary  design and environmental assessment upon Council approval of the preferred concept alternative.      Recurring Projects  Bicycle and  Pedestrian  Transportation Plan  Implementation  (PL‐04010)           Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $52,695 $2,400,000 Office of Transportation N/A Recurring  Project Status: This project funds the Bicycle and Pedestrian Transportation Plan Update, which has kicked off  recently and is slated to take approximately 18 months to complete (Summer 2025).  This project also funds the  implementation of various individual bicycle and pedestrian projects. Currently, one of the projects is the  Embarcadero Road Improvements Project (from Emerson to High Street), which provides improvements on both  the north and south sides of Embarcadero Road, from Emerson to High Street. Improvements include intersection  improvements at Emerson and Kingsley, landscaping, new pedestrian level lighting, and bicycle and pedestrian  enhancements. Final Design is currently being completed, and the project will be ready to bid for construction in  2024.       Parking District  Implementation  (PL‐15003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $1863,900 Office of Transportation N/A Recurring  Project Status: This project introduces additional parking permit programs throughout the city. One aspect of this  project is to update City Council‐approved Residential Preferential Parking (RPP) ordinance language to establish  uniform and streamlined procedures and processes to implement RPP districts through the process outlined in  Municipal Code 10.50.        Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 7 of 8  Safe Routes to  School  (PL‐00026)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $53,956 $969,106 Office of Transportation N/A Recurring  Project Status: This project enables the City’s Safe Routes to School program, including school commute planning,  encouragement activities, and capital improvements along local and collector streets that may be impacted by  school commute activities.  The capital improvements include traffic calming devices, enhanced crosswalks, and  improved signage along suggested safe routes to school.  The community engagement and planning process for  the construction of the South Palo Alto Bikeways project began in FY 2021.  The project will implement buffered  or protected bike lanes on East Meadow Drive from Alma Way to Fabian Way, Fabian Way from East Meadow  Drive to East Charleston Road, and widen and repave the Waverley Avenue Bike Path between East Meadow Drive  and Charleston Road.  Due to lack of staff resources, the project schedule was delayed, and the City relinquished  construction grant funds prior to expiration of funding. Staff will continue to apply for grant funds to aid in  construction costs. In FY 2024, this project funded education to improve school access and safety. In addition, this  project supported a secondary school needs assessment to identify middle and high school education and  encouragement programs and to query the Safe Routes Partnership for the resources to support these programs.    Traffic Signal and  Intelligent  Transportation  Systems  (PL‐05030)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $232,807 $1,451,217 Office of Transportation N/A Recurring  Project Status: This project includes design and construction of traffic signals, traffic signal communications  networks, detection, and data projects for transportation use, and maintenance of the City’s traffic signal central  management system.  The project includes the replacement of traffic signal controllers/cabinets, video detection  systems, accessible pedestrian buttons, and related field equipment. Design for traffic signal safety and  operational improvements at the intersection of San Antonio Road and Charleston Road is nearing 100%  completion.  Staff is finalizing the plans and will be preparing bid documents for construction to be released in  spring 2024, with construction anticipated to begin in summer 2024.  Staff is in the procurement process to update  the Centralized Traffic Management system servers to improve operational functions and system security.   Traffic and Transportation Projects               Status as of December 2023  Traffic and Transportation Projects – Page 8 of 8  Transportation and  Parking  Improvements   (PL‐12000)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $56,374 $914,692 Office of Transportation N/A Recurring  Project Status:   This project implements miscellaneous neighborhood traffic calming improvements including  neighborhood traffic studies and parking improvements. This project also funds the development of grant  proposals used to procure funding for future projects. For the traffic calming project in the Crescent Park  neighborhood, City Council approved proceeding with the design of permanent improvements in November 2023.  Staff will work with the on‐call consultant for the design of requirement improvements.  In addition to traffic  calming, staff will also begin conducting an Engineering and Traffic Survey for select roadway segments to study  prevailing speeds and review traffic conditions in order to establish and/or certify posted speed limits.   Furthermore,  staff is also working on the quiet zone project for all railroad crossings along the Caltrain corridor.  A quiet zone study was performed for the Palo Alto Avenue and Alma Street crossing in collaboration with City of  Menlo Park in 2022. Staff has retained the services of the consultant to design final improvements at this crossing.  In addition, staff is working through procurement process to conduct a study for evaluation of quiet zones at the  other three crossings of Churchill Avenue, Meadow Drive, and Charleston Road.  The $200K Safe Streets for All  (SS4A) Safety Action Plan is funded via this project but will be reimbursed up to $160K by a federal grant. The plan  will target eliminating traffic deaths and life‐changing injuries on local streets.         Airport Projects   Status as of December 2023    Airport Projects – Page 1 of 2  One‐Time Projects  Airport Access  Road  Reconstruction  (AP‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0   $3,754,870 Public Works Design Summer 2027  Project Status:  This project is for the design and reconstruction of the pavement on Embarcadero Way, which is  the main access road for airport businesses and the Air Traffic Control Tower at the Airport. The Airport did not  receive FAA funding for this project and the project is currently on hold.     Airport Layout  Plan  (AP‐21000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $426,977   $967,100 Public Works Construction Summer 2024  Project Status:  This project provides updates to the Airport Layout Plan, also known as the Long Range Facilities  and Sustainability Plan, including a narrative report and environmental study.  The Airport received funding for a  Phase I portion of this project in fall 2020. Phase I is approximately 75% complete, and funding for Phase II was  received in fall. The Airport conducted the initial public and Project Advisory Committee meetings in April 2023.  The project is expected to be completed by summer 2024. There have been 3 public meetings held for this project,  and the Phase II project is approximately 50% complete, while the Phase I project is 85% complete.     Airport Parking  Lot Electric  Vehicle  Charger  Installation  (AP‐24001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0   $28,994 Public Works Design Summer 2026  Project Status:  This project will install electric vehicle charging stations in the Airport customer parking lot. The  Airport is currently unable to offer electric vehicle charging to its customers, but there is increasing demand for  vehicle charging capability from Airport tenants. This project has been delayed as the Airport explores further  funding options.     Airport  Temporary  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $947   $411,105 Public Works Procurement Winter 2024  Airport Projects   Status as of December 2023    Airport Projects – Page 2 of 2  Office  Buildings  (AP‐22001)  Project Status:  This project provides funding for the installation and Furniture, Fixtures, & Equipment (FF&E) of  existing temporary modular buildings at the airport to provide adequate office space for airport staff as well as  terminal space for the public.   This project has been delayed to as the Airport explores further funding options.    Airport Zero  Emission  Vehicle Fleet  Replacement  Program  (AP‐23000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $25,957 $369,008 Public Works Procurement Summer 2024  Project Status:  The Airport vehicle fleet will be replaced by three zero emissions vehicles (ZEV), to be supported  by three electric charging stations. The van is used for the transportation of airport guests and passengers and  improves safety by minimizing foot traffic on the airport apron. The truck is used as a maintenance, first response,  and operations vehicle. The ZEV fleet will include one passenger vehicle and two trucks. Procurements for truck  replacements went out in May 2023 and only one bid was received. FAA funding is expected in the fall 2023, to  complete the fleet replacement. The Airport purchased the passenger van in Oct 2023, but the truck did not meet  the Federal Buy America requirements. The Airport will be issuing a new RFP in spring 2024 for a truck.     Automated  Weather  Observation  System  (AWOS)  AP‐19000  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0   $514,109 Public Works Design Summer 2024  Project Status:  This project provides a new weather information system to be installed at the Palo Alto Airport.   The Airport has applied for FAA funding, and is waiting for the grant agreement to start design. The Airport will go  out to bid for a contractor in February 2024. It is anticipated that funding for the project will be received in summer  2024.         Recurring Projects    2024‐2028 – Airport Capital Improvements Program Projects: There are no recurring projects scheduled at this time.   Electric Fund Projects Status as of December 2023 Electric Fund Projects – Page 1 of 9  One‐Time Projects  115 kV Electric  Intertie   (EL‐06001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $705,491 $1,801,190 Utilities Pre‐Design Summer 2027  Project Status: This project will perform a technical feasibility study to determine the general project requirements  to establish a 115 kV electric intertie line and construct a 115/60 kV substation to connect the City's electric system  directly to the 115 kV transmission line at an additional location.  Staff did not receive California Independent  System Operator’s commitment to support this interconnection.   Staff has retained the services of a consultant to  evaluate the options available to the City. Staff anticipates having an initial draft report for review by June 30,  2024.  Coleridge  Cowper  Tennyson   4/12kV  Conversion   (EL‐14000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $180,813 $2,680,811 Utilities Design Summer 2025  Project Status: This project converts the primary electric distribution system in the Coleridge Avenue, Cowper  Street, Tennyson Avenue area from 4 kV to 12 kV.  This individual project will be closed but the scope of work will  be covered under the EL‐24000 Grid Modification project.   Colorado  Distribution  Feeder Outlet  Replacement  (EL‐22002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $10,576 $400,000 Utilities Design TBD  Project Status: This project is for the installation of a new underground duct bank and cable at Colorado Substation.   The installation will improve reliability for all Colorado circuits.  The design is complete and construction will begin  by winter 2024. Staff is waiting on 12Kv pad‐mount switches with a 48‐month backlog.  Colorado Power  Station  Equipment  Upgrades  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $4,343,887 $11,536,114 Utilities Pre‐Design Fall 2027  Project Status: This project is for the upgrades to equipment at the Colorado Power substation. In FY 2022 staff  completed the evaluation of existing equipment and will proceed with replacing the COP‐3 115 kV/60 kV  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 2 of 9  (EL‐19001) transformer bank and the 115 kV breaker.   Engineering is working on design RFPs and construction IFBs for  contract services to complete substation projects.      Colorado  Substation Site  Improvements  (EL‐19002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $251,919 $1,425,693 Utilities Design Fall 2025  Project Status: This project will make modifications to the substation driveways and fence to provide adequate  ingress and egress for utility vehicles used for maintenance and repair.  Staff has prepared an overall master plan  for Colorado Substation to include all proposed improvements.  Detailed designs for lighting, driveway, fences,  walls, and an oil containment improvement have been prepared. The design is complete and staff is presenting  the design to Planning to secure a planning permit by the end of February 2024.      East Meadow  Circles 4/12kV  Conversion   (EL‐17001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $268,097 $1,742,527 Utilities Design Spring 2025  Project Status: This project converts the primary electric distribution system in the East Charleston Road, Alma  Street, East Meadow Drive, Middlefield Road areas from 4 kV to 12 kV and is challenging because of the  configuration of the streets and rear easement facilities. This project has been split into six design and construction  phases. Engineering has completed the design and construction for Phase 1. The City’s electrification goals have  changed the priority, schedule, and the allocation of staff resources for this CIP project.     Foothills Rebuild  (Fire Mitigation)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $4,494,104 $14,999,589 Utilities Construction Fall 2025  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 3 of 9  (EL‐21001) Project Status: This project will rebuild the approximately 11 miles of overhead line in Foothills Park, as necessary  to mitigate the possibility of wildfire due to overhead electric lines. This could include the utilization of more robust  equipment or construction practices, rerouting to avoid vegetation and improve access for inspection and  maintenance, or converting the overhead lines to underground where feasible.  Two proposals were received for  this project and both proposals were rejected because they did not provide an option to underground existing  overhead electric lines. Substructure for Phases 1 and 2 are completed.   Phase 3 substructure is currently in  construction and Phase 4 is currently in design.   Grid  Modernization  for Electrification  (EL‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $300,000,000 Utilities Design Winter 2030  Project Status:  This project will provide the City with an electric infrastructure adequate to support the City’s goal  of 100% electrification and 80% carbon emissions reduction by the year 2030. To attain the 100% electrification  scenario, the City must maximize use of electric energy and phase out carbon‐based end uses such as natural gas  appliances and internal combustion vehicles. The electric system must be updated to meet the needs of  electrification, and older components in the distribution infrastructure must be replaced to mitigate chances of  overloading the system. Examples of assets to be replaced are distribution and substation transformers,  primary/secondary distribution circuits. A Pilot area was designated and engineering staff in conjunction with a  consultant have completed the distribution system design for the Pilot area, with a handful of power poles replaced  and installed as initial construction efforts start to take shape. The estimated completion date for the Pilot is  December 2024.    Hopkins  Substation 4/12  kV Conversion  (EL‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $2,010,000 Utilities Design Fall 2025  Project Status: This project will convert the distribution system connected to the Hopkins Substation from 4 kV to  12 kV.  The future conversion of the Hopkins Substation from 4 kV to 12 kV requires that all the areas currently  served at 4 kV from the Hopkins Substation be converted to 12 kV. This project will improve operating flexibility of  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 4 of 9  the system, service reliability, and back‐up to customers in downtown and other adjacent areas. The City’s  electrification goals have changed the priority, schedule, and the allocation of staff resources for this CIP project.  Staff is working on an RFP for the engineering design for electrification of all overhead circuits. This individual  project will be closed but the scope of work will be covered under the EL‐24000 Grid Modification project.    Inter‐Substation  Line Protection  Relay  (EL‐17005)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $370,372 $1,601,626 Utilities Construction Summer 2027  Project Status: This project replaces the existing HCB pilot wire relays with a new microprocessor line differential  protective relay to protect the city’s 60 kV sub‐transmission line sections and equipment from damage due to  faults (i.e. short circuits) on the 60 kV line sections. This project is being done in phases, with design and  construction happening concurrently on the different phases.  Construction of these improvements relies on work  completed by other projects to install fiber optic connections. Engineering design for segments Colorado  substation to Adobe Creek substation, Park Boulevard substation to Quarry substation, and Maybell substation to  Park Boulevard substation is in progress. A test plan is being written to prove the equipment will work as designed.  Quarry to Park substation segment is expected to be completed by April 2024. Park Boulevard substation to  Maybell substation segment to be completed by June 2024.     Rebuild  Underground  District 15   (EL‐11003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $43,348 $1,293,337 Utilities Design Fall 2027  Project Status: This project rebuilds and replaces the underground electric system in Underground District 15, the  area bounded by Los Palos Avenue, Glenbrook Drive, Pomona Avenue, and Arastradero Road. This project is in the  preliminary stages of engineering design and work will be coordinated with EL‐16000 which is currently rebuilding  the electric system along Arastradero Road.  Work on this project was delayed due to public input regarding the  design of the project.  Changes to the Rules and Regulations will require property owners to pay for the differential  cost should they want submersible equipment instead of pad mount.  This project will fall under the underground  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 5 of 9  scope of work for electrification. Funds will be returned to reserves. Please see EL‐24000 Grid Modernization for  Electrification for future updates.     Rebuild  Underground  District 16   (EL‐13003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $28,742 $728,735 Utilities Design Spring 2027  Project Status: This project rebuilds and replaces the underground electric system in Underground District 16, the  area along Louis Road between Greer Street and Loma Verde Avenue.  The engineering design work is complete.   The City’s electrification goals have changed the priority, schedule, and the allocation of staff resources for this CIP  project. This project will fall under the underground scope of work for electrification. Funds will be returned to  reserves. Please see EL‐24000 Grid Modernization for Electrification for future updates.    Rebuild  Underground  District 24   (EL‐10006)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,949,767 $2,522,451 Utilities Design   Fall 2024  Project Status: This project rebuilds and replaces the underground electric system in Underground District 24, the  area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street.  The engineering design is in  progress and will be completed in winter 2024. Construction will follow in December 2024.     Rebuild  Underground  District 26   (EL‐16000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $36,817 $1,359,808 Utilities Design  Spring 2025  Project Status: This project rebuilds and replaces the underground electric system in Underground District 26, the  area along Arastradero Road between El Camino Real and Hillview Avenue.  This is a four‐phase project.  The first  phase design is complete. The engineering design is in progress and will be completed by December 2024.    Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $5,653,491 $17,690,021 Utilities Construction Fall 2024  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 6 of 9  Smart Grid  Technology  Installation  (EL‐11014)  Project Status: Council approved the Advanced Metering Infrastructure (AMI) with Sensus on October 18, 2021.   The project includes replacement of 30,000 electric meters and retrofit of 20,800 water and 24,200 gas meters  with radio endpoints to transmit meter data to the AMI network.  The proof of concept phase including AMI  network installation, meter testing, and system integration will occur between January 2022 and August 2023. Full  deployment is anticipated to run from September 2023 through April 2025      Substation   Breaker  Replacement   (EL‐17002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,490,136 $7,368,743 Utilities Pre‐Design Summer 2028  Project Status: This project replaces high voltage circuit breakers that interconnect the nine electric substations  and two power switching stations that are reaching the end of their useful life and are now underrated for their  use.  This project is being done in phases, with design and construction happening concurrently on the different  phases.  Staff completed the construction on the first phase and is working to procure a multi‐year contract with  a contractor to complete the design and replacement of the remaining breakers. Staff is working on the design RFP  and the construction IFB for contract services to complete substation projects. Lead times for circuit breakers are  currently at around 18 months.      Substation  Physical Security   (EL‐16003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,078,888 $6,895,187 Utilities Construction Winter 2025  Project Status: This project installs facilities providing physical protection of electric substations from vandalism  and intrusion.   A professional services contract was awarded to Burns and McDonnell and the study was  completed. Staff continues to implement recommendations from the study each fiscal year.   Substructure  construction is in progress, and with the exception of Colorado Substation, substructure installations have been  completed at all of the remaining substations.           Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 7 of 9      Recurring Projects  Communications  System  Improvements   (EL‐89031)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $4,587 $100,000 Utilities N/A Recurring  Project Status: This project installs high frequency coaxial cable, fiber optic cable, and related equipment to  provide communications services for traffic signal coordination, telephone links, computer data transmission, and  the Electric Supervisory Control and Data Acquisition (SCADA) system.  This project is funding a portion of the  design phase of an expanded Utilities fiber optic network.  The contract for design of this network was approved  by Council in June 2020.  Staff is in the planning stages for design implementation.      Electric Customer  Connections   (EL‐89028)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,172,465 $2,700,000 Utilities N/A Recurring  Project Status: This project installs services, transformers, and meters for new customers; upgrading of existing  services; temporary service connections; and overhead and underground extensions for new or existing  customers.  Projects are in many stages of design and construction to provide temporary and permanent power  to residential and commercial customers in Palo Alto.      Electric System  Improvements   (EL‐98003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,308,637 $2,500,000 Utilities N/A Recurring  Project Status: This project consists of various projects that replace deteriorated facilities or install protective  devices that improve the Electric Distribution System. Projects are in many stages of development to replace  transformers, replace poles, replace overhead wires, and install protective devices to improve service reliability.      Electric Utility  Geographic  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $221,620 $250,000 Utilities N/A Recurring  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 8 of 9  Information  System   (EL‐02011)  Project Status: This project enhances the citywide Geographical Information System (GIS).  The primary emphasis  will be to provide a compatible user interface and estimating software, to edit and update data which will reside  in the citywide GIS.  This funding is also being used to pay for Utilities Electric Division’s share of cost for the  implementation of new city‐wide GIS system (ESRI) led by IT.  Utilities and Information Technology staff are also  working to assess GIS needs and the transition of the mapping information to ESRI.  The migration for Electric is  100% complete.    SCADA System  Upgrades   (EL‐02010)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $70,488 $220,000 Utilities N/A Recurring  Project Status: This project upgrades the Supervisory Control and Data Acquisition (SCADA) system hardware.   Staff completed upgrade of the servers used for monitoring the utility substations and equipment in 2014.  The  next hardware and software upgrade is currently in progress at the factory and work will occur in winter 2024    Substation  Facility  Improvements   (EL‐89044)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $173,711 $1,200,000 Utilities N/A Recurring  Project Status: This project makes improvements to facilities at the electric substations in Palo Alto.  Staff is  working on the replacement of Remote Terminal Units (RTU) at various substations, upgrading gravel and  grounding, 60 kV air switches, and reconfiguring steel trusses and associated devices. Engineering is working on  design and construction for contract services to complete substation projects. Staff has completed the install for  Nexus meters at Hansen Way (22/23) and Colorado (20/21). Design for Hansen Way (20/21) is in progress.        Substation  Protection  Improvements   (EL‐89038)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $47,052 $3000,000 Utilities N/A Recurring  Project Status: This project makes improvements to equipment used at electric substations to protect the  substation equipment and circuits emanating from the substation from damage due to faults (i.e. short circuits)  Electric Fund Projects Status as of December 2023    Electric Fund Projects – Page 9 of 9  on the electric system. Staff issued a task order with Soudi Consultants to review and revise protection settings  and training on the commissioning of Park Boulevard relays. .      Underground  System Rebuild   (EL‐16001)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $350,000 Utilities N/A Recurring  Project Status: This project replaces underground electric equipment in areas that were originally installed  underground, that are not part of an Underground District.  Staff is working to identify areas where the age of the  existing cables are a high priority for cable replacement.  To date, this includes areas in the Stanford Research  Park, Arastradero Road, and along East Bayshore Road.  New areas have been identified and progress has been  made on development of the project.  Construction of this project was deferred to maintain zero rate increases  to ease economic recovery because of COVID‐19.    Wood Pole  Replacement  (EL‐19004)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $603,564 $1,500,000 Utilities N/A Recurring  Project Status: This project will fund the annual replacement of deteriorated wood power poles.   Staff has  completed the replacement of 15 poles in the first half of FY 2024.         Fiber Optics Fund Projects Status as of December 2023    Fiber Optics Fund Projects – Page 1 of 2  One‐Time Projects  Fiber Optic  Network  System  Rebuild  (FO‐16000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,000,100 $32,103,876 Utilities Design Fall 2025  Project Status:  This project is for the System Capacity Improvement that rebuilds portions of the "dark" fiber optic  network around Palo Alto.   In September 2022, Council approved the City’s fiber expansion plan including  construction of a new fiber backbone and a phased buildout of a fiber‐to‐the‐premises network.  The Fiber Optic  Network System Rebuild CIP will be replaced with new Fiber Backbone and Fiber‐to‐the‐Premises (FTTP) CIP’s in FY  2024. Staff has hired a consultant to complete the Fiber Backbone and FTTP conceptual design. The conceptual  design has been completed the contract has been amended to complete the design and all provide documentation  necessary for procurement of a construction contract. Staff is updating fiber databases and reviewing the current  inventory of fiber strands in order to determine what sections of the Fiber Backbone should be upgraded first. Staff  anticipates this initial review phase to be completed by June 2024, to be followed by the design stage for the Fiber  Backbone Upgrade, with an anticipated date to complete the Fiber Backbone upgrade of December 2025.    Fiber to the  Premises  (FTTP)  (FO‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $ 20,000,000 Utilities Design Winter 2030  Project Status:  This project will build Fiber‐to‐the‐Premises (FTTP) to deliver broadband (high‐speed internet) for  homes and businesses in the City of Palo Alto. As the City builds the FO‐16000 ‐ Fiber Optics Network ‐ System Rebuild   Staff has divided up the City into smaller sections for a phased approach of the Fiber‐to‐the‐Premises project.  Furthermore, Staff has proceeded to combine the Phase 1 Fiber‐to‐the‐Premise design with a Grid Modernization  Project covering the same area. Staff is capitalizing on inherent synergies between the two projects, as well as taking  advantage of economies of scale deployment that can be realized as a result of combining the two projects. Staff has  contracted with an Engineering firm to  produce design drawings and specifications. Preliminary design drawings are  anticipated by the end of January 2024. Additionally, Staff is preparing RFPs to acquire the necessary cables and  materials, including the FTTP operations Hut to be placed at Colorado Substation. The FTTP Phase 1 pilot is targeted  for completion by December 2024.        Fiber Optics Fund Projects Status as of December 2023    Fiber Optics Fund Projects – Page 2 of 2    Recurring Projects  Fiber Optics  Customer  Connections  (FO‐10000)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $28,594 $251,600 Utilities  N/A Recurring  Project Status:  This project enables the installation of fiber optic infrastructure for new service connections.  Projects are developed as needed to meet customer requests for leasing of fibers on the Dark Fiber system.  There  have been no new customer connections in the first half of FY 2024.    Fiber Optics  Network  System  Improvements  (FO‐10001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $51,967 $561,000 Utilities N/A Recurring  Project Status: This project improves the reliability within the fiber optic network system.   As part of the City’s  wildfire mitigation plan, this project will add new fiber conduit and substructure in the foothills to support city  infrastructure and improve telecommunication and connectivity in the open space. In the first half of FY24, 6 dark  fiber projects were completed and 13,000 Feet of 432 strand fiber optic cable were installed, and there were 2.38  miles of fiber conduit installed in the Foothills. The next phase of conduit installation is currently in construction.        Gas Fund Projects                    Status as of December 2023       Gas Fund Projects – Page 1 of 3    One‐Time Projects  Gas Main  Replacement  Project 24  (GS‐14003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,568,607 $10,063,205 Utilities Construction Spring 2025  Project Status:  This project enables the design and construction to replace approximately 20,100 linear feet (which  represents 1.9% of the City's Gas distribution main system) of distribution main and 260 gas services constructed mainly  of PVC on various streets within the University Park, and Crescent Park neighborhoods.  Release of the project for bidding  has been delayed, to include the Town & Country Village scope.  This project was split into GMR24A and GMR24B.  GMR24A (Stanford Shopping Center) was completed spring 2023.  GMR24B construction is anticipated to start at the end  of January 2024, pending weather.    Gas Main  Replacement  Project 25  (GS‐15000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $10,000,000 Utilities Design Winter 2024  Project Status:  This Gas Main Replacement (GMR) project replaces approximately 20,000 ‐ 26,000 linear feet (which  represents 2.4 percent of the City’s Gas Distribution System) of leaking, inadequately sized, and structurally deficient  gas mains and services located on various streets in the neighborhoods of Community Center, Leland Manor, Midtown,  and Palo Verde neighborhoods. Staff identifies problematic mains/services by researching maintenance and leak  histories, analyzing performance of the entire Gas Distribution System, and considering risks ratings of the Distribution  Integrity Management Plan. A federal grant application was submitted in August 2023 and if awarded the project will  replace 26,000 linear feet of main.  If the grant application is not awarded, a scaled down project will be proposed.        Recurring Projects  Gas  Distribution  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $190,158 $1,005,796 Utilities N/A Recurring  Gas Fund Projects                    Status as of December 2023       Gas Fund Projects – Page 2 of 3    System  Improvements  (GS‐11002)  Project Status: This project enables Gas Distribution System improvements.   Typical activities include increasing  distribution system capacity for load growth, replacing deteriorated capital facilities, reconfiguring/adding to the system  to improve service reliability, and conducting research related to performance of the gas distribution system or its  various components making general improvements to the system.  The City must continuously evaluate service reliability  needs and make improvements to the system to maintain top level service to City customers and to minimize potential  economic losses due to service interruptions.  In the first half of FY 2024, city crews completed the replacement of various  gas services and valves throughout the system, including 450 feet of gas mainline and eight gas services on Seneca Street  between Forest Avenue and Boyce Avenue.    Gas  Equipment  and Tools  (GS‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $19,823 $100,000 Utilities N/A Recurring  Project Status:   This project purchases polyethylene (PE) fusion equipment and tools, directional boring/locating  equipment and tools, and general shop equipment and tools.  The equipment needs to be upgraded on an annual basis  to safely operate and maintain a natural gas distribution system and to ensure operators’ safety and productivity.  In the  first half of FY 2024, no new equipment has been purchased.   New Sensit gas detectors and battery operated  electrofusion processing machines are planned for purchase in the last half of FY 2024.    Gas Meters  and  Regulators  (GS‐80019)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $359,636 $500,000 Utilities N/A Recurring  Project Status:  This project provides replacement of the existing gas meters and regulators annually. The coordination  of gas meter and regulator replacements with gas meters identified to be replaced under the AMI contract, which is  generally gas meters that are 25 years or older.  The gas meter replacement program ensures the accuracy of gas  consumption measurement, reduces possible revenue loss due to under‐registered gas, and provides customers with  accurate monthly bills.  Replacement of aged gas meters and regulators is on‐going.  The next major replacement of  meters and regulators will be coordinated with Gas Main Replacement Project 24 (GS‐14003) and the Advanced Metering  Infrastructure project.  Gas Fund Projects                    Status as of December 2023       Gas Fund Projects – Page 3 of 3    Gas System,  Customer  Connections  (GS‐80017)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $696,488 $810,900 Utilities  N/A Recurring  Project Status:  This project enables the Gas Distribution System to be extended in order to provide gas service to new  customers and augment service to customers with increased natural gas demands.  Improvements include new mains,  services, valves, regulators, meters, and accessories.   This project upgrades infrastructure to provide gas service  connections to new customers, meet changes in existing customer service demands, and respond to changes in gas  service requirements due to new development or redevelopment.  This project is funded partially from reimbursements  by customers.  City crews completed 5 new gas service installations and 36 gas service demolitions in the first half of FY  2024.        Stormwater Management Projects                Status as of December 2023  Stormwater Management Projects ‐  Page 1 of 3  One‐Time Projects  Corporation  Way System  Upgrades and  Pump Station  (SD‐21000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $181,234 $4,146,556 Public Works Design Spring 2026  Project Status:  This project incorporates a design of a new small pump station with 25 cubic feet per second  capacity and upgrades 700 linear feet of pipe to 30‐inch diameter High Density Polyethylene pipe.  The existing  system does not have the force needed to discharge storm flows into the Adobe Creek.  Adding a pump station in  advance of the outfall and upsizing the storm pipe will eliminate the routine flooding along East Bayshore Road and  convey runoff from a 10‐year storm event.  Staff secured an easement for the pump station from adjacent property  owners.  The design consultant has submitted a 99% design that is  currently under review by the Planning and  Building Department for final comments prior to issuing a procurement contract for construction in spring 2024.    East Meadow  Drive System  Upgrades  (SD‐22000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $31,884 $636,405 Public Works Construction Summer 2024  Project Status:  This project adds approximately 407 linear feet of new 24‐inch high density polyethylene to be  parallel to the existing 36‐inch pipe within East Meadow Drive to increase the capacity of the storm drain system.  This project includes upsizing manholes based on new pipes and reconnecting laterals from private property and  catch basins.  A construction contract was awarded in October 2023, and construction began in November 2023.  Completion is anticipated in June 2024.       East Meadow  Circle  Connection to  Adobe Creek  Pump Station  (SD‐26000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $634,016 Public Works Construction Summer 2024  Project Status:  This project will install approximately 600 linear feet of 15‐inch pipe and manholes along East  Meadow Circle. The new 15‐inch line will eliminate flooding that occurs within East Meadow Circle when the water  level within Barron Creek is higher than the flap‐gate, and flows are not able to drain into the creek. The new 15‐ inch HDPE line extension provides allows flows to drain away from Barron Creek and into Adobe Creek, where they  can be pumped. The project also includes a small bioretention area to treat low flow runoff within East Meadow  Stormwater Management Projects                Status as of December 2023  Stormwater Management Projects ‐  Page 2 of 3  Circle before discharging into either creek.  A construction contract was awarded in October 2023, and construction  began November 2023. Completion is anticipated in June 2024.       Trash Capture  Device  Installation  (SD‐22002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $261,579 $818,837 Public Works Construction Spring 2024  Project Status:  This project will design and construct a large trash capture device (TCD) to be installed in the  planting strip along Embarcadero Road located in front of the Palo Alto Baylands Golf Links parking lot. The TCD will  be integrated into a 36‐inch storm pipe to capture trash as small as five millimeters from a section of the storm  drain system prior to discharging to the San Francisco Bay. The 189‐acre drainage area treated by the TCD consists  of 169 acres of commercial and office land use in the City’s jurisdiction and 20 acres in the California Department  of Transportation (Caltrans) right‐of‐way. Construction began in summer 2023 and is expected to be completed by  spring 2024.    West Bayshore  Road Pump  Station  (SD‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $254,750 $3,058,138 Public Works Design   Spring 2026  Project Status:  This project incorporates design and construction of a new small pump station with 15 cubic feet  per second capacity.  Installing a new pump station will allow storm flows to be pumped into the Adobe Barron  Creek confluence while adding a pump station in advance of the outfall would eliminate the routine flooding along  West Bayshore Road and allow the system to convey runoff from a 10‐year storm event. Staff secured an easement  for the pump station from adjacent property owners The project is currently under review by the Planning and  Building Department for final comments prior to issuing a procurement contract for construction in spring 2024.     West Bayshore  Road Trunk Line  Improvements  (SD‐23000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $5,550 $2,542,314 Public Works Design Spring 2026  Project Status:  This project replaces approximately 1,400 linear feet of existing 15‐inch diameter pipe with 36‐inch  High Density Polyethylene pipe.  These improvements along with the new West Bayshore Road Pump Station (SD‐ Stormwater Management Projects                Status as of December 2023  Stormwater Management Projects ‐  Page 3 of 3  20000) will eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from  a 10‐year storm event. Staff secured an easement for the pump station from adjacent property owners  The project  is currently under review by the Planning and Building Department for final comments prior to issuing a  procurement contract for construction in spring 2024.     Recurring Projects  Green  Stormwater  Infrastructure  (SD‐22001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $2,005,559 Public Works N/A Recurring  Project Status:  This project provides funding for Green Stormwater Infrastructure (GSI) projects and the integration  of GSI features in the design and implementation of planned CIP projects supported by other funds. GSI mimics the  natural environment to slow, spread, infiltrate, and filter stormwater runoff through native or engineered soils or  other pervious material rather than discharging it directly into storm drain inlets. Types of GSI include bioretention  planters, tree wells, and pervious pavement to manage stormwater runoff.   The FY 2024 budget is allocated as a  match to fund the balance of a GSI project partially funded by the U.S. Environmental Protection Agency and also  provides funding for adding a GSI component to the East Meadow Circle Connection to Adobe Creek pump station  project (SD‐26000).    Storm Drainage  System  Replacement  and  Rehabilitation  (SD‐06101)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $738,001 $1,525,681 Public Works N/A Recurring  Project Status: This project provides for annual replacement and rehabilitation to maintain the integrity of the  storm drain system, including deteriorated storm drain piping, manholes, and storm drain inlets.  The rehabilitation  includes replacement of broken corrugated metal pipe with High Density Polyethylene pipe. Based on the recent  pipe failures that occurred in early 2023, staff is proposing to replace storm drain pipes at three locations (Forest  Avenue, Embarcadero Road, and Fielding Drive), as part of CIP projects SD‐22000 and SD‐26000.   A construction  contract was awarded in October 2023 and construction began in November 2023 and is anticipated to be  completed in June 2024.     Wastewater Collection Fund Projects              Status as of December 2023    Wastewater Collection Fund Projects – Page 1 of 2  One‐Time Projects  Wastewater  Collection  System  Rehabilitation  Augmentation  Project 31   (WC‐19001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $199,019 $8,635,244 Utilities Construction Spring 2024  Project Status:  This project funds the design and construction of high priority main replacement work, which reduces  inflow of rainfall and groundwater into the collection system. The project replaces approximately 11,000 linear feet  (which represents 1.0 percent of the City’s Wastewater Collection System) for El Camino Real from Page Mill Road to  Cesano Court, and Page Mill Road from Ramos Way to Ash Street. The project is comprised of mains identified in video  inspection work or through maintenance records as structurally deficient and in need of replacement. The work is in  Caltrans (El Camino Real) and the County of Santa Clara (Page Mill Road) right‐of‐way. The construction contract was  approved in May 2023. The construction Notice to Proceed  was issued in July 2023. Construction is underway with  completion anticipated in May 2024.             Recurring Projects  Sewer  Lateral/Manhole  Rehabilitation  and  Replacement   (WC‐99013)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $716,171 $850,000 Utilities N/A Recurring  Project Status: This project replaces defective sewer laterals, cleanouts, manholes, backwater devices, and equipment  to support these activities to maintain the Wastewater Collection System, as well as to comply with the Sanitary Sewer  Master Plan (SMP).  Information collected during routine annual maintenance activities is used to prioritize work.  The  continued work performed will also help reducing both sewage blockage and the City's treatment expenses to treat  rainwater or groundwater infiltration.   A new 3‐year construction contract was approved in FY 2023 to replace  problematic sewer laterals. In the first half of FY 2024, fifty‐six sewer lateral replacements were completed.   Wastewater Collection Fund Projects              Status as of December 2023    Wastewater Collection Fund Projects – Page 2 of 2  Sewer System,  Customer  Connections   (WC‐80020)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $360,124 $450,000 Utilities N/A Recurring  Project Status: This project installs sewer lateral connections and additions or extensions of existing mains to serve  new customers and to respond to changes in sewer requirements due to redevelopment.  Old existing non‐plastic  sewer laterals with condition deficiencies per Utilities Operations’ criteria are required to be replaced in accordance  with the latest 2022 WGW Standards. In the first half of FY 2024, two new lateral connection or extensions mains were  performed.      Wastewater  General  Equipment and  Tools   (WC‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $102,495 $108,941 Utilities N/A Recurring  Project Status:   This project provides funds to procure new general equipment and new tools. In the first half of FY  2024, no new general equipment or tools were procured.  Wastewater  System  Improvements   (WC‐15002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $799,501 Utilities N/A Recurring  Project Status: This project implements improvements to the Wastewater Collection System by increasing system  capacity for growth, flow monitoring, hydraulic modeling and system analysis, load simulations, asset management  analysis and assessment, system inflow/infiltration analysis, and sanitary sewer overflow monitoring and reduction.  Part of this project funds the Sewer Master Plan Study, which will evaluate the City’s existing wastewater collection  system, flows, and flow patterns to determine system capacity to meet current and future flows and recommend and  prioritize capital improvement projects where needed. The consultant contract was approved in November 2023. The  consultant started work in December 2023.            Wastewater Treatment Fund Projects   Status as of December 2023    Wastewater Treatment Fund Projects – Page 1 of 4  One‐Time Projects  Advanced  Water  Purification  Facility  (WQ‐19003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,977,452 $59,974,964 Public Works Design Winter 2026  Project Status: This project enables the design and construction of an Advanced Water Purification Facility to further  improve the quality of the tertiary‐treated recycled water by ultrafiltration followed by reverse osmosis to reduce the  level of total dissolved solids.  The water reuse partnership agreement with Valley Water and Mountain View provides  $16 million in funding from Valley Water for this project.  The City has also received grant funding for a portion of the  project costs and a State low‐interest loan for the design and construction phases.  Palo Alto and Mountain View staff  agreed that Mountain View would pay the remainder of the capital costs associated with this project. Mountain View  staff recommended this project and Mountain View’s City Council approved it on June 27, 2023 (SR #2308‐1863). The  design is currently at 100%, and meetings with ARB and Planning and Transportation Commission are ongoing.    Headworks  Facility  Replacement  (WQ‐16002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $52,095,872 Public Works Design Spring 2032  Project Status: This project replaces the existing two outdated influent pump stations and their associated equipment  and ancillary systems, including the suction and discharge piping manifolds, valves, electrical and controls system,  screening equipment, grit handling equipment, pumps, flow meters and yard piping. Solicitation for a consultant to  perform advanced planning and preliminary design began in  summer 2023. A consultant was selected in spring 2024.    Horizontal  Levee Pilot  (WQ‐22001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $39,421 $738,511 Public Works Design Fall 2029  Project Status:  This project consists of the design, permitting, and construction of a horizontal levee pilot system. The  system will utilize treated wastewater to create a transitional brackish habitat on the Bayside of a future flood control  levee located in the Palo Alto Baylands, adjacent to the Regional Water Quality Control Plant (RWQCP). Information  and data collected by this pilot system could support broader implementation of horizontal levees as green  infrastructure components in larger flood control levee improvement projects within Palo Alto and beyond. The project  Wastewater Treatment Fund Projects   Status as of December 2023    Wastewater Treatment Fund Projects – Page 2 of 4  completed 90% design, CEQA review, conducted several stakeholder outreach events, created a project webpage,  submitted construction applications to resource agencies, and received a recommendation from the Parks and  Recreation Commission. The project is currently finalizing the design, working with resource agencies to obtain  construction permits, coordinating future community engagement activities including BioBlitz’ and King Tide Walks,  and working to bring the Park Improvement Ordinance and Cooperative Agreement to Council in early 2024. The San  Francisco Estuary Partnership/Association of Bay Area Governments will be posting the project for solicitation in early  2024.    Joint  Intercepting  Sewer  Rehabilitation  (Phase 1)   (WQ‐24000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $12,573,488 Public Works Construction Winter 2025  Project Status: This project will rehabilitate 2,364 linear feet of the 60” and 72” diameter Joint Intercepting Sewer (JIS)  trunk line leading to the Regional Water Quality Control Plant (RWQCP). The entire trunk sewer line, constructed in  1972, is approximately 9,000 feet long consisting of 13 manholes/junction structures. The JIS conveys raw wastewater  mainly from the City of Mountain View, City of Los Altos, Los Altos Hills, and a portion Palo Alto, which accounts for  more than half of the RWQCP’s influent flows. Solicitation for construction was completed in fall 2023. Construction is  scheduled to begin in spring 2024 and be completed by winter 2025.      New  Laboratory  and  Environmental  Services  Building  (WQ‐14002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $363,705 $23,979,898 Public Works Pre‐Design Fall 2030  Project Status:  This project was originally envisioned to replace the existing plant laboratory and environmental  services offices.  Staff is currently revising space planning assumptions as the City and RWQCP are investigating the  potential acquisition of a property adjoining the RWQCP and have put further design efforts on hold. The original design  contract was terminated in March 2021. Solicitation for engaging a new consultant for detailed design will begin after  advanced planning and siting analysis are completed as part of the Long Range Facilities Plan Update.      Wastewater Treatment Fund Projects   Status as of December 2023    Wastewater Treatment Fund Projects – Page 3 of 4  Outfall Line  Construction  (WQ‐19000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $17,923,113 Public Works Design Summer 2026  Project Status:  This project consists of the construction of a new parallel outfall pipe to convey final plant effluent to  San Francisco Bay.  A re‐design of the pipeline is needed to accommodate a potential future runway shift at Palo Alto  Airport.  Staff is currently working with the Federal Aviation Administration (FAA) to gain FAA concurrence for the  pipeline construction and permanent easements on Airport property.  The re‐design is anticipated to begin in summer  2024, moving immediately to construction upon design completion.       Plant Master  Plan   (WQ‐10001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $457,871 $442,587 Public Works Construction Winter 2028  Project Status:  This project enables the ongoing program management support for major capital projects.  Current  tasks include developing scopes of work, evaluating consultant proposals, coordinating project management activities,  pursuing State low‐interest loans for multiple projects, and updating partner agreements.  The consultant provides  support for the projects associated with the Long‐Range Facilities Plan (LRFP), with a contract that expires in 2028.    Primary  Sedimentation  Tank  Rehabilitation   (WQ‐14003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $10,326,903 $20,449,644 Public Works Construction Spring 2024  Project Status: This project enables the design and construction for new protective coatings on each of the four  concrete primary sedimentation tanks, with replacement of worn rotating parts and mechanical and electrical  equipment.  These tanks were installed in 1972 and the recoating project will extend the concrete life for another 30  years.  Construction began in summer 2021, with completion expected by spring 2024.    Secondary  Treatment  Upgrades  (WQ‐19001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $15,774,759 $193,317,009 Public Works Construction Winter 2028  Project Status: This project upgrades the Secondary Treatment process at the RWQCP.   The existing Secondary  Treatment process has two main components, the Fixed Film Reactors (FFR) and the Activated Sludge (AS) Process.   Wastewater Treatment Fund Projects   Status as of December 2023    Wastewater Treatment Fund Projects – Page 4 of 4  This project includes the reconstruction of the AS process, rehabilitation and reconfiguration of the AS Aeration Basins,  the elimination of the FFRs, addition of denitrification capabilities, and replacement of equipment beyond its useful  life.  Construction began in winter 2023 with completion of new denitrification treatment and retirement of the FFRs  expected in 2028.              Recurring Projects  Plant Repair,  Retrofit and  Equipment  Replacement  (WQ‐19002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $2,116,235 $10,141,002 Public Works N/A Recurring  Project Status:   This project enables the assessment, repair, and retrofit of the RWQCP’s concrete and metal  structures; the replacement of necessary equipment and ancillary facilities, including electrical equipment/systems,  to maintain treatment reliability and existing infrastructure; and the replacement of large diameter flow meters built  into the wastewater treatment system on sewers, pipes, and water lines.  Design of the 12 kV Electrical Loop Upgrade  Project was completed in spring 2022. A construction contract for phase 1 was executed in winter 2023, with expected  completion in summer 2024. Solicitation for Phase 2 construction is anticipated to commence in summer 2024.      Water Fund Projects                    Status as of December 2023    Water Fund Projects – Page 1 of 5  One‐Time Projects  Water Main  Replacement  Project 29  (WS‐15002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $201,968 $9,307,828 Utilities Construction Summer 2024  Project Status: This project will fund the design and replacement of structurally deficient water mains and  appurtenances. Mains are selected by researching the maintenance history of the system and identifying those  that are undersized, corroded, and/or subject to breaks. The project scope includes approximately 7,500 linear feet  (which represents 0.6 percent of the City’s Water Distribution System) of mains and services on various streets  within the City, including areas in the Evergreen Park and Ventura neighborhoods. Construction started in  November 2023 and will complete in August 2024.    Water Main  Replacement  Project 30  (WS‐16001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $9,350,000 Utilities Design Spring 2026  Project Status: This project will fund the replacement of structurally deficient water mains and appurtenances in  Fiscal Year 2026. Mains are selected by researching the maintenance history of the system and identifying those  that are undersized, corroded, and subject to breaks. The project scope includes approximately 10,000 linear feet  (which represents 0.8 percent of the City’s Water Distribution System) of mains and services on various streets  within the City, including areas in Midtown/Midtown West, Palo Verde, and Green Meadow neighborhoods.    Water Recycling  Facilities  (WS‐07001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $710,106 $852,674 Utilities Pre‐Design   Fall 2024  Project Status: This project allows the City to hire a consultant to prepare a business plan, prepare preliminary  design, and secure funding options for an expansion of the existing recycled water delivery system in the City.  The  expansion pipeline is one of several water reuse projects being considered in the Northwest County Recycled Water  Strategic Plan.  One Water Plan development is underway to evaluate alternative water supplies, define existing  and future uncertainties and supply risks, and identify community needs and priorities. The One Water Plan is  tentatively scheduled for Council approval in 2024.   Water Fund Projects                    Status as of December 2023    Water Fund Projects – Page 2 of 5  Water  Regulation  Station  Improvements  (WS‐07000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,876,641 $2,960,477 Utilities Construction Summer 2024  Project Status: This project for Water Regulation Station Improvements includes seismic upgrades, piping  improvements and other various upgrades to increase the structural reliability of two of the City’s turnouts with  SFPUC.   Work under this project includes Seismic Upgrade of California and Page Mill Turnouts.   Structural  evaluation for restraining the Page Mill turnout and piping was included in the design.  City Council approved this  project and the construction for the Page Mill Turnout is completed. The California Avenue Turnout work will begin  in January 2024 and is anticipated to be completed in May 2024.     Water Tank  Seismic Upgrade  and  Rehabilitation  (WS‐09000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $9,574,814 $26,989,834 Utilities Construction Fall 2027  Project Status: This project for Seismic Water System Upgrades includes seismic upgrades at the Montebello,  Mayfield, Corte Madera, Park, Boronda, and Dahl Reservoirs in compliance with the American Society of Civil  Engineers (ASCE 7) seismic codes.  Mayfield Reservoir was seismically retrofitted in 2011.  Seismic upgrades of  Boronda and Montebello Reservoirs was completed in 2016 and 2018.  The new concrete Corte Madera Reservoir  was completed in April 2022. The Park Reservoir is scheduled next for retrofit or replacement, followed by Dahl  Reservoir. Park Reservoir was assessed in spring 2023, and staff completed the update to the financial analysis of  retrofit versus replacement and made a recommendation in summer 2023 to replace the tank roof. Design for Park  Reservoir is expected to be completed by the beginning of 2025, and construction completed by the end of 2026.  Dahl Reservoir will be assessed in 2025 and the retrofit and rehabilitation is expected to be completed by the end  of 2027.            Water Fund Projects                    Status as of December 2023    Water Fund Projects – Page 3 of 5  Recurring Projects  Water  Distribution  System  Improvements  (WS‐11003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $19,247 $646,029 Utilities N/A Recurring  Project Status: This project enables improvements to water distribution system deliverability and reliability.   Typical activities include installing restraining joints at critical pipelines and bridge crossings, increasing the size of  inadequate facilities, system leakage surveys, network modeling, and fire flow studies or other system  improvements as required.   Continuous evaluation of system needs and making required improvements is  necessary to maintain adequate quantities of quality water, meeting local, state, and federal safe drinking water  standards.  The Pump Station Painting project to paint the five foothill pump stations, is planned for summer 2024.     Water, Gas,  Wastewater  Utility GIS Data  (WS‐02014)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $120,703 $513,400 Utilities N/A Recurring  Project Status: This project enables contracts related to Utilities GIS (Geographic Information System) needs.  AME  database is heavily utilized by Utilities Engineering staff to update the utility information in GIS.  The updated  information is used by various City staff, such as marking/locating underground utilities to comply with USA  (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects; verifying  existing underground utilities during construction activities; creating customized utility map books for field crews  and on‐call personnel to meet their specific needs.  Annual surveying contracts collect GPS points of existing above‐ ground utility features within CIP project areas.  The data being collected continues to be used to correct the GIS  database.  Accurate utility data helps the design to select new pipe alignment to minimize construction conflicts  and provides data for additional road feature linework to be corrected in the older GIS/AVEC database via ESRI.    Water General  Equipment/Tools  (WS‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,602 $50,000 Utilities N/A Recurring  Project Status: This project acquires new equipment and tools, the replacement of existing fusion equipment, and  other associated tools.  The fusion equipment is used to fuse together pipe joints in the City's water distribution  Water Fund Projects Status as of December 2023  Water Fund Projects – Page 4 of 5  system.  Equipment and tools are required to be upgraded on an annual basis to maintain high quality standards  for the installation of the City's water distribution mains, along with the associated service standards and worker  safety and productivity measures.  Purchase of a Synergi gas model software license and completion of the gas  model is anticipated to be completed in fall 2024 to assist with the Capital Improvement Plan projects and gas  decommissioning.  Water Meters  (WS‐80015)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $116,080 $1,599,821 Utilities N/A Recurring  Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current  customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable.  This funding  also allows for annual testing and calibration of selected meters to maintain meter accuracy and reliability.  During  the AMI implementation process, approximately 50% of the meters will be replaced, with a focus on meters more  than twenty years old. Staff is currently targeting large diameter meter sets to be replaced first in preparation for  the upcoming AMI project. Staff completed testing a batch of large meters in 2023; additional testing will be  conducted in 2024.  Water Service  and Hydrant  Replacement   (WS‐80014)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $129,230 $400,000 Utilities N/A Recurring  Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goosenecks,  and fire hydrant valves and assemblies per the Fire Department’s flow testing, upgrades fire hydrants in main line  replacement project areas, and replaces existing undersized or deteriorated copper water services on an as needed  basis. Staff has been working on an extensive valve audit and to date have operated and evaluated approximately  60% of the City’s 6,500 water valves. This project will be increasing work to replace inoperative and leaking valves  identified during this audit process. In addition, the City will be doing additional work to look for possible lead  whips in our distribution system as we continue to comply with the new lead and copper rule revisions (LCRR). Water Fund Projects Status as of December 2023  Water Fund Projects – Page 5 of 5  Water System  Customer  Connections  (WS‐80013)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $781,090 $932,000 Utilities N/A Recurring  Project Status: This project allows for improvements that include new main extensions, valves, domestic services,  meters on upgraded services, backflow devices, fire services, and fire hydrants.  System extensions are required to  provide service to new large developments and to serve existing customers requesting expanded service on  Development Services projects. A total of sixty‐six water services and four hydrants were installed in 2023.  Water System  Supply  Improvements  (WS‐11004)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $14,560 $3,617,000 Utilities N/A Recurring  Project Status: This project evaluates and improves the City’s water distribution system on an as‐needed basis. This  project includes piping modifications, equipment replacements associated with water delivery, supervisory control  software upgrades, system modifications for water system quality compliance, conditional assessment of the  reliability of transmission mains, and security system installations.  The water system includes the connection  facilities between the City’s and the San Francisco Public Utility Commission’s pipelines, emergency water wells  within the City, pumping stations, water reservoirs, and pipelines. Security cameras will also be added to various  tanks, pump stations, and turnouts as part of the Security Cameras project. Staff is planning to lease  a mobile  generator for Foothill pump stations in summer 2024 and purchase generators by summer 2025.   List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date PE‐19001 Water, Gas, Wastewater  Office Remodel This project incorporated renovations to the Utilities Water Gas Wastewater  (WGW) office space at the Municipal Service Center (MSC).  The new work area  includes a small reception area, a renovated kitchen and printer area, additional  offices and cubicles, upgrades to the HVAC system, lighting improvements and  fire life safety systems upgrade.  Construction was completed in April 2023. Construction Buildings and  Facilities Public Works Spring 2023  $              1,234,354.00  FD‐22000 Extrication Tool Replacement This project provided funding for the replacement of all extrication tools for the Fire Department. Extrication tools, also known as "Jaws of Life", are used to rescue victims of car accidents and other emergencies where the victims are trapped in confined spaces. Equipment was purchased in winter 2023 and the project is complete.  Procurement Buildings and  Facilities Fire Department Winter 2023 298,200.00$                   WS‐14001 Water Main Replacement  Project 28 This project has replaced approximately 18,600 linear feet (which represents 1.6% of the City's water distribution system) of mains and 265 services on various streets in the City, including areas in the Duveneck, St. Francis, Barron Park and Charleston Meadows neighborhoods. Construction started in April 2022 and the project was substantially completed in spring 2023. Construction Water Utilities Spring 2023 10,305,619.00$             WC‐17001 Wastewater Collection  System Rehabilitation  Augmentation Project 30  This project included the design and construction of high priority mains with  structural defects that could not be addressed with routine maintenance.  The  wastewater mains on various streets in the City were replaced with  approximately 10,000 linear feet of HDPE sanitary sewer mains and associated  laterals in the Ventura, Charleston Meadows, Fair Meadow, and Palo Verde  neighborhoods.   The project achieved substantial completion in April 2023.  Construction Wastewater  Collection Utilities Spring 2023 4,656,777.00$               AP‐16000 Airport Apron Reconstruction This project included the design and reconstruction of the Palo Alto Airport  apron.  The need to reconstruct the aircraft parking apron is critical to airport  safety.  Construction Phase I was completed in November 2017.  Construction  Phase II was completed in winter 2020. Construction on Phase III reached  substantial completion  in June 2023 Construction Airport Airport Spring 2023 41,563,570.00$             PE‐21003 Magical Bridge Playground  Rubber and Synthetic Turf  Resurfacing This project replace rubberized and synthetic turf surfacing in the playground and replace play equipment including swings, climbing net, and playhouse. An IFB was issued in November 2021 and Council awarded a construction contract in spring 2022. Installation of rubberized and synthetic surfacing, replacement of climbing nets and renovation of the playhouse took place in fall 2022. Project was completed in December 2022. Construction Parks and Open  Space Public Works Fall 2022 857,380.00$                   Jun e   20 2 3 1 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date GS‐13001 Gas Main Replacement  Project 23 This project designed and constructed approximately 21,700 linear feet (which  represents 1.9% of the City's Gas distribution main system) of distribution main  and 320 gas services constructed mainly of PVC material on various streets  within the Midtown, Evergreen Park, Ventura, College Terrace, Charleston  Terrace, and Research Park neighborhoods.   Construction began in winter  2021and was completed in summer 2022  Construction Gas Utilities Summer 2022 7,951,858.00$               FD‐21000 Automated External  Defibrillator Replacement This project replaced the entire complement of Automated External  Defibrillators (AEDs) throughout City facilities and emergency response vehicles,  which currently totals 93 AEDs.  The RFP process was completed in fall 2021.   The new AEDs were purchased and deployed in summer 2022.  Procurement Buildings and  Facilities Fire Department Summer 2022  $                 237,500.00  PF‐17000 Municipal Service Center A, B,  & C Roof Replacement This project replaced the existing MSC roofs. The existing asphalt and gravel roofs have reached the end of their useful life and needed to be replaced. The new roofs will meet current cool roofing codes to optimize energy efficiency. Construction was completed in November 2022.  Construction Buildings and  Facilities Public Works Fall 2022 2,013,475.00$               EL‐16002 Capacitor Bank Installation  This project installed capacitor banks at electric substations and on distribution  lines to ensure Northern California Power Association Power Factor  requirements are met.   Capacitor banks were installed at Hanover Avenue,  Hansen Way, Maybell Avenue, and Park Boulevard Substations.    The project  was substantially completed in June 2022 and will be commissioned and  energized in summer 2022.   Construction Electric Utilities Spring 2022  $1,050,443  EL‐17007 Facility Relocation for Caltrain  Modernization Project The Utilities Department removed the overhead lines allowing for the  installation of the Overhead Catenary System above the rails for the Caltrain  Modernization.  This project was completed in spring 2022 Construction Electric Utilities Spring 2022  $3,055,472  PE‐08001 Rinconada Park Improvement This project upgraded safety, site amenities, playground facilities, a new  restroom, irrigation, drainage, and ADA accessibility improvements at  Rinconada Park.  These improvements were identified in the Rinconada Long  Range Plan (LRP).  Phase 1 of construction started in August 2021 and  construction was completed in spring 2022.  Construction Parks and Open  Space Public Works Spring 2022  $4,646,247  EL‐14005 Reconfigure Quarry Feeders  This project reconfigured the distribution circuits to the substation transformer  at Quarry Substation.  Design of QR 27 feeder replacement was completed in  spring 2021. Construction was completed in December 2021 . Construction Electric Utilities Fall 2021 792,034$  De c e m b e r  20 2 2 Jun e  20 2 2 2 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date AC‐18001 JMZ Renovation  This project provided for the relocation of the Junior Museum and Zoo to  Cubberley for two years while a new JMZ was being built, tenant improvements  to the Cubberley Auditorium and then removal of tenant improvements post‐ construction.  Construction of the new Junior Museum and Zoo started in June  2018 and was completed in late 2021. The new Junior Museum and Zoo was  opened to the public on November 12, 2021.   Construction Buildings and  Facilities Community  Services Fall 2021 2,927,870.00$               PE‐18002 High and Bryant Street  Garages Waterproofing and  Repairs  This project included a systems analysis and repaired the water proofing system  in the High Street and Bryant Street parking garages.  Water proofing repairs  were completed in the High Street parking garage.   Additional funding was  added and the contractor completed waterproofing repairs in the subterranean  stairwells in the Bryant Street garage in fall 2021. Construction Buildings and  Facilities Public Works Fall 2021 264,235.00$                   PE‐11011 Highway 101 Pedestrian  Bicycle Overpass Project As part of the 2014 Council Infrastructure Plan, this project designed and  constructed a new pedestrian bridge across Highway 101 at Adobe Creek.  Council approved a contract with Granite Construction in November 2019.   Construction began in January 2020.  The project construction completed on  November 20, 2021,  with a ribbon‐cutting ceremony and a community  celebration. Construction Traffic and  Transportation Public Works Fall 2021 22,889,453$                   EL‐12001 Underground District 46   Charleston This project undergrounded the existing overhead utility systems in the area  along the 400 block of West Charleston and El Camino Real.   Staff  completed   cable, equipment installation and 100% of customer service conversions. The  construction for the final phase of the project to install two 60 foot tall steel  poles and to reconductor the 60 kV sub‐transmission lines was completed in the  fall 2021. Construction Electric Utilities Fall 2021  $3,904,425  OS‐18001 Pearson Arastradero Preserve  Parking lot Improvement This project improved the Pearson Arastradero Preserve parking lot by  improving the base rock surfacing, adding drainage, widening the entrance for  safety, and new fencing.  This new improvement will allow the overflow parking  area to be open year round.  The work was completed in May 2021. Construction Parks and Open  Space Community  Services Spring 2021  $170,300  CB‐16001 Cubberley Community Center  Master Plan This project developed the master plan  for future use of the Cubberley  Community Center site by the City and Palo Alto Unified School District.Study Buildings and  Facilities Community  Services Spring 2021  $926,792  CB‐19001 Cubberley Building  Management Systems This project replaced the Building management System(BMS) controls for the  pavilion, Theater, Wing I, and Gyms A and B boiler rooms at the Cubberley  Community Center.  The project included the installation of control points for  each building along with controllers, valve and damper actuators. Construction Buildings and  Facilities Public Works Spring 2021  $350,000  De c e m b e r  20 2 1 21 3 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date FD‐14002 Fire Ringdown System  Replacement This project replaced the current ring down system that provides an audible  alert of calls in the fire stations.  Ongoing installations started in 2018 and were  completed with Fire Station #3. Construction Buildings and  Facilities Fire Departent Spring 2021  $400,144  PD‐14000 Internal Alarm System  Replacement The project replaced the citywide internal alarm system.  The alarms at City Hall  migrated to this new system in FY 2019, but was completed in early 2021.Construction Buildings and  Facilities Police  Department Winter 2021  $77,569  FD‐20001 Self Contained Breathing  Apparatus (SCBA) Air  Compressor Replacement This project replaced the central air compressor that provides air for the self‐ contained breathing apparatus (SCBA) tanks to ensure firefighter safety when  entering environments with hazardous air quality. Construction Buildings and  Facilities Fire Department Spring 2021  $94,500  AP‐20000 Airport Electrical  Improvements This project replaced the outdated electrical panels for the Palo Alto Airport  office rental spaces.  Construction was completed in January 2021.Construction Airport Public Works Winter 2021  $146,466  PE‐18000 New California Avenue Area  Parking Garage  This project built the California Avenue Area Parking Garage, as part of the 2014  Council Infrastructure Plan.   The parking garage has 627 parking spaces with 2  basement levels and 4 above grade floors.  The garage features an automated  parking space guidance system, EV charging stations, bicycle parking, and  motorcycle parking. The garage was opened to the public on December 8, 2020. Construction Buildings and  Facilities Public Works Fall 2020  $                 50,119,976  PF‐14002 Fire Station 1 Improvements  This project updated the individual sleeping quarters in the firehouse to address  gender issues and privacy concerns.  Fire Station #1 was the only fire station in  the City that did not have separate bedrooms to accommodate male and female  firefighters.   This project was completed in fall 2020. Construction Buildings and  Facilities Public Works Fall 2020  $187,064  GS‐18000 Gas ABS/Tenite Replacement  Project  This project replaced gas services laterals constructed of Acrylonitrile‐butadiene‐ styrene (ABS) or Tenite material on various streets.  Council approved funding in  June 2019.  The project replaced 104 ABS and Tenite gas services.  The WQCP  ABS gas service is assigned to Utility Operations for replacement and the  remaining five ABS gas services will be scheduled for replacement once the five‐ year moratorium ends on those streets.  As of November 2020, this project is  complete. Construction Gas Utilities Fall 2020  $2,615,100  SD‐19000 Loma Verde Avenue Trunk  Line Improvements  This project replaced 1,750 linear feet of storm drain with 48‐inch diameter High  Density Polyethylene (HDPE) pipe and associated catch basins, laterals and  manholes.  In addition to underground work, additional street restoration and  concrete work was completed. Work includes resurfacing one full lane on Loma  Verde from the beginning to the end of the project limits, replacement of  driveways, sidewalk, and 718 linear feet of curb and gutter.   The contract was  awarded in June 2020, construction work began in August 2020,  and was  completed in December 2020. Construction Storm Drain Utilities Fall 2020  $2,976,813  Jun e  20 2 De c e m b e r  20 2 0 4 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date WS‐19000 Mayfield Reservoir Subgrade  and Venting Repair  This project is part of the City’s recent Seismic Upgrade and Emergency Water  Supply and Storage Projects.  The reservoir was drained in 2012 for  approximately two years to allow extensive seismic rehabilitation work to be  performed and construction of a new pump station.  Subsequently hairline  cracks were sealed in the reservoir.  A geotechnical consultant was hired to  evaluate the tank foundation.  This study was completed and there were several  options identified.  Staff has completed the design and construction of the vent  Construction Water Utilities Fall 2020  $600,000  EL‐11010 Underground District 47   Middlefield, Homer, Webster,  Addison  This project undergrounded the existing overhead distribution system in the  area bounded by Middlefield Road, Homer Avenue, Webster Street, and  Addison Avenue. Installation of substructures and utility electric system is  completed.  Where possible, the overhead electric lines were removed and  poles cut down to the level of the communication lines.   Construction Electric Utilities Fall 2020  $3,649,356  WC‐16001 Wastewater Collection  System Rehabilitation   Augmentation Project 29  This project replaced of 8,972 linear feet of wastewater mains.  The sanitary  sewer mains, laterals, and manholes to be rehabilitated or replaced in this  project are located in the Charleston Meadows neighborhood.  Construction  started in February 2020 and was suspended for almost 3 months due to COVID‐ 19 County’s Shelter‐in‐Place Order.  The project is complete as of December  2020. Construction Wastewater  Collection Utilities Fall 2020  $4,434,839  PF‐18000 Parking Lot J Elevator  Modernization This project modernized the existing elevators at parking Lot J.  The project  involves upgrading the interior of the elevators, elevator control interface, call  buttons, and meeting current ADA standards.  Construction started in April  2019.  Project is complete except for the State final inspection on the second  car.  State is behind because of COVID, but the inspection should be done by the  end of July 2020.   Construction Buildings and  Facilities Public Works Spring 2020  $781,324  PE‐15003 Fire Station 3 Replacement This project replaced the existing Fire Station at Embarcadero Road and Newell  Road with a new structure that meets essential services standards and current  program needs.   Construction completed in March 2020.   Construction Buildings and  Facilities Public Works Winter 2020  $                 10,080,258  WS‐08001 Water Reservoir Coating  Improvements This project included the recoating of four steel tanks. Work under this project  was included in the Seismic Upgrade of four Steel Tanks and the three Turnout  Projects. Once construction started, it was found that the Montebello Reservoir  was in very poor condition. Due to escalating costs associated with roof  replacement, staff decided to complete construction of the Montebello  Reservoir and re‐evaluate the remaining three tanks for replacement.  Construction Water Utilities Spring 2020  $2,141,172  5 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date WS‐13001 Water Main Replacement ‐  Project 27 This project replaced approximately 9,600 linear feet of structurally deficient,  aging, or corroded water mains and services along the mains on Sand Hill Road,  Oak Creek Drive (5%) and Fulton Avenue.  Construction Water Utilities Spring 2020  $7,786,998  WC‐15001 Wastewater Collection  System Rehabilitation  Augmentation Project 28  This project enabled the design and construction of a high priority wastewater  main and lateral replacement work to reduce inflow of rainfall and ground  water into the collection system. The project replaced or rehabbed  a total of  7,655 linear feet of wastewater mains  located in the Leland Manor/Garland,  Midtown West, and Lower Page Mill/Los Altos Hills areas of the City.   Construction Wastewater  Collection Utilities Spring 2020  $5,665,897  EL‐17003 VA Hospital ‐ Customer Load  Requirements  This project met the growing electric needs of the VA Hospital. Staff has had  numerous discussions with VA Hospital on electric load growth at the hospital  and anticipated needs from the utility. Much of the cost is reimbursed to the  City by the VA Hospital. Staff has prepared preliminary designs for interim  solutions and is awaiting additional information from VA to develop long range  plans to meet their future needs.   Design Electric Utilities Spring 2020  $84,984  EL‐04012 Utility Site Security  Improvements This project added electronic security systems at utility sites to protect  equipment at electric substations, water pumping plants, reservoirs, and gas  stations from intrusion and vandalism.  Cameras and detection systems have  been installed at nine electric substations, three water stations, and one natural  gas station to monitor facilities.   Construction Electric Utilities Spring 2020  $1,644,681  EL‐11008 Rebuild Underground District  19  This project rebuilt and replaced the underground electric system in  Underground District 19, the area bounded by Forest Avenue, Waverley Street,  Addison Avenue, and Alma Street.  Construction Electric Utilities Spring 2020  $149,023  FD‐18000 Self Contained Breathing  Apparatus Replacement This project replaced Self Contained Breathing Apparatus equipment (SCBA)  used by firefighters when entering hazardous conditions when responding to  fire and hazardous materials incidents. The SCBA provides breathable air for  firefighters when entering environments where the atmosphere is immediately  dangerous to life or health.  The expected service life for SCBAs is 15 years.  Purchase Buildings and  Facilities Fire Department Spring 2020  $799,999  FD‐20000 Cardiac Monitor Replacement This project replaced the entire complement of twenty cardiac monitors in the  Department. Along with other tools needed for patient assessment and airway  verification, cardiac monitors assess cardiac activity in patients and provide  defibrillation and pacing.   Purchase Buildings and  Facilities Fire Department Spring 2020  $850,000  Jun e  20 2 0 6 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date PL‐16001 Downtown Mobility and  Safety Improvements  This project included the construction of curb extensions and the installation of  new pedestrian signal heads and traffic signal modifications in 2019 as part of  the Upgrade Downtown project. Construction Traffic and  Transportation Office of  Transportation Fall 2019  $1,819,847  FD‐20002 Thermal Imaging Cameras  Replacement     This project replaced the Thermal Imaging Cameras (TICs) on all fire and  response vehicles used to help identify the location of victims; assess the source  of fires, smoke, and heat; to assist in creating a plan of action.  Purchase Buildings and  Facilities Fire Department Fall 2019  $99,000  WC‐11000 Wastewater Collection  System Rehabilitation  Augmentation Project 24 This project  addressed areas that were identified in Wastewater Capital  Improvement Project 17 (Cleaning and Video Inspection of the Collection  System) as needing rehabilitation. This project was combined with Project 25  and 26(WC‐12001; WC‐13001).   Construction Wastewater  Collection Utilities Fall 2019  $3,131,595  WC‐13001 Wastewater Collection  System Rehabilitation  Augmentation Project 26 This project was combined with Project 24 and 25(WC‐11001; WC‐12001). All  new service laterals were installed from the new sewer main to the new sewer  cleanouts located in the City’s right‐of‐way. Construction Wastewater  Collection Utilities Fall 2019  $3,309,998  CB‐19000 Cubberley Track and Field  Replacement This project replaced the synthetic turf field, installed an all‐weather track and a  fitness area.Construction Parks and Open  Space Public Works Fall 2019  $1,851,708  PE‐14018 Baylands Boardwalk  Improvements  This project replaced the existing boardwalk with similar alignment and  configuration. Construction Buildings and  Facilities Public Works Winter 2019 2,123,681$  PE‐17009 City Hall Floor 4 Remodel This project improved the Administrative Services Department offices on the  fourth floor of City Hall.Construction Buildings and  Facilities Public Works Winter 2019 494,818$  PE‐14015 Lucie Stern Buildings  Mechanical and Electrical  Upgrades This project replaced and upgraded the mechanical, electrical, and fire/life  safety systems at Lucie Stern Children’s Theater, Lucie Stern Community  Theater, and Lucie Stern Community Center.  Construction Buildings and  Facilities Public Works Spring 2019 6,142,607$  PL‐16000 Quarry Road Improvements  and Transit Center Access This project included planning, design and construction of bicycle and  pedestrian improvements along Quarry Road.Construction Traffic and  Transportation Planning and  Community  Environment Spring 2019 5,148,378$  EL‐17008 Utility Control Center  Upgrades This project upgraded the Utility Control Center working environment. Construction Electric Utilities Winter 2019 499,997$  GS‐12001 Gas Main Replacement  Project 22 This project replaced approximately 23,700 linear feet of gas mains and services  along University Avenue and other streets in the Downtown North  nieghborhood. Construction Gas Utilities Spring 2019 11,658,997$                   WC‐12001 Wastewater Collection  System Rehabilitation /  Augmentation Project 25  This project was combined with Project 24 and 26 (WC‐11001; WC‐13001)  replacing 45,294 linear feet of sanitary sewer mains in university South,  Professorville and Old palo Alto neigborhoods. Construction Wastewater  Collection Utilities Spring 2019 3,211,998$  Jun e  201 9 D e c e m b e r  20 1 9 7 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date WQ‐14001 Dewatering and Loadout  Facility This project provides funding for the design and construction of the sludge  dewatering facility and truck loadout to retire existing dewatering and sewage  sludge incinerators.  Construction Wastewater  Treatment Public Works Spring 2019 27,497,551$                   WS‐12001 Water Main Replacement –  Project 26  This project replaced approximately 11,000 linear feet of aging water mains and  services which included water main replacement as part of the Upgrade  Downtown Project. Construction Water Utilities Spring 2019 7,506,161$  PE‐17009 City Hall Floor 5 Remodel This project improved the Planning and Community Environment (PCE)  Department offices on the fifth floor of City Hall. Construction Buildings and  Facilities Public Works Summer 2018 525,000$  AC‐14001 Baylands Nature Interpretive  Center Exhibit Improvements  This project replaced worn out or non‐functioning exhibits at the Baylands  Nature Interpretive Center.Construction Buildings and  Facilities Community  Services Summer 2018 56,000$  PE‐17000 Mitchell Park Adobe Creek  Bridge Replacement This project replaced the existing bridge over Adobe Creek in Mitchell Park. Construction Parks and Open  Space Public Works Summer 2018 250,000$  PD‐14000 Internal Alarm System  Replacement This project replaced the citywide system of panic alarms from various  departments and the Council chambers.Construction Buildings and  Facilities Police Summer 2018 78,000$  EL‐14004 Maybell 1&2 4/12kV  Conversion This project converted circuits 1 & 2 at Maybell substation from 4kV to 12kV. Construction Electric Utilities Fall 2018 364,796$  GS‐15001 Security at City Gas Receiving  Stations This project equiped the City’s four Gas Receiving Stations with video  surveillance systems. Construction Gas Utilities Summer 2018 150,000$  SD‐13003 Matadero Creek Storm Water  Pump Station and Trunk Line  Improvements  This project upgraded the capacity to the Matadero Creek Storm Water Pump  Station, which serves a low‐lying 1200‐acre area of southeastern Palo Alto. Construction Storm Drain Public Works Summer 2018 6,685,317$  AP‐16002 Wildlife Hazard Management  Plan The Wildlife hazard Management Plan identified the specific actions the airport  will take to mitigate the risk of wildlife strikes on or near the airport.Study Airport Public Works Summer 2018 63,415$  WC‐14001 Wastewater Collection  System Rehabilitation  Augmentation Project 27  This project replaced 16,859 linear feet of sanitary sewer mains of various sizes  on various streets.Construction Wastewater  Collection Utilities Winter 2018 4,022,455$  PG‐15000 Buckeye Creek Hydrology  Study  This project analyzed flooding conditions and recommended flood control  structures and drainage and erosion control solutions for the creek located  within Foothills Park.   Study Parks and Open  Space Public Works Spring 2018 167,741$  Jun e  20 1 8 D e c e m b e r  20 1 8 8 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date PE‐17004 CalTrain Corridor Video  Management System  Installation  This project replaced two existing gateway signs in the right‐of‐way for the  California Avenue business district. Construction Streets and  Sidewalks Public Works Spring 2018 1,550,000$  PF‐16003 Parking Lot Q Elevator  Modernization This project modernized the existing elevator at Parking Lot Q.Construction Buildings and  Facilities Public Works Fall 2017 170,608$  PE‐13003 Parks, Trails, Open Space, and  Recreation Master Plan  This master plan provided guidance on the recreation and improvement needs  for Palo Alto’s parks, trails, open space and recreational programs.  Study Parks and Open  Space Community  Services Fall 2017 627,057$  PE‐12003 Rinconada Park Master Plan  This project developed a plan for short, medium and long range improvements  to the regional park including the consideration of pathways, new restrooms  and playgrounds, new landscaping, and revitalization of underutilized areas  within the park.   Study Parks and Open  Space Community  Services Fall 2017 541,355$  PE‐13012 Structural Assessment of City  Bridges  The project developed an inventory of all City‐owned bridges and culvert  structures, condition assessment, cost estimate for rehabilitation, and  recommendation for future inspection frequencies, assessment and  improvements. Study Buildings and  Facilities Public Works Fall 2017 198,529$  WC‐11000 Wastewater Collection  System Rehabilitation /  Augmentation Project 24  Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced  and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of  various sizes, 779 sewer laterals, and 121 sewer manholes.   Construction Wastewater  Collection Utilities Fall 2017 3,119,806$  WC‐13001 Wastewater Collection  System Rehabilitation /  Augmentation Project 26  Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced  and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of  various sizes, 779 sewer laterals, and 121 sewer manholes.   Construction Wastewater  Collection Utilities Fall 2017 3,361,118$  PG‐13003 Golf Reconfiguration and  Baylands Athletic Center  Improvements  This project completed the rehabilitation of the Palo Alto Municipal Golf Course,  including  a new layout for the course, new prefabricated restroom, new water‐ saving turf and irrigation system, and rebranded the course as the Baylands Golf  Links. Construction Parks and Open  Space Public Works Fall 2017 13,675,177$                   GS‐11000 Gas Main Replacement –  Project 21 This project combined with GWR 19B & GMR 20 and replaced ABS gas mains  and services.  Construction Gas Utilities Winter 2017 2,364,937$  WS‐11000 Water Main Replacement –  Project 25  This project provided installation of approximately 11,869 linear feet of new  High Density Polyethylene (HDPE) water mains, 232 new HDPE water services,  and 15 new fire hydrants within the City limits.  Construction Water Utilities Winter 2017 5,445,069$  WS‐15004 Water System Master Plan  The 2015 Water System Master Plan identified present capital improvements  and replacement rates required to ensure optimal reliability levels of service to  the existing distribution and transmission systems.  Study Water Utilities Spring 2017 500,000$  De c e m b e r  20 1 7 9 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date WC‐10002 Wastewater Collection  System Rehabilitation /  Augmentation Project 23  Combined with Project 22 (WC‐09001).  This project replaced and/or  rehabilitated approximately 33,497 linear feet of sanitary sewer mains of  various sizes, 554 sewer laterals, and 102 sewer manholes.   Construction Wastewater  Collection Utilities Winter 2017 1,272,289$  EL‐10009 Street Light System  Street  Light System Conversion  Project  This project converted HPS streetlights to LED and the conversion of  approximately 4500 cobrahead streetlight fixtures.  Construction Electric Utilities Spring 2017 696,918$  EL‐13006 Sand Hill / Quarry 12kV  InterTie  This project installed new wire to connect circuits QR‐24 and QR‐27 in the Sand  Hill/Quarry area. Construction Electric Utilities Winter 2017 208,648$  EL‐15001 Electric Substation Battery  Replacement This project replaced the batteries in all nine of the City's electric substations. Construction Electric Utilities Winter 2017 400,000$  PG‐13001 Stanford/Palo Alto Playing  Fields Soccer Turf  Replacement  This project replaced the synthetic turf at the Stanford/Palo Alto Playing Fields. Construction Parks and Open  Space Community  Services Fall 2016 1,499,979$  PG‐09003 Park Maintenance Shop  Remodel  This project renovated and remodeled the Parks maintenance shop for safety  and efficienciency upgrades.Construction Parks and Open  Space Community  Services Summer 2016 94,419$  PE‐12017 City Hall First Floor  Renovations This project installed new elevator control panels and replaced the gray‐painted  panels inside the elevators.Construction Buildings and  Facilities Public Works Summer 2016 3,974,963$  PE‐11012 Temporary Main Library This project created a temporary main Library to be used while the new one was  being constructed.Construction Buildings and  Facilities Public Works 156,254$  PE‐15029 Baylands Nature Interpretive  Center Facility Improvement  The project replaced decking, railings, structural framing members, exterior  wood flooring, and cabinetry, restroom reconfiguration, and provided  Americans with Disabilities Act (ADA) improvements.   Construction Buildings and  Facilities Public Works Spring 2017 889,452$  PE‐13008 Bowden Park Improvements  This project improved the children’s playground and included park amenity  upgrades such as new playground equipment, a new retaining wall, surfacing  and pathway upgrades, planting restoration and irrigation renovations, and  replaced of damaged wood benches and the playground perimeter fence.   Construction Parks and Open  Space Community  Services Summer 2016 421,126$  PE‐13020 Byxbee Park Trails This project provided trail and site amenities over the remaining area of the  landfill cap.  Construction Parks and Open  Space Public Works Fall 2016 334,607$  Jun e  20 1 7 10 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project Budget  **CMR Date PE‐17002 City Hall Floor 3 Remodel  This project improved the Utilities Department administrative offices on the  third floor of City Hall. It included new carpet, wall reconfiguration, a  kitchenette, cabinets, paint, soundproofing, office furniture, doors, and  associated building systems.  Construction Buildings and  Facilities Public Works Spring 2017 440,000$  PE‐14015 Lucie Stern Buildings  Mechanical and Electrical  Upgrades – Phase 1  This project replaced and upgraded the mechanical, electrical, and fire/life  safety systems at Lucie Stern Children’s Theater, Lucie Stern Community  Theater, and Lucie Stern Community Center.   Construction Buildings and  Facilities Public Works Summer 2016 3,247,248$  PG‐12004 Sarah Wallis Park  Improvements  This project improved site amenities with new concrete pathways, replaced old  furnishings, and upgraded landscape with drought tolerant species. Construction Parks and Open  Space Community  Services Winter 2017 65,000$  AP‐16003 Airport Perimeter Fence  This project replaced the perimeter fencing and gates surrounding the Palo Alto  Airport boundaries to prevent unauthorized access to the airport runway in  accordance with Federal and State standards.  Construction Airport Public Works Spring 2017 2,003,540$  SD‐11101 Channing Avenue/Lincoln  Avenue Storm Drain  Improvements  This project installed of 5,800 linear feet of 36‐inch to 60‐inch diameter storm  drain along Channing and Lincoln Avenues over three project phases to increase  drainage system capacity.   Construction Storm Drain Public Works Winter 2016 7,676,275$  GS‐14004 Gas Distribution System  Model  This project included the development, model installation, testing,  documentation, and staff training of a natural gas distribution system model.  Study Gas Utilities Summer 2016 149,500$  AC‐14000 Art Center Auditorium Audio,  Visual and Furnishings This project replaced outdated audio visual equipment and furnishings  following the auditorium’s use as a temporary library.  Construction Buildings and  Facilities Community  Services Winter 2016 150,000$  PF‐15000 Rinconada Pool Locker Room This project renovated the Rinconada Pool locker room including the changing  area, restrooms, and showers in the women's and men's locker rooms.  Construction Buildings and  Facilities Public Works Winter 2016 464,433$  PE‐13016 El Camino Park Restoration This project installed new athletic fields, synthetic turf, field lighting, fencing, a  new restroom, scorekeeper booth and storage buildings, an expanded parking  lot, new bike and pedestrian pathways, landscaping, benches, and other  amenities.   Construction Parks and Open  Space Community  Services Fall 2015 5,611,122$  353,550,656$               Notes: ** Final Project Actuals may be different from Total Project Budget amounts Grand Total De c e m b e r  20 1 6 11