Agenda Item
14.Adoption of a Resolution Suspending Enforcement of Municipal Code Sections
16.14.090, 16.14.110 and 16.14.300 Requiring All-electric Construction and Direction to
Staff to Commence Work on Local Amendments to the California Energy Code
Establishing a One Margin Standard. CEQA Status – Not a Project. Presentation, Public
Comments
City Council
Staff Report
From: City Manager
Report Type: ACTION ITEMS
Lead Department: Planning and Development Services
Meeting Date: February 26, 2024
Report #:2402-2644
TITLE
Adoption of a Resolution Suspending Enforcement of Municipal Code Sections 16.14.090,
16.14.110 and 16.14.300 Requiring All-electric Construction and Direction to Staff to Commence
Work on Local Amendments to the California Energy Code Establishing a One Margin Standard.
CEQA Status – Not a Project.
RECOMMENDATION
Staff recommends that Council:
1. Consider adopting a Resolution (Attachment A) suspending enforcement of Municipal
Code sections 16.14.090, 16.14.110 and 16.14.300, which require new residential and
non-residential buildings to be all electric, in light of the decision of the U.S. Court of
Appeals for the Ninth Circuit in California Restaurant Association v. City of Berkeley; and,
2. Direct staff to return to Council with amendments to the California Energy Code as
codified in Title 16 of the Palo Alto Municipal Code Building Regulations establishing a
“One Margin” standard, which would allow for installation of natural gas plumbing while
imposing more stringent energy efficiency and all-electric readiness requirements to all
new buildings, which incentivizes the additional efficiency and lower emissions of all-
electric equipment using clean electricity.
EXECUTIVE SUMMARY
In the last five years, more than seventy U.S. cities and states have adopted regulations requiring
or strongly incentivizing new building construction to be all electric. The first of these laws was
passed in August 2019, in the City of Berkeley. In response to a court challenge the Ninth Circuit
Court of Appeals found that Berkeley’s gas infrastructure ban is invalid because it is preempted
by the federal Energy Policy and Conservation Act (EPCA). That decision is the final opinion of the
Ninth Circuit1 and applies throughout the Ninth Circuit’s jurisdictional area, which includes
California and many other western states. Moreover, the Ninth Circuit found that EPCA
preemption applies to state and local building codes.
In support of its 80-by-30 and carbon neutrality goals, in November 2022 Palo Alto adopted a set
of policies requiring that new construction and substantial remodels utilize all-electric design,
effective January 2023.2 In light of the Ninth Circuit decision, staff proposes that Council consider
two parallel paths forward.
First, staff recommends that Council consider a temporary moratorium on enforcement of Palo
Alto’s current all-electric requirement. For Council’s consideration, staff has prepared a
Resolution (Attachment A) establishing a moratorium on enforcement of Municipal Code
sections 16.14.090, 16.14.110, and 16.14.300 effective on adoption through December 31, 2024,
or until further Council action, likely on adoption of an alternative electrification program. If
adopted by Council, the Resolution would apply to pending and future development applications,
including retrofits to add gas to already-constructed buildings, and to requests to modify
previously-issued permits.
Second, staff recommends Council direction to pursue a replacement Reach Code. For a
replacement Reach Code, staff is aware of various options being considered by other agencies
and by environmental advocacy groups. Of these alternatives the codes most likely to conform
to the EPCA-preemption standards set by the court in its decision is the “One-Margin” code. Staff
believes timeliness is critical in adopting this code. Work for the 2026-2028 code cycle begins
next year in 2025, so any replacement code the City adopts in 2024 will only be in effect for just
over a year. Rather than considering and researching a variety of policy options, staff
recommends Council provide direction to proceed with development of a One Margin code.
BACKGROUND
Cities, Counties and States Adopt Building Electrification Requirements
In the last five years, more than seventy U.S. cities and states have adopted regulations requiring
or strongly incentivizing new building construction to be all electric. The first of these laws was
passed in August 2019, in the City of Berkeley. Since then, dozens of cities and counties
throughout the U.S., and several states, including Palo Alto, adopted all electric requirements for
new buildings. The laws differ in a number of respects, including the type of regulation used (e.g.
building code or health and safety regulation) and whether exceptions are made for certain uses
1 Cal. Rest. Assoc. v. City of Berkeley, 89 F.4th 1094 (9th Cir. 2024). The denial of en banc review includes a lengthy
dissent from the denial, signed by 11 of the 50 active judges who participated in consideration of the petition for
rehearing. While a dissent has no force of law, the dissenting judges explained in detail why they believe the
original three-judge panel misinterpreted EPCA and reached the wrong result, in order “to urge any future court
that interprets the Energy Policy and Conservation Act not to repeat the panel opinion’s mistakes.” Id. at p. 1119.
2 https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=82100
or building types or can be requested based on feasibility or hardship. Lawsuits have been filed
challenging many of these laws.
Palo Alto’s All-Electric New Building Requirement
In support of its 80-by-30 and carbon neutrality goals, in November 2022 Palo Alto adopted a set
of policies requiring that new construction and substantial remodels utilize all-electric design,
effective January 2023.3 There is no provision for exceptions. The City implemented this all-
electric policy though local amendments to the California Green Building Code. These
amendments can be found in:
•PAMC Section 16.14.090 (for residential uses) – requiring “full electrification” for new
buildings, substantial remodels, and new outdoor appliances/equipment such as grills,
firepits, swimming pool heaters, and similar equipment. The Code prohibits plumbing for
natural gas in addition to gas appliances. “Full electrification” is defined as “[a] building
or parcel of land whose sole source of energy is electricity and contains no combustion
equipment or plumbing for combustion equipment.”
•PAMC Section 16.14.110 (for residential uses) – requiring that Heat Pump Water Heaters
be utilized for all existing structures replacing or adding a water heater.
•PAMC Section 16.14.300 (for non-residential uses) - requiring “full electrification” for new
buildings, substantial remodels, and new outdoor appliances/equipment. The Code
prohibits plumbing for natural gas in addition to gas appliances. “Full electrification” is
defined as “[a] building or parcel of land whose sole source of energy is electricity and
contains no combustion equipment or plumbing for combustion equipment.”
Note that the base California Energy Code (CEC) already includes several measures that
effectively require heat pump space conditioning and water heating in Palo Alto’s climate zone.
Heat pumps are required for both space heating and water heating in new single-family homes,
and for space heating only in new multifamily residences and most commercial uses. While the
base CEC allows a developer to show that an alternative approach is just as energy-efficient as
heat pump space and water hearing, the vast majority of developers use the pre-approved path.
The City’s local codes go further than the base California Energy Code by: (1) requiring
electrification without allowing a theoretical alternative, (2) requiring electric appliances for
cooking and accessory uses in new single-family homes, (3) requiring heat pump water heaters
for new multifamily and commercial projects; and (4) requiring heat pumps when replacing a
water heater.
3 https://recordsportal.paloalto.gov/Weblink/DocView.aspx?id=82100
Legal Challenges to Local and State Building Electrification Laws
In adopting its all-electric requirement, Berkeley invoked its general police power to amend its
Health and Safety Code to prohibit gas piping in new building construction.4 In November 2019,
the California Restaurant Association (“CRA”) sued Berkeley, alleging, among other things, that
Berkeley’s gas infrastructure ban is invalid because it is preempted by the federal Energy Policy
and Conservation Act (EPCA).
CRA is an association of restaurant owners and chefs, purportedly including members that seek
to open or relocate a restaurant in a new building in Berkeley but for the ban on natural gas.5
CRA has publicly stated that it believes other cities’ regulations would be similarly preempted by
EPCA but sued Berkeley because it was the first city to adopt a local gas ban for new construction.
The federal trial court dismissed the suit, holding that EPCA preemption is limited to ordinances
that directly regulate covered appliances.6 CRA appealed to the Ninth Circuit. The U.S.
Department of Justice and Department of Energy weighed in, and amicus briefs were filed by
numerous state Attorneys General, associations of cities and counties, academics and interest
groups.
On April 17, 2023, the Ninth Circuit issued a decision holding Berkeley’s regulation invalid
because it is preempted by EPCA.7 Berkeley sought rehearing from a larger en banc panel of Ninth
Circuit judges. On January 2, 2024, the Ninth Circuit denied the request for en banc rehearing,
with 39 of the 50 non-recused active judges declining to review the matter. The decision of the
original three-judge Ninth Circuit panel was reissued with minor amendments that do not change
the substance or reasoning of the opinion. That decision is the final opinion of the Ninth Circuit.8
The Ninth Circuit decision applies throughout the Ninth Circuit’s jurisdictional area, which
includes California and many other western states. 9
Berkeley has 90 days from the denial of rehearing en banc to ask the U.S. Supreme Court to hear
the case (approximately April 1, 2024). If Berkeley requests review, the Supreme Court has
discretion whether to accept the case, and there is no specific time for the Court’s response. In
practice, the Court accepts only a small fraction of the review petitions it receives. Berkeley has
not announced whether it will seek Supreme Court review.
4 Berkeley Municipal Code, Chapter 12.80.
5 Cal. Rest. Assoc. v. City of Berkeley, 547 F. Supp. 3d 878, 882 (N.D. Cal. 2021).
6 Ibid.
7 Cal. Rest. Assoc. v. City of Berkeley, 65 F.4th 1045 (9th Cir. 2023).
8 Cal. Rest. Assoc. v. City of Berkeley, 89 F.4th 1094 (9th Cir. 2024). The denial of en banc review includes a lengthy
dissent from the denial, signed by 11 of the 50 active judges who participated in consideration of the petition for
rehearing. While a dissent has no force of law, the dissenting judges explained in detail why they believe the
original three-judge panel misinterpreted EPCA and reached the wrong result, in order “to urge any future court
that interprets the Energy Policy and Conservation Act not to repeat the panel opinion’s mistakes.” Id. at p. 1119.
9 The Ninth Circuit includes Alaska, Arizona, California, Hawaii, Idaho, Montana, Nevada, Oregon, Washington,
Guam and the Northern Mariana Islands.
Outside of the Ninth Circuit, legal challenges have been filed against electrification requirements
in New York City and the State of New York.
The Ninth Circuit’s decision in California Restaurant Association v. City of Berkeley
CRA v. City of Berkeley is whether CRA has sufficient standing to challenge
Berkeley’s regulation. To establish associational standing, and organization must demonstrate
that (1) at least one of its members has suffered an injury in fact that is (a) concrete and
particularized and (b) actual or imminent, rather than conjectural or hypothetical; (2) the injury
is fairly traceable to the challenged action; and (3) it is likely, not merely speculative, that the
injury will be redressed by a favorable decision.10 Because the case came to the Ninth Circuit on
appeal from an order granting a motion to dismiss—a preliminary motion that requires the court
to assume the truth of facts pled in a complaint—the Ninth Circuit held that CRA’s bare assertion
that one or more of its members would open a restaurant in a new building Berkeley but for the
all-electric ordinance was sufficient to establish standing, even without identifying an affected
member, a specific location, or a plan or timeframe for opening a restaurant.11
12 As currently implemented, DOE enforces test procedures and
minimum standards for more than 60 products covering residential, commercial and industrial,
lighting, and plumbing applications. By its terms, EPCA implements a national energy policy and
expressly preempts state and local regulations concerning the energy efficiency, energy use, and
energy conservation standards for covered products.13
CRA v. City of Berkeley, the Ninth Circuit held that the EPCA preempts Berkeley’s ordinance
because by banning gas piping in new construction Berkeley effectively rendered gas appliances
useless even though gas service is available, thereby impermissibly regulating energy use by
covered products. The court characterized Berkeley’s regulation as an attempt to circumvent
10 Cal. Rest. Assoc. v. City of Berkeley, 89 F.4th at p. 1099, citing Nat. Res. Def. Council v. EPA, 735 F.3d 873, 878 (9th
Cir. 2013).
11 Id., p. 1100.
12 42 U.S.C. §§ 6291–6309.
13 EPCA includes the following definitions: “Energy efficiency” means “the ratio of the useful output of services
from a consumer product to the energy use of such product…” 42 U.S. Code § 6291(5). “Energy use” means “the
quantity of energy directly consumed by a consumer product at point of use...” 42 U.S. Code § 6291(4). And
“energy conservation standard” is defined, among other things, as “a performance standard which prescribes a
minimum level of energy efficiency or a maximum quantity of energy use.” 42 U.S. Code § 6291(6).
EPCA preemption by doing indirectly what Congress has said may not be done directly: “Berkeley
can’t evade preemption by merely moving up one step in the energy chain and banning natural
gas piping within those buildings. Otherwise, the ability to use covered products is ‘meaningless’
if consumers can’t access the natural gas available at the meter on the premises.”14
15, the Ninth Circuit found that EPCA preemption is not limited to facial
regulations of consumer products but rather reaches regulations that “concern” covered
products (i.e., banning delivery of natural gas to appliances “concerns” the energy use of covered
products).16 The Ninth Circuit concluded that a regulation that imposes a total ban on natural gas
is not exempt from the EPCA just because it lowers energy use to zero.17
18 The Circuit noted
that there is “no doubt Berkeley’s ban, if adopted by States and localities throughout the country,
would significantly burden the sale of covered products on a national basis.”19
20, the
Ninth Circuit stated that finding EPCA preemption in this context does not necessarily require
Berkeley to affirmatively make natural gas available everywhere. Rather, the Ninth Circuit stated
that its decision is limited: the EPCA prevents Berkeley from banning gas piping from the point of
delivery at the meter within new construction buildings. The Circuit stated that its holding does
not address the question of whether Berkeley has any obligation to maintain or expand the
availability of a utility’s delivery of gas to meters21, effectively leaving that question open for now.
ANALYSIS
14 Cal. Rest. Assoc. v. City of Berkeley, 89 F.4th at p. 1107.
15 Cal. Rest. Assoc. v. City of Berkeley, 547 F. Supp. 3d 878, 891-892 (N.D. Cal. 2021).
16 Cal. Rest. Assoc. v. City of Berkeley, 89 F.4th at p. 1103-1105.
17 Id., p. 1102.
18 Id., p. 1101.
19 Id., p. 1104 (internal quotations omitted).
20 Cal. Rest. Assoc. v. City of Berkeley, 547 F. Supp. 3d 878, 891 (N.D. Cal. 2021).
21 Id., p. 1106.
reach code provisions—called One Margin—that staff, with Council direction, will bring forward
as soon as possible. Second, staff seeks Council’s endorsement to pursue development of the
One Margin program as the quickest way to implement strong incentives for new building
electrification. Staff will continue to evaluate potential regulatory approaches for the Council to
consider with the next cycle of Building Code regulations that are slated to come to Council in
2025, for 2026-2028.
Moratorium on Enforcement of PAMC Sections 16.14.090, 16.14.110, and 16.14.300
CRA v. Berkeley, state and local government
agencies within the western region covered by the Circuit that have regulations prohibiting the
installation or use of gas have repealed their regulations, suspended enforcement, or initiated
substantial changes to the regulations.22 Staff is not aware of a jurisdiction with a regulation
similar to Palo Alto’s that is continuing active enforcement.
Develop a One Margin Reach Code
22 This includes Washington state; the City of Eugene, Oregon; and the California Cities of Encinitas, Brisbane, San
Luis Obispo, Sacramento, Santa Cruz, Menlo Park and San Jose.
mixed-fuel buildings but requires them to be highly energy efficient and electrification ready, i.e.
constructed with the electric infrastructure (space in the electric panel and electric circuits) to
accommodate future electric appliances. In practice, the California Energy Code is an “electric
preferred” code, with mixed-fuel allowed but compliance being easier with all-electric equipment
since it is difficult to comply with the California Energy Code without installing electric heat pump
space and water heating systems.
•High-performance approach with additional efficiency requirements for new mixed-fuel
buildings only (All-Electric Preferred reach code)
•High-performance approach with additional efficiency requirements for all new buildings
(One Margin reach code)
•Emissions limit approach with local air quality requirements for nitrous oxides (NOx) or
other greenhouse gases
CRA v. City of
Berkeley is the “One-Margin” reach code. The decision specifically acknowledges an exception
within EPCA that allows for reach codes, provided they satisfy seven requirements.23 The One-
23 42 USC 6297 (3)”… [A] regulation or other requirement contained in a State or local building code for new
construction concerning the energy efficiency or energy use of such covered product is not superseded by this part
if the code complies with all of the following requirements:
(A) The code permits a builder to meet an energy consumption or conservation objective for a building by selecting
items whose combined energy efficiencies meet the objective.
(B) The code does not require that the covered product have an energy efficiency exceeding the applicable energy
conservation standard established in or prescribed under section 6295 of this title, except that the required
efficiency may exceed such standard up to the level required by a regulation of that State for which
the Secretary has issued a rule granting a waiver under subsection (d).
(C) The credit to the energy consumption or conservation objective allowed by the code for installing covered
products having energy efficiencies exceeding such energy conservation standard established in or prescribed
under section 6295 of this title or the efficiency level required in a State regulation referred to in subparagraph (B)
is on a one-for-one equivalent energy use or equivalent cost basis.
(D) If the code uses one or more baseline building designs against which all submitted building designs are to be
evaluated and such baseline building designs contain a covered product subject to an energy conservation
standard established in or prescribed under section 6295 of this title, the baseline building designs are based on
Margin reach code applies additional efficiency requirements to all new buildings, but takes into
account energy use at the source, which favors the additional efficiency and lower emissions of
all-electric equipment using clean electricity. It uses standard energy modeling practices to set
its requirements rather than novel approaches like local air-quality standards. It does not
discriminate between gas and electric appliances like an “Electric-preferred” code.
the efficiency level for such covered product which meets but does not exceed such standard or the efficiency level
required by a regulation of that State for which the Secretary has issued a rule granting a waiver under subsection
(d).
(E) If the code sets forth one or more optional combinations of items which meet the energy consumption or
conservation objective, for every combination which includes a covered product the efficiency of which exceeds
either standard or level referred to in subparagraph (D), there also shall be at least one combination which
includes such covered product the efficiency of which does not exceed such standard or level by more than 5
percent, except that at least one combination shall include such covered product the efficiency of which meets but
does not exceed such standard.
(F) The energy consumption or conservation objective is specified in terms of an estimated total consumption
of energy (which may be calculated from energy loss- or gain-based codes) utilizing an equivalent amount
of energy (which may be specified in units of energy or its equivalent cost).
(G) The estimated energy use of any covered product permitted or required in the code, or used in calculating the
objective, is determined using the applicable test procedures prescribed under section 6293 of this title, except
that the State may permit the estimated energy use calculation to be adjusted to reflect the conditions of the
areas where the code is being applied if such adjustment is based on the use of the applicable test procedures
prescribed under section 6293 of this title or other technically accurate documented procedure.
Thus, if the City were to pursue the One Margin reach code amendment, then time is of the
essence. Because staff will begin it work on comprehensive building code updates for the 2026-
2028 code cycle early next year, any replacement code the City adopts in the interim will be in
effect for approximately one year. Rather than considering and researching a variety of policy
options, staff recommends Council provide direction to proceed with development of a One
Margin code. Staff would aim for fall of this year for adoption if possible. Staff will continue to
track other approaches by state or local agencies, and if they appear viable staff can present them
as policy options as part of the work on the updates for the 2026-2028 code cycle.
FISCAL/RESOURCE IMPACT
STAKEHOLDER ENGAGEMENT
ENVIRONMENTAL REVIEW
ATTACHMENTS
APPROVED BY:
Attachment A
NOT YET APPROVED
Resolution No. _________
Resolution of the Council of the City of Palo Alto
Establishing a Temporary Moratorium on Enforcement of Palo Alto Municipal Code
Sections 16.14.090, 16.14.110 and 16.14.300 (Requiring Full Electrification for New and
Substantially Remodeled Residential and Commercial Buildings)
R E C I T A L S
A. On November 14, 2022, the Palo Alto City Council adopted an ordinance amending Title
16 of the Palo Alto Municipal Code, Chapter 14, by adding Sections 16.14.090, 16.14.110 and
16.14.300 (the “Electrification Requirements”) to support progress towards the City’s 80-by-30
carbon reduction goal by promoting electrification of new residential and commercial
construction and substantial remodels.
B. The Electrification Requirements prohibit installation of combustion equipment or
plumbing for combustion equipment in new residential and non-residential buildings, in
substantial remodels of residential and non-residential buildings, and with respect to new
outdoor appliances and equipment such as grills, firepits, swimming pool heaters, and similar
equipment. The Electrification Requirements also require use of heat pump water heaters for
all existing structures replacing or adding a water heater. The Electrification Requirements
became effective January 1, 2023.
C. In the case of California Restaurant Association v. City of Berkeley, 89 F.4th 1094 (9th
Cir. 2024), the United States Court of Appeals for the Ninth Circuit held that the state and local
governments may not prohibit installation of gas piping in new construction because such
regulations are preempted by the Energy Policy and Conservation Act (EPCA), 42 U.S. Code sect.
6201 et. seq.
D. The Palo Alto Council finds that suspending enforcement of the Electrification
Requirements is appropriate at this time, pending potential further developments including,
but not limited to, final resolution of California Restaurant Association v. City of Berkeley
litigation or amendments to the EPCA and any rules promulgated thereunder.
NOW, THEREFORE, the Council of the City of Palo Alto does hereby RESOLVE as follows:
SECTION 1. Enforcement of Palo Alto Municipal Code Sections 16.14.090, 16.14.110 and
16.14.300 is suspended. This moratorium on enforcement is effective immediately on adoption
of this Resolution and shall remain in place until repealed by Council or December 31, 2024,
whichever is sooner. This moratorium on enforcement shall apply to all applications for building
permits or other development project entitlements including, without limitation, currently-
pending applications, new applications filed after adoption of this Resolution, requests for
Attachment A
NOT YET APPROVED
modification of pending applications, and applications for modification of previously-issued
permits or entitlements.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSENT:
ABSTENTIONS:
ATTEST:
City Clerk Mayor
APPROVED AS TO FORM:
City Manager or Designee
City Attorney
Director of Planning and Development
Services
February 26, 2024 www.cityofpaloalto.org
Item 14 – Resolution Suspending Reach Code Enforcement
City Council
1
Background
•Since 2019 more than 70 US cities/states have adopted
incentives or requirements for all-electric construction
•The City adopted its Reach Code Nov 2022, effective Jan 2023
•Requires all-electric design for new buildings with no exceptions
•Applies to some types of remodels
•City's existing code exceeds the State's Code, which:
•Requires significant energy efficiency, making it far easier to comply
with heat pump space and water heating
•Mixed-fuel homes would require large solar and storage systems
•Requires electrification readiness for mixed-fuel homes
1
Legal Challenges to Building Electrification Laws
•California Restaurant Association v. City of Berkeley
•Challenge to Berkeley’s ban on gas piping in new construction
•Final 9th Circuit decision (1/2/2024) invalidated Berkeley’s ban
•Berkeley has 90 days to seek review in the U.S. Supreme Court
•Implications for Reach Codes in 9th Circuit Jurisdiction
•9th Circuit held that Federal Energy Policy and Conservation Act (EPCA)
preempts state and local regulations for covered products
•All-electric codes are very likely preempted
•Project applicants in Palo Alto are requesting clarification of
the City’s regulations
1
Other Cities Actions
•At least seven cities have suspended enforcement of their
all-electric Reach Codes
•Staff is not aware of any jurisdiction continuing enforcement
•Some cities have adopted alternatives
•Zero NOx Code (Town of Los Altos Hills)
•Uses State code section authorizing local agencies to establish
air pollution standards stricter than State/Federal standards
•One Margin Code (San Luis Obispo, Santa Cruz, San Jose)
•Applies a single efficiency standard to all-electric and mixed-
fuel buildings
•Takes source energy into account (easier to meet with all-
electric design)
1
Staff Recommendation
•Staff recommends suspending enforcement of Palo Alto’s
all-electric Reach Code
•Once enforcement is suspended, new construction would be
subject to the State’s Code
•Staff also recommends Council direct staff to pursue the
One Margin Code approach for fall adoption
•Staff evaluating resources required
•This code would apply through the end of 2025, when the
2026 – 2028 code cycle begins
•Staff can evaluate alternatives to the One Margin code when
developing recommendations for the 2026-2028 code cycle
From:David Coale
To:Council, City; Shikada, Ed; Abendschein, Jonathan; Lait, Jonathan; Eggleston, Brad
Subject:Suspension of all electric code
Date:Monday, February 26, 2024 9:02:21 AM
CAUTION: This email originated from outside of the organization. Be cautious of opening attachments and clicking on links.
Dear Mayor and Council members,
It is too bad that Palo Alto is suspending it’s all electric code for what is a technicality in the
law suit brought against Berkeley for their ban of gas piping in new buildings. Berkeley is
correct in calling out the health issues with gas use in buildings. The BAAQMD has passed a
ruling that new appliances should produce zero Nox starting in 20271, due to health issues
with the combustion of natural gas. This rule however did not address gas cooktops in that
BAAQMD does not address indoor air quality. This is, in my mind, another unfortunate
technicality as gas cooktops produce much worse air quality and potential health issues
(https://www.mothersoutfront.org/news/gas-stoves-health-and-air-quality-impacts-and-
solutions/)2 than the other gas appliances in the home.
With Staff’s recommendations, Palo Alto will have three different sets of rules for gas use in
the home within a year’s time frame. Another unfortunate outcome of a technicality where no
other city, accepting Berkeley, has had a problem with their gas bans. It would be best to just
keep the codes the way they are until the change is ready to be put in place, reducing extra
work and confusion of having three different rules.
In any event, the Development Center should be reminding all applicants that are looking to
install gas cooktops, that according to real estate law, any item or condition that might affect
the cost of a home upon sale, must be disclosed to the buyer. This would include gas cooktops
as multiple studies have found that childhood asthma rates are 20% higher in homes with gas
cooktops3.
Sincerely,
David Coale
----------
1 FAQ on BAAQMD ruling for zero Nox appliances:
https://www.baaqmd.gov/~/media/dotgov/files/rules/reg-9-rule-4-nitrogen-oxides-from-fan-
type-residential-central-furnaces/2021-amendments/documents/20230522_faq_appliance-
rules_final-pdf.pdf?rev=b425fe938f644fa7839f8d938cad41fd
2 Study by Physicians for Social Responsibility, Rocky Mountain Institute, Sierra Club and Mothers Out
Front. Many references cited in the appendix of this report.
https://www.mothersoutfront.org/news/gas-stoves-health-and-air-quality-impacts-and-
solutions/
3 Population Attributable Fraction of Gas Stoves and Childhood Asthma in the United States:
https://www.mdpi.com/1660-4601/20/1/75
From:Andrea Eckstein Gara
To:Council, City
Cc:Hilary Glann; aashton@gmail.com
Subject:Comment RE: Item 14, Feb. 26 Council Regular Meeting
Date:Friday, February 23, 2024 5:39:30 PM
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
Palo Alto City Council Members,
We, as environmentally concerned community groups, have been watching developments
after the Berkeley 9th Circuit Court of Appeals decision closely. While we acknowledge that
the city has an incentive to be conservative and avoid lawsuits, we also know that we
cannot allow the chilling effect of this case to slow our response to climate change. Our
S/CAP goals remain in place, and 2030 is not far away. Scientists have confirmed this past
year that 2030 is indeed the date by which steep emissions cuts must be made.
We were also disheartened to see recently that Palo Alto did not meet a number of our
climate goals for the past year, putting our 80 x 30 goal further in jeopardy. As Council
considers One Margin as the model to replace our all-electric reach codes, here are some
other steps that we would like to see taken:
1.
The Berkeley decision focused on EPCA covered indoor appliances. The city
should continue to enforce parts of the reach codes that are not affected by the
ruling, for example gas lines to outdoor appliances, such as fire pits and
BBQs.
2.
We all know that, despite this set-back, electrification is coming due to state and
regional regulations, such as BAAQMD and CARB rules on NOX-emitting appliance
sales. The city should continue to enforce and expand electrification readiness
in remodels and new construction.
3.
Studies have shown that building electric-only multi-family homes is less expensive
than dual-fuel homes. The city needs to encourage developers, through
incentives and through a streamlined permitting process, to build all multi-
family homes with only electric power. This could be done by utilizing bonus FAR
or other development incentives if projects agree to electrification. This could apply to
the approximately 2,000 Builders Remedy units that have been submitted to the city.
4.
We are now entering a window of backsliding on our electrification goals, as new
construction will continue without electrification mandates. The city should enact One
Margin quickly to contain the damage.
5.
Nevertheless, damage will be done as some residents are likely to opt for dual-fuel
new construction. The city should consider other steps that could be taken to
make up for this S/CAP set-back.
a.
Create near-term incentive (rebate) for replacement of older gas furnaces with
heat pump HVAC systems, followed by development of a heat [ump HVAC
program modeled on the HPWH program.
b.
Fast-track action on other S/CAP goals, such as building housing near transit,
increasing allowable density near transit, increasing the number of bike
lanes/facilities and pedestrian connections within the city, charging for parking,
and requiring unbundled parking at new developments, etc.
c.
Widen Tier 1 electricity pricing to cover more electric consumption, so that
whole home electrification + EV ownership is not penalized.
d.
Continue appealing to the State for a legislative fix to the Berkeley setback.
e.
Lean into the pollution arguments against burning fossil fuels: ramp up the
public awareness campaign about health dangers of burning methane gas
inside the home, and in the community.
f.
f) Develop a public awareness campaign on how to use batteries large and
small (including using the batteries in electric vehicles) to provide power to a
home during an outage and/or develop a battery/backup strategy at different
substations to keep a low level of power available at all Palo Alto homes.
Finally, the Berkeley decision does not address the gas distribution system, so the ruling
has no bearing on setting a gas sunset date. Here is a quote from the 9th circuit
opinion:
“…our holding here has nothing to say about a State or local government regulation of a
utility’s distribution of natural gas to premises where covered products might be used.” (end
quote)
A gas sunset date, which is specified in our S/CAP goals, should be set quickly for
ease of planning and to accelerate the switch to electric buildings, getting us back on track
to meet our sustainability pledges.
Thank you,
350 SV Palo Alto
Palo Alto Forward
From:bretande@pacbell.net
To:Council, City
Subject:Temporary Moratorium on Reach Code Enforcement, Feb 26 Council Agenda item 14
Date:Friday, February 23, 2024 9:17:47 AM
Some people who received this message don't often get email from bretande@pacbell.net. Learn why this isimportant
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
Subject: Temporary Moratorium on Reach Code Enforcement, Feb 26 Council
Agenda item 14
Honorable Council Members and City Staff,
City staff is to present its proposal for a temporary moratorium on reach code
enforcement at the next Council meeting. Their idea to switch to implement a One
Margin reach code as soon as possible looks like a good way to minimize the
duration of the suspension and avoid continued litigation risks.
We recommend the following actions to minimize the risk of backsliding on our new
building electrification efforts.
Consider implementing a “stranded gas asset” fee to pay for the permitting,
installation and eventual decommissioning of new stranded gas assets that will
unnecessarily burden existing gas customers. The state base code already
requires mixed fuel buildings to be all-electric as the switch to electric
appliances is inevitable while we transition away from gas.
Clearly communicate that the suspension is temporary and limited. The
suspension of the reach code is a temporary measure to avoid the risk of
litigation created by a surprise court ruling. It also appears that the suspension
should only apply to the extension of gas piping from existing meters to points
within the new building. The staff report indicates that the city is under no
obligation to continue or expand service to gas meters or to connect new gas
meters:
From the Staff Report, p6: “Rather, the Ninth Circuit stated that its
decision is limited: the EPCA prevents Berkeley from banning gas piping
from the point of delivery at the meter within new construction buildings.
The Circuit stated that its holding does not address the question of
whether Berkeley has any obligation to maintain or expand the availability
of a utility’s delivery of gas to meters effectively leaving that question open
for now.”
Use the announcement of the moratorium as an opportunity to reiterate the
benefits of the city’s electrification investments in our community.
The city is establishing all-electric building codes in order to meet the
changing needs and desires of the Palo Alto community
CPAU is helping customers avoid further investment in obsolete gas
equipment and go all-electric in the interest of safety, health, efficiency,
reliability, resiliency and economic savings. At the planning stage, a notice
regarding the more serious indoor health risks of gas stoves (reference link)
may additionally help people to avoid them in the first place.
CPAU is investing over $300M to maintain and modernize our electric grid
to support a complete electric transition for all buildings, new and existing,
by 2030.
The most important steps for CPAU and building owners to take now is to
avoid the installation of obsolete gas infrastructure that burdens us with
extra costs and locks in damaging climate-harming carbon pollution for
years.
Thank you for considering our perspective.
Carbon Free Palo Alto
From:Ryan Palmer
To:Council, City
Cc:Chris Wade; John Beard; Lait, Jonathan; Yang, Albert
Subject:Comment Letter // February 26, 2024 Meeting - Agenda Item 14 (Suspension of All-Electric Code Sections)
Date:Thursday, February 22, 2024 1:18:00 PM
Attachments:CRW Comment Letter re Gas Ban Moratorium (02-22-24) (01342810xA4507).PDF
Some people who received this message don't often get email from ryan@ssllawfirm.com. Learn why this isimportant
CAUTION: This email originated from outside of the organization. Be cautiousof opening attachments and clicking on links.
Good Afternoon – please see the attached comment letter from Christine R. Wade regarding the
above referenced subject matter. Let us know if you have any questions or have trouble opening
the attached.
Thank you,
Ryan PalmeR | Paralegal | SSl laW FIRm llP | 505 Montgomery Street, Suite 620 | San Francisco, CA 94111 |
Direct: 415.243.2680 | Cell: 415.652.0503 | Fax: 415.814.6401 | Email: ryan@ssllawfirm.com
This email and any attachments may contain material that is confidential, privileged and/or attorney work product for the sole use of the intended recipient. Any review,
reliance or distribution by others or forwarding without express permission is strictly prohibited. If you are not the intended recipient, please contact the sender and
delete all copies. Legal Advice Disclaimer: You should recognize that responses provided by this e-mail means are akin to ordinary telephone or face-to-face
conversations and do not reflect the level of factual or legal inquiry or analysis which would be applied in the case of a formal legal opinion. A formal opinion could
reach a different result.
505 MONTGOMERY STREET, SUITE 620
SAN FRANCISCO, CA 94111
TELEPHONE: 415.814.6400
FACSIMILE: 415.814.6401
business@ssllawfirm.com
CHRISTINE R. WADE
DIRECT TEL: 415.243.2088
chris@ssllawfirm.com
February 22, 2024
VIA EMAIL ONLY
City Council
CITY OF PALO ALTO
Office of the City Clerk – City Hall, 7th Floor
250 Hamilton Avenue
Palo Alto, CA 94301
City.Council@cityofpaloalto.org
RE: FEBRUARY 26, 2024 MEETING, AGENDA ITEM 14;
SUSPENSION OF ALL-ELECTRIC CODE SECTIONS
Dear City Council Members,
We write on behalf of the owner of residential real property at 1325 Parkinson Avenue,
Palo Alto, California 94303 in support of City staff’s recommendation on Agenda Item 141 for the
City Council to adopt a resolution suspending enforcement of Municipal Code sections 16.14.090,
16.14.110, and 16.14.300 (“All-Electric Requirements”).
And, as discussed further below, we also write to confirm our understanding of the impact
of the draft resolution, if adopted as is, on previously-issued building permits that required the
removal of a property’s gas connection and meter and with which the property owner has already
complied.
I. Recent federal case law compels the City to suspend enforcement of the All -
Electric Requirements.
We believe that the draft resolution is not only consistent with the recent decision by the
United States Court of Appeals for the Ninth Circuit in California Restaurant Association v. City
of Berkeley,2 it is compelled by it due to the similarity between Berkeley’s prohibition and the
City’s All-Electric Requirements.
Like Berkeley’s prohibition on “natural gas infrastructure” (i.e., “fuel gas piping”),
Palo Alto’s All-Electric Requirements prohibit plumbing for combustion equipment in newly
1 Item 14 of the February 26, 2024 agenda: “Adoption of a Resolution Suspending Enforcement of Municipal Code Sections
16.14.090, 16.14.110 and 16.14.300 Requiring All-electric Construction and Direction to Staff to Commence Work on Local
Amendments to the California Energy Code Establishing a One Margin Standard. CEQA Status – Not a Project.”
2 Case No. 21-16278, filed on April 17, 2023, as amended January 2, 2024 (“CRA v. Berkeley”).
City Council
CITY OF PALO ALTO
February 22, 2024
Page 2 of 2
constructed buildings. (The All-Electric Requirements also prohibit such plumbing for existing
buildings undergoing alterations or additions.) The CRA v. Berkeley court reasoned that the
Berkeley prohibition was a building code that prohibits consumers from using natural gas-powered
appliances. The All-Electric Requirements cannot be reasonably distinguished from the Berkeley
prohibition—both concern gas piping and both can be considered “building codes” as discussed in
CRA v. Berkeley.
Like City staff, we believe that “[g]iven this similarity, the City of Palo Alto faces legal
risk if it were to continue enforcement of its blanket prohibition on natural gas plumbing in new
buildings.” (City Council Staff Report for Item 14.)
II. Impact on previously-issued building permits.
The draft resolution states, “This moratorium on enforcement shall apply to all applications
for building permits or other development project entitlements including, without limitation,
currently pending applications, new applications filed after adoption of this Resolution, requests
for modification of pending applications, and applications of previously-issued permits or
entitlements.” (Section 1.)
Our understanding is that the resolution would allow for property owners with previously-
issued building permits for alterations or additions to their homes to re-install gas piping (and
meters, etc.) for gas-powered appliances, even if they had previously removed such piping in
accordance with their permits. We believe our position is supported by the Ninth Circuit’s decision
in CRA v. Berkeley, and by City staff.3
We ask that the Counsel and/or staff confirm our understanding and comment on the steps
such owners should take to reinstall gas piping.
Very truly yours,
SSL LAW FIRM, LLP
Christine R. Wade
cc: Client
Jonathan Lait (jonathan.lait@cityofpaloalto.org)
Albert Yang (Albert.Yang@CityofPaloAlto.org)
[all via email]
3 As stated in the City Council Staff Report, “If adopted by Council, the Resolution would apply to pending and future development
applications, including retrofits to add gas to already-constructed buildings, and to requests to modify previously-issued permits.”