HomeMy WebLinkAboutStaff Report 2303-11931
9
3
5
City Council
Staff Report
From: City Manager
Report Type: CONSENT CALENDAR
Lead Department: Public Works
Meeting Date: June 12, 2023
Report #: 2303-1193
TITLE
Authorize Amendment No. 2 to Contract No. C20175537 with Kennedy Jenks Consultants, Inc. to
extend the term of the contract for the Primary Outfall Line Project (WQ-19002) through
December 31, 2027
RECOMMENDATION
Staff recommends that Council approve and authorize the City Manager or their designee to
execute Amendment No. 2 to Contract No. C20175537 with Kennedy Jenks Consultants (Kennedy
Jenks) (Attachment A) to extend the term of the contract for the Primary Outfall Line (Outfall)
Project (WQ-19000) four years through December 31, 2027.
BACKGROUND
The Regional Water Quality Control Plant (RWQCP) discharges treated effluent to the San
Francisco Bay through a 54-inch diameter outfall line installed in 1964 that passes beneath the
Palo Alto Airport. The RWQCP’s Long Range Facilities Plan accepted by Council in July 20121
identified the need for a capital project to replace and rehabilitate the outfall pipeline due to
insufficient capacity in the existing outfall line. On October 16, 2016, after completion of a
request for proposals process, Council approved a professional services contract2 for design
services with Kennedy Jenks Consultants for the RWQCP Primary Outfall Line Project (WQ-
19000). On December 14, 2022, the contract was amended (Amendment No. 1) to extend the
contract duration six months through June 30, 2023, with no cost impact.
1 City Council, July, 2 2012; Agenda Item #7; SR# 2914, https://www.cityofpaloalto.org/files/assets/public/agendas-
minutes-reports/reports/city-manager-reports-cmrs/year-archive/2012/id-2914.pdf
2 City Council, October,16,2016; Agenda Item #4; SR#7245,
https://www.cityofpaloalto.org/files/assets/public/agendas-minutes-reports/reports/city-manager-reports-
cmrs/year-archive/2016/101716-7245-design-services-for-wqcp-primary-outfall-line-design.pdf
Item 5
Item 5 Staff Report
Item 5: Staff Report Pg. 1 Packet Pg. 139 of 461
1
9
3
5
ANALYSIS
A number of issues related to approvals from regulatory bodies (e.g., State Lands Commission
and the Federal Aviation Administration) require significant redesign work for the outfall project,
and therefore staff recommends extending the term of the professional services contract with
Kennedy Jenks.
The contract with Kennedy Jenks is expiring June 30, 2023 and requires amendment for a new
contract expiration date. A further amendment increasing the not-to-exceed value of the
contract will also be required when the precise project timeline and scope of new services are
determined. The not-to-exceed value of the design contract is $279,660, of which $193,603 has
been spent to date.
Kennedy Jenks completed design on the outfall pipeline in September 2020. All permits were
obtained, except from the Federal Aviation Administration (FAA). In parallel with the Outfall
Pipeline project design, Public Works Department staff had been working with regional and
federal agencies on a new elevated flood protection levee, protecting low-lying areas including
the airport and the RWQCP. Reconciliation of these issues requires redesign of the outfall. In
addition, some project permit applications need to be re-filed. Council approval of the Kennedy
Jenks contract term extension will support the redesign and re-permitting efforts for a safer,
deeper pipe.
Design and re-permitting are anticipated to take an estimated two years, followed by
construction. Construction of the Outfall project is estimated to be completed by December 31,
2027, with engineering services during construction scheduled to be completed by the same
date.
FISCAL/RESOURCE IMPACT
While there is no fiscal impact associated with the contract amendment, redesign of the outfall
pipeline to be deeper is expected to increase construction cost. Staff cannot provide a precise
estimate of ultimate project construction cost at this time, but for context, the pipeline
construction cost estimate from the initial design work was approximately $11 million.
The design and construction of the project are included in the Wastewater Treatment Enterprise
Fund, Capital Improvement Program using Outfall Design (WQ-19002) and Outfall Pipeline
Construction (WQ-19000), respectively. The project costs are shared among the City’s partner
agencies, with Palo Alto’s share being 38.16%.
STAKEHOLDER ENGAGEMENT
This project is part of the Plant’s major capital improvement program funded by Palo Alto and its
five additional partner agencies. The five partner agencies are regularly updated about both the
need for and the progress on wastewater treatment capital work. Updates are provided each
year at an annual meeting and at other periodic meetings established to inform partner agency
Item 5
Item 5 Staff Report
Item 5: Staff Report Pg. 2 Packet Pg. 140 of 461
1
9
3
5
staff about the major capital improvement program. With respect to Palo Alto itself, the open
meetings on the budget process serve as the main vehicle for engaging the community on both
new projects such as this and associated rate impacts.
ENVIRONMENTAL REVIEW
Because the new outfall alignment will be constructed near the sensitive Baylands environmental
habitat, environmental review under CEQA was completed through preparation of an Initial
Study/Mitigated Negative Declaration. This project was evaluated in the Outfall Project Mitigated
Negative Declaration adopted by Council on May 21, 20183.
Although the pipeline alignment will not change with this re-design, the pipe profile will be
deepened. As a result of the deeper profile, a CEQA amendment may be required as part of the
re-permitting effort for the project.
ATTACHMENTS
Attachment A: C20175537 Kennedy Jenks Contract Amendment No. 2
APPROVED BY:
Brad Eggleston, Director Public Works/City Engineer
3 City Council, May 21, 2018; Agenda Item #4; SR# 9096,
https://www.cityofpaloalto.org/files/assets/public/agendas-minutes-reports/reports/city-manager-reports-
cmrs/year-archive/2018/id-9096-council-approval-of-an-mnd-and-design-of-rwqcp-new-outfall-line.pdf
Item 5
Item 5 Staff Report
Item 5: Staff Report Pg. 3 Packet Pg. 141 of 461
Vers.: Aug. 5, 2019
Page 1 of 4
AMENDMENT NO. 2 TO CONTRACT NO. C20175537
BETWEEN THE CITY OF PALO ALTO AND
KENNEDY/JENKS CONSULTANTS, INC.
This Amendment No. 2 (this “Amendment”) to Contract No. C20175537 (the “Contract” as
defined below) is entered into as of June 12, 2023, by and between the CITY OF PALO ALTO, a
California chartered municipal corporation (“CITY”), and KENNEDY/JENKS CONSULTANTS, INC., a
California corporation, located at 1500 NE Irving Street, Suite 200, Portland, OR 97232
(“CONSULTANT”). CITY and CONSULTANT are referred to collectively as the “Parties” in this
Amendment.
R E C I T A L S
A. The Contract (as defined below) was entered into by and between the Parties hereto
for the provision of providing engineering design and support services for a new outfall pipeline at
the Regional Water Quality Control Plant (RWQCP), as detailed therein.
B. The Parties entered into Amendment No. 1 to extend the contract term by six (6)
months through June 30, 2023, at no additional cost to the City, as detailed therein.
C. The Parties now wish to amend the Contract in order to extend the contract term by
fifty-five (55) months through December 31, 2027, at no additional cost to the City, as detailed
herein.
NOW, THEREFORE, in consideration of the covenants, terms, conditions, and provisions of
this Amendment, the Parties agree:
SECTION 1. Definitions. The following definitions shall apply to this Amendment:
a. Contract. The term “Contract” shall mean Contract No. C20175537
between CONSULTANT and CITY, dated August 12, 2019, as amended by:
Amendment No. 1, dated December 14, 2022
b. Other Terms. Capitalized terms used and not defined in this Amendment
shall have the meanings assigned to such terms in the Contract.
SECTION 2. Section 2 “TERM” of the Contract is hereby amended to read as follows:
“The term of this Agreement shall be from the date of its full execution through the earlier of
December 31, 2027, or completion of the services in accordance with the Schedule of Performance
attached at Exhibit “B” unless terminated earlier pursuant to Section 19 of this Agreement.”
DocuSign Envelope ID: 196CE771-E0D9-4AE5-9657-EBD606D28C35
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 4 Packet Pg. 142 of 461
Vers.: Aug. 5, 2019
Page 2 of 4
SECTION 3. The following exhibit(s) to the Contract is/are hereby amended or added, as
indicated below, to read as set forth in the attachment(s) to this Amendment, which is/are hereby
incorporated in full into this Amendment and into the Contract by this reference:
a. Exhibit “B” entitled “SCHEDULE OF PERFORMANCE, AMENDMENT NO. 2”,
AMENDED, REPLACES PREVIOUS.
SECTION 4. Legal Effect. Except as modified by this Amendment, all other provisions of the
Contract, including any exhibits thereto, shall remain in full force and effect.
SECTION 5. Incorporation of Recitals. The recitals set forth above are terms of this
Amendment and are fully incorporated herein by this reference.
(SIGNATURE BLOCK FOLLOWS ON THE NEXT PAGE.)
DocuSign Envelope ID: 196CE771-E0D9-4AE5-9657-EBD606D28C35
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 5 Packet Pg. 143 of 461
Vers.: Aug. 5, 2019
Page 3 of 4
SIGNATURES OF THE PARTIES
IN WITNESS WHEREOF, the Parties have by their duly authorized representatives executed
this Amendment effective as of the date first above written.
CITY OF PALO ALTO
______________________________
City Manager
APPROVED AS TO FORM:
______________________________
City Attorney or Designee
KENNEDY/JENKS CONSULTANTS, INC.
Officer 1
By:___________________________
Name:________________________
Title:_________________________
Officer 2
By:___________________________
Name:________________________
Title:__________________________
Attachments:
Exhibit “B” entitled “SCHEDULE OF PERFORMANCE, AMENDMENT NO. 2” (AMENDED, REPLACES
PREVIOUS)
DocuSign Envelope ID: 196CE771-E0D9-4AE5-9657-EBD606D28C35
Mark Minkowski, Vice President
Vice President
Vice President
Patrick Huston, Assistant Secretary
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 6 Packet Pg. 144 of 461
Vers.: Aug. 5, 2019
Page 4 of 4
EXHIBIT “B”
SCHEDULE OF PERFORMANCE, AMENDMENT NO. 2
(AMENDED, REPLACES PREVIOUS)
CONSULTANT shall perform the Services so as to complete each milestone within the number of
weeks specified below. The time to complete each milestone may be increased or decreased by
mutual written agreement of the project managers for CONSULTANT and CITY so long as all work is
completed within the term of the Agreement. CONSULTANT shall provide a detailed schedule of
work consistent with the schedule below within 2 weeks of receipt of the Notice to Proceed (NTP).
Milestones Completion No. of Weeks from NTP
(NTP issued on August 21, 2019)
1. Design Re-Kickoff Meeting 02
2. Submit 100% Design (Bid Documents) 10
3. Services During Bidding 290
4. Services During Construction 436
DocuSign Envelope ID: 196CE771-E0D9-4AE5-9657-EBD606D28C35
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 7 Packet Pg. 145 of 461
Certificate Of Completion
Envelope Id: 196CE771E0D94AE59657EBD606D28C35 Status: Completed
Subject: Complete with DocuSign: C20175537 Kennedy Jenks-Amendment #2 (REV3)
Source Envelope:
Document Pages: 4 Signatures: 2 Envelope Originator:
Certificate Pages: 2 Initials: 0 O'Brien, Nanette
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-08:00) Pacific Time (US & Canada)
250 Hamilton Ave
Palo Alto , CA 94301
Nanette.OBrien@CityofPaloAlto.org
IP Address: 199.33.32.254
Record Tracking
Status: Original
5/30/2023 12:44:19 PM
Holder: O'Brien, Nanette
Nanette.OBrien@CityofPaloAlto.org
Location: DocuSign
Security Appliance Status: Connected Pool: StateLocal
Storage Appliance Status: Connected Pool: City of Palo Alto Location: DocuSign
Signer Events Signature Timestamp
Mark Minkowski, Vice President
markminkowski@kennedyjenks.com
Vice President
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 50.226.164.82
Sent: 5/30/2023 12:45:37 PM
Viewed: 5/30/2023 1:28:24 PM
Signed: 5/30/2023 1:28:45 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Patrick Huston, Assistant Secretary
patrickhuston@kennedyjenks.com
Vice President
Security Level: Email, Account Authentication
(None)Signature Adoption: Pre-selected Style
Using IP Address: 72.111.117.192
Sent: 5/30/2023 1:28:47 PM
Viewed: 5/30/2023 4:37:15 PM
Signed: 5/30/2023 4:37:34 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Tom Kapushinski
Tom.Kapushinski@CityofPaloAlto.org
Project Engineer
City of Palo Alto
Security Level: Email, Account Authentication
(None)
Sent: 5/30/2023 4:37:35 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 8 Packet Pg. 146 of 461
Carbon Copy Events Status Timestamp
James Allen
james.allen@cityofpaloalto.org
Manager Water Quality Control Plant
City of Palo Alto
Security Level: Email, Account Authentication
(None)
Sent: 5/30/2023 4:37:36 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Karin North
karin.north@cityofpaloalto.org
Manager Watershed Protection
City of Palo Alto
Security Level: Email, Account Authentication
(None)
Sent: 5/30/2023 4:37:37 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Xiangquan Li
XiangquanLi@kennedyjenks.com
Security Level: Email, Account Authentication
(None)
Sent: 5/30/2023 4:37:38 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 5/30/2023 12:45:37 PM
Certified Delivered Security Checked 5/30/2023 4:37:15 PM
Signing Complete Security Checked 5/30/2023 4:37:34 PM
Completed Security Checked 5/30/2023 4:37:38 PM
Payment Events Status Timestamps
Item 5
Attachment A -
C20175537 Kennedy
Jenks Contract
Amendment No. 2
Item 5: Staff Report Pg. 9 Packet Pg. 147 of 461