HomeMy WebLinkAboutStaff Report 14602 (2) City of Palo Alto (ID # 14602) City Council Staff Report Meeting Date: 11/14/2022 Report Type: Consent Calendar City of Palo Alto Page 1 Title: Approval of a Construction Contract with Anderson Pacific Engineering Construction in the Amount of $6,070,000; Authorization for the City Manager or Their Designee to Negotiate and Execute Change Orders up to a Not-to-Exceed Amount of $607,000; Approval of Amendment #1 to Contract Number C21176592C with Carollo Engineers to Add Services, to Increase Compensation by $604,246 for a New Maximum Compensation Not-to- Exceed $604,247 for the Wastewater Treatment Fund for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project funded by the Plant Repair, Retrofit, and Equipment Replacement Project (WQ-19002) at the Regional Water Quality Control Plant From: City Manager Lead Department: Public Works Recommendation Staff recommends that Council: 1. Approve and authorize the City Manager or their designee to execute the contract with Anderson Pacific Engineering Construction, Inc., (APEC)1, in the amount of $6,070,000 for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project, funded in the Plant Repair, Retrofit, and Equipment Replacement Project (WQ-19002) at the Regional Water Quality Control Plant; 2. Authorize the City Manager or their designee to execute one or more change orders to the contract with APEC, for related, additional but unforeseen work that may develop during the project, the total value of which shall not exceed $607,000; and 3. Authorize the City Manager or their designee to execute Amendment No. 1 o Contract No. C21176592C with Carollo Engineers to increase the contract amount by $604,246 to provide construction management and inspection services during construction for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project funded in the Plant Repair, Retrofit, and Equipment Replacement project (WQ-19002). The revised 1 Contract C23185744 Anderson Pacific Engineering Construction, Inc., https://www.cityofpaloalto.org/files/assets/public/public-works/water-quality-control-plant/attachment-d- c23185744-anderson-pacific_cc_minutetraq.pdf City of Palo Alto Page 2 total contract amount is not to exceed $604,247 including $549,315 for basic services and $54,932 for additional services. Background The Regional Water Quality Control Plant (RWQCP) obtains electrical power from the City of Palo Alto Utilities (CPAU) Department. Onsite distribution of the medium voltage power is through a radial 12,470-volt (12kV) underground distribution system, which feeds ten power distribution load centers where the voltage is transformed from 12kV down to 480-volts. The 480-volt power is the key power supply for the RWQCP’s industrial treatment equipment. The 12kV distribution system has feeder distribution cables installed around 1980. The 12kV cables, the existing load centers, and 12kV electrical switches are at the end of their useful life and in need of replacement. In October 2012, the City adopted the Long Range Facilities Plan (LRFP), which provided a roadmap for future improvements at the RWQCP. This project is one of the projects recommended by the LRFP. Based on consultation with CPAU, replacement of the aging electrical infrastructure at the RWQCP is needed to maintain reliably safe operation. The design of the 12kV Electrical Power Distribution Loop Rehabilitation Project (Project) was completed in April 2022 under a separate contract (C19170648) with Salas O’Brien Engineers approved by Council in October 20182. The Project includes replacement of aging electrical cables, pad- mounted switches, and load centers; work includes construction of elevated equipment pads to adapt to the City’s Sea Level Rise policy. The Project design includes plant-wide electrical system harmonic assessments and arc-flash hazard risk assessments. Contract documents include a sequence of work that allows the construction work to be commenced in seven phases to allow for coordination with other RWQCP ongoing and upcoming capital program projects. This construction package is designated as Construction Bid Package 1, and it covers work under Phase 1 as indicated on the construction drawings. Currently, the Engineer’s Estimate for the remaining Phases 2 through 7 is $9.7 million; however, market conditions in the upcoming years will determine the actual cost of the remaining phases of the project. Phase Description Estimate Remarks 02 CPAU Secondary Service Cabinet and Switch 1910X $3,566,859 LC1 03 Medium Voltage Switch 1594X Replacement $1,213,442 Cap Bank 04 Medium Voltage Switch 1911X Replacement $1,549,061 LC2 05 Refeed Load Center LC9 $146,380 06 Medium Voltage Switch 1912X Replacement $1,908,116 LC 5 & 6 07 Medium Voltage Switch 1913X Replacement $1,276,063 LC7 2 City Council Staff Report ID# 9274 October 2018 https://www.cityofpaloalto.org/files/assets/public/agendas- minutes-reports/reports/city-manager-reports-cmrs/year-archive/2018/id-9274-design-services-for-wqcp- medium-voltage-electrical-distribution-network-rehabilitation.pdf City of Palo Alto Page 3 Phases 2 through 7 $9,659,921 Staff intends to execute one or more phases of the project every two years. The schedule and packaging of the phases will depend on priority of the phase, the availability of funds, and coordination with other on-going projects at the Plant. Discussion The 12kV Electrical Power Distribution Loop Rehabilitation Project includes seven phases of work that are being planned and sequenced in upcoming years to coordinate with other RWQCP ongoing capital projects. Under Bid Package 1 (IFB 185744), the Contractor will perform Phase 1 work including • the replacement of electrical Switchgear 1914X, replacement of Load Center Nos. 3 and 4, and replacement of associated conductors; • installation of temporary conductors and conduits during shutdown and switchover; • demolition of existing equipment (load centers, switchgears, and transformers); • site preparation work such as vegetation, pavement, and curb removal; • site civil grading; • installation of elevated equipment pads in conformance with City’s Sea Level Rise Policy; • installation of 45-feet deep foundation piers; and • other miscellaneous work as specified in the contract documents. Bid Process On July 12, 2022, the City solicited formal bids from qualified contractors for the 12kV Electrical Power Distribution Loop Bid Package 1 Project. The bidding period was 41 calendar days. Three bids were received on August 22, 2022, with bid prices ranging from $6,070,000 to $7,601,819 as listed in the attached Bid Summary (Attachment B). Table 1: Summary of Bid Process Bid Name/Number 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project (IFB No. 185744) Proposed Length of Project 26 months after Notice to Proceed # of Bid Packages downloaded by Contractors 45 # of Bid Packages downloaded by Builder’s Exchanges 1 Total Days to Respond to Bid 41 Pre-Bid Meeting Yes # of Company Attended Pre-Bid Meeting 16 # of Bids Received: 3 Base Bid Price Range $6,070,000 to $7,601,819 Staff has reviewed all bids submitted and recommends the bid of $6,070,000 submitted by APEC be accepted, and APEC be declared the lowest responsible bidder. The base bid is 76.5% City of Palo Alto Page 4 above the engineer's estimate of $3,440,000. This cost escalation is attributed to the higher equipment and material prices owing to the supply chain challenges in electrical equipment manufacturing and the tight labor market locally and nationwide. The medium voltage equipment specified by the design engineer meets the requirements of the Palo Alto Utilities Department electrical utility standards; this equipment is currently subject to long lead times and rising costs, which is a national issue. A contingency amount of $607,000 (10% of the bid price) is recommended for related, additional but unforeseen work that may develop during the project. Staff confirmed with the Contractor's State License Board that the contractor has an active license on file. The City received one bid protest during this procurement process from the Foundation for Fair Contracting, a non-profit organization. Staff reviewed the allegations as well as information from the California Division of Occupational Safety and Health and Labor Commissioner. Based upon independent review (Attachment C), staff recommends proceeding with the award. Selection of a Construction Management Firm On June 21, 2021, Council approved five separate contracts3 (Contract C21179265 - with MNS Engineers, Inc.; CDM Smith; Carollo Engineers; MCK Americas, Inc.; and Tanner Pacific, Inc. These contracts provide for RWQCP on-call construction management and inspection services. They were initially set at a not-to-exceed amount of $1 per contract to allow the City to select the firm that will provide qualified consultants for on-call services during construction of individual capital projects recommended by the LRFP. Services to be used are on a per-project basis, at the City’s discretion. On July 13, 2022, staff provided each of the five construction management consultants a scope of services with a list of tasks needed for the upcoming construction project (i.e., Work Order #2). Three proposals were received from Carollo Engineers, MNS Engineers, and MCK Americas with prices ranging from $602,247 to $1,916,410. Table 2: Summary of Construction Management Work Order Proposals Request for Work Order Proposal Issued July 13, 2022 Deadline for Questions, Clarifications August 3, 2022 Proposals Due August 10, 2022 Proposals Received 3 Finalist Identified 1 Proposals Price Range $604,247 to $1,916,410 An evaluation committee consisting of Public Works Department staff was formed to review the three proposals. The committee carefully reviewed each firm's qualifications and submittal 3 City Council Staff Report #1224 June 21, 2021 https://www.cityofpaloalto.org/files/assets/public/agendas- minutes-reports/reports/city-manager-reports-cmrs/year-archive/2021/id-12324.pdf City of Palo Alto Page 5 in response to the criteria identified in the Request for Work Order Proposal, including quality and completeness of the proposal, quality and effectiveness of services, experience with projects of similar scope and complexity, prior record of performance, cost, proposer’s financial stability, and ability to provide future maintenance and/or services. Staff recommends amending the contract with Carollo, who provided a comprehensive approach to the services, demonstrated a clear understanding of needs, and proposed innovative solutions to the challenges of the complex capital program. Timeline The construction work for phase 1 is anticipated to be complete by December 31, 2024. Resource Impact The Palo Alto RWQCP treats the combined wastewater from Palo Alto, Los Altos, Los Altos Hills, Mountain View, Stanford University, and the East Palo Alto Sanitary District. Palo Alto’s share of this project is 35% and the other five agencies’ share is 65%, based on the fixed capacity established in partners’ agreements. As the lead agency, the City of Palo Alto appropriated the funding for this Project in the Wastewater Treatment Enterprise Fund Capital Improvement Program as part of the FY 2023 Adopted Budget in the Plant Repair, Retrofit, and Equipment Replacement Project (WQ-19002) which has sufficient funding including the higher than estimated cost of this project. Policy Implications This recommendation does not represent any change to existing City policies and supports the Comprehensive Plan Policy N.4-16. Stakeholder Engagement This project is part of the RWQCP’s minor capital improvement program funded by Palo Alto and the five partner agencies who use the RWQCP for wastewater treatment. The five partner agencies are regularly updated on both the need for and the progress of wastewater treatment capital work. Updates are provided each year at an annual meeting and at other periodic meetings established to inform partner agency staff about the major capital improvement program. With respect to Palo Alto itself, open meetings and the budget process serve as the main vehicle for engaging the community on both new projects such as this and associated rate impacts. Environmental Review Authorizing the City Manager to select one consultant to provide construction management services for the Medium Voltage Electrical Distribution System (12kV loop) Rehabilitation does not constitute a project under the California Environmental Quality Act (CEQA); therefore, an Environmental Assessment is not required. The construction of this project has been determined to be exempt from CEQA under CEQA Guidelines Section 15301, subsections (b) and (e)(1), Existing Facilities, as it involves the repair City of Palo Alto Page 6 and maintenance of an existing publicly-owned utility used to provide sewerage treatment services with a minor addition to an existing building. Attachments: • Attachment A: Carollo Engineers Contract; C21179265C Amendment #1 • Attachment B: Bid Summary, Anderson Pacific • Attachment C: Determination Letter • Attachment D: Anderson Pacific Engineering Construction Contract; C23185744 Excerpt Page 1 of 19 Vers.: Aug. 5, 2019 AMENDMENT NO. 1 TO CONTRACT NO. C21179265C BETWEEN THE CITY OF PALO ALTO AND CAROLLO ENGINEERS, INC. This Amendment No. 1 (this “Amendment”) to Contract No. C21179265C (the “Contract” as defined below) is entered into as of November 14, 2022, by and between the CITY OF PALO ALTO, a California chartered municipal corporation (“CITY”), and CAROLLO ENGINEERS, INC., a California corporation, located at 2795 Mitchell Drive, Walnut Creek, CA 94598 (“CONSULTANT”). CITY and CONSULTANT are referred to collectively as the “Parties” in this Amendment. R E C I T A L S A. The Contract (as defined below) was entered into by and between the Parties to provide construction management and inspection services on an on-call, as-needed, time-limited basis in connection with individual projects or inspection tasks at the Regional Water Quality Control Plant (RWQCP), as detailed therein. B. The Parties now wish to amend the Contract in order to add Task 2 services (referred to as Work Order No. 2) for Construction Management and Inspection Services for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project, and to increase compensation by Six Hundred Four Thousand Two Hundred Forty-Six Dollars ($604,246.00), from One Dollar ($1.00) to Six Hundred Four Thousand Two Hundred Forty-Seven Dollars ($604,247.00), as detailed herein. NOW, THEREFORE, in consideration of the covenants, terms, conditions, and provisions of this Amendment, the Parties agree: SECTION 1. Definitions. The following definitions shall apply to this Amendment: a. Contract. The term “Contract” shall mean Contract No. C21179265C between CONSULTANT and CITY, dated June 14, 2021. b. Other Terms. Capitalized terms used and not defined in this Amendment shall have the meanings assigned to such terms in the Contract. SECTION 2. Section 4 “NOT TO EXCEED COMPENSATION” of the Contract is hereby amended to read as follows: The CITY is engaging multiple consultants, including CONSULTANT, that are eligible to respond with proposals to the CITY’s project-specific Task Orders under the process described in Exhibit A. The compensation to be paid to CONSULTANT for performance of the Services shall be based on the DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 2 of 19 Vers.: Aug. 5, 2019 compensation structure detailed in Exhibit C, entitled “COMPENSATION,” including any reimbursable expenses specified therein, and the maximum total compensation shall not exceed One Dollar ($1), unless CITY selects CONSULTANT, according to the process in Exhibit A, to perform services under a Task Order not to exceed One Million Four Hundred Fifty Thousand Dollars ($1,450,000) over the term of the Agreement. No pre-qualified consultant, including the CONSULTANT under this Agreement, is guaranteed selection or assured of any minimum quantity of work to be performed. In the event CONSULTANT is not selected to provide Services under a Task Order, no payment is due from CITY. The hourly schedule of rates, if applicable, is set out in Exhibit C-1, entitled “SCHEDULE OF RATES.” Any work performed, or expenses incurred for which payment would result in a total exceeding the maximum compensation set forth in this Section 4 shall be at no cost to the CITY. A. The City has selected CONSULTANT to perform Work Order #2, for construction management and inspection services for the Medium Voltage Electrical Network (12kV Elec. Loop) Rehabilitation Bid Package 1 Project, in the amount not to exceed Five Hundred Forty-Nine Thousand Three Hundred Fifteen Dollars ($549,315.00). CONSULTANT agrees to complete all Basic Services, including reimbursable expenses, within this amount. In the event Additional Services (as defined below) are authorized, the total compensation for Basic Services, Additional Services and reimbursable expenses shall not exceed Six Hundred Four Thousand Two Hundred Forty-Seven Dollars ($604,247.00). Optional Additional Services Provision (This provision applies only if checked and a not-to- exceed compensation amount for Additional Services is allocated below under this Section 4.) In addition to the not-to-exceed compensation specified above, CITY has set aside the not-to- exceed compensation amount of Fifty-Four Thousand Nine Hundred Thirty-Two Dollars ($54,932.00) for the performance of Additional Services (as defined below). The total compensation for performance of the Services, Additional Services and any reimbursable expenses specified in Exhibit C, shall not exceed Six Hundred Four Thousand Two Hundred Forty Seven Dollars ($604,247.00) as detailed in Exhibit C. “Additional Services” means any work that is determined by CITY to be necessary for the proper completion of the Project, but which is not included within the Scope of Services described in a Task Order issued under Exhibit A. CITY may elect to, but is not required to, authorize Additional Services up to the maximum amount of compensation set forth for Additional Services in this Section 4. CONSULTANT shall provide Additional Services only by advanced, written authorization from CITY as detailed in this Section. Additional Services, if any, shall be authorized by CITY with a Task Order assigned and authorized by CITY’s Project Manager, as identified in Section 13 (Project Management). Each Task Order shall be in substantially the same form as Exhibit A-1, entitled “PROFESSIONAL SERVICES TASK ORDER”. Each Task Order shall contain a specific scope of services, schedule of performance and DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 3 of 19 Vers.: Aug. 5, 2019 maximum compensation amount, in accordance with the provisions of this Agreement. Compensation for Additional Services shall be specified by CITY in the Task Order, based on whichever is lowest: the compensation structure set forth in Exhibit C, the hourly rates set forth in Exhibit C-1, or a negotiated lump sum. To accept a Task Order, CONSULTANT shall sign the Task Order and return it to CITY’s Project Manager within the time specified by the Project Manager, and upon authorization by CITY (defined as counter-signature by the CITY Project Manager), the fully executed Task Order shall become part of this Agreement. The cumulative total compensation to CONSULTANT for all Task Orders authorized under this Agreement shall not exceed the amount of compensation set forth for Additional Services in this Section 4. CONSULTANT shall only be compensated for Additional Services performed under an authorized Task Order and only up to the maximum amount of compensation set forth for Additional Services in this Section 4. Performance of and payment for any Additional Services are subject to all requirements and restrictions in this Agreement. SECTION 3. The following exhibit(s) to the Contract are hereby amended, as indicated below, to read as set forth in the attachment(s) to this Amendment, which are hereby incorporated in full into this Amendment and into the Contract by this reference: a. Exhibit “A-2” entitled ““PROFESSIONAL SERVICES TASK ORDER NO. 2, AMENDMENT NO. 1” (ADDED). b. Exhibit “B” entitled “SCHEDULE OF PERFORMANCE, AMENDMENT NO. 1” (AMENDED, REPLACES PREVIOUS) c. Exhibit “C” entitled “COMPENSATION, AMENDMENT NO. 1,” (AMENDED, REPLACES PREVIOUS). SECTION 4. Legal Effect. Except as modified by this Amendment, all other provisions of the Contract, including any exhibits thereto, shall remain in full force and effect. SECTION 5. Incorporation of Recitals. The recitals set forth above are terms of this Amendment and are fully incorporated herein by this reference. (SIGNATURE BLOCK FOLLOWS ON THE NEXT PAGE.) DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 4 of 19 Vers.: Aug. 5, 2019 SIGNATURES OF THE PARTIES IN WITNESS WHEREOF, the Parties have by their duly authorized representatives executed this Amendment effective as of the date first above written. CITY OF PALO ALTO ______________________________ City Manager or Designee APPROVED AS TO FORM: ______________________________ City Attorney or Designee CAROLLO ENGINEERS, INC. Officer 1 By:_____________________________ Name:__________________________ Title:____________________________ Officer 2 By:_____________________________ Name:__________________________ Title:____________________________ Attachments: Exhibit “A-2”: PROFESSIONAL SERVICES TASK ORDER NO. 2 Exhibit “B”: SCHEDULE OF PERFORMANCE Exhibit “C”: COMPENSATION DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Rick Chan, Senior Vice President Senior Vice President Vice President Anne E. Prudhel, Vice President Page 5 of 19 Vers.: Aug. 5, 2019 EXHIBIT “A-2” PROFESSIONAL SERVICES TASK ORDER NO. 2 CONSULTANT shall perform the Services detailed below in accordance with all the terms and conditions of the Agreement referenced in Item 1A below. All exhibits referenced in Item 8 are incorporated into this Task Order by this reference. CONSULTANT shall furnish the necessary facilities, professional, technical and supporting personnel required by this Task Order as described below. CONTRACT NO. C21179265C 1A. MASTER AGREEMENT NO.: C21179265C 1B. TASK ORDER NO 2: Work Order No. 2 for Construction and Inspection Management Services for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project 2. CONSULTANT NAME: CAROLLO ENGINEERS, INC. 3. PERIOD OF PERFORMANCE: START: Immediately Once Notice To Proceed (NTP) is Issued; COMPLETION: 120 Weeks from NTP 4 TOTAL TASK ORDER NO. 1 PRICE: $549,315 BALANCE REMAINING IN MASTER AGREEMENT/CONTRACT: $900,685 5. WBS/CIP: WQ-19002 6. CITY PROJECT MANAGER: Padmakar Chaobal, Public Works Department, Environmental Services Division, RWQCP 7. DESCRIPTION OF SCOPE OF SERVICES MUST INCLUDE:  Services And Deliverables To Be Provided  Schedule Of Performance  Maximum Compensation Amount And Rate Schedule (As Applicable)  Reimbursable Expenses, If Any (With “Not To Exceed” Amount) 8. ATTACHMENTS: Task Order No. 2 Scope Of Services, including Schedule of Performance and Compensation Schedule TASK ORDER #2 SCOPE OF SERVICES WORK ORDER NO. 2: CONSTRUCTION AND INSPECTION MANAGEMENT SERVICES FOR THE 12KV ELECTRICAL POWER DISTRIBUTION LOOP REHABILITATION BID PACKAGE 1 PROJECT Task 1: General Requirements 1. For any work which requires licensing, the Proposers shall be appropriately licensed in accordance with the laws of the State of California. The cost for any required licenses or permits shall be the responsibility of the successful Proposers. 2. CONSULTANT shall provide all necessary administration, project controls, quality assurance and professional oversight of the project to provide that the project remains on schedule, within budget, provides for continuity of information, and DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 6 of 19 Vers.: Aug. 5, 2019 satisfies the requirements of the CONTRACT. CONSULTANT shall prepare and distribute a Project Management Plan to include schedule, budget, roles, contracts and procedures. 3. At the beginning of each month, CONSULTANT shall submit to the CITY monthly invoices for the cost incurred during previous month; including subconsultant and expenses. 4. CONSULTANT shall prepare and submit monthly invoice packages to the City. The City prefers processing CONSULTANT pay requests that cover one calendar month. Monthly invoice packages are to include a progress report documenting progress. The report shall include the progress by each task, the budget status (authorized amount, current billing, billed to date, previously billed, amount remaining, and percent spent), outstanding issues, potential changes, project schedule and schedule impacts. CONSULTANT shall identify and mitigate potential budget overruns; and notify CITY Project Manager as soon as the potential overrun is identified. If SRF funding is used, progress reports shall include a summary of SRF eligible costs per month. Task 2: Preconstruction Phase 1. CONSULTANT shall perform reviews of construction drawings and specifications at varies levels of design, as assigned by the CITY with focus on constructability of the project. At a minimum, the CONSULTANT shall provide and log comments regarding the plans, specifications, and construction cost estimate in an Excel Workbook, provided by CITY. Comments should at a minimum include feedback on measurement and payment, sequencing, schedule, temporary facilities, constructability, and required contractor qualifications. The City may assign milestone reviews of other projects in the preconstruction phase. Reviews shall determine the coordination required between the subject project and other projects for concurrent work and the constructability of other projects following the completion of the subject project. 2. CONSULTANT shall assist the City with evaluation of construction bids to determine the lowest responsive and responsible bidder. 3. For each milestone meeting, CONSULTANT will prepare the agenda for the meeting, facilitate the meeting, address administrative and non-design issues, and prepare record of discussions of the meeting for distribution. CITY, ENGINEER and CONTRACTOR’s team will attend the meeting. The ENGINEER will address design issues. At a minimum, there will be the following milestone meetings: a. Project kick-off Meeting b. Pre-bid Meeting 4. Administration a. CONSULTANT to propose a project administration procedure, including an online document tracking system, for CITY approval. The administration procedure will detail how the CONSULTANT will track, store, distribute, and manage digital and hardcopy correspondence and project documentation and strategy for managing project communications. DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 7 of 19 Vers.: Aug. 5, 2019 b. CONSULTANT shall establish and maintain a health and safety plan specific for CONSULTANT’s staff and subconsultants. During construction activities, CONSULTANT shall follow CONTRACTOR(S)’s health and safety plan(s), if it is more stringent. 5. Office Setup a. CONSULTANT shall organize the hardcopy and digital files for the project prior to commencement of construction and coordinate with the CITY and CONTRACTOR for office trailer set-up. b. CITY will designate location for the office trailer and provide utility connection points. c. CONSULTANT will provide furnished office trailer, copier, phone/service, and internet access, unless otherwise provided by City. 6. Preconstruction Activities a. Site Walk Observations and Documentation i. CONSULTANT will conduct preconstruction inspections, documenting conditions in a log and providing digital photographs and video(s). b. Preconstruction Submittals i. CONSULTANT to develop a list of CONTRACTOR pre-construction submittals. ii. CONSULTANT to review CONTRACTOR’s pre-construction submittals, schedule of values, and preliminary schedule. Task 3: State Revolving Fund (SRF) Compliance – NOT APPLICABLE Task 4: Construction Phase 1. Construction Administration a. Project Coordination i. CONSULTANT shall act as the project coordinator and the point of contact for all communications with the CONTRACTOR. The CONSULTANT shall coordinate construction activities of the CITY, ENGINEER, and CONTRACTOR. CONSULTANT responsibilities include: Conduct team meetings within the consulting firm to review progress, coordinate evaluations and identify information needs; Disseminate information to the design team; Manage the project budget; Manage the project schedule; Manage sub-consultants; Manage QA / QC team; Coordinate communications with other ongoing project’s construction managers to facilitate the construction of ongoing projects and continuous Plant operations. ii. CONSULTANT shall provide a contact phone number to respond to issues related to construction activity or coordination, 24 hours a day, 7 days a week. b. Document Tracking System: CONSULTANT shall establish, implement and DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 8 of 19 Vers.: Aug. 5, 2019 maintain an online system for tracking all correspondence and documents on the Project or shall adopt a project administration procedure previously approved by CITY. CONSULTANT shall incorporate within the tracking system the means to track the routing of submittals/RFIs to the CITY’s other consultants. c. Construction Administration Services: CONSULTANT shall provide administrative and management services. The CONSULTANT shall receive all correspondence from the CONTRACTOR and address all inquiries from the CONTRACTOR and construction related correspondence. The ENGINEER will be responsible for providing design input. 2. Meetings a. CONSULTANT shall prepare agenda for progress meetings and other construction meetings required during the Project, which will include weekly meetings with the CONTRACTOR and CITY. b. CONSULTANT shall facilitate and prepare records of discussions for the progress meetings and other construction related meetings. c. CONSULTANT shall have all pending decisions detailed for the meetings as well as project statistics (schedule updates, approximate percent project complete, near-term milestones). d. Anticipated Meetings i. Construction kick-off meeting ii. Weekly update meeting iii. Minimum two (2) Electrical Service (Power Feed) Coordination Meeting with Palo Alto Electric Utilities iv. Participate in an I&C Standards Review Meeting with RWQCP Technology / SCADA Support Staff v. Project close-out Meeting vi. Attend other concurrent projects’ kickoff meetings vii. Periodic coordination meetings with other ongoing projects’ construction managers and the City 3. Submittals a. CONSULTANT shall use the online document tracking system to log and coordinate the submittal process. b. CONSULTANT shall receive the submittals, including CONTRACTOR’s red-line drawings, from the CONTRACTOR and check the submittals for general conformity with the Construction Contract requirements. If obvious deficiencies are apparent in the submittal, the CONSULTANT shall reject and send the submittal back to the CONTRACTOR for correction. c. CONSULTANT shall route the submittals to the ENGINEER for review and shall route the reviewed submittal back to the CONTRACTOR. The CONSULTANT shall review comments on the submittals to determine if additional follow-up with the CONTRACTOR and/or ENGINEER is warranted and to identify any DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 9 of 19 Vers.: Aug. 5, 2019 scope changes. d. CONSULTANT shall coordinate the ENGINEER’s submittal review and the track the status of shop drawing resubmittals with the CONTRACTOR. e. In addition to the CONSULTANT, ENGINEER to review all design related submittals and all submittals for temporary facilities. f. CONSULTANT shall review temporary facilities submittals for conflicts with other ongoing projects’ active and/or proposed construction. The City may request CONSULTANT review other ongoing projects’ temporary facilities submittals for constructability issues. g. CONSULTANT shall review temporary facilities submittals for operability. 4. Request for Information/Clarification Process a. CONSULTANT shall utilize the online document tracking system for processing requests for design clarifications. b. CONSULTANT shall receive all requests for information (RFIs) from the CONTRACTOR and determine if the request is a valid RFI; i. If valid, ENGINEER will review the RFIs and provide design response. CONSULTANT shall review the ENGINEER’s response, verify acceptability of response and transmit the Clarification Response to the CONTRACTOR. ii. If not, CONSULTANT shall return the RFI to the CONTRACTOR with justifications. c. CONSULTANT shall provide a response within 10 days to the CONTRACTOR for any administrative, field condition specific and general RFI. d. ENGINEER shall prepare Design Clarifications where design issues are identified by the CONSULTANT, ENGINEER, or CITY. CONSULTANT shall prepare the Clarification Letter for transmittal to the CONTRACTOR of the ENGINEER’s Design Clarification and other clarifications. e. CONSULTANT shall work with the CITY Project Manager to maintain an Error and Omission Log to document RFIs and RFCs that are a result of ENGINEER and CONTRACTOR errors in design and construction, respectively. The log shall record the hours spent by the ENGINEER to respond to the RFIs/ RFCs and associated cost impact to the construction. CITY may seek reimbursement from the ENGINEER and/or CONTRACTOR. 5. Change Order Preparation, Negotiation & Processing a. CONSULTANT shall review all change order requests (either initiated by the CITY or by the CONTRACTOR). i. CONSULTANT shall utilize the online document tracking system to log, track, and process changes. ii. CONSULTANT shall maintain Change Event files. These files shall compile all data related to specific items that arise that may have cost or time impacts or neither. b. CONSULTANT shall judge the validity and/or merits of all CONTRACTOR DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 10 of 19 Vers.: Aug. 5, 2019 initiated change order requests. CONTRACTOR initiated change orders deemed unnecessary, or not substantiated by a deficiency in the construction documents shall be returned to CONTRACTOR unapproved with an explanation. c. CONSULTANT shall negotiate change orders with the CONTRACTOR, considering impact to the schedule, as well as, reasonableness of cost, and impact to total project budget. CONSULTANT shall provide updates regarding potential cost and schedule changes to CITY. d. CONSULTANT shall prepare an independent cost estimate and/or verify the acceptability of the CONTRACTOR’s cost proposal for each approved change request. At CITY’s discretion, ENGINEER’s opinion may be requested for specific equipment and material costs. e. CONSULTANT shall prepare change orders using CITY’s procedure for execution by the CITY and CONTRACTOR. i. CONSULTANT shall prepare a Change Order Memorandum, if requested by the CITY, to provide additional background discussion for need of the change and reasonableness of cost and schedule impact. ii. ENGINEER shall prepare design details for change requests as needed. CONSULTANT to coordinate schedule and distribution of design details. iii. CONSULTANT shall prepare, and issue approved change order requests to the CONTRACTOR with the appropriate design documents as directed by the CITY. f. In the event the CONTRACTOR encounters a time sensitive problem where time is not available to negotiate a settlement, CONSULTANT shall issue a field order. i. All work done under a field order will be completed on a time and material basis. CONSULTANT to track actual time and material expended for the field order work. ii. Field orders shall be reviewed and approved with the CITY prior to issuance. 6. Documentation of Environmental Compliance a. CONSULTANT shall document compliance with environmental permitting and mitigation measures in accordance with the requirements of the environmental documents and regulatory permits. 7. Progress Payment a. CONSULTANT shall review the initial schedule of values (cost breakdown) prepared by the CONTRACTOR and generate a progress payment request form for the CONTRACTOR’s use. b. CONSULTANT shall review and process the progress payment requests and determine whether the amount requested reflects the actual status of the Contractor’s work in place, materials on site and other contract DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 11 of 19 Vers.: Aug. 5, 2019 requirements. c. CONSULTANT shall perform the appropriate administration, preparation and processing of the monthly progress payments so the CITY can respond in accordance with the time periods set forth in the Public Contract Code. d. CONSULTANT shall prepare the summary cover sheet for the progress payments which will be executed by CONSULTANT, CONTRACTOR and CITY. e. CONSULTANT shall not recommend final payment to the CONTRACTOR until the CONSULTANT has determined CONTRACTOR has complied with the project closeout requirements, including submittals of record documents, warranties, and operations and maintenance manuals. CITY will release the retention only after a Notice of Completion has been recorded with the Santa Clara County Clerk’s Recorder Office. f. CONSULTANT shall work with Contractor to develop an estimate of CONSULTANT as well as contractor’s anticipated monthly pay request (billing/invoicing) schedule for the entire duration of the construction phase. 8. CONTRACTOR’s Certified Payroll a. On a bi-weekly basis, or when otherwise requested by the CITY, State, or other agency or public inquiry, the CONSULTANT shall collect certified payrolls from the CONTRACTOR. Apart from the regular, bi-weekly collection, the CONSULTANT shall obtain payroll records within 10 days of the CITY’s request. b. CONTRACTOR is responsible for submitting electronically their certified payroll records to the State Department of Industrial Relations. c. CONSULTANT shall be responsible for documenting and conducting interviews of the CONTRACTOR’s field staff/crew for compliance with CITY prevailing wage ordinance. 9. Schedule a. CONSULTANT shall review CONTRACTOR’s initial Baseline schedule submittal to determine whether it is realistic and prepared in accordance with the Contract Documents, that the milestone and Substantial Completion dates meet the overall goal for schedule and that no major conflicts exist. The CONSULTANT shall advise CITY of the review determination and provide written comments to the CONTRACTOR. b. CONSULTANT shall review the CONTRACTOR’s schedule updates and provide written comments to the submitted update. c. CONSULTANT shall review and evaluate the CONTRACTOR’s requests for Contract Time extension and make written recommendations to the CITY regarding entitlement and the number of days, if any, to be added to the Contract Time(s). If requested by the CITY, CONSULTANT shall provide a written assessment of the time request. CONSULTANT shall negotiate schedule adjustments with the CONTRACTOR. 10. Field Quality Control (Inspectional Services) DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 12 of 19 Vers.: Aug. 5, 2019 a. CONSULTANT shall provide field observation services to monitor compliance with the Contract Documents. i. CONSULTANT staff shall have sufficient training and experience regarding the specific construction activities being performed by CONTRACTOR. 1) CONSULTANT shall provide staff proportional as what is required to observe CONTRACTOR’s activities. 2) CONSULTANT shall submit inspection schedule showing inspection frequency, duration and level of efforts. 3) CONSULTANT shall provide subconsultant(s) as needed to observe specialty work or increase staffing levels (see Special Inspections). 4) CITY may set an allowance on a task order specific basis for the increased cost only of inspectional services if required during off hours and on weekends. Consultant to provide sufficient hours to cover all inspectional services anticipated at standard rates. b. Reporting i. CONSULTANT shall prepare daily inspection reports documenting observed field activities, field crews, CONTRACTOR equipment, and field problems. CONSULTANT shall collect and compile CONTRACTOR daily reports. ii. CONSULTANT shall provide and maintain photographs of field activities for status monitoring of the project. iii. CONSULTANT shall monitor record documents (redline drawings) on a bi- weekly basis to determine if they are being maintained by the CONTRACTOR and are in substantial conformance with the CONSULTANT’s information/observations. iv. CONSULATNT shall prepare a monthly report to include major work performed, outstanding issues, project photographs, schedule status, pending and executed change orders summary, and quality issues. This report shall also be part of CONSULTANT’s monthly progress payment report. c. Special Inspections i. CONSULTANT shall furnish the materials testing and special inspections required to be performed for the Project. Special Inspection and materials testing includes, but not limited to: 1) Soils testing for HazMat compliance 2) Soils compaction and relevant testing Asphalt compaction and relevant testing 3) Concrete sampling and testing 4) Structural steel welding DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 13 of 19 Vers.: Aug. 5, 2019 5) Coating inspection 6) Medium voltage electrical installation inspection & testing 7) Low voltage electrical installation inspection & testing 8) Special inspections as listed in the project specific design drawings and specs. 9) Factory inspection and witness test of Load Centers / Unit Substations prior to shipment. ii. CONSULTANT shall schedule and coordinate the material testing services and have responsibility for the specialty inspections and testing services. d. Medium Voltage Inspections i. CONSULTANT shall notify City staff (for CPAU) at least one week in advance of CONTRACTOR scheduled medium voltage construction, including placement and orientation of medium voltage equipment, conduit trenching, utility clearances, and splices. ii. Any field activities, including inspection, performed by CPAU is independent of the CONSULTANT’s inspection work and shall be performed separately and in parallel. 11. System Outages a. CONSULTANT shall review and evaluate the CONTRACTOR’s system outage requests (SOR) in conjunction with the CITY. CONSULTANT shall assess the reasonableness of the duration of the requested shutdown. b. The SORs shall be reviewed and approved at least three weeks ahead of the actual outage/shutdown. c. CONSULTANT shall facilitate/coordinate shutdowns with the CONTRACTOR, CITY and ENGINEER. i. CITY is responsible for reviewing and approving system outage request and duration, confirming the outage is properly planned, implementing the outage, and bringing services back online after the outage. 12. Means and Methods of Construction a. CONSULTANT shall not direct the means and methods of construction. CONTRACTOR shall be solely responsible for the means and methods of construction. Concerns or suggestions regarding the CONTRACTOR’s means and methods shall be communicated to CITY and ENGINEER. 13. Safety a. CONSULTANT shall comply with appropriate regulatory, project and CITY codes in addition to CONSULTANT’s Health and Safety Plan regarding necessary safety equipment and procedures used during performance of the CONSULTANT’s work and shall take necessary precautions for safe operation of the CONSULTANT’s work, and the protection of the CONSULTANT’s personnel from injury and damage from such work. DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 14 of 19 Vers.: Aug. 5, 2019 b. Neither the professional activities of the CONSULTANT, nor the presence of the CONSULTANT’s employees or sub-consultants at the construction/project site, shall relieve the CONTRACTOR and any other entity of their obligations, duties and responsibilities including, but not limited to, construction means, methods, sequence, techniques or procedures necessary for performing, superintending, or coordinating their work in accordance with the Contract Documents, City codes, and any health or safety precautions required by pertinent regulatory agencies. CONSULTANT and its personnel have no authority to exercise any control over any CONTRACTOR or other entity or their employees in connection with their work or any health or safety precautions. 14. Spare Parts a. CONSULTANT shall prepare a list of required spare parts from the specifications and vendor O&M Manuals or recommended spare parts lists. b. CONSULTANT shall inventory spare parts as they are delivered by the CONTRACTOR and transfer spare parts to the CITY. The transfer of part shall be documented via material transmittal, signed by Contractor, CONSULTANT and CITY. 15. Operation and Maintenance (O&M) Manuals a. CONSULTANT shall prepare a list of anticipated O&M Manuals and track the submittal and review process in the online document tracking system. b. CONSULTANT shall verify that the submitted O&M manuals are the correct and latest version, and that the ‘lessons learned’ and notes taken during startup and commissioning are included in the O&M manuals. CONSULTANT shall coordinate delivery of final hardcopies from CONTRACT to CITY. 16. Testing and Training a. CONSULTANT shall coordinate training requirements and activities. b. ENGINEER shall provide design assistance during testing operations. c. CONSULTANT shall work with CONTRACTOR, ENGINEER and CITY on the development of the Testing and Startup Plan. d. CONSULTANT shall provide oversight and administration of training and testing. e. CONSULTANT shall coordinate the training with the CONTRACTOR, vendor and CITY staff. Some equipment may need training for third party personnel with whom the CITY may be contracting with. CITY will provide the vendor contact information for CONSULTANT to coordinate with. Trainings shall be coordinated so that key CITY staff can attend; schedule shall accommodate key CITY staff/ Plant operations shifts. Multiple training sessions for day shift and night shift operators may be required. f. CONSULTANT shall observe start-up and testing as the CITY’s representative and maintain copies of start-up documentation in an organized binder that shall be turned over at the end of the project. DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 15 of 19 Vers.: Aug. 5, 2019 g. CONSULTANT shall attend training sessions and collect attendance sheets and copies of training material. h. If required by CITY, CONSULTANT shall coordinate production quality audio and video recording and editing of training sessions to be used for future training sessions. The final digital copy shall be labeled and have an introduction that indicates the type of training, the process area, the equipment name, the vendor(s) / manufacturer(s) if applicable, the date, and the CONTRACTOR. i. Refer CITY’s Demonstration and Training Standards for more details. j. Corrective Work Item List: The CONSULTANT shall prepare and maintain a Corrective Work Item list (CWL) with the input from the CITY and ENGINEER. k. CONSULTANT shall confirm that the items identified in the CWL are completed in preparation for issuance of Substantial Completion Certificate (SCC). l. CONSULTANT shall prepare the SCC for execution by the CITY and the CONTRACTOR when the Corrective Work Items are completed to the CITY’s, ENGINEER’s and The CONSULTANT’s satisfaction. 17. Corrective Work Item List a. The CONSULTANT shall prepare and maintain a Corrective Work Item list (CWL) with the input from the CITY and ENGINEER. b. CONSULTANT shall confirm that the items identified in the CWL are completed in preparation for issuance of Substantial Completion Certificate (SCC). c. CONSULTANT shall prepare the SCC for execution by the CITY and the CONTRACTOR when the Corrective Work Items are completed to the CITY’s, ENGINEER’s and The CONSULTANT’s satisfaction. E. Task 5: Project Closeout Phase 1. Punch List and Final Inspection a. Punch List i. CONSULTANT shall in conjunction with the CITY prepare the list of outstanding deficiencies. ii. CONSULTANT shall prepare and issue the Punch List(s) from the list of deficiencies. iii. CONSULTANT shall have primary responsibility for verifying that the Punch List work is complete. b. Final Inspection i. CONSULTANT shall have primary responsibility for conducting the final inspection. 1) CITY will participate and provide input on the final inspection. 2) ENGINEER will provide design input on final inspection items if determined necessary by the CITY. 3) CONSULTANT shall be responsible for oversight and review of the final inspection. 2. Warranty Coordination a. CONSULTANT shall maintain a warranty file in the online document tracking DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 16 of 19 Vers.: Aug. 5, 2019 system. All warranty documentation shall be handed off to the CITY at conclusion of the contract. 3. Project Closeout a. CONTRACTOR shall furnish record documents, which the CONSULTANT shall review and transmit to ENGINEER for conforming and final issuance to CITY. b. CONSULTANT shall prepare necessary CITY documentation recommending acceptance of the completed work by the CITY. c. CONSULTANT shall turnover project documentation to the CITY in an orderly manner and in a timely manner after completion of the project and all Punch- list activities. The CONSULTANT shall retain all change event files at the end of the project. The CITY shall have the right to request review and/or copies of the change events files. Work Order No. 2: Milestone Schedule Of Performance TASK # MILESTONES NUMBER OF WEEKS TO COMPLETION FROM WORK ORDER #1 NOTICE TO PROCEED (NTP) Task 1 General Requirements 125 Weeks Task 2 Pre-Construction 13 Weeks Task 3 SRF Compliance N/A Task 4 Construction Phase 113Weeks Task 5 Project Closeout 125 Weeks Work Order No. 2: Milestone Compensation Schedule TASK # MILESTONES NOT TO EXCEED AMOUNT Task 1 General Requirements $17,685 Task 2 Pre-Construction $8,240 Task 3 SRF Compliance $0 Task 4 Construction Phase $459,050 Task 5 Project Closeout $14,340 Inspection Allowance $50,000 Sub-total Basic Services $549,315 Reimbursable Expenses $0 Total Basic Services and Reimbursable Expenses $549,315 Additional Services (per Section 4) (Not to Exceed) $54,932 Maximum Total Compensation $604,247 DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 17 of 19 Vers.: Aug. 5, 2019 DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Page 18 of 19 Vers.: Aug. 5, 2019 EXHIBIT “B” SCHEDULE OF PERFORMANCE Optional Schedule of Performance Provision for On-Call or Additional Services Agreements. (This provision only applies if checked and only applies to on-call agreements per Section 1 or agreements with Additional Services per Section 4.) The schedule of performance shall be as provided in the approved Task Order, as detailed in Section 1 (Scope of Services) in the case of on-call Services, or as detailed in Section 4 in the case of Additional Services, provided in all cases that the schedule of performance shall fall within the term as provided in Section 2 (Term) of this Agreement. WORK ORDER #2 Tasks 1-5 completed within 125 Weeks from the Notice to Proceed for Work Order 2, as detailed in the Milestone Schedule of Performance attached to Work Order #2. DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF Vers.: Aug. 5, 2019 Page 19 of 19 EXHIBIT “C” COMPENSATION CITY agrees to compensate CONSULTANT for on-call, as-needed, time-limited project support services performed in accordance with the terms and conditions of this Agreement, and as set forth in a specific Task Order budget schedule. Compensation shall be calculated based on the rate schedule attached as Exhibit C-1 up to the not to exceed budget amount for each task set forth in a specific Task Order. CITY’s Project Manager may approve in writing the transfer of budget amounts between any of the tasks or categories within a specific Task Order, provided that the total compensation for the Services, including any specified reimbursable expenses, and the total compensation for Additional Services (if any, per Section 4 of the Agreement) do not exceed the amounts set forth in Section 4 of this Agreement. CONSULTANT agrees to complete all Services, any specified reimbursable expenses, and Additional Services (if any, per Section 4), within this/these amount(s). Any work performed or expenses incurred for which payment would result in a total exceeding the maximum amount of compensation set forth in this Agreement shall be at no cost to the CITY. REIMBURSABLE EXPENSES CONSULTANT’S ordinary business expenses, such as administrative, overhead, administrative support time/overtime, information systems, software and hardware, photocopying, telecommunications (telephone, internet), in-house printing, insurance and other ordinary business expenses, are included within the scope of payment for Services and are not reimbursable expenses hereunder. Reimbursable expenses, if any are specified as reimbursable under this section, will be reimbursed at actual cost. The expenses (by type, e.g. travel) for which CONSULTANT will be reimbursed are: NONE up to the not-to-exceed amount of $0.00. WORK ORDER #2 Compensation as detailed in the Milestone Compensation Schedule attached to Work Order #2., Not to Exceed: Total Basic Services and Reimbursable Expenses $549,315 Additional Services (per Section 4) (Not to Exceed) $54,932 Maximum Total Compensation $604,247 DocuSign Envelope ID: 6091A862-A230-4545-B1EA-EA63CA8CD1EF BIDDER Price REMARKS % Over Anderson Pacific Engineering Construction 6,070,000$ Low Bidder 76.45% Pacific Industrial Electric 7,309,475$ 112.48% Stronghold Engineering Inc.7,601,819$ 120.98% Engineer's estimate 3,440,000$ 0.00% Attachment B - Bid Summary 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Invitation for Bids (IFB) Number: 185744 Attachment C Rev. September 29, 2021 1 PART 4 – CONSTRUCTION CONTRACT CONSTRUCTION CONTRACT Contract No. C23185744 City of Palo Alto 12kV Electrical Power Distribution Loop Rehabilitation Bid Package 1 Project Attachment D Rev. September 29, 2021 2 PART 4 – CONSTRUCTION CONTRACT CONSTRUCTION CONTRACT TABLE OF CONTENTS SECTION 1 INCORPORATION OF RECITALS AND DEFINITIONS…………………………………….………….6 1.1 Recitals……………………………………………………………………………………………………………………...6 1.2 Definitions………………………………………………………………………………………………………………….6 SECTION 2 THE PROJECT………………………………………………………………………………………………………..6 SECTION 3 THE CONTRACT DOCUMENTS.……………………………………………………………………………...7 3.1 List of Documents.…………………………………………………………………………………………..............7 3.2 Order of Precedence…………………………………………………………………………………………….......7 SECTION 4 CONTRACTOR’S DUTY…………………………………………………………………………………………..7 4.1 Contractor's Duties……………………………………………………………………………………………………..7 SECTION 5 PROJECT TEAM……………………………………………………………………………………………………..8 5.1 Contractor's Co-operation…………………………………………………………………………………………..8 SECTION 6 TIME OF COMPLETION………………………………………………………………………………………….8 6.1 Time Is of Essence……………………………………………………………………………………………………….8 6.2 Commencement of Work……………………………………………………………………………………………8 6.3 Contract Time…………………………………………………………………………………………………………….8 6.4 Liquidated Damages…………………………………………………………………………………………………..8 6.4.1 Other Remedies……………………………………………………………………………………………………….8 6.5 Adjustments to Contract Time……………………………………………………………………………………9 SECTION 7 COMPENSATION TO CONTRACTOR………………………………………………………………………9 7.1 Contract Sum………………………………………………………………………………………………………………9 7.2 Full Compensation………………………………………………………………………………………………………9 SECTION 8 STANDARD OF CARE……………………………………………………………………………………………..9 8.1 Standard of Care…………………………………………………………………………………..……………………9 SECTION 9 INDEMNIFICATION…………………………………………………………………………………………..……9 9.1 Hold Harmless……………………………………………………………………………………………………………9 9.2 Survival………………………………………………………………………………………………………………………10 SECTION 10 NON-DISCRIMINATION……..………………………………………………………………………………..10 10.1 Municipal Code Requirement…………….………………………………..……………………………………..10 SECTION 11 INSURANCE AND BONDS.……………………………………………………………………………………10 11.1 Evidence of Coverage…………………………………………………………………………………………………10 Rev. September 29, 2021 3 PART 4 – CONSTRUCTION CONTRACT SECTION 12 PROHIBITION AGAINST TRANSFERS………………………………………………………………….….10 12.1 Assignment…………………………………………………………………………………………………………………10 12.2 Assignment by Law.……………………………………………………………………………………………………10 SECTION 13 NOTICES……………………………………………………………………………………………………………….10 13.1 Method of Notice ………………………………………………………………………………………………………10 13.2 Notice Recipents ……………………………………………………………………………………………………….11 13.3 Change of Address……………………………………………………………………………………………………..11 SECTION 14 DEFAULT…………………………………………………………………………………………………………......12 14.1 Notice of Default………………………………………………………………………………………………………..12 14.2 Opportunity to Cure Default………………………………………………………………………………………12 SECTION 15 CITY'S RIGHTS AND REMEDIES……………………………………………………………………………..12 15.1 Remedies Upon Default………………………………………………………………………………………….....12 15.1.1 Delete Certain Services…………………………………………………………………………………………..12 15.1.2 Perform and Withhold……………………………………………………………………………………………..12 15.1.3 Suspend The Construction Contract………………………………………………………………………..12 15.1.4 Terminate the Construction Contract for Default…………………………………………………….12 15.1.5 Invoke the Performance Bond…………………………………………………………………………………..12 15.1.6 Additional Provisions………………………………………………………………………………………………13 15.2 Delays by Sureties……………………………………………………………………………………………………….13 15.3 Damages to City………………………………………………………………………………………………………….13 15.3.1 For Contractor's Default………………………………………………………………………………………….13 15.3.2 Compensation for Losses………………………………………………………………………………………..13 15.4 Suspension by City……………………………………………………………………………………………………..13 15.4.1 Suspension for Convenience……………………………………………………………………………………13 15.4.2 Suspension for Cause…………………………………………………………………………………………......13 15.5 Termination Without Cause……………………………………………………………………………………….14 15.5.1 Compensation…………………………………………………………………………………………………………14 15.5.2 Subcontractors………………………………………………………………………………………………………….14 15.6 Contractor’s Duties Upon Termination………………………………………………………………...........14 SECTION 16 CONTRACTOR'S RIGHTS AND REMEDIES…………………………………………………………………15 16.1 Contractor’s Remedies……………………………………..………………………………………………………….15 16.1.1 For Work Stoppage……………………………………………………………………………………………………15 Rev. September 29, 2021 4 PART 4 – CONSTRUCTION CONTRACT 16.1.2 For City's Non-Payment……………………………………………………………………………………………..15 16.2 Damages to Contractor………………………………………………………………………………………………….15 SECTION 17 ACCOUNTING RECORDS………………………………………………………………………………….……….15 17.1 Financial Management and City Access………………………………………………………………………….15 17.2 Compliance with City Requests………………………………………………………………………………………16 SECTION 18 INDEPENDENT PARTIES…………………………………………………………………………………………….16 18.1 Status of Parties……………………………………………………………………………………………………………..16 SECTION 19 NUISANCE……………………………………………………………………………………………………….………..16 19.1 Nuisance Prohibited………………………………………………………………………………………………………..16 SECTION 20 PERMITS AND LICENSES…………………………………………………………………………………………..16 SECTION 21 WAIVER…………………………………………………………………………………………………………………….16 SECTION 22 GOVERNING LAW AND VENUE; COMPLIANCE WITH LAWS………………………………………..17 22.1 Governing Law…………………………………………………………………………………………………………………17 22.2 Compliance with Laws……………………………………………………………………………………………………..17 22.2.1 Palo Alto Minimum Wage Ordinance ………………………………………….…………………………………17 SECTION 23 COMPLETE AGREEMENT…………………………………………………………………………………………...17 23.1 Integration……………………………………………………………………………………………………………………….17 SECTION 24 SURVIVAL OF CONTRACT…………………………………………………………………………………………..17 24.1 Survival of Provisions……………………………………………………………………………………………………....17 SECTION 25 PREVAILING WAGES…………………………………………………………………………………………………..17 SECTION 26 NON-APPROPRIATION……………………………………………………………………………………………….18 26.1 Appropriation…………………………………………………………………………………………………………………..18 SECTION 27 AUTHORITY……………………………………………………………………………………………………………….18 27.1 Representation of Parties………………………………………………………………………………………………..18 SECTION 28 COUNTERPARTS……………………………………………………………………………………………….........18 28.1 Multiple Counterparts……………………………………………………………………………………………………18 SECTION 29 SEVERABILITY…………………………………………………………………………………………………………..18 29.1 Severability…………………………………………………………………………………………………………………….18 SECTION 30 STATUTORY AND REGULATORY REFERENCES ………………………………………………….........18 30.1 Amendments of Laws…………………………………………………………………………………………………….18 SECTION 31 WORKERS’ COMPENSATION CERTIFICATION………………………………………………….……….19 31.1 Workers Compensation…………………………………………………………………………………………………19 Rev. September 29, 2021 5 PART 4 – CONSTRUCTION CONTRACT SECTION 32 DIR REGISTRATION AND OTHER REQUIREMENTS………………………………………..…………19 32.1 General Notice to Contractor……………………………………………………………………………………….19 32.2 Labor Code section 1771.1(a)……………………………………………………………………………………...19 32.3 DIR Registration Required……………………………………………………………………………………………19 32.4 Posting of Job Site Notices……………………………………………………………………………………………19 32.5 Payroll Records…………………………………………………………………………………………………………….19 32.6 Employment of Apprentices…………………………………………………………………………………………20 Rev. September 29, 2021 6 PART 4 – CONSTRUCTION CONTRACT CONSTRUCTION CONTRACT THIS CONSTRUCTION CONTRACT entered into on November 14, 2022 (“Execution Date”) by and between the CITY OF PALO ALTO, a California chartered municipal corporation ("City"), and ANDERSON PACIFIC ENGINEERING CONSTRUCTION, INC. ("Contractor"), is made with reference to the following: R E C I T A L S: A.City is a municipal corporation duly organized and validly existing under the laws of the State of California with the power to carry on its business as it is now being conducted under the statutes of the State of California and the Charter of City. B.Contractor is a corporation duly organized and in good standing in the State of California, Contractor’s License Number 245215 and Department of Industrial Relations Registration Number 1000000061. Contractor represents that it is duly licensed by the State of California and has the background, knowledge, experience and expertise to perform the obligations set forth in this Construction Contract. C.On July 12, 2022, City issued an Invitation for Bids (IFB) to contractors for the 12kV Electrical Power Distribution Loop Rehabilitation Bid Pkg 1 (“Project”). In response to the IFB, Contractor submitted a Bid. D.City and Contractor desire to enter into this Construction Contract for the Project, and other services as identified in the Contract Documents for the Project upon the following terms and conditions. NOW THEREFORE, in consideration of the mutual promises and undertakings hereinafter set forth and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, it is mutually agreed by and between the undersigned parties as follows: SECTION 1 INCORPORATION OF RECITALS AND DEFINITIONS. 1.1 Recitals. All of the recitals are substantive parts of this Construction Contract and are hereby incorporated herein by reference. 1.2 Definitions. Capitalized terms shall have the meanings set forth in this Construction Contract (sometimes referred to herein as the “Contract”) and/or in the General Conditions. If there is a conflict between the definitions in this Construction Contract and in the General Conditions, the definitions in this Construction Contract shall prevail. SECTION 2 THE PROJECT. The Project is the 12kV Electrical Power Distribution Loop Rehabilitation Bid Pkg 1 Project, located at 2501 Embarcadero Way, Palo Alto, CA. 94303 ("Project"). / / / / Rev. September 29, 2021 7 PART 4 – CONSTRUCTION CONTRACT SECTION 3 THE CONTRACT DOCUMENTS. 3.1 List of Documents. The Contract Documents (sometimes collectively referred to as “Agreement” or “Bid Documents”) consist of the following documents which are on file with the Purchasing Division and are hereby incorporated into this Construction Contract by reference. 1) Change Orders 2) Field Orders 3) Construction Contract 4) Bidding Addenda 5) Special Provisions 6) General Conditions 7) Project Plans and Drawings 8) Technical Specifications 9) Instructions to Bidders 10) Invitation for Bids 11) Contractor's Bid/Non-Collusion Declaration 12) Reports listed in the Contract Documents 13) Public Works Department’s Standard Drawings and Specifications (most current version at time of Bid) 14) Utilities Department’s Water, Gas, Wastewater, Electric Utilities Standards (most current version at time of Bid) 15) City of Palo Alto Traffic Control Requirements 16) City of Palo Alto Truck Route Map and Regulations 17) Notice Inviting Pre-Qualification Statements, Pre-Qualification Statement, and Pre-Qualification Checklist (if applicable) 18) Performance and Payment Bonds 3.2 Order of Precedence. For the purposes of construing, interpreting and resolving inconsistencies between and among the provisions of this Contract, the Contract Documents shall have the order of precedence as set forth in the preceding section. If a claimed inconsistency cannot be resolved through the order of precedence, the City shall have the sole power to decide which document or provision shall govern as may be in the best interests of the City. SECTION 4 CONTRACTOR’S DUTY. 4.1 Contractor’s Duties Rev. September 29, 2021 8 PART 4 – CONSTRUCTION CONTRACT Contractor agrees to perform all of the Work required for the Project, as specified in the Contract Documents, all of which are fully incorporated herein. Contractor shall provide, furnish, and supply all things necessary and incidental for the timely performance and completion of the Work, including, but not limited to, provision of all necessary labor, materials, equipment, transportation, and utilities, unless otherwise specified in the Contract Documents. Contractor also agrees to use its best efforts to complete the Work in a professional and expeditious manner and to meet or exceed the performance standards required by the Contract Documents. SECTION 5 PROJECT TEAM. 5.1 Contractor’s Co-operation. In addition to Contractor, City has retained, or may retain, consultants and contractors to provide professional and technical consultation for the design and construction of the Project. The Contract requires that Contractor operate efficiently, effectively and cooperatively with City as well as all other members of the Project Team and other contractors retained by City to construct other portions of the Project. SECTION 6 TIME OF COMPLETION. 6.1 Time Is of Essence. Time is of the essence with respect to all time limits set forth in the Contract Documents. 6.2 Commencement of Work. Contractor shall commence the Work on the date specified in City’s Notice to Proceed. 6.3 Contract Time. Work hereunder shall begin on the date specified on the City’s Notice to Proceed and shall be completed not later than December 31, 2024. within calendar days () after the commencement date specified in City’s Notice to Proceed. By executing this Construction Contract, Contractor expressly waives any claim for delayed early completion. 6.4 Liquidated Damages. Pursuant to Public Contract Code Section 7203, if Contractor fails to achieve Final Completion of the entire Work within the Contract Time, including any approved extensions thereto, City may assess liquidated damages on a daily basis for each day of Unexcused Delay in achieving Final Completion, based on the amount of Five Thousand Six Hundred Eighteen Dollars ($5,618) per day, or as otherwise specified in the Special Provisions. Liquidated damages may also be separately assessed for failure to meet milestones specified elsewhere in the Contract Documents, regardless of impact on the time for achieving Final Completion. The assessment of liquidated damages is not a penalty but considered to be a reasonable estimate of the amount of damages City will suffer by delay in completion of the Work. The City is entitled to setoff the amount of liquidated damages assessed against any payments otherwise due to Contractor, including, but not limited to, setoff against release of retention. If the total amount of liquidated damages assessed exceeds the amount of unreleased retention, City is entitled to recover the balance from Contractor or its sureties. Occupancy or use of the Project in whole or in part prior to Final Completion, shall not operate as a waiver of City’s right to assess liquidated damages. 6.4.1 Other Remedies. City is entitled to any and all available legal and equitable remedies City may have where City’s Losses are caused by any reason other than Contractor’s failure to achieve Substantial Completion of the entire Work within the Contract Time. Rev. September 29, 2021 9 PART 4 – CONSTRUCTION CONTRACT 6.5 Adjustments to Contract Time. The Contract Time may only be adjusted for time extensions approved by City and memorialized in a Change Order approved in accordance with the requirements of the Contract Documents. SECTION 7 COMPENSATION TO CONTRACTOR. 7.1 Contract Sum. Contractor shall be compensated for satisfactory completion of the Work in compliance with the Contract Documents the Contract Sum of Six Million Seventy Thousand Dollars ($6,070,000.00). [This amount includes the Base Bid and Additive Alternates .] 7.2 Full Compensation. The Contract Sum shall be full compensation to Contractor for all Work provided by Contractor and, except as otherwise expressly permitted by the terms of the Contract Documents, shall cover all Losses arising out of the nature of the Work or from the acts of the elements or any unforeseen difficulties or obstructions which may arise or be encountered in performance of the Work until its Acceptance by City, all risks connected with the Work, and any and all expenses incurred due to suspension or discontinuance of the Work, except as expressly provided herein. The Contract Sum may only be adjusted for Change Orders approved in accordance with the requirements of the Contract Documents. SECTION 8 STANDARD OF CARE. 8.1 Standard of Care. Contractor agrees that the Work shall be performed by qualified, experienced and well-supervised personnel. All services performed in connection with this Construction Contract shall be performed in a manner consistent with the standard of care under California law applicable to those who specialize in providing such services for projects of the type, scope and complexity of the Project. SECTION 9 INDEMNIFICATION. 9.1 Hold Harmless. To the fullest extent allowed by law, Contractor will defend, indemnify, and hold harmless City, its City Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter individually referred to as an “Indemnitee” and collectively referred to as "Indemnitees"), through legal counsel acceptable to City, from and against any and liability, loss, damage, claims, expenses (including, without limitation, attorney fees, expert witness fees, paralegal fees, and fees and costs of litigation or arbitration) (collectively, “Liability”) of every nature arising out of or in connection with the acts or omissions of Contractor, its employees, Subcontractors, representatives, or agents, in performing the Work or its failure to comply with any of its obligations under the Contract, except such Liability caused by the active negligence, sole negligence, or willful misconduct of an Indemnitee. Contractor shall pay City for any costs City incurs to enforce this provision. Except as provided in Section 9.2 below, nothing in the Contract Documents shall be construed to give rise to any implied right of indemnity in favor of Contractor against City or any other Indemnitee. Pursuant to Public Contract Code Section 9201, City shall timely notify Contractor upon receipt of any third-party claim relating to the Contract. Rev. September 29, 2021 10 PART 4 – CONSTRUCTION CONTRACT 9.2 Survival. The provisions of Section 9 shall survive the termination or expiration of this Construction Contract. SECTION 10 NON-DISCRIMINATION. 10.1 Municipal Code Requirement. As set forth in Palo Alto Municipal Code section 2.30.510, Contractor certifies that in the performance of this Agreement, it shall not discriminate in the employment of any person due to the race, skin color, gender, gender identity, age, religion, disability, national origin, ancestry, sexual orientation, pregnancy, genetic information or condition, housing status, marital status, familial status, weight or height of such person. Contractor acknowledges that it has read and understands the provisions of Section 2.30.510 of the Palo Alto Municipal Code relating to Nondiscrimination Requirements, and the penalties for violation thereof, and will comply with all requirements of Section 2.30.510 pertaining to nondiscrimination in employment. SECTION 11 INSURANCE AND BONDS. 11.1 Evidence of coverage. Within ten (10) business days following issuance of the Notice of Award, Contractor shall provide City with evidence that it has obtained insurance and shall submit Performance and Payment Bonds satisfying all requirements in Article 11 of the General Conditions. SECTION 12 PROHIBITION AGAINST TRANSFERS. 12.1 Assignment. City is entering into this Construction Contract in reliance upon the stated experience and qualifications of the Contractor and its Subcontractors set forth in Contractor’s Bid. Accordingly, Contractor shall not assign, hypothecate or transfer this Construction Contract or any interest therein directly or indirectly, by operation of law or otherwise without the prior written consent of City. Any assignment, hypothecation or transfer without said consent shall be null and void, and shall be deemed a substantial breach of contract and grounds for default in addition to any other legal or equitable remedy available to the City. 12.2 Assignment by Law. The sale, assignment, transfer or other disposition of any of the issued and outstanding capital stock of Contractor or of any general partner or joint venturer or syndicate member of Contractor, if the Contractor is a partnership or joint venture or syndicate or co-tenancy shall result in changing the control of Contractor, shall be construed as an assignment of this Construction Contract. Control means more than fifty percent (50%) of the voting power of the corporation or other entity. SECTION 13 NOTICES. 13.1 Method of Notice. All notices, demands, requests or approvals to be given under this Construction Contract shall be given in writing and shall be deemed served on the earlier of the following: (i) On the date delivered if delivered personally; (ii) On the third business day after the deposit thereof in the United States mail, postage prepaid, and addressed as hereinafter provided; (iii) On the date sent if sent by facsimile transmission; (iv) On the date sent if delivered by electronic mail; or (v) On the date it is accepted or rejected if sent by certified mail. Rev. September 29, 2021 11 PART 4 – CONSTRUCTION CONTRACT 13.2 Notice to Recipients. All notices, demands or requests (including, without limitation, Change Order Requests and Claims) from Contractor to City shall include the Project name and the number of this Construction Contract and shall be addressed to City at: To City: City of Palo Alto City Clerk 250 Hamilton Avenue P.O. Box 10250 Palo Alto, CA 94303 Copy to: City of Palo Alto Public Works Administration 2501 Embarcadero Way Palo Alto, CA 94303 Attn: Padmakar Chaobal [Include Construction Manager, If Applicable.] Carollo Engineers 2795 Mitchell Drive Walnut Creek, CA 94598 Attn: Rick Chan, PE Email: rchan@carollo.com In addition, copies of all Claims by Contractor under this Construction Contract shall be provided to the following: Palo Alto City Attorney’s Office 250 Hamilton Avenue P.O. Box 10250 Palo Alto, California 94303 All Claims shall be sent by registered mail or certified mail with return receipt requested. All notices, demands, requests or approvals from City to Contractor shall be addressed to Contractor at: To Contractor: Anderson Pacific Engineering Construction, Inc. 1370 Norman Avenue Santa Clara, CA 95054 Attn: Peter E. Anderson Email: pea@andpac.com 13.3 Change of Address. In advance of any change of address, Contractor shall notify City of the change of address in writing. Each party may, by written notice only, add, delete or replace any individuals to whom and addresses to which notice shall be provided. Rev. September 29, 2021 12 PART 4 – CONSTRUCTION CONTRACT SECTION 14 DEFAULT. 14.1 Notice of Default. In the event that City determines, in its sole discretion, that Contractor has failed or refused to perform any of the obligations set forth in the Contract Documents, or is in breach of any provision of the Contract Documents, City may give written notice of default to Contractor in the manner specified for the giving of notices in the Construction Contract, with a copy to Contractor’s performance bond surety. 14.2 Opportunity to Cure Default. Except for emergencies, Contractor shall cure any default in performance of its obligations under the Contract Documents within two (2) Days (or such shorter time as City may reasonably require) after receipt of written notice. However, if the breach cannot be reasonably cured within such time, Contractor will commence to cure the breach within two (2) Days (or such shorter time as City may reasonably require) and will diligently and continuously prosecute such cure to completion within a reasonable time, which shall in no event be later than ten (10) Days after receipt of such written notice. SECTION 15 CITY'S RIGHTS AND REMEDIES. 15.1 Remedies Upon Default. If Contractor fails to cure any default of this Construction Contract within the time period set forth above in Section 14, then City may pursue any remedies available under law or equity, including, without limitation, the following: 15.1.1 Delete Certain Services. City may, without terminating the Construction Contract, delete certain portions of the Work, reserving to itself all rights to Losses related thereto. 15.1.2 Perform and Withhold. City may, without terminating the Construction Contract, engage others to perform the Work or portion of the Work that has not been adequately performed by Contractor and withhold the cost thereof to City from future payments to Contractor, reserving to itself all rights to Losses related thereto. 15.1.3 Suspend the Construction Contract. City may, without terminating the Construction Contract and reserving to itself all rights to Losses related thereto, suspend all or any portion of this Construction Contract for as long a period of time as City determines, in its sole discretion, appropriate, in which event City shall have no obligation to adjust the Contract Sum or Contract Time, and shall have no liability to Contractor for damages if City directs Contractor to resume Work. 15.1.4 Terminate the Construction Contract for Default. City shall have the right to terminate this Construction Contract, in whole or in part, upon the failure of Contractor to promptly cure any default as required by Section 14. City’s election to terminate the Construction Contract for default shall be communicated by giving Contractor a written notice of termination in the manner specified for the giving of notices in the Construction Contract. Any notice of termination given to Contractor by City shall be effective immediately, unless otherwise provided therein. 15.1.5 Invoke the Performance Bond. City may, with or without terminating the Construction Contract and reserving to itself all rights to Losses related thereto, exercise its rights under the Performance Bond. Rev. September 29, 2021 13 PART 4 – CONSTRUCTION CONTRACT 15.1.6 Additional Provisions. All of City’s rights and remedies under this Construction Contract are cumulative, and shall be in addition to those rights and remedies available in law or in equity. Designation in the Contract Documents of certain breaches as material shall not waive the City’s authority to designate other breaches as material nor limit City’s right to terminate the Construction Contract, or prevent the City from terminating the Agreement for breaches that are not material. City’s determination of whether there has been noncompliance with the Construction Contract so as to warrant exercise by City of its rights and remedies for default under the Construction Contract, shall be binding on all parties. No termination or action taken by City after such termination shall prejudice any other rights or remedies of City provided by law or equity or by the Contract Documents upon such termination; and City may proceed against Contractor to recover all liquidated damages and Losses suffered by City. 15.2 Delays by Sureties. Time being of the essence in the performance of the Work, if Contractor’s surety fails to arrange for completion of the Work in accordance with the Performance Bond, within seven (7) calendar days from the date of the notice of termination, Contractor’s surety shall be deemed to have waived its right to complete the Work under the Contract, and City may immediately make arrangements for the completion of the Work through use of its own forces, by hiring a replacement contractor, or by any other means that City determines advisable under the circumstances. Contractor and its surety shall be jointly and severally liable for any additional cost incurred by City to complete the Work following termination. In addition, City shall have the right to use any materials, supplies, and equipment belonging to Contractor and located at the Worksite for the purposes of completing the remaining Work. 15.3 Damages to City. 15.3.1 For Contractor's Default. City will be entitled to recovery of all Losses under law or equity in the event of Contractor’s default under the Contract Documents. 15.3.2 Compensation for Losses. In the event that City's Losses arise from Contractor’s default under the Contract Documents, City shall be entitled to deduct the cost of such Losses from monies otherwise payable to Contractor. If the Losses incurred by City exceed the amount payable, Contractor shall be liable to City for the difference and shall promptly remit same to City. 15.4 Suspension by City 15.4.1 Suspension for Convenience. City may, at any time and from time to time, without cause, order Contractor, in writing, to suspend, delay, or interrupt the Work in whole or in part for such period of time, up to an aggregate of fifty percent (50%) of the Contract Time. The order shall be specifically identified as a Suspension Order by City. Upon receipt of a Suspension Order, Contractor shall, at City’s expense, comply with the order and take all reasonable steps to minimize costs allocable to the Work covered by the Suspension Order. During the Suspension or extension of the Suspension, if any, City shall either cancel the Suspension Order or, by Change Order, delete the Work covered by the Suspension Order. If a Suspension Order is canceled or expires, Contractor shall resume and continue with the Work. A Change Order will be issued to cover any adjustments of the Contract Sum or the Contract Time necessarily caused by such suspension. A Suspension Order shall not be the exclusive method for City to stop the Work. 15.4.2 Suspension for Cause. In addition to all other remedies available to City, if Contractor fails to perform or correct work in accordance with the Contract Documents, City may immediately order the Work, or any portion thereof, suspended until the cause for the suspension has been eliminated to City’s satisfaction. Contractor shall not be entitled to an increase in Contract Time or Contract Price for a suspension occasioned by Contractor’s failure to comply with the Contract Documents. City’s right to suspend the Work shall not give rise to a duty to suspend the Work, and City’s failure to suspend the Work shall not constitute a defense to Contractor’s failure to comply with the requirements of the Contract Documents. Rev. September 29, 2021 14 PART 4 – CONSTRUCTION CONTRACT 15.5 Termination Without Cause. City may, at its sole discretion and without cause, terminate this Construction Contract in part or in whole upon written notice to Contractor. Upon receipt of such notice, Contractor shall, at City’s expense, comply with the notice and take all reasonable steps to minimize costs to close out and demobilize. The compensation allowed under this Paragraph 15.5 shall be the Contractor’s sole and exclusive compensation for such termination and Contractor waives any claim for other compensation or Losses, including, but not limited to, loss of anticipated profits, loss of revenue, lost opportunity, or other consequential, direct, indirect or incidental damages of any kind resulting from termination without cause. Termination pursuant to this provision does not relieve Contractor or its sureties from any of their obligations for Losses arising from or related to the Work performed by Contractor. 15.5.1 Compensation. Following such termination and within forty-five (45) Days after receipt of a billing from Contractor seeking payment of sums authorized by this Paragraph 15.5.1, City shall pay the following to Contractor as Contractor’s sole compensation for performance of the Work: .1 For Work Performed. The amount of the Contract Sum allocable to the portion of the Work properly performed by Contractor as of the date of termination, less sums previously paid to Contractor. .2 For Close-out Costs. Reasonable costs of Contractor and its Subcontractors: (i) Demobilizing and (ii) Administering the close-out of its participation in the Project (including, without limitation, all billing and accounting functions, not including attorney or expert fees) for a period of no longer than thirty (30) Days after receipt of the notice of termination. .3 For Fabricated Items. Previously unpaid cost of any items delivered to the Project Site which were fabricated for subsequent incorporation in the Work. .4 Profit Allowance. An allowance for profit calculated as four percent (4%) of the sum of the above items, provided Contractor can prove a likelihood that it would have made a profit if the Construction Contract had not been terminated. 15.5.2 Subcontractors. Contractor shall include provisions in all of its subcontracts, purchase orders and other contracts permitting termination for convenience by Contractor on terms that are consistent with this Construction Contract and that afford no greater rights of recovery against Contractor than are afforded to Contractor against City under this Section. 15.6 Contractor’s Duties Upon Termination. Upon receipt of a notice of termination for default or for convenience, Contractor shall, unless the notice directs otherwise, do the following: (i) Immediately discontinue the Work to the extent specified in the notice; (ii) Place no further orders or subcontracts for materials, equipment, services or facilities, except as may be necessary for completion of such portion of the Work that is not discontinued; (iii) Provide to City a description in writing, no later than fifteen (15) days after receipt of the notice of termination, of all subcontracts, purchase orders and contracts that are outstanding, including, without limitation, the terms of the original price, any changes, payments, balance owing, the status of the portion of the Work covered and a copy of the subcontract, purchase order or contract and any written changes, amendments or modifications thereto, together with such other information as City may determine necessary in order to decide whether to accept assignment of or request Contractor to terminate the subcontract, purchase order or contract; (iv) Promptly assign to City those subcontracts, purchase orders or contracts, or portions thereof, that City elects to accept by assignment and cancel, on the most favorable terms reasonably possible, all Rev. September 29, 2021 15 PART 4 – CONSTRUCTION CONTRACT subcontracts, purchase orders or contracts, or portions thereof, that City does not elect to accept by assignment; and (v) Thereafter do only such Work as may be necessary to preserve and protect Work already in progress and to protect materials, plants, and equipment on the Project Site or in transit thereto. Upon termination, whether for cause or for convenience, the provisions of the Contract Documents remain in effect as to any Claim, indemnity obligation, warranties, guarantees, submittals of as-built drawings, instructions, or manuals, or other such rights and obligations arising prior to the termination date. SECTION 16 CONTRACTOR'S RIGHTS AND REMEDIES. 16.1 Contractor’s Remedies. Contractor may terminate this Construction Contract only upon the occurrence of one of the following: 16.1.1 For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any Subcontractor, due to issuance of an order of a court or other public authority other than City having jurisdiction or due to an act of government, such as a declaration of a national emergency making material unavailable. This provision shall not apply to any work stoppage resulting from the City’s issuance of a suspension notice issued either for cause or for convenience. 16.1.2 For City's Non-Payment. If City does not pay Contractor undisputed sums within ninety (90) Days after receipt of notice from Contractor, Contractor may terminate the Construction Contract (30) days following a second notice to City of Contractor’s intention to terminate the Construction Contract. 16.2 Damages to Contractor. In the event of termination for cause by Contractor, City shall pay Contractor the sums provided for in Paragraph 15.5.1 above. Contractor agrees to accept such sums as its sole and exclusive compensation and agrees to waive any claim for other compensation or Losses, including, but not limited to, loss of anticipated profits, loss of revenue, lost opportunity, or other consequential, direct, indirect and incidental damages, of any kind. SECTION 17 ACCOUNTING RECORDS. 17.1 Financial Management and City Access. Contractor shall keep full and detailed accounts and exercise such controls as may be necessary for proper financial management under this Construction Contract in accordance with generally accepted accounting principles and practices. City and City's accountants during normal business hours, may inspect, audit and copy Contractor's records, books, estimates, take-offs, cost reports, ledgers, schedules, correspondence, instructions, drawings, receipts, subcontracts, purchase orders, vouchers, memoranda and other data relating to this Project. Contractor shall retain these documents for a period of three (3) years after the later of (i) Final Payment or (ii) final resolution of all Contract Disputes and other disputes, or (iii) for such longer period as may be required by law. Rev. September 29, 2021 16 PART 4 – CONSTRUCTION CONTRACT 17.2 Compliance with City Requests. Contractor's compliance with any request by City pursuant to this Section 17 shall be a condition precedent to filing or maintenance of any legal action or proceeding by Contractor against City and to Contractor's right to receive further payments under the Contract Documents. City many enforce Contractor’s obligation to provide access to City of its business and other records referred to in Section 17.1 for inspection or copying by issuance of a writ or a provisional or permanent mandatory injunction by a court of competent jurisdiction based on affidavits submitted to such court, without the necessity of oral testimony. SECTION 18 INDEPENDENT PARTIES. 18.1 Status of parties. Each party is acting in its independent capacity and not as agents, employees, partners, or joint venturers of the other party. City, its officers or employees shall have no control over the conduct of Contractor or its respective agents, employees, subconsultants, or subcontractors, except as herein set forth. SECTION 19 NUISANCE. 19.1 Nuisance Prohibited. Contractor shall not maintain, commit, nor permit the maintenance or commission of any nuisance in connection in the performance of services under this Construction Contract. SECTION 20 PERMITS AND LICENSES. Except as otherwise provided in the Special Provisions and Technical Specifications, the Contractor shall provide, procure and pay for all licenses, permits, and fees, required by the City or other government jurisdictions or agencies necessary to carry out and complete the Work. Payment of all costs and expenses for such licenses, permits, and fees shall be included in one or more Bid items. No other compensation shall be paid to the Contractor for these items or for delays caused by non-City inspectors or conditions set forth in the licenses or permits issued by other agencies. SECTION 21 WAIVER. A waiver by either party of any breach of any term, covenant, or condition contained herein shall not be deemed to be a waiver of any subsequent breach of the same or any other term, covenant, or condition contained herein, whether of the same or a different character. Rev. September 29, 2021 17 PART 4 – CONSTRUCTION CONTRACT SECTION 22 GOVERNING LAW AND VENUE; COMPLIANCE WITH LAWS. 22.1 Governing Law and Venue. This Construction Contract shall be construed in accordance with and governed by the laws of the State of California, without regard to conflict of law provisions, and venue shall be in a court of competent jurisdiction in the County of Santa Clara, California and no other place. 22.2 Compliance with Laws. Contractor shall comply with all applicable federal and California laws and city laws, including, without limitation, ordinances and resolutions, in the performance of work under this Construction Contract. 22.2.1 Palo Alto Minimum Wage Ordinance. Contractor shall comply with all requirements of the Palo Alto Municipal Code Chapter 4.62 (Citywide Minimum Wage), as amended from time to time. In particular, for any employee otherwise entitled to the State minimum wage, who performs at least two (2) hours of work in a calendar week within the geographic boundaries of the City, Contractor shall pay such employees no less than the minimum wage set forth in Palo Alto Municipal Code section 4.62.030 for each hour worked within the geographic boundaries of the City of Palo Alto. In addition, Contractor shall post notices regarding the Palo Alto Minimum Wage Ordinance in accordance with Palo Alto Municipal Code section 4.62.060. SECTION 23 COMPLETE AGREEMENT. 23.1 Integration. This Agreement represents the entire and integrated agreement between the parties and supersedes all prior negotiations, representations, and contracts, either written or oral. This Agreement may be amended only by a written instrument, which is signed by the parties. SECTION 24 SURVIVAL OF CONTRACT. 24.1 Survival of Provisions. The provisions of the Construction Contract which by their nature survive termination or expiration of the Construction Contract or Final Completion, including, without limitation, all warranties, indemnities, payment obligations, and City’s right to audit Contractor’s books and records, shall remain in full force and effect after Final Completion or any termination or expiration of the Construction Contract. SECTION 25 PREVAILING WAGES. This Project is not subject to prevailing wages and related requirements. Contractor is not required to pay prevailing wages and meet related requirements under the California Labor Code and California Code of Regulations in the performance and implementation of the Project if the Contract: (1) is not a public works contract; (2) is for a public works construction project of $25,000 or less, per California Labor Code Sections 1782(d)(1), 1725.5(f) and 1773.3(j); or (3) is for a public works alteration, demolition, repair, or maintenance project of $15,000 or less, per California Labor Code Sections 1782(d)(1), 1725.5(f) and 1773.3(j). Or This Project is subject to prevailing wages and related requirements as a “public works” under California Labor Code Sections 1720 et seq. and related regulations. Contractor is required to pay general prevailing wages as defined in California Labor Code Section 1773.1 and Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et Rev. September 29, 2021 18 PART 4 – CONSTRUCTION CONTRACT seq., as amended from time to time. Pursuant to Labor Code Section 1773, the City has obtained the general prevailing rate of per diem wages and the general rate for holiday and overtime work in this locality for each craft, classification, or type of worker needed to execute the contract for this Project from the State of California Department of Industrial Relations (“DIR”). Copies of these rates may be obtained at the City’s Purchasing Department office. The general prevailing wage rates are also available at the DIR, Division of Labor Statistics and Research, website (see e.g. http://www.dir.ca.gov/DLSR/PWD/index.htm) as amended from time to time. Contractor shall post a copy of the general prevailing wage rates at all Project job sites and shall pay the adopted prevailing wage rates as a minimum. Contractor shall comply with all applicable provisions of Division 2, Part 7, Chapter 1 of the California Labor Code (Labor Code Section 1720 et seq.), including, but not limited to, Sections 1720, 1725.5, 1771, 1771.1, 1771.4, 1773.2, 1774, 1775, 1776, 1777.5, 1782, 1810, 1813 and 1815, and all applicable implementing regulations, including but not limited to Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq. (8 CCR Section 16000 et seq.), as amended from time to time. SECTION 26 NON-APPROPRIATION. 26.1 Appropriations. This Agreement is subject to the fiscal provisions of the Charter of the City of Palo Alto and the Palo Alto Municipal Code. This Agreement will terminate without any penalty (a) at the end of any fiscal year in the event that the City does not appropriate funds for the following fiscal year for this event, or (b) at any time within a fiscal year in the event that funds are only appropriated for a portion of the fiscal year and funds for this Construction Contract are no longer available. This section shall take precedence in the event of a conflict with any other covenant, term, condition, or provision of this Agreement. SECTION 27 AUTHORITY. 27.1 Representation of Parties. The individuals executing this Agreement represent and warrant that they have the legal capacity and authority to do so on behalf of their respective legal entities. SECTION 28 COUNTERPARTS 28.1 Multiple Counterparts. This Agreement may be signed in multiple counterparts, which, when executed by all the parties, shall together constitute a single binding agreement. SECTION 29 SEVERABILITY. 29.1 Severability. In case a provision of this Construction Contract is held to be invalid, illegal or unenforceable, the validity, legality and enforceability of the remaining provisions shall not be affected. SECTION 30 STATUTORY AND REGULATORY REFERENCES. 30.1 Amendments to Laws. With respect to any amendments to any statutes or regulations referenced in these Contract Documents, the reference is deemed to be the version in effect on the date that the Contract was awarded by City, as may be amended from time to time, unless otherwise required by law. Rev. September 29, 2021 19 PART 4 – CONSTRUCTION CONTRACT SECTION 31 WORKERS’ COMPENSATION CERTIFICATION. 31.1 Workers Compensation. Contractor shall secure the payment of workers’ compensation to its employees as provided in Labor Code Sections 1860 and 3700. Pursuant to Labor Code Section 1861, by signing this Contract, Contractor thereby certifies as follows: “I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the Work on this Contract.” SECTION 32 DIR REGISTRATION AND OTHER REQUIREMENTS. 32.1 General Notice to Contractor. City requires Contractor and its Subcontractors to comply with all applicable requirements of the California Labor Code including but not limited to Labor Code Sections 1720 through 1861, and all applicable related regulations, including but not limited to Subchapter 3, Title 8 of the California Code of Regulations Section 16000 et seq., as amended from time to time. Additional information regarding public works and prevailing wage requirements is available on the DIR website (see e.g. http://www.dir.ca.gov) as amended from time to time. 32.2 Labor Code section 1771.1(a) City provides notice to Contractor of the requirements of California Labor Code section 1771.1(a), which reads: “A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or Section 10164 or 20103.5 of the Public Contract Code, provided the contactor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.” 32.3 DIR Registration Required. City will not accept a bid proposal from or enter into this Construction Contract with Contractor without proof that Contractor and its Subcontractors are registered with the California Department of Industrial Relations (“DIR”) to perform public work, subject to limited exceptions. 32.4 Posting of Job Site Notices; Compliance Monitoring. City gives notice to Contractor and its Subcontractors that Contractor is required to post all job site notices prescribed by law or regulation and Contractor is subject to compliance monitoring and enforcement by DIR. 32.5 Payroll Records. Contractor shall furnish certified payroll records directly to the Labor Commissioner (DIR) in accordance with Subchapter 3, Title 8 of the California Code of Regulations Section 16461 (8 CCR Section 16461). City requires Contractor and its Subcontractors to comply with the requirements of Labor Code section 1776, including but not limited to: Rev. September 29, 2021 20 PART 4 – CONSTRUCTION CONTRACT (i) Keep accurate payroll records, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by, respectively, Contractor and its Subcontractors, in connection with the Project. (ii) The payroll records shall be verified as true and correct and shall be certified and made available for inspection at all reasonable hours at the principal office of Contractor and its Subcontractors, respectively. (iii) At the request of City, acting by its Project Manager, Contractor and its Subcontractors shall make the certified payroll records available for inspection or furnished upon request to the City’s Project Manager within ten (10) days of receipt of City’s request. City requests Contractor and its Subcontractors to submit the certified payroll records to the City’s Project Manager at the end of each week during the Project. (iv) If the certified payroll records are not provided as required within the 10-day period, then Contractor and its Subcontractors shall be subject to a penalty of one hundred dollars ($100.00) per calendar day, or portion thereof, for each worker, and City shall withhold the sum total of penalties from the progress payment(s) then due and payable to Contractor. This provision supplements the provisions of Section 15 hereof. (v) Inform the City’s Project Manager of the location of Contractor’s and its Subcontractors’ payroll records (street address, city and county) at the commencement of the Project, and also provide notice to the City’s Project Manager within five (5) business days of any change of location of those payroll records. 32.6 Employment of Apprentices. Contractor shall comply with the statutory requirements regarding employment of apprentices including without limitation Labor Code Section 1777.5. The statutory provisions will be enforced for penalties for failure to pay prevailing wages and for failure to comply with wage and hour laws. Rev. September 29, 2021 21 PART 4 – CONSTRUCTION CONTRACT IN WITNESS WHEREOF, the parties have caused this Construction Contract to be executed the date and year first above written. CITY OF PALO ALTO ____________________________ Purchasing Manager City Manager APPROVED AS TO FORM: ____________________________ City Attorney or Designee APPROVED: ____________________________ Public Works Director ANDERSON PACIFIC ENGINEERING CONSTRUCTION, INC. Officer 1 By:___________________________ Name:________________________ Title:__________________________ Date: _________________________ Officer 2 By:____________________________ Name:__________________________ Title:___________________________ Date:___________________________