HomeMy WebLinkAboutStaff Report 13612 City of Palo Alto (ID # 13612) City Council Staff Report Meeting Date: 4/11/2022 Report Type: Information Reports City of Palo Alto Page 1 Title: Semiannual Update on the Status of Capital Improvement Program Projects From: City Manager Lead Department: Public Works Recommendation This report is provided for information only and requires no Council action. Executive Summary The City Council and Palo Alto community can be proud of the City’s capital improvement program (CIP). The CIP represents major investments in infrastructure functionality and sustainability, funded largely through the 2014 Council Infrastructure Plan as well as utility rates and various other sources. The 2022-2026 five-year CIP totaled $720.5 million for 170 projects as reviewed by the Council in its adoption of the FY 2022 Capital Budget. Over the past five years, the City has completed 84 individual community-serving projects totaling nearly $276 million in improvements. The CIP also represents a major effort for much of the City workforce. The following table summarizes the status of all projects for the six-month period of June to December 2021. Project Type Active Projects Construction Phase (excludes Recurring) Completed One-Time Recurring Buildings & Facilities 18 9 5 2 Parks & Open Space 9 9 2 - Streets & Sidewalks 2 8 - - Traffic & Transportation 8 4 2 1 Airport 4 - 1 - Electric Fund 20 9 5 2 Fiber Optics Fund 1 2 - - Gas Fund 2 4 1 - City of Palo Alto Page 2 Stormwater Management Fund 5 1 - - Water Fund 4 7 1 - Wastewater Collection Fund 1 4 1 - Wastewater Treatment Fund 8 1 1 - Totals 83 60 20 5 Background This report provides Council with an update on the status of capital improvement program (CIP) projects and does not include Internal Service Funds Capital Projects (IT and Vehicle). Prior to 2016, year-end and mid-year financial reports included very simple status updates on CIP projects. In contrast, this semiannual report provides more detailed and useful information for the Council and public regarding general fund and enterprise fund projects that appear on Council agendas and will be visible throughout the community. Discussion Project Update Organization The City has a robust capital improvement program, and many individual projects are in progress at any given time. The 2022-2026 five-year CIP totaled $720.5 million for 170 projects as reviewed by the Council as part of the Adoption of the FY 2022 Capital Budget. The attached CIP project tables are intended to provide Council with a quick overview of each project, including budgetary information, the anticipated completion date, a brief description of the project scope, the status of the project, and upcoming activities including Council actions. Also included in the report is a list of all completed projects since the introduction of the Infrastructure Management System. Major/Significant Projects Summary The 2014 Council Infrastructure Plan is a major focus of staff’s capital improvement program efforts. The following table details the Total Project Budget and Total Actual Expenses through the first half of Fiscal Year 2022 for the Infrastructure Plan projects. Significant milestones have been achieved on the Infrastructure Plan projects since June 2020, even though construction delays occurred due to the COVID-19 pandemic. The Highway 101 Pedestrian/Bicycle Bridge project was completed in November 2021 and significant progress has been made on the last phase of the Charleston/Arastradero Corridor Project and on the Public Safety Building. Current Infrastructure Plan project schedules can be found at http://www.infrastructure.cityofpaloalto.org/ Council Infrastructure Plan Projects CIP Number Update Total Project Budget Total Actual Expenses* New Public Safety Building PE-15001 Construction is underway with completion expected in summer 2023. $117,037,811 $14,745,147 City of Palo Alto Page 3 Bicycle and Pedestrian Transportation Implementation Plan PL-04010 Project on hold pending recent project evaluation and review of future project scoping. $15,276,377 $9,435,106 New Downtown Parking Garage PE-15007 Council directed staff to look at the feasibility of partnering with a private entity to develop new parking using downtown in- lieu parking fees in conjunction with housing or other uses, including the use of City surface lots or privately held parcels. $6,991,903 $1,440,311 New California Avenue Area Parking Garage PE-18000 Completed; project closeout in progress $50,149,954 $48,402,786 Charleston Arastradero Corridor Project PE-13011 Phase 1 & 2 improvements are complete. Phase 3 construction is underway with completion expected fall 2022. $20,788,951 $13,136,360 Fire Station 3 Replacement PE-15003 Completed; project closeout in progress $10,503,209 $9,772,438 Highway 101 Pedestrian/Bicycle Overpass Project PE-11011 Completed; project closeout in progress $22,898,724 $18,468,438 Fire Station 4 Replacement PE-18004 A contract for design services will be brought to Council for approval in early 2022. $10,167,779 $293,192 Byxbee Park Completion PE-18006 On hold pending completion of Baylands Comprehensive Conservation Plan. $3,249,335 $368,192 Downtown Parking Guidance System PL-15002 A design/build contract was approved by Council in August 2021 but could not be bonded by the Contractor. A new design/build RFP will be issued in early 2022. $2,579,860 $198,350 Total Project Budget and Total Actual Expenses $259,643,903 $116,260,320 *Expenses as of December 31, 2021 Key considerations for the information presented in the project update tables include: • Project status information is current as of December 2021 • The individual project tables align with the Capital Improvement Fund categories in the FY 2022-2026 capital budget: Buildings and Facilities, Parks and Open Space, Streets and Sidewalks, and Traffic and Transportation. Enterprise Fund projects follow the order of their respective Fund in the capital budget • Department Technology Upgrades and Improvements projects and Cubberley Property Infrastructure Fund projects are included in the Buildings and Facilities table • Additional project information is available in the FY 2022-2026 capital budget • Each project table is divided into a section for one-time projects and a section for recurring projects that have ongoing annual funding • Budgetary figures include staff oversight costs for projects to which staff costs have been allocated City of Palo Alto Page 4 • The table of completed projects, provides a summary of all CIP projects completed since the Biannual CIP updates to council began in 2016. The data is sorted from most recent to oldest Completed Projects Projects completed in the first half of Fiscal Year 2022, since the last update in June 2021, from July 2021 to December 2021 include the following: Capital Improvement Fund (general fund): • Highway 101 Pedestrian Bicycle Overpass Project (PE-11011) • High and Bryant Street Garages Waterproofing and Repairs (PE-18002) • JMZ Renovation (AC-18001) Electric Fund: • Underground District 46 – Charleston, El Camino Real (EL-12001) • Reconfigure Quarry Feeders (EL-14005) These completed projects do not include the significant amount of annual work completed under ongoing recurring projects, such as streets and sidewalks repairs, parking lot maintenance, roofing replacements, and regular maintenance of Utilities assets. Below are some photos of completed projects: Highway 101 Pedestrian/Bicycle Overpass Project (PE-11011) City of Palo Alto Page 5 City of Palo Alto Page 6 Projects Under Construction Projects that are currently under construction include the following: Capital Improvement Fund (general fund): • Automated External Defibrillator Replacement (FD-21000) • Charleston-Arastradero Corridor Project (PE-13011) • Civic Center Electrical Upgrade and EV Charger Installation (PE-17010) • Civic Center Waterproofing Study and Repairs (PE-15020) • Emergency Vehicle Traffic Signal Preemption System Pilot (PL‐19000) • Magical Bridge Playground Rubber and Synthetic Turf Resurfacing (PE-21003) • Municipal Service Center A, B and C Roof Replacement (PF-17000) • New Public Safety Building (PE-15001) • Rinconada Park Improvements (PE-08001) Airport Fund • Airport Apron Reconstruction (AP-16000) Electric Fund • Capacitor Bank Installation (EL-06001) • Facility Relocation for Caltrain Modernization (EL-17007) • Inter Substation Line Protection Relay (EL-17005) • Rebuild Underground District 24 (EL-10006) • Substation Physical Security (EL-16003) Gas Fund • Gas Main Replacement Project 23 (GS-13001) Wastewater Collection Fund City of Palo Alto Page 7 • Wastewater Collection System Rehabilitation Augmentation Project 30 (WC-17001) Wastewater Treatment Fund • Primary Sedimentation Tank Rehabilitation (WQ-14003) Water Fund • Water Tank Seismic System Upgrades (WS-09000) As described above for completed projects, the list of projects under construction does not include work currently being conducted under recurring CIP projects. Below are some photos of projects under construction: New Public Safety Building (PE-15001) City of Palo Alto Page 8 Public Safety Building Update City of Palo Alto Page 9 The Public Safety Building project made significant progress in the first half of Fiscal Year 2022. Excavation was completed in November and the mat slab foundation was poured in December 2021. As of February 2022, construction is 34% complete and 39% of the project’s construction contingency has been used. As with other large construction projects Public Works is managing, staff has seen an increase in claims from contractors. To date, Public Works staff has coordinated with the City’s Attorney’s Office to resolve two claims from the construction contractor. Staff continues to coordinate with the City Auditor, Baker Tilly, on the Public Safety Building Construction Audit by providing project documents on a monthly basis. Per Council direction at construction contract award, staff is conducting a full review of the Furniture, Fixtures, and Equipment (FF&E) plan that will be completed this spring. Additionally, a cross- departmental staff team is meeting monthly to review and coordinate construction of the Public Safety Building and other projects in the California Avenue area, with a goal of communicating and mitigating the impacts. Capital Improvements of Note Implemented by Other Agencies El Camino Real: El Camino Real (State Highway 82) is maintained by Caltrans. Pavement Condition Index scores for El Camino Real are significantly lower than the average for Palo Alto streets. Staff has been communicating with Caltrans about the upcoming plans to repave El Camino Real from the Mountain View to Menlo Park borders. Currently, this work is planned for late 2022. Caltrain Electrification: The majority of construction for Caltrain Electrification in Palo Alto has been completed, including the installation of all of the foundations, poles and wires for the project. Construction is continuing at the Paralleling Station near Page Mill Road which is scheduled to be complete in spring 2022. The Caltrain Electrification Project is scheduled to be complete in fall 2024. Palo Alto Flood Basin Tide Gate Replacement Project: Santa Clara Valley Water District (Valley Water) is working on a project to replace the existing tide gate structures built in 1957. City staff received and reviewed the 60% design documents and Valley Water presented to the Parks and Recreation Commission in August 2021. The revised 90% plans are anticipated to be resubmitted for City staff review in early 2022. Valley Water anticipates starting construction in September 2023 and completing the project in 2027. Resource Impact Funding for the projects discussed in this report is provided in the Fiscal Year 2022 Adopted Capital Budget and 2022-2026 Five-Year CIP. Stakeholder Engagement Stakeholder engagement is conducted separately for each project. Attachments: • Attachment A: Semiannual CIP Updates and List of Completed Projects ATTACHMENT A DECEMBER 2021  Semiannual Update on the Status of Capital Improvement Program Projects  Capital Improvement Fund CIP Projects  Buildings and Facilities Projects Parks and Open Space Projects Streets and Sidewalks Projects Traffic and Transportation Projects Enterprise Fund CIP Projects  Airport Projects Electric Projects Fiber Optics Projects Gas Projects Stormwater Management Projects Wastewater Collection Projects Wastewater Treatment Projects Water Projects List of Completed Projects                             Blank page  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 1 of 8  One‐Time Projects  Animal Shelter  Renovation   (PE‐19002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,708,120 $3,967,759 Public Works Design Summer 2023  Project Status:  This project installs interim facility improvements to the Animal Shelter that accompany the  agreement for operation of the shelter by Pets in Need approved by City Council in November 2018.  The medical  area upgrades and the modular office building are complete.  The new kennel addition has been submitted for  building permit. Project was placed on hold following receipt of Pets‐In‐Need's letter providing one‐year  notification of termination of the agreement between Pets‐In‐Need and the City. Public Works and Community  Service Department staff are reviewing the project as negotiations continue on a new agreement.    Automated External  Defibrillator  Replacement  (FD‐21000)  Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $0 $237,500 Fire Department Construction Summer 2022   Project Status:  This project replaces the entire complement of Automated External Defibrillators (AEDs)  throughout City facilities and emergency response vehicles, which currently totals 93 AEDs.  The RFP process was  completed in fall 2021 and the contract is currently underway.  The project will be complete by June 2022.    City Facilities  Assessment and  Record Plan  Management  System                (PE‐20002)        Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $314,800 Public Works Design Winter 2023  Project Status:  The Kitchell Report in 2008 summarized the last City‐wide facility condition assessment.  A new  facility condition assessment is warranted per the City’s APWA reaccreditation requirements.  All City facilities will  be assessed to bring current the “catch‐up” and “keep up” costs.  In addition, an electrification assessment will be  included to help the City reach its sustainability goals for 2030.  Staff is evaluating if the current asset management  system can be utilized to meet the needs of an Electronic Records Management System.  Staff is reviewing  proposals received in June 2021 and expects to award a contract in April 2022.     Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 2 of 8  City Hall Space  Planning  (PE‐19000)  $0 $682,900 Public Works Pre‐Design Fall 2024  Project Status:  This project involves space planning to determine future workgroup space needs and programming  for the City Hall office building.  The project will include preliminary design of the space following the initial  feasibility phase.    Civic Center  Electrical Upgrade  & EV Charger  Installation  (PE‐17010)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $415,754 $1,016,519 Public Works Construction Spring 2023  Project Status: This project installed EV chargers in existing downtown garages and will replace the aging Civic  Center electrical switchgear and motor control centers.  Five new dual head EV chargers were installed in the Civic  Center garage.  Two new dual head EV chargers were installed in the Bryant Street garage.  Six new dual head EV  chargers were installed at the Webster Street garage.  EV charger construction was completed in December 2021.  A contract was awarded in June 2021 for the design of the switchgear replacement and is currently underway.     Civic Center Fire  Life Safety  Upgrades   (PE‐18016)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $211,637 $642,681 Public Works Design Spring 2022  Project Status:  This project will assess, update, and replace the Civic Center fire alarm system.  The fire life safety  system is approaching the end of its useful life.  The fire alarm panel and associated equipment need an upgrade  to meet current code requirements.   The award of a design‐build contract was approved by Council in June 2021  and design is underway.  Plans are expected to be submitted for permit in early 2022.    Civic Center  Waterproofing   Study and Repairs  (PE‐15020)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $67,933 $721,546 Public Works Construction Winter 2022  Project Status:  This project includes a condition assessment of the Civic Center plaza deck structural system.  In  late 2016, RDH Building Science, Inc. was hired to investigate the problem.  The results indicated that the expansion  joint on the plaza can be repaired.  The scope expanded to include replacing the waterproof coatings on the inside  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 3 of 8  of the plaza perimeter planter boxes.  The Contract has been approved by Council and construction will begin in  early 2022.  Fire Station 4  Replacement  (PE‐18004)    Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $293,192 $10,167,779 Public Works Design Fall 2025  Project Status:  This project provides funding to replace Fire Station #4 at the corner of Middlefield Road and East  Meadow Drive.  The replacement facility will be based on the prior Replacement Study and Needs Assessment  prepared in 2005.  The consultant has been selected. However, the design contract was deferred due to budget  and staffing constraints and is anticipated to begin in spring 2022.    Extrication Tool  Replacement  (FD‐22000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $298,200 Fire Department Design Summer 2025  Project Status:  This project provides funding for the replacement of all extrication tools for the Fire Department.  Extrication tools, also known as "Jaws of Life", are used to rescue victims of car accidents and other emergencies  where the victims are trapped in confined spaces.    High and Bryant  Street Garages  Waterproofing and  Repairs   (PE‐18002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $264,235 $455,626 Public Works Completed  Fall 2021  Project Status:  This project includes a study for analysis and repairs to the water proofing system in the High  Street and Bryant Street parking garages.  Water proofing repairs have been completed in the High Street parking  garage.  Repairs per the original CIP were completed.  Additional funding was added for waterproofing repairs to  the subterranean stairwells.  The contractor completed waterproofing repairs in the subterranean stairwells in the  Bryant Street garage in fall 2021.    JMZ Renovation  (AC‐18001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,927,870 $4,474,903 Community Services Completed Fall  2021  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 4 of 8   Project Status:  This project provided for the relocation of the Junior Museum and Zoo to Cubberley for two years  while a new JMZ was being built, tenant improvements to the Cubberley Auditorium and then removal of tenant  improvements post‐construction.  Construction of the new Junior Museum and Zoo was completed in November  2021, and was opened to the public on November 12, 2021.  An additional federal grant associated with this CIP  funds a portion of the California Dinosaur Garden to be completed in spring 2024.    Library Automated  Material Handling  LB‐21000  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $44,715 $1,060,300 Library Design Winter 2023  Project Status:  This project is to provide the design and construction of three new Automated Material Handling  (AMH) Systems for the College Terrace, Children’s, and Downtown Libraries.  AMH systems efficiently sort  returned library materials based on the Radio Frequency Identification Devices (RFID) on the materials.  Design  work began in October 2021.    Municipal Service  Center A, B, & C  Roof Replacement  (PF‐17000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $105,457 $2,173,683 Public Works Construction Spring 2022  Project Status:  This project will replace the existing MSC roofs.  The existing asphalt and gravel roofs have reached  the end of their useful life and need to be replaced.  The new roofs will meet current cool roofing codes to optimize  energy efficiency.  Council approved a construction contract in June 2021 and construction is underway.  Cold and  wet weather has hampered the work, so the work has been extended through spring 2022.     Municipal Service  Center Lighting,  Mechanical, and  Electrical  Improvements  (PF‐16006)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $970,493 $8,001,422 Public Works Design Summer 2023  Project Status:  This project replaces original mechanical, electrical, and lighting systems installed in 1966.  It also  includes design and construction for office renovations for the Zero Waste group.  Bids for the site‐wide  mechanical and electrical upgrades exceeded the available budget.  Additional funding was added for FY 2020.  A  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 5 of 8  new contract with the design consultant is currently in negotiation.  Staff will prepare a design contract  amendment for Council’s approval in spring 2022.      New Downtown  Parking Garage  (PE‐15007)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,440,311 $6,991,903 Public Works Design  Spring 2024  Project Status: This project was intended to provide a new parking structure in the University Avenue commercial  area at existing Parking Lot D at the corner of Hamilton Avenue and Waverley Street.  The project received ARB  approval in July 2018.  In February 2019, the City Council certified the EIR by adopting the Resolution and  Mitigation Monitoring and Reporting Program.  The Record of Land Use Action was also approved.  As part of the  FY 2021 budget strategy, all Capital Improvement Fund funding has been removed and only the downtown parking  in‐lieu fee funding remains for this project.  In December 2021, Council directed staff to look at the feasibility of  partnering with a private entity to develop new parking using downtown in‐lieu parking fees in conjunction with  housing or other uses, including the use of City surface lots or privately held parcels.     New Public Safety  Building  (PE‐15001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $14,745,147 $ 117,037,811 Public Works Construction Summer 2023  Project Status: This project will provide a new, modern Public Safety Building (PSB) that will meet essential services  standards and the current and future needs of the public safety departments.  The PSB and new garage in the  California Avenue business district are now an integrated project and both are part of the 2014 Council  Infrastructure Plan.  Construction started in March 2021 and will continue through summer 2023.  The mat slab  concrete foundation in the excavation was placed in early December 2021.    Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $43,400 $470,600  Community Services Design Summer 2022  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 6 of 8  Performing Arts  Venues Seat  Replacement   (AC‐18000)  Project Status:  This project will replace all the seats in the Community and Children’s Theatres.  Staff has identified  a consultant to advise on ADA upgrade requirements that need to be completed with the seat replacement, in  assessing the costs and finalizing the scope of the project.  The contract for design has been awarded.  Cost  estimates and designs are anticipated to be complete by spring 2022.      Water, Gas,  Wastewater Office  Remodel  (PE‐19001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $157,186 $874,389 Public Works Design Fall 2022  Project Status:  This project incorporates renovations to the Utilities Water Gas Wastewater (WGW) office space  at the Municipal Service Center (MSC).  The current space no longer meets the operational needs of the  department.  This project will reconfigure the work area so it is more efficient for department operations and  replace aging furniture and finishes.  The new space will include a small reception area, a renovated kitchen and  printer area, additional offices and cubicles, upgrades to the HVAC system, lighting improvements and fire life  safety systems upgrade.  The project is currently in plan review and construction is anticipated to start in spring  2022.        Recurring Projects  Americans With  Disabilities Act  Compliance   (PF‐93009)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $124,143 $767,776 Public Works N/A Recurring  Project Status:  This project provides accessibility upgrades to City facilities and equipment.  It includes continued  funding for improvements such as path of travel, restrooms, drinking fountains, and counters.  An updated ADA  Transition Plan was adopted by Council in June 2021.  Staff set up Sharepoint for internal access to the ADA  Transition Plan in order to track and document the City’s progress.  Staff will be procuring new software in spring  2022 that will allow staff to identify and log new barriers, track grievances from the public, and update the ADA  Transition Plan Report.  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 7 of 8    Building Systems  Improvements   (PF‐01003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $40,213 $1,025,091 Public Works N/A Recurring  Project Status:  This project provides electrical, mechanical, plumbing, structural, and security upgrades for City  facilities.  This CIP was partially defunded because of COVID budget cuts.  The new cooling tower media replacement  originally scheduled for winter 2020 has been delayed until FY 2022.  A consultant has been selected to develop  design drawings for the replacement of the Utility Control Center generator.  A contractor has been selected for  the tennis courts lighting upgrade project.  Materials are on order and construction will start in March 2022.  New  boilers were installed for the Rinconada lap pool and kiddie pool.    City Facility  Parking Lot  Maintenance  (PE‐09003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $319,943 $235,000 Public Works N/A Recurring  Project Status:  This project maintains parking lots and walkways at City facilities.  No work has been performed at  City facility parking lots in the first half of FY 2022.    Cubberley Repairs  (CB‐17001)   Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $104,426 $343,347 Public Works N/A Recurring   Project Status:   This project is for general maintenance needs of the Cubberley campus.  Due to a staffing shortage,  no further work has been done in FY 2022. Staff is currently assessing water damage to the gymnasium following  crawlspace flooding in early 2022.  Cubberley Roof  Replacements  (CB‐16002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $58,657 $1,123,020 Public Works N/A Recurring  Project Status:  This project replaces existing roofs at Cubberley Community Center.  The contract to reroof Wings  F and FH has been awarded.  The Contractor is waiting for materials and good weather to start the job.  The project  to reroof Wing H was put out to bid in December 2021.  Buildings and Facilities Projects        Status as of December 2021  Buildings and Facilities Projects – Page 8 of 8    Facility Interior  Finishes  Replacement  (PF‐02022)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $51,273 $700,100 Public Works N/A Recurring  Project Status:  This project improves the interior finishes of City facilities, including flooring, walls, cabinets, paint,  lighting, ceiling tiles, soundproofing, and fixed office furniture, doors, windows, and associated fire/life safety,  mechanical, electrical and plumbing code compliance requirements.  Remodel of the City Auditor’s Office is taking  place to create more meeting spaces, transient staff desk stations, and a mother’s nursing room.    Police Video  Recording Systems  Replacement  (PD‐20000)  Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $48,482 $193,200 Police Department N/A Recurring  Project Status:  This project maintains the Palo Alto Police Department video recording systems used to record  events in the field with up to five in‐car cameras as well as body‐worn cameras (BWC).  In‐car units were added to  new vehicles as they came into service in FY 2022.  Roofing  Replacement   (PF‐00006)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $129,604 $713,294 Public Works N/A Recurring  Project Status: This project replaces existing roofs at City facilities that have outlived their useful lifespans.  The  roof replacement for the Ventura Community Center has been completed.  The Animal Shelter roof recoating has  been delayed due to roof modifications required for the current remodel of the facility.  Staff is working on the  design for the Peers Park Field House roof replacement.    University Avenue  Parking  Improvements  (PF‐14003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $22,265 $197,600 Public Works N/A Recurring  Project Status: This project maintains parking lots and parking structures within the University Avenue Downtown  Business Parking District.  With the completion of work on Parking Lot C in spring 2019, all University Avenue parking  district lots have been resurfaced and no additional work is planned at this time.    Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 1 of 6  One‐Time Projects  Boulware Park  Improvements  (PE‐17005)  Prior Years Actuals    Total Project Budget Implementing Department Project Phase Project Completion  $362,274 $4,083,101 Public Works Design Fall 2022  Project Status: This park renovation project was initially planned in FY 2018 but was postponed due to project priorities  and potential purchase of the adjacent AT&T lot located at 3350 Birch Street.  In fall 2019, the lot was purchased by  the City.  In response to the purchase, the City utilized the funding for the initial renovation project for preliminary  design and outreach for both the existing park and the newly purchased park land.  Additional funding was requested  as part of the FY 2021 CIP process to implement park renovations for the existing Boulware Park and the new park land.   In 2020, a Parks and Recreation Commission meeting and two community meetings were held to obtain input on  project design.  A Park Improvement Ordinance for the improvements was adopted by the City Council in October 2021.   Bidding and construction of the project is anticipated to start in summer 2022.    Byxbee Park  Completion  (PE‐18006)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $368,192 $3,249,335 Public Works Pre‐Design Spring 2025  Project Status: This project allows for the remaining improvements to Byxbee Park that follows the completion of the  landfill capping work.  The Baylands Comprehensive Conservation Plan (BCCP), which is currently undergoing CEQA  analysis, will include recommendations on the scope of the Byxbee Park project.  The BCCP and the conceptual plan for  Byxbee Park are anticipated to be completed in summer 2022.      Cameron Park  Improvements  (PG‐14002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $127,666 $236,419 Community Services Design Summer 2022  Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 2 of 6  Project Status: This project upgrades and renovates safety and accessibility features at Cameron Park with a primary  focus on the park playground.  The project is currently in the design and planning phase.  Community meetings were  held in May and July 2020 in addition to the Parks and Recreation Commission discussion in September 2020.  A park  improvement ordinance was approved by Council in February 2021.  The project will go out to bid in February 2022  and construction will start in summer 2022.    Cubberley Field  Restroom   (CB‐17002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $149,883 $455,367 Public Works Design Winter 2023  Project Status: This project will install a new restroom in the sports field area of the Cubberley Community Center.   Design for the project started in fall 2018 along with public outreach.  A community meeting was held, and the Parks  and Recreation Commission reviewed the project in November 2018.  The project design needs to be completed prior  to review by the Architectural Review Board.  Due to staffing constraints and other priorities, the restroom installation  is anticipated in winter 2023.      Foothills Nature  Preserve  Boronda Lake  Dock  Replacement  (OS‐18000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $230,700 Public Works Pre‐design Fall 2022  Project Status: This project replaces an aged and deteriorating Boronda Lake Dock located in the Foothills Nature  Preserve.  Due to staffing constraints, the design for this project is on hold until spring 2022.      Foothills Nature  Preserve Dam  Seepage  Investigation  and Repairs  (PE‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $32,400 Public Works Pre‐design Spring 2023  Project Status: This project will study a location of historic seepage from the Foothills Nature Preserve Dam at the  sharp bend in the road on the face of the dam.  The seepage is very minor, but it appears to be slowly worsening.  The  source of the seepage is suspected to be the trench backfill around the pipe that returns shallow groundwater to  Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 3 of 6  Boronda Lake.  This project will locate and investigate the pipe and trench backfill material.  Due to staffing constraints  and other priorities, this project has been moved to FY 2023.    Magical Bridge  Playground  Rubber and  Synthetic Turf  Resurfacing  (PE‐21003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,078 $891,600 Community Services Construction Summer 2022  Project Status: This project will replace rubberized and synthetic turf surfacing in the playground and will repair or  replace play equipment including swings, climbing net, and playhouse.  An IFB was issued  in November 2021 and staff  anticipates the construction contract to be awarded by Council in early 2022.    Ramos Park  Improvements   (PG‐14000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $210,412 $227,772 Community Services Design Summer 2022  Project Status: This project includes safety and accessibility improvements at Ramos Park.  The work includes replacing  the existing park playground, benches, drinking fountains, and resurfacing the basketball court playing surface.  A Park  Improvement Ordinance (PIO) for these improvements went to the Parks and Recreation Commission in December  2020.  Council approved the PIO in spring 2021 and construction is planned for summer 2022.    Rinconada Park  Improvements  (PE‐08001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,517,819 $8,830,594 Public Works Construction Spring 2025  Project Status: This project provides upgrades to safety, site amenities, playground facilities, a new restroom, irrigation,  drainage, and ADA accessibility improvements at Rinconada Park.  These improvements were identified in the  Rinconada Long Range Plan (LRP).  Council awarded a contract for Phase 1 of construction in June 2021 which  started  in August 2021. Phase 1 is anticipated to be complete in winter 2022.  Phase 2 of the project will include improvements  to the eastern half of the park by FY 2025 including pathway improvements, new restroom, ADA upgrades, planting,  irrigation, lighting, and site furnishings.  According to the LRP, future improvement phases would include renovations  to the eastern side of the park, arbor and pool areas, and development around the electrical substation.    Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 4 of 6  Recurring Projects  Art in Public  Spaces  (AC‐86017)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $138,347 $1,508,784 Community Services N/A Recurring  Project Status: This project provides the ongoing temporary and permanent artworks throughout the City.  The FY  2022 budget funded temporary public artwork at the Public Safety Building construction site, the Code: ART festival  in October, the completion of the Highway 101 Bike and Pedestrian Bridge artwork, the initiation of the Artist  Residency, and the completion of artwork at the Junior Museum and Zoo and Art Lift microgrant projects throughout  the City .  Projects in process include artworks for King Plaza via the King Artist Residency, artwork for the Charleston‐ Arastradero Corridor, and temporary/permanent artworks at the Public Safety Building.     Athletic Courts  Resurfacing   (PG‐06001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $13,170 $138,840 Community Services N/A Recurring  Project Status: This project repairs and resurfaces tennis and basketball courts in various Palo Alto parks.  In spring  2021, the Cubberley Community Center and Peers Park tennis court project went out to bid.  Construction is  expected to start in spring 2022.    Benches, Signage,  Walkways,  Perimeter  Landscaping   (PG‐06003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $195,411 $191,000 Community Services N/A Recurring  Project Status: This project restores and replaces existing benches, signage, fencing, walkways, and landscaping at  various City facilities. In fall 2021, a new entry sign was built and installed for Foothills Nature Preserve, new surfacing  at Peers dog park was installed with engineered wood fiber, and Lytton Plaza had site amenities replaced.    Dog Park  Installation and  Renovation   (PG‐18001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $100 $163,400 Community Services N/A Recurring   Project Status: This project enables the construction of dog parks at various City parks and facilities that currently  do not have dog parks, as well as renovating existing dog parks.  The next dog park installation or renovation has not  Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 5 of 6  been determined as several locations are under consideration.  Staff is meeting with the Parks and Recreation  Commission to discuss location options and expansion of existing dog parks at Greer Park and Mitchell Park.    Off‐Road Pathway  Resurfacing and  Repair   (OS‐09001)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $55,739 $142,500 Public Works N/A Recurring  Project Status: This project resurfaces failing and broken pathways within the City.  Pathways are chosen based on  inspections and resident requests.  The Adobe Creek Reach Trail construction was completed with the Highway 101  Pedestrian and Bicycle Overcrossing Project in November 2021.  A pedestrian pathway through Hoover Park was  replaced in December 2021.     Open Space Lakes  and Pond  Maintenance   (OS‐00002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $31,150 $62,600 Community Services N/A Recurring  Project Status: This project rehabilitates lakes and ponds in open space nature preserves to protect wildlife habitat  and recreational safety and to meet State Division of Safety of Dams requirements.  A new three‐year maintenance  contract was awarded and the first pond servicing with removal of aquatic vegetation was completed in fall 2021.    Open Space Trails  and Amenities   (OS‐00001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $513,143 $232,000 Community Services N/A Recurring  Project Status: This project restores unpaved trails, fences, picnic areas, and campgrounds at Foothills, Baylands,  and Pearson‐Arastradero Nature Preserves.  In fall 2021, a new three‐year trail maintenance contract was awarded  and service of various open space trails throughout Foothills Nature Preserve and Pearson Arastradero Preserve was  completed in November 2021.    Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $202,069 $188,500 Community Services N/A Recurring  Parks and Open Space Projects         Status as of December 2021    Parks and Open Space Projects – Page 6 of 6  Parks and Open  Space Emergency  Repairs   (PG‐09002)  Project Status: This project replaces or repairs playgrounds, play yard surfaces, wooden structures, park amenities,  and play equipment in the event of storms, fire, vandalism or structural failure.  In summer 2021, repair of fencing  was completed a the Cubberley Community Center tennis courts.  Repair to damaged fencing caused by a fallen tree  at the Palo Alto Bowling green was completed in October 2021.    Park Restroom  Installation  (PG‐19000)  Prior Years Actuals Current Year Budget Implementing Department Project Phase Project Completion  $16,962 $456,839 Community Services N/A Recurring  Project Status: This project installs new restrooms at City parks that currently do not have restroom facilities.  The  restrooms may be prefabricated. A Park Improvement Ordinance (PIO) for adding a new restroom at Ramos Park  was reviewed and recommended for Council approval by the Parks and Recreation Commission in December 2020.   Council approved the PIO in March 2021.  The restroom design needs to be completed prior to being reviewed by  the Architectural Review Board.  Due to staffing constraints and other priorities, the restroom installation is  anticipated in spring 2023.        Streets and Sidewalks Projects         Status as of December 2021    Streets and Sidewalks Projects – Page 1 of 4    One‐Time Projects  California Avenue  District Gateway  Signs   (PE‐17004)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $20,162 $150,488 Public Works Design Summer 2022  Project Status: This project includes the design and replacement of two existing gateway signs for the California  Avenue business district.  Public outreach was completed in winter 2021.  The signs are expected to be replaced in  summer 2022.    Newell Road  San  Francisquito  Creek Bridge   Replacement  (PE‐12011)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,723,995 $18,227,483 Public Works Design Spring 2024  Project Status: This project removes and replaces the Newell Road bridge over San Francisquito Creek with a clear  span to allow the channel to convey up to the natural capacity of the San Francisquito Creek, approximately 7,500  cubic feet per second, and improved safety for vehicular, bicycle, and pedestrian traffic.  The project is being closely  coordinated with the City of East Palo Alto, Santa Clara Valley Water District, and the San Francisquito Creek Joint  Powers Authority (JPA).  The design consultant amendment and cooperative agreement with the City of East Palo  Alto were approved by Council in June 2021. Work to advance the design and prepare regulatory permit applications  began in summer 2021. The Bridge Type Selection Report was submitted to Caltrans in September 2021. The City had  meetings with Caltrans to discuss and respond to their comments and to resubmit the revised report. Staff anticipates  an approval memo from Caltrans in February 2022. Staff will bring forward an amendment to the funding agreement  with Santa Clara Valley Water District in spring 2022.         Recurring Projects  City Bridge  Improvements  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $9,746 $149,030 Public Works N/A Recurring  Streets and Sidewalks Projects         Status as of December 2021    Streets and Sidewalks Projects – Page 2 of 4    (PE‐20001) Project Status: This project includes bridge inspections, maintenance, repair, and an improvement program over the  next five years. This program will include on‐going inspections to report physical changes to the structures,  recommendations for work to be done, and additional information to meet functional and structural standards in  accordance with industry standards.  Staff hired an on‐call structural engineering firm to assist with the bridge  inspection and repair program.  Staff prioritized twenty‐five bridge and culvert structures for assessment in fall 2021,  and inspections are tentatively scheduled in winter 2022.      Curb and Gutter   Repairs  (PO‐12001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $339,713 $133,200 Public Works N/A Recurring  Project Status: This project repairs curbs and gutters uplifted by tree roots. The FY 2021 Street Maintenance Project   completed 1,380 linear feet of three foot wide valley gutter as part of this project in summer 2021. All remaining curb  and gutter work included in this project will be completed in early 2022.    San Francisquito  Creek Joint  Powers  Authority  Ongoing Creek  Projects  (PE‐22000)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $61,000 Public Works N/A Recurring  Project Status: This project provides funding for studies and completion of the design for the San Francisquito Creek  Joint Powers Authority (JPA) upstream project including channel widening and Continuing Authority Program Section  205 (CAP 205) study. Completion of the CAP 205 study will make the channel widening components eligible for federal  funding and will help fund the construction of the upstream project and address elements of the JPA’s comprehensive  flood management program.    Sidewalk Repairs  (PO‐89003)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $947,768 $622,599 Public Works N/A Recurring  Project Status: This project repairs and replaces broken and uplifted sidewalks.  The program completed all twenty‐ three sidewalk districts in 2017, a thirty‐year (1986–2017) sidewalk repair district cycle.  Council approved a sidewalk  assessment contract in November 2017 to evaluate the sidewalk program and assess potential improvements to the  Streets and Sidewalks Projects         Status as of December 2021    Streets and Sidewalks Projects – Page 3 of 4    current district‐based program.  Staff used this assessment to compile a list of areas that require prompt action at  varying locations throughout Palo Alto.  These priority locations were repaired in FY 2020. Funding was reduced in FY  2022 as part of the FY 2022 Capital Improvement Program budget strategy.  Remaining funding will be used to  perform emergency maintenance and spot repairs.  There were no new sidewalk repairs performed FY 2022.    Sign Reflectivity   Upgrade  (PO‐11000)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $31,358 $69,800 Public Works N/A Recurring  Project Status: This project includes the annual inventorying, upgrading and maintaining of all traffic signs.  A list of  signs not meeting the minimum requirement is derived from MUTCD approved Nighttime Visual Inspection surveys.   Due to Covid‐19 and understaffing, there were no new signs identified for reflectivity replacement in the first half of  FY 2022.    Street Lights   Improvements  (PO‐05054)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $183,186 $112,400 Public Works N/A Recurring  Project Status: This project replaces streetlights, including poles, pole foundations, luminaires and wiring as needed  to restore or improve street lighting.  There were seven knockdown locations, including three with substructure  repairs completed in the first half of FY 2022.    Street  Maintenance  (PE‐86070)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $8,556,531 $2,804,686 Public Works N/A Recurring  Project Status: This project includes the annual resurfacing, micro‐seal, crack seal, and reconstruction of various city  streets.  This project funds the street maintenance work that supports Council’s adopted goal of achieving a citywide  average pavement condition index (PCI) score of 85, representing very good or excellent conditions, by 2019.  The  citywide PCI goal of 85 was met at the end of calendar year 2018, and the emphasis has been shifted to maintaining  the 85 score while addressing the remaining streets with PCI scores less than 60.  The FY 2021 Streets Preventive  Maintenance Project was completed in September 2021 and applied a slurry seal treatment to 14.4 lane miles of city  Streets and Sidewalks Projects         Status as of December 2021    Streets and Sidewalks Projects – Page 4 of 4    roads, repaired 61,000 SF of pavement base repairs, and applied 121,100 linear feet of crack sealing. The FY 2021  Street Resurfacing Project is still in construction.  When the project is completed in early 2022, the project will have  repaved 5.82 lane‐miles of arterial and residential streets with PCI’s averaging 44. This will help maintain and improve  the City’s Pavement Condition Index (PCI) beyond its average of 83 and will address many streets whose PCI scores  fall below the City’s minimum goal of 60. The FY 2022 Street Resurfacing Project is currently out to bid and is expected  to start construction in spring 2022. Due to the FY 2021 Capital Improvement Program budget strategy, street  resurfacing projects will have reduced scope, resulting in less lane miles of roadways being resurfaced through FY  2023.    Thermoplastic  Lane Marking  and Striping  (PO‐11001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $101,800 Public Works N/A Recurring  Project Status: This project maintains the thermoplastic markings on roadways.  Thermoplastic lane marking and  striping is incorporated into annual Pavement Preventive Maintenance Projects.  As a part of the FY 2021 Streets  Preventive Maintenance Project, 45,000 linear feet of thermoplastic striping and 647 thermoplastic legends were  installed between CIP PE‐86070 and PO‐11001.             Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 1 of 6   One‐Time Projects  Charleston  Arastradero  Corridor Project  (PE‐13011)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $13,136,360 $20,788,951 Public Works Construction Fall 2022  Project Status: This project is part of the 2014 Council Infrastructure Plan.  It will reconfigure the Charleston  Arastradero Corridor to provide new landscaped median islands, bulb outs, enhanced bike lanes, traffic signal  improvements, and new street trees to complement the new lane configurations that were approved for  permanent retention.  Phase 1 (Arastradero Road between Foothill Expressway to Clemo Avenue) and Phase 2  (Charleston Road from Alma Street to Middlefield Road) were completed in 2020. Phase 3 (Arastradero Road from  Los Palos Avenue to El Camino Real, Charleston Road from El Camino Real to Alma Street and from Middlefield Road  to San Antonio Road) was approved by Council in June 2021.  Temporary improvements were installed in August  2021 to let corridor users and residents test drive the planned street changes.   Construction began in September  2021 with tree trimming and tree removals. New curb extensions, curb ramps, sidewalks, and curb and gutter were  constructed at Grove Avenue, Charleston Court, Los Palos Avenue, Suzanne Drive, McKellar Lane, Ruthelma Avenue,  Park Boulevard, Alta Mesa Avenue, and Clemo Avenue. New storm drain pipes, catch basins, and manholes were  installed at Suzanne Drive, east of El Camino, Park Boulevard, Charleston Court, and Sutherland Drive. Potholing for  new traffic signal poles was completed at the Louis Road/Montrose Avenue intersection and is in progress at Wilkie  Way and Fabian Way intersections.    Churchill Avenue  Enhanced  Bikeway  (PL‐14000)  Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $315,398 $4,040,908 Office of Transportation Design Fall 2023  Project Status: This project includes planning, design and construction of a shared‐use path along the north side of  Churchill Avenue between the existing shared‐use path at Castilleja Avenue and the Stanford Perimeter Trail.  It also  includes intersection improvements at Churchill Avenue and El Camino Real, which will include a new dedicated  westbound right‐turn lane.  The project is anticipated to gain PAUSD approval and will go out to bid in summer 2022.   Construction is anticipated to be completed by fall 2023.     Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 2 of 6  Churchill Avenue  Alma Street  Railroad Crossing  Safety  Improvements  (PL‐20000)  Prior Years Actuals  Total Project Budget Implementing Department Project Phase Project Completion  $110,152 $5,099,300 Office of Transportation Design Summer 2023  Project Status: This project is a railroad crossing improvement project to enhance safety at the intersection of  Churchill Avenue and Alma Street.  This crossing was identified for possible funding for hazard elimination and safety  improvements through the Federal Section 130 funds.  Design includes traffic signal modifications, street lighting  improvements, roadway resurfacing, sidewalk realignment and/or widening, drainage improvements, utility  relocations, signage, and striping.  Council approved the concept plan in May 2021 after community outreach.  Staff  is currently working with Caltrain, Caltrans, and California Public Utilities Commission for final plan development and  approvals. The design plans reached completion in fall 2021.  Staff is preparing bid documents for construction to be  released in spring 2022.  Construction is anticipated to begin in summer 2022.     Downtown  Automated  Parking   Guidance  Systems, Access  Controls &   Revenue  Collection  Equipment  (PL‐15002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $198,350 $2,579,860 Office of Transportation Design Winter 2023  Project Status:  This project includes design and installation of new downtown parking guidance systems, access  controls and revenue collection equipment that will be coordinated with both the Downtown Parking Wayfinding,  PL‐15004 project and the 2016 Downtown Parking Management.  Staff contracted with Dixon Resources for  additional management support in design and procurement for the system installation in the Downtown garages on  University Avenue.  In fall 2020, staff released a design‐build RFP for a camera‐based parking guidance system  similarly installed at the new California Avenue Parking Garage.  Council awarded the design‐build contract in August  2021, however, the City rescinded its notice to award due to insufficient bonding by the contractor.  In winter 2022,  staff will issue a new design‐build RFP.     Emergency  Vehicle Traffic  Signal  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $486,422 $686,322  Fire Department Construction Summer 2022  Project Status:  This project will purchase and implement an emergency vehicle preemption system pilot project.  The system will integrate with the City’s current traffic signal management system and with the City’s computer‐ Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 3 of 6  Preemption  System Pilot   (PL‐19000)  aided emergency response dispatch system to provide safer and quicker response times for emergency vehicles.   This project is a pilot on 25 intersections.  The traffic signal controls software were updated in in spring 2020 and  staff is working with our CAD and Signal System vendors to integrate the two systems for communication across the  two platforms.  Purchasing is drafting the contract for the plug‐in software and staff expects the project will be  complete by June 2022.     Highway 101  Pedestrian  Bicycle Overpass  Project  (PE‐11011)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $18,468,438 $22,898,724 Public Works Completed Fall 2021  Project Status:  This project, part of the 2014 Council Infrastructure Plan, includes the design and construction of a  new pedestrian bridge across Highway 101 at Adobe Creek. Council approved a contract with Granite Construction  in November 2019.  Construction began in January 2020.  The project construction completed in November 2021  with a ribbon‐cutting ceremony and a community celebration on November 20, 2021.     Quarry Road  Improvements  and   Transit Center  Access   (PL‐16000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,282,050 $3,130,759 Office of Transportation Pre‐Design Fall 2024  Project Status:  This project includes the planning, design, and construction of bicycle, pedestrian, and transit access  improvements along Quarry Road between El Camino Real and Welch Road, including, but not limited to, upgraded  bicycle lanes and crosswalks, innovative intersection treatments for bicyclists, improved access to transit stops,  roadway improvements for transit access, and signal modification.  Planning, design, and construction of bicycle  lanes and pedestrian improvements between the Palo Alto Transit Center bus depot and the intersection of Quarry  Road and El Camino Real, and between El Camino Real and Welch Road have been completed.  The next phase of  the project will provide the transit access from Quarry Road to the Transit Center.  Currently, the City is working with  Stanford on evaluating the land ownership and entitlements before proceeding with design of such improvements.    Railroad Grade  Separation and  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $3,771,788 $15,883,876 Office of Transportation Pre‐Design Fall 2025  Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 4 of 6  Safety  Improvements  (PL‐17001)  Project Status: This project is a community‐based process to advance the railroad grade crossing circulation study  and context sensitive solutions study envisioned by the City Council.  It will also fund the preparation of a Project  Study Report and environmental analysis that will be required for the City to realize its goals of advancing grade  separations.  This capital project provides funds to perform preliminary engineering design, conduct project related  studies, and to prepare environmental documents for the project.  The consultant in collaboration with the  community prepared several conceptual plans for grade separations.  In 2019, City Council established the Expanded  Community Advisory Panel (XCAP) for reviewing the selected nine alternatives at the three crossing locations  (Churchill Avenue, Meadow Drive and Charleston Road) to provide recommendation to the City Council.  XCAP  delivered its final report to Council in March and April 2021.  In early 2021, Council performed the review of the  alternatives under consideration and eliminated the two south Palo Alto Tunnel Alternatives. Later in the year, upon  further review, Council eliminated viaduct alternatives from further consideration for all three crossing locations. In  addition, Council selected the partial underpass alternatives as preferred alternative for Churchill Avenue crossing.  The Churchill Closure with mitigations was recommended as an alternative.  Council directed staff to perform  additional studies to review geotechnical conditions, refine the underpass/partial underpass alternatives, and to  reconvene the Rail Committee and discuss the financial considerations in 2022.                        Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 5 of 6  Recurring Projects  Bicycle and  Pedestrian  Transportation Plan  Implementation  (PL‐04010)                  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $9,435,106 $15,276,377 Office of Transportation N/A Recurring  Project Status: The Neighborhood Traffic Safety and Bicycle Boulevards Phase 1 Project along Amarillo  Avenue/Moreno Avenue and Ross Road was completed in November 2018.  Conceptual plans for the  Neighborhood Traffic Safety and Bicycle Boulevards Phase 2 Project along Bryant Street, Maybell Avenue, Stanford  Avenue, Park Boulevard, and Wilkie Way were adopted by City Council in 2015.  Currently, Phase 2 is on hold at  75% design until a community engagement process is identified.   Safe Routes to  School  (PL‐00026)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $70,370 $1,141,128 Office of Transportation N/A Recurring  Project Status: This project enables the City’s Safe Routes to School program, including school commute planning,  encouragement activities, and capital improvements along local and collector streets that may be impacted by  school commute activities.  The capital improvements include traffic calming devices, enhanced crosswalks, and  improved signage along suggested safe routes to school.  In FY 2021 and early FY 2022, the installation of school  zone speed limit signage was completed.  The community engagement and planning process for the construction  of the South Palo Alto Bikeways project began in FY 2021.  The project will implement buffered or protected bike  lanes on East Meadow Drive from Alma to Fabian Way, Fabian Way from East Meadow Drive to East Charleston  Road, and widen and repave the Waverley Avenue Bike Path between East Meadow Drive and Charleston Road  were completed.  Construction is expected to start in early 2023.    Traffic Signal and  Intelligent  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $227,010 $980,450 Office of Transportation N/A Recurring  Traffic and Transportation Projects        Status as of December 2021  Traffic and Transportation Projects – Page 6 of 6  Transportation  Systems  (PL‐05030)   Project Status: This project includes design and construction of traffic signals, traffic signal communications  networks, detection, and data projects for transportation use, and maintenance of the City’s traffic signal central  management system.  The project includes the replacement of traffic signal controllers/cabinets, video detection  systems, accessible pedestrian buttons, and related field equipment.  The new controllers enable additional traffic  signal timing strategies and improve the reliability of the City's traffic signals.  Design for traffic signal safety and  operational improvements at the intersection of San Antonio Road and Charleston Road is currently in progress.   The design is 65% complete.  Staff is working on the final plans and will be preparing bid documents for  construction to be released in fall 2022.  Construction is anticipated to begin in late 2022.   Transportation and  Parking  Improvements   (PL‐12000)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $62,198 $585,400 Office of Transportation N/A Recurring  Project Status:  This project implements miscellaneous neighborhood traffic calming improvements including  neighborhood traffic studies and parking improvements.  This project also funds the development of grant  proposals used to procure funding for future projects.  Projects currently in progress include the Crescent Park  neighborhood traffic calming pilot.  The conceptual plan for the traffic calming pilot project in the Crescent Park  neighborhood was approved by Council in November 2020.  Traffic calming elements were placed in summer 2021  for a one‐year trial period.        Airport Projects  Status as of December 2021    Airport Projects – Page 1 of 2  One‐Time Projects  Airport Apron  Reconstruction  (AP‐16000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $26,992,534 $41,996,212 Public Works Construction Spring 2022  Project Status:  This project includes the design and reconstruction of the Palo Alto Airport apron and is being  implemented in multiple phases.  The pavement surfaces at the airport are failing and uneven.  The need to  reconstruct the aircraft parking apron is critical to airport safety.  Construction Phase I was completed in November  2017.  Construction Phase II was completed in winter 2020. Construction on Phase III began in November 2020 and  the project is 80% complete.  The project is expected to be completed in spring 2022.    Airport Layout  Plan  (AP‐21000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0  $741,500 Public Works Design Summer 2024  Project Status:  This project provides updates to the Airport Layout Plan (ALP), including a narrative report and  environmental study.   The Airport received funding for a Phase I portion of this project in fall 2020. Phase I is  approximately 50% complete, and it is anticipated that funding for Phase II will be received in spring 2022.  The  project is expected to be completed in summer 2024.  Airport  Temporary  Office  Buildings  AP‐22001  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0  $181,000 Public Works Design Winter 2022  Project Status:  This project provides funding for the installation and Furniture, Fixtures, & Equipment (FF&E) of  existing temporary modular buildings at the airport to provide adequate office space for airport staff as well as  terminal space for the public.  This project is in the permitting phase, with construction planned to be completed  in winter 2022.     Automated  Weather  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0  $607,700 Public Works Design Summer 2024  Airport Projects  Status as of December 2021    Airport Projects – Page 2 of 2  Observation  System  (AWOS)  AP‐19000  Project Status:  This project provides a new weather information system to be installed at the Palo Alto Airport.   The Airport has applied for FAA funding, and is waiting for the grant agreement to start design.         Recurring Projects    2022‐2026 – Airport Capital Improvements Program Projects: There are no recurring projects scheduled at this time.   Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 1 of 9  One‐Time Projects  115 kV Electric  Intertie   (EL‐06001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $578,055 $6,990,040 Utilities Pre‐Design Summer 2027  Project Status: This project will perform a technical feasibility study to determine the general project requirements  to establish a 115 kV electric intertie line and construct a 115/60 kV substation to connect the City's electric system  directly to the 15kV transmission line at an additional location.          Capacitor Bank  Installation   (EL‐16002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $482,872 $1,050,443 Utilities Construction Fall 2022  Project Status: This project installs capacitor banks at electric substations and on distribution lines to ensure  Northern California Power Association Power Factor requirements are met.  Staff has performed an analysis of  where capacitors are needed to provide VAR support to enhance the voltage regulation and stability of the system.   Capacitor banks will be installed at Hanover Avenue, Hansen Way, Maybell Avenue, and Park Boulevard  Substations.  Engineering has completed the design and procurement of materials for the project and is currently  75% complete with the construction and installation phase.  The Hansen Way and Park Boulevard projects are  complete. Hanover Avenue is waiting on the arrival of two new switches and will be energized by summer 2022.  The Maybell Avenue project will begin in early spring 2022. The project is expected to be completed by fall 2022.  Coleridge  Cowper  Tennyson   4/12kV  Conversion   (EL‐14000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $180,813 $2,661,878 Utilities Design Summer 2022  Project Status: This project converts the primary electric distribution system in the Coleridge Avenue, Cowper  Street, Tennyson Avenue area from 4 kV to 12 kV.  This project is a precursor to work being planned for the  Colorado Street and Hopkins Avenue Substations.  Design is at 90% completion and is delayed due to COVID‐19  restrictions.  Construction of this project was deferred to maintain zero rate increases to ease economic recovery  because of COVID‐19.     Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 2 of 9  Colorado  Distribution  Feeder Outlet  Replacement  (EL‐22002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $400,000 Utilities Design Summer 2022  Project Status: This project is for the installation of a new underground duct bank and cable at Colorado Substation.   The installation will improve reliability for all Colorado circuits. The design is in progress and the construction will  begin only after a new substructure contract has been approved by Council.     Colorado Power  Station  Equipment  Upgrades  (EL‐19001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $4,282,025 $10,865,445 Utilities Pre‐Design Fall 2025  Project Status: Staff is evaluating the need to replace the COP‐3 115 kV/60 kV transformer bank at Colorado  Substation.  Future project completion dates will be based on the outcome of this evaluation.    Colorado  Substation Site  Improvements  (EL‐19002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $183,204 $1,306,071 Utilities Design Fall 2023  Project Status: This project will make modifications to the substation driveways and fence to provide adequate  ingress and egress for utility vehicles used for maintenance and repair.    Staff is preparing an overall master plan  for Colorado Substation to include all proposed improvements.  Preliminary designs for lighting, driveway, fences,  and an oil containment improvement have been prepared.  All the proposed improvements are coordinated, to  ensure a cohesive design and plan for construction.      East Meadow  Circles 4/12kV  Conversion   (EL‐17001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $53,072 $1,838,701 Utilities Design Spring 2024  Project Status: This project converts the primary electric distribution system in the East Charleston/Alma  Street/East Meadow Drive/Middlefield Road area from 4 kV to 12 kV and is challenging because of the  configuration of the streets and rear easement facilities. This project has been split into six design and construction  phases. Engineering has completed the substructure design for Phase 1 and will proceed with the substructure  design for Phase 2. Construction for Phases 1 and 2 will be completed by spring 2022.  All six phases are targeted  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 3 of 9  to be completed by spring 2024. Construction for this project was deferred to maintain zero rate increases to ease  economic recovery because of COVID‐19. Phase 1 substructure construction is completed. Phase 1 and 2 electrical  design is in progress.     Facility  Relocation for  Caltrain  Modernization   Project  (EL‐17007)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,399,789 $3,055,472 Utilities Construction Spring 2022  Project Status: The Utilities Department received approval from Caltrain to continue removal of the overhead lines  in October 2018.  The installation of the Overhead Catenary System above the rails to power the trains will cause  conflicts with the City's overhead electric and communication lines, as well as those owned by others, including  AT&T and Comcast, which cross the railroad tracks.  This project is in its last phase and expected to be completed  in 2022.   Foothills Rebuild  (Fire Mitigation)  (EL‐21001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $185,384 $4,000,000 Utilities Design Fall 2025  Project Status: This project will rebuild the approximately 11 miles of overhead line in Foothills Park, as necessary  to mitigate the possibility of wildfire due to overhead electric lines. This could include the utilization of more robust  equipment or construction practices, rerouting to avoid vegetation and improve access for inspection and  maintenance, or converting the overhead lines to underground where feasible.  Two proposals were received for  this project and both proposals were rejected because they did not provide an option to underground existing  overhead electric lines.  Staff is currently looking at different options to complete this work. Staff completed 7,000  feet of substructure work which will eliminate 26 poles as a pilot project in 2021.   Hopkins  Substation 4/12  kV Conversion  (EL‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $2,010,000 Utilities Design Fall 2025  Project Status: This project will convert the distribution system connected to the Hopkins Substation from 4 kV to  12 kV.  The future conversion of the Hopkins Substation from 4 kV to 12 kV requires that all the areas currently  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 4 of 9  served at 4 kV from the Hopkins Substation be converted to 12 kV. This project will improve operating flexibility of  the system, service reliability, and back‐up to customers in downtown and other adjacent areas.    Inter‐Substation  Line Protection  Relay  (EL‐17005)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $366,351 $821,030 Utilities Construction Summer 2022  Project Status: This project replaces the existing HCB pilot wire relays with a new microprocessor line differential  protective relay to protect the city’s 60 kV sub‐transmission line sections and equipment from damage due to  faults (i.e. short circuits) on the 60 kV line sections.  This project is being done in phases, with design and  construction happening concurrently on the different phases.  Construction of these improvements relies on work  completed by other projects to install fiber optic connections.  Staff is working on the design for the replacement  of relays at Park Substation and Switching Station and between line sections COP‐PB, COP‐AC and COP‐HO.    Rebuild  Underground  District 15   (EL‐11003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $43,348 $1,293,337 Utilities Design Fall 2022  Project Status: This project rebuilds and replaces the underground electric system in Underground District 15, the  area bounded by Los Palos Avenue, Glenbrook Drive, Pomona Avenue, and Arastradero Road. This project is in the  preliminary stages of engineering design and work will be coordinated with EL‐16000 which is currently rebuilding  the electric system along Arastradero Road.  Work on this project was delayed due to public input regarding the  design of the project.  Changes to the Rules and Regulations will require property owners to pay for the differential  cost should they want submersible equipment instead of pad mount.  Design of the project is delayed as staff  prepares cost information to present to affected property owners showing how much they will have to pay.      Rebuild  Underground  District 16   (EL‐13003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $27,456 $735,335 Utilities Design Spring 2022  Project Status: This project rebuilds and replaces the underground electric system in Underground District 16, the  area along Louis Road between Greer Street and Loma Verde Avenue.  The project design and cost estimate are  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 5 of 9  nearly complete, and this project will be bundled with other similar type jobs for bidding to obtain more favorable  pricing.  Construction of this project is deferred to maintain zero rate increases to ease economic recovery because  of COVID‐19.    Rebuild  Underground  District 24   (EL‐10006)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,945,085 $2,525,338 Utilities Construction Spring 2022  Project Status: This project rebuilds and replaces the underground electric system in Underground District 24, the  area bounded by Lytton Avenue; Bryant Street; Forest Avenue; and Alma Street.   This project is projected to be  completed in 2022.    Rebuild  Underground  District 26   (EL‐16000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $30,810 $312,447 Utilities Design  Spring 2025  Project Status: This project rebuilds and replaces the underground electric system in Underground District 26, the  area along Arastradero Road between El Camino Real and Hillview Avenue.   This is a four‐phase project.  The first  phase design is complete, and construction will begin in 2022.    Reconfigure  Quarry Feeders  (EL‐14005)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $519,836 $792,034 Utilities Completed Fall 2021  Project Status: This project reconfigures how distribution circuits are connected to each substation transformer  at Quarry Substation.  While phases of this project have been completed in construction, other phases still need  to be designed and constructed. Design of QR 27 feeder replacement was completed in spring 2021.  Construction was completed in December 2021.  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $970,478 $17,674,003 Utilities Design Fall 2024  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 6 of 9  Smart Grid  Technology  Installation  (EL‐11014)  Project Status: Council approved the Advanced Metering Infrastructure (AMI) with Sensus on October 18, 2021.   The project includes replacement of 30,000 electric meters and retrofit of 20,800 water and 24,200 gas meters  with radio endpoints to transmit meter data to the AMI network.  The proof of concept phase including AMI  network installation, meter testing, and system integration will occur between January 2022 and June 2023. Full  deployment is anticipated to run from July 2023 through December 2024.      Substation 60kV  Breaker  Replacement   (EL‐17002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,355,718 $6,062,637 Utilities Design Summer 2027  Project Status: This project replaces high voltage circuit breakers that interconnect the nine electric substations  and two power switching stations that are reaching the end of their useful life and are now underrated for their  use.  This project is being done in phases, with design and construction happening concurrently on the different  phases.  Four breakers were replaced recently while anticipating the multi‐year contract procurement method.   Staff completed the construction on the first phase and is working to procure a multi‐year contract with a  contractor to complete the design and replacement of the remaining breakers.    Substation  Physical Security   (EL‐16003)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $974,914 $3,200,190 Utilities Construction Winter 2025  Project Status: This project installs facilities providing physical protection of electric substations from vandalism  and intrusion.  A professional services contract was awarded to Burns & McDonnell and the study was completed.  Staff continues to implement recommendations from the study each fiscal year.  Procurement for improvements  at Hanover Avenue were completed in 2021.   Hansen Way improvements are in process.  CPAU intends to go out  to bid for a wide‐scale 9 electric substation security camera and lighting upgrade in 2022, with construction  occurring in 2023.     Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,568,077 $3,904,425 Utilities Completed Fall 2021  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 7 of 9  Underground  District 46   Charleston  El Camino Real   (EL‐12001)  Project Status: This project undergrounds the existing overhead utility systems in the area along the 400 block of  West Charleston and El Camino Real.  Underground substructures have been installed.    Staff has completed 100%  of cable and equipment installation and 100% of customer service conversions. A construction contract was  awarded for the final phase of the project to install two 60 foot tall steel poles and to reconductor the 60 kV sub‐ transmission lines and the project was completed in the fall 2021.        Recurring Projects  Communications  System  Improvements   (EL‐89031)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $14 $170,000 Utilities N/A Recurring  Project Status: This project installs high frequency coaxial cable, fiber optic cable, and related equipment to  provide communications services for traffic signal coordination, telephone links, computer data transmission, and  the Electric Supervisory Control and Data Acquisition (SCADA) system.  This project is funding a portion of the  design phase of an expanded Utilities fiber optic network.  The contract for design of this network was approved  by Council in June 2020.  Staff is in the planning stages for design implementation.      Electric Customer  Connections   (EL‐89028)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,255,231 $2,700,000 Utilities N/A Recurring  Project Status: This project installs services, transformers, and meters for new customers; upgrading of existing  services; temporary service connections; and overhead and underground extensions for new or existing  customers.  Projects are in many stages of design and construction to provide temporary and permanent power  to residential and commercial customers in Palo Alto.  There are ongoing electric customer connections each year.    Electric System  Improvements   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $909,344 $2,597,000 Utilities N/A Recurring  Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 8 of 9  (EL‐98003) Project Status: This project consists of various projects that replace deteriorated facilities or install protective  devices that improve the Electric Distribution System. Projects are in many stages of development to replace  transformers, replace poles, replace overhead wires, and install protective devices to improve service reliability.   There are ongoing electric systems improvements each year.    Electric Utility  Geographic  Information  System   (EL‐02011)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $172,408 $492,100 Utilities N/A Recurring  Project Status: This project enhances the citywide Geographical Information System (GIS).  The primary emphasis  will be to provide a compatible user interface and estimating software, to edit and update data which will reside  in the citywide GIS.  This funding is also being used to pay for Utilities Electric Division’s share of cost for the  implementation of new city‐wide GIS system (ESRI) led by IT.  Staff is also working directly with IT to assess GIS  needs and the transition of the mapping information to ESRI.  The ESRI GIS web portal is completed and has been  rolled out to Engineering and Operations staff. The data migration to ESRI’s Utility Network Model is in progress.     SCADA System  Upgrades   (EL‐02010)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $283,489 $405,674 Utilities N/A Recurring  Project Status: This project upgrades the Supervisory Control and Data Acquisition (SCADA) system hardware.   Staff completed upgrade of the servers used for monitoring the utility substations and equipment in 2014.  The  next hardware and software upgrade will occur in spring 2022.    Substation  Facility  Improvements   (EL‐89044)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $264,757 $450,000 Utilities N/A Recurring  Project Status: This project makes improvements to facilities at the electric substations in Palo Alto.  Staff is  working on the replacement of Remote Terminal Units (RTU) at various substations, upgrading gravel and  grounding, 60 kV air switches, and reconfiguring steel trusses and associated devices.     Electric Fund Projects Status as of December 2021    Electric Fund Projects – Page 9 of 9  Substation  Protection  Improvements   (EL‐89038)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $183,000 $480,000 Utilities N/A Recurring  Project Status: This project makes improvements to equipment used at electric substations to protect the  substation equipment and circuits emanating from the substation from damage due to faults (i.e. short circuits)  on the electric system.     Underground  System Rebuild   (EL‐16001)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $36,944 $349,999 Utilities N/A Recurring  Project Status: This project replaces underground electric equipment in areas that were originally installed  underground, that are not part of an Underground District.  Staff is working to identify areas where the age of the  existing cables are a high priority for cable replacement.  To date, this includes areas in the Stanford Research  Park, Arastradero Road, and along East Bayshore Road.  New areas have been identified and progress has been  made on development of the project.  Construction of this project was deferred to maintain zero rate increases  to ease economic recovery because of COVID‐19.    Wood Pole  Replacement  (EL‐19004)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,297,848 $1,739,927 Utilities N/A Recurring  Project Status: This project will fund the annual replacement of deteriorated wood power poles.   The project is  in the design phase with expected completion in September 2022 and construction starting 2023.  The project is  delayed this year because of staffing shortages. CPAU is working to bring on a consultant to work on the design  phase of this project.          Fiber Optics Fund Projects Status as of December 2021    Fiber Optics Fund Projects – Page 1 of 1  One‐Time Projects  Fiber Optic  Network  System Rebuild  (FO‐16000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $351,887 $1,242,156 Utilities Design Spring 2024  Project Status:  This project is for the System Capacity Improvement that rebuilds portions of the "dark" fiber  optic network around Palo Alto.  The first phase of this project has been constructed.  Additional work is being  assessed and will be coordinated with the project to expand the Utilities Fiber Optic Network (EL‐89031).  This  project is postponed due to the Fiber Expansion Project.  Fiber contractor is expected to finish design in April  2022.      Recurring Projects  Fiber Optics  Customer  Connections  (FO‐10000)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $48,111 $250,000 Utilities  N/A Recurring  Project Status:  This project enables the installation of fiber optic infrastructure for new service connections.  Projects are developed as needed to meet customer requests for leasing of fibers on the Dark Fiber system.  Staff  have processed and completed fifteen customer connection projects in FY 2021, in addition to several smaller  projects involving existing fiber optic cable connections that were handled directly by Operations staff.  The  reduced number of projects was impacted by COVID‐19 work restrictions.    Fiber Optics  Network  System  Improvements  (FO‐10001)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $221,227 $200,000 Utilities N/A Recurring  Project Status: This project improves the reliability within the fiber optic network system.  A project to install a  new fiber optic cable from Park Substation to the Stanford Research Park to enhance capabilities and reliability  is identified and waiting for availability of staff to design This project is postponed due to the Fiber Expansion  Project. The fiber contractor is expected to finish design in April 2022.    Gas Fund Projects           Status as of December 2021      Gas Fund Projects – Page 1 of 3   One‐Time Projects  Gas Main  Replacement  Project 23  (GS‐13001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $984,811 $7,951,869 Utilities Construction Spring 2022  Project Status:  This project enables the design and construction to replace approximately 21,700 linear feet (which  represents 1.9% of the City's Gas distribution main system) of distribution main and 320 gas services constructed mainly  of PVC material on various streets within the Midtown, Evergreen Park, Ventura, College Terrace, Charleston Terrace, and  Research Park neighborhoods. Construction began in winter 2021 with construction scheduled to be completed in spring  2022.  Gas pipeline replacement at the Town & Country Village property is on hold, while the pipeline replacement on  Embarcadero Road and El Camino Real will continue.    Gas Main  Replacement  Project 24  (GS‐14003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $9,000,000 Utilities Design Fall 2023  Project Status:  This project enables the design and construction to replace approximately 20,100 linear feet (which  represents 1.9% of the City's Gas distribution main system) of distribution main and 260 gas services constructed mainly  of PVC on various streets within the University Park, Stanford, and Green Gables neighborhoods.  Construction is  anticipated to begin summer 2022.  Currently the project is on schedule to meet these dates.      Recurring Projects  Gas  Distribution  System  Improvements  (GS‐11002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $323,979 $500,000 Utilities N/A Recurring  Project Status: This project enables Gas Distribution System improvements.  Typical activities include increasing  distribution system capacity for load growth, replacing deteriorated capital facilities, reconfiguring/adding to the system  to improve service reliability, and conducting research related to performance of the gas distribution system or its  various components making general improvements to the system.  The City must continuously evaluate service reliability  Gas Fund Projects           Status as of December 2021      Gas Fund Projects – Page 2 of 3   needs and make improvements to the system to maintain top level service to City customers and to minimize potential  economic losses due to service interruptions.  In the first half of FY 2022, replacement of various gas services throughout  the system was completed.    Gas  Equipment  and Tools  (GS‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $8,922 $50,000 Utilities N/A Recurring  Project Status:  This project purchases polyethylene (PE) fusion equipment and tools, directional boring/locating  equipment and tools, and general shop equipment and tools.  The equipment needs to be upgraded on an annual basis  to safely operate and maintain a natural gas distribution system and to ensure operators’ safety and productivity.  The  purchase of new polyethylene peelers for all six utility crew trucks was completed in the first half of FY 2022.    Gas Meters  and  Regulators  (GS‐80019)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $140,566 $500,000 Utilities N/A Recurring  Project Status: This project provides replacement of the existing gas meters and regulators annually. The coordination  of gas meter and regulator replacements with gas meters identified to be replaced under the AMI contract, which is  generally gas meters that are 25 years or older.  The gas meter replacement program ensures the accuracy of gas  consumption measurement, reduces possible revenue loss due to under‐registered gas, and provides customers with  accurate monthly bills.  Replacement of aged gas meters and regulators is on‐going.  The next major replacement of  meters and regulators will be coordinated with Gas Main Replacement Project 23 (GS‐13001) and the Advanced Metering  Infrastructure project.    Gas System,  Customer  Connections  (GS‐80017)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,207,298 $1,124,169 Utilities  N/A Recurring  Project Status:  This project enables the Gas Distribution System to be extended in order to provide gas service to new  customers and augment service to customers with increased natural gas demands. Improvements include new mains,  services, valves, regulators, meters, and accessories.  This project upgrades infrastructure to provide gas service  Gas Fund Projects           Status as of December 2021      Gas Fund Projects – Page 3 of 3   connections to new customers, meet changes in existing customer service demands, and respond to changes in gas  service requirements due to new development or redevelopment.  This project is funded partially from reimbursements  by customers.  City crews completed 45 new gas services installations and 49 gas service demolitions in the first half of  FY 2022.               Stormwater Management Projects         Status as of December 2021  Stormwater Management Projects ‐  Page 1 of 3  One‐Time Projects  Corporation  Way System  Upgrades and  Pump Station  (SD‐21000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $144,863 $3,949,241 Public Works Design Fall 2022  Project Status:  This project incorporates a design of a new small pump station with 25 cubic feet per second  capacity and upgrades 700 linear feet of pipe to 30‐inch diameter High Density Polyethylene pipe.  The existing  system does not have the force needed to discharge storm flows into the Adobe Creek.  Adding a pump station in  advance of the outfall and upsizing the storm pipe will eliminate the routine flooding along East Bayshore Road and  convey runoff from a 10‐year storm event.  The design consultant contract was awarded in June 2020. The  consultant has reached 90% completion of the design plans. Staff is also in the process to secure an easement for  the pump station from adjacent property owners.  The final design will be completed in spring 2022 and  construction is anticipated to start in summer 2022.    Green  Stormwater  Infrastructure  (SD‐22001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $500,800 Public Works Design Summer 2023  Project Status:  This project provides funding for Green Stormwater Infrastructure (GSI) projects and the integration  of GSI features to be included in the design and implementation of planned CIP projects supported by other funds  and in the future maintenance of the City’s GSI assets. GSI mimics the natural environment to slow, spread, sink,  and filter storm runoff through native or engineered soils or other pervious material rather than discharging it  directly into storm drain inlets. Elements include bioretention planters, tree wells, pervious pavement, and  rainwater harvesting (rain barrels and cisterns) to manage stormwater runoff.  The GSI project for parking Lot A at  Lytton Avenue and Emerson Street is still in design.    Trash Capture  Device  Installation  (SD‐22002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $613,000 Public Works Design Fall 2022  Project Status:  This project provides funding for the design and construction of a large trash capture device (TCD)  to be installed in the planting strip along Embarcadero Road located in front of the Palo Alto Baylands Golf Links  Stormwater Management Projects         Status as of December 2021  Stormwater Management Projects ‐  Page 2 of 3  parking lot. The TCD will be integrated into a 36‐inch storm pipe to capture trash as small as five millimeters from  a section of the storm drain system prior to discharging to the San Francisco Bay. The 189‐acre drainage area treated  by the TCD consists of 169 acres of commercial and office land use in the City’s jurisdiction and 20 acres in the  California Department of Transportation (Caltrans) right‐of‐way. A Request for Proposals will be released in spring  2022 for design and construction support.     West Bayshore  Road Pump  Station  (SD‐20000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $215,393 $1,795,272 Public Works Design  Spring 2024   Project Status:  This project incorporates design and construction of a new small pump station with 15 cubic feet  per second capacity.  Installing a new pump station will allow storm flows to be pumped into the Adobe Barron  Creek confluence while adding a pump station in advance of the outfall would eliminate the routine flooding along  West Bayshore Road and allow the system to convey runoff from a 10‐year storm event.  The design consultant  contract was awarded in June 2020.  The consultant has reached 90% completion of the design plans. Staff is also  in the process to secure an easement for the pump station from adjacent property.  The final design will be  completed in spring 2022.  Construction will start in fall 2023 with project completion expected in spring 2024.    West Bayshore  Road Trunk Line  Improvements  (SD‐23000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $5,271 $2,410,175 Public Works Design Spring 2024  Project Status:  This project replaces approximately 1,400 linear feet of existing 15‐inch diameter pipe with 36‐inch  High Density Polyethylene pipe.  These improvements along with the new West Bayshore Road Pump Station (SD‐ 20000) will eliminate the routine flooding along West Bayshore Road and allow the system to convey runoff from  a 10‐year storm event.  Once the design for the pump station is finalized the consultant will advance the design for  the capacity upgrades.  The final design will be completed in spring 2022.  Construction will start in fall 2023 with  project completion expected in spring 2024.        Stormwater Management Projects         Status as of December 2021  Stormwater Management Projects ‐  Page 3 of 3  Recurring Projects  Storm Drainage  System  Replacement and  Rehabilitation  (SD‐06101)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $374,725 $1,013,063 Public Works N/A Recurring  Project Status: This project provides for annual replacement and rehabilitation to maintain the integrity of the  storm drain system, including deteriorated storm drain piping, manholes, and storm drain inlets.  The  rehabilitation includes cured‐in‐place pipe (CIPP) lining, and replacement of broken pipe with HDPE.  The  rehabilitation project went to bid in summer 2021 with construction expected to start in early 2022.      Wastewater Collection Fund Projects        Status as of December 2021    Wastewater Collection Fund Projects – Page 1 of 2  One‐Time Projects  Wastewater  Collection  System  Rehabilitation  Augmentation  Project 30   (WC‐17001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $233,372 $4,436,778 Utilities Construction Fall 2022  Project Status:  This project includes the design and construction of high priority mains with structural defects that  cannot be addressed with routine maintenance.  The wastewater mains on various streets in the City, will be replaced  with approximately 10,000 linear feet of sanitary sewer mains and associated laterals in the Ventura, Charleston  Meadows, Fair Meadow, and Palo Verde neighborhoods.  The anticipated start date for construction is March 2022.        Recurring Projects  Sewer  Lateral/Manhole  Rehabilitation  and  Replacement   (WC‐99013)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $0 $800,000 Utilities N/A Recurring  Project Status: This project replaces defective sewer laterals, cleanouts, manholes, backwater devices, and equipment  to support these activities to maintain the Wastewater Collection System, as well as to comply with the Sanitary Sewer  Master Plan (SSMP).  Information collected during routine annual maintenance activities is used to prioritize work.   The continued work performed will also help reducing both sewage blockage and the City's treatment expenses to  treat rainwater or groundwater infiltration.      Sewer System,  Customer  Connections   (WC‐80020)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $436,902 $450,000 Utilities N/A Recurring  Project Status: This project installs sewer lateral connections and additions or extensions of existing mains to serve  new customers and to respond to changes in sewer requirements due to redevelopment.  Old existing non‐plastic  sewer laterals with condition deficiencies per Utilities Operations’ criteria are required to be replaced in accordance  Wastewater Collection Fund Projects        Status as of December 2021    Wastewater Collection Fund Projects – Page 2 of 2  with the latest 2021 WGW Standards.  This project recovers the cost for installation and maintenance through  customer connection fees and capacity increase fees for connecting to the wastewater collection system.     Wastewater  General  Equipment and  Tools   (WC‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $53,446 $120,000 Utilities N/A Recurring  Project Status:  This project includes the acquisition of new fusion equipment to fuse pipe joints together and other  tools needed to clean and inspect the collection system.  As the equipment ages, the quality of the fusion joints begins  to decline, and the operators must spend more time scraping, aligning, and fusing construction joints to maintain high  standards for the installation of sewer pipes.  Recent examples of equipment replacement are the new jetter to flush  the pipes and CCTV camera to inspect the condition of the pipes.  Wastewater  System  Improvements   (WC‐15002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $201,040 $200,000 Utilities N/A Recurring  Project Status: This project implements improvements to the Wastewater Collection System by increasing system  capacity for growth, flow monitoring, hydraulic modeling and system analysis, load simulations, asset management  analysis and assessment, system inflow/infiltration analysis, and sanitary sewer overflow monitoring and reduction.   Replacement of the City’s legacy wastewater maintenance and asset management software (from ICOM to Sedaru)  was completed in May 2021.            Wastewater Treatment Fund Projects  Status as of December 2021    Wastewater Treatment Fund Projects – Page 1 of 3  One‐Time Projects  Advanced  Water  Purification  Facility  (WQ‐19003)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $223,692 $20,216,590 Public Works Design Fall 2024  Project Status: This project enables the design and construction of an Advanced Water Purification Facility to further  improve the quality of the tertiary‐treated recycled water by ultrafiltration  followed by reverse osmosis to reduce the  level of total dissolved solids.  The water reuse partnership agreement with Valley Water and Mountain View provides  $16 million in funding from Valley Water for this project.  The City has received a State low‐interest loan for the design  and construction phases.  The design is currently at 60% completion and is expected to be completed in fall 2022, with  project construction completion in fall 2024.     Headworks  Facility  Replacement  (WQ‐16002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $49,120,400 Public Works Design Fall 2027  Project Status: This project replaces influent pumping, including the suction and discharge piping, pipe manifolds,  valves, the electrical and controls system, screening equipment, grit handling equipment, the force main to the  primaries and modifying headworks building, and yard piping. Solicitation for a consultant to perform Advance  Planning is expected in summer 2022.    Horizontal  Levee Pilot  (WQ‐22001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $832,100 Public Works Design Summer 2027  Project Status:  This project consists of the design, permitting, and construction of a horizontal levee pilot system.  The system will utilize treated wastewater to create a transitional brackish habitat on the Bayside of a future flood  control levee located in the Palo Alto Baylands, adjacent to the City of Palo Alto’s Regional Water Quality Control  Plant (RWQCP). Information and data collected by this pilot system could support broader implementation of  horizontal levees as green infrastructure components in larger flood control levee improvement projects within Palo  Alto and beyond. The project is currently at 60% design and working towards completing CEQA review by the end of  2022.   Wastewater Treatment Fund Projects  Status as of December 2021    Wastewater Treatment Fund Projects – Page 2 of 3  New  Laboratory and  Environmental  Services  Building  (WQ‐14002)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $363,705 $24,149,059 Public Works Design Fall 2027  Project Status:  This project was originally envisioned to replace the existing plant laboratory and environmental  services offices.  A design consultant completed preliminary design in early 2020.  Staff are currently revising space  planning assumptions and have put further design efforts on hold until more advanced planning can be completed.   Outfall Line  Construction  (WQ‐19000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $0 $10,668,115 Public Works Design Summer 2026  Project Status:  This project consists of the construction of a new parallel outfall pipe to convey final plant effluent to  San Francisco Bay.  Design was completed in fall 2020. The PWE / USACOE Levee Project requires a re‐design of the  pipeline to accommodate a potential failure runway shift at PAO Airport.  Staff is currently working with PAO / FAA  staff towards gaining FAA concurrence for the project re‐design.  The re‐design and re‐permitting could delay the  project by several years.  The City has received a State low‐interest loan for the design and construction phase, and  the State is working with the City to retain the loan through the re‐design process.     Plant Master  Plan   (WQ‐10001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $4,509,091 $5,513,891 Public Works Construction Fall 2022  Project Status:  This project enables the ongoing program management support for major capital projects.  Current  tasks include developing scopes of work, evaluating consultant proposals, coordinating project management activities,  pursuing State low‐interest loans for multiple projects, and updating partner agreements.  The consultant continues  to provide support for the projects associated with the Long‐Range Facilities Plan (LRFP).    Primary  Sedimentation  Tank  Rehabilitation   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $770,112 $20,616,546 Public Works Construction Winter 2023  Project Status: This project enables the design and construction for new protective coatings on each of the four  concrete primary sedimentation tanks, with replacement of worn rotating parts and mechanical and electrical  Wastewater Treatment Fund Projects  Status as of December 2021    Wastewater Treatment Fund Projects – Page 3 of 3  (WQ‐14003) equipment.  These tanks were installed in 1972 and the recoating project will extend the concrete life for another 30  years.  Construction began in June 2021.  The design and construction cost of the project is funded by a state low‐ interest loan via Clean Water State Revolving Fund with the Installment Sale Agreement executed on 7/12/2021.    Secondary  Treatment  Upgrades  (WQ‐19001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $2,432,159 $128,952,177 Public Works Design Winter 2026  Project Status: This project upgrades the Secondary Treatment process at the Regional Water Quality Control Plant.   The existing Secondary Treatment process has two main components; the Fixed Film Reactors (FFR) and the Activated  Sludge (AS) Process.  This project includes the reconstruction of the AS process, rehabilitation of the AS Aeration  Basins, and the elimination of the FFRs.  The 90% design milestone is complete, with a completion of design expected  in spring 2022.  Construction is expected to start in spring 2023.  The City has received a State low‐interest loan for  the design and construction phases.      Recurring Projects  Plant Repair,  Retrofit and  Equipment  Replacement  (WQ‐19002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $2,269,938 $8,791,959 Public Works N/A Recurring  Project Status:  This project enables the assessment, repair, and retrofit of the Plant's concrete and metal  structures; the replacement of necessary Plant equipment and ancillary facilities, including electrical  equipment/systems, to maintain treatment reliability and existing infrastructure; and the replacement of large  diameter flow meters built into the wastewater treatment system on sewers, pipes, and water lines.  Current  projects include the design of the 12kV Electrical Loop Upgrade Project, which is 90% complete and the construction  of the Secondary Clarifier Nos. 4 and 6 Mechanism Replacement project, which was completed in October 2021.      Water Fund Projects           Status as of December 2021    Water Fund Projects – Page 1 of 4  One‐Time Projects  Water Main  Replacement  Project 28  (WS‐14001)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $267,126 $11,106,620 Utilities Design Fall 2023  Project Status: This project will replace approximately 18,600 linear feet (which represents 1.6% of the City's water  distribution system) of mains and 265 services on various streets in the City, including areas in the Duveneck, St.  Francis, Barron Park and Charleston Meadows neighborhoods.  Construction is anticipated to begin in summer  2022.     Water Recycling  Facilities  (WS‐07001)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $710,106 $1,243,714 Utilities Pre‐Design  Fall 2023  Project Status: This project allows the City to hire a consultant to prepare a business plan, prepare preliminary  design, and secure funding options for an expansion of the existing recycled water delivery system in the City.  The  pipeline will primarily serve the Stanford Research Park and provide an alternative supply source of 435,600 cubic  feet per year, roughly 10% of Palo Alto’s total water consumption in 2015.  The environmental impact report was  completed in September 2015.  The expansion pipeline is one of several water reuse projects being considered in  the Northwest County Recycled Water Strategic Plan.  This, or one of the other projects, may be recommended to  Council for design and construction.  Staff is considering expanding the recycled water distribution system as one  project to be evaluated against other alternatives in the One Water Plan tentatively scheduled for council approval  in spring 2023. The earliest such a project could begin is fall 2023.    Water  Regulation  Station  Improvements  (WS‐07000)   Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $1,632,938 $2,099,995 Utilities Design Summer 2023  Project Status: This project for Water Regulation Station Improvements includes seismic upgrades, piping  improvements and other various upgrades to increase the structural reliability of three of the City’s turnouts with  SFPUC.  Work under this project includes Seismic Upgrade of California and Page Mill Turnouts.  Structural  Water Fund Projects           Status as of December 2021    Water Fund Projects – Page 2 of 4  evaluation for restraining the Page Mill turnout and piping will be included in the design.  The design for both  turnouts will be posted for bid in winter 2022, with construction anticipated to begin in fall 2022.    Water Tank  Seismic Water  System  Upgrades  (WS‐09000)  Prior Years Actuals Total Project Budget Implementing Department Project Phase Project Completion  $4,809,313 $26,311,365 Utilities Construction Spring 2022  Project Status: This project for Seismic Water System Upgrades includes seismic upgrades at the Montebello,  Mayfield, Corte Madera, Park, Boronda, and Dahl Reservoirs in compliance with the American Society of Civil  Engineers (ASCE 7) seismic codes.  Seismic upgrade of Boronda and Montebello Reservoirs was completed in 2016  and 2018.  The Mayfield Reservoir was rehabilitated in September 2020.  The tank replacement work at Corte  Madera Reservoir is currently under construction.  The new steel tank is expected to be completed in spring 2022.   The financial study (rehabilitation vs. replacement) of the Park and Dahl Reservoir was completed.  Further  investigation of the existing tank‐roof condition is needed before a final recommendation can be made.  The design  for the Park and Dahl Reservoirs is anticipated to begin in spring 2022.        Recurring Projects  Water  Distribution  System  Improvements  (WS‐11003)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $351,430 $277,553 Utilities N/A Recurring  Project Status: This project enables improvements to water distribution system deliverability and reliability.   Typical activities include installing restraining joints at critical pipelines and bridge crossings, increasing the size of  inadequate facilities, system leakage surveys, network modeling, and fire flow studies or other system  improvements as required.  Continuous evaluation of system needs and making required improvements is  necessary to maintain adequate quantities of quality water, meeting local, state, and federal safe drinking water  standards.  During the last six months the Mayfield Reservoir variable frequency drive (VFD) replacement and back‐ up controls were completed.  El Camino Pump Station pump programming was completed and tested to add the  capability for the El Camino Reservoir to pump into zone 1 in addition to zone 2.    Staff continues the asbestos  Water Fund Projects           Status as of December 2021    Water Fund Projects – Page 3 of 4  cement pipe (ACP) study and is in the process of collecting pipe samples whenever we encounter an ACP to be  replaced.     Water, Gas,  Wastewater  Utility GIS Data  (WS‐02014)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $174,173 $483,958 Utilities N/A Recurring  Project Status: This project enables contracts related to Utilities GIS (Geographic Information System) needs.  AME  database is heavily utilized by Utilities Engineering staff to update the utility information in GIS.  The updated  information is used by various City staff, such as marking/locating underground utilities to comply with USA  (Underground Service Alert) requirements; developing design drawings for pipeline replacement projects; verifying  existing underground utilities during construction activities; creating customized utility map books for field crews  and on‐call personnel to meet their specific needs.  Annual surveying contracts collect GPS points of existing above‐ ground utility features within the CIP project areas.  The data being collected continues to be used to correct the  GIS database.  Accurate utility data helps the design to select new pipe alignment to minimize construction  conflicts.     Water General  Equipment/Tools  (WS‐13002)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $38,271 $100,000  Utilities N/A Recurring  Project Status: This project acquires new equipment and tools, the replacement of existing fusion equipment, and  other associated tools.  The fusion equipment is used to fuse together pipe joints in the City's water distribution  system.  Equipment and tools are required to be upgraded on an annual basis to maintain high quality standards  for the installation of the City's water distribution mains, along with the associated service standards and worker  safety and productivity measures.  Staff purchased new Polyethylene peelers for pipe fusions in the first half of FY  2022.     Water Meters  (WS‐80015)   Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $92,385 $546,364 Utilities N/A Recurring  Water Fund Projects           Status as of December 2021    Water Fund Projects – Page 4 of 4  Project Status: This project enables the purchasing of meters for new customers, upgrading meters for current  customers, installing meter bypasses, and replacing obsolete meters that are no longer repairable.  This funding  also allows for annual testing and calibration of selected meters to maintain meter accuracy and reliability.  During  the AMI implementation process approximately 50% of the meters will be replaced. Staff is currently targeting  large diameter meter sets to be replaced first in preparation for the upcoming AMI project.    Water Service  Hydrant  Replacement   (WS‐80014)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $84,364 $400,000 Utilities N/A Recurring  Project Status: This project replaces system control valves, deteriorated galvanized service lines, lead goosenecks,  and fire hydrant valves and assemblies per the Fire Department’s flow testing, upgrades fire hydrants in main line  replacement project areas, and replaces existing undersized or deteriorated copper water services.      Water System  Customer  Connections  (WS‐80013)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $1,000,327 $877,250 Utilities N/A Recurring  Project Status: This project allows for improvements that include new main extensions, valves, domestic services,  meters on upgraded services, backflow devices, fire services, and fire hydrants.  System extensions are required to  provide service to new large developments and to serve existing customers requesting expanded service.    Water System  Supply  Improvements  (WS‐11004)  Prior Year Actuals Current Year Budget Implementing Department Project Phase Project Completion  $277,553 $197,013 Utilities N/A Recurring  Project Status: This project evaluates and improves the City’s water distribution system on an as‐needed basis. This  project includes piping modifications, equipment replacements associated with water delivery, supervisory control  software upgrades, system modifications for water system quality compliance, conditional assessment of the  reliability of transmission mains, and security system installations.  The water system includes the connection  facilities between the City’s and the San Francisco Public Utility Commission’s pipelines, emergency water wells  within the City, pumping stations, water reservoirs, and pipelines.  List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date EL‐14005 Reconfigure Quarry  Feeders  This project reconfigured the distribution circuits to the substation transformer  at Quarry Substation.  Design of QR 27 feeder replacement was completed in  spring 2021. Construction was completed in December 2021 . Construction Electric Utilities Fall 2021 792,034$                AC‐18001 JMZ Renovation  This project provided for the relocation of the Junior Museum and Zoo to  Cubberley for two years while a new JMZ was being built, tenant improvements  to the Cubberley Auditorium and then removal of tenant improvements post‐ construction.  Construction of the new Junior Museum and Zoo started in June  2018 and was completed in late 2021. The new Junior Museum and Zoo was  opened to the public on November 12, 2021.   Construction Buildings and  Facilities Community  Services Fall 2021 2,927,870.00$       PE‐18002 High and Bryant Street  Garages Waterproofing  and Repairs  This project included a systems analysis and repaired the water proofing system  in the High Street and Bryant Street parking garages.  Water proofing repairs  were completed in the High Street parking garage.   Additional funding was  added and the contractor completed waterproofing repairs in the subterranean  stairwells in the Bryant Street garage in fall 2021. Construction Buildings and  Facilities Public Works Fall 2021 264,235.00$           PE‐11011 Highway 101 Pedestrian  Bicycle Overpass Project As part of the 2014 Council Infrastructure Plan, this project designed and  constructed a new pedestrian bridge across Highway 101 at Adobe Creek.  Council approved a contract with Granite Construction in November 2019.   Construction began in January 2020.  The project construction completed on  November 20, 2021,  with a ribbon‐cutting ceremony and a community  celebration. Construction Traffic and  Transportation Public Works Fall 2021 22,889,453$           EL‐12001 Underground District 46   Charleston This project undergrounded the existing overhead utility systems in the area  along the 400 block of West Charleston and El Camino Real.   Staff  completed   cable, equipment installation and 100% of customer service conversions. The  construction for the final phase of the project to install two 60 foot tall steel  poles and to reconductor the 60 kV sub‐transmission lines was completed in the  fall 2021. Construction Electric Utilities Fall 2021  $            3,904,425  OS‐18001 Pearson Arastradero  Preserve Parking lot  Improvement This project improved the Pearson Arastradero Preserve parking lot by  improving the base rock surfacing, adding drainage, widening the entrance for  safety, and new fencing.  This new improvement will allow the overflow parking  area to be open year round.  The work was completed in May 2021. Construction Parks and Open  Space Community  Services Spring 2021  $               170,300  CB‐16001 Cubberley Community  Center Master Plan This project developed the master plan  for future use of the Cubberley  Community Center site by the City and Palo Alto Unified School District.Study Buildings and  Facilities Community  Services Spring 2021  $               926,792  De c e m b e r  20 2 1 1 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date CB‐19001 Cubberley Building  Management Systems This project replaced the Building management System(BMS) controls for the  pavilion, Theater, Wing I, and Gyms A and B boiler rooms at the Cubberley  Community Center.  The project included the installation of control points for  each building along with controllers, valve and damper actuators. Construction Buildings and  Facilities Public Works Spring 2021  $               350,000  FD‐14002 Fire Ringdown System  Replacement This project replaced the current ring down system that provides an audible  alert of calls in the fire stations.  Ongoing installations started in 2018 and were  completed with Fire Station #3. Construction Buildings and  Facilities Fire Departent Spring 2021  $               400,144  PD‐14000 Internal Alarm System  Replacement The project replaced the citywide internal alarm system.  The alarms at City Hall  migrated to this new system in FY 2019, but was completed in early 2021.Construction Buildings and  Facilities Police  Department Winter 2021  $                 77,569  FD‐20001 Self Contained Breathing  Apparatus (SCBA) Air  Compressor Replacement This project replaced the central air compressor that provides air for the self‐ contained breathing apparatus (SCBA) tanks to ensure firefighter safety when  entering environments with hazardous air quality. Construction Buildings and  Facilities Fire Department Spring 2021  $                 94,500  AP‐20000 Airport Electrical  Improvements This project replaced the outdated electrical panels for the Palo Alto Airport  office rental spaces.  Construction was completed in January 2021.Construction Airport Public Works Winter 2021  $               146,466  PE‐18000 New California Avenue  Area Parking Garage  This project built the California Avenue Area Parking Garage, as part of the 2014  Council Infrastructure Plan.   The parking garage has 627 parking spaces with 2  basement levels and 4 above grade floors.  The garage features an automated  parking space guidance system, EV charging stations, bicycle parking, and  motorcycle parking. The garage was opened to the public on December 8, 2020. Construction Buildings and  Facilities Public Works Fall 2020  $         50,119,976  PF‐14002 Fire Station 1  Improvements  This project updated the individual sleeping quarters in the firehouse to address  gender issues and privacy concerns.  Fire Station #1 was the only fire station in  the City that did not have separate bedrooms to accommodate male and female  firefighters.   This project was completed in fall 2020. Construction Buildings and  Facilities Public Works Fall 2020  $               187,064  GS‐18000 Gas ABS/Tenite  Replacement Project  This project replaced gas services laterals constructed of Acrylonitrile‐butadiene‐ styrene (ABS) or Tenite material on various streets.  Council approved funding in  June 2019.  The project replaced 104 ABS and Tenite gas services.  The WQCP  ABS gas service is assigned to Utility Operations for replacement and the  remaining five ABS gas services will be scheduled for replacement once the five‐ year moratorium ends on those streets.  As of November 2020, this project is  complete. Construction Gas Utilities Fall 2020  $            2,615,100  Ju n e  20 2 1 2 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date SD‐19000 Loma Verde Avenue Trunk  Line Improvements  This project replaced 1,750 linear feet of storm drain with 48‐inch diameter High  Density Polyethylene (HDPE) pipe and associated catch basins, laterals and  manholes.  In addition to underground work, additional street restoration and  concrete work was completed. Work includes resurfacing one full lane on Loma  Verde from the beginning to the end of the project limits, replacement of  driveways, sidewalk, and 718 linear feet of curb and gutter.   The contract was  awarded in June 2020, construction work began in August 2020,  and was  completed in December 2020. Construction Storm Drain Utilities Fall 2020  $            2,976,813  WS‐19000 Mayfield Reservoir  Subgrade and Venting  Repair  This project is part of the City s recent Seismic Upgrade and Emergency Water  Supply and Storage Projects.  The reservoir was drained in 2012 for  approximately two years to allow extensive seismic rehabilitation work to be  performed and construction of a new pump station.  Subsequently hairline  cracks were sealed in the reservoir.  A geotechnical consultant was hired to  evaluate the tank foundation.  This study was completed and there were several  options identified.  Staff has completed the design and construction of the vent  screen replacement and cracksealing Construction Water Utilities Fall 2020  $               600,000  EL‐11010 Underground District 47   Middlefield, Homer,  Webster, Addison  This project undergrounded the existing overhead distribution system in the  area bounded by Middlefield Road, Homer Avenue, Webster Street, and  Addison Avenue. Installation of substructures and utility electric system is  completed.  Where possible, the overhead electric lines were removed and  poles cut down to the level of the communication lines.   Construction Electric Utilities Fall 2020  $            3,649,356  WC‐16001 Wastewater Collection  System Rehabilitation   Augmentation Project 29  This project replaced of 8,972 linear feet of wastewater mains.  The sanitary  sewer mains, laterals, and manholes to be rehabilitated or replaced in this  project are located in the Charleston Meadows neighborhood.  Construction  started in February 2020 and was suspended for almost 3 months due to COVID‐ 19 County’s Shelter‐in‐Place Order.  The project is complete as of December  2020. Construction Wastewater  Collection Utilities Fall 2020  $            4,434,839  PF‐18000 Parking Lot J Elevator  Modernization This project modernized the existing elevators at parking Lot J.  The project  involves upgrading the interior of the elevators, elevator control interface, call  buttons, and meeting current ADA standards.  Construction started in April  2019.  Project is complete except for the State final inspection on the second  car.  State is behind because of COVID, but the inspection should be done by the  end of July 2020.   Construction Buildings and  Facilities Public Works Spring 2020  $               781,324  PE‐15003 Fire Station 3 Replacement This project replaced the existing Fire Station at Embarcadero Road and Newell  Road with a new structure that meets essential services standards and current  program needs.   Construction completed in March 2020.   Construction Buildings and  Facilities Public Works Winter 2020  $         10,080,258  De c e m b e r  20 2 0 3 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date WS‐08001 Water Reservoir Coating  Improvements This project included the recoating of four steel tanks. Work under this project  was included in the Seismic Upgrade of four Steel Tanks and the three Turnout  Projects. Once construction started, it was found that the Montebello Reservoir  was in very poor condition. Due to escalating costs associated with roof  replacement, staff decided to complete construction of the Montebello  Reservoir and re‐evaluate the remaining three tanks for replacement.  Construction Water Utilities Spring 2020  $            2,141,172  WS‐13001 Water Main Replacement ‐  Project 27 This project replaced approximately 9,600 linear feet of structurally deficient,  aging, or corroded water mains and services along the mains on Sand Hill Road,  Oak Creek Drive (5%) and Fulton Avenue.  Construction Water Utilities Spring 2020  $            7,786,998  WC‐15001 Wastewater Collection  System Rehabilitation  Augmentation Project 28  This project enabled the design and construction of a high priority wastewater  main and lateral replacement work to reduce inflow of rainfall and ground  water into the collection system. The project replaced or rehabbed  a total of  7,655 linear feet of wastewater mains  located in the Leland Manor/Garland,  Midtown West, and Lower Page Mill/Los Altos Hills areas of the City.   Construction Wastewater  Collection Utilities Spring 2020  $            5,665,897  EL‐17003 VA Hospital ‐ Customer  Load Requirements  This project met the growing electric needs of the VA Hospital. Staff has had  numerous discussions with VA Hospital on electric load growth at the hospital  and anticipated needs from the utility. Much of the cost is reimbursed to the  City by the VA Hospital. Staff has prepared preliminary designs for interim  solutions and is awaiting additional information from VA to develop long range  plans to meet their future needs.   Design Electric Utilities Spring 2020  $                 84,984  EL‐04012 Utility Site Security  Improvements This project added electronic security systems at utility sites to protect  equipment at electric substations, water pumping plants, reservoirs, and gas  stations from intrusion and vandalism.  Cameras and detection systems have  been installed at nine electric substations, three water stations, and one natural  gas station to monitor facilities.   Construction Electric Utilities Spring 2020  $            1,644,681  EL‐11008 Rebuild Underground  District 19  This project rebuilt and replaced the underground electric system in  Underground District 19, the area bounded by Forest Avenue, Waverley Street,  Addison Avenue, and Alma Street.  Construction Electric Utilities Spring 2020  $               149,023  Ju n e  20 2 0 4 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date FD‐18000 Self Contained Breathing  Apparatus Replacement This project replaced Self Contained Breathing Apparatus equipment (SCBA)  used by firefighters when entering hazardous conditions when responding to  fire and hazardous materials incidents. The SCBA provides breathable air for  firefighters when entering environments where the atmosphere is immediately  dangerous to life or health.  The expected service life for SCBAs is 15 years.  Purchase Buildings and  Facilities Fire Department Spring 2020  $               799,999  FD‐20000 Cardiac Monitor  Replacement This project replaced the entire complement of twenty cardiac monitors in the  Department. Along with other tools needed for patient assessment and airway  verification, cardiac monitors assess cardiac activity in patients and provide  defibrillation and pacing.   Purchase Buildings and  Facilities Fire Department Spring 2020  $               850,000  PL‐16001 Downtown Mobility and  Safety Improvements  This project included the construction of curb extensions and the installation of  new pedestrian signal heads and traffic signal modifications in 2019 as part of  the Upgrade Downtown project. Construction Traffic and  Transportation Office of  Transportation Fall 2019  $            1,819,847  FD‐20002 Thermal Imaging Cameras  Replacement     This project replaced the Thermal Imaging Cameras (TICs) on all fire and  response vehicles used to help identify the location of victims; assess the source  of fires, smoke, and heat; to assist in creating a plan of action.  Purchase Buildings and  Facilities Fire Department Fall 2019  $                 99,000  WC‐11000 Wastewater Collection  System Rehabilitation  Augmentation Project 24 This project  addressed areas that were identified in Wastewater Capital  Improvement Project 17 (Cleaning and Video Inspection of the Collection  System) as needing rehabilitation. This project was combined with Project 25  and 26(WC‐12001; WC‐13001).   Construction Wastewater  Collection Utilities Fall 2019  $            3,131,595  WC‐13001 Wastewater Collection  System Rehabilitation  Augmentation Project 26 This project was combined with Project 24 and 25(WC‐11001; WC‐12001). All  new service laterals were installed from the new sewer main to the new sewer  cleanouts located in the City’s right‐of‐way. Construction Wastewater  Collection Utilities Fall 2019  $            3,309,998  CB‐19000 Cubberley Track and Field  Replacement This project replaced the synthetic turf field, installed an all‐weather track and a  fitness area.Construction Parks and Open  Space Public Works Fall 2019  $            1,851,708  PE‐14018 Baylands Boardwalk  Improvements  This project replaced the existing boardwalk with similar alignment and  configuration. Construction Buildings and  Facilities Public Works Winter 2019 2,123,681$             PE‐17009 City Hall Floor 4 Remodel This project improved the Administrative Services Department offices on the  fourth floor of City Hall.Construction Buildings and  Facilities Public Works Winter 2019 494,818$                PE‐14015 Lucie Stern Buildings  Mechanical and Electrical  Upgrades This project replaced and upgraded the mechanical, electrical, and fire/life  safety systems at Lucie Stern Children’s Theater, Lucie Stern Community  Theater, and Lucie Stern Community Center.  Construction Buildings and  Facilities Public Works Spring 2019 6,142,607$             De c e m b e r  20 1 9 5 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date PL‐16000 Quarry Road  Improvements and Transit  Center Access This project included planning, design and construction of bicycle and  pedestrian improvements along Quarry Road.Construction Traffic and  Transportation Planning and  Community  Environment Spring 2019 5,148,378$             EL‐17008 Utility Control Center  Upgrades This project upgraded the Utility Control Center working environment. Construction Electric Utilities Winter 2019 499,997$                GS‐12001 Gas Main Replacement  Project 22 This project replaced approximately 23,700 linear feet of gas mains and services  along University Avenue and other streets in the Downtown North  nieghborhood. Construction Gas Utilities Spring 2019 11,658,997$           WC‐12001 Wastewater Collection  System Rehabilitation /  Augmentation Project 25  This project was combined with Project 24 and 26 (WC‐11001; WC‐13001)  replacing 45,294 linear feet of sanitary sewer mains in university South,  Professorville and Old palo Alto neigborhoods. Construction Wastewater  Collection Utilities Spring 2019 3,211,998$             WQ‐14001 Dewatering and Loadout  Facility This project provides funding for the design and construction of the sludge  dewatering facility and truck loadout to retire existing dewatering and sewage  sludge incinerators.  Construction Wastewater  Treatment Public Works Spring 2019 27,497,551$           WS‐12001 Water Main Replacement  – Project 26  This project replaced approximately 11,000 linear feet of aging water mains and  services which included water main replacement as part of the Upgrade  Downtown Project. Construction Water Utilities Spring 2019 7,506,161$             PE‐17009 City Hall Floor 5 Remodel This project improved the Planning and Community Environment (PCE)  Department offices on the fifth floor of City Hall. Construction Buildings and  Facilities Public Works Summer 2018 525,000$                AC‐14001 Baylands Nature  Interpretive Center Exhibit  Improvements  This project replaced worn out or non‐functioning exhibits at the Baylands  Nature Interpretive Center.Construction Buildings and  Facilities Community  Services Summer 2018 56,000$                  PE‐17000 Mitchell Park Adobe Creek  Bridge Replacement This project replaced the existing bridge over Adobe Creek in Mitchell Park. Construction Parks and Open  Space Public Works Summer 2018 250,000$                PD‐14000 Internal Alarm System  Replacement This project replaced the citywide system of panic alarms from various  departments and the Council chambers.Construction Buildings and  Facilities Police Summer 2018 78,000$                  EL‐14004 Maybell 1&2 4/12kV  Conversion This project converted circuits 1 & 2 at Maybell substation from 4kV to 12kV. Construction Electric Utilities Fall 2018 364,796$                GS‐15001 Security at City Gas  Receiving Stations This project equiped the City’s four Gas Receiving Stations with video  surveillance systems. Construction Gas Utilities Summer 2018 150,000$                Ju n e  20 1 9 De c e m b e r  20 1 8 6 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date SD‐13003 Matadero Creek Storm  Water Pump Station and  Trunk Line Improvements  This project upgraded the capacity to the Matadero Creek Storm Water Pump  Station, which serves a low‐lying 1200‐acre area of southeastern Palo Alto. Construction Storm Drain Public Works Summer 2018 6,685,317$             AP‐16002 Wildlife Hazard  Management Plan The Wildlife hazard Management Plan identified the specific actions the airport  will take to mitigate the risk of wildlife strikes on or near the airport.Study Airport Public Works Summer 2018 63,415$                  WC‐14001 Wastewater Collection  System Rehabilitation  Augmentation Project 27  This project replaced 16,859 linear feet of sanitary sewer mains of various sizes  on various streets.Construction Wastewater  Collection Utilities Winter 2018 4,022,455$             PG‐15000 Buckeye Creek Hydrology  Study  This project analyzed flooding conditions and recommended flood control  structures and drainage and erosion control solutions for the creek located  within Foothills Park.   Study Parks and Open  Space Public Works Spring 2018 167,741$                PE‐17004 CalTrain Corridor Video  Management System  Installation  This project replaced two existing gateway signs in the right‐of‐way for the  California Avenue business district. Construction Streets and  Sidewalks Public Works Spring 2018 1,550,000$             PF‐16003 Parking Lot Q Elevator  Modernization This project modernized the existing elevator at Parking Lot Q. Construction Buildings and  Facilities Public Works Fall 2017 170,608$                PE‐13003 Parks, Trails, Open Space,  and Recreation Master  Plan  This master plan provided guidance on the recreation and improvement needs  for Palo Alto’s parks, trails, open space and recreational programs.  Study Parks and Open  Space Community  Services Fall 2017 627,057$                PE‐12003 Rinconada Park Master  Plan  This project developed a plan for short, medium and long range improvements  to the regional park including the consideration of pathways, new restrooms  and playgrounds, new landscaping, and revitalization of underutilized areas  within the park.   Study Parks and Open  Space Community  Services Fall 2017 541,355$                PE‐13012 Structural Assessment of  City Bridges  The project developed an inventory of all City‐owned bridges and culvert  structures, condition assessment, cost estimate for rehabilitation, and  recommendation for future inspection frequencies, assessment and  improvements. Study Buildings and  Facilities Public Works Fall 2017 198,529$                WC‐11000 Wastewater Collection  System Rehabilitation /  Augmentation Project 24  Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced  and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of  various sizes, 779 sewer laterals, and 121 sewer manholes.   Construction Wastewater  Collection Utilities Fall 2017 3,119,806$             Ju n e  20 1 8 De c e m b e r  20 1 7 7 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date WC‐13001 Wastewater Collection  System Rehabilitation /  Augmentation Project 26  Combined with Project 25 and 26 (WC‐12001; WC‐13001), this project replaced  and/or rehabilitated approximately 42,398 linear feet of sanitary sewer mains of  various sizes, 779 sewer laterals, and 121 sewer manholes.   Construction Wastewater  Collection Utilities Fall 2017 3,361,118$             PG‐13003 Golf Reconfiguration and  Baylands Athletic Center  Improvements  This project completed the rehabilitation of the Palo Alto Municipal Golf Course,  including  a new layout for the course, new prefabricated restroom, new water‐ saving turf and irrigation system, and rebranded the course as the Baylands Golf  Links. Construction Parks and Open  Space Public Works Fall 2017 13,675,177$           GS‐11000 Gas Main Replacement –  Project 21 This project combined with GWR 19B & GMR 20 and replaced ABS gas mains  and services.  Construction Gas Utilities Winter 2017 2,364,937$             WS‐11000 Water Main Replacement  – Project 25  This project provided installation of approximately 11,869 linear feet of new  High Density Polyethylene (HDPE) water mains, 232 new HDPE water services,  and 15 new fire hydrants within the City limits.  Construction Water Utilities Winter 2017 5,445,069$             WS‐15004 Water System Master Plan  The 2015 Water System Master Plan identified present capital improvements  and replacement rates required to ensure optimal reliability levels of service to  the existing distribution and transmission systems.  Study Water Utilities Spring 2017 500,000$                WC‐10002 Wastewater Collection  System Rehabilitation /  Augmentation Project 23  Combined with Project 22 (WC‐09001).  This project replaced and/or  rehabilitated approximately 33,497 linear feet of sanitary sewer mains of  various sizes, 554 sewer laterals, and 102 sewer manholes.   Construction Wastewater  Collection Utilities Winter 2017 1,272,289$             EL‐10009 Street Light System  Street  Light System Conversion  Project  This project converted HPS streetlights to LED and the conversion of  approximately 4500 cobrahead streetlight fixtures.  Construction Electric Utilities Spring 2017 696,918$                EL‐13006 Sand Hill / Quarry 12kV  InterTie  This project installed new wire to connect circuits QR‐24 and QR‐27 in the Sand  Hill/Quarry area. Construction Electric Utilities Winter 2017 208,648$                EL‐15001 Electric Substation Battery  Replacement This project replaced the batteries in all nine of the City's electric substations. Construction Electric Utilities Winter 2017 400,000$                PG‐13001 Stanford/Palo Alto Playing  Fields Soccer Turf  Replacement  This project replaced the synthetic turf at the Stanford/Palo Alto Playing Fields. Construction Parks and Open  Space Community  Services Fall 2016 1,499,979$             8 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date PG‐09003 Park Maintenance Shop  Remodel  This project renovated and remodeled the Parks maintenance shop for safety  and efficienciency upgrades.Construction Parks and Open  Space Community  Services Summer 2016 94,419$                  PE‐12017 City Hall First Floor  Renovations This project installed new elevator control panels and replaced the gray‐painted  panels inside the elevators.Construction Buildings and  Facilities Public Works Summer 2016 3,974,963$             PE‐11012 Temporary Main Library This project created a temporary main Library to be used while the new one  was being constructed.Construction Buildings and  Facilities Public Works 156,254$                PE‐15029 Baylands Nature  Interpretive Center Facility  Improvement  The project replaced decking, railings, structural framing members, exterior  wood flooring, and cabinetry, restroom reconfiguration, and provided  Americans with Disabilities Act (ADA) improvements.   Construction Buildings and  Facilities Public Works Spring 2017 889,452$                PE‐13008 Bowden Park  Improvements  This project improved the children’s playground and included park amenity  upgrades such as new playground equipment, a new retaining wall, surfacing  and pathway upgrades, planting restoration and irrigation renovations, and  replaced of damaged wood benches and the playground perimeter fence.   Construction Parks and Open  Space Community  Services Summer 2016 421,126$                PE‐13020 Byxbee Park Trails This project provided trail and site amenities over the remaining area of the  landfill cap.  Construction Parks and Open  Space Public Works Fall 2016 334,607$                PE‐17002 City Hall Floor 3 Remodel  This project improved the Utilities Department administrative offices on the  third floor of City Hall. It included new carpet, wall reconfiguration, a  kitchenette, cabinets, paint, soundproofing, office furniture, doors, and  associated building systems.  Construction Buildings and  Facilities Public Works Spring 2017 440,000$                PE‐14015 Lucie Stern Buildings  Mechanical and Electrical  Upgrades – Phase 1  This project replaced and upgraded the mechanical, electrical, and fire/life  safety systems at Lucie Stern Children’s Theater, Lucie Stern Community  Theater, and Lucie Stern Community Center.   Construction Buildings and  Facilities Public Works Summer 2016 3,247,248$             PG‐12004 Sarah Wallis Park  Improvements  This project improved site amenities with new concrete pathways, replaced old  furnishings, and upgraded landscape with drought tolerant species. Construction Parks and Open  Space Community  Services Winter 2017 65,000$                  AP‐16003 Airport Perimeter Fence  This project replaced the perimeter fencing and gates surrounding the Palo Alto  Airport boundaries to prevent unauthorized access to the airport runway in  accordance with Federal and State standards.  Construction Airport Public Works Spring 2017 2,003,540$             Ju n e  20 1 7 9 List of Completed Projects CIP #Project Name Project Description Project Type Fund Source Department Season  Completed Year  Completed Total Project  Budget **CMR Date SD‐11101 Channing Avenue/Lincoln  Avenue Storm Drain  Improvements  This project installed of 5,800 linear feet of 36‐inch to 60‐inch diameter storm  drain along Channing and Lincoln Avenues over three project phases to increase  drainage system capacity.   Construction Storm Drain Public Works Winter 2016 7,676,275$             GS‐14004 Gas Distribution System  Model  This project included the development, model installation, testing,  documentation, and staff training of a natural gas distribution system model.  Study Gas Utilities Summer 2016 149,500$                AC‐14000 Art Center Auditorium  Audio, Visual and  Furnishings This project replaced outdated audio visual equipment and furnishings following  the auditorium’s use as a temporary library.  Construction Buildings and  Facilities Community  Services Winter 2016 150,000$                PF‐15000 Rinconada Pool Locker  Room This project renovated the Rinconada Pool locker room including the changing  area, restrooms, and showers in the women's and men's locker rooms.  Construction Buildings and  Facilities Public Works Winter 2016 464,433$                PE‐13016 El Camino Park Restoration This project installed new athletic fields, synthetic turf, field lighting, fencing, a  new restroom, scorekeeper booth and storage buildings, an expanded parking  lot, new bike and pedestrian pathways, landscaping, benches, and other  amenities.   Construction Parks and Open  Space Community  Services Fall 2015 5,611,122$             275,679,761$       Notes: ** Final Project Actuals may be different from Total Project Budget amounts Grand Total De c e m b e r  20 1 6 10