HomeMy WebLinkAbout2000-10-10 City Council (6)TO:
City of Palo Alto
Manager’s Report
HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE:OCTOBER 10, 2000 CMR:375:00
SUBJECT:APPROVAL OF BUDGET AMENDMENT ORDINANCE IN THE
AMOUNT OF $142,000 TO CREATE NEW INFRASTRUCTURE
CAPITAL IMPROVEMENT PROGRAM PROJECT 10120,
CUBBERLEY CHILLER :REPLACEMENT PROJECT, AND TO
REIMBURSE THE CUBBERLEY OPERATING ACCOUNT IN THE
AMOUNT OF $22,000 FOR THE TEMPORARY LEASE EXPENSE
OF A CHILLER
5
RECOMMENDATION
Approve a new Capital Improvement Program (CIP project #10120) for the
replacement of the chiller and related equipment at the Cubberley Community
Theatre.
Approve a Budget Amendment Ordinance (BAO) in the amount of $164,000. The
amount of $142,000 will fund the Cubberley Chiller Replacement Project (CIP
# 10120) from the General Fund Infrastructure Reserve. The remaining balance of
$22,000, funded from the General Fund Stabilization Reserve, will reimburse the
Cubberley operating account for the lease expense of a temporary chiller.
DISCUSSION
The existing air conditioning system for the Cubberley Theatre, which is original to the
building, became inoperable in July and is not repairable due to its age and condition.
This unit was scheduled for replacement under the Infrastructure Management Plan for
fiscal year 2004-05 and is now scheduled for replacement in 2000-01. The unit will be
replaced with a similar system that fits within the existing mechanical room. In addition
to the chiller, pumps and controls require replacement for compatibility with the new
system.
A chiller was leased to air condition the space during the time the unit has been out of
service, and through the remainder of the warm season. Due to the immediate nature of
the need, Cubberley operating funds were used for the leased equipment.
CMR:375:00 Page 1 of 2
RESOURCE IMPACT
The attached BAO requests funds of $164,000, including $142,000 from the
Infrastructure Reserve to fund CIP #10120 and $22,000 from the General Fund
Stabilization Reserve to reimburse the Cubberley operating account for the lease of a
temporary chiller. This is a one-time expense and there are no future year resource needs
anticipated as a result of this BAO. Attachment B summarizes the BAO’s approved to-
date in 2000-01 that impact reserves.
POLICY IMPLICATIONS
This report does not represent any change to existing City policies.
ENVIRONMENTAL ASSESSMENT
This project is categorically exempt from the California Environmental Quality Act and
no further environmental review is necessary.
ATTACHMENTS
Attachment A:Budget Amendment Ordinance
Attachment B:Budget Amendment Ordinances Impacting Reserves Approved to Date
in 2000-01
Attachment C: CIP Project 10120, Cubberley Theatre Chiller Replacement Project
PREPARED BY: Karen Smith, Manager of Facilities Maintenance and Projects
DEPARTMENT HEAD:
GLENN S. ROBERTS
Director of Public Works
CITY MANAGER APPROVAL:
]~MILY HARRISON-----
Assistant City Manager
CMR:375:00 Page 2 of 2
ORDINANCE NO.
ATTACHMENT A
ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO
AMENDING THE BUDGET FOR THE FISCAL YEAR 2000-01 TO
PROVIDE AN APPROPRIATION OF $142,000 FOR CUBBERLEY
THEATRE CHILLER REPLACEMENT CAPITAL IMPROVEMENT PROJECT,
NUMBER 10120 AND AN ADDITIONAL APPROPRIATION OF $22,000
FOR THE TEMPORARY LEASE EXPENSE OF A CHILLER
WHEREAS, pursuant to the provisions of Section 12 of Article
III of the Charter of the City of Palo Alto, the Council on June 19,
2000 did adopt a budget for fiscal year 2000-01; and
WHEREAS, the existing, air conditioning system for the
Cubberley The~ ~re became inoperable in July 2000 and is not
repairable due to its age and condition; and
WHEREAS,~the chiller unit was scheduled for replacement under
the Infrastructure Management Plan for fiscal year 2004-05 and will
now be replaced in 2000-01; and
WHEREAS, with the use of Cubberley operating funds, a leased
chiller has provided air conditioning to the theatre since July; and
WHEREAS, the budget~needs tO be amended to create and fund a
capital improvement project for the purchase of a new chiller at the
Cubberley Theatre and to reimburse the Cubberley operating expense
account for the lease of a temporary chiller; and
WHEREAS, the additional appropriation of funds from the
General Fund Budget Stabilization and Infrastructure Reserves is a
one-time cost and no future year ongoing costs are anticipated~ and
WHEREAS, City Council authorization is needed to amend the
2000-01 budget as hereinafter set forth.
NOW, THEREFORE,~-the Council of the City of Palo Alto does
ORDAIN as follows: ~
SECTION i. CapitaT: Improvement~Project (CIP) 10120, Cubberley
Theatre Chiller Replacement, is hereby created.
SECTION 2. The sum of One Hundred Forty Two Thousand Dollars
($142,000) is hereby appropriated to Capital Improvement Project No.
10120 and the Infrastructure Reserve is correspondingly reduced.
SECTION 3. The sum of Twenty Two Thousand Dollars ($22,000) is
hereby appropriated to’ non-salary expenses in the Structures and
Grounds Functional Area in the Public Works Department, and the
General Fund Stabilization Reserve is correspondingly reduced.
SECTION 4. The transactions mentioned above will reduce the
Infrastructure Reserve from $12,377,000 to $12,235,000 and the
Budget Stabilization Reserve from $14,346,753 to $14,324,753.
SECTION 5. As specified in Section’2.28.080(a) of the Palo
Alto Municipal Code, a two-thirds vote of the City Council is
required to adopt this ordinance.
SECTION 6. This project has been determined to be
categorically exempt under Section 15302 of the California
Environmental Quality Act.
SECTION 7. As provided in Section 2.04.350 of the Palo Alto
Municipal code, this ordinance shall become.effective upon adoption.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
ATTEST:APPROVED:
City Clerk Mayor
APPROVED AS TO FORM~City Manager
Senior Asst. City Attorney Director of
Services
Administrative
Director of Public Works
City of pJo A to
ATTACHMENT B
Budget Amendment Ordinances Impacting General Fund Reserves Approved-To-Date ~000=01
Placeh~ ~ ~lmpactonthe
AO Already ~ ~ae , General FundB Description ~ ~¯cost’~Revenue~ , 20004)1 Adopted
BSR
Estimated
Future Year’
Ongoing Costs
Estimated Beginning Budget Stabilization Reserve 0ISR) Balance
Adopted Budget Addition to BSR
Public Safety Building - CIP 19~820
Planning Transcription Services
Office of Transportation Safety Grant
Arts Council Silicon Valley Grant
Cubberley Theatre Chiller Replacement - CIP 10120
$13,385,753
$1,075,000
($74,000)($74,000)
($40,000)($40,000) $40,000
($187,065)$187,065 $0 $17,000
($5,192)$5,192 $0
($22,000)($22,000)
BSR Balance After BAO’s I$14,324’753 I
Budget Amendment Ordinances Impacting Infrastructure Reserve Approved-To-Date in 2000-01
Placeholders , Impact on the: Estimated
BAO Description Cost Revenue Alre~ly In the General Fund Future Year¯2(~]-~:~ Adopted BSR Ongoing Costs~Jdget
Estimated Beginning Infrastructure Reserve Balance $12,377,000
Cubberley Theatre Chiller Replacement - CIP 10120 ($22,000)($142,,090,)
BSR Balance After BAO’s [ $12,235,000
ATTACHMENT C
PROJECT DESCRIPTION
This project will replace the air conditioning system at the Cubberley Community Center Theatre. A new air
conditioning system will be installed in the existing equipment room, and the controls will be replaced to optimize
temperature control and energy efficiency.
PROJECT JUSTIFICATION
The Cubberley Community Center Theatre is a multi-use facility that is rented out to the public throughout the year.
The existing air conditioning system, which is original to the building, no longer functions and is not repairable due
to its age and condition. Without air conditioning, this facility would be unusable during the summer months.
Restoring the air conditioning system will provide for continued year round use.
FUTURE FINANCIAL REQUIREMENTS
FISCAL YEAR AMOUNT "COMPONENTS
PY Budget
2000-01 $142,000
2001-02
2002-03
2003 -04
2004-05
Sources of Funding: General Fund Infrastructure Reserve.
IMPACT AND SUPPORT ANALYSIS
Environmental:
Design Elements:
Operating:
Telecommunications:
Purchase and installation of chiller
Categorically exempt from CEQA under Section 15301.
None.
None.
None.
COMPREHENSIVE PLAN
This project furthers Policy C-24 of the Comprehensive Plan.
451