HomeMy WebLinkAbout2000-06-12 City Council (10)City of Palo Alto City Manager’s Report TO:HONORABLE CITY COUNCIL FROM:CITY MANAGER DEPARTMENT: POLICE PUBLIC WORKS DATE:JUNE 12, 2000 CMR:279:00 SUBJECT:RESULTS OF PHASE ONE WORK ASSOCIATED WITH THE FOUR SITES UNDER CONSIDERATION FOR A NEW PUBLIC SAFETY BUILDING REPORT IN BRIEF In March 1999, Council authorized staff to proceed with the conceptual designs, cost estimations, and environmental assessments at four potential sites for a public safety building: 1) the existing Police building; 2) City Parking Lot 6 at 251 Sherman Avenue, 3) 2747 and 2785 Park Boulevard, and 4) Page Mill Road and E1 Camino Real. Additionally, Council directed staff to identify creative and cost-effective opportunities to deal with the current site deficiencies and to provide an associated economic impact analysis. Ross Drulis Architects, the City’s project consultants, and City staff have completed the following: major revisions to the original architectural program; a split-facility analysis; and preliminary environmental assessments, economic impact analysis, cost analyses, and conceptual designs for the four sites. This report summarizes the findings, proyides a summary of the advantages and disadvantages of each site and the split-facility concept, and will serve as the basis of discussion with the Council. Staff will return to Council in July with as specific site recommendation and request for approval to proceed with Phase Two of this project. CMR:279:00 Page 1 of 10 This information is presented as background for the June 12 study session on this issue. On July 17, staff will present site selection recommendations incorporating Council’s input from the June 12 study session. Due to the length of the project definition document, copies are not being included for general packet distribution, but are available at the Police Department for interested citizens. BACKGROUND In 1997, the City completed a preliminary needs analysis to determine if a new public safety facility should be pursued. The preliminary analysis concluded that, based upon the age of the building, the growth in the Police Department, the changes in codes and standards for police facilities, and the significant changes in basic law enforcement procedures and operations that have occurred over 30 years, the current building does not meet the Department’s programmatic needs, is operationally and technologically deficient, . and does not conform with many current codes and standards. The study identified eight major areas in the Police Department which required attention if efficient and effective public safety services were to continue to be provided: evidence processing and storage, prisoner processing and detention, locker rooms/equipment and records storage; conference room/interview/office space availability; technology~ training, vehicle parking, and a dedicated Emergency Operations Center (EOC) (CMR:342:97). The study confirmed that the Police Department was in violation on a number of codes and was unable to comply with certain standards relating to prisoner processing and evidence processing, handling, and storage. The study also found that the existing lighting, electrical service, emergency power and other infrastructure is inadequate, has no capacity for expansion, and under certain circumstances (e.g. major earthquake) could render the current facility inoperable. It was determined that the current building would have great difficulty in accommodating new technologies. In addition to general inefficiencies and the inability to meet legal requirements, the study concluded that the current facility presented health, safety risks and security risks. The study also looked at the needs for the Fire Department Administration. As a result of this analysis, the Council concluded that there was a very compelling case to move forward with planning for a new facility and directed staff to formally initiate the process needed for site selection and construction of a new building. The Council reinforced this ¯ decision in December 1998. After reviewing a list General Fund capital projects, the Council approved a recommendation that a new public safety building be included in the list of top priority projects for initial funding. Between July 1997 and March 1999, City staffand the consultant hired by the City, Ross/Drulis Architects, completed a draft architectural program, prepared a preliminary site survey and evaluation, and conducted considerable community outreach. Based upon that work, in March CMR:279:00 Page 2 of 10 1999, staff recommended that Council provide direction to proceed with the conceptual designs, cost estimates and environmental assessments for a public safety building at four potential sites: Site One - Existing Police Building Site Two - Downtown Library Site at 270 Forest Avenue Site Three - City Parking Lot 6 at 251 Sherman Avenue Site Four - 2747 and 2785 Park Boulevard Council approved proceeding with further analysis of Sites One, Three and Four. However, the Council removed the Downtown Library site from consideration due to its proximity to residential areas and the strong organized public opposition from those areas; and added the site at Page Mill Road and E1 Camino Real to the list. Additionally, Council directed staff to identify creative and cost-effective opportunities to deal with the current site (split-facility study) and to complete an associated cost analysis. Staff returned to Council on May 24, 1999, with a Budget Amendment Ordinance (BAO) to cover the costs of the revised scope of services for Ross Drulis Architects. The revised scope of services included the completion of the split-facility study and a detailed economic impact analysis for each of the four sites. Since then, the consultants, with City staff assistance, have: - revised the original architectural program - completed a split-facility operational and. cost analysis - conducted a preliminary environmental assessment and comparison for each site - developed conceptual designs for each site - completed an economic impact analysis for each site, and - prepared a cost analysis for each site . This report summarizes the conclusions of each of these tasks and provides the advantages and disadvantages for each site, as well as the split-facility study. The attached project definition document provides detailed information. DISCUSSION Architectural Program As a result of the comments and discussion by Council, in March 1999, staff and the consultants completed several reviews and significantly reduced the original architectural program. Staff CMR:279:00 Page 3 of 10 concurred with Council comments and as a result, the program included in the attached document reflects a 26 percent reduction in the size, compared to the originally proposed program. After reviewing all the information, staff believes that it is essential to proceed with a facility that would house the Police Department, the Communications 9-1-1 Center, and the Emergency Operations Center (EOC). Inclusion of Fire Department Administration in the new building would be eliminated from further consideration. Staff believes that a public safety building totaling approximately 52,700 feet would provide adequate space for next 20 to 30 years and is consistent with the International Association of Chiefs of Police (IACP) facility guidelines for police buildings. It is important to note that a large part of the space is required to complete tasks such as evidence handling and processing and storage, interviewing of crime suspects, victims and witnesses, emergency response, prisoner processing and equipment storage. The staffing projections, that have been made as part of the architectural program process are based upon staff’s best estimates for community needs, crime issues, technology forecasting, and .demographic predictions for the next 20 years. Areas that staff believes additional personnel resources will be needed in the future include traffic, parking and high-tech investigators. This process, used by every jurisdiction that plans for new public safety buildings, is followed to project space needs for police departments. In discussions with numerous other cities who have built public safety facilities within the last five to ten years, it is very apparent that those cities who underestimate future needs or reduce up-front costs usually end up spending significantly more dollars to correct their projections and/or deficiencies. Staff clearly understands that any additions to the Police Department’s staffing authorizations would go through normal budget and Council approvals over the life of the facility. Split-Facility At Council direction, the consultant completed a split-facility study that looked at various alternatives to the construction of a new full-sized, full-service public safety building. As detailed in the attached document, six options were analyzed relativeto operational considerations, staffing projections, building size, and costs. While several of the split-facility options are theoretically feasible and initially cost less for construction, staff only recommends pursuing the one that reflects a facility that would include the Police Department, Communications Center, and the City’s EOC. The others are not recommended due to cost considerations, the need for increased staffing resources, inefficiencies and space redundancies. If different divisions of the Police Department were to be housed in separate facilities, some degradation in the Command and control of the organization would occur. Redundancy in some CMR:279:00 Page 4 of 10 staff positions would also be required, resulting in higher long,range costs for the City. As an example, currently Traffic, Parking, Special Events, and Police Reserve staff all share the same clerical personnel. If Traffic and Parking offices were to be located in a separate building, clerical staff would be needed for both locations. Other inefficiencies would also occur. Traffic officers provide back up to patrol officers in many calls-for-service and their frequent interaction at .briefings, meetings, and training with patrol officers is required. Loss of productive time would result if officers were required to travel between Department locations. After reviewing the architectural program, cost estimates, and the size of the space at each of the four sites, staff believes that only split-facility option number three should be pursued. While the Fire Department would certainly use the training and conference rooms in the new building, staff believes it would be prudent to handle Fire Department administrative functions in existing facilities. Because a new building would be built to "essential facility" standards that would ensure, continued operations after a major earthquake or disaster, it would be important to include the Communications Center and the City’s EOC in the new public safety facility. Site Comparisons After a review of all the information, it is clear that one perfect site does not exist, but that there are advantages and disadvantages to each one. Based upon all of the information obtained to date, the following is a summary of the advantages and disadvantages for each site. 1)Current Site Advantages: ¯ Property Ownership: The City owns the property and therefore land acquisition expenditures would not be a factor in the costs for the building. ¯Zoning: No zone change would be required. Disadvantages: ¯ Cost: The expansion of the current facility is one of the most costly of the alternatives studied. Approximately $10 million would be needed for temporary relocation costs. This would have to be considered a one-time cost that would not result in additional assets for the City. ¯Size: In order to achieve the needed square footage, three additional stories would have to be added. The size of the structure so close to a residential area would be incompatible. ¯Operational Disruption: If the current site was expanded, a temporary-leased facility of adequate size would have to be found, and the Police Department CMR:279:00 Page 5 of.10 2) would need to be relocated during the time of construction. The disruption associated with two complete moves (one to a temporary site and one to the expanded facility) would be significant. Additionally, based on the information provided in seismic evaluation, the Council Chambers would not be available for use during the time of construction. Unavailability of Space for Other City Use: Expansion at the current site would preclude the space being used for other City purposes. Staff has had preliminary discussions about the potential of using the space that would be vacated by the Police Department for the City’s Development Center and/or the Fire Department Administration. Another location would have to be found or a continuation of the current costly leased space arrangement would be needed to keep the Development Center operational: Time Delay: There could be a delay of up to one year in the actual expansion project created by the search for a temporary facility and negotiation of a lease agreement, the purchase and installation of equipment for a temporary Communications Center, and the relocation of remaining furniture and equipment. The consultant’s estimate that each year of delay in the project at this site represents approximately $1.26 million in additional construction costs, due solely to inflation. Sherman Avenue Parking Lots Advantages: ¯ Property Ownership: The City owns the property and land acquisition costs would not be a factor. ¯Size of Property: The size of the property is conducive for a public safety building. ¯Use of Civic Center Space for Other City Needs: As noted above, the space vacated by the Police Department could be used for the City’s Development Center, the Fire Department or other purposes. ¯Zoning: Because this location is already zoned Public Facilities (PF), no zone change would be required. Disadvantages: ¯ Parking Garage Construction: Prior to the construction of the public safety building, a replacement parking structure would need to be built in order to accommodate the parking needs of the California Avenue business district. The construction of a garage would extend the disruption to the area by about 12 CMR:279:00 Page 6 of 10 months and would delay the actual safety building project by that amount of time. Again, this would add to the construction costs of the building. Cost: Due to the cost of constructing the parking garage, as well as the costs of delaying the .project ($2.2 million per year), the analysis revealed that this site would be the most costly for a police building. Economic Impact to Businesses: Based upon the information in the economic impact analysis report, businesses in the area could expect to experience a temporary loss in revenue during construction. There would be a reduction in the number of customers that would frequent the businesses due to the disruption and temporary loss of parking. Community Opposition: Of the four remaining sites on the list, this site is the most controversial. There has already been considerable public opposition, especially by California Avenue business owners and residents of the Palo Alto Central condominium complex. 2747 and 2785 Park Boulevard Site Advantages: ¯ Current Occupancy: With the exception of the office building on the small portion of the site (2747 Park Boulevard), there are no structures on this site. ¯Cost: Even considering land acquisition, the cost estimates for this site are the lowest on the list, $4 to $15 million lowerthan the other locations. ¯Public Support: Of all the sites, this one has received the most public support and is the least controversial. Disadvantages: ¯ Property Ownership:The two parcels associated with this site are privately owned. The owner of at least one of the parcels has indicated through third parties that he would not be interested in selling the property. Environmental Concerns: The preliminary environmental assessment indicated that there may be the potential for significant environmental impacts including impacts on local traffic. The completion of one initial study and a full environmental impact report (EIR) would be required to determine the extent of the impacts and what mitigation measures would be needed to reduce the impacts to less than significant levels. It should be noted that similar potential impacts have been identified at all four sites that are under consideration. An EIR would also include a study that would identify any hazardous materials on the site and would prescribe appropriate mitigation measures where necessary. CMR:279:00 Page 7 of 10 Zoning: This site is currently zoned for General Manufacturing (GM) uses. The project would require that Planned Community (PC) zoning be adopted for the property. 4) .Page Mill Road/El Camino Real Advantages: ¯Current Occupancy: There are currently not any structures located on the property. ¯Size of Property: The size of the property would allow for the construction of the public safety building without the need for subterranean construction. Disadvantages: ¯ Property Ownership: The property is owned by Stanford University. During very informal discussions that occurred early in the process, Stanford representatives indicated that they would not be interested in selling the property to the City. ¯Environmental Concerns: The environmental assessment revealed that a groundwater plume .at the adjacent Superfund site may affect sub-grade-areas of the site. A full EIR would be required to determine the impact and the extent of mitigations. ¯Zoning: This site is currently zoned for Multi-Family Residential (RM-30) and would require a zone change for a police facility. Green Building Concept The construction of a new police building provides an opportunity for the City to initiate its vision of "green building" strategies. The building could serve as a model for the implementation of environmentally sensitive building construction. Design of the project could include green building, elements such as day-lighting, the use of recycled building materials, energy conservation, and water efficiency planning. While the initial costs associated with the use of green building strategies may be expected to add 15 percent to construction costs, over the life of the building, significant cost reductions related to maintenance would result. The estimated annual operational costs listed in the attached document do not reflect these long-term operational cost reductions, but substantial reductions would be expected. Upon conceptual approval of the green building concept by City Council, staff will include an expert on the design team to conduct a.life-cycle benefit analysis that would be conducted as part of Phase Two of the project. CMR:279:00 Page 8 of 10 Public Art In keeping with the City’s policy of including public art in new facilities, staff has included two percent of construction costs for public art in the estimates. Depending upon the site, these costs range from approximately $592,000 to $997,000. RESOURCE IMPACTS A total of $389,320 has been spent on this project to date since 1997. Staff will return to Council with a Budget Amendment Ordinance that would cover Phase Two of the project costs at the same time a recommended site is presented for Council approval on July 17. Phase Two costs are estimated to :be approximately $1.5 million. Funding for site acquisition and construction is anticipated to come from debt financing. The debt financing is also anticipated to recover all costs incurred in Phases I and II, leading up to construction. Phase Two tasks would include completion of an EIR, preliminary design, geo-technical analysis, green building evaluation, and public outreach. The following are the estimated costs for each site: Initial Construction Costs Site Mitigation Costs Green Building & Allowance for Public Art Land Acquisition Costs Soft Costs @ 30% Total Existing Civic Center $29,645,5O0 California Avenue Area $31,750,000 Park Boulevard $32,527,OOO E! Camino / Page Mill $29,595,000 $10,234,000 $11,587,000 $0 $0 $5,040,000 $7,501,000 $5,530,000 $5,031,000 $0 $0 $2,364,000 $13,653,504 $I0,405,000 $15,258,000 $11,417,000 $10,387,800 $55,324~500 $66,096,000 $51,838,100 $58,667,304 CMR:279:00 Page 9 of 10 While there has been a substantial reduction in the amount of space compared to the original estimates, due to the addition of green building and public art costs, the total estimated costs of the facility have not changed significantly. ENVIRONMENTAL REVIEW Preliminary environmental assessments on the four sites are attached. A full environmental impact report on the selected site would be included among the tasks as part of Phase Two of the proj ect. ATTACHMENTS CMR:342:97 Public Safety Building Project Definition Document PREPARED BY: Lynne Johnson, Assistant Police Chief DEPARTMENT HEAD REVIEW: PATRICK of Police GLENN ROBERTS, Public Works Director CITY MANAGER APPROVAL: HARRISON,Manager CMR:279:00 Page 10 of 10 City of Palo Alto City Manager’s Repor t TO:HONORABLE CITY COUNCIL FROM: AGENDA DATE: SUBJECT: CITY MANAGER JULY 28, 1997 DEPARTMENT:POLICE FIRE CMR:342:97 NEEDS ANALYSIS AND RECOMMENDATION FOR APPROVAL TO INITIATE FORMAL PROCESS FOR ~ BUILDING OF A NEW PUBLIC SAFETY BUILDING. Sta~ with assistance f~om EKONA Architecture and Planning, have completed a preliminary needs assessment relative to current and future space and building requirements and a study investigating the feasibility of constructing a new publiC safety facility. This report provides Council with the findings of the study. As a resultof the information obtained from this work, staff’requests Council approval to formally initiate the process required for the site selection and construction of a new pubfic safety building. Staff would return to Council at a later time with a request for funding that would be needed to hire consultants to assist with the completion of a more formal and detailed’ needs assessment, feasibility study and site selection evaluation. RECOMMENDATIONS Staff recommends that Council direct staff to formally initiate the process needed for site selection and construction of a new.pubfic safety building. POLICY IMPLICATIONS " - This proposal does not seek to change the level of- services provided b~ the Police and Fire Departments in the City. The consolidation of the various divisions and the two departments into an efficiently laid out, technologically advanced facifity will enhance existing operations, reduce potential liabilities, and increase efficiency and productivity of personnel. The proposal is consistent with the City Council’s existing priority on infrastructure and with the proposed Comprehensive Plan section on Community Services and Facilities. CMR:M2:97 Page 1 of 13 BACKGROUND_ The Police Department and the majority .of the Fire Department’s administrative staff are housed in the Civic Center, which was built in 1970. Since the time of construction, a number of piecemeal changes have been made to the original design in efforts to accommodate additional pubfic safety space needs, changes in the way business is conducted, and the increases in public .safety staff. However, these and other stopgap measures have not adequately kept pace with the changing pubfic safety environment. The 27-year-old facility no longer provides an efficient, code or legally compfiant environment. Based upon projections for the next 20 years, the deterioration of the usefulness of the facility will result in even greater safety, health, ~md security concerns. As a result of these concerns, staff completed a preliminary assessment of current and future space needs and identified specific operational deficiencies ~.associated with the facility. With the assistance of EKONA Architecture and Planning consultants, a preliminary feasibility study for expansion of the existing building or the construction of new structure has been.prepared. This report provides detailed information regarding the process used in this assessment, themajor areas of concern, a summary of the ¯potential options and primary issues for City Council consideration and possible funding mechanisms. DISCUSSION Staff con. ducted an internal assessment of curr~nt and future public safety needs based upon personnel, technology, operational considerations and State and local code requirements. Staff reviewed current services provided and developed projections for the next 20 years regarding staffing and service levels. It should be emphasized that ~ preliminary needs assessment was not intended to be a detailed comparison between current existing conditions and ideal conditions or an architectural design. A project team consisting of the Assistant Police Chief, Deputy Fire Chief~ Acting Assistant Director of Public Works, Public Works Engineer, and an Administrative Services Senior Finaacial Analyst was formed. As. part of the study, the project team visited a number of other cities which have recently built or are in the process of building new public safety facilities." The purpose of these visits was to determine what they experienced and concluded during completion of their needs analysis, design, and construction phases, what things they did well and what things they would do differently. Attachment One is a matrix that provides information about these other agencies’ building projects. While this work was being completed, a Request for Proposal (RFP) was developed for consultant services to review and analyze the data. gathered by the project team; to project space needs for the next 20 years based upon demographic and departmental information; to assess CMR:342:97 Page 2 of 13 the cun:ent ~ctural con~tion of the e~-sting facilities; and to evaluate potential options. The RFP was sent to five consultant firms; four responses were received. The project team reviewed the proposals and Selected three for an interview (the fourth company asked to be removed from consideration). Based upon information received in the proposal and the interview, the project team selected EKONA Architecture and Planning to assist in. the completion.of the study. EKONA has extensive experience in pubfic safety facility analysis, and design. The agreement was less than $25,000, so Council approval was not required. The City Manager’s contingency fund was used to pay for the study. Areas of Ma_ior Em_nhasi~ During the initial needs assessment process, staff identified eightmajor areas which require attention due to operational and procedural changes; judicial and legal decisions that have already taken place; and anticipated changes that most probably will occur during the next five years. These areas include training; evidence processing and storage; prisoner processing and detention; locker rooms/equipment and records storage; conference room/interview/office space availability; technology; vehicle parking; and a dedicated Emergency Operations Center (EOC). While the detailed list of operational deficiencies is included in the ~ttached consultant’s report, the following is a sunmuuy of the issues associated with each of the major areas: Txaiaillg - The quantity, methods, and variety of training which are required for police and fire employees has increased substantially over the years. On an average, fire fighters and pofice officers receive about 250 hours of training annually per employee. " The medium used for training is also undergoing significantmodification. In place of the traditional classroom, teacher-lecture format, a transition to simulation and interactive/video individual training is occurring. This process reduces costs.associated with sending employees off-site and, on many. occasions, out of town for training; however, space is needed in order to have the training equipment available for use by staff at any time. It should also be noted that, presently, the Police Department rents the training space at the Cubberley site-over 350 hours a year at a cost of almost $10,000. The Fire Department’s annual cost for use of the Cubberley space is approximately $5,200. If space were available in a public safety building for this and the other training mentioned, not only would therebe a cost savings, but the space atCubbedey would be available for rental to other organizations. Pofice and Fire would share the training room in order to maximize its use. Evidence Processin~Storag~ , The importance of proper evidence processingand storage and the critical role evidence plays in successful prosecutions of criminals has gained significant attention over the last several years. The mishandling, improper CMR:M2:97 Page 3 of 13 storage, or incomplete analyzing of crucial pieces of evidence can have severe consequences, such as charges not being filed by the District Attorney, mistrials, and acquittals. The methods of retrieval and the types o£ evidence items collected have undergone substantial changes due to advanced technology. The conventional p~ocess of dusting for fingerprints is rapidly becoming obsolete and the use of Chemicals and equipment such as ninhydrin, fume hoods and laser instruments is becoming the norm. While the Police Department currently has a fume hood located in one o£the general evidence storage rooms, the space surrounding the hood is cramped and inadequate, making the task of processing larger items awkward and potentially dangerous.. . The use of DNA comparisons in identification of suspects and victims was only a theory in 1986. Today, this technique is widely used, especially in major homicide and sexual assault cases. The processing of DNA ev!.’dence requires very specific conditions and space resources. In order to safely deal with pathogens on materials that are-still wet with blood and other substances, to collect all available specimens that may drop off the items while they are drying, and to conveniently and safely allow for subsequent cleanup, special biohazard materials storage containers should be used to dry the items. These containers require special ventilation. Large freezer units are then needed for storage of the items, until they can be destroyed..The containers and freezer units require a considerable amount of space that is not available in the Police building. As a result, when fitced with the task of dealing with these items, Police evidence technicians must do their best to improvise. The use of photographs, video and audio tapes as evidence has also increased sub.stantially over the years. Up until 14. years ago, Police Department staff developed ana printed all evidence photographs in a well-equipped darkroom. The darkroom was dismantled, however, when space Was needed for data entry and records staff work stations. Since then, outside vendors have processed all photos. While, fortunately, Palo Alto Police have not yet experienced any situations similar to some other agencies where their prosecutions have been jeopardized after employees of private processing vendors have released photos to the press and other people, there have been problems that have arisen regarding the timeliness with which the processing takes place. There ,are few, if any, v~dors available for printing of photographs on weekends or in the early morning hours. This has resulted in the loss of valuable investigative time in certain cases while waiting for the store’s normal business hours. Similar issues involve the expanded use of video and audio equipment for crime scene investigations and victim, witness and suspect recordings. Presently, the only space available for the playing and duplication of these tapes is again in a cramped corner of CMR:342:97 Page 4 of 13 one of the general property storage areas. Additional room is necessary for the equipment. The processing of vehicles used in major crimes is also of concern. Ideally, the vehicles should be totally secured in an area that has extremely limited access. Currently, vehicles must be parked in the pofice garage. This presents two problems: l) the limited amount.of secured space for pofice vehicles is reduced even further, and 2) there is no guarantee that contamination of evidence in/on the vehicle will not occur as numerous employees have access to the police garage. Prisoner Processin_p~Detention Ar~a - State law now requires that there not be any contact between adult prisoners and minor prisoners who are being held in temporary custody. Contact is defined as any communications including verbal, visual or immediate physical presence. In the Police Department’s current building configuration, this separation is exb’emely difficult and, on rare occasions, is impossible. The recent arrests of five suspects (three- adults and two juveniles) simultaneously in the Kay homicide clearly illustrated the Department’s.inability to meet this requirement. The present configtwafion consisting of two holding areas located directly adjacent to the property/evidence room result in inefficiencies and safety concerns.. While this area has been made as secure as.possible within existing space constraints, the level of security and the lack of a separate prisoner transport sally port necessitate the presence of at least two officers to ensure the safety of personnel. Not only are a minimum of two officers required while .suspects are being escorted to/from patrol vehicles, but also during the period of time the suspects are held in the temporary holding cells. This results in one less officer being available to respond to calls for service. Thebooking fees the city pays to the County (estimated to be about $173,000 for FY 1997-98) have been a source of considerable discussion over the last six years. In attempts to reduce the fees Palo Alto,.along with other Cities in the county, has decreased the number of suspects actually booked. With the exception of violent or very serious felony offenders, many arrestees are released after a citation has been issued to them. In continuing efforts t~o reduce booking fees, a county-wide satellite booking plan is being finalized for implementation within the next two years. Under this plan, each police department would have computer access to the jail computer system that would enable entry of the required arrestee information to be completed by the arresting officer at his/her own facility. This work, together with the fingerprinting and photographing of the arrestees, will be finished at each agency prior to the transportation of the individuals to jail. The intent of the plan is not only to reduce fees, but also to decrease CMR:342:97 Page $ of 13 the loss of productive officer time ~frequently spent waiting in line at the jail. for the processing of arrestees. Due to configuration of Palo Alto’s present temporary holding area and the less-than-ideal level of security, for the safety of the Department’s officers, Police staff does not anticipate participating in the program until such time improvements can be made to the current situation. Locker Room/Equi_oment and Records Storage. - The amount and types of equipment issued to police officers today differs signific .antly from that issued 10 to.20 years ago. Previously, officers shared portable radios which were recharged in units located in each patrol vehicle, used flashlights that required regular alkafine batteries, and handwrote their reports on NCR .forms. Today, each officer is issued his/her own portable radio with batteries which are recharged in special charging um’ts; halogen flashlights which must be recharged; and laptop computers to prepare their reports. Additionally, the equipment associated with specialized teams such as SWAT, canine, commercial tra~c ¯ enforcement, and accident reconstruction continues to require more and more storage space. At the time the present facility was built with only one locker room, there were not any female pofice officers in the department, nor other female employees in positions such as community service and parking enforcement. Since then, there have been up to 35 female employees at one time requiring lo~kers. As a result, due to. the lack of space and the costs associated with additional remodeling, there are now five different locker rooms of different sizes and configurations. Even with the addition of these other locker rooms, there is not adequate space. Lockers for officers assigned to the detective division are on a stairwell landing that does not provide for any priva~. Space needed for the storage of bicycles that have been recovered or that are¯ being held as evidence has been a problem for some time. Approximately 50 bikes are retrieved per month~ While police staff return, a number of the bikes to owners when proof.of ownership is demonstrated, at any given time there is an accumulation of well over 200 bikes..Presently, some bi~eS are kept in the police garage. Other bikes are stored in large containers at theCity’sMunicipal Service Center 0VISC). This situation is very. inefficient, in that staff or volunteers are forced to make numerous trips back and forth to the MSC to allow citizens to view bikes for possible identification or pick up bikes that have been determined to belong to them. Also the continual need to transport the bikes back and forth has already been the cause of some employee back injuries caused from the lifting of the bikes. ¯ Page 6 of 13 t Due to lack of storage space, Police personnel records are currently kept in file cabinets which are in unsecured common areas or in a staff member’ s office. The consequences include compromised integrity of records, as well as numerous interruptions to work. There is not any centralized storage space for Fire Department administration records or standard office supplies, causing files to be stored in boxes under or beside desks, and most suppliesto be kept in remote areas. This situation not only creates a safety hazard, but also does not provide for convenient access or organization. Conference/Interview Rooms/Office Space - Sufficient room is not available for interviews with.victims and/or witnesses. Only one actual interview room exists and its availability has been limited in the past when the room has been utilized for other purposes, such as volunteer work space. It is not uncommon, therefore, for interviews to be conducted in the public lobby area or in detectives’ offices, resulting in the lack .of confidentiality of information received :from citizens, and a compromise in employee sffety. The lack of conference rooms, especially those which would accommodate six people or fewer, together with the number of offices that are shared by two or more .people, impedes private counseling sessions or .uninterrupted private mee.tings: A shortage of office/workspace continues to be a significant issue forboth the Police Department and Fire Administration. In 19"/0, Pofice Department staff totaled 136 and the Fire Department 96.. Since then, the number of Pofice Department employees has increased to 16"/.5 and the Fire Department to 123 positions. While there is not a one- to-one correlation between the number of staff and the number of offices/work spaces, the increase in the nmnber of employees over the years.has created a severe office/work space shortage. At the time the .Civic Center was constructed, the use of volunteer~,, other than police reserve officers, was not even a consideration. Today, the Police Department has a very active complement of volunteers; about 35 volunteers, provide services on a weeHy basis. The environment in which they currently work is cramped, inconvenient and not conducive for attracting additional volunteer assistance. Today, Fire administrators are spread out over four completely different locations, the repercussions of which include unproductive time spent traveling to/from meetings and inefficient day-to-day operations. CMR:342:97 Page 7 of 13 o Q ~ - The increased use of technology in the day-to-day public safety operations has been significant over the last 10 years. It is impossible to complete routine types of tasks without the assistance of computers. As an example, officers are writing police reports on personal computers and notebooks. Lack of existing space has meant the Police Department has had to setup computer work stations in the Police briefing room, and temporarily relocate its daily watch briefings into the existing Emergency Operations Center (EOC). The Police Department is accessing numerous ~’ederal, state, and local law enforcement and private databases, many of which require special installation and equipment. These computers are currently installed on a space available basis, rather than in areas where they can be most efficiently used. Additionally, much of the hardware requires special air conditioning and temperature control to ensure optimal operation. More electrical and wiring connections are also anticipated... The consultants have determined that the current electrical .system at the Civic Center has reached its maximum loading and provides no capacity for expansion. If Police and Fire intend on keeping up. with technological changes, this .problem must be resolved. As additional technologies become available and are implemented for daily .law enforcement operation (e.g., Computer Aided Dispatch (CAD), Automated Fingerprint Identification System(AFIS), and others): the current shortage of processing and work space throughout the Pofice Department will be exacerbated. Vehicle Parking, -Over the years, the number of police vehicles has increased. In addition to regnl~ patrol cars, vehicles have been added to the fleet, including trucks for community service o~cers, electric Cushmans for the parking enforcement officers and, most recently, motorcycles for the traffic team. Including the unmarked cars used by detectives, there are 65 cars assigned to the Pofice Department that must have parking available in .the Civic Center. Originally, the secured pofice garage was .built with parking spaces for 31 .vehicles. Since then, a ~otal of eight spaces have been lost due to the building retrofit work that was ,completed several years ago; space needed for the motorcycles; and space needed to park and recharge the electric Cushmans. As a consequence of the lack of secured parking, the remaining patrol and unmarked vehicles must be kept in the Civic Center garage when not in use. As a result, .some patrol cars have been the target of vandalism. Dedicated Emergency_ Operations Center .(EOC) - For over the past 15 years, the City’s EOC has been used for various other purposes, including computer training and CMR:342:97 Page 8 of 13 conference room. Cun’ently, it serves as the Police Department’s shiiYbriefing room. As a result, the City’s ability to mobiliz~e the EOC in the event of a disaster in a timely fashion has been impaired. A dedicated, fully-equipped EOC is needed in order to save time and resources during responses to disasters and critical incidents. POTENTIAL OPTIONS Based upon the information, that was gathered and analyzed, the .preliminary findings of the needs .assessment indicate that the Pofice and Fire Departments have alreadyoutgrown existing facilities and require approximately double the existing space. The original design and age of the current building, together with the changes in codes, standards, and the general way business is conduvted have resulted in inefficient operations and potentially unsafe conditions, and have left the City vulnerable to potential future legal actions. Three conceptual options were developed and evaluated as a result of this information. Option One looked at expansion and renova~on to the ~u’rent Police Department building. While this option certainly provides some relief to the operational a~d space deficiencies that have been identified, it leaves some unresolved issues (e.g., the lack of enough space for secured parking for police vehicles) and would require major disruptions to the entire Police Dep .ar~m. ent operations, for the.duration of the build-out.and renovation. Option Two involves the construction of a new facility at some other site. While this option would cost more, it certainly provides the most comprehensive solution to the deficiencies and needs. Additionally~ the vacated space at the current site could be used forother City departments and services. The consultants and staff believe that this option best meets the City’s needs.. Option Three is to do nothing. While there are no concrete costs associated with this option, the potential impact resulting from legal actions, health, Safety, and security concerns, and the continued inefficiencies of operation would over time be substantial. PRIMARY ISSUES FOR COUNCIL CONSIDERATIOI~y Staff believes three issues are critical in Council’s consideration of recommendation to pursue development of a new public safety building. selection, potential use of the vacated Civic Center space, and funding. the proposed These are site CMR:342:97 Page 9 of 13 ~ - A crucial part of the proposed formal process wouldbe a comprehensive site evaluation. The process used for selection of an appropriate site and the impact on the surrounding neighborhood would require considerable attention. During thecourse of .the preliminary feasibility .study, limited discussion took place regarding the availability 0fpotential sites for a new building,. The increase in project costs associated with the purchase of property (estimated to be about $I0 million) compared .to using City-owned property would be substantial. Additionally, the farther away the site would befrom City Hall, the greater the costs for the required dedicated computer and telephone hook-ups. Staff briefly reviewed City-owned property and determined that there are three potential sites that meet the minimum size requirement. These include the Downtown Library, the current PASCO site on Geng Road and the property on Embarcadero Road adjacent to the Main Library. Formal evaluations of each of these sites wouldbe necessary prior to the development of any specific location recommendation. Because theie will be vaDring .levels of impacts to adjacent neighborhoods associated with each option, staff intends to facilitate participation from. the residents of thosd neighborhoods as part of the decision making process. An additional factor that enters into the site selection p~’ocess is Council’s direction on the library master plan that will be presented, to the Council within the next few months. Reuse Of Civic Center Spa~. - There are numerous alternatives for reuse of space that would be vacated at the Civic Center on the sixth floor, and in the Police wing. Some preliminary ideas include the potential relocation of the Downtown Library if’ that site was selected for the new public safety building; a one-stop permit center; and additional office space for other departments. While staff is not prepared at this time to make any specific recommendations, a logical course of action would be for the City to hire a consultant to evaluate the @aceand develop the recommendations as part of this overall effort. " Fundin_~ Mechanism - Other cities that have funded such capital expenditures have used various financing options. A common option, the use of redevelopment money, is not available to the City of Palo Alto. The options include: General Obligation Bonds: General obligation (GO) bonds can be issued to pay for capital projects related to real property acquisition, new building construction, and major renovations to existing buildings or building systems. ~ GO bonds generate a.new source of funding through a lien on property tax bills of all Palo Alto properties. The issuance of general obfigation bonds requires a general election and the-approval of two-thirds of the voters. ¯ CMR:342:97 Page 10 of 13 Because GO bonds are paid for through additional revenue ~rom property taxes, they have no impact on current General Fund spending levels or programs. In other words, because they provide additional fimds, they do not require that existing programs be reduced or other types of revenue increased. However, because this method of financing requires voter approval, it is more difficult to obtain. The City of Palo Alto has not issued GO bonds for many years. Certificates of Participation: Another financing mechanism available to the City is Certificates of Participation (COPs). With COPs, the financing is not technically considered "debt" but instead is a long-term lease. Because COPs are considered long-term leases, they are. exempt from the State Constitution’s requirement for voter approval of long-term debt. They are commonly used in California, and have been used by the City of Palo Alto to fund improvements at the Golf Course (1978) and the Civic Center for seismic improvements (early 1980s). .. COPs allow the City to raise tax-exempt funds through the leasinKof a public facility to a non-profit corporation that the City establishes as a separate legal entity. That entity enters into a long-term lease arrangement with the City to lease a City asset. Investors buy..shares of the lease payments in the financial markets. The proceeds from this .sale of the long-term leage are then used to fmance the construction of the improvements. The City pays back the investors by leasing the facility back from the corporation, with the lease payments senting as debt Service payments. At the end of the lease period, typically 20-25 years, the lease obligation is disencumbered and the City retains full title to the asset. As with GO bonds, COPs may be used to finance land acquisition, construction of new buildings, and major renovationsto existing buildings or building systems. Unlike GO bonds, the lease payments come out of the General Fund’s existing revenues, as no new revenue is generated. Thus, they obligate the City over the life of the payments, and potentially restrict the City’s future ability to offer new programs and services. Funding fi’om Reserves: Another financing option available is the use of reserves to.fund capital expenditures. Given the estimated expense of either option, while the whole cost could not be funded out of reserves, a portion of it could be, Page 11 of 13 do ¯ Pa_v As You Go: Another financing option is "pay as you go," which is how the ¯ City has historically paid for capital expenditures. Similar to the use of reserve funds, the projected cost of either option precludes this method of financing. STEPS/PROJECT TIMELINI~. Pending Council approval of staff’s recommendation to initiate a formal process for site selection, design, and construction of a new public safety building, the following represents the actual steps associated with the process and an estimated timeline: Initiate process for completion of a detailed needs analysis; architectural program; concept design; and site selection. August 1997 - September 1998. This step would include the selection of a consultant to assist with the formal needs analysis, identification of preliminary architectural issues, and evaluation of potential sites. Finalize financing plan, prepare preliminary design, Complete environmental impact assessment, and finalize relocation plan. October 1998 - August 1999.. Prepare final design, obtain appropriate permits, obtain financing, bid/award construction contract. August 1999 - June 2000. Construction of new facility. June 2000 June 2002. FISCAL IMPACT As indicated in the attached study, the estimated cost for Option 1 is approximately $19,200,000 and Option 2 is $31,600,000. It should be noted that these estimates have been escalated to the projected midpoint of construction. In other words, these are estimated for the year 2001 dollars. Projected costs for Option 2 include land acquisition costs and, if City- owned property was selected as the potential site, the property purchase price would be eliminated. If the land cost is eliminated, the cost of Option 2 would be approximately $2 million more than Option 1. Costs for both options include new furniture and equipment. It is important to point out.that estimated costs for Option 2 do NOT include those associated with renovation of the current Civic Center space currently occupied by the Police Department so that the space could be used for other services. Staff estimates these renovation costs would be several million dollars. ENVIRONMENTAL ASSESSMENT CMR:342:97 Page 12 of 13 An environmental assessment would be necessary prior to final decisions being made and . therefore would be part of the proposed formal process. A’I~I’ACHMENTS Attachment 1: Matrix of Other Cities’ Public Safety Building Projects EKONA Feasibility Study ¯ PREPARED BY:Lynne Johnson, Assistant Police Chief Judith A. Jewell, Deputy Fire Chief ¯ Shannon Gaffaey, Senior DEPARTMENT HEAD REVIEW: DURKIN, Police Chief ’ ROBEN G.RIJALV~ Fire Ch~f/d-’- " CITY MANAGER APPROVAL: Administrative Services .Director cc Joette Farrand Page 13 of 13