C ty Manager’s Report
2
TO:
FROM:
DATE:
SUBJECT:
HONORABLE CITY COUNCIL
CITY MANAGER
APRIL 10, 2000
DEPARTMENT: UTILITIES
CMR:194:00
APPROVAL OF AMENDMENT NO. 4 TO CONTRACT NO.
C8096901 WITH UNDERGROUND CONSTRUCTION CO., INC.,
FOR ELECTRIC UTILITY TRENCH AND SUBSTRUCTURE
INSTALLATION
RECOMMENDATION
Staff recommends that Council approve and authorize the Mayor to execute the attached
Amendment No. 4 to contract C8096901 with Underground Construction Co., Inc., to
increase the contract amount by $300,000 for a total contract price of $1,669,881.
BACKGROUND
The l~lectric Utility establishes an annual contract with a general contractor to dig trenches
and install conduits for electric utility customer services, small extensions, replacements to
the existing underground electric system and to install communications, street light, traffic
signal, and fiber optic conduits and foundations. Each small job is individually quoted, a
price agreed upon and payment made upon completion of work.
In July 1997, the City entered into a contract with Underground Construction Co., Inc., in
the amount of $377,627 for electric utility trench and substructure installation
(CMR:317:97). Underground Construction was selected as the lowest responsible bidder at
that time. Underground Construction has been working under that contract and has
performed very well.
The contract allowed the City and Underground Construction to extend the contract for two
more years, through the FY 1999-2000. In June 1998, the City issued Amendment No.1 to
the contract (Reference CMR:286:98), to extend the performance period through fiscal year
1998-99 and increase the contract amount by $377,627 for a total contract price of $755,254.
CMR: 194:00 Page 1 of 3
In January 1999, the City issued Amendment No.2 to the contract (CMR:123:99), to
increase the contract amount by $200,000 for a total contract price of $955,254. The
additional funds were used to construct projects that had not been anticipated and were not
included in the original contract estimate for FY 1998/99 work. In May 1999, staff issued
contract change order #2 to use the $37,000 contingency fund for additional unforeseen work
that have developed during the contract period. The change order increased the total contract
amount to $992,254.
Finally, in June 1999, staff issued Amendment No.3 to the contract (CMR:286:99), to
exercise the option of extending the contract for an additional, final 12 month period, as
stated in the original contract. At the time Amendment No. 3 was drafted, it was believed
that the contract amount used for FY 1999-00 ($377,627) would be sufficient for the entire
fiscal year. From July 2000 through February 2000, approximately $277,000 has been spent
and there is $100,000 in funding remaining on the contract. It is estimated that an additional
$300,000 is required for electric utility trench and substructure installation work for the
remainder of FY 1999-00, through July 31,2000. This will increase the total contract
amount to $1,669,881.
DISCUSSIO________~N
The primary factor which created the need for this coiatract amendment is the acceleration
of construction for the following three major projects:
Stanford Research Park Underground Cable/Equipment Replacement
Fiber Optic Service Connections
East Bayshore Underground Cable/Equipment Replacement
The construction of conduit and substructure systems for these three projects had not been
anticipated to be performed under this contract and was not included in the original contract
estimate for FY 99/00 work.
POLICY IMPLICATIONS
This report does not represent any change to existing City policies.
RESOURCE IMPACT
This amendment will increase the contract amount by $300,000. Funds for this work are
included in the 1999/2000 budget for Electric Fund CIP.
CMR: 194:00 Page 2 of 3
ENVIRONMENTAL REVIEW
Categorically exempt from California Environmental Quality Act (CEQA.)
ATTACHMENTS
Attachment:Amendment No. 4 to Contract No. C8096901
PREPARED BY: Sager Farraj, Senior Power Engineer
DEPARTMENT HEAD:
ULRICH
of Utilities
CITY MANAGER
HARRISON
Assistant City Manager
CMR: 194:00 Page 3 of 3
AMENDMENT NO. FOUR TO CONTRACT NO. C8096901
BETWEEN THE CITY OF PALO ALTO AND
UNDERGROUND CONSTRUCTION CO., INC.
This Amendment No.Four to Contract No. C8096901
("Contract") is entered into , by and between the
CITY OF PALO ALTO, a chartered city and a municipal corporation of
the State of California (~’CITY"), and UNDERGROUND CONSTRUCTION~CO.,
INC., a California corporation, located at 5145 Industrial Way,
Benicia, California 94510 ("CONTRACTOR").
RECITALS:
WHEREAS, the Contract was entered into
parties for the provision of electric utility
substructure installation services; and"
between the
trench and
WHEREAS, the parties wish to amend the Contract;
NOW, THEREFORE, in consideration of the covenants, terms,
conditions, and provisions of this Amendment, the parties agree.:
SECTION i. Section 2 is hereby amended, so that the Base
Contract amount for FY 1999-2000 shall be $677,627 for a total
contract price of $1,669,881.
SECTION 2. Except as herein modified, all other
provisions of the. Contract, including any exhibits and subsequent
amendments thereto, shall remain in full fo}ce and effect.
//
//
//
//
00307 c10071833
IN WITNESS WHEREOF, the parties hereto have by their duly
authorized }epresentatives executed this Contracton the date first
above written.
ATTEST:CITY OF PALO ALTO
City Clerk Mayor
APPROVED AS TO FORM:
Senior Asst. City Attorney
APPROVED:
Assistant City Manager
Director of Utilities
UNDERGROUND CONSTRUCTION CO.,
INC.
Name :
Title
Taxpayer Identification No.
76-0575471
Director of Administrative
Services
Insurance Review
(Compliance with Corp. Code § 313 is
required if the entity on whose behalf
this contract is signed is a corporation.
In the alternative, a certified corporate
resolution attesting to the signatory
authority of the individuals signing in
their respective capacities is acceptable)
00307 cl 0071833
CERTIFICATE OF ACKNOWLEDGMENT
(Civil Code § 1189)
STATE OF California
COUNTY OF Solano
)
)
)
On March 14, 2000 , before me, the undersigned, a
notary public in and for said County, personally appeared
Harry T. Robinson and Ann-~rieTalbot ,
personally known to me (or proved to me on the basis of
satisfactory evidence) to be the person(s) whose name(s) ~s/are
subscribed to the within instrument, and acknowledged to me that
heCtare/they executed the same in h~ht~r/their authorized
capacity(ies), and that by iri~h~=r/their signature(s) on the
instrument the person(s), or the entity upon behalf of which the
person(s)-acted, executed t~e instrument.
WITNESS my hand and official seal.
Notary Public