Loading...
HomeMy WebLinkAbout2000-03-06 City CouncilCity of Palo Alto City Manager’s Re t TO:HONORABLE CITY COUNCIL FROM:CITY MANAGER DEPARTMENT: PUBLIC WORKS DATE:MARCH 6, 2000 CMR:126:00 SUBJECT:APPROVAL OF A BUDGET AMENDMENT ORDINANCE FOR $30,100 AND REQUEST FOR AN INCREASE IN CHANGE ORDER AUTHORITY WITH O’GRADY PAVING FOR PAGE MILL ROAD/FOOTHILL EXPRESSWAY IMPROVEMENTS (CIP 19073) RECOMMENDATION Approve a Budget Amendment Ordinance (BAO) for $30,100 to increase Capital Improvement Project (CIP) 19073, Major Intersection Improvements. The funding will come from Pacific Gas and Electric (PG&E) ($10,100) and Santa Clara County ($20,000). (See Attachments A and B). Increase the contract change order authority with O’Grady Paving for contract C90112268 from $143,500 to $173,600. The increase is requested to reimburse proje.ct funds for the protection of a PG&E gasline and to upgrade intersection landscaping and/or pathways. DISCUSSION Improvements to the Page Mill/Foothill intersection are currently in progress, and include traffic signal upgrades, bicycle and turn lanes improvements, and median and roadside landscaping. The intersection is under the jurisdiction of Santa Clara County, which has responsibility for maintenance of the road. Due to the intersection’s importance as a main thoroughfare into the City, staff has, with County approval, taken the lead role for design, construction and funding. During construction a 24-inch gas line was discovered at a shallower depth than had been shown on the plans. In order to protect the gas line from potential future damage by excavation equipment, PG&E requested that the City install a concrete cap over the gasline. PG&E will provide $10,100 to reimburse the City for the cost of this work (see Attachment C, Item 3). CMR:126:00 Page 1 of 2 As a result of budgetary constraints, the City had eliminated or reduced the scope of. certain landscaping and pathway improvements that had originally been planned as part of the project. Santa Clara County has recently identified funds that could be used to Upgrade some of these landscaping or footpath improvements.The Coun~ will contribute up to $20,000 towards this work. RESOURCE IMPACT The attached BAO requests an additional appropriation of expenses and has no impact on the Budget Stabilization Reserve and no future year General Fund ongoing costs are anticipated as a result of this BAO. Attachment B summarizes the BAO’s approved to date in 1999-00 that impacts the General Fund Budget Stabilization Reserve. This attachment also estimates future year ongoing costs associated with BAO’s approved to date to provide a projection for the future resource needs from the General Fund for those programs approved after the adoption of the 1999-00 Budget. TIMELINE ImProvements to the intersection are expected to be substantially complete in March 2000. ENVIRONMENTAL ASSESSMENT An Environmental Assessment recommending a Negative Declaration was approved by Council on July 28, 1997. ATTACHMENTS Attachment A: Budget Amendment Ordinance Attachment B: Budget Amendment Ordinances Impacting the General Fund Approved to Date in 1999-00 Attachment C: First Amended Landscape Maintenance Agreement Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway PREPARED BY: Karen Bengard, Senior Engineer, Public Works DEPARTMENT HEAD: GLENN S. ROBERTS Directo/’~f Public Works CITY MANAGER APPROVAL://__JUNE ~LE~ U City Mana~.r~] CMR:126:00 Page 2 of 2 " ATTACHME NT A ORDINANCE NO. ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO AMENDING THE BUDGET FOR THE FISCAL YEAR 1999-00 TO PROVIDE AN ADDITIONAL APPROPRIATION OF $30,100 FOR THE MAJOR INTERSECTION IMPROVEMENTS CAPITAL PROJECT NUMBER 19073 WHEREAS, pursuant to the provisions of Section 12 of Article III of the Charter of the City of Palo Alto, the Council on June 28, 1999 did adopt a budget for fiscal year 1999-00; and WHEREAS, the Major Intersection Improvements Capital improvement Program Project 19073 was established to fund improvements to reduce traffic congestion and improve traffic flow; and WHEREAS, the Page Mill/Foothill intersection is under the jurisdiction of Santa Clara County, which is responsible for maintenance of the road; and WHEREAS, due to the intersection’s importance as a main thoroughfare into the City, staff has, with County approval, taken the lead role for funding and implementing the design and construction of improvements; and WHEREAS, improvements to the Page Mill/Foothill intersection are currently in progress, and include traffic signal upgrades, bicycle and turn lane improvement, as well as median and roadside landscaping; and WHEREAS, Pacific Gas and Electric (PG&E) requested that the CitY install a concrete cap over a gas line underneath the Page Mill/Foothill intersection to prevent future damage by excavation equipment and will fully reimburse the City for the cost of this work; and WHEREAS, Santa Clara County requested that the City continue certain landscaping and pathway improvements that had been eliminated or reduced due to budgetary constraints and will contribute up to $20,000 for the cost of this work; and WHEREAS, City Council authorization is needed to accept and expend the revenue from PG&E and Santa Clara County for the work described above; and WHEREAS, the additional appropriation of funds requested has no impact on the Budget Stabilization Reserve and no future year General Fund ongoing costs are anticipated as a result of this ordinance; and WHEREAS, City Council authorization is needed to amend the 1999-00 budget as hereinafter set forth. NOW, THEREFORE, the Council of the City of Palo Alto does ORDAIN as follows: SECTION i. Revenue in CIP Project Number 19073 is increased by the sum of Thirty Thousand One Hundred Dollars ($30,100) for receipt of funds from Pacific Gas and Electric ($20,000) and Santa Clara County ($i0,i00) o SECTION 2. The sum of Thirty Thousand One Hundred Dollars ($30,100) is hereby appropriated to Capital Improvement Program Project Number 19073, Major Intersections Improvements. SECTION 3 This transaction will have no impact on reserves. SECTION 4 As specified in Section 2.28.080(a) of the Palo Alto Municipal Code, a two-thirds vote of .the City Council is required to adopt this ordinance. SECTION 5. The Council approved a Negative Declaration for this project on July 28, 1997. SECTION 6. As provided in Section 2.04.350 of the Palo Alto Municipal Code, this ordinance shall become effective upon adoption. INTRODUCED AND PASSED: AYES: NOES: ABSTENTIONS: ABSENT: ATTEST:APPROVED: City Clerk Mayor APPROVED AS TO FORM:City Manager Senior Asst. City Attorney Director of Services Administrative Director of Public Works City of pJo Alto ATTACHMENT B Budget Amendment Ordinances Impacting General Fund Reserves,Approved-To-Date in 1999-00 Estimated Beginning Budget Stabilization Reserve (BSR) Balance Adopted Budget Addition to BSR Downtown Urban Design Improvements, CIP 19608 Salary and Benefit Increases Retroactive to July 1, 1999 for Management and Confidential Employees City Manager Executive Recruitment Friends of the Palo Alto Library Grant Arts Council of Santa Clara County Grant Palo Alto Art Center Foundation Donation Cost of Sound Wall for Tennis Facility at 3005 Middlefield Rd. IT Strategic Plan Citizens Options for Public Safety (COPS) Local Law Enforcement (LLE) Block Grant Downtown Parking Structure Feasibility Study, CIP 19530 Golf Course Management Agreement City Membership in ChildrenFirst Back-up Child Care Center Police Department Table of Organization Change Animal Services Fees Major Intersection Improvements, CIP 19073 $18,877,888 $1,214,000 ($120,349)($120,349) ($432,200)($432,200)($432,20~ ($26,000)($26,000) ($58,000)$58,000 $0 ($5,407)$5,407 $0 ($10,000)$10,000 $0($50,00O)($50,000) ($250,100)$60,534 $189,566 $0 ($317,917 ($135,901)$135,901 $0 ($26,192)$26,192 $0 ($308,000)($308,000) ($34,100)$103,900 -$69,800 ($26,000)($26,000)($26,00~ ($10,000)$0 ($7,00~ ($1,200)$1,750 $550 $1,70 ($30,100)$30,100 $0 $0 BSR Balance After BA O’s $19,199,689 As of 2/29/00 ATTACHMENT C FIRST AMENDED LANDSCAPE MAINTENANCE AGREEMENT Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway THIS LANDSCAPE MAINTENANCE AGREEMENT ("Agreement") is made and entered into as of the ~ day of ,1999, by the City of Palo Alto, a ehart~ere_d city, 250 Hamilton Avenue, Palo Alto, CA 94301, ("Applicant") and the COUNTY OF SANTA CLARA, a political subdivision of the State of California ("County"), collectively referred to herein as the "Parties" and individually, a "Party". RECITALS WHEREAS, the County is the fee Owner(s) of that certain real property located at ¯ Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway City of Palo Alto, County of Santa Clara, State of California, which property is more particularly described on Exhibit "A" at*ached hereto and incorporated herein by reference (the "Property"),~ and which property is depicted in the map attached hereto as Exhibit "B"; and WHEREAS, certain landscaping (the "Landscaping") is being iristalled and constructed within the County right-of-way along Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway as shown on Exhibit "B"; and WHEREAS, subject to and in accordance with the terms and conditions.of this Agreement, the Applicant has agreed to retain all responsibility for the ordinary maintenance and repair of the Landscaping; and WHEREAS, the Parties desire to memorialize these agreements in writing. NOW, THEREFORE, in consideration of the mutual covenants and conditions contained herein and other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Parties hereby agree as follows: 1.Incorporation. The above Recitals are hereby incorporated herein and made a part hereof. Maintenance and Repair. The Applicant shall, at no cost or expense to the County, at all times during the term hereof maintain, or cause to be maintained, the Landscaping in good, dean and orderly condition (the "Maintenance"). The Maintenance shall consist of the following: (a) trimming, clipping and mowing the Landscaping as necessary to keep the same in good, clean and orderly condition; (b) removing all papers, debris, filth and refuse to the extent necessary to keep the Landscaping in good, clean and orderly condition; and (e) pruning and trimaning the trees and shrubs as necessary, in such a manner as to not interfere with sight clearance for pedestrian and vehicle traffic on adjacent roadways; (d) maintaining and repairing irrigation systems exclusively serving the Landscaping; and (e) paying all costs and expenses~ for the water used to irrigate the Landscaping. In no event shall the Maintenance include: (i) maintaining, repairing or replacing public utilities; (ii) maintaining, repairing or replacing street lights, traffic signals or related fixtures or equipment; (iii) FIRST AMENDED LANDSCAPE MAINTENANCE AGREEMENT Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway maintainin, g, repairing or replacing storm drains, sewers or any other subsurface imprc~vements, except as specifically provided otherwise in (d) above; or, (iv) maintaining, repairing or replacing street improvements adjacent to the Landsqapi_ng, including, without limitation, curb and gutter: J Installation of Landscapinl~. County agrees to contribute a total of twenty-five thousand dollars ($25,000.00) towards the initial installation of the landscaping or pathway improvements. All other installation costs shall be the responsibility of Applicant. Indemnification and Insurance. The Applicant shall indemnify, defend, and hold harmless the County of Santa Clara (hereinafter "County") and, its officers, agents and employees from any claim, liability, loss, injury or damage arising out of, or in connection with, performance of this Agreement by Applicant and/or its agents, employees or sub-contractors, excepting only loss, injury or damage caused by the sole negligence or willful misconduct ofpersormel employed by the County. It is the intent of the parties to this agreement to provide the broadest possible coverage for the County. The Applicant shall reimburse the county for all costs, attomeys’ fees, expenses and liabilities incurred with respect to any litigation in which the Applicant is obligated to indemnify, defend and hold harmless the County under this Agreement. The Applicant shall maintain a program of self-insurance and/or insurance for general liability and ~vorkers’ compensation coverage in the amount of at least one million dollars per occurrence and in the aggregate. This coverage shall remain in force during the entire term of this Agreement. The Applicant shall provide evidence in the form of an opinion of legal counsel that the required coverage is in place. Attorney’s Fees..In the event a Party commences a legal proceeding to enforce any of the terms of this Agreement, the prevailing Party !n such action shall have the right to recover reasonable attorneys’ fees and costs from the other Party, to be fixed by the court in the same action. The term "legal proceedings" as used above shall be deemed to include appeals from a lower court judgment and it shall include proceedings in the Federal Bankruptcy Court, whether or not they are adversary proceedings or contested matters. The term "prevailing Party as used above in reference to proceedings in the Federal Bankruptcy Court shall be deemed to mean the prevailing Party in any adversary proceeding or contested matter, or any other actions taken.by the non-bankrupt Party which are reasonably necessary to protect its rights under the terms of this Agreement. 6.Recordation. This Agreement shall be recorded in the appropriate public records of Santa Clara County, California. 7. Term. This Agreement shall remain in effect until terminated by mutual agreement of ¯ the Parties or pursuant to Sections 9 or 10, below. FIRST AMENDED LANDSCAPE MAINTENANCE AGREE1VIENT Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway Inurement. This Agreement shall run with the land and shall inure to the benefit of and be binding on the Parties, and their personal representatives, successors apd _ assigns having a fee ownership interest in and to any part of Page Mill Road/Page Mill Expressway/Junipero Serra Blvd./Foothill Expressway. (Property Address) Termination by County. In the event Applicant fails to maintain the landscaping as required herein, County shall give Applicant a minimum of 30 days notice to come into compliance with this Agreement unless there is an immediate safety concem. In the event of an immediate safety concern, or after 30 days notice, County may, at its option, provide maintenance and collect all costs from Applicant(s). County shall also have the option to terminate the Agreement and to require the right-of-way to be returned to its natural state, in which event the Applicant shall be deemed to be fully and completely released from all obligations hereunder, except as specifically provided otherwise in Section 4 of this Agreement. 10.Termination by City. City may ’terminate the Agreement if it removes the landscaping and pathway improvements, retums the right-of-way to its natural state and returns to the County the County’s contribution of twenty-five thousand dollars ($25,000.00) towards the initial installation of the landscaping and pathway improvements. 11.Notices. All notices, requests, demands, and other communications hereunder shall be in writing and shall be given (i) by Federal Express (or other established overnight express delivery service which maintains delivery records), (ii) by hand delivery, or (iii) by certified or registered mail, postage prepaid, return receipt requested, to the Parties at the following addresses, or at such other address as the Parties may designate by written notice in the above manner. to the Applicant:Original to: City of Palo Alto Director of Parks & Golf Division 3201 East Bayshore Road Palo Alto, CA 94303 FAX: (650) 496-5925 Copy to: City of Palo Alto City Clerk 250 Hamilton Ave. Palo Alto, CA 94301 to the Co~_5_~."Property Management County of Santa Clara Roads and Airports Department 101 Skyport Drive San Jose, CA 95110 FAXNo.: (408) 441-0275 3 FIRST AMENDED LANDSCAPE MAINTENANCE AGREEMENT Page Mill Road/P~ge Mill Expressway/Junipero Serra Blvd./Foothill Expressway 12. Such communications may also be given by facsimile transmission, provided any such communication is concurrently given by one of the above methods. Notjces~ " shall be deemed effective upon receipt,’or upgn attempted delivery thereof if delivery is refused by the intended recipient or if delivery is impossible because the intended recipient has failed to provide a reasonable means for accomplishing delivery. Miscellaneous. This Agreement shall be interpreted and construed only by the contents hereof, and there shall be no presumption or standard of construction in favor of or against either Party. This Agreement may be modified or amended only by a writing duly executed by both Parties. The invalidity or unenforceability of any provision of this Agreement or the applicability or inapplicability to either Party, as determined by a court, shall in no way affect the validity or enforceability of any of the remaining provisions hereof or their applicability to the other Party. This Agreement shall be construed according to and governed by the laws of the State of California. IN WITNESS WHEREOF, the Parties have entered into this Agreement as of the date first above written. ATTEST:CITY OF PALO ALTO Clerk, City of Palo Alto APPROVED AS TO FORM AND LEGALITY: BY: City Manager DATE: City Attorney (ATTACH NOTARY FORM) ATTEST:COUNTY OF SANTA CLARA Clerk, Board of Supervisors BY: Chairperson, Board of Supervisors DATE: APPROVED AS TO FORM AND LEGALITY: Deputy County Counsel