HomeMy WebLinkAbout2001-10-15 City Council (8)City of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:
DATE:
SUBJECT:
CITY MANAGER DEPARTMENT: COMMUNITY SERVICES
OCTOBER 15, 2001 CMR:386:01
APPROVAL OF CHANGE ORDER NO. 2 TO CONTRACT NO.
Cl129753 WITH BRAGATO CONSTRUCTION COMPANY IN THE
AMOUNT OF $28,131 TO PROVIDE REPLACEMENT OF FAILED
ASPHALT WALKWAY SURFACES OF THE DUCK POND PARKING
LOTS
RECOMMENDATION
Staffrec0mmends that Council approve and authorize the City Manager or his designee to
negotiate and execute a change order to the contract with Bragato Construction Company for
related, additional but unforeseen stabilization of the subgrade surface of the Duck Pond
parking lots, the total value of which shall not exceed $28,131.
DISCUSSION
In November 2000, Council approved a contract for the paving and rehabilitation of the two
parking lots adjacent to the Duck Pond (Attachment A). The scope of the work includes
removing the existing asphalt surface; regrading and properly compacting the subgrade
surface; paving the surface; creating bio-swales for the collection and filtering of run-off
water; and applying stripes, curbs and directional arrows.
Construction on this project started March 19, 2001, with the removal of the existing asphalt
surface and the top twelve inches of subgrade material. In the process of regrading the lots,
the contractor found that the final grade elevations on the plans did not match existing
elevations of the adjacent existing asphalt walkways. The existing walkways will iaot drain
as designed to the valley gutter and bio-swales. Furthermore, the edges and portions of the
walkways have failed and pose a safety hazard to pedestrians.
A bid from Bragato Construction was requested for this additional work. The bid price of
$28,131 has been evaluated by both the City’s design consultants and Public Works
Engineering. Both the contractors and City engineers believe the bid is reasonable.
Staff hopes to proceed at once with the work covered by the change order in order to quickly
resume construction to avoid inconvenience for the public. A large informational
CMR:386:01 Page 1 of 2
construction sign is posted at the edge of the Duck Pond to explain the scope of work and
project timeline to the public. This information will be updated to reflect the unexpected
delays in construction.
RESOURCE IMPACT
Funds for the change order are available in the current Capital Improvement Program for
Open Space parking lot and road improvements (Project 10003). This change order amount
is an increase to the original approved contract change order authority, bringing the total
change order authority to $115,658, which represents 85 percent of the contract amount.
POLICY IMPLICATIONS
Recommendations of this staff report are consistent with existing City policies.
ENVIRONMENTAL REVIEW
This is a maintenance project and is therefore categorically exempt from CEQA.
ATTACHMENTS
Attachment A:
Attachment B:
Contract Amendment #2
CMR:426:00
PREPARED BY:
DEPARTMENT HEAD:
-- ~/ ’ GREG"~E~TS
Superintendent, Open Space & Sciences
Director of Community Services
CITY MANAGER APPROVAL:
EMIL:
Assistant City Manager
CMR:386:01 Page 2 of 2
8505~i 07;Attachment A
500 Bracero Road
San Cedes CA 94070
650.592.2107 Fax
10ragatoconstructlon @ pacbell.net
www.bragatoconstruction.com
[Cu~.__~orner Name \ Address It
City of Pale Alto Open Spac
14~ 1 Middlefield Road
[Palo~o, CA 9~301
[A~’. Greg
PROPOSAL
CONTRACT
9/19/200t 245
We are pleased to provide ~-~ with this proposal for the removal and replacement or thfled asphalt walk~’ays
located al gaylands.
Soufl~ Lot:13,656.00
D~mo and rcragvc existing ; ~phalt and base mat~ri~l to a depth of 7" (inches). Re compact existing sub-grade
material. Furnish and install V’ (inches) of new class 2 bascrock. Furnish, install and compact 3" (inches) of new
asphalt concrete. Area apprt ~ 2,075 sq.R.
~,Iorth Lot:14,475.00
)emo and remove existing ~ ~phalt, base material and existing fill ~ a depth of 7" (inches). Also overexcavate
further where new ",,alley gu tee and existing pathway show grade change. Furnish and install 4" (inches) of new
class 2 baaeroc~. £pread an,, compact 3" (inches) of new asphalt concrete. Area ia approx 1.820 sq.ft.
Wood Plomters:0.00
Dcmo and remove wood pl~ ~ters in lhe Nurth Park.trig Lot.
No Charge
,l _OtTEXas ~NO CoNornoNs a~$2&
Items proposal, m.30e by ~ra~ato C ~slruction Cor.p~.U. Inc.. hefc~l~f!.or referred to as ~he contractor, v,~ll expire within 30 Gay~ from the dale r’~¢oot.
a=:ceFmd wi~in said lime, The cu.’ 3mar agree3 to fJ~y tl’~e cha~ge_q f~ the above dcseribc~ work upon compta~iel’i or [h6 worK, Any extra casL~ Will only
ex~.CUtL-’d upon written change cod{ and will become an extra cnarg~ over and above the es~Jmate. Progress payments Ior w~rk In progress shall be made by
the l 0~n of th6 month fo~lowin9 the. ~ am of billing No adjustment o~ allowance will be. made unless a claim in v~ting iS Bed yell1 the contract&" al n~s office
ten {10) days from completion orw( k. NO radii or adjustment will b~ allowed by the con~;racwx unless made in warms] by an autnC~ zen agent of me contractor,
The cus4omer shall not be allowed ~ )y offse! or credit for personal injuries sustalneO ~ f~ propert~ damage claimeO against the cc~tracto¢ since the contractormaintains public tiabil~ insurance i the event payment is not made in aco&,dance with terms and condi’Jons set toPJ~ herein, lne unpa=O balance shall bear
delinquency charge .3t 2% per mot] ~ and i[~ [he even[ an action be commenced for tl~e collection o~ the unpaid balance, ~e customer agrees to pay reasonable
attorney’s fees
DISCLAIMER
tf the asphalt or the Concrete is thick r than the total depth describecl In the base bid. or #the subsurface is wet and mr. subbase will not s~abilize aRe~ compaction,then any additio~ql costs for further =xcava~=on anO replacement [0 p’operly COmpact the subsuffacu ~hall b~ :~gol|aled with the owner and a representative of
8ragato CensbuC0on Company, In( A change order 5hall be signed a[td issued for further cos[. The earth-eater denies end disclaims any and all liabili~" and
resp~;~Sibillty i’0~ any and all deruL;t.~ ~Jamages. repairs, replacement and!or failure of ~aid work, pre.~ent o~ future, due to sub~.,urface Conditions who[see.vet.
ur~0erS[oxx:lthatthecnotracl.orv,~ll r =~beresp~ns~blef~nydamago~au~ed[~nyundergr~undservicesinCOnnecti~nwiththeab~vementj~nedc~nstruc~n.
Said damages will be tf’re re’spon~t: iDJ of the customer.
Contract Accepts Ice:wa accept the following proposal and aggree to all information described above.
Please note: No work will commence until signed acceptance is received.
Signature C#ml~ny N~r~ -.D~ta
ur~oertneMECHANICSLIEN LA’ i{Cal~f~-nmCMICode, Sectlen 3109eL.~;)a.ycentrac.BIll, GATe ~on~l~u~tl~ll C~ml~ln~, In,
t~. 5ubc0nEac[or, E]be~, .~up~l ~" or otJ3er [:~rr, on who P0etp~ to imp~vc you p{oper~ but
is not paid ror his work or supplie has a right to enforce t~ claim against your prop~ly. This
n’E’.ans that. after a cowl heafinc, your proper~ could bQ g~QId by a cou~t ol~cer and pro-By
~,=s,,...
~
r.eeds of the sale us.e~ to gatJsty ie m~3ep[edness. ]l~is can happen ever~ if you have pai(l
year own Contractor io frill, ff t~e IDCOi3LrBctOf, laborer, c~ supplier remains unpairt
Attachment B
TO:
City of Palo Alto
City Manager’s port
HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: COMMUNITY SERVICES
DATE:APRIL 30, 2001 CMR:209:01
SUBJECT:APPROVAL OF A CHANGE ORDER NO. 1 TO CONTRACT NO.
Cl129753 WITH BRAGATO .CONSTRUCTION COMPANY IN THE
AMOUNT OF $66,527 TO PROVIDE UNFORESEEN STABILIZATION
OF THE SUBGRADE SURFACE OF THE DUCK POND PARKING
LOTS
RECOMMENDATION
Staff recommends that Council approve and authorize the City Manager or his designee to
negotiate and execute a change order to the contract with Bragato Construction Company for
related, additional but unforeseen stabilization of the subgrade surface of the Duck Pond
parking lots, the total value of which shall not exceed $66,527.00.
This change order amount is an increase to the original approved contract change order
authority, bringing the total change order authority to $87,527, which represents 65 percent
of the contract amount.
BACKGROUND
In November 2000, Council approved a contract for the paving and rehabilitation of the two
parking lots adjacent to the Duck Pond (Attachment A). The scope of the work includes
removing the existing asphalt surface; regrading and properly compacting the subgrade
surface; paving the surface; creating bio-swales for the collection and filtering of run-off
water; and applying stripes, curbs and directional arrows.
DISCUSSION
Construction on this project started March 19, 2001, with the removal of the existing asphalt
surface and the top twelve inches of subgrade material. In the process of regrading the lots,
the contractor found that, because of the high water table around the Pond, the soil was
-extremely unstable and shifting. Despite early soil samples during the design phase,., the
extent of the soil unstableness was unexpected.
Geotechnical engineers from Lowney Associates were consulted with to find appropriate
methods to stabilize the base surface, and providing a subgrade that will remain firm under
CMR:209:01 Page 1 of 2
the high volume of traffic that these lots experience. The consultants recommended that an
additional six inches of soil be removed from the surface, Tensar geogrid material be
installed, on top of which, six additional inches of new class 2 baserock be added and
compacted. A bid from Bragato Construction was requested for this additional work. The
bid price of $66,527 has been evaluated by both the City’s design consultants and Public
-Works Engineering. Both the contractors and City engineers feels the bid is reasonable.
Staff hopes to proceed at once with the change order in order to quickly resume construction
to avoid inconvenience for the public. A large informational construction sign is posted at
the edge of the Duck Pond to explain the scope of work and project timeline to the public.
This information will be updated to reflect the unexpected delays in construction.
RESOURCE IMPACT.
Funds for the change order are available in the current Capital Improvement Program for
Open Space parking lot and road improvements (Project 10003).
POLICY IMPLICATIONS
Recommendations of this staff report are consistent with existing City policies.
.ENVIRONMENTAL REVIEW
This is a maintenance project and is therefore categorically exempt from CEQA.
ATTACHMENTS
Attachment A:
Attachment B:
Contract Amendment # 1
CMR:426:00
PREPARED BY:
GREG BETTS
Superintendent, Open Space & Sciences
PAUL T. THILTGEN
Director of Community Services
CITY MANAGER APPROVAL:
Y HARRISON
Assistant City Manager
CMR:209:01 Page 2 of 2
TO:
FROM:
DATE:
SUBJECT:
Attachment A
City of Pal lAito
City Manager’s R6 rt
HONORABLE C1TY COUNCIL
CITY MANAGER DEPARTMENT: COMMUNITY SERVICES
NOVEMBER 27, 2000 CMR:426:00
APPROVAL OF CONTRACT WITH BRAGATO CONSTRUCTION
COMPANY IN THE AMOUNT OF $133,506 FOR PAVING OF THE
DUCK POND PARKING LOTS,CAPITAL IMPROVEMENT
PROGRAM PROJECT 10003
RECOMMENDATION
Staff recommends that Council:
1. Approve and authorize the Mayor to execute the attached contract with Bragato
Construction Company in the amount of $133,506 for the paving of two parking lots at
the Palo Alto Duck Pond.
2. Authorize the City Manager or his designee to negotiate and execute one or more change
orders to the contract with Bragato Construction Company for related, additional but
3. Unforeseen expenditures associated with the project, the total value of which shall not
exceed $20,000.
DISCUSSION
Project Description
The work to be performed under the contract is for the paving of the parking lots adjacent
to the Duck Pond. Parking lots on the north and south side of the Duck Pond have not been
resurfaced in more than twenty-five years, and have badly deteriorated. This project will
completely reg;,=de the lots to properly collect run-offwater and channel it through naturally
filtering bio-swales. The present ~-p~?oblems with pooling of water in the lots will be
eliminated. Parking stalls have been designed to improve circulation and safety. Design
engineers have worked with staff from the City’s Water Quality Control Division to integrate
state-of-the-art techniques to reduce environmental effects from ran-off water.
The project scope of the proposed work includes removing the existing asphalt surface, re-
grading and properly compacting the subgrade surface, paving the surface, and applying
stripes, curbs and directional arrows. Electrical and telephone conduits will be installed under
the parking lots to facilitate the under-grounding of utilities in the future.
CMR:426:00 Page 1 of 3
Staff hopes to begin construction in early December, as weather conditions permit.
Following the award of contract, public notices will be posted at all entrances to the Duck
Pond advising the public of the construction schedule and likely parking lot closures.
Bid Process
A notice inviting formal bids for the paving project was sent on October 3, 2000 to two
builders’ exchanges and 27 paving contractors. The bidding period was 35 days. Bids were
received from four qualified contractors on November 7, 2000, as listed on the attached bid
summary (Attachment A). Bids ranged from a high of $257,877 to a low bid of $133,506.
Contractors not responding indicated that they did not submit a bid because they either were
too busy bidding for other jobs or because they did not feel their bids would be competitive.
Staff has reviewed all bids submitted and recommends that the bid of $133,506 submitted
by Bragato Construction Company be accepted and that Bragato Construction Company be
declared the lowest responsible bidder. The bid is 8.9 percent below the engineer’s estimate
of $146,500. The change order amount of $20,000, which equals 15 percent of the total
contract, is requested to resolve unforeseen problems that may arise during the construction
period.
Staff checked references supplied by the contractor for previous work performed and found
no significant complaints. Staff also checked with the Contractor’s State License Board and
found that the contractor has an active license on file.
RESOURCE IMPACT
Funds for this project are available in the Capital Improvement Program Project 10003 for
open space road and parking lot repair.
POLICY IMPLICATIONS
This recommendation does not represent any change to existing City policies.
ENVIRONMENTAL REVIEW
This project is exempt from the provisions of the California Environmental Quality Act
under Section 15302 of the guidelines, and no further environmental review is required.
All necessary permits from the California Fish and Game Department,. United States Fish and
Wildlife Service have been obtained. Permits were not required for this project by the Bay
Conservation and Development Commission, Regional Water Quality Board or Army Corps
of Engineers.
CMR:426:00 Page 2 of 3
ATrACHMENTS
Attachment A:
Attachment B:
PREPARED BY:
Bid Summary
Contract
Greg Betts, Superintendent, Open Space & Sciences
DEPARTMENT HEAD:
PAUL T. THILTGEN
Director of Community Services
CITY MANAGER.APPROVAL: ~rr~~
Assistant to the City Manager
CMR:253:00 Page 3 of 3