HomeMy WebLinkAbout2001-07-02 City CouncilTO: City of Palo Alto City Manager’s Report HONORABLE CITY COUNCIL 2 FROM:CITY MANAGER DEPARTMENT: POLICE PUBLIC WORKS DATE:JULY 2, 2001 CMR:291:01 SUBJECT:CONCEFFUAL APPROVAL TO PROCEED WITH CONCEFFUAL DESIGN FOR EXPANSION/MODERNIZATION OF THE CURRENT POLICE BUILDING RECOMMENDATIONS Staff recommends that the City Council: 1)approve in concept the current Police Department building site for a facility expansion/modernization project and, 2)direct staff to proceed with the conceptual design for expansion and modernization of the current site. BACKGROUND Since the last feasibility study for a new public safety building was completed five years ago, staff has been working to determine space needs, costs, and potential locations for a new facility. Considerable work has been completed regarding the amount of space needed for a new building and the associated costs. In 1999, staff estimated space needs for the year 2020 to be about 66,820 square feet at an approximate cost of $66 million at other sites and $55.3 million at the current site. Included in those estimates was room for Fire Department Administration and a large community room. A stand-alone police building was estimated to be about 52,790 square feet at a projected cost between $51.8 and $66 million, of which $2.3 to $13.6 million would be the cost of land purchase. After an initial review of 10 potential sites for a new facility, the list was narrowed down to four: 1) current location with the addition of three stories, 2) Page Mill Road and E1 Camino Real, 3) Park Avenue and Page Mill Road, and 4) California Avenue. On October 10, 2000, staff requested Council support for staff’s CMR:291:01 Page 1 of 6 recommendation to prepare a detailed study of the Downtown Library site as a potential location after it became apparent that the four options were either too costly or not feasible. Due to community opposition expressed at that meeting, Council did not take any action but requested that the item be continued to a date uncertain. DISCUSSION After further analysis, staffhas concluded that the Downtown Library site should be removed from the list of potential sites and has focused on reducing the space needs requirements to an absolute minimum to make viable the option of expanding and modernizing the current police facility. This report provides preliminary information regarding four potential options at the current location, as well as cost comparisons to the original three other sites. It also summarizes issues that will need to be resolved at a later time and provides a description of the further work that needs to be done. Revised Square Footage and Cost Estimates The Police Department currently occupies 18,298 square feet in the Civic Center complex (not including a parking garage or storage areas). If the City was to build on a vacant piece of property, an estimated 49,000 square feet would be sufficient to meet the needs of the Department for 20 to 30 years. This does not include parking or space needed for a property/evidence warehouse/storage area for bikes and bulk property/evidence items (4,450 square feet) but does include an Emergency Operations Center (EOC). It is important to emphasize that the most significant increase in space needs from the current building results not from increases in staffing but from providing the necessary law enforcement facilities including: interview rooms, evidence processing, storage, prisoner detention areas, etc. Staff believes that further reduction in square footage would significantly reduce the operational functionality of the proposed building and could result in service delivery problems or inhibit the City’s ability to provide enough space for anticipated law enforcement changes over the next 20 to 30 years. The City’s consultants have compared the cost estimates at the other three sites using this revised square footage. SITE California Avenue E1 Carnino / Page Mill Road Park Boulevard Options at Current Site (~) REVISED COSTS 2001 2004 $47.1 million $54.2 million $44.7 million $49.5 million $30.1 million $34.2 million $28.7 to $35 million $30.9 million CMR:291:01 Page 2 of 6 (The above listed estimates for the current site options do not include print shop relocation or bidding contingency costs.) The factors that result in higher potential costs at the current facility compared to previously discussed estimates include the following: ¯It is more expensive to expand/modernize and seismically retrofit an existing structure than it is to build on a vacant plot of land; ¯Potential in-lieu parking fees would exceed the costs to construct a surface parking lot. ¯The expansion/modernization of the existing building would require relocation of the Police Department during construction resulting in the cost of two moves instead of one. ¯Building at the existing site requires the expense of a temporary Emergency 9-1-1 Dispatch Center. Expansion / Modernization Option After reviewing the costs, community reaction, and feasibility, staff believes that the current police building is the most desirable option to provide a new facility for the following reasons: ¯The City already owns the property. ¯Relatively less environmentally complex. ¯Greater community support. ¯Centrally located City services. Staff has identified four potential options for modernization!expansion of the current site. They include the following: Option A - Expansion into most of A-level, remodel of existing police building envelope on the podium level, build out of mezzanine, and addition of third floor. No expansion over existing deck. Mushroom columns remain. Cost: $30.1 million (2001) Option B - Expansion into most of A-level, remodel of existing police building envelope on the podium level, build out of the mezzanine, and single story expansion over deck on podium level. Mushroom columns remain. Cost: $28.7 million (2001) Option C - Expansion into most of A-level, remodel of existing police building envelope on the podium level, build out of the mezzanine, and two story expansion over deck on podium level. Mushroom columns removed. Cost: $30 million (2001) CMR:291:01 Page 3 of 6 Option D - Expansion into most of A-level, remodel of existing police building envelope on the podium level, build out of the mezzanine, addition of third floor, and two story expansion over deck on podium level. Mushroom columns removed. Cost: $35 million (2001) Attachment A reflects the square footage and detailed costs for each option, with the inclusion of bidding contingency and print shop relocation estimates. It should be noted that because no actual building designs have been completed, costs are approximate. For comparison purposes, costs are provided in 2001 and 2004 dollars. Further refinement of costs will result from the completion of the next phase associated with preliminary design. Pending Council’s approval, staff will analyze in detail the four options and return with a recommended option. While staff is optimistic that the current site is suitable for expansion!modernization, there are several issues associated with this alternative that staff believes are important for the Council to be aware of and that will need to be resolved. Additional detailed work is needed to obtain the information that will assist in the resolution process; the. work that Ross/Drulis will be completing in the next phase will provide that information. The issues include the following: 1)Space Shortfalls Within Existing Envelope - Any of the potential options for expansion!modernization at the current site would either require building up at least to the mezzanine level or out under the overhangs, the remodel of the existing police building, and the use of the majority of A-level space. If these options cannot be considered, the current site would not be large enough to meet the projected space needs. Each option includes the offsite lease of approximately 4,450 square feet for property/evidence warehouse space that would house bicycles and bulk property items. Because Option B and C are smaller in square footage, the leased property/evidence warehouse space needs would increase to 8,450 square feet. 2)Seismic Retrofitting - In order to bring the building up to essential facility standards, additional seismic retrofitting will need to. be completed. This will require a separation of the Council Chamber roof from the City Hall Tower during construction. During this period, which is estimated to take up to three to six months, the Council and other meetings would need to be held at other facilities. 3)Parking Costs -Under the City’s Municipal Code, parking in-lieu fees would be required to address the additional parking spaces that would result from the increased square footage. Staff will be looking to see if there are other alternatives to address the parking issue. CMR:291:01 Page 4 of 6 4)Temporary Relocation - The Police Department, including the 9-1-1 Emergency Communications Center, would need to be entirely relocated to other sites during construction. Staff will be reviewing alternatives such as trailers and use of other existing City facilities. It should be noted that the cost estimates provided are based upon the use of City property for trailer placement. Should private property be used for this purpose, there would probably be significant additional costs. 5)Changes to Building.Exterior - All the range of options that have preliminarily been discussed would require some change in the building’s current exterior. As noted above, these changes could include everything from an additional story to a build out of the podium level. These design options would be developed and reviewed during the conceptual design phase. 6)Additional Staffing Costs - Because all of the potential options would require off-site warehouse space for bicycles and bulk property and evidence storage, some additional staffing costs associated with the operation of that facility are expected and should be factored into the operational costs. RESOURCE IMPACT Funds in the amount of $400,000 are included in the FY 2002-2004 Capital Improvement Project budget to cover the costs associated with this conceptual design phase of the project. POLICY IMPLICATIONS This request is consistent with prior Council direction. ENVIRONMENTAL ASSESSMENT A preliminary environmental assessment would be completed as part of the more detailed analysis. CMR:291:01 Page 5 of 6 TIMELINE Pending Council direction, staff would intend on the following next steps for this project: 1) 2) 3) 4) 5) 6) 7) S) Begin conceptual design activities and evaluate range of options. Conduct public outreach to obtain input from the community. Present two viable options to the Council for consideration. Begin schematic design on the selected option. Integrate public a~t and green building concepts into the design. Present design to ARB and Planning Commission for review. Complete the CEQA documentation for final site selection. Complete detailed cost estimation for funding proposal. ATTACHMENTS Attachment A: PREPARED BY: Square Footage and Detai~d Costs for ,Options A-D LYNNE JOHNSON Assistant Police Chief DEPARTMENT HEAD: CITY MANAGER APPROVAL: PATRICK Chief of Police Director of Public Works EMILY’I-’HARRISON Assistant City Manager CMR:291:01 Page 6 of 6 ATTACHMENT A Option A 48,410 Square Feet 2001 2004 Construction Cost $13.15~ million $15.125 million Relocation 3.420 million 3.420 million Parking 3.700 million 3.700 million Offsite warehouse 2.421 million 2.421 million Green building/public art .986 million 1.134 million Soft Costs 6.664 million 7.230 million Subtotal $30.3 million $33 million City Elective Options/1.716 million 1.815 million Relocation of Print Shop Total $32.059 million $34.845 million Option B 42,257 Square Feet 2001 2004 Construction Cost $11.192 million $12.871 million Relocation 3.420 million 3.420 million ....Parking 2.650 million 2.650 million Offsite warehouse 4.597 million 4.597 million ,,Green building/public art .839 million .965 million Soft Costs 5.870 million 6.368 million Subtotal $28.7 million $30.9 million City Elective Options/1.618 million 1.703 million Relocation of Print Shop Total $30.303 million $32.574 million Construction Relocation Parking Offsite Warehouse Green building/public art Soft Costs Subtotal City Electives/Relocation of Print Shop Option C 44,780 Square Feet 2001 $11.763 million 3.420 million 3.150 million 4.597 million .882 million 6.137 million $30 million 1.647 million 2004 $13.528 million 3.420 million 3.150 million 4.597 million 1.015 million 6.647 million $32.4 million 1.735 million Total $31.596 million $34. 091 million Construction Relocation Parking Offsite warehouse Option D 56,106 Square Feet 2001 $15.232 million 3.420 million 2004 $17.517 million 3.420 million Green Building~ublic Art Soft Costs Subtotal City Electives/Relocation of Print Shop Total 5.250 million 2.421 million 1.142 million 7.531 million $35 million .761 million 5.250 million 2.421 million 1.314 million 8.190 million $38.1 million 1.935 million $35.757 million $40.047 million