HomeMy WebLinkAbout2001-06-04 City Council (3)City of Palo Alto City Manager’s Report TO:HONORABLE CITY COUNCIL 3 FROM: CITY MANAGER DEPARTMENT: UTILITIES DATE: SUBJECT: JUNE 4, 2001 CMR:239:01 REQUEST FOR APPROVAL OF A BUDGET AMENDMENT ORDINANCE IN THE AMOUNT OF $200,000 FOR CAPITAL IMPROVEMENT PROJECT NUMBER 9802, DARK FIBER OPTICS COMMERCIAL CUSTOMER DESIGN AND CONNECTION SERVICES RECOMMENDATION Staff recommends that Council adopt the attached Budget Amendment Ordinance (BAO) in the amount of $200,000 for the Fiber Optics Customer Design and Connection Services Capital Improvement Program Project (CIP Number 9802). BACKGROUND The Fiber Optics Customer Design and Connection Services CIP provides capital funding for the addition of new fiber optic plant for customer connections. The improvements provided in this CIP include the installation of new conduits, fiber optic cables, splices, and, enclosures. The City receives 100 percent cost reimbursement from customers for the installation of new services, DISCUSSION The volume of requests for connections tothe City’s fiber optic network has accelerated over the last year due to the increased customer requests for fiber optic service. The adjusted budget for this CIP for fiscal year 2000-2001 was $489,303~ For fiscal year 2000-01, approximately $434,154 has been expended in completing customer connections as of March 31,2001. Approximately $ 55,149 remains to fund customer connections, however this is not sufficient funding to complete all the projects currently in process. Furthermore, the telecommunications group now has marketing staff; therefore customer interest in the fiber optic connections is expected to increase. Staff projects the need for an additional $200,000 in order to fund service connections through the end of the fiscal year. Each service connection increases revenue through leasing of the fiber backbone, and all service connection costs are fully reimbursed by the connected customers. CMR:239:01 Page 1 of 2 RESOURCE IMPACT The $200,000 increase requested will be offset by a $200,000 increase, in revenues from customer connection payments. In addition, the additional connections will generate ongoing revenue through the associated leasing of the fiber backbone. The attached BAO requests an additional appropriation of expenses and has no impact on the Electric Distribution Rate Stabilization Reserve and no future year ongoing costs are anticipated as a result of this BAO. POLICY IMPLICATIONS This report does not represent any change to existing City policies. ENVIRONMENTAL REVIEW This project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) pursuant to Section 15301 (existing facilities) of the CEQA guidelines. ATTACHMENTS A: Budget Amendment Ordinance PREPARED BY: DEPARTMENT HEAD APPROVAL: CITY MANAGER APPROVAL: .JOH~ "~~l~ector of Utilities EM~EM~:" ’ILY HA~ SOLON Assistant City Manager CMR:239:01 Page 2 of 2 ORDINANCE NO. ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO AMENDING THE BUDGET FOR THE FISCAL YEAR 2000~01 TO PROVIDE AN ADDITIONAL APPROPRIATION OF $200,000 FOR THE FIBER OPTIC CUSTOMER DESIGN AND CONNECTION SERVICES CAPITAL IMPROVEMENT PROJECT NUMBER 9802 WHEREAS, pursuant to the provisions of Section 12 of Article III of the Charter of the City of Palo Alto, the Council on June19, 2000 did adopt a budget for fiscal year 2000-01; and WHEREAS, the Fiber Optics Customer Design and Connection Services capital improvement project provides funding for the addition of new fiber optics for customer connections, including ihe installation of new conduits, fiber optic cables, splices, and enclosures; and WHEREAS, the volume of requests for connections to the City’s fiber optic network has accelerated; and WHEREAS, an additional appropriation of $200,000 is.needed to fulfill the anticipated request for service connections through the end of the fiscal year; and WHEREAS, this cost will be fully reimbursed by customers; and WHEREAS, the additional appropriation of funds is aone-time cost and no future year ongoing costs are anticipated; and WHEREAS, CityCouncil authorization is needed to amend the 2000-01 budget as hereinafter set forth. NOW, THEREFORE, the Council of the City of Palo Alto does ORDAIN as follows: SECTION i. Revenue in the Electric Fund is increased, by the. sum of $200,000 to reflect reimbursement from customers for service connections. SECTION 2. The sum of Two Hundred Thousand Dollars ($200,000) is hereby appropriated to Capital Improvement Program Project Number 9802, Customer Design and Connection Services. SECTION 3. As specified in Section 2.28.080(a) of the Palo Alto Municipal Code, a two-thirds vote of the City Council is required to adopt this ordinance. SECTION 4. This project is categorically exempt from the .provisions of the California Environmental Quality Act (CEQA) pursuant to Section 15301 (existing facilities) of the CEQA guidelines. SECTION 5. As provided in Section 2.04.350 of the Palo Alto Municipal Code, this ordinance Shall become effective upon adoption. INTRODUCED AND PASSED: AYES: NOES: ABSTENTIONS: ABSENT: ATTEST:APPROVED: City Clerk Mayor APPROVED AS TO.FORM:City Manager Senior Asst. City Attorney Director of Services Administrative Director of Utilities CITY OF PALO ALTO MEMORANDUM DATE: TO: SUBJECT: May 21,2001 City Council Members APPROVAL OF A BUDGET AMENDMENT ORDINANCE TO CREATE CAPITAL IMPROVEMENT PROJECT 0121, NATURAL GAS BACK UP GENERATOR PROJECT, IN THE AMOUNT OF $4,612,739 AND APPROVAL OF CONTRACT WITH ENERGY MASTERS INTERNATIONAL IN THE AMOUNT OF $4,512,739 FOR THE PROCUREMENT, INSTALLATION, AND START-UP OF A 5 MEGAWATT BACK UP NATURAL GAS GENERATOR SYSTEM Some corrections needed to be made to the staff report for item No. 8. They are as follows: The sales tax on the equipment purchased had been omitted from the budget numbers and exhibits. The CMR, BAO and CONTRACT have all been modified to include the amount of $259,200 in sales tax. A Planergy International subsidiary, ENERGY MASTERS INTERNATIONAL, needs to be the signatory on the contract due to General Contractor licensing conditions. Energy Masters International is a wholly owned subsidiary of Planergy International. The people signing the contract and doing the work are unchanged. The CMR and Contract have been modified to reflect the CONTRACTOR name substitution. of City-ofPalo Alt~ Utilities E~~SON Assistant City Manager