HomeMy WebLinkAboutStaff Report 7411
City of Palo Alto (ID # 7411)
City Council Staff Report
Report Type: Consent Calendar Meeting Date: 11/14/2016
City of Palo Alto Page 1
Summary Title: Approval of $3,175,600 Appropriation to Capital
Improvement Program Project VR-17000
Title: Approval of $3,175,600 Appropriation to Capital Improvement Program
Project VR-17000 from Vehicle Replacement and Maintenance Fund Reserve
and Approval of Budget Amendments in Various Funds
From: City Manager
Lead Department: Public Works
Recommendation
Staff recommends that Council amend the Fiscal Year 2017 Budget Appropriation
Ordinance for
a. the Water Fund by:
i. Increasing the transfer to the Vehicle Replacement and
Maintenance Fund in the amount of $15,407; and
ii. Decreasing the Rate Stabilization Reserve in the amount of
$15,407; and
b. the Gas Fund by:
i. Increasing the transfer to the Vehicle Replacement and
Maintenance Fund in the amount of $15,407; and
ii. Decreasing the Rate Stabilization Reserve in the amount of
$15,407; and
c. the Wastewater Fund by:
i. Increasing the transfer to the Vehicle Replacement and
Maintenance Fund in the amount of $15,406; and
ii. Decreasing the Rate Stabilization Reserve in the amount of
$15,406; and
d. the Vehicle Replacement and Maintenance Fund by:
i. Increasing the transfer from the Water Fund by $15,407;
ii. Increasing the transfer from the Gas Fund by $15,407;
City of Palo Alto Page 2
iii. Increasing the transfer from the Wastewater Fund by $15,406;
iv. Decreasing the ending fund balance by $232,380;
v. Eliminating the Reserve for 2017 Vehicle Replacements in the
amount of $2,897,000; and,
vi. Increasing the Scheduled Vehicle and Equipment Replacement
Fiscal Year 2017 project VR-17000 in the amount of $3,175,600
Background
During the Fiscal Year 2017 budget process, staff reviewed its current progress on
vehicle replacements for Fiscal Years 2015 and 2016. In May 2016 staff requested
a total of $4.9 million be reappropriated from prior year Capital Improvement
Program (CIP) projects VR-15000 and VR-16000 as vehicle replacements had not
yet been completed. At that same time, the decision was made, as part of the the
Fiscal Year 2017 Budget, to hold $2,897,000 for CIP project VR-17000 vehicle
replacements in a reserve while staff caught up with the previous year’s
replacements.
The process for vehicle replacement can be lengthy and includes procurement,
outfitting, and delivery. Some vehicles take up to 18 months to build and outfit
before staff can deliver to customer departments. There are four vehicles in CIP
projects VR-15000 and VR-16000 that still require Council approval, since they are
over $250,000. All other replacement vehicles/equipment in CIP projects VR-
15000 and VR-16000 have been ordered, thirty-three of which have yet to be
received from vendors. Once received, the vendors can be paid, outfitting can
ensue if needed, vehicles can be delivered to departments, and the process for
closing the VR-15000 and VR-16000 projects can be executed.
Discussion
Staff recommends moving the $2,897,000 from reserves under capitalized
equipment to CIP VR-17000 in order to begin issuing purchase orders for the
Fiscal Year 2017 vehicle replacements.
Staff also recommends amending the FY 2017 budget appropriation ordinance for
the Vehicle Fund by $278,600 for the escalated replacement cost of two Utilities
vehicles, both used by the Gas/Water division and being replaced due to
maintenance issues, and one Community Services Department Parks and Open
Space vehicle, being replaced due to irrepareable damage caused in an accident.
City of Palo Alto Page 3
Unit 7214 is a 2010 Mercedes Sprinter, high roof cargo van with custom interior,
used for 24-hour emergency customer response. It is the only vehicle of its kind
in the fleet, and is used for valve repairs and repairing water and gas pipe leaks.
This vehicle has had ongoing electrical issues, causing safety concerns. The
continued maintenance costs for this vehicle will far exceed the costs of replacing.
Unit 8279 is a 2000 Ford F-450 with a utility body, used to support the gas and
water valve maintenance programs. It is also used as a secondary weld truck and
carries a PV-66 vacuum used for valve and meter box maintenance. This vehicle is
critical to maintaining optimum operation of the gas and water distribution
systems. This vehicle has had extensive maintenance issues.
Unit 2764 is a 2003 Ford F-350 Wildland Patrol unit used by park rangers for
general patrol and is the first responder for emergencies in Open Space and the
vicinity. Responses for emergency situations range from pedestrian and cyclist
injuries to medical emergencies and fire suppression. This vehicle is critical to
accessing remote areas of parks and preserves as some police/fire vehicles cannot
travel off paved roads. On April 8, 2016, it was involved in an accident causing
major damage.
According to Vehicle and Equipment Use, Maintenance and Replacement Policy
and Procedures, unit 8279 should have been replaced in 2009/2010 and unit 2764
should have been replaced in 2013. Including the replacement of units 8279 and
7214 in CIP VR-17000 was approved by the Fleet Review Committee on
September 12, 2016, and unit 2764 on October 18, 2016. Some funds have been
collected for the future replacement but not enough for the total cost due to the
escalated replacement.
Resource Impact
The Scheduled Vehicle and Equipment Replacement Fiscal Year 2017 CIP (VR-
17000) does not have sufficient funding to purchase the additional three vehicles.
Traditionally, vehicle procurements are funded through annual charges to the
department/fund that uses the vehicle in order to collect the total replacement
cost of the vehicle by the year it’s scheduled for replacement. In the Fiscal Year
2017 budget for VR-17000, nothing was allocated for the replacement of these
three vehicles, because they were not scheduled to be replaced in FY 2017. To
City of Palo Alto Page 4
support this purchase, an appropriation of $278,600 to the Scheduled Vehicle and
Equipment Replacement Fiscal Year 2017 CIP project (VR-17000) in the Vehicle
Replacement and Maintenance Fund, offset by transfers of $46,220 from the
Utilities Water, Gas, and Wastewater Collection Funds, and $232,380 from the
Vehicle Replacement and Maintenance Fund ending fund balance is
recommended.
Policy Implications
Approval of recommendations does not represent any change to the existing
policy.
Environmental Review
These vehicles will meet the EPA 2016 Emissions standards.