HomeMy WebLinkAboutStaff Report 7360 City of Palo Alto (ID # 7360) City Council Staff Report Report Type: Consent Calendar Meeting Date: 11/7/2016 City of Palo Alto Page 1 Summary Title: Contract Amendment for McGuire Pacific Contractors Title: Approval of Amendment Number 3 to Contract Number C15157271 with McGuire Pacific Construction to Extend the Term of the Contract for Downtown Residential Preferential Parking Sign Installation to September 1, 2018 With no Additional Costs From: City Manager Lead Department: Planning and Community Environment Recommendation Staff recommends that Council approve and authorize the City Manager to execute Amendment Three to Contract No. C15157271 with McGuire Pacific Constructors (Attachment A) to extend the term of the Contract for standard sign installation for the Downtown Residential Preferential Parking (RPP) program through September 1, 2018, at no additional cost to the City. Executive Summary In March 2015, Council awarded a 12-month contract to McGuire Pacific Constructors for fabrication and installation of all Downtown RPP signage, and for initiating underground utilities verification for all proposed signage locations. In February 2016, Amendment One was executed, which added $154,500 for construction services to support the expanded boundary of the Downtown RPP district. In June 2016, Amendment Two was executed, extending the term of the contract through September 1, 2016. A further extension of the existing signage contract with McGuire Pacific Constructors is needed to accommodate sign installation as new streets within the “eligibility area” downtown opt into the program. Background and Discussion City Council directed staff to move forward with the implementation of a Residential Preferential Parking (RPP) program in the Downtown neighborhoods. An expansion of the program boundary and approval of an eligibility area adjacent to the Downtown RPP district were later approved by City Council. City of Palo Alto Page 2 Streets within the approved eligibility area are able to opt in through a petition and survey process, and be approved for the program administratively. The RPP program requires standard signage to be installed on all streets where parking restrictions have been adopted. The streets opt in on a rolling basis, requiring signage to be installed following each request. Resource Impact This is an extension of time only, and no tasks are added to this contract. There are sufficient resources to fund this contract. There is no additional resource impact by extending the term of the contract through Amendment Three. Staff expects to return to Council to request additional funds when new Residential Preferential Parking (RPP) districts are approved and signage installation is required. Policy Implications The recommended action is consistent with prior City Council direction to implement residential preferential parking downtown. Environmental Review Approval of an extension of time for an existing contract is not a “project” requiring review under the California Environmental Quality Act (CEQA). Attachments:  Attachment A: C15157271 McGuire Amendment No 3.doc (PDF) 1 of 1 Revision April 28, 2014 AMENDMENT NO. 3 TO CONTRACT NO. C15157271 BETWEEN THE CITY OF PALO ALTO AND MC GUIRE PACIFIC CONSTRUCTORS This Amendment No. 3 to Contract No. C15157271 (“Contract”) is entered into June 10, 2016, by and between the CITY OF PALO ALTO, a California chartered municipal corporation (“CITY”), and MC GUIRE PACIFIC CONSTRUCTORS, a Sole Proprietor, located at 12500 Locksley Lane, Auburn, California, 95602, Telephone Number: (530) 888-0527 (“CONTRACTOR”). R E C I T A L S A. The Contract was entered into between the parties for the provision to perform standard highway sign installations in support of a new Residential Preferential Parking (RPP) district in Downtown Palo Alto. B. CITY intends to extend the Contract term C. The parties wish to amend the Contract. NOW, THEREFORE, in consideration of the covenants, terms, conditions, and provisions of this Amendment, the parties agree: SECTION 1. Section 3 TERM is hereby amended to read as follows: “3. TERM. The term of this Agreement is from March 2, 2015 to September 18, 2018 inclusive, subject to the provisions of Sections Q and V of the General Terms and Conditions.” SECTION 2. Except as herein modified, all other provisions of the Contract, including any exhibits and subsequent amendments thereto, shall remain in full force and effect. IN WITNESS WHEREOF, the parties have by their duly authorized representatives executed this Amendment on the date first above written. CITY OF PALO ALTO APPROVED AS TO FORM: MC GUIRE PACIFIC CONSTRUCTORS DocuSign Envelope ID: 4A64376B-B0F4-40F0-92F5-A3C4A60B2EBF John McGuire owner