City of Palo Alto (ID # 3328)
City Council Staff Report
Report Type: Consent Calendar Meeting Date: 3/4/2013
City of Palo Alto Page 1
Council Priority: Environmental Sustainability
Summary Title: Recycled Water Project Contract
Title: Approval of a Water Enterprise Fund Contract with RMC Water and
Environment, Inc. for a Total Not to Exceed Amount of $193,914 to Complete
the Environmental Analysis of Expanding the City's Recycled Water Delivery
System
From: City Manager
Lead Department: Utilities
Recommendation
Staff recommends that Council approve a contract with RMC Water and Environment, Inc.
(RMC) to complete the environmental analysis of an expanded recycled water project to serve
the Stanford Research Park for $176,286, plus a contingency of $17,628, for an amount not to
exceed $193,914. Staff also recommends that Council approve this contract as a “sole source”
exemption from the City’s competitive bidding process under its authority in Palo Alto
Municipal Code Section 2.30.360(d).
Executive Summary
Staff continues to prepare the environmental documents for the proposed project to extend
the recycled water distribution system to customers in the Stanford Research Park area. Due to
unforeseen delays largely related to completion of the project’s environmental impact report
(EIR), the project has extended beyond the consultant’s contract termination date. Staff
requests approval of a new contract with RMC to complete the work. The expiration date for
the new contract is December 2014. Funds remaining from the expired contract will be re-
authorized for the new contract, so there is no funding increase included in this request. A
contract extension will allow the City to capture the remaining grant funds from the Bureau of
Reclamation.
City of Palo Alto Page 2
Background
On April 16, 2007, the City Council authorized the City Manager to execute a contract with RMC
for preparation of a recycled water Facility Plan and associated environmental documents for
Capital Improvement Project WS-07001 (CMR 191:07). RMC completed the Facility Plan for the
project in June 2008, and staff has been working on the Federal and State environmental
documents since then. Since execution of the original contract, Council has approved three
amendments to the contract. The project cost and approval chronology are provided in Table 1
along with actual expenditures to date.
Table 1: RMC Budget and Cost Summary1
Approved Budgeted
Costs
Actual
Expenditures
Original RMC Contract April 16, 2007 (CMR: 191:07) $242,700 $242,700
Amendment No. 1 June 2, 2008 (CMR: 255:08) $25,000 $25,000
Amendment No. 2 Nov. 8, 2008 (CMR: 431:08) $35,000 $35,000
Amendment No. 3 April 12, 2010 (CMR: 207:10) $372,000 $161,848
Total RMC Contract with all amendments $674,700 $464,442
1These are gross costs, and do not include grants. Project costs net of grants are discussed below
Discussion
The recycled water project has experienced significant delays since completion of the Facility
Plan in June 2008, and the RMC contract expired in June 2011. While staff has addressed many
issues regarding a future recycled water project, the replacement of high quality potable water
with recycled water remains a concern for the landscape community and has required staff and
RMC to complete additional work in preparation of the project’s EIR. These additional studies
and consultations were a major factor in pushing the project completion date beyond the
deadline in the RMC contract. Staff has also re-directed efforts on several occasions to
activities unrelated to the preparation of the environmental documents, but critical to position
the recycled water project project for success (i.e. grant funding pursuits). Completion of the
environmental document is essential for securing Federal or State grant or loan funding for the
construction of the project.
City of Palo Alto Page 3
Staff is recommending that Council approve a new contract with RMC to extend the time to
complete the work required. The tasks and scope of work – completion of the environmental
documents - are substantially the same with minor modifications to the deadlines and
individual tasks to ensure they are consistent with current information and the new project
schedule. The scope has also been updated to reflect work already completed and to ensure
that updated NEPA requirements from the US Bureau of Reclamation are included.
The City selected RMC through a competitive bidding process for the original contract. Staff
has consulted with Purchasing and recommends that the Council approve this new contract
with RMC as a sole source contract. This project qualifies for an exception to the competitve
bidding process under Palo Alto Municipal Code Section 2.30.360(d) since there is no adequate
substitute for this consultant’s services given the substantial work done to date on this complex
project. The City has completed significantly more than half of the work required on this
project and has been using the same consultant for these professional services throughout. .
Staff anticipates the remaining funds in the expired RMC contract will be sufficient to complete
both the Federal and State environmental documents.
The project received a $75,000 grant from the State Water Resources Control Board (SRWCB) to
complete the Facility Plan. Since Amendment #3 to the prior contract with RMC, staff applied
for and received an additional planning grant. The new grant is a 50% cost share planning grant
administered by the Federal Bureau of Reclamation (Reclamation) under the Title XVI recycled
water program. Staff has submitted and received reimbursement for approximately 2/3 of the
grant. Table 2 illustrates the net project cost (total projected cost less grants). The total RMC
cost for the expired contract and the new proposed contract has been lowered from $674,700
(as shown in Table 1) to $658,336 (as shown in Table 2) due to a lower contingency amount in
the new contract.
Table 2: Project costs and grants
Staff costs included in CIP Budget $42,300
Total RMC Cost (including new contract) $658,336
Total CIP Budget $700,636
Less SWRCB Planning Grant (State) ($75,000)
Less Bureau of Reclamation Planning Grant (Federal) ($326,000)
Total Net CIP Cost $299,636
The Reclamation grant is a cost share agreement, so the City must first incur the costs in order
to get reimbursement. The City has already received about $219,000 from Reclamation. Once
City of Palo Alto Page 4
the environmental documents are complete, staff will submit invoices to Reclamation for
reimbursement of the remaining grant amount of approximately $107,000. Reclamation has
strict grant administration guidelines, and the new RMC contract is important to ensure staff
can resume progress on the project and capture the remaining grant funds.
Resource Impact
The proposed contract does not require any additional funds to complete all necessary work.
There is approximately $210,000 remaining in Capital Improvement Project WS-07001 funds
originally budgeted for the expired contract to complete the environmental work for the
project. The $193,914 needed for the new contract will be reauthorized in this request, and the
balance will return to the Water Fund reserves. The new contract funding requirement is lower
than that of the expired contract due to a reduction in the contingency amount.
Policy Implications
Executing the proposed contract is consistent with Council policy. This project is consistent
with the Council-adopted Water Integrated Resource Plan Guideline 3: “Actively participate in
development of cost effective regional recycled water plans.” The project is also consistent
with Council direction to reduce imported water supplies and limit or reduce diversions from
the Tuolumne River.
Environmental Review
The project is undergroing Federal and State-mandated environmental review.
Attachments:
Attachment A - Contract (PDF)
Professional Services
Rev. June 2, 2010
CITY OF PALO ALTO CONTRACT NO. C13148958
AGREEMENT BETWEEN THE CITY OF PALO ALTO
AND RMC WATER AND ENVIRONMENT, INC.
FOR PROFESSIONAL SERVICES
This Agreement is entered into on this 4th day of March, 2013, (“Agreement”) by and
between the CITY OF PALO ALTO, a California chartered municipal corporation (“CITY”), and
RMC WATER AND ENVIRONMENT, INC., a California corporation, located at 2290 North First
Street, Suite 212, San Jose, CA 95131 ("CONSULTANT").
RECITALS
The following recitals are a substantive portion of this Agreement.
A. CITY intends to study the water quality impacts of irrigation with recycled water
(“Project”) and desires to engage a consultant to prepare a single-issue EIR to address the water
quality impacts with recycled water in connection with the Project (“Services”).
B. CONSULTANT has represented that it has the necessary professional expertise,
qualifications, and capability, and all required licenses and/or certifications to provide the Services.
C. CITY in reliance on these representations desires to engage CONSULTANT to provide the
Services as more fully described in Exhibit “A”, attached to and made a part of this Agreement.
NOW, THEREFORE, in consideration of the recitals, covenants, terms, and conditions, this
Agreement, the parties agree:
AGREEMENT
SECTION 1. SCOPE OF SERVICES. CONSULTANT shall perform the Services described in
Exhibit “A” in accordance with the terms and conditions contained in this Agreement. The
performance of all Services shall be to the reasonable satisfaction of CITY.
SECTION 2. TERM.
The term of this Agreement shall be from the date of its full execution through December 31, 2014
unless terminated earlier pursuant to Section 19 of this Agreement.
SECTION 3. SCHEDULE OF PERFORMANCE. Time is of the essence in the performance of
Services under this Agreement. CONSULTANT shall complete the Services within the term of this
Agreement and in accordance with the schedule set forth in Exhibit “B”, attached to and made a part
of this Agreement. Any Services for which times for performance are not specified in this
Agreement shall be commenced and completed by CONSULTANT in a reasonably prompt and
timely manner based upon the circumstances and direction communicated to the CONSULTANT.
Professional Services
Rev. June 2, 2010
CITY’s agreement to extend the term or the schedule for performance shall not preclude recovery of
damages for delay if the extension is required due to the fault of CONSULTANT.
SECTION 4. NOT TO EXCEED COMPENSATION. The compensation to be paid to
CONSULTANT for performance of the Services described in Exhibit “A”, including both payment
for professional services and reimbursable expenses, shall not exceed One Hundred Seventy Six
Thousand Two Hundred Eighty Six Dollars ($176,286). In the event Additional Services are
authorized, the total compensation for services and reimbursable expenses shall not exceed One
Hundred Ninety Three Thousand Nine Hundred Fourteen Dollars ($193,914). The applicable rates
and schedule of payment are set out in Exhibit “C”, entitled “COMPENSATION ” which is attached
to and made a part of this Agreement.
Additional Services, if any, shall be authorized in accordance with and subject to the provisions of
Exhibit “C”. CONSULTANT shall not receive any compensation for Additional Services performed
without the prior written authorization of CITY. Additional Services shall mean any work that is
determined by CITY to be necessary for the proper completion of the Project, but which is not
included within the Scope of Services described in Exhibit “A”.
SECTION 5. INVOICES. In order to request payment, CONSULTANT shall submit monthly
invoices to the CITY describing the services performed and the applicable charges (including an
identification of personnel who performed the services, hours worked, hourly rates, and
reimbursable expenses), based upon the CONSULTANT’s billing rates (set forth in Exhibit “C”). If
applicable, the invoice shall also describe the percentage of completion of each task. The
information in CONSULTANT’s payment requests shall be subject to verification by CITY.
CONSULTANT shall send all invoices to the City’s project manager at the address specified in
Section 13 below. The City will generally process and pay invoices within thirty (30) days of
receipt.
SECTION 6. QUALIFICATIONS/STANDARD OF CARE. All of the Services shall be
performed by CONSULTANT or under CONSULTANT’s supervision. CONSULTANT represents
that it possesses the professional and technical personnel necessary to perform the Services required
by this Agreement and that the personnel have sufficient skill and experience to perform the Services
assigned to them. CONSULTANT represents that it, its employees and subconsultants, if permitted,
have and shall maintain during the term of this Agreement all licenses, permits, qualifications,
insurance and approvals of whatever nature that are legally required to perform the Services.
All of the services to be furnished by CONSULTANT under this agreement shall meet the
professional standard and quality that prevail among professionals in the same discipline and of
similar knowledge and skill engaged in related work throughout California under the same or similar
circumstances.
SECTION 7. COMPLIANCE WITH LAWS. CONSULTANT shall keep itself informed of and
in compliance with all federal, state and local laws, ordinances, regulations, and orders that may
affect in any manner the Project or the performance of the Services or those engaged to perform
Services under this Agreement. CONSULTANT shall procure all permits and licenses, pay all
charges and fees, and give all notices required by law in the performance of the Services.
Professional Services
Rev. June 2, 2010
SECTION 8. ERRORS/OMISSIONS. CONSULTANT shall correct, at no cost to CITY, any and
all errors, omissions, or ambiguities in the work product submitted to CITY, provided CITY gives
notice to CONSULTANT. If CONSULTANT has prepared plans and specifications or other design
documents to construct the Project, CONSULTANT shall be obligated to correct any and all errors,
omissions or ambiguities discovered prior to and during the course of construction of the Project.
This obligation shall survive termination of the Agreement.
SECTION 9. COST ESTIMATES. If this Agreement pertains to the design of a public works
project, CONSULTANT shall submit estimates of probable construction costs at each phase of
design submittal. If the total estimated construction cost at any submittal exceeds ten percent (10%)
of the CITY’s stated construction budget, CONSULTANT shall make recommendations to the
CITY for aligning the PROJECT design with the budget, incorporate CITY approved
recommendations, and revise the design to meet the Project budget, at no additional cost to CITY.
SECTION 10. INDEPENDENT CONTRACTOR. It is understood and agreed that in performing
the Services under this Agreement CONSULTANT, and any person employed by or contracted with
CONSULTANT to furnish labor and/or materials under this Agreement, shall act as and be an
independent contractor and not an agent or employee of the CITY.
SECTION 11. ASSIGNMENT. The parties agree that the expertise and experience of
CONSULTANT are material considerations for this Agreement. CONSULTANT shall not assign or
transfer any interest in this Agreement nor the performance of any of CONSULTANT’s obligations
hereunder without the prior written consent of the city manager. Consent to one assignment will not
be deemed to be consent to any subsequent assignment. Any assignment made without the approval
of the city manager will be void.
SECTION 12. SUBCONTRACTING.
CONSULTANT shall not subcontract any portion of the work to be performed under this Agreement
without the prior written authorization of the city manager or designee.
CONSULTANT shall be responsible for directing the work of any subconsultants and for any
compensation due to subconsultants. CITY assumes no responsibility whatsoever concerning
compensation. CONSULTANT shall be fully responsible to CITY for all acts and omissions of a
subconsultant. CONSULTANT shall change or add subconsultants only with the prior approval of
the city manager or his designee.
SECTION 13. PROJECT MANAGEMENT. CONSULTANT will assign Suet Chau as the
Project Supervisor to have supervisory responsibility for the performance, progress, and execution of
the Services and to represent CONSULTANT during the day-to-day work on the Project. If
circumstances cause the substitution of the project director, project coordinator, or any other key
personnel for any reason, the appointment of a substitute project director and the assignment of any
key new or replacement personnel will be subject to the prior written approval of the CITY’s project
manager. CONSULTANT, at CITY’s request, shall promptly remove personnel who CITY finds do
not perform the Services in an acceptable manner, are uncooperative, or present a threat to the
adequate or timely completion of the Project or a threat to the safety of persons or property.
Professional Services
Rev. June 2, 2010
The City’s project manager is Nicolas Procos, Utilities Department, Resource Division, 250
Hamilton Avenue, Palo Alto, CA 94303, Telephone: (650)329-2214. The project manager will be
CONSULTANT’s point of contact with respect to performance, progress and execution of the
Services. The CITY may designate an alternate project manager from time to time.
SECTION 14. OWNERSHIP OF MATERIALS. Upon delivery, all work product, including
without limitation, all writings, drawings, plans, reports, specifications, calculations, documents,
other materials and copyright interests developed under this Agreement shall be and remain the
exclusive property of CITY without restriction or limitation upon their use. CONSULTANT agrees
that all copyrights which arise from creation of the work pursuant to this Agreement shall be vested
in CITY, and CONSULTANT waives and relinquishes all claims to copyright or other intellectual
property rights in favor of the CITY. Neither CONSULTANT nor its contractors, if any, shall make
any of such materials available to any individual or organization without the prior written approval
of the City Manager or designee. CONSULTANT makes no representation of the suitability of the
work product for use in or application to circumstances not contemplated by the scope of work.
SECTION 15. AUDITS. CONSULTANT will permit CITY to audit, at any reasonable time
during the term of this Agreement and for three (3) years thereafter, CONSULTANT’s records
pertaining to matters covered by this Agreement. CONSULTANT further agrees to maintain and
retain such records for at least three (3) years after the expiration or earlier termination of this
Agreement.
SECTION 16. INDEMNITY.
16.1. To the fullest extent permitted by law, CONSULTANT shall protect,
indemnify, defend and hold harmless CITY, its Council members, officers, employees and agents
(each an “Indemnified Party”) from and against any and all demands, claims, or liability of any
nature, including death or injury to any person, property damage or any other loss, including all
costs and expenses of whatever nature including attorneys fees, experts fees, court costs and
disbursements (“Claims”) resulting from, arising out of or in any manner related to performance or
nonperformance by CONSULTANT, its officers, employees, agents or contractors under this
Agreement, regardless of whether or not it is caused in part by an Indemnified Party.
16.2. Notwithstanding the above, nothing in this Section 16 shall be construed to
require CONSULTANT to indemnify an Indemnified Party from Claims arising from the active
negligence, sole negligence or willful misconduct of an Indemnified Party.
16.3. The acceptance of CONSULTANT’s services and duties by CITY shall not
operate as a waiver of the right of indemnification. The provisions of this Section 16 shall survive
the expiration or early termination of this Agreement.
SECTION 17. WAIVERS. The waiver by either party of any breach or violation of any covenant,
term, condition or provision of this Agreement, or of the provisions of any ordinance or law, will not
be deemed to be a waiver of any other term, covenant, condition, provisions, ordinance or law, or of
any subsequent breach or violation of the same or of any other term, covenant, condition, provision,
ordinance or law.
Professional Services
Rev. June 2, 2010
C13148958
SECTION 18. INSURANCE.
18.1. CONSULTANT, at its sole cost and expense, shall obtain and maintain, in full
force and effect during the term of this Agreement, the insurance coverage described in Exhibit "D".
CONSULTANT and its contractors, if any, shall obtain a policy endorsement naming CITY as an
additional insured under any general liability or automobile policy or policies.
18.2. All insurance coverage required hereunder shall be provided through carriers
with AM Best’s Key Rating Guide ratings of A-:VII or higher which are licensed or authorized to
transact insurance business in the State of California. Any and all contractors of CONSULTANT
retained to perform Services under this Agreement will obtain and maintain, in full force and effect
during the term of this Agreement, identical insurance coverage, naming CITY as an additional
insured under such policies as required above.
18.3. Certificates evidencing such insurance shall be filed with CITY concurrently
with the execution of this Agreement. The certificates will be subject to the approval of CITY’s Risk
Manager and will contain an endorsement stating that the insurance is primary coverage and will not
be canceled, or materially reduced in coverage or limits, by the insurer except after filing with the
Purchasing Manager thirty (30) days' prior written notice of the cancellation or modification,
CONSULTANT shall be responsible for ensuring that current certificates evidencing the insurance
are provided to CITY’s Purchasing Manager during the entire term of this Agreement.
18.4. The procuring of such required policy or policies of insurance will not be
construed to limit CONSULTANT's liability hereunder nor to fulfill the indemnification provisions
of this Agreement. Notwithstanding the policy or policies of insurance, CONSULTANT will be
obligated for the full and total amount of any damage, injury, or loss caused by or directly arising as
a result of the Services performed under this Agreement, including such damage, injury, or loss
arising after the Agreement is terminated or the term has expired.
SECTION 19. TERMINATION OR SUSPENSION OF AGREEMENT OR SERVICES.
19.1. The City Manager may suspend the performance of the Services, in whole or
in part, or terminate this Agreement, with or without cause, by giving ten (10) days prior written
notice thereof to CONSULTANT. Upon receipt of such notice, CONSULTANT will immediately
discontinue its performance of the Services.
19.2. CONSULTANT may terminate this Agreement or suspend its performance of
the Services by giving thirty (30) days prior written notice thereof to CITY, but only in the event of
a substantial failure of performance by CITY.
19.3. Upon such suspension or termination, CONSULTANT shall deliver to the
City Manager immediately any and all copies of studies, sketches, drawings, computations, and
other data, whether or not completed, prepared by CONSULTANT or its contractors, if any, or given
to CONSULTANT or its contractors, if any, in connection with this Agreement. Such materials will
become the property of CITY.
19.4. Upon such suspension or termination by CITY, CONSULTANT will be paid
Professional Services
Rev. June 2, 2010
C13148958
for the Services rendered or materials delivered to CITY in accordance with the scope of services on
or before the effective date (i.e., 10 days after giving notice) of suspension or termination; provided,
however, if this Agreement is suspended or terminated on account of a default by CONSULTANT,
CITY will be obligated to compensate CONSULTANT only for that portion of CONSULTANT’s
services which are of direct and immediate benefit to CITY as such determination may be made by
the City Manager acting in the reasonable exercise of his/her discretion. The following Sections will
survive any expiration or termination of this Agreement: 14, 15, 16, 19.4, 20, and 25.
19.5. No payment, partial payment, acceptance, or partial acceptance by CITY will
operate as a waiver on the part of CITY of any of its rights under this Agreement.
SECTION 20. NOTICES.
All notices hereunder will be given in writing and mailed, postage prepaid, by
certified mail, addressed as follows:
To CITY: Office of the City Clerk
City of Palo Alto
Post Office Box 10250
Palo Alto, CA 94303
With a copy to the Purchasing Manager
To CONSULTANT: Attention of the project director
at the address of CONSULTANT recited above
SECTION 21. CONFLICT OF INTEREST.
21.1. In accepting this Agreement, CONSULTANT covenants that it presently has
no interest, and will not acquire any interest, direct or indirect, financial or otherwise, which would
conflict in any manner or degree with the performance of the Services.
21.2. CONSULTANT further covenants that, in the performance of this Agreement,
it will not employ subconsultants, contractors or persons having such an interest. CONSULTANT
certifies that no person who has or will have any financial interest under this Agreement is an officer
or employee of CITY; this provision will be interpreted in accordance with the applicable provisions
of the Palo Alto Municipal Code and the Government Code of the State of California.
21.3. If the Project Manager determines that CONSULTANT is a “Consultant” as
that term is defined by the Regulations of the Fair Political Practices Commission, CONSULTANT
shall be required and agrees to file the appropriate financial disclosure documents required by the
Palo Alto Municipal Code and the Political Reform Act.
SECTION 22. NONDISCRIMINATION. As set forth in Palo Alto Municipal Code section
2.30.510, CONSULTANT certifies that in the performance of this Agreement, it shall not
discriminate in the employment of any person because of the race, skin color, gender, age, religion,
disability, national origin, ancestry, sexual orientation, housing status, marital status, familial status,
Professional Services
Rev. June 2, 2010
C13148958
weight or height of such person. CONSULTANT acknowledges that it has read and understands the
provisions of Section 2.30.510 of the Palo Alto Municipal Code relating to Nondiscrimination
Requirements and the penalties for violation thereof, and agrees to meet all requirements of Section
2.30.510 pertaining to nondiscrimination in employment.
SECTION 23. ENVIRONMENTALLY PREFERRED PURCHASING AND ZERO WASTE
REQUIREMENTS. CONSULTANT shall comply with the City’s Environmentally Preferred
Purchasing policies which are available at the City’s Purchasing Department, incorporated by
reference and may be amended from time to time. CONSULTANT shall comply with waste
reduction, reuse, recycling and disposal requirements of the City’s Zero Waste Program. Zero
Waste best practices include first minimizing and reducing waste; second, reusing waste and third,
recycling or composting waste. In particular, Consultant shall comply with the following zero waste
requirements:
All printed materials provided by Consultant to City generated from a personal
computer and printer including but not limited to, proposals, quotes, invoices,
reports, and public education materials, shall be double-sided and printed on a
minimum of 30% or greater post-consumer content paper, unless otherwise approved
by the City’s Project Manager. Any submitted materials printed by a professional
printing company shall be a minimum of 30% or greater post-consumer material and
printed with vegetable based inks.
Goods purchased by Consultant on behalf of the City shall be purchased in
accordance with the City’s Environmental Purchasing Policy including but not
limited to Extended Producer Responsibility requirements for products and
packaging. A copy of this policy is on file at the Purchasing Office.
Reusable/returnable pallets shall be taken back by the Consultant, at no additional
cost to the City, for reuse or recycling. Consultant shall provide documentation from
the facility accepting the pallets to verify that pallets are not being disposed.
SECTION 24. NON-APPROPRIATION
24.1. This Agreement is subject to the fiscal provisions of the Charter of the City of
Palo Alto and the Palo Alto Municipal Code. This Agreement will terminate without any penalty (a)
at the end of any fiscal year in the event that funds are not appropriated for the following fiscal year,
or (b) at any time within a fiscal year in the event that funds are only appropriated for a portion of
the fiscal year and funds for this Agreement are no longer available. This section shall take
precedence in the event of a conflict with any other covenant, term, condition, or provision of this
Agreement.
SECTION 25. MISCELLANEOUS PROVISIONS.
25.1. This Agreement will be governed by the laws of the State of California.
25.2. In the event that an action is brought, the parties agree that trial of such action
will be vested exclusively in the state courts of California in the County of Santa Clara, State of
California.
25.3. The prevailing party in any action brought to enforce the provisions of this
Agreement may recover its reasonable costs and attorneys' fees expended in connection with that
Professional Services
Rev. June 2, 2010
C13148958
action. The prevailing party shall be entitled to recover an amount equal to the fair market value of
legal services provided by attorneys employed by it as well as any attorneys’ fees paid to third
parties.
25.4. This document represents the entire and integrated agreement between the
parties and supersedes all prior negotiations, representations, and contracts, either written or oral.
This document may be amended only by a written instrument, which is signed by the parties.
25.5. The covenants, terms, conditions and provisions of this Agreement will apply
to, and will bind, the heirs, successors, executors, administrators, assignees, and consultants of the
parties.
25.6. If a court of competent jurisdiction finds or rules that any provision of this
Agreement or any amendment thereto is void or unenforceable, the unaffected provisions of this
Agreement and any amendments thereto will remain in full force and effect.
25.7. All exhibits referred to in this Agreement and any addenda, appendices,
attachments, and schedules to this Agreement which, from time to time, may be referred to in any
duly executed amendment hereto are by such reference incorporated in this Agreement and will be
deemed to be a part of this Agreement.
25.8 If, pursuant to this contract with CONSULTANT, City shares with
CONSULTANT personal information as defined in California Civil Code section 1798.81.5(d)
about a California resident (“Personal Information”), CONSULTANT shall maintain reasonable and
appropriate security procedures to protect that Personal Information, and shall inform City
immediately upon learning that there has been a breach in the security of the system or in the
security of the Personal Information. CONSULTANT shall not use Personal Information for direct
marketing purposes without City’s express written consent.
25.9 All unchecked boxes do not apply to this agreement.
25.10 The individuals executing this Agreement represent and warrant that they
have the legal capacity and authority to do so on behalf of their respective legal entities.
IN WITNESS WHEREOF, the parties hereto have by their duly authorized
representatives executed this Agreement on the date first above written.
Professional Services
Rev. June 2, 2010
C13148958
CITY OF PALO ALTO
____________________________
City Manager
APPROVED AS TO FORM:
__________________________
Senior Asst. City Attorney
RMC WATER AND ENVIRONMENT,
INC.
By:___________________________
Name:_________________________
Title:________________________
Attachments:
EXHIBIT “A”: SCOPE OF WORK
EXHIBIT “B”: SCHEDULE OF PERFORMANCE
EXHIBIT “C”: COMPENSATION
EXHIBIT “D”: INSURANCE REQUIREMENTS
Professional Services
Rev. June 2, 2010
EXHIBIT “A”
SCOPE OF SERVICES
RMC will prepare a single-issue EIR to address water quality impacts of irrigation with recycled
water. The EIR will be based on the same pipeline alignments and pump station sites as evaluated in
the Initial Study/Mitigated Negative Declaration (IS/MND) published by the City in March 2009.
RMC will, in consultation with the City, determine the alternatives to be analyzed upon reinitiation
of the project. RMC will evaluate the No Project Alternative, Proposed Project, and one other
alternative (e.g. additional treatment). This approach is preliminary; the scope of the CEQA
alternatives analysis would be confirmed and may require revision following the public scoping
period and conclusion of the water quality impact evaluation. RMC will also prepare environmental
documents that meet the Bureau of Reclamation National Environmental Policy Act requirements.
Each task is described below.
Environmental Impact Report
Notice of Preparation and Scoping Meeting
This task has been completed.
Draft EIR Preparation
The Draft EIR will focus on the water quality analysis of impacts of irrigation on landscape plants in
the project area, with particular emphasis on redwood trees. The Initial Study (IS) Checklist, which
includes the analysis for the remaining environmental topic areas, will be included as an appendix.
Other Draft EIR-related sections not specific to an environmental resource area, including the
Summary, Introduction, Project Description, and Alternatives will be presented in the upfront
sections of the EIR. Tasks for completion of the EIR are described below.
Administrative Draft EIR
The RMC team began work on the Project starting April 2010 and had prepared, to varying degrees,
different sections of the Administrative EIR. RMC will resume work on the Administrative Draft
EIR upon completion of the Project Description.
Project Description
RMC previously submitted a draft Project Description to the City. Upon receipt of requested details
and comments by the City, RMC will revise the project description. The City will confirm the
strategy for addressing redwood trees and other vegetation, If necessary, the Adaptive Management
Program that was included in the original project description will be modified to include any
recommendations developed as part of the water quality analysis. RMC will update the project
description that is included in the EIR.
Water Quality Analysis
The Water Quality section will focus only on salinity issues, with particular emphasis on effects on
redwood trees/vegetation. Other topics relating to hydrology and water quality have already been
addressed in the IS, which will be included as an appendix. The EIR will describe the existing
environmental and regulatory setting relevant to evaluation of salinity impacts, state where relevant
the impact significance criteria, describe the impacts of the proposed project, assess their
significance, and develop feasible mitigation measures as applicable to reduce or eliminate identified
impacts. The EIR will identify any cumulative and unavoidable impacts associated with use of
Professional Services
Rev. June 2, 2010
recycled water for irrigation.
HortScience, Inc. completed an investigation in June 2011 to evaluate impacts on plants of irrigation
with recycled water. The investigation consisted of the following: 1) collecting and sampling of
soils; 2) identifying plant species present and rating their appearance; 3) inspecting and describing
soil profiles within root zones; 4) mapping the 12 locations where such activities occurred; 5)
performing a survey-level soil landscape evaluation; 6) identifying constraints in using recycled
water on plants; and describing the effects of irrigation with recycled water. A summary report was
prepared following the above work activities. The findings of the HortScience report will be
incorporated into the EIR as appropriate.
Initial Study Update
RMC will update the IS/MND to reflect comments made during public review of the March 2009
IS/MND, and to meet new Bay Area Air Quality Management District (BAAQMD) requirements for
quantification of construction-period emissions. A new CNDDB search and a new NWIC search
were conducted in 2011 to determine if new, sensitive biological and cultural resources occur in the
project area. Beside the searches, field work and analysis had been initiated in 2011 on these
subjects, and more than 90 percent of the biological resources work and approximately 20 percent of
the cultural resources work had been done. The City will provide additional details requested in the
Project Description to complete the biological and cultural resources efforts. Due to the delays in the
project, there may be changes in the regulatory environment that warrant new searches be conducted
and revisions to the work already completed. This scope does not include such efforts. The
biological and cultural resources reports previously prepared for SWRCB will be updated as
necessary for submittal to the SWRCB.
Please refer to Exhibits C, D and E regarding the scope and budget for the biological and cultural
resources tasks conducted by Christopher Joseph and Associates (now Environ) and William Self
Associates, respectively.
CEQA Required Analyses
Most of the CEQA required analyses can be based on the analysis contained in the IS/MND. This
section will include evaluation of growth inducing impacts and cumulative impacts, and
identification of any significant irreversible environmental changes or significant unavoidable
adverse impacts. The EIR will also include a summary and evaluation of alternatives, including
identification of the environmentally superior alternative. With the exception of the cumulative
analysis, the other sections will be integrated in the upfront portion of the EIR. The cumulative
analysis will be included in the IS Checklist.
Document Preparation
RMC will prepare a concise, clearly written, and easily understandable Administrative Draft EIR
(ADEIR) summarizing the information developed in the above tasks. RMC will prepare all CEQA
Mandated Sections. RMC will include tangible (i.e., quantifiable) performance objectives for all
identified mitigation to the extent feasible, identification of appropriately timed monitoring,
identification of agency or staff responsible for monitoring, and mitigation or measures to be
implemented should the performance objectives not be met.
RMC will submit the ADEIR to the City for internal review and comment.
Screencheck Draft EIR
The City will provide comments on a single annotated comment copy of the ADEIR that provides
clear direction for revisions. Upon receipt of comments from the City, RMC will hold a meeting to
review comments and discuss the approach for revising the document. RMC will prepare a
Professional Services
Rev. June 2, 2010
Screencheck Draft EIR incorporating necessary revisions and refinements based upon comments
received from the City on the ADEIR. RMC will ensure that all City comments are addressed
thoroughly.
Deliverables: RMC will submit an ADEIR to the City. City staff will have up to three (3) weeks to
review the ADEIR and provide comments. Following receipt of comments from the City, RMC will
submit a Screencheck Draft within three (3) weeks. The City will have up to one (1) week to review
the Screencheck Draft EIR.
Public Review of Draft EIR
RMC will prepare a Draft EIR, incorporating necessary revisions and refinements based upon the
City’s final edits on the Screencheck Draft EIR. RMC will submit the Draft EIR in hard copy (20
bound copies, one unbound copy, and 20 CD copies) and electronic format ready for posting on the
City’s website. RMC will also submit a draft Notice of Availability and Notice of Completion
(NOC) to the City so that the City can advertise in the local newspaper and file the NOC at the State
Clearinghouse (along with 15 CD copies of the Draft EIR), respectively. RMC will submit 8 hard
copies of the Draft EIR and supporting documentation to the SWRCB. RMC will work with the City
to refine the NOP distribution list to produce a distribution list for the EIR.
RMC will work with the City to plan and conduct a public meeting to answer questions regarding
the Draft EIR. The public meeting may include an open house format to allow the maximum
opportunity for the public to ask questions and get information about the project.
Deliverables: RMC will prepare a Draft EIR within one (1) week of receipt of comments from the
City on the Screencheck Draft EIR. RMC will submit a NOA and NOC to the City. RMC will assist
the City in preparing for and conducting a public review meeting during the EIR public comment
period.
Final EIR and Associated Documents
RMC will meet with the City at the close of the comment period during the final EIR phase to
identify and develop approaches for key issues raised. If appropriate, RMC may use master
responses for topics of greatest interest to local agencies and the surrounding community. The scope
of work assumes 78 hours of staff time to determine with the City the approach to respond to public
comments, bracket the comments, and provide written response to the comments; should the
estimated level of effort for preparing responses exceed the hours assumed, additional work would
need to be authorized through a contract modification.
Draft Final EIR (Response to Comments document), MMRP, and Findings
The Final EIR will consist of the Response to Comments (RTC) document and Public Draft EIR.
RMC will prepare an a RTC document that includes: 1) all letters received on the Draft EIR and
summaries of all substantive comments made on the Draft EIR at the public meeting, 2) responses to
each comment, and 3) text revisions to the Draft EIR shown in errata format. RMC will also prepare
a Draft MMRP, which will consolidate all required and recommended mitigation measures into one
table. In addition, RMC will prepare draft Findings. RMC will submit the Draft Response to
Comments document, Draft MMRP, and Draft Findings to the City for review.
Screencheck Final EIR (RTC document), MMRP, and Findings
RMC will revise the Draft RTC document, Draft MMRP, and Draft Findings per City
recommendations and a screencheck will be submitted for review.
Professional Services
Rev. June 2, 2010
Final EIR (RTC document), MMRP, and Findings
RMC will submit the Final Response to Comments document, MMRP, and Findings to the City in
electronic format. RMC will provide 20 bound copies and one unbound copy of the final Response
to Comments document. RMC will attend the certification hearing and will be prepared to answer
questions from the City Council. RMC will prepare a Notice of Determination for the City to file
with the State Clearinghouse.
Deliverables: RMC will prepare a Draft Response to Comments document, draft and Final MMRP,
and draft and Final Findings. RMC will also prepare a Notice of Determination. The City will have
up to two (2) weeks to review and provide comments. Following receipt of comments, RMC will
submit a Screencheck Response to Comments Document, MMRP, and Findings to the City within
one (1) week. The City will have one (1) week to review and provide comments. Following receipt
of comments, RMC will submit the Final EIR, MMRP, and Findings within one week.
NEPA Documentation
RMC will assist the City in obtaining NEPA clearance from the U.S. Bureau of Reclamation
(USBR), so that the project can qualify for federal funding. Previously, it was assumed that an EA
would be required for USBR compliance. As such, preparation of the EA had occurred in parallel
with the EIR. However, based on communication with USBR in July 2011, a new strategy has been
identified. USBR recommended preparation of a brief Supplemental Information Document.
Combined with the CEQA EIR, the Supplemental Information Document would lead to a Finding of
No Significant Impact (FONSI). USBR has suggested that the Supplemental Information Document
would be prepared close to the completion of the EIR (during the latter part of the Final EIR
preparation stage), so that all issues have been dealt with adequately in the EIR process. RMC will
complete the tasks identified below. Please refer to Exhibits C, D and E regarding the scope and
budget for the biological and cultural resources tasks conducted by Environ and William Self
Associates, respectively.
Administrative Draft Supplemental Information Document
RMC will prepare Administrative Drafts of a Supplemental Information Document to submit to
USBR. The Supplemental Information Document will be brief (less than 20 pages) and would
include additional topical analysis required by NEPA, including socioeconomics and environmental
justice.
Deliverables: RMC will submit an Administrative Draft Supplemental Information Document to
USBR. It is assumed that USBR staff will require up to four (4) weeks to review and comment on the
Administrative Draft Supplemental Information Document and associated documents.
Screencheck Draft Supplemental Information Document
USBR will provide comments on a single annotated comment copy of the Administrative Draft
Supplemental Information Document that provides clear direction for revisions. Upon receipt of
comments from USBR, RMC will revise the document and prepare a Screencheck Draft
Supplemental Information Document, incorporating necessary revisions and refinements based upon
comments received from USBR on the supplemental document . RMC will ensure that all USBR
comments are addressed thoroughly. Deliverables: Following receipt of comments from USBR,
RMC will submit a Screencheck Draft within three (3) weeks. USBR will have up to one (1) week to
review the Screencheck Draft EA.
Professional Services
Rev. June 2, 2010
Final Supplemental Information Document
RMC will prepare the Final Supplemental Information Document, incorporating necessary revisions
and refinements based upon USBR final edits on the Screencheck Draft Supplemental Information
Document. RMC will submit the Final Supplemental Information Document to USBR in hard copy
(10 bound copies and one unbound copy) and electronic format.
Deliverables: RMC will prepare a Final Supplemental Information Document within one (1) week
of receipt of comments from USBR on the Screencheck Draft Supplemental Information Documents.
Project Management / Meetings
RMC will coordinate with the City, USBR, RMC’s subconsultants and internal staff on all CEQA
and NEPA items related to the project. This task also includes two conference calls / one meeting
with the City and/or USBR to discuss CEQA / NEPA issues at key junctures of the process. This
task also covers preparation of monthly invoices and progress reports. It should be noted that as the
project timeframe has been extended well beyond the anticipated 10 months (although a portion of
time the project was on hold), and project management tasks (including conference calls and
meetings) were still being conducted to address outstanding issues (e.g., salinity approach), the
remaining budget for this task is limited.
Deliverables: RMC will submit monthly status reports to the City.
Optional Services
The following tasks are optional tasks that will require authorization by the City before can be
initiated. It should be noted that portions of the optional tasks have been authorized for both Environ
and WSA.
NEPA Documentation
USBR may have additional consultation requirements related to Section 7 and Section 106
consultation. The need for and level of consultation have not been determined and will be
determined based on discussions with USBR. The optional tasks include both Sections 7 and 106
consultations. Please refer to Exhibits C, D and E regarding the scope and budget for the biological
and cultural resources tasks conducted by Environ and William Self Associates, respectively. The
current strategy related to Section 7 consultation (to address biological resources effects) is to
include biological resources-related environmental commitments (Avoidance Measures) in the
Project Description so the City can proceed with informal consultation with the USFWS (rather than
formal consultation). We will need the City’s confirmation to commit to these measures. It should be
noted that the final determination for formal or informal consultation has not yet been determined
and will be determined by USFWS.
Assumptions
Additional outreach beyond the EIR preparation is not assumed in this scope of work /
budget.
No new substantive issues (beyond those the City has already encountered during the public
comment phase of the IS/MND) are assumed to arise.
The Project Description is assumed to be generally complete, with the exception of
additional details that will require City input. Once the City responds to the requested
information on the Project Description and provides direction on salinity strategy, the project
Professional Services
Rev. June 2, 2010
will be reinitiated. Currently, the project is anticipated to reinitiate on March 4, 2013. For the
purposes of the Microsoft schedule the initiation date is assumed to be March 4, 2013.
The City will provide comments (including requested information) on all deliverables
promptly.
Other sections of the EIR that will be developed include: Summary, Introduction,
Alternatives, and Cumulative Impacts. With the exception of the Cumulative Impacts, the
other sections will be included in the upfront portion of the EIR.
One public meeting is assumed during the public comment period for the Public Draft EIR.
RMC will provide support (presentation preparation) and attend the Public Meeting (4 hours
for two staff members). The City will coordinate the meeting planning, present at, and
facilitate the meeting.
ODCs for the Public Draft EIR covers printing, mailing, and travel expenses. Graphics in the
document will be printed in black and white only. A maximum of 28 hard copies will be
printed (which includes 20 copies for the City and 8 copies for SWRCB), a maximum of 50
copies of a CD will be burned if needed (15 will be sent to SCH), and a maximum of 100
notices (NOA) if needed will be printed. The City will be responsible for publishing the
notice in the local newspaper and/or posting the notice at the project sites.
Preparation of the Response to Comments document is based on hours, which may increase
depending on the number of comments received. Should the estimated level of effort exceed
the hours assumed, additional work would need to be authorized through a contingency
release or other appropriate contract modification.
The City will prepare and send response letters to responsible agencies commenting on the
EIR.
The Draft EIR and the Response to Comments (with errata) constitutes the Final EIR
document; RMC will not print an Integrated EIR.
For all deliverables, only one administrative draft and one screencheck are proposed. If
additional deliverables are included, then the work effort will increase.
For all CEQA-related deliverables, we assume one set of consolidated, non-conflicting
comments from the Utilities and Planning Departments.
For all NEPA-related deliverables, we assume they will be reviewed by the USBR only (not
the City). Thus, the hours identified for preparation of NEPA deliverables are based on two
rounds of comments from USBR only, and not additional comments from the City.
For NEPA deliverables, we assume one set of consolidated, non-conflicting comments from
the USBR.
USBR will be responsible for all noticing of NEPA documents.
The City will file the Notice of Determination with the State Clearinghouse.
It is assumed that the NEPA Supplemental Information Document would be published after
the publication of the EIR, such that any issues arising from the EIR will have been resolved.
The EIR, in combination with the Supplemental Information Document, is the basis of the
FONSI.
Professional Services
Rev. June 2, 2010
Project management includes coordination with the City, USBR, and the internal team. It is
possible that the schedule as shown will be delayed if the initiation date is delayed, the
salinity approach requires further refinement beyond RMC’s control, or the NEPA process
takes longer than expected.
We assume that protocol-level surveys for special-status plants or animal species or formal
delineation of waters and wetlands will not be conducted. The Environ biological team can
conduct such studies if required and requested; however, an expanded scope and cost
estimate would be required for such services.
Professional Services
Rev. June 2, 2010
EXHIBIT “B”
SCHEDULE OF PERFORMANCE
CONSULTANT shall perform the Services so as to complete each milestone within the number
of days/weeks specified below. The time to complete each milestone may be increased or
decreased by mutual written agreement of the project managers for CONSULTANT and CITY
so long as all work is completed within the term of the Agreement. CONSULTANT shall
provide a detailed schedule of work consistent with the schedule below within 2 weeks of receipt
of the notice to proceed.
Task Name Duration Start Finish
Project Reinitiated / City provides all outstanding items on PD 1 day Mon 3/4/13 Mon 3/4/13
1.2 DEIR Preparation 176 days Tue 3/5/13 Mon 11/11/13
RMC Prepares ADEIR 80 days Tues 3/5/13 Tues 6/25/13
City reviews ADEIR 45 days Wed 6/26/13 Wed 8/28/13
RMC prepares Screencheck DEIR 25 days Thu 8/29/13 Thu 10/3/13
City reviews Screencheck DEIR 25 days Fri 10/4/13 Fri 11/8/13
Meeting with City to discuss City comments on
Screencheck EIR
1 day Mon 11/11/13 Mon 11/11/13
1.3 Public Review of Draft EIR 55 days Tue 11/12/13 Mon 2/3/14
RMC prepares Draft EIR, NOA, and NOC 25 days Tue 11/12/13 Wed 12/18/13
DEIR publication 0 days Wed 12/18/13 Wed 12/18/13
DEIR public review period 47edays Wed 12/18/13 Mon 2/3/14
Public Meeting 0 days Mon 1/13/14 Mon 1/13/14
1.4 Final EIR and Associated Documents 129 days Tue 2/4/14 Wed 8/6/14
Meeting with City to discuss public comments on DEIR 1 day Tue 2/4/14 Tues 2/4/14
RMC prepares Draft RTC, MMRP, Findings 30 days Wed 2/5/14 Wed 3/19/14
City reviews Draft RTC, MMRP, Findings 30 days Thu 3/20/14 Wed 4/30/14
RMC prepares screencheck RTC, MMRP, and Findings 20 days Thu 5/1/14 Thu 5/29/14
City reviews screencheck RTC, MMRP, and Findings 20 days Fri 5/30/14 Thu 6/26/14
RMC prepares Final RTC, MMRP, and Findings 20 days Fri 6/27/14 Fri 7/25/14
EIR Certification/Project Approval (2nd and last Weds of
the month)
1 day Tue 8/5/14 Tue 8/5/14
File NOD 1 day Wed 8/6/14 Wed 8/6/14
2 NEPA Documentation 128 days Fri 6/27/14 Wed 12/31/14
RMC prepares Administrative Draft Supplemental
Information Document
30 days Fri 6/27/14 Fri 8/8/14
USBR reviews Administrative Draft Supplemental
Information Document
30 days Mon 8/11/14 Mon 9/22/14
RMC prepares Screencheck Draft Supplemental
Information Document
20 days Tue 9/23/14 Tue 10/21/14
USBR reviews Screencheck Draft Supplemental
Information Document
20 days Wed 10/22/14 Wed 11/19/14
RMC prepares Final Supplemental Information Document 8 days Thu 11/20/14 Tue 12/2/14
Supplemental Information Document and FONSI
Publication/signatures
20 days Wed 12/3/14 Wed 12/31/14
Professional Services
Rev June 2, 2010
EXHIBIT “C”
COMPENSATION
The CITY agrees to compensate the CONSULTANT for professional services performed in
accordance with the terms and conditions of this Agreement, and as set forth in the budget
schedule below. Compensation shall be calculated based on the hourly rate schedule as in
Exhibit C up to the not to exceed budget amount for each task set forth below.
The compensation to be paid to CONSULTANT under this Agreement for all services
described in Exhibit “A” (“Basic Services”) and reimbursable expenses shall not exceed
$176,286. CONSULTANT agrees to complete all Basic Services, including reimbursable
expenses, within this amount. In the event CITY authorizes any Additional Services, the
maximum compensation shall not exceed $193,914. Any work performed or expenses
incurred for which payment would result in a total exceeding the maximum amount of
compensation set forth herein shall be at no cost to the CITY.
CONSULTANT shall perform the tasks and categories of work as outlined and budgeted
below. The CITY’s Project Manager may approve in writing the transfer of budget amounts
between any of the tasks or categories listed below provided the total compensation for Basic
Services, including reimbursable expenses, does not exceed $176,286 and the total
compensation for Additional Services does not exceed $17,628.
BUDGET SCHEDULE NOT TO EXCEED AMOUNT
Task 1 $97,778
(Environmental Impact Report)
Task 2 $31,507
(NEPA Documentation)
Task 3 $8,601
(Project Management)
Task 4 $38,400
(Optional Tasks)
Sub-total Basic Services $176,286
Total Basic Services and Reimbursable expenses $176,286
Additional Services (Not to Exceed) $17,628
Maximum Total Compensation $193,914
REIMBURSABLE EXPENSES
Professional Services
Rev June 2, 2010
The administrative, overhead, secretarial time or secretarial overtime, word processing,
photocopying, in-house printing, insurance and other ordinary business expenses are included
within the scope of payment for services and are not reimbursable expenses. CITY shall
reimburse CONSULTANT for the following reimbursable expenses at cost.
All requests for payment of expenses shall be accompanied by appropriate backup
information. Any expense anticipated to be more than $500 shall be approved in advance by
the CITY’s project manager.
ADDITIONAL SERVICES
The CONSULTANT shall provide additional services only by advanced, written
authorization from the CITY. The CONSULTANT, at the CITY’s project manager’s request,
shall submit a detailed written proposal including a description of the scope of services,
schedule, level of effort, and CONSULTANT’s proposed maximum compensation, including
reimbursable expense, for such services based on the rates set forth in Exhibit C. The
additional services scope, schedule and maximum compensation shall be negotiated and
agreed to in writing by the CITY’s Project Manage and CONSULTANT prior to
commencement of the services. Payment for additional services is subject to all requirements
and restrictions in this Agreement
Professional Services
Rev June 2, 2010
EXHIBIT “D”
INSURANCE REQUIREMENTS
CONTRACTORS TO THE CITY OF PALO ALTO (CITY), AT THEIR SOLE EXPENSE, SHALL FOR THE TERM OF THE CONTRACT
OBTAIN AND MAINTAIN INSURANCE IN THE AMOUNTS FOR THE COVERAGE SPECIFIED BELOW, AFFORDED BY COMPANIES
WITH AM BEST’S KEY RATING OF A-:VII, OR HIGHER, LICENSED OR AUTHORIZED TO TRANSACT INSURANCE BUSINESS IN
THE STATE OF CALIFORNIA.
AWARD IS CONTINGENT ON COMPLIANCE WITH CITY’S INSURANCE REQUIREMENTS, AS SPECIFIED, BELOW:
REQUIRED TYPE OF COVERAGE REQUIREMENT
MINIMUM LIMITS
EACH
OCCURRENCE AGGREGATE
YES
YES
WORKER’S COMPENSATION
EMPLOYER’S LIABILITY
STATUTORY
STATUTORY
YES
GENERAL LIABILITY, INCLUDING
PERSONAL INJURY, BROAD FORM
PROPERTY DAMAGE BLANKET
CONTRACTUAL, AND FIRE LEGAL
LIABILITY
BODILY INJURY
PROPERTY DAMAGE
BODILY INJURY & PROPERTY DAMAGE
COMBINED.
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
YES AUTOMOBILE LIABILITY, INCLUDING
ALL OWNED, HIRED, NON-OWNED
BODILY INJURY
- EACH PERSON
- EACH OCCURRENCE
PROPERTY DAMAGE
BODILY INJURY AND PROPERTY
DAMAGE, COMBINED
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
$1,000,000
PROFESSIONAL LIABILITY, INCLUDING,
ERRORS AND OMISSIONS,
MALPRACTICE (WHEN APPLICABLE),
AND NEGLIGENT PERFORMANCE
ALL DAMAGES $1,000,000
YES THE CITY OF PALO ALTO IS TO BE NAMED AS AN ADDITIONAL INSURED: CONTRACTOR, AT ITS SOLE COST AND EXPENSE,
SHALL OBTAIN AND MAINTAIN, IN FULL FORCE AND EFFECT THROUGHOUT THE ENTIRE TERM OF ANY RESULTANT
AGREEMENT, THE INSURANCE COVERAGE HEREIN DESCRIBED, INSURING NOT ONLY CONTRACTOR AND ITS SUBCONSULTANTS,
IF ANY, BUT ALSO, WITH THE EXCEPTION OF WORKERS’ COMPENSATION, EMPLOYER’S LIABILITY AND PROFESSIONAL
INSURANCE, NAMING AS ADDITIONAL INSUREDS CITY, ITS COUNCIL MEMBERS, OFFICERS, AGENTS, AND EMPLOYEES.
I. INSURANCE COVERAGE MUST INCLUDE:
A. A PROVISION FOR A WRITTEN THIRTY DAY ADVANCE NOTICE TO CITY OF CHANGE IN
COVERAGE OR OF COVERAGE CANCELLATION; AND
B. A CONTRACTUAL LIABILITY ENDORSEMENT PROVIDING INSURANCE COVERAGE FOR
CONTRACTOR’S AGREEMENT TO INDEMNIFY CITY.
C. DEDUCTIBLE AMOUNTS IN EXCESS OF $5,000 REQUIRE CITY’S PRIOR APPROVAL.
II. CONTACTOR MUST SUBMIT CERTIFICATES(S) OF INSURANCE EVIDENCING REQUIRED COVERAGE.
III. ENDORSEMENT PROVISIONS, WITH RESPECT TO THE INSURANCE AFFORDED TO “ADDITIONAL
INSUREDS”
A. PRIMARY COVERAGE
WITH RESPECT TO CLAIMS ARISING OUT OF THE OPERATIONS OF THE NAMED INSURED, INSURANCE AS
AFFORDED BY THIS POLICY IS PRIMARY AND IS NOT ADDITIONAL TO OR CONTRIBUTING WITH ANY OTHER
INSURANCE CARRIED BY OR FOR THE BENEFIT OF THE ADDITIONAL INSUREDS.
B. CROSS LIABILITY
Professional Services
Rev June 2, 2010
THE NAMING OF MORE THAN ONE PERSON, FIRM, OR CORPORATION AS INSUREDS UNDER THE POLICY SHALL
NOT, FOR THAT REASON ALONE, EXTINGUISH ANY RIGHTS OF THE INSURED AGAINST ANOTHER, BUT THIS
ENDORSEMENT, AND THE NAMING OF MULTIPLE INSUREDS, SHALL NOT INCREASE THE TOTAL LIABILITY OF
THE COMPANY UNDER THIS POLICY.
C. NOTICE OF CANCELLATION
1. IF THE POLICY IS CANCELED BEFORE ITS EXPIRATION DATE FOR ANY REASON OTHER
THAN THE NON-PAYMENT OF PREMIUM, THE ISSUING COMPANY SHALL PROVIDE CITY
AT LEAST A THIRTY (30) DAY WRITTEN NOTICE BEFORE THE EFFECTIVE DATE OF
CANCELLATION.
2. IF THE POLICY IS CANCELED BEFORE ITS EXPIRATION DATE FOR THE NON-PAYMENT
OF PREMIUM, THE ISSUING COMPANY SHALL PROVIDE CITY AT LEAST A TEN (10) DAY
WRITTEN NOTICE BEFORE THE EFFECTIVE DATE OF CANCELLATION.
NOTICES SHALL BE MAILED TO:
PURCHASING AND CONTRACT ADMINISTRATION
CITY OF PALO ALTO
P.O. BOX 10250
PALO ALTO, CA 94303