HomeMy WebLinkAbout2002-06-24 City Council (11)City of Palo Alto
City Manager’s Report
TO:
FROM:
DATE:
HONORABLE CITY COUNCIL
CITY MANAGER
JUNE 24, 2002
DEPARTMENT: UTILITIES
CMR:287:02
SUBJECT:APPROVAL OF A CONTRACT WITH ST. FRANCIS ELECTRIC
IN THE AMOUNT OF $269,915 FOR CONSTRUCTION OF
DOWNTOWN STREET LIGHTING IMPROVEMENTS
RECOMMENDATION
Staff recommends that Council:
o
Approve and authorize the Mayor to execute the attached contract with St. Francis
Electric in the amount of $269,915 for downtown street lighting improvements.
Authorize the City Manager or his~ designee to negotiate and execute one or more
change orders to the contract with St. Francis Electric for related, additional but
unforeseen work, which may develop during the project, the total value of which
shall not exceed $ 26,990.
DISCUSSION
Project Description
In 1997, Council directed staff to undertake a number of projects to improve the safety in
the downtown area. In 1999, an assessment of the lighting levels found that there were
dark spots that needed additional lighting. This project will increase lightinglevels. If this
project is not performed, lighting levels in the downtown area will remain at present
levels.
The work to be performed under the contract is the installation of new street light poles
and fixtures in the downtown area, including labor, equipment, and material to install the
complete substructure and duct system and necessary landscaping repairs. The new lights
CMR:287:02 Page 1 of 3
will be in.stalled in the area bordered by Alma Street, Lytton Avenue, Middlefield Road,
and Hamilton Avenue. However, no additional lights will be installed on University
Avenue between Alma Street and Webster Street because lighting levels are sufficient.
This area was improved in 1994..
Bid Process
A notice inviting formal bids for downtown street and roadway lighting improvements
project was sent on April 29, 2002 to five contractors. The bidding period was 29 days.
A pre-bid meeting was held on May 16, 2002; ~two bidders attended the meeting. Bids
were received from three qualified contractors on May 28, 2002, as listed on the attached
bid summary (Attachment A).. Bids ranged from a high of $401,599 to a low bid of
$269,915. One contractor did not respond. Another contractor indicated that his street
lighting group was too busy. Staff has reviewed all bids submitted and recommends that
the bid of $269,915 submitted by St. Francis Electric be accepted and that St. Francis
Electric be declared the lowest responsible bidder. The bid is 24 percent below the
staff/engineer’s estimate of $356,000 of available funds. The change order amount of
$26,990, which equals 10 percent of the total contract, is requested tO cover related but
unforeseen work (e.g., possible underground obstacles or conflicts which may arise while
digging in the downtown area).
Staff checked references supplied by the contractor for previous work performed and
found no significant complaints. Staff also checked with the Contractor’s State License
Board and found that the contractor has an active license on file.
RESOURCE IMPACT
Operating impact equals increased maintenance expenses for ,the new lights, poles, and
for tree trimming around the new lights. Utilities is contracting for this construction
because the two person street lighting crew is busy maintaining the approximately 6,000 ¯
existing street lights and does not have time available for a large construction project.
Funds are available in the FY-01/02 CIP (Project 0116).
POLICY IMPLICATIONS
This recommendation is consistent with current City policy and with the Council
approved Utilities Strategic Plan, especially supporting strategy 7: Implement programs
that improve the quality of the environment.
CMR:287:02 Page 2 of 3
ENVIRONMENTAL REVIEW
Categorically exempt from environmental
replacement of existing utility facilities.
ATTACHMENTS
A:Bid Summary
B:Contract
impact under Section 15302
PREPARED BY:
Sr. Electric Project Engineer
of CEQA,
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
CH
of Utilities
EMIL~HA~RI-SON
Assistant City Manager
CMR:287:02 Page 3 of 3
Attachment A
Bid Summary
Base Bid
Alternate 1
Alternate 2
Total
St. Francis Electric
$209,500
$27,215
$33,200
$269,915
Underground Const.West Valley Const.Lewis & Tibbitts Rosendin Electric
$330,858 $313,600 No Bid No Bid
$28,296 $30,500
$42,445 $34,200
$401,599 $378,300 No Bid No Bid
s.w.zuccaro
06/10~002
FORMAL CONTRACT SECTION 500
CONTRACT No. C2143754
(public work)
Utilities Department
This Contract, number C2143754 dated June 24, 2002 is entered into by and between the City of Palo Alto, a
chartered city and a municipal corporation of the State of California (City), and St. Francis Electric (Contractor).
For and in consideration of the covenants, terms, and conditions (the. prov sons) of this Contract, City and Contractor
(the parties) agree:
Term. This Contract shall commence and be binding on the parties on the Date of Execution of this Contract,
and shall expire on the date of recordation of the Notice of Substantial Completion, or, if no such notice is
required to be filed, on the date that final payment is made hereunder, subject to the earlier termination of this
Contract.
General Scope of Project and Work. Contractor shall furnish labor, services, materials and equipment in
connection with the construction of the Project and complete the Work in accordance with the covenants, terms
and conditions of this Contract to the satisfaction of City. The Project and Work is generally described as
follows:
Title of Project: ’ Downtown Street and Roadway Lighting Improvements Project, Invitation for Bid (IFB)
Number 143754
3°
Bid:$ 269,915.00
Contract Documents. This Contract shall consist of the documents set forth below, which are on file with the
City Clerk and are hereby incorporated by reference. For the purposes of construing, interpreting and resolving
inconsistencies between and among the provisions of this Contract, these documents and the provisions
thereof are set forth in the following descending order of precedence.
This Contract.
Invitation For Bid.
Project Specifications.
Drawings.
Change Orders.
Bid.
Supplementary Conditions.
General Conditions.
Standard Drawings and Specifications (1999).
Certificate of Insurance, Performance Bond, Labor & Materials (Payment) Bond.
Other Specifications, or part thereof, not expressly incorporated in the Contract Specifications or the
Standard Drawings and Specifications (1999).
Any other document not expressly mentioned herein which is issued by City or entered into by the
parties.
4=Compensation. In consideration of Contractor’s performance of its obligations hereunder, City shall pay to
Contractor the amount set forth in Contractor’s Bid in accordance with the provisions of this Contract and upon
the receipt of written invoices and all necessary supporting documentation within the time set forth in the
Contract Specifications and the Standard Drawings and Specifications (1999), or, if no time is.stated, within
thirty (30) Days of the date Of receipt of Contractor’s invoices.
5o Insurance. On or before the Date of Execution, Contractor shall obtain and maintain the policies of insurance
coverage described in the Invitation For Bid on terms and conditions and in amounts as may be required bythe
Risk Manager. City shall not be obligated to take out insurance on Contractor’s personal property or the
personal property of any person performing labor or services or supplying materials or equipment under the
Project. Contractor shall furnish City with the certificates of insurance and with original endorsements affecting
coverage required under this Contract on or before the Date of Execution. The certificates and endorsements
for each insurance policy shall be signed by a person who is authorized by that insurer to bind coverage in its
behalf. Proof of insurance shall be mailed to the Project Manager to the address set forth in Section 15 of this
CITY OF PALO ALTO C2143754 PAGE 1 OF 7
FORMAL CONTRACT
Contract.
=
8o
o
10.
SECTION 500
11.
Indemnification. Contractor agrees to protect, defend, indemnify and hold City, its council members, officers,
employees, agents and representatives harmless from and against any and all claims, demands, liabilities,
losses, damages, costs, expenses, liens, penalties, suits, or judgments, arising, in whole or in part, directly or
indiractiy, at any time from any injury to or death of persons or damage to property as a result of the willful acts
¯ or the negligent acts or omissions of Contractor, or which results from Contractor’s noncompliance with any Law
respecting the condition, use, occupation or safety of the Project site, or any part thereof, or which arises from
Contractor’s failure to do anything required under this Contract or for doing anything which Contractor is
required not to do under this Contract, or which adses from conduct for which any Law may impose strict liability
on Contractor in the performance of or failure to perform the provisions of this Contract, except as may adse
from the sole willful acts or negligent acts or omissions of City or any of its Council members, officers,
employees, agents or representatives. This indemnification shall extend to any and all claims, demands, or
liens made or filed by reason of any work performed by Contractor under this contract at any time dudng the
term of this Contract, or arising thereafter.
To the extent Contractor will use hazardous materials in connection with the execution of its obligations under
this Contract, Contractor further expressly agrees to protect, indemnify, hold harmless and defend City, its City
Council members, officers and employees from and against any and all claims, demands, liabilities, losses,
damages, costs, expenses, liens, penalties, suits, or judgments City may incur, arising, in whole or in part, in
connection with or as a result of Contractor’s willful acts or negligent acts or omissions under this Contract,
under the Comprehensive Environmental Response, Compensation and Liability Act (42 U.S.C. ~9601-6975,
as amended); the Resource Conservation and Recovery Act (42 U.S.C. ~6901-6992k, as amended); the Toxic
Substances Control Act (15 U.S.C. ~2601-2692, as amended); the Carpenter-Presley-Tanner Hazardous
Substance Account Act (Health & Safety Code, ~25300-25395, as amended); the Hazardous Waste Control
Law (Health & Safety Code, ~25100-25250.25, as amended); the Safe Drinking Water and Toxic Enforcement
Act (Health &.Safety Code, ~25249.5-25249.13, as amended); the Underground Storage of Hazardous
Substances Act (Health & Safety Code, ~25280-25299.7, as amended); or under any other local, state or
federal law, statute or ordinance, or at common law.
Assumption of Risk. Contractor agrees to voluntarily assume any and all risk of loss, damage, or injury to the
property of Contractor which may occur in, on, or about the Project site at any time and in any manner,
excepting such loss, injury, or damage as may be caused by the sole willful act or negligent act or omission of
City or any of its Council members, officers, employees, agents or representatives.
Waiver. The acceptance of any payment or performance, or any part thereof, shall not operate as a waiver by
City of its rights under this Contract. A waiver by City of any breach of any part or provision of this Contract by
Contractor shall not operate as a waiver or continuing waiver of any subsequent breach of the same or any
other provision, nor shall any custom or practice which may adse between the parties in the administration of
any part or provision of this Contract be construed to waive or to lessen the right of City to insist upon the
performance of Contractor in strict compliance with the covenants, terms and conditions of this Contract.
No Exoneration By Inspection: The City has the dght, but not the duty, to inspect Contractor’s Work. The right
of inspection is solely for the benefit of City, Contractor has the obligation to complete the Work in a
satisfactory manner in compliance with Contract requirements. The presence of a City inspector does not shift
that obligation to the City or relieve Contractor from its obligations to completa the Work in a satisfactory
manner in compliance with the Contract requirements.
Compliance with Laws. Contractor shall comply with all Laws now in force or which may hereafter be in force
pertaining to the Project and Work and this Contract, with the requirement of any bond or fire underwriters or
other similar body now or hereafter constituted, with any discretionary license or permit issued pursuant to any
Law of any public agency or official as well as with any provision of all recorded documents affecting the Project
site, insofar as any are required by reason of the use or occupancy of the Project site, and with all Laws
pertaining to nondiscrimination in employment and hazardous materials.
Bonds. As a co.ndition precedent to City’s obligation to pay compensation to Contractor, and on or before the
Date of Execution, Contractor shall fumish to the Project Manager the Bonds as required under the Invitation
For Bid.
CITY OF PALO ALTO C2143754 PAGE 2 OF 7
FORMAL CONTRACT SECTION 500
12.Representations and Warranties. In the supply of any materials and equipment and the rendering of labor and
services during the course and scope of the Project and Work, Contractor represents and warrants:
ao Any materials and equipment which shall be used dudng the course and scope of the Project and
Work shall be vested in Contractor;
bo Any materials and equipment which shall be Used during the course and scope of the Project and
Work shall be merchantable and fit to be used for the particular purpose for which the materials are
required;
Any labor and services rendered and materials and equipment used or employed dudng the course
and scope of the Project and Work shall be free of defects in workmanship for a period of one (1) year
after the recordation of the Notice of Substantial Completion, or, if no such notice is required to be
filed, on the date that final payment is made hereunder;
d°Any manufacturer’s warranty obtained by Contractor shall be obtained or shall be deemed obtained by
Contractor for and in behalf of City.
Any information submitted by Contractor pdor to the award of Contract, or thereafter,, upon request,
whether or not submitted under a continuing obligation by the terms of the Contract to do so, is true
and correct at the time such information is submitted or made available to the City;
Contractor has not colluded, conspired, or agreed, directly or indirectly, withany person in regard to
the terms and conditions of Contractor’s Bid, except as may be permitted by the Invitation For Bid;
Contractor has the power and authority to enter into this Contract with City, that the individual
executing this Contract is duly authorized to do so by appropriate resolution, and that this Contract
shall be executed, delivered and performed pursuant to the power and authority conferred upon the
person or persons authorized to bind Contractor;
ho Contractor has not made an attempt to exert undue influence with the Purchasing Manager or Project
Manager or any other person who has directly contributed to C ty’s decision to award the contract to
Contractor;
There are no unresolved claims or disputes between Contractor and City which would materially affect
Contractor’s ability to perform under the Contract;
Contractor has furnished and will furnish true and accurate statements, records, reports, resolutions,
certifications, and other wdtten information as may be requested of Contractor by City from time to
time during the term of this Contract;
k°Contractor and any person performing labor and services under this Project are duly licensed by the
State of Califomia as required by California Business & Professions Code Section 7028, as amended;
and
Contractor has fully examined and inspected the Project site and has full knowledge of the physical
conditions of the Project site.
13.Assignment. This Contract and the performance required hereunder is personal to Contractor, and it shall not
be assigned by Contractor. Any attempted assignment shall be null and void.
14.Claims of Contractor. All claims pertaining to extra work, additional charges, or delays within the Contract Time
or other disputes arising out of the Contract shall be submitted by Contractor to City in writing by certified or
registered mail within ten (10) Days after the claim arose or within such other time as may be permitted or
required by law, and shall be described in sufficient detail to give adequate notice of the substance of the claim
to City.
15.Audits by City. During the term of this Contract and for a period of not less than three (3) years after the
expiration or earlier termination of this Contract City shall have the right to audit Contractor’s Project-related ¯
CITY OF PALO ALTO C2143754 PAGE 3 OF 7
FORMAL CONTRACT SECTION 500
and Work-related writings and business records, as such terms are defined in California Evidence Code
Sections 250 and 1271, as amended, during the regular business hours of Contractor, or, if Contractor has no
such hours, during the regular business hours of City.
Notices. All agreements, appointments, approvals, authorizations, claims, demands, Change Qrders, consents,
designations, notices, offers, requests and statements given by either party to the other shall be in writing and
shall be sufficiently given and served upon the other party if (1) personally served, (2) sent by the United States
mail, postage prepaid, (3) Sent by private express delivery service, or (4) in the case of a facsimile transmission,
if sent to the telephone FAX number set forth below during regular business hours of the receiving party and
followed within two (2) Days by delivery of a hard copy of the material sent by facsimile transmission, in
accordance with (1), (2) or (3) above. Personal service shall include, without limitation, service by delivery and
service by facsimile transmission.
To City:City of Palo Alto
City Clerk
250 Hamilton Avenue
P.O. Box 10250
Palo Alto, CA 94303
Copy to:City of Palo Alto
Utilities Department
250 Hamilton Avenue
Palo Alto, CA 94303
Attn: Sam Zuccaro, Project Manager
To Contractor:St. Francis Electric
23294 Connecticut Street
Hayward; CA 94545
17.
18,
Attn: Tom Spinardi
Appropriation of City Funds. This Contract is subject to the fiscal provisions of Article III, Section 12 of the
Charter of the City of Palo Alto. Any charges hereunder forlabor, services, materials and equipment may
accrue only after such expenditures have been approved in advance in writing in accordance with applicable
Laws. This Contract shall terminate without penalty (I) at the end of any fiscal year in the event that funds are
not appropriated for the following fiscal year, or (ii) at any time within a fiscal year in the event that funds are
only appropriated for a portion of the fiscal year and funds for this Contract are no longer available. This
Section 17 shall control in the event of a conflict with any other prov!sion of this Contract.
Miscellaneous.
Bailee Disclaimer. The parties understand and agree that City does not purport to be Contractor’s
bailee, and City is, therefore, not responsible for any damage to the personal property of Contractor.
Consent. Whenever in this Contract the approval or consent of a party is required, such approval or
consent shall be in writing and shall be executed by a person having the express authority to grant
such approval or consent.
Controlling Law. The parties agree that this Contract shall be governed and construed by and in
accordance with the Laws of the State of California.
Definitions. The definitions and terms set forth in Section 1 of the Standard Draw ngs and
Specifications (1992) of this Contract are incorporated herein by reference.
Force Majeure. Neither party shall be deemed to be in default on account of any delay or failure to
perform its obligations under this Contract which directly results from an Act of God or an act of a
superior governmental authority.
CITY OF PALO ALTO C2143754 PAGE 4 OF 7
FORMAL CONTRACT SECTION 500
f.Headings. The paragraphheadings are not a part of this Contract and shall have no effect upon the
construction or interpretation of any part of this Contract;
Incorporation of Documents. All documents constituting the Contract documents described in Section
3 hereof and all documents which may, from time to time, be referred to in any duly executed
amendment hereto are by such reference incorporated in this Contract and shall be deemed to be part
of this Contract.
ho Integration. This Contract and any amendments hereto between the parties constitute the entire
agreement between the parties conceming the Project and Work, and there are no other prior oral or
.wdtten agreements between the parties that are not incorporated in this Contract.
Modification of Agreement. This Contract shall not be modified or be binding upon the parties, unless
such modification, is agreed to in wdting and signed by the parties.
jo Provision. Any agreement, covenant, condition, clause, qualification, restriction,.reservation, term or
other stipulation in the Contract shall define or otherwise control, establish, or limit the performance
required or permitted or to be required of or permitted by either party. All provisions, whether
covenants or conditions, shall be deemed to be both covenants and conditions.
Resolution. Contractor shall submit with its Bid a copy of any corporate or partnership resolution or
other writing, which authorizes any director, officer or other employee or partner to act for or in behalf
of Contractor or which authorizes Contractor to enter into this Contract.
Severability. If a court of competent jurisdiction finds or rules that any provision 0fthis Contract is void
or unenfomeable, the provisions of this Contract not so affected shall remain in full fome and effect.
mo Status of Contractor. In the exercise of dghts and obligations under this Contract, Contractor acts as
an Independent contractor and not as an agent or employee of City. Contractor shall not be entitled to
any rights and benefits accorded or accruing to the City Council members, officers or employees of
City, and Contractor expressly waives any and all claims to such rights and benefits.
Successors and Assigns. The provisions of this Contract shall inure to the benefit of, and shall apply
to and bind, the successors and assigns of the parties.
Time of the Essence. Time is of the essence of this Contract and each of its provisions. In the
calculation of time hereunder, the time in which an act is to be performed shall be computed by
excluding the first Day and including the last. If the time in which an act is to be performed falls on a
Saturday, Sunday, or any Day observed as a legal holiday by City, the time for performance shall be
extended to the following Business Day..
Altemative Dispute Resolution. The parties shall endeavor to resolve any disputes or claims arising
out of or relating to this Contract by mediation, which, unless the parties agree otherwise, shall be
conducted under the auspices of the Judicial Arbitration and Mediation Service (JAMS), San Jose,
California. The intent of the parties is that the mediation shall proceed in advance of litigation;
however, if any party should commence litigation before the conclusion of mediation, such litigation,
including discovery, shall be stayed pending completion of mediation, and by executing this Contract
the parties stipulate to mediation in accordance with Santa Clara County
Superior Court Local Rule 1.15 or Rule 2-3(b) of the ADR Local Rules of the U.S. District Court for the
Northem District of California, as such rules may be amended from time to time. The parties shall
share the cost of the mediation, including the mediator’s fee, equally. Any written agreement reacl’~ed
in mediation shall be enforceable pursuant to California Code of Civil Procedure § 664.6, as amended.
Venue. Unless the parties mutually agree otherwise, mediation shall take place in San Jose,
California. In the event that litigation is commenced by any party hereunder, the parties agree that
such action shall be vested exclusively in the state courts of California in the County of Santa Clara or
in the United States District Court for the Northern District of California.
r.’ Recovery of Costs. Each Party shall bear its own costs,-including attorney’s fees, through the
CITY OF PALO ALTO C2143754 PAGE 5 OF 7
FORMAL CONTRACT SECTION 500
completion of mediation. If the claim or dispute is not resolved through mediation, orif litigation is
necessary to enforce a settlement reached at mediation pursuant to Califomia Code of Civil Procedure
§ 664.6, as amended, then the prevailing party in any subsequent litigation may recover its reasonable
costs, including attomey’s fees, incurred subsequent to conclusion of the mediation.
So Flow-down. Contractor agrees to include provisions of this Contract relating to Alternative Dispute
Resolution, Venue. and Recovery of Costs in any subcontracts or major matedal purchase
agreements which it enters into in connection with this Contract, and to require its subcontractors to
include those provisions in any sub-contracts or major matedal purchase agreements, such that any
mediation or litigation of any claim or dispute asserted by a subcontractor or major material supplier
will be consolidated with any related claim or dispute between the Contractor and the City. Should the
Contractor fail to do so, such that the City is required to defend an action brought by a subcontractor
or material supplier inconsistent.with the Alternative Dispute and Venue provisions of this Contract,
Contractor shall indemnity City for City’s costs of defense, including reasonable attorney’s fees. ’
IN WITNESS WHEREOF, the parties have by their duly.appointed representatives executedthis Contract in the city of
Palo Alto, County of Santa Clare, State of California on the date first stated above.
AI-rEST:
City Clerk
APPROVED AS TO FORM:
CITY OF PALO ALTO
By:
Its Mayor
Senior Assistant City Attomey
APPROVED:CONTRACTOR:
Assistant City Manager
Director of Utilities
By:
Name:
Title:
Director of Administrative Services
Contract Manager (Insurance Review)
By:
Name:
Title:
(Compliance with California Corporations Code ~ 313 is required
if the entity on whose behalf this contract is signed is a
corporation. In the alternative, a certified corporate resolution
attesting to the signatory authority of the individuals signing in
their respective capacities is acceptable.)
CITY OF PALO ALTO C2143754 PAGE 6 OF 7
FORMAL CONTRACT
CERTIFICATE OF ACKNOWLEDGMENT
SECTION 500
(Civil Code ~ 1189)
STATE OF
COUNTY OF
On , before me, , a
notary public in and for said County, personally appeared
personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose
name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the
same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the
person(s), or the entity upon behalf of which the person(s) acted, executed the instrument,
WITNESS my hand and official seal.
Signature (Seal)
CITY OF PALO ALTO C2143754 PAGE 7 OF 7
FORMAL CONTRACT SECTION 500
CERTIFICATE OF ACKNOWLEDGMENT
(Civil Code ~ 1189)
STATE OF
COUNTY OF
On , before me, , a
notary public in and for said County, personally appeared
personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose
name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the
same in hislherltheir authorized capacity(ies), and that by hislherltheir signature(s) on the instrument the
person(s), or the entity upon behalf of which the person(s) acted, executed the instrument,
WITNESS my hand and official seal.
Signature (Seal)
CITY OF PALO ALTO C2143754 PAGE 7 OF 7
PART II- PERFORMANCE BOND SECTION 610
Contractor’s Performance Bond
WHEREAS, the City Council of the City of Palo Alto, State of Califomia (=City") and St. Francis Electric, (=Principal")
have entered into an agreement dated July 15, 2002, and identified as Downtown Streets and Roadway
Improvements Proiect, which is hereby referred to and made a part here of whereby Principal agrees to install and
complete certain designated public improvements; and
WHEREAS, Principal is required under the terms of said agreement to furnish a bond for the faithful performance of
said agreement.
NOW, THEREFORE, Principal and , as Surety, incorporated under the laws of
the State of STATE, and duly authorized to transact business as an admitted surety, under the Laws of the State of
Califomia, are held and firmly bound unto City in the penal sum of Two Hundred Sixty Nine Thousand Nine Hundred
Fifteen dollars ($269,915.00), for the payment whereof Principal and Surety bind themselves, their heirs, executors,
administrators, success.ors, and assigns, jointly and severally, firmly by these presents.
The condition of this obligation is such that if the Principal, Principal’s heirs, executors, administrators, successors, or
assigns shall promptly and faithfully keep and perform the covenants, conditions, and provisions of the above-
mentioned agreement and any alteration thereof, with or without notice to the Surety, and if Principal shall satisfy all
claims and demands incurred under such agreement and shall fully protect, indemnify, defend, and hold harmless
City, its officers, agents, and employees from all claims, demands, or liabilities which may arise by reason of
Principal’s failure to do so, and shall reimburse and repay City all outlay and expenses which City may incur in
making good any default, then this obligation shall be null and void; otherwise, it shall remain in full force and effect.
As part of the obligations secured hereto, and in addition to the face amount specified therefor, there shall be
included costs and reasonable expenses and fees, including reasonable aftomey’s fees incurred by City in
successfully enforcing such obligations, all to be taxed as costs and included in any judgment rendered. Surety shall
be liable for any liquidated damages for which the Principal may be liable under its agreement with the City, and such
liquidated damages shall be part of the obligations secured hereto, and in addition to the face amount specified
therefor.
The Surety hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the
agreement or to the work to be performed thereunder or the specifications accompanying the same, shall in any way
affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration,
or addition to the terms of the agreement or to the work or to the specifications.
IN WITNESS WHEREOF, this instrument has been duly executed by the Surety named on ,2002.
SURETY,
PHONE NUMBER:
BY:
Its:
.(Type Company Name)
CERTIFICATE OF ACKNOWLEDGMENT
(Civil Code § 1189)
STATE OF .)
COUNTY OF .)
On , before me,, a notary public in and for said
County personally appeared ,personally
known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose name(s) is/are
subscribed to the within instrument and acknowledged to me that helshelthey executed the same in his/her/their
authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon
behalf of which the person(s) acted, executed the instrument.
WITNESS my hand and official seal..
Signature (Seal)
CITY OF PALO ALTO C2143754 PAGE 1 OF 1
PART II - PAYMENT (LABOR & MATERIALS) BOND SECTION 620
Contractor’s Payment (Labor and Materials) BondWHEREAS, the City Council of the City of Palo Alto State of California ("City") and St. Francis Electric,
("Principal’), have entered into an agreement dated July 15, 2002 , and identified as Downtown Street and
Roadway Li.qhtin.q Improvements Project, which is hereby referred to and made a part here of, whereby Principal
agrees to install and complete certain designated public improvements; and
WHEREAS, under the terms of said agreement, Principal is required before entedng Upon the performance of the
work to file a good and sufficient payment bond with the City of Palo Alto to secure the claims to which reference is
made in Title 15 (commencing with Section 3082) of Park 4 of Division 3 of the Civil Code of the State of California.
NOW, THEREFORE, Principal and , as Surety, incorporated under the laws ofthe State of , and duly authorized to transact business as an admitted surety, under the
La.ws of the State of Califomia, are held and firmly bound unto City in the penal sum of Two Hundred Sixty Nine
Thousand Nine Hundred Fifteen Dollars ($269,915.00), for the payment whereof Principal and Surety bind
themselves, their heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these
presents.
The condition of this obligation is such that if Principal, Principal’s subcontractors, heirs, executors, administrators,
successors, or assigns shall fail to pay any of the persons, companies, or corporations, referred to in Section 3181 of
the California Civil Code, as amended, with respect to any work of labor performed or materials supplied.by any such
persons, companies, or corporations, which work, labor, or materials are covered by the above-mentioned agreement
and any amendments, changes, change order, additions, alterations,~ or modifications thereof, or any amounts due
under the Califomia Unemployment Insurance Code with respect to such work or labor, or for any amounts raquirad
to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees
of the contractor and his subcontractors pursuant to Section 13020 of the Unemployment Insurance Code, as
amended, with respect to such work and labor, the Surety will pay for the same, in an amount not exceeding the sum
herein above specified, and also, in case suit is brought upon this bond, the Surety will pay a reasonable attomey’s
fee to be fixed in court.
It.is hereby expressly stipulated and agreed that this bond shall inure to the benefit of any and all persons,
companies, and corporations entitled named in Section 3181 of the California Civil Code, as amended, so as to give
a right of action to them or their assigns in any suit brought upon this bond.
The Surety hereby stipulates and agrees that no amendment, change, order, addition, alteration, or modification to
the terms of the agreement of to the work to be performed thereunder or the specifications accompanying the same,
shall in any way affect its obligations on this bond, and it does hereby waive notice of any such amendment, change,
change order, addition, alteration, or modification to the terms of the agreement or to the work performed thereunder
or to the specifications accompanying the same.
IN WITNESS WHEREOF, this instrument has been duly executed by the Surety named on ,2002.
SURETY,
PHONE NUMBER:
BY:
Its:
(Type Company Name)
CERTIFICATE OF ACKNOWLEDGMENT
(Civil Code § 1189)STATE OF )
COUNTY OF )
On , before me,, a notary public in and for saidCounty, personally appeared ,personallyknown to me (or proved to me on the basis of satisfaCtory evidence) to be the person(s)whose, name(s) is/are
subscribed to the within instrument and acknowledged to me that he/she/they executed the same in hislherltheir
authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon
behalf of which the person(s) acted, executed the instrument.
WITNESS my hand and official seal.
Signature (Seal)
CITY OF PALO ALTO C2143754 PAGE 1 OF 1