City of Palo Alto (ID # 6983)
City Council Staff Report
Report Type: Consent Calendar Meeting Date: 6/27/2016
City of Palo Alto Page 1
Summary Title: Lucie Stern Buildings Mechanical and Electrical Upgrades
Title: Approval of a Construction Contract for the Lucie Stern Buildings
Mechanical and Electrical Upgrades, Capital Improvements Program Project
PE-14015, With Iron Construction, Inc. in the Amount of $2,239,781 and
Approval of Amendment Number 2 to Contract Number C13148737 With
Advance Design Consultants Inc. in the Amount of $349,512 for a Not-to-
Exceed Amount of $670,267 for Construction Phase Services
From: City Manager
Lead Department: Public Works
Recommendation
Staff recommends that Council:
1. Approve and authorize the City Manager or his designee to execute the
attached contract with Iron Construction, Inc. in the amount of $2,239,781
(Attachment A) for the Lucie Stern Mechanical and Electrical Upgrades
Capital Improvement Program project PE-14015;
2. Authorize the City Manager or his designee to negotiate and execute one or
more change orders to the contract with Iron Construction, Inc. for related,
additional but unforeseen work which may develop during the project, the
total value of which shall not exceed a ten percent contingency of
$223,978; and
3. Approve and authorize the City Manager or his designee to execute the
attached Amendment Number 2 to Contract C13148737 with Advanced
Design Consultants, Inc. (Attachment B) in the amount of $349,512 and a
total contract amount not-to-exceed $670,267 for construction phase
services for the Lucie Stern Mechanical and Electrical Upgrades Capital
City of Palo Alto Page 2
Improvement Program project PE-14015.
Background
The Lucie Stern Center was constructed in 1936 and consists of four buildings
located at 1305 Middlefield Road. In the past 80 years the Lucie Stern Community
Center, Children’s Theatre, Community Theatre, and Children’s Library have been
through successive remodeling.
Following an expansion to the Children’s Library, the width of the fire access lane
behind the Children’s Theatre was reduced, limiting emergency vehicle access. To
mitigate, the City of Palo Alto Fire Department requested an upgrade of the
existing fire/life safety (wet sprinkler and fire alarm) system in the Children’s
Theatre. Additionally, other mechanical and electrical systems in the Children’s
Theatre are nearing the end of their useful lives. Similar deficiencies were found
in the Community Theatre and Community Center. To address these issues, the
Lucie Stern Mechanical and Electrical Upgrades Capital Improvement Program
project PE-14015 was created and a design consultant hired to study the
buildings’ mechanical, electrical, and fire/life safety components and create plans
to upgrade the buildings.
Discussion
Scope Overview
The primary scope of this project is to construct a complete fire/life safety system
to meet current National Fire Protection Association codes and Palo Alto Fire
Department regulations in the Children’s Theatre, Community Theatre, and
Community Center. Coinciding project goals include mechanical and electrical
design proficiency, energy savings, code compliance, and aesthetics.
Project scope specific to each of the three buildings includes a properly anchored,
code-compliant staircase leading to the outdoor stage balcony to be constructed
in the Children’s Theatre; the electrical systems in the Community Theatre are to
be upgraded and/or replaced, including additional receptacles where needed; and
the mechanical systems in the Community Center are to be upgraded and/or
replaced, including the addition of air-conditioning.
The buildings will remain occupied during the course of the project, however
there may be some temporary relocation of department staff to accommodate
City of Palo Alto Page 3
construction. Work will be scheduled to keep systems operational during working
hours and minimize the impacts of construction on staff and the public. In the
Timeline section, the designated shutdown periods to accommodate overhead
work and the replacement of electrical switchgear are listed for each building .
Bid Process
On March 30, 2016, a notice inviting formal bids (IFB) for the Lucie Stern Buildings
Mechanical and Electrical Upgrades project was posted to PlanetBids through the
City’s web portal and sent to 223 contractors. The bidding period was 27 days. No
bids were received from a qualified contractor on the April 26, 2016 due date.
Summary of Bid Process
Bid Name/Number
Lucie Stern Buildings Mechanical and Electrical
Upgrades Project – IFB 163446
Proposed Length of Project 388 calendar days
Number of vendors notified
through PlanetBids 230
Number of Builder’s Exchanges
notified through PlanetBids 7
Total Days to Respond to Bid 27
Pre-Bid Meeting April 7, 2016
Attendees at Mandatory Pre-
Bid Meeting
9 firms attended: 4 General Contractors and 5
Subcontractors
Number of Bids Received: 0
Base Bid Price Range N/A
Staff inquired as to why contractors did not submit bids and received feedback
similar to past projects, where smaller firms indicated that bonds for projects over
$1.5 million are difficult to obtain and larger firms felt the projects were too small
and difficult. Other responses indicated that in the current construction
environment, private sector work is plentiful with public works projects
considered too risky in comparison. This project in particular, is more difficult as
it involves working on historical buildings with key milestone dates that must be
met or the contractor will incur substantial liquidated damages.
City of Palo Alto Page 4
In situations where no bids are received during a formal bidding solicitation, the
Palo Alto Municipal Code Section 2.30.360 provides for an exemption from
competitive solicitation requirements:
“(c) Where competitive bids or requests for proposals have been solicited
and no bid or proposal has been received or no bid or proposal meeting the
requirements of the invitation to bid or request for proposal has been
received, provided that, in the case of a public works project, the project is
not otherwise required by the Charter to be formally bid.”
Following the formal bid process, staff solicited a bid from one general contractor
that showed an earnest effort during the formal bid process. The contractor had
been preparing a formal bid to submit, but on the final due date one of their
primary subcontractors withdrew from the process. Upon learning of this reason,
staff requested they continue to prepare and submit a quote for the work.
The sole quote received, $4,188,101, was above the budgeted allotment of
$2,895,405 appropriated for this combined project. Staff believes that the busy
local construction industry has resulted in higher prices and the higher quote is
still reasonable for the complex nature of this project (i.e. historical buildings,
tight construction schedule, and milestone liquidated damages). The construction
industry is booming in the bay area and local general contractors have been
unable to keep up. Many out of state general contractors are coming to the bay
area to bid on projects such as the Apple campus. Another contributing factor
comes from Senate Bill (SB) 7 and SB 854, which now require bids for Charter
Cities to include prevailing wages. Prevailing wages were not factored into the
original project budget. Additionally, the fire/life safety upgrades were designed
to include the Community Theatre and the Community Center.
In attempting to remain within the project’s budgeted allotment, bid components
were reviewed and prioritized for inclusion into the construction contract. The
following items are included:
1) The fire/life safety upgrade for the Children’s Theatre, Community
Theatre, and Community Center;
City of Palo Alto Page 5
2) Replacement of the out-of-compliance wooden staircase in the
Children’s Theatre used by young actors to access the balcony during
performances;
3) Replacement of the outdated electrical components at the Community
Theatre;
4) Replacement and upgrading of the current out-of-compliance
Community Theatre Company Switch (integrates the equipment
provided by companies leasing the theatre);
5) Replacement and updating of the mechanical system at the Community
Center with the inclusion of air-conditioning; and
6) Upgrading the fireplaces in the Lucie Stern Ballroom from wood burning
to gas inserts.
The electrical and mechanical upgrade components to the Children’s Theatre
have been removed from the scope of the current recommended construction
contract in an attempt to stay within the current budget. These components will
be brought forth in a future CIP when funding is available.
Staff reviewed the quote submitted and recommends that Iron Construction be
awarded a construction contract. Staff recommends that the City award the
modified Base Bid ($2,232,806) plus Add Alternate 1 ($6,975) for a total contract
award amount of $2,239,781.
A contingency amount of $223,978 equal to 10 percent of the total contract is
requested for unforeseen conditions, which may be discovered during
construction. With renovation of an existing facility, there is a high likelihood of
additional required repairs or system replacement triggered by the base
construction. In addition, due to the time constraints placed upon the contractor
to complete their work during off hours, staff expects that any needed change
orders will be billed at a premium rate for night or weekend work.
Staff confirmed with the Contractor’s State License Board the contractor has an
active license on file. Staff checked references supplied by the contractor for
previous work performed and found their projects were similar to this project and
were completed to the satisfaction of the owners.
Advanced Design Consultants, Inc. (ADC) Contract – Construction Phase Services
City of Palo Alto Page 6
The contract amendment with the design consultant, ADC (Attachment B) will
provide for the consultant’s construction phase services consisting of: general
construction administration, construction management, testing, photographic
records, and systems commissioning during the project work. As the designer of
record, ADC will respond to design questions and issues raised by the contractor,
attend meetings at the job site, make construction observations, review material
submittals, review project schedules, review change order requests, answer
requests for information (RFIs), review payment applications, and assist in the
preparation of the record documents at the completion of construction.
The original request for proposal (RFP) and contract scope with ADC indicated
that an amendment for construction phase services would be negotiated if and
when the project proceeded to actual construction. Staff recommends that
Council approve the attached contract amendment with ADC to provide the
resources necessary to successfully manage the construction.
Timeline
The construction of the upgrades to the Lucie Stern buildings are to be completed
in 388 days. The project is broken down including milestones that need to be met
in order to complete the required work while occupancy is blocked out. These
milestones are critical due to the temporary relocation of department staff and
cancellation of theatre and ballroom venues. The timeframes for closure of the
facilities have been coordinated with the user groups, and the construction
contract includes liquidated damages specific to each of the three buildings to
ensure the contractor completes the work with minimal impact to users.
The timing for the key project phases when full or partial facility closures will
occur are as follows:
1. Children’s Theatre- August 9, 2016 thru October 9, 2016. Liquidated
damages will be assessed at $1658/day.
2. Community Theatre- August 22, 2016 thru September 2, 2016.
Liquidated damages will be assessed at $742/day.
3. Community Center- January 1, 2017 thru March 15, 2017. Liquidated
damages will be assessed at $1992/day.
Resource Impact
Funding for this project as modified has been allocated in Lucie Stern Buildings
City of Palo Alto Page 7
Mechanical and Electrical Upgrades Capital Improvement Program project PE-
14015. Staff anticipates a new CIP or a request for additional funding for PE-
14015 will be proposed in the next budget cycle to cover the deferred mechanical
and electrical upgrades to the Children’s Theatre building.
Policy Implications
This recommendation does not represent any change to existing City policies.
Environmental Review
This project is categorically exempt from California Environmental Quality Act
(CEQA) under Sections 15301 and 15302 of the CEQA guidelines as an alteration
to an existing facility and no further environmental review is necessary.
Attachments:
A- Iron Construction Contract C16163446 (PDF)
B - ADC Contract Amendment No. 2 (PDF)
Invitation for Bid (IFB) Package 1 Rev. April 27, 2016
CONSTRUCTION CONTRACT
CONSTRUCTION CONTRACT
Contract No. C16163446
City of Palo Alto
Lucie Stern Buildings Mechanical and Electrical Upgrades
Project
Invitation for Bid (IFB) Package 2 Rev. April 27, 2016
CONSTRUCTION CONTRACT
CONSTRUCTION CONTRACT
TABLE OF CONTENTS
SECTION 1 INCORPORATION OF RECITALS AND DEFINITIONS…………………………………….…………..6
1.1 Recitals…………………………………………………………………………………………………………………….6
1.2 Definitions……………………………………………………………………………………………………………….6
SECTION 2 THE PROJECT………………………………………………………………………………………………………...6
SECTION 3 THE CONTRACT DOCUMENTS………………………………………………………………………………..7
3.1 List of Documents…………………………………………………………………………………………….........7
3.2 Order of Precedence……………………………………………………………………………………………......7
SECTION 4 CONTRACTOR’S DUTY…………………………………………………………………………………………..8
4.1 Contractor's Duties…………………………………………………………………………………………………..8
SECTION 5 PROJECT TEAM……………………………………………………………………………………………………..8
5.1 Contractor's Co-operation………………………………………………………………………………………..8
SECTION 6 TIME OF COMPLETION…………………………………………………………………………………….......8
6.1 Time Is of Essence…………………………………………………………………………………………………….8
6.2 Commencement of Work…………………………………………………………………………………………8
6.3 Contract Time…………………………………………………………………………………………………………..8
6.4 Liquidated Damages…………………………………………………………………………………………………8
6.4.1 Other Remedies……………………………………………………………………………………………………..9
6.5 Adjustments to Contract Time………………………………………………………………………………….9
SECTION 7 COMPENSATION TO CONTRACTOR……………………………………………………………………….9
7.1 Contract Sum……………………………………………………………………………………………………………9
7.2 Full Compensation……………………………………………………………………………………………………9
SECTION 8 STANDARD OF CARE……………………………………………………………………………………………..9
8.1 Standard of Care…………………………………………………………………………………..…………………9
SECTION 9 INDEMNIFICATION…………………………………………………………………………………………..…10
9.1 Hold Harmless……………………………………………………………………………………………………….10
9.2 Survival…………………………………………………………………………………………………………………10
SECTION 10 NON-DISCRIMINATION……..………………………………………………………………………………10
10.1 Municipal Code Requirement…………….………………………………..……………………………….10
SECTION 11 INSURANCE AND BONDS.…………………………………………………………………………………10
Invitation for Bid (IFB) Package 3 Rev. April 27, 2016
CONSTRUCTION CONTRACT
11.1 Evidence of Coverage…………………………………………………………………………………………..10
SECTION 12 PROHIBITION AGAINST TRANSFERS…………………………………………………………….…11
12.1 Assignment………………………………………………………………………………………………………….11
12.2 Assignment by Law.………………………………………………………………………………………………11
SECTION 13 NOTICES …………………………………………………………………………………………………………….11
13.1 Method of Notice …………………………………………………………………………………………………11
13.2 Notice Recipents ………………………………………………………………………………………………….11
13.3 Change of Address……………………………………………………………………………………………….12
SECTION 14 DEFAULT…………………………………………………………………………………………………………...12
14.1 Notice of Default………………………………………………………………………………………………….12
14.2 Opportunity to Cure Default…………………………………………………………………………………12
SECTION 15 CITY'S RIGHTS AND REMEDIES…………………………………………………………………………..13
15.1 Remedies Upon Default……………………………………………………………………………………….13
15.1.1 Delete Certain Services…………………………………………………………………………………….13
15.1.2 Perform and Withhold……………………………………………………………………………………..13
15.1.3 Suspend The Construction Contract…………………………………………………………………13
15.1.4 Terminate the Construction Contract for Default………………………………………………13
15.1.5 Invoke the Performance Bond………………………………………………………………………….13
15.1.6 Additional Provisions……………………………………………………………………………………….13
15.2 Delays by Sureties……………………………………………………………………………………………….13
15.3 Damages to City…………………………………………………………………………………………………..14
15.3.1 For Contractor's Default…………………………………………………………………………………..14
15.3.2 Compensation for Losses…………………………………………………………………………………14
15.4 Suspension by City……………………………………………………………………………………………….14
15.4.1 Suspension for Convenience……………………………………………………………………………..14
15.4.2 Suspension for Cause………………………………………………………………………………………..14
15.5 Termination Without Cause…………………………………………………………………………………14
15.5.1 Compensation………………………………………………………………………………………………….15
15.5.2 Subcontractors………………………………………………………………………………………………..15
15.6 Contractor’s Duties Upon Termination………………………………………………………………...15
SECTION 16 CONTRACTOR'S RIGHTS AND REMEDIES……………………………………………………………16
16.1 Contractor’s Remedies……………………………………..………………………………..………………….16
Invitation for Bid (IFB) Package 4 Rev. April 27, 2016
CONSTRUCTION CONTRACT
16.1.1 For Work Stoppage……………………………………………………………………………………………16
16.1.2 For City's Non-Payment…………………………………………………………………………………….16
16.2 Damages to Contractor………………………………………………………………………………………..16
SECTION 17 ACCOUNTING RECORDS………………………………………………………………………………….…16
17.1 Financial Management and City Access………………………………………………………………..16
17.2 Compliance with City Requests…………………………………………………………………………….17
SECTION 18 INDEPENDENT PARTIES……………………………………………………………………………………..17
18.1 Status of Parties……………………………………………………………………………………………………17
SECTION 19 NUISANCE……………………………………………………………………………………………………….…17
19.1 Nuisance Prohibited……………………………………………………………………………………………..17
SECTION 20 PERMITS AND LICENSES…………………………………………………………………………………….17
20.1 Payment of Fees…………………………………………………………………………………………………..17
SECTION 21 WAIVER…………………………………………………………………………………………………………….17
21.1 Waiver………………………………………………………………………………………………………………….17
SECTION 22 GOVERNING LAW AND VENUE; COMPLIANCE WITH LAWS……………………………….18
22.1 Governing Law…………………………………………………………………………………………………….18
22.2 Compliance with Laws…………………………………………………………………………………………18
22.2.1 Palo Alto Minimum Wage Ordinance…………….………………………………………………….18
SECTION 23 COMPLETE AGREEMENT……………………………………………………………………………………18
23.1 Integration………………………………………………………………………………………………………….18
SECTION 24 SURVIVAL OF CONTRACT…………………………………………………………………………………..18
24.1 Survival of Provisions……………………………………………………………………………………………18
SECTION 25 PREVAILING WAGES………………………………………………………………………………………….18
SECTION 26 NON-APPROPRIATION……………………………………………………………………………………….19
26.1 Appropriation………………………………………………………………………………………………………19
SECTION 27 AUTHORITY……………………………………………………………………………………………………….19
27.1 Representation of Parties…………………………………………………………………………………….19
SECTION 28 COUNTERPARTS………………………………………………………………………………………………..19
28.1 Multiple Counterparts………………………………………………………………………………………….19
SECTION 29 SEVERABILITY……………………………………………………………………………………………………19
29.1 Severability………………………………………………………………………………………………………….19
SECTION 30 STATUTORY AND REGULATORY REFERENCES …………………………………………………..19
Invitation for Bid (IFB) Package 5 Rev. April 27, 2016
CONSTRUCTION CONTRACT
30.1 Amendments of Laws…………………………………………………………………………………………..19
SECTION 31 WORKERS’ COMPENSATION CERTIFICATION………………………………………………….….19
31.1 Workers Compensation…………………………………………………………………………………….19
SECTION 32 DIR REGISTRATION AND OTHER SB 854 REQUIREMENTS………………………………..…20
32.1 General Notice to Contractor…………………………………………………………………………….20
32.2 Labor Code section 1771.1(a)…………………………………………………………………………….20
32.3 DIR Registration Required…………………………………………………………………………………20
32.4 Posting of Job Site Notices…………………………………………………………………………………20
32.5 Payroll Records…………………………………………………………………………………………………20
Invitation for Bid (IFB) Package 6 Rev. April 27, 2016
CONSTRUCTION CONTRACT
CONSTRUCTION CONTRACT
THIS CONSTRUCTION CONTRACT entered into on June 27, 2016 (“Execution Date”) by and between the
CITY OF PALO ALTO, a California chartered municipal corporation ("City"), and IRON CONSTRUCTION, INC.
("Contractor"), is made with reference to the following:
R E C I T A L S:
A. City is a municipal corporation duly organized and validly existing under the laws of the State of
California with the power to carry on its business as it is now being conducted under the statutes of the
State of California and the Charter of City.
B. Contractor is a Corporation duly organized and in good standing in the State of California,
Contractor’s License Number 806231 and Department of Industrial Relations Registration Number
1000037617. Contractor represents that it is duly licensed by the State of California and has the
background, knowledge, experience and expertise to perform the obligations set forth in this Construction
Contract.
C. On April 26, 2016, City issued an Invitation for Bids (IFB163446) to contractors for the Lucie Stern
Buildings Mechanical and Electrical Upgrades (“Project”). The City did not receive any Bids in response to
the IFB, Per PAMC 2.30.360(C) the City requested a Bid from one Contractor and the Contractor submitted
a Bid.
D. City and Contractor desire to enter into this Construction Contract for the Project, and other
services as identified in the Contract Documents for the Project upon the following terms and conditions.
NOW THEREFORE, in consideration of the mutual promises and undertakings hereinafter set forth
and for other good and valuable consideration, the receipt and sufficiency of which are hereby
acknowledged, it is mutually agreed by and between the undersigned parties as follows:
SECTION 1 INCORPORATION OF RECITALS AND DEFINITIONS.
1.1 Recitals.
All of the recitals are incorporated herein by reference.
1.2 Definitions.
Capitalized terms shall have the meanings set forth in this Construction Contract and/or in the General
Conditions. If there is a conflict between the definitions in this Construction Contract and in the General
Conditions, the definitions in this Construction Contract shall prevail.
SECTION 2 THE PROJECT.
The Project is the Lucie Stern Buildings Mechanical and Electrical Upgrades Project, located at 1305
Middlefield Road, Palo Alto, CA. 94301 ("Project").
Invitation for Bid (IFB) Package 7 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 3 THE CONTRACT DOCUMENTS.
3.1 List of Documents.
The Contract Documents (sometimes collectively referred to as “Agreement” or “Bid Documents”) consist
of the following documents which are on file with the Purchasing Division and are hereby incorporated by
reference.
1) Change Orders
2) Field Orders
3) Contract
4) Bidding Addenda
5) Special Provisions
6) General Conditions
7) Project Plans and Drawings
8) Technical Specifications
9) Instructions to Bidders
10) Invitation for Bids
11) Contractor's Bid/Non-Collusion Declaration
12) Reports listed in the Contract Documents
13) Public Works Department’s Standard Drawings and Specifications (most current version at
time of Bid)
14) Utilities Department’s Water, Gas, Wastewater, Electric Utilities Standards (most current
version at time of Bid)
15) City of Palo Alto Traffic Control Requirements
16) City of Palo Alto Truck Route Map and Regulations
17) Notice Inviting Pre-Qualification Statements, Pre-Qualification Statement, and Pre-
Qualification Checklist (if applicable)
18) Performance and Payment Bonds
3.2 Order of Precedence.
For the purposes of construing, interpreting and resolving inconsistencies between and among the
provisions of this Contract, the Contract Documents shall have the order of precedence as set forth in the
preceding section. If a claimed inconsistency cannot be resolved through the order of precedence, the City
shall have the sole power to decide which document or provision shall govern as may be in the best
interests of the City.
Invitation for Bid (IFB) Package 8 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 4 CONTRACTOR’S DUTY.
4.1 Contractor’s Duties
Contractor agrees to perform all of the Work required for the Project, as specified in the Contract
Documents, all of which are fully incorporated herein. Contractor shall provide, furnish, and supply all
things necessary and incidental for the timely performance and completion of the Work, including, but not
limited to, provision of all necessary labor, materials, equipment, transportation, and utilities, unless
otherwise specified in the Contract Documents. Contractor also agrees to use its best efforts to complete
the Work in a professional and expeditious manner and to meet or exceed the performance standards
required by the Contract Documents.
SECTION 5 PROJECT TEAM.
5.1 Contractor’s Co-operation.
In addition to Contractor, City has retained, or may retain, consultants and contractors to provide
professional and technical consultation for the design and construction of the Project. The Contract
requires that Contractor operate efficiently, effectively and cooperatively with City as well as all other
members of the Project Team and other contractors retained by City to construct other portions of the
Project.
SECTION 6 TIME OF COMPLETION.
6.1 Time Is of Essence.
Time is of the essence with respect to all time limits set forth in the Contract Documents.
6.2 Commencement of Work.
Contractor shall commence the Work on the date specified in City’s Notice to Proceed.
6.3 Contract Time.
Work hereunder shall begin on the date specified on the City’s Notice to Proceed and shall be completed
not later than .
within Three hundred eighty eight calendar days (388) after the commencement date
specified in City’s Notice to Proceed.
By executing this Construction Contract, Contractor expressly waives any claim for delayed early
completion.
6.4 Liquidated Damages.
Pursuant to Government Code Section 53069.85, if Contractor fails to achieve Substantial Completion of
the entire Work within the Contract Time, including any approved extensions thereto, City may assess
liquidated damages on a daily basis for each day of Unexcused Delay in achieving Substantial Completion,
based on the amount of Five Hundred dollars ($500) per day, or as otherwise specified in the Special
Provisions. Liquidated damages may also be separately assessed for failure to meet milestones specified
elsewhere in the Contract Documents, regardless of impact on the time for achieving Substantial
Completion. The assessment of liquidated damages is not a penalty but considered to be a reasonable
Invitation for Bid (IFB) Package 9 Rev. April 27, 2016
CONSTRUCTION CONTRACT
estimate of the amount of damages City will suffer by delay in completion of the Work. The City is entitled
to setoff the amount of liquidated damages assessed against any payments otherwise due to Contractor,
including, but not limited to, setoff against release of retention. If the total amount of liquidated damages
assessed exceeds the amount of unreleased retention, City is entitled to recover the balance from
Contractor or its sureties. Occupancy or use of the Project in whole or in part prior to Substantial
Completion, shall not operate as a waiver of City’s right to assess liquidated damages.
6.4.1 Other Remedies. City is entitled to any and all available legal and equitable remedies City may
have where City’s Losses are caused by any reason other than Contractor’s failure to achieve Substantial
Completion of the entire Work within the Contract Time.
6.5 Adjustments to Contract Time.
The Contract Time may only be adjusted for time extensions approved by City and memorialized in a
Change Order approved in accordance with the requirements of the Contract Documents.
SECTION 7 COMPENSATION TO CONTRACTOR.
7.1 Contract Sum.
Contractor shall be compensated for satisfactory completion of the Work in compliance with the Contract
Documents the Contract Sum of Two million two hundred thousand thirty nine thousand seven hundred
eighty one Dollars ($2,239,781).
[This amount includes the Base Bid and Add Optional 1.
7.2 Full Compensation.
The Contract Sum shall be full compensation to Contractor for all Work provided by Contractor
and, except as otherwise expressly permitted by the terms of the Contract Documents, shall cover all
Losses arising out of the nature of the Work or from the acts of the elements or any unforeseen difficulties
or obstructions which may arise or be encountered in performance of the Work until its Acceptance by
City, all risks connected with the Work, and any and all expenses incurred due to suspension or
discontinuance of the Work, except as expressly provided herein. The Contract Sum may only be adjusted
for Change Orders approved in accordance with the requirements of the Contract Documents.
SECTION 8 STANDARD OF CARE.
8.1 Standard of Care.
Contractor agrees that the Work shall be performed by qualified, experienced and well-supervised
personnel. All services performed in connection with this Construction Contract shall be performed in a
manner consistent with the standard of care under California law applicable to those who specialize in
providing such services for projects of the type, scope and complexity of the Project.
Invitation for Bid (IFB) Package 10 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 9 INDEMNIFICATION.
9.1 Hold Harmless.
To the fullest extent allowed by law, Contractor will defend, indemnify, and hold harmless City, its City
Council, boards and commissions, officers, agents, employees, representatives and volunteers (hereinafter
individually referred to as an “Indemnitee” and collectively referred to as "Indemnitees"), through legal
counsel acceptable to City, from and against any and liability, loss, damage, claims, expenses (including,
without limitation, attorney fees, expert witness fees, paralegal fees, and fees and costs of litigation or
arbitration) (collectively, “Liability”) of every nature arising out of or in connection with the acts or
omissions of Contractor, its employees, Subcontractors, representatives, or agents, in performing the Work
or its failure to comply with any of its obligations under the Contract, except such Liability caused by the
active negligence, sole negligence, or willful misconduct of an Indemnitee. Contractor shall pay City for any
costs City incurs to enforce this provision. Except as provided in Section 9.2 below, nothing in the Contract
Documents shall be construed to give rise to any implied right of indemnity in favor of Contractor against
City or any other Indemnitee.
Pursuant to Public Contract Code Section 9201, City shall timely notify Contractor upon receipt of
any third-party claim relating to the Contract.
9.2 Survival.
The provisions of Section 9 shall survive the termination of this Construction Contract.
SECTION 10 NON-DISCRIMINATION.
10.1 Municipal Code Requirement.
As set forth in Palo Alto Municipal Code section 2.30.510, Contractor certifies that in the performance of
this Agreement, it shall not discriminate in the employment of any person because of the race, skin color,
gender, age, religion, disability, national origin, ancestry, sexual orientation, housing status, marital status,
familial status, weight or height of such person. Contractor acknowledges that it has read and understands
the provisions of Section 2.30.510 of the Palo Alto Municipal Code relating to Nondiscrimination
Requirements and the penalties for violation thereof, and will comply with all requirements of Section
2.30.510 pertaining to nondiscrimination in employment.
SECTION 11 INSURANCE AND BONDS.
11.1 Evidence of coverage.
Within ten (10) business days following issuance of the Notice of Award, Contractor shall provide City with
evidence that it has obtained insurance and shall submit Performance and Payment Bonds satisfying all
requirements in Article 11 of the General Conditions.
Invitation for Bid (IFB) Package 11 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 12 PROHIBITION AGAINST TRANSFERS.
12.1 Assignment.
City is entering into this Construction Contract in reliance upon the stated experience and qualifications of
the Contractor and its Subcontractors set forth in Contractor’s Bid. Accordingly, Contractor shall not
assign, hypothecate or transfer this Construction Contract or any interest therein directly or indirectly, by
operation of law or otherwise without the prior written consent of City. Any assignment, hypothecation or
transfer without said consent shall be null and void, and shall be deemed a substantial breach of contract
and grounds for default in addition to any other legal or equitable remedy available to the City.
12.2 Assignment by Law.
The sale, assignment, transfer or other disposition of any of the issued and outstanding capital stock of
Contractor or of any general partner or joint venturer or syndicate member of Contractor, if the Contractor
is a partnership or joint venture or syndicate or co-tenancy shall result in changing the control of
Contractor, shall be construed as an assignment of this Construction Contract. Control means more than
fifty percent (50%) of the voting power of the corporation or other entity.
SECTION 13 NOTICES.
13.1 Method of Notice.
All notices, demands, requests or approvals to be given under this Construction Contract shall be given in
writing and shall be deemed served on the earlier of the following:
(i) On the date delivered if delivered personally;
(ii) On the third business day after the deposit thereof in the United States mail, postage prepaid, and
addressed as hereinafter provided;
(iii) On the date sent if sent by facsimile transmission;
(iv) On the date sent if delivered by electronic mail; or
(v) On the date it is accepted or rejected if sent by certified mail.
13.2 Notice to Recipients.
All notices, demands or requests (including, without limitation, Change Order Requests and Claims) from
Contractor to City shall include the Project name and the number of this Construction Contract and shall be
addressed to City at:
To City: City of Palo Alto
City Clerk
250 Hamilton Avenue
P.O. Box 10250
Palo Alto, CA 94303
Copy to: City of Palo Alto
Public Works Administration
250 Hamilton Avenue
Palo Alto, CA 94301
Attn: Matt Raschke
AND
Invitation for Bid (IFB) Package 12 Rev. April 27, 2016
CONSTRUCTION CONTRACT
[Include Construction Manager, If Applicable.]
City of Palo Alto
Utilities Engineering
250 Hamilton Avenue
Palo Alto, CA 94301
Attn:
In addition, copies of all Claims by Contractor under this Construction Contract shall be provided to the
following:
Palo Alto City Attorney’s Office
250 Hamilton Avenue
P.O. Box 10250
Palo Alto, California 94303
All Claims shall be delivered personally or sent by certified mail.
All notices, demands, requests or approvals from City to Contractor shall be addressed to:
IRON CONSTRUCTION, INC
ATTN: Daryl Young
270 E. Caribbean Drive
Sunny Vale, CA 94089
13.3 Change of Address.
In advance of any change of address, Contractor shall notify City of the change of address in writing. Each
party may, by written notice only, add, delete or replace any individuals to whom and addresses to which
notice shall be provided.
SECTION 14 DEFAULT.
14.1 Notice of Default.
In the event that City determines, in its sole discretion, that Contractor has failed or refused to perform any
of the obligations set forth in the Contract Documents, or is in breach of any provision of the Contract
Documents, City may give written notice of default to Contractor in the manner specified for the giving of
notices in the Construction Contract, with a copy to Contractor’s performance bond surety.
14.2 Opportunity to Cure Default.
Except for emergencies, Contractor shall cure any default in performance of its obligations under the
Contract Documents within two (2) Days (or such shorter time as City may reasonably require) after receipt
of written notice. However, if the breach cannot be reasonably cured within such time, Contractor will
commence to cure the breach within two (2) Days (or such shorter time as City may reasonably require)
and will diligently and continuously prosecute such cure to completion within a reasonable time, which
shall in no event be later than ten (10) Days after receipt of such written notice.
Invitation for Bid (IFB) Package 13 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 15 CITY'S RIGHTS AND REMEDIES.
15.1 Remedies Upon Default.
If Contractor fails to cure any default of this Construction Contract within the time period set forth above
in Section 14, then City may pursue any remedies available under law or equity, including, without
limitation, the following:
15.1.1 Delete Certain Services. City may, without terminating the Construction Contract, delete
certain portions of the Work, reserving to itself all rights to Losses related thereto.
15.1.2 Perform and Withhold. City may, without terminating the Construction Contract, engage
others to perform the Work or portion of the Work that has not been adequately performed by
Contractor and withhold the cost thereof to City from future payments to Contractor, reserving to
itself all rights to Losses related thereto.
15.1.3 Suspend The Construction Contract. City may, without terminating the Construction
Contract and reserving to itself all rights to Losses related thereto, suspend all or any portion of
this Construction Contract for as long a period of time as City determines, in its sole discretion,
appropriate, in which event City shall have no obligation to adjust the Contract Sum or Contract
Time, and shall have no liability to Contractor for damages if City directs Contractor to resume
Work.
15.1.4 Terminate the Construction Contract for Default. City shall have the right to terminate
this Construction Contract, in whole or in part, upon the failure of Contractor to promptly cure
any default as required by Section 14. City’s election to terminate the Construction Contract for
default shall be communicated by giving Contractor a written notice of termination in the manner
specified for the giving of notices in the Construction Contract. Any notice of termination given to
Contractor by City shall be effective immediately, unless otherwise provided therein.
15.1.5 Invoke the Performance Bond. City may, with or without terminating the Construction
Contract and reserving to itself all rights to Losses related thereto, exercise its rights under the
Performance Bond.
15.1.6 Additional Provisions. All of City’s rights and remedies under this Construction Contract
are cumulative, and shall be in addition to those rights and remedies available in law or in equity.
Designation in the Contract Documents of certain breaches as material shall not waive the City’s
authority to designate other breaches as material nor limit City’s right to terminate the
Construction Contract, or prevent the City from terminating the Agreement for breaches that are
not material. City’s determination of whether there has been noncompliance with the
Construction Contract so as to warrant exercise by City of its rights and remedies for default under
the Construction Contract, shall be binding on all parties. No termination or action taken by City
after such termination shall prejudice any other rights or remedies of City provided by law or
equity or by the Contract Documents upon such termination; and City may proceed against
Contractor to recover all liquidated damages and Losses suffered by City.
15.2 Delays by Sureties.
Time being of the essence in the performance of the Work, if Contractor’s surety fails to arrange for
completion of the Work in accordance with the Performance Bond, within seven (7) calendar days from the
date of the notice of termination, Contractor’s surety shall be deemed to have waived its right to complete
the Work under the Contract, and City may immediately make arrangements for the completion of the
Work through use of its own forces, by hiring a replacement contractor, or by any other means that City
determines advisable under the circumstances. Contractor and its surety shall be jointly and severally
Invitation for Bid (IFB) Package 14 Rev. April 27, 2016
CONSTRUCTION CONTRACT
liable for any additional cost incurred by City to complete the Work following termination. In addition, City
shall have the right to use any materials, supplies, and equipment belonging to Contractor and located at
the Worksite for the purposes of completing the remaining Work.
15.3 Damages to City.
15.3.1 For Contractor's Default. City will be entitled to recovery of all Losses under law or
equity in the event of Contractor’s default under the Contract Documents.
15.3.2 Compensation for Losses. In the event that City's Losses arise from Contractor’s default
under the Contract Documents, City shall be entitled to deduct the cost of such Losses from
monies otherwise payable to Contractor. If the Losses incurred by City exceed the amount
payable, Contractor shall be liable to City for the difference and shall promptly remit same to City.
15.4 Suspension by City
15.4.1 Suspension for Convenience. City may, at any time and from time to time, without
cause, order Contractor, in writing, to suspend, delay, or interrupt the Work in whole or in part for
such period of time, up to an aggregate of fifty percent (50%) of the Contract Time. The order
shall be specifically identified as a Suspension Order by City. Upon receipt of a Suspension Order,
Contractor shall, at City’s expense, comply with the order and take all reasonable steps to
minimize costs allocable to the Work covered by the Suspension Order. During the Suspension or
extension of the Suspension, if any, City shall either cancel the Suspension Order or, by Change
Order, delete the Work covered by the Suspension Order. If a Suspension Order is canceled or
expires, Contractor shall resume and continue with the Work. A Change Order will be issued to
cover any adjustments of the Contract Sum or the Contract Time necessarily caused by such
suspension. A Suspension Order shall not be the exclusive method for City to stop the Work.
15.4.2 Suspension for Cause. In addition to all other remedies available to City, if Contractor
fails to perform or correct work in accordance with the Contract Documents, City may
immediately order the Work, or any portion thereof, suspended until the cause for the suspension
has been eliminated to City’s satisfaction. Contractor shall not be entitled to an increase in
Contract Time or Contract Price for a suspension occasioned by Contractor’s failure to comply
with the Contract Documents. City’s right to suspend the Work shall not give rise to a duty to
suspend the Work, and City’s failure to suspend the Work shall not constitute a defense to
Contractor’s failure to comply with the requirements of the Contract Documents.
15.5 Termination Without Cause.
City may, at its sole discretion and without cause, terminate this Construction Contract in part or in whole
upon written notice to Contractor. Upon receipt of such notice, Contractor shall, at City’s expense, comply
with the notice and take all reasonable steps to minimize costs to close out and demobilize. The
compensation allowed under this Paragraph 15.5 shall be the Contractor’s sole and exclusive
compensation for such termination and Contractor waives any claim for other compensation or Losses,
including, but not limited to, loss of anticipated profits, loss of revenue, lost opportunity, or other
consequential, direct, indirect or incidental damages of any kind resulting from termination without cause.
Termination pursuant to this provision does not relieve Contractor or its sureties from any of their
obligations for Losses arising from or related to the Work performed by Contractor.
Invitation for Bid (IFB) Package 15 Rev. April 27, 2016
CONSTRUCTION CONTRACT
15.5.1 Compensation. Following such termination and within forty-five (45) Days after receipt
of a billing from Contractor seeking payment of sums authorized by this Paragraph 15.5.1, City
shall pay the following to Contractor as Contractor’s sole compensation for performance of the
Work :
.1 For Work Performed. The amount of the Contract Sum allocable to the portion of the
Work properly performed by Contractor as of the date of termination, less sums previously paid to
Contractor.
.2 For Close-out Costs. Reasonable costs of Contractor and its Subcontractors:
(i) Demobilizing and
(ii) Administering the close-out of its participation in the Project (including, without
limitation, all billing and accounting functions, not including attorney or expert fees) for a
period of no longer than thirty (30) Days after receipt of the notice of termination.
.3 For Fabricated Items. Previously unpaid cost of any items delivered to the Project Site
which were fabricated for subsequent incorporation in the Work.
.4 Profit Allowance. An allowance for profit calculated as four percent (4%) of the sum of
the above items, provided Contractor can prove a likelihood that it would have made a profit if
the Construction Contract had not been terminated.
15.5.2 Subcontractors. Contractor shall include provisions in all of its subcontracts, purchase
orders and other contracts permitting termination for convenience by Contractor on terms that
are consistent with this Construction Contract and that afford no greater rights of recovery against
Contractor than are afforded to Contractor against City under this Section.
15.6 Contractor’s Duties Upon Termination.
Upon receipt of a notice of termination for default or for convenience, Contractor shall, unless the notice
directs otherwise, do the following:
(i) Immediately discontinue the Work to the extent specified in the notice;
(ii) Place no further orders or subcontracts for materials, equipment, services or facilities,
except as may be necessary for completion of such portion of the Work that is not
discontinued;
(iii) Provide to City a description in writing, no later than fifteen (15) days after receipt of the
notice of termination, of all subcontracts, purchase orders and contracts that are
outstanding, including, without limitation, the terms of the original price, any changes,
payments, balance owing, the status of the portion of the Work covered and a copy of
the subcontract, purchase order or contract and any written changes, amendments or
modifications thereto, together with such other information as City may determine
necessary in order to decide whether to accept assignment of or request Contractor to
terminate the subcontract, purchase order or contract;
(iv) Promptly assign to City those subcontracts, purchase orders or contracts, or portions
thereof, that City elects to accept by assignment and cancel, on the most favorable terms
reasonably possible, all subcontracts, purchase orders or contracts, or portions thereof,
that City does not elect to accept by assignment; and
(v) Thereafter do only such Work as may be necessary to preserve and protect Work already
in progress and to protect materials, plants, and equipment on the Project Site or in
transit thereto.
Upon termination, whether for cause or for convenience, the provisions of the Contract
Documents remain in effect as to any Claim, indemnity obligation, warranties, guarantees,
Invitation for Bid (IFB) Package 16 Rev. April 27, 2016
CONSTRUCTION CONTRACT
submittals of as-built drawings, instructions, or manuals, or other such rights and obligations
arising prior to the termination date.
SECTION 16 CONTRACTOR'S RIGHTS AND REMEDIES.
16.1 Contractor’s Remedies.
Contractor may terminate this Construction Contract only upon the occurrence of one of the following:
16.1.1 For Work Stoppage. The Work is stopped for sixty (60) consecutive Days, through no act
or fault of Contractor, any Subcontractor, or any employee or agent of Contractor or any
Subcontractor, due to issuance of an order of a court or other public authority other than City
having jurisdiction or due to an act of government, such as a declaration of a national emergency
making material unavailable. This provision shall not apply to any work stoppage resulting from
the City’s issuance of a suspension notice issued either for cause or for convenience.
16.1.2 For City's Non-Payment. If City does not make pay Contractor undisputed sums within
ninety (90) Days after receipt of notice from Contractor, Contractor may terminate the
Construction Contract (30) days following a second notice to City of Contractor’s intention to
terminate the Construction Contract.
16.2 Damages to Contractor.
In the event of termination for cause by Contractor, City shall pay Contractor the sums provided for in
Paragraph 15.5.1 above. Contractor agrees to accept such sums as its sole and exclusive compensation
and agrees to waive any claim for other compensation or Losses, including, but not limited to, loss of
anticipated profits, loss of revenue, lost opportunity, or other consequential, direct, indirect and incidental
damages, of any kind.
SECTION 17 ACCOUNTING RECORDS.
17.1 Financial Management and City Access.
Contractor shall keep full and detailed accounts and exercise such controls as may be necessary for proper
financial management under this Construction Contract in accordance with generally accepted accounting
principles and practices. City and City's accountants during normal business hours, may inspect, audit and
copy Contractor's records, books, estimates, take-offs, cost reports, ledgers, schedules, correspondence,
instructions, drawings, receipts, subcontracts, purchase orders, vouchers, memoranda and other data
relating to this Project. Contractor shall retain these documents for a period of three (3) years after the
later of (i) Final Payment or (ii) final resolution of all Contract Disputes and other disputes, or (iii) for such
longer period as may be required by law.
Invitation for Bid (IFB) Package 17 Rev. April 27, 2016
CONSTRUCTION CONTRACT
17.2 Compliance with City Requests.
Contractor's compliance with any request by City pursuant to this Section 17 shall be a condition precedent
to filing or maintenance of any legal action or proceeding by Contractor against City and to Contractor's
right to receive further payments under the Contract Documents. City many enforce Contractor’s
obligation to provide access to City of its business and other records referred to in Section 17.1 for
inspection or copying by issuance of a writ or a provisional or permanent mandatory injunction by a court
of competent jurisdiction based on affidavits submitted to such court, without the necessity of oral
testimony.
SECTION 18 INDEPENDENT PARTIES.
18.1 Status of parties.
Each party is acting in its independent capacity and not as agents, employees, partners, or joint ventures’
of the other party. City, its officers or employees shall have no control over the conduct of Contractor or
its respective agents, employees, subconsultants, or subcontractors, except as herein set forth.
SECTION 19 NUISANCE.
19.1 Nuisance Prohibited.
Contractor shall not maintain, commit, nor permit the maintenance or commission of any nuisance in
connection in the performance of services under this Construction Contract.
SECTION 20 PERMITS AND LICENSES.
20.1 Payment of Fees.
Except as otherwise provided in the Special Provisions and Technical Specifications, The Contractor shall
provide, procure and pay for all licenses, permits, and fees, required by the City or other government
jurisdictions or agencies necessary to carry out and complete the Work. Payment of all costs and expenses
for such licenses, permits, and fees shall be included in one or more Bid items. No other compensation
shall be paid to the Contractor for these items or for delays caused by non-City inspectors or conditions set
forth in the licenses or permits issued by other agencies.
SECTION 21 WAIVER.
21.1 Waiver.
A waiver by either party of any breach of any term, covenant, or condition contained herein shall not be
deemed to be a waiver of any subsequent breach of the same or any other term, covenant, or condition
contained herein, whether of the same or a different character.
Invitation for Bid (IFB) Package 18 Rev. April 27, 2016
CONSTRUCTION CONTRACT
SECTION 22 GOVERNING LAW AND VENUE; COMPLIANCE WITH LAWS.
22.1 Governing Law.
This Construction Contract shall be construed in accordance with and governed by the laws of the State of
California, and venue shall be in a court of competent jurisdiction in the County of Santa Clara, and no
other place.
22.2 Compliance with Laws.
Contractor shall comply with all applicable federal and California laws and city laws, including, without
limitation, ordinances and resolutions, in the performance of work under this Construction Contract.
22.2.1 Palo Alto Minimum Wage Ordinance. Contractor shall comply with all requirements of
the Palo Alto Municipal Code Chapter 4.62 (Citywide Minimum Wage), as it may be amended from
time to time. In particular, for any employee otherwise entitled to the State minimum wage, who
performs at least two (2) hours of work in a calendar week within the geographic boundaries of
the City, Contractor shall pay such employees no less than the minimum wage set forth in Palo
Alto Municipal Code section 4.62.030 for each hour worked within the geographic boundaries of
the City of Palo Alto. In addition, Contractor shall post notices regarding the Palo Alto Minimum
Wage Ordinance in accordance with Palo Alto Municipal Code section 4.62.060.
SECTION 23 COMPLETE AGREEMENT.
23.1 Integration.
This Agreement represents the entire and integrated agreement between the parties and supersedes all
prior negotiations, representations, and contracts, either written or oral. This Agreement may be amended
only by a written instrument, which is signed by the parties.
SECTION 24 SURVIVAL OF CONTRACT.
24.1 Survival of Provisions.
The provisions of the Construction Contract which by their nature survive termination of the Construction
Contract or Final Completion, including, without limitation, all warranties, indemnities, payment
obligations, and City’s right to audit Contractor’s books and records, shall remain in full force and effect
after Final Completion or any termination of the Construction Contract.
SECTION 25 PREVAILING WAGES.
This Project is not subject to prevailing wages. Contractor is not required to pay prevailing wages in the
performance and implementation of the Project in accordance with SB 7, if the public works contract does
not include a project of $25,000 or less, when the project is for construction work, or the contract does not
include a project of $15,000 or less, when the project is for alteration, demolition, repair, or maintenance
(collectively, ‘improvement’) work.
Or
Contractor is required to pay general prevailing wages as defined in Subchapter 3, Title 8 of the
California Code of Regulations and Section 16000 et seq. and Section 1773.1 of the California Labor Code.
Pursuant to the provisions of Section 1773 of the Labor Code of the State of California, the City Council has
obtained the general prevailing rate of per diem wages and the general rate for holiday and overtime work
Invitation for Bid (IFB) Package 19 Rev. April 27, 2016
CONSTRUCTION CONTRACT
in this locality for each craft, classification, or type of worker needed to execute the contract for this
Project from the Director of the Department of Industrial Relations (“DIR”). Copies of these rates may be
obtained at the Purchasing Division’s office of the City of Palo Alto. Contractor shall provide a copy of
prevailing wage rates to any staff or subcontractor hired, and shall pay the adopted prevailing wage rates
as a minimum. Contractor shall comply with the provisions of all sections, including, but not limited to,
Sections 1775, 1776, 1777.5, 1782, 1810, and 1813, of the Labor Code pertaining to prevailing wages.
SECTION 26 NON-APPROPRIATION.
26.1 Appropriations.
This Agreement is subject to the fiscal provisions of the Charter of the City of Palo Alto and the Palo Alto
Municipal Code. This Agreement will terminate without any penalty (a) at the end of any fiscal year in the
event that the City does not appropriate funds for the following fiscal year for this event, or (b) at any time
within a fiscal year in the event that funds are only appropriated for a portion of the fiscal year and funds
for this Construction Contract are no longer available. This section shall take precedence in the event of a
conflict with any other covenant, term, condition, or provision of this Agreement.
SECTION 27 AUTHORITY.
27.1 Representation of Parties.
The individuals executing this Agreement represent and warrant that they have the legal capacity and
authority to do so on behalf of their respective legal entities.
SECTION 28 COUNTERPARTS
28.1 Multiple Counterparts.
This Agreement may be signed in multiple counterparts, which shall, when executed by all the parties,
constitute a single binding agreement.
SECTION 29 SEVERABILITY.
29.1 Severability.
In case a provision of this Construction Contract is held to be invalid, illegal or unenforceable, the validity,
legality and enforceability of the remaining provisions shall not be affected.
SECTION 30 STATUTORY AND REGULATORY REFERENCES.
30.1 Amendments to Laws.
With respect to any amendments to any statutes or regulations referenced in these Contract Documents,
the reference is deemed to be the version in effect on the date that the Contract was awarded by City,
unless otherwise required by law.
SECTION 31 WORKERS’ COMPENSATION CERTIFICATION.
31.1 Workers Compensation.
Pursuant to Labor Code Section 1861, by signing this Contract, Contractor certifies as follows:
Invitation for Bid (IFB) Package 20 Rev. April 27, 2016
CONSTRUCTION CONTRACT
“I am aware of the provisions of Section 3700 of the Labor Code which require every employer to be
insured against liability for workers’ compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the performance of the
Work on this Contract.”
SECTION 32 DIR REGISTRATION AND OTHER SB 854 REQUIREMENTS.
32.1 General Notice to Contractor.
City requires Contractor and its listed subcontractors to comply with the requirements of SB 854.
32.2 Labor Code section 1771.1(a)
City provides notice to Contractor of the requirements of California Labor Code section 1771.1(a), which
reads:
“A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the
requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract
for public work, as defined in this chapter, unless currently registered and qualified to perform public work
pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a
bid that is authorized by Section 7029.1 of the Business and Professions Code or Section 10164 or 20103.5
of the Public Contract Code, provided the contactor is registered to perform public work pursuant to
Section 1725.5 at the time the contract is awarded.”
32.3 DIR Registration Required.
City will not accept a bid proposal from or enter into this Construction Contract with Contractor without
proof that Contractor and its listed subcontractors are registered with the California Department of
Industrial Relations (“DIR”) to perform public work, subject to limited exceptions.
32.4 Posting of Job Site Notices.
City gives notice to Contractor and its listed subcontractors that Contractor is required to post all job site
notices prescribed by law or regulation and Contractor is subject to SB 854-compliance monitoring and
enforcement by DIR.
32.5 Payroll Records.
City requires Contractor and its listed subcontractors to comply with the requirements of Labor Code
section 1776, including:
(i) Keep accurate payroll records, showing the name, address, social security
number, work classification, straight time and overtime hours worked each day
and week, and the actual per diem wages paid to each journeyman, apprentice,
worker, or other employee employed by, respectively, Contractor and its listed
subcontractors, in connection with the Project.
(ii) The payroll records shall be verified as true and correct and shall be certified
and made available for inspection at all reasonable hours at the principal office
of Contractor and its listed subcontractors, respectively.
Invitation for Bid (IFB) Package 21 Rev. April 27, 2016
CONSTRUCTION CONTRACT
(iii) At the request of City, acting by its project manager, Contractor and its listed
subcontractors shall make the certified payroll records available for inspection
or furnished upon request to the project manager within ten (10) days of receipt
of City’s request.
City requests Contractor and its listed subcontractors to submit the certified
payroll records to the project manager at the end of each week during the
Project.
(iv) If the certified payroll records are not produced to the project manager within
the 10-day period, then Contractor and its listed subcontractors shall be subject
to a penalty of one hundred dollars ($100.00) per calendar day, or portion
thereof, for each worker, and City shall withhold the sum total of penalties from
the progress payment(s) then due and payable to Contractor. This provision
supplements the provisions of Section 15 hereof.
(v) Inform the project manager of the location of contractor’s and its listed
subcontractors’ payroll records (street address, city and county) at the
commencement of the Project, and also provide notice to the project manager
within five (5) business days of any change of location of those payroll records.
IN WITNESS WHEREOF, the parties have caused this Construction Contract to be executed the
date and year first above written.
CITY OF PALO ALTO
____________________________
Purchasing Manager
City Manager
APPROVED AS TO FORM:
____________________________
City Attorney or designee
APPROVED:
____________________________
Public Works Director
CONTRACTOR
By:___________________________
Name:________________________
Title:__________________________
Date: _________________________
1 Revision April 28, 2014
AMENDMENT NO. TWO TO CONTRACT NO. C13148737
BETWEEN THE CITY OF PALO ALTO AND ADVANCED DESIGN CONSULTANTS, INC.
This Amendment No. Two to Contract No. C13148737 (“Contract”) is entered
into on this 26th day of June, 2016, by and between the CITY OF PALO ALTO, a California
chartered municipal corporation (“CITY”), and ADVANCED DESIGN CONSULTANTS, INC , a
California corporation, located at 998 Park Avenue, San Jose, CA 95126("CONSULTANT").
R E C I T A L S
A. The Contract was entered into between the parties for the provision of design services
for the Lucie Stern Buildings Mechanical/ Electrical Upgrades project.
B. The parties wish to amend the Contract to increase the scope of services
to include Full Construction Administration and Construction Management Services, increase
compensation in the amount of $317,738 for Basic Services and $31,774 for Additional Services
and extend the contract term through May 19, 2018.
NOW, THEREFORE, in consideration of the covenants, terms, conditions, and
provisions of this Amendment, the parties agree:
SECTION 1. Section 1, SCOPE OF SERVICES, is hereby amended to read as
follows:
“CONSULTANT shall perform the Services described in the attached Exhibit “A-1”
as an addition to the scope of services described in Exhibit “A” of the original contract, and
Exhibit “A” of Amendment No. 1 in accordance with the terms and conditions contained in this
Agreement. The performance of all Services shall be to the reasonable satisfaction of CITY.”
SECTION 2. Section 2, TERM, is hereby amended to read as follows:
The term of this Agreement shall be from the date of its full execution through May 19, 2018
unless terminated earlier pursuant to Section 19 of this Agreement.
SECTION 3. Section 4, NOT TO EXCEED COMPENSATION, is hereby amended
to read as follows:
“The compensation to be paid to CONSULTANT for performance of the Services
described in Exhibit “A “and Exhibit “A-1”, including both payment for professional services and
reimbursable expenses, shall not exceed Six hundred nine thousand three hundred thirty three
dollars($609,333). In the event Additional Services are authorized, the total compensation for
Services, Additional Services and reimbursable expenses shall not exceed Six hundred seventy
thousand two hundred sixty seven dollars($670,267). The applicable rates
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
2 Revision April 28, 2014
and schedule of payment are set out in Exhibit “C-1” entitled “HOURLY RATE SCHEDULE” of the
original contract, and Exhibit “C-3” of Amendment No.2.entitled “HOURLY RATE SCHEDULE,”
which is attached to and made a part of this Agreement.
Additional Services, if any, shall be authorized in accordance with and subject to the provisions
of Exhibit “C” of the original contract, Exhibit “C” of Amendment No.1 and Exhibit “C-2” of
Amendment No.2. CONSULTANT shall not receive any compensation for Additional Services
performed without the prior written authorization of CITY. Additional Services shall mean any
work that is determined by CITY to be necessary for the proper completion of the Project, but
which is not included within the Scope of Services described in Exhibit “A” and Exhibit “A-1”.
SECTION 4. The following exhibit(s) to the Contract is/are hereby amended to
read as set forth in the attachment(s) to this Amendment, which are incorporated in full by this
reference:
a. Exhibit “A-1” entitled “SCOPE OF SERVICES”.
b. Exhibit “B-1” entitled “SCHEDULE OF PERFORMANCE”.
c. Exhibit “C-2” entitled “COMPENSATION”.
d. Exhibit “C-3” entitled “HOURLY RATE SCHEDULE”.
SECTION 5. Except as herein modified, all other provisions of the Contract,
including any exhibits and subsequent amendments thereto, shall remain in full force and
effect.
IN WITNESS WHEREOF, the parties have by their duly authorized representatives
executed this Amendment on the date first above written.
3 Revision April 28, 2014
CITY OF PALO ALTO
____________________________
CITY MANAGER
APPROVED AS TO FORM:
_____________________________
Senior Deputy City Attorney
ADVANCED DESIGN CONSULTANTS, INC
By:___________________________
Name:_________________________
Title:________________________
Attachments:
Exhibit “A-1” entitled “SCOPE OF SERVICES”.
Exhibit “B-1” entitled “SCHEDULE OF PERFORMANCE”.
Exhibit “C-2” entitled “COMPENSATION.
Exhibit “C-3” entitled “HOURLY RATE SCHEDULE.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
Project Manager
Lorenzo Rios Jr
1
EXHIBIT A-1
SCOPE OF SERVICES AMENDMENT NO. 2
Construction Phase Services for the Lucie Stern project are required at this time and the City is accordingly issuing a contract amendment for these services.
The Consultant’s services shall include full construction administration and construction management
services as required to assist City staff in the management of the construction of the project, as well as
with any claims or other contract disputes that may arise. All work performed by Consultant shall be in accordance with the professional standard and quality that prevail among professional construction managers in the Peninsula region.
If at any time, the City is not satisfied with the performance of Consultant’s staff, the City reserves the
right to request the services of a different individual. If for any reason Consultant proposes a change of staffing during the course of the project, the City reserves the right to approve any new staff. Staffing changes must be approved a minimum of 21 calendar days in advance of any staffing changes, in
writing, by the City’s Project Manager (PM).
Office space or trailer, computers, cell phones, furnishings and other equipment needed for Consultant’s staff shall be provided by Consultant. Consultant may arrange, at Consultant cost, to have the City’s general contractor (Contractor) provide trailer space and furnishings. Consultant shall list the cost of
any needed office trailer and accompanying furnishings and equipment as a separate line item in their
proposal.
Task 1: Construction Phase Services
Consultant shall in accordance with the professional standard and quality that prevail among
professional construction managers in the Peninsula region:
Consultant shall be the point of contact for the Contractor and shall enforce compliance with all of Contractor’s contractual requirements, as follows:
Site Construction Management: Consultant shall oversee the major construction work performed by the
Contractor. Consultant shall track the construction process, logistics, Request for Information (RFI),
Architect’s Supplemental Information (ASI), Change Order (CO) and other information or requests.
Consultant shall oversee the construction activities and ensure that all aspects of the building permit construction requirements are followed and documented and shall work closely with the project's Commissioning Agent, who is a direct consultant to the City.
Consultant shall work with the Contractor and any involved parties to implement logistical and
communications measures to minimize any impacts to the nearby residential neighborhood, park, fire
station, and the various schools in the vicinity. Consultant shall implement expeditious methods for resolving conflicts. Consultant shall handle the coordination between the City staff, Commissioning
Agent, Contractor, and design staff.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
2
If night time, holiday or weekend work is required to minimize building occupant impacts or due to delay in the schedule, Consultant services shall still be required in full effect based on hourly rates
within T&M contract.
Establishment of deadlines: Consultant shall coordinate with City staff, Contractor, and design staff to
establish deadlines for submittal of and response to RFI’s, deferred submittals, construction coordination drawings, construction schedules, inspection requests, change order requests, and claims. Consultant shall track all such requests and submittals to ensure compliance with deadlines. Consultant shall track
all requests and submittals in a format acceptable to City staff, and shall make the tracking document
available to City staff through electronic file sharing. Consultant shall increase its project staffing in a
timely manner if needed to process requests and submittals in accordance with the established deadlines and to avoid delays.
Outreach: Consultant shall provide monthly construction updates, including project construction cost-
tracking, and shall attend quarterly meetings with the building user stakeholders. At these meetings,
Consultant shall discuss project progress, distribute recent jobsite photos and answer questions that might arise.
Consultant shall respond within 24 hours to Occupants questions and complaints. Consultant shall
provide updates suitable for uploading onto the City’s website or other information site.
Printing of any needed flyers, presentation boards, advertisement and other related outreach material
costs shall be considered a Reimbursable expense, the cost for which shall be approved in writing in advance by the PM.
Meetings: Throughout the construction process, Consultant shall be prepared to address comments and
concerns of the Contractor, PM, City Staff, and the general public on an as-needed basis. Consultant
shall set up and conduct weekly progress OAC meetings during major construction time periods and any
other meetings necessary to facilitate the project work. City will provide the administrative support to provide a meeting room and invite attendees. Consultant shall write and distribute the meeting agendas and meeting minutes, including: commissioning meetings, regular site meetings, and meetings with the
City staff, contractors, various City departments, and the public. The meeting minutes will explicitly
track who has the responsibility for each action item with expected completion dates.
Field Inspection and Supervision: Consultant shall provide a CM Field Superintendent (CMFS) who shall maintain a field presence whenever major construction or hazardous work is under way by the
Contractor. The role of the CMFS will be to enforce the Construction Contract periodically in the field
to ensure that the work is being constructed in compliance with the contract documents, the approved
shop drawings, the current RFI answers, and other Construction Contract documents, and in general, to
protect the interest of the City daily in the field. The CMFS will also observe and report field problems with respect to quality, cost and schedule. The CMFS will develop and maintain deficiency, incomplete
work item, and preliminary punch list reports and will maintain a weekly construction report, as the
weekly history of the project, to include significant jobsite field events that occur each day. The CMFS
will periodically monitor any ‘time and materials’ work performed by the Contractor to ensure that the
work being performed is being charged appropriately to Field Order and not to contract work. The CMFS will not be responsible for means and methods of the Contractor, nor for safety of any of the
Contractor’s employees, but will have the authority, although not the responsibility, to observe and
report concerns with regard to such issues.
Documentation: Consultant shall oversee, manage and track the Contractor’s preparation and/or review
of all necessary documentation for the project including, but not limited to: daily logs and inspection progress reports, photos/videos, RFI, ASI, correspondence, and shop drawings. Consultant shall
maintain all files and documentation related to managing the project via City provided cloud based
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
3
storage site, such as SharePoint. Responses, approvals, and decisions relative to Contractor's documents shall be provided in a timely manner and as required in the construction documents.
Consultant shall review and comment on any project-related correspondence as requested by the City.
Routine correspondence that is related to product information or minor design issues may be prepared
and answered by Consultant on its letterhead, with a copy of the response directed to PM and design staff. Correspondence requiring City response, including but not limited to correspondence with residents, cost or contractual issues, may be drafted by Consultant, but shall be signed only by City.
Submittals: Consultant shall manage, log and track all project submittals (i.e. shop drawings, product
information, substitution request, and samples) for approval in a timely manner as required by the
construction documents and in order to prevent any delays to the project. Comments from different reviewers of the submittal shall be compiled before being returned to the Contractor for revisions. All submittals shall be sent directly between the Contractor and design staff, with copies, documentation and
management reports submitted to and managed by the Consultant.
Electronic file sharing: Consultant shall contract with, host and maintain an electronic file sharing
internet site, like Dropbox or SharePoint, in order for the Consultant, City staff, design staff, Contractor, commissioning agent, and others as appropriate to post project documents for shared viewing. Documents shall include: plans and specifications, submittals, RFI’s, ASI’s, inspection logs, schedules,
meeting agendas and minutes, and any other project documents requested to be posted by City or that
will benefit the various parties involved.
Construction Schedule: Consultant shall review the Contractor's construction schedule. Consultant shall analyze, monitor, and request updates for the master schedule as the project progresses. Consultant shall
analyze the schedule for construction constraints, level of critical activities and to verify progress in
conjunction with the analysis of pay applications. Consultant shall review Contractors' individual
Critical Path Method (CPM) schedules, monitor Contractor's progress, notify the City of any slippage,
and coordinate Contractor recovery plans.
Progress Payments: Consultant shall review progress payment requests submitted by Contractor within
five (5) days of receipt and verify the accuracy and percentage of completion against the schedule and
resolve any discrepancies in the invoices. Consultant shall review the invoices and backup for
completeness and compliance with contract documents and make a recommendation to PM for payment
of the progress payment requests.
Change Order Monitoring and Processing: Consultant shall review all change order requests submitted
to the City for accuracy, completeness, appropriateness, and compliance with the City contract
documents. Consultant shall work with design staff to determine the validity of change order requests,
however, the design staff will not be expected to provide input on the validity of the dollar value of the
claim, only input as to whether the work is indeed ‘extra’. In instances when the work is determined to be extra, Consultant shall make recommendations to the City on the pricing of the change orders using compensation methodologies specified in the Construction Contract. If necessary or if requested by the
City, Consultant shall prepare an independent estimate of the value of the additional work to verify the
reasonableness of fixed price change order requests. Consultant shall reject change order requests that
are determined to be invalid. Consultant shall process change order requests according to the schedule developed under “Establishment of deadlines”, and shall coordinate response with the City.
Claims: Consultant shall analyze any claims from the Contractor (i.e., compensation and delay) as to
whether they are excusable, inexcusable, or compensable and prepare a response for City. Consultant
shall process claims according to the schedule developed under “Establishment of deadlines”.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
4
Quality Control and Assurance: Consultant shall monitor and document the Contractor's work for any
deviations in scope, schedule, or performance and keep the City informed of and assist in resolving any
issues that may arise.
Record Drawings: Consultant shall coordinate the preparation of record drawings with the Contractor and design staff on a regular basis, both during the construction and post-construction phases, and
review the drawings for "as-built" accuracy.
Commissioning: Consultant shall work with the commissioning agent, design staff, and the Contractor
to ensure that all new equipment have been installed in accordance with the contract documents, are
working properly as stand-alone equipment, and are working properly as part of a complete system.
Substantial Completion: As per the construction contract, once the Contractor requests substantial
completion and it is determined to be warranted, Consultant shall prepare and compile a project punch
list with the assistance from the City and design staff to be forwarded to the Contractor. Consultant shall
oversee the completion of the punch list items before the final notice of completion is issued.
Close Out: Consultant shall ensure completion and delivery of all required close out documents including operation and maintenance (O&M) manuals, record drawings, and warranties. Consultant shall
review all these materials for compliance with the contract documents and for completeness and report
any deficiencies or discrepancies to Contractor for corrections and re-submittal. Consultant shall work
under the direction of the PM to resolve any contract claim issues that may arise (stop work notices,
bonding, delays, extra work, etc). As-Built drawings shall be scanned by Consultant for archiving by City.
Files: Consultant shall consolidate and deliver all project files and documentation to be retained by the
City.
Task 2: Photographic Recording
Project Documentation – Photographic Record: Based upon a build period of 12 months, Consultant shall provide a photographic record of the following: pre-construction site-survey of existing
conditions;20 maximum exterior progressions; interior progressions; 20 maximum interior mechanical,
electrical and fire sprinkler; and finished condition prior to occupancy.
All documentation shall include consultations with City identifying project-specific needs, appropriate
photographic intervals, schedules, determination of optimal locations based on the site plans, a representative number of digital photographs at such intervals and for such durations and at the specified
milestones; linking each photo set to the appropriate location on the site plans and floor plans; and two
USB, CD or DVD ROM copies of the entire photo documentation upon completion.
Task 3: Allowance for Testing
Testing and Special Inspections: If needed, a testing and inspection agency(s) shall be under contract
with and paid for by the Consultant. Consultant shall coordinate with the Contractor in scheduling the
testing agency services for materials testing and special inspections needed for the life of the project.
This testing includes, but is not limited to, soils tests, concrete strength and weld inspection. Consultant shall ensure that all required sign-offs are reviewed and distributed and are in compliance with the
specifications and the California Building Codes.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
5
Consultant shall list an allowance of $25,000 for this task. This allowance shall only be expended if authorized in advance, in writing, by the City’s Project Manager.
Task 4: Allowance for Commissioning Agent
Commissioning: A Commissioning Agent shall be under contract with and paid for by the Consultant.
Consultant shall coordinate with the Contractor in scheduling all commissioning activities including but
not limited to testing, trending, operation verification, etc. Consultant shall ensure that all required sign-
offs are reviewed and distributed and are in compliance with the specifications and City requirements.
Consultant shall list an allowance of $30,000 for this task. This allowance shall only be expended if authorized in advance, in writing, by the City’s Project Manager.
Task 5: Post Construction Services
Record Drawings and Close-Out: Within 60 calendar days after the “Notice of Completion to the Contractor”, Consultant shall:
• Coordinate the preparation of record drawings with the Contractor and review these drawings for
“as-built” accuracy
• Ensure completion and delivery of all Contractor required close-out documentation including O&M manuals, record drawings, warranties, etc.
• Consolidate all project files and documentation maintained by the CM to be retained by the City
• Under the direction of the City’s Project Manager, work to resolve any contract claim issues (stop notices, bonding, delays, extra work etc.), that may arise
• Consultant will set up and coordinate contractor-provided training of City staff as required by the
contract documents and as necessary to ensure that the appropriate City personnel are adequately
trained and familiar with the new and refurbished equipment
• Consultant shall, as requested by the City’s Project Manager, respond to and coordinate with the
Contractor or responsible party to repair and/or replace defective work items that are included in
the project’s 1-year warranty period, which may extend to one year from the Notice of
Completion.
Post Construction and Warranty Services: Consultant shall meet with building occupants and Public
Works staff monthly for three months commencing after the building is open to the public in order to
complete any remaining punch-list items and/or to contact the Contractor for any warranty issues that
might arise. After the initial three month period, Consultant shall contact the Staff quarterly for a period of nine months to determine whether any new systems issues have been identified. Systems deficiencies
that cannot be resolved by the Contractor shall be reported to the Commissioning Agent, design staff
and City.
Commissioning Verification: Consultant shall participate in the post-construction activities of the
Commissioning Agent as follows:
Participate in an off-season testing (i.e., testing the heating system prior to winter) session and work
with the Contractor to correct any deficiencies.
Compile the final testing documentation for inclusion in the Commissioning Record and in the O&M
manuals.
12 Month Warranty Follow Up: Consultant shall return to the site at month 10 of the 12 month warranty
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
6
period and review operating conditions with City facility staff and the Commissioning Agent in order to identify any outstanding issues related to the original and seasonal commissioning. The Commissioning
Agent will interview facility staff and identify problems or concerns that they have with operating the
building as originally intended. The Commissioning Agent will make suggestions for improvements and
for recording these changes in the O&M manuals. The Commissioning Agent will identify areas that may come under warranty or under the original construction contract. The Consultant shall work with the Contractor to resolve any warranty issues.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
7
EXHIBIT B-1 SCHEDULE OF PERFORMANCE
AMENDMENT NO. 2
The CITY agrees to compensate the CONSULTANT for professional services performed in accordance with the terms and conditions of this Agreement, and as set forth in the budget schedule below.
Compensation shall be calculated based on the hourly rate schedule attached as exhibit C-3 up to the not
to exceed budget amount for each task set forth below.
CONSULTANT shall perform the tasks and categories of work as outlined and budgeted below. The CITY’s Project Manager may approve in writing the transfer of budget amounts between any of the
tasks or categories listed below provided the total compensation for Basic Services, including
reimbursable expenses, and the total compensation for Additional Services do not exceed the amounts
set forth in Section 4 of
Tasks Completion
Task 1 - Construction Phase 1 Services
• Construction Start Concurrent with Construction NTP
• Community Center completion 388 days following NTP
• Children’s Theater completion 388 days following NTP
• Community Theater completion 388 days following NTP
Task 2 - Photographic Recording on-going during construction
Task 3 - Additional Testing on-going during construction Task 4 – Commissioning on-going during construction
• Project Close-Out 30 days following NOC of construction
contract
Task 5 - Post-Construction Phase Services
• Warranty Period 12 months following NOC of construction
contract
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
8
EXHIBIT C-2 COMPENSATION
AMENDMENT NO. 2
The CITY agrees to compensate the CONSULTANT for professional services performed in accordance
with the terms and conditions of this Agreement, and as set forth in the budget schedule below. Compensation shall be calculated based on the hourly rate schedule attached as Exhibit C-3 up to the
not-to-exceed budget amount for each task set forth below.
For subconsultants, such as inspectors, special inspectors, electronic document services, and
photographic documentation services, the CITY agrees to compensate the CONSULTANT for services
performed in accordance with the terms and conditions of this Agreement, and as set forth in the budget schedule below. Compensation shall be calculated based on the actual cost of the subconsultant, plus a
fee of 5%, up to the not-to-exceed budget amount for each task set forth below.
CONSULTANT shall perform the tasks and categories of work as outlined and budgeted below. The
CITY’s Project Manager may approve in writing the transfer of budget amounts between any of the
tasks or categories listed below provided the total compensation for Basic Services, including reimbursable expenses, and the total compensation for Additional Services do not exceed the amounts
set forth in Section 4 of this Agreement.
TASKS NOT-TO-EXCEED AMOUNT
Task 1 - Construction Phase Services $226,983
Task 2 - Photographic Recording $21,253
Task 3 - Allowance: Additional Testing $25,000 Task 4 -Allowance Commissioning $30,000
Task 5 - Post-Construction Phase Services $14,502 TOTAL BASIC SERVICES $317,738
Reimbursable Expenses $0
Additional Services (Not to Exceed) $31,774
Total Amendment No. 2: Not To Exceed Compensation: $349,512
REIMBURSABLE EXPENSES
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
9
The administrative, overhead, secretarial time or secretarial overtime, word processing,
photocopying, in-house printing, insurance and other ordinary business expenses are included
within the scope of payment for services and are not reimbursable expenses. CITY shall
reimburse CONSULTANT for the following reimbursable expenses at cost. Expenses for which
CONSULTANT shall be reimbursed are:
A. Travel outside the San Francisco Bay area, including transportation and meals, will be
reimbursed at actual cost subject to the City of Palo Alto’s policy for reimbursement of travel and
meal expenses for City of Palo Alto employees.
B. Long distance telephone service charges, cellular phone service charges, facsimile transmission
and postage charges are reimbursable at actual cost.
All requests for payment of expenses shall be accompanied by appropriate backup information.
Any expense anticipated to be more than $0 shall be approved in advance by the CITY’s project manager.
ADDITIONAL SERVICES
The CONSULTANT shall provide additional services only by advanced, written authorization
from the CITY. The CONSULTANT, at the CITY’s project manager’s request, shall submit a
detailed written proposal including a description of the scope of services, schedule, level of effort,
and CONSULTANT’s proposed maximum compensation, including reimbursable expense, for
such services based on the rates set forth in Exhibit C-3. The additional services scope, schedule and maximum compensation shall be negotiated and agreed to in writing by the CITY’s Project
Manager and CONSULTANT prior to commencement of the services. Payment for additional
services is subject to all requirements and restrictions in this Agreement
Additional Services include, but are not limited to, attendence at Council and Commission
meetings not originally intended in the scope of work and reimbursable expenses not included in
the base fee.
DocuSign Envelope ID: A58194CB-9B95-4703-9BC2-DD2B03DDA0D9
998 Park Avenue San Jose, CA 95126
P: 408.297.1881 | F: 408.294.3186
www.adcengineers.com
REV015.216
EXHIBIT C-3
HOURLY RATE SCHEDULE
AMENDMENT NO. 2
Item Discipline Billing Rate
0001 Project Manager $214.10
0002 CM Field Superintendent $149.75
0003 CM Project Engineer $108.07
0004 Senior Architect $156.83
0005 Architect‐Designer $108.07
0006 Senior Structural Engineer $154.46
0007 Structural Designer $108.07
0008 Senior Mechanical Engineer $131.43
0009 Mechanical Designer $102.23
0010 Senior Electrical Engineer $131.43
0011 Electrical Designer $102.23
0012 Fire Protection Engineer $128.51
0013 CADD $90.10
0014 Clerical $65.00
These hourly rates are based on personnel salaries, overhead, mark-up, and profit.