HomeMy WebLinkAbout2002-04-22 City Council (6)TO:
FROM:
City of Palo Alto
City Manage R port
IIONORA~LE CITY COUNCIL ¯
CITY MANAGER DEPARTMENT: City Manager’s
Office
DATE:
SUBJECT:
APRIL 22, 2002 CMR: 219:02
OPTIONS FOR PHASING LIBRARY
COMMUNITY FACILITIES PROJECTS
AND OTHER
REPORT IN BRIEF
The Library Advisory Commission’s (LAC) New Library Plan (NLP) recommends
two expanded, full service Resource Libraries in north (Children’s, Main) and south
(Mitchell Park) Palo Alto, and retaining smaller, popular reading Neighborhood
Libraries (Terman Park, Downtown and College Terrace). The City Council
adopted the NLP in concept in October 2000 and directed staff to proceed with
development of Phase 1 of the plan, which includes feasibility and costing studies
for expansion of the Resource Libraries and completion of a consultant study of
staffing requirements, job assignments, and a transition plan. Because the Mitchell
Park Community Center and Art Center share the sites of the Mitchell Park Library
and Main Library respectively, they have been added to the projects being
considered for a bond measure in November 2002. Site feasibility studies have
been completed for all projects and conceptual design begun, along with required
environmental review. Preliminary cost estimates have been prepared. A library
staffing study was prepared (Simmons report) which makes recommendations for
augmenting current staff’mg to .accommodate-hours and service operation; and
presents a p!an for the new positions required if the expanded facilities are
approved.
This staff report provides the Council with options to consider in determining what
to incorporate into the second community survey, planned for May 2002, on
community facilities that will be on the ballot in November 2002. Four options are
detailed, along with pros and cons for each option:
¯Option 1: Single Bond Measure = All Facilities
¯Option 2: Two Bond Measures - In 2002, Mitchell Park Center and Children’s
Library and $5 million contribution to Art Center project; in 2010, Main Library
¯Option 3.: Two Bond Measures - in 2002, Children’s Library and Mitchell.Park
Community Center, with reduced Mitchell Park Library and reduced Main
CMR:219:02 Page 1 of 17
Library and a $5 million contribution to the Art Center project; in 2010,
remainder of projects for Mitchell Park Library and Main Library
Option 4: Single Bond Measure - In 2002, Children’s Library and Mitchell Park
Community Center, with reduced Mitchell Park Library and Main Library and a
$5 million contribution to the Art Center Project
Financing for both the one-time and the ongoing costs associated with the bond
¯ measure projects is discussed. In addition to the capital costs, which can be debt
financed, there are one-time costs to furnish the expanded facilities; and on-going
staffing, operations and maintenance costs. -Private fundraising is suggested as a
viable alternative for the one-time furnishings costs; and a strategy is proposed to
address the short-term and long-term issues related to staffing and on-going
operations. A preliminary staffing plan was prepared using the Simmons report as a
basis for cost estimation purposes; this will be the subject of further review both by
staff and the Library Advisory Commission.
CMR:219:02 Page 2 of 17
RECOMMENDATION
Staff recommends that the City Council:
1.Review the options for phasing the capital program to renovate and expand
the Main Library, Children’s Library, Art Center, Mitchell Park Library and
Mitchell Park Community Center and determine the preferred option, which
will be the basis for a second community survey in May 2002.
2. Approve the recommended approach to funding library staffing for the
period of January 2003 to July 2004.
3.Provided a bond measure .for renovating the Resource Libraries is successful
in November, work with the Library Advisory Commission to prepare a
staffing plan and related funding options. Options will include both
expenditure and service reduction options within the General Fund budget as
well as new revenues (e.g. parcel tax).
BACKGROUND
New Library Plan
In May 2000, the City’s Library Advisory Commission produced the New Library
Plan. This document contains the LAC’s vision and recommendations for
improving the City’s library system. Specifically, the LAC recommends two
expanded, full service Resource Libraries in north (Children’s, Main) and south
(Mitchell Park) Palo Alto, and retaining smaller, popular reading Neighborhood
Libraries (Terman Park, Downtown and College Terrace). The City Council
adopted the NLP in concept in October 2000 and directed staff to proceed with
development of Phase 1 of the plan, which includes feasibility and costing studies
for expansion of the Resource Libraries and completion of a consultant study of
staffing requirements, job assignments, and a transition plan.
Design of Library_ and Community Facilities Projects
In the summer of 2001, the City Council directed staff to fast track the Main,
Mitchell Park and Children’s Library projects in order to have conceptual designs
and associated cost estimates completed by June 2002. The intent was for Council
to have the necesshry information regarding each project to be able to make a
determination which projects would be included in a bond measure on the
November 2002 ballot.
Since last summer, many steps have been taken to achieve the June 2002 deadline
for conceptual designs. Two additional projects have been added to the three NLP
projects. The Council approved coordinating the Main Library expansion project
CMR:219:02 Page 3 of 17
with the Art Center Foundation’s proposed expansion of the Art Center, as the two
facilities share the same site. The Council also approved coordinating the Mitchell
Park Library expansion project with the proposed renovation of the Mitchell Park
Community Center as those two facilities share the same site. These five projects
now comprise the community facility projects for potential inclusion in the
upcoming bond measure.
To objectively determine the recommended building square footage for each of the
five projects, the City retained architects to prepare programming studies. The
studies list all the different types of spaces and the associated square footages
necessary to achieve the vision for the renovated and expanded facilities. Below is
a list of the current and programmed square footages (sq. ft.) for each of the
projects:
Children’s Library
Mitchell Park Library
Mitchell Park Community Center
Main Library
Art Center
TOTAL (rounded)
Existing sq. It.Programmed sq. It.
3,400 12,000
9,500 55,000
10,200 16,800
26,800 66,000
28,600 .55,000
75,500 205,000
Next, architects were retained to prepare feasibility studies for each site except
Children’s. These studies investigated different configurations of buildings,
parking, site circulation and landscaping. The Children’s Library feasibility study
had already been completed in 2000, recommending both a north and a south
addition to the existing historic library with an estimated project cost of
approximately $6 million.
The Main Library and Art Center site feasibility study was completed and presented
to Council in February 2002. Two schemes were approved by Council for
continuation into conceptual design: a scheme to keep the main. reading room of the
existing library and add on to it; and a scheme that demolishes the existing library
in order to construct a new one. The Art Center has one scheme, which consists of
three separate phases of additions to the existing building. Phase. 1 of the Art
Center expansion is a 10,000 square feet addition and is the only phase that the Art
Center Foundation intends to pursue in the near future. The estimated project costs
were approximately $42 million for the Main Library and $18 million for the Art
Center (Phase 1 only). The Art Center Foundation is working withits architect to
reduce its project cost to $10 million and is requesting a $5 million contribution
from the City, to be matched by private fundraising.
CMR:219:02 Page 4 of 17
The Mitchell Park Library and Community Center site feasibility study was
completed and presented to Council in March 2002. One scheme was approved for
continuation into conceptual design. This scheme demolishes the existing
buildings, replacing them with two facilities with a common entry/lobby. The new,
shared facility would be on the south side of the site abutting the park. The
estimated project costs are approximately $30 million for the Library and $9 million
for the Community Center.
All of the feasibility studies went through an extensive community review process,
including numerous community, board and commission meetings. Currently,
architects are preparing the conceptual designs and more refined cost estimates for
all the projects. Conceptual designs will also be reviewed by the community,
boards and commissions prior to being presented to Council.
Concurrent with development of conceptual designs, the California Environmental
Quality Act (CEQA) process is underway for each site. An Environmental Impact
Report (EIR) is being prepared for the Main Library/Art Center site. Mitigated
Negative Declarations are being prepared for the Mitchell Park Library/Community
Center (Mitchell Park Center) site and the Children’s Library site. The projects are
all on schedule for presentation of conceptual designs, cost estimates and completed
CEQA documentation to Council in June 2002.
Staffing to Implement New Library_ Plan
In June 2001, the City contracted with Beverley Simmons and Associates to analyze
and recommend appropriate staffing for the proposed Resource and Neighborhood
Libraries; develop a staffing transition plan from current service levels through
those recommended in the NLP; and develop new job descriptions for library
positions. The report was completed in January 2002 and distributed to Council in
February (CMR 152:02).
The Simmons report is comprehensive in its analysis of library operations, and
includes recommendations for a more functional and effective Library organization.
The key findings of the report include the following:
¯Staffing levels are critically low given the high level of service demand with
very limited staffing resources. Compared to neighboring city libraries and
similar libraries around the state, Palo Alto has twice the number of facilities
and nearly twice the number of service hours.
¯Multi-branch library systems introduce complexities such as multiple service
points, movement of collections among locations, overlapping maintenance
issues for facilities, technology, collections, equipment, etc, Staffing levels
must take these complexities into account.
CMR:219:02 Page 5 of 17
¯Establishment of a Baseline Staffing Plan is necessary. However, even the
Baseline Staffing Plan recommended by the consultant leaves Palo Alto
ranking lowest in staff per service hour when compared with neighboring
and comparable libraries.
¯Heavy workloads impede service delivery.
¯The number of management level staffing is insufficient.
¯Implementation of the NLP will require a significant number of additional
positions.
DISCUSSION
Staff has developed four options for Council consideration in determining ’how to
approach both the second community survey and eventually what will go on the
ballot for Palo Alto voters in November 2002. The costs of all four options are
summarized on Attachment 1.
Description of Options
Option 1: Single Bond Measure -All Facilities
This option places the Children’s Library, Mitchell Park Center (Library. and
Community Center), Main Library and a $5 million City contribution to the
public/private partnership for expansion and renovation of the Art Center on the
November ballot. The estimated one-time cost of this option .is $91.5 million,
including financing costs. The City will also need to identify up to $4.3 million of
one-time funding to furnish the facilities and $4.0 million per year in ongoing
staffing, program and maintenance/operations costs over the next 6 years to fully
implement this option.
Pros - Single Bond Measure, All Facilities
¯Completes long-term NLP vision
¯Most efficient use of resources for planning and scheduling of library design
and construction
¯Most efficient in terms of total project costs and par value of bonds
¯Saves effort and cost of conducting second election.
¯Most attractive for voters "all over town"
Cons - Single Bond Measure, All Facilities
¯Size of measure may be of concern to voters
CMR:219:02 Page 6 of 17
Option 2: Two Bond Measures - In 2002, Mitchell Park Center, Children’s Library
and $5 million contribution to Art Center project," in 2010, Main Library
This option envisions two bond measures, for Mitchell Park Center and the
Children’s Library in November 2002, followed by a bond measure in 2010 for the
Main Library. The second, bond measure would occur after construction is
completed on Children’s Library and Mitchell Center, and provides time for a
second citizen’s campaign to approve the second bond measure., The City’s $5
million contribution to the Art Center project could be included in either bond
measure. However, the Art Foundation strongly suplSorts inclusion in the first bond
measure and is working with its architect to develop a building project that would
allow it to proceed prior to initiation of construction on the Main Library. The
estimated one-time cost of the first bond measure in 2002 is $50.8 million, which
includes a $5 million contribution toward the Art Center and financing costs. The
2010 measure would total $48.8 million. The City will also need to identify $4.7
million in one-time costs to furnish the new facilities, and $412 million per year in
ongoing staffing and maintenance/operations costs over the next 11 years tO fully
implement this option.
Pros: Two Bond Measures - in 2002, Mitchell Park Center, Children’s Library and
a $5 million contribution for the Art Center project; in 2010, Main Library
¯Addresses library service needs at the two facilities having the greatest need
¯Provides some service improvements in both north and south areas of city
¯Community has opportunity to experience using two new/expanded libraries
which may help "sell" Main Library project/financing
Cons: Two Bond Measures - in 2002, Mitchell Park Center, Children’s Library,
and a $5 million contribution for the Art Center project; in 2010, Main Library
¯Potential that Main Library improvements would not be approved by voters
.and NLP vision would be compromised
¯Effort and cost required to pass a second bond measure
¯First bond measure may not secure sufficient north Palo Alto support; second
bond measure may. not secure sufficient south Palo Alto voter support.
¯Delaying design and construction of the Main Library will increase the cost
due to escalation.
¯Complicates coordination of project with adjacent Art Center.
Option 3." Two Bond Measures - in 2002, Children’s Library and Mitchell Park
Community Center, with reduced Mitchell Park Library and reduced Main Library
CMR:219:02 Page 7 of 17
and a $5 million contribution to the Art Center project," in 2010, remainder of
projects for Mitchell Park Library and Main Library
The third option also envisions two separate bond measures. It reduces the Mitchell
Park Library and Main Library square footage, related programs and
staffing/operating costs for the initial bond measure. Mitchell Park Community
Center and Children’s Library stay at 100% in the first phase in this option. This
option was developed using the vision of the NLP building and services expansion
for the Resource Libraries, i.e. that the north and south portions of the City would
contain roughly equivalent and complete library services. The 2002 bond measure
would cost $72.3 million; the 2010 bond measure would cost $28.6 million. The
City will need to identify $4.6 million in onetime costs to furnish the. new facilities,
and $4.2 million per year in ongoing staffing and operation/maintenance costs over
the next 11 years to fully implement this option.
Main Library: This phasing option includes 67% of the current building program
Phase 1 and 33% in Phase 2. This translates to an architectural design of an
approximately 44,000 square foot Phase 1 and an approximately 22,000 square foot
Phase 2.
The following programmatic components would be included in Phase 1:
Collections would increase by 19% or 23,000 volumes, as opposed to
36% or 45,000 volumes in the full implementation option.
75% of the local history area and staff lounge would be retained
compared to the original space plan. 75% or three of four self check out
circulation stations would be realized; 36 (of 48) or 75% of computers
throughout the building and two (of four) small group rooms will be
retained.
The large public meeting room, technology laboratory (room and 14
computers), homework center, caf6, designated quiet study area, Friends
of the Library administration and sorting areas (retains in-library book
sale area), drive up book drop, and a conference room (for joint use by
public and staff) would be postponed until the second phase.
Mitchell Park Library: This phas.ing option includes 74% of the current building
program in Phase 1 and 26% in Phase 2. This translates to an approximately 40,000
square foot Phase 1 and an approximately 14,000 square foot Phase 2.
The impact of the phaging would result in the following in Phase 1:
CMR:219:02 Page 8 of 17
¯Collections would increase by 53% or 60,500 volumes, as opposed to
105% or 109,500 volumes required to reach the Resource Library goal
for this facility.
¯Ten computers, instead of 14, will be retained in the Technology Lab;
50% of storage space, 75% of exhibit area, 90% of staff lounge, 66% of
group study rooms, and sufficient general seating throughout the building
and work staff workspace will be retained. In addition, the Friends of the
Library sales area has been retained, with storage area for the Friends and
library operations reduced 50-75%.
¯The large public meeting room has. been eliminated and is compensated
by the adjacent community room in the Community Center.
¯Two conference rooms (for joint use by public and staff), the quiet study
area and the drive up book drop have been postponed until the second
phase.
Pros: Two Bond Measures - in 2002, Children’s Library and Mitchell Park
Community Center, with reduced Mitchell Park Library and Main Library and a $5
million contributionto the Art Center project; in 2010, remainder of projects for
Mitchell Park Library and Main Library
¯Provides relatively equal Resource Libraries and service improvements to-
both North and South Palo Alto
¯Reduced cost may make a more attractive package to voters
Cons: Two Bond Measures - in 2002, Children’s Library and Mitchell Park
Community Center, with reduced Mitchell Park Library and Main Library and a $5
¯ million contribution to the Art Center project; in 2010, remainder of projects for
Mitchell Park Library and Main Library
¯It is very difficult to make each phase of a project work well
programmatically and functionally.
¯Phasing a project in this way creates additional costs.. In terms of design, the
work of the project architects is more extensive, and consequently more
expensive. There are additional costs to produce separate bid documents and
to bid two projects instead of one. There is the need to consider and
incorporate provisions in the design that will allow Phase 1 to operate as a
complete facility in case Phase 2 does not happen or does not happen for a
long time. Additionally, Phase 2 must be mostly designed while Phase 1 .is
being designed to ensure compatibility of the architectural, structural and
other building systems. If and when Phase 2 is funded, it may need to be
redesigned if there have been significantchanges applicable codes.
¯Construction costs to phase a project are more than if the project was built all
at once. This is due to the costs to mobilize the contractors’ forces twice
Page 9 of 17
instead of once and the necessity of having to demolish a portion of the
Phase 1 work in order to add on Phase 2. Escalation must also be factored
into the costs of Phase 2.
¯Certain building equipment and systems must be installed or constructed in
Phase 1 to be able to later accommodate Phase 2. However, if Phase 2 does
not go ahead, money will have been wasted in providing for additional
capacity that was not used/needed.
¯Effort and cost required to pass second bond measure.
¯Potential that second bond measure does not pass or is not put on a second
ballot
Option 4: Single Bond Measure in 2002 - Children’s Library, reduced Mitchell
Park Library and reduced Main Library, Mitchell Park Community Center and a $5
million contribution to the Art Center project
The fourth option reduces the Mitchell Park Library and Main Library .square
footage to amounts proposed by the LAC and detailed in a staff report to Council in
January (CMR: 125:02): 46,725 square feet at Mitchell Park Library and 53,200
square feet at Main Library, saving over 20,000 square feet total between the two
buildings as compared to the full NLP program amounts. There would be no
subsequent bond measures or building phases to achieve the full program square
footages. The estimated one-time cost of this option is $78.4 million, including
financing costs. The City will need to identify $3.8 million in one-time funding to
furnish the facilities and $3.8 million in ongoing staffing~ program and operation
and maintenance costs o.ver the next six years to fully implement this option.
The following programmatic components would be impacted by this option:
Main Library (80% of NLP program realized):
¯ Collections would increase by 23%, or 28,500 volumes, as opposed to 36% or
45,000 in the full implementation option.
¯Retains 90% of teen area; 75% of local history area; 35 (of 48) or 73% of
computers in building; two (of four) small group rooms; 45 computers (instead
of 56 throughout the building); 50% of storage space and 28% of space for
Friends of the Library (only the in-library sales area).
¯The technology laboratory (room and 14 computers), caf6, homework center,
and drive-up book drop window would be eliminated.
Mitchell Park Library (85% of NLP program realized):
¯ Collections would have space to increase by 135% over period of years, or by
96,292 volumes, as opposed to 155%, or 109,500 volumes required to reach the
Resource Library goal for this facility.
CMR:2.19:02 Page 10 of 17
¯Retains 90% of teen area; 50% of storage space; one (of two) conference rooms
for joint use by public and staff; 75% of exhibit area; 90% of staff lounge, the
Friends sales area and sufficient general seating throughout the building and
staff workspace.
¯The large public meeting room has been eliminated and is compensated by the
adjacent community room in the Community Center.
Pros: Single Bond Measure - In 2002, Children’s Library, reduced Mitchell Park
Library and Main Library, Mitchell Park Community Center and a $5 million
contribution to the Art Center project
¯Reduces construction expense (compared to Option 1) and therefore may be
more palatable to voters
¯Minimizes building footprints for Mitchell Park and Main Libraries
¯Allows projects to proceed with known plan
¯Makes efficient use of resources for planning and scheduling of library .design
and construction
¯Saves effort and cost of ~onducting second election
¯Attractive for voters "all over town"
¯L.owest cost to complete all projects ~¯Completes all projects per original schedule (no phasing, no second bond
measure)
¯Reduced size of Main and Mitchell Libraries creates fewer environmental
impacts, including less traffic, less parking, less energy usage
Cons: Single Bond Measure - In 2002, Children’s Library and Mitchell Park
Community Center, with reduced Mitchell Park Library and Main Library and a $5
million contribution to the Art Center project
¯Does not implement full NLP
Financing
The Long Range Financial Plan (LRFP) presented to Council in Fall 2001
(CMR:355:01) indicated that new revenues will be required to meet the costs of
new infrastructure projects or significant new program efforts. The LRFP included
a financing plan for rehabilitating existing infrastructure. Recent shortfalls in major
City revenue sources such as sales and transient occupancy taxes have caused staff
to revise future revenue projections and to initiate an expenditure reduction
program.
CMR:219:02 Page 11 of 17
One-Time Costs
The magnitude of capital costs presented in this report requires the City to debt
finance construction. The traditional financing mechanism for major, new public
capital projects is General Obligation (GO) bonds. Requiring two-thirds approval
by voters, bond prOceeds can be used only for capital expenditures.. The bonds
would be repaid through a new revenue source, an ad valorem property tax levied
on all property owners. The Palo Alto Unified School District (PAUSD) used GO
bonds to fund its "Building for Excellence" capital program.
The amount of the overall levy is dependent upon the principal amount (e.g. costs of
design, construction, and bond issuance) authorized by the voters for the projects
and the interest rate at the time bonds are issued. Attachment 1 shows the principal
amount for each of the options presented. Option 1 involves one vote or
authorization on total costs by residents and two bond issues given project
schedules; Option 2 include two votes and two bond issuances; and Option 3
includes two votes and three bond issues; Option 4 involves one vote and two bond
issues. Each time the City issues bonds it incurs financing costs. Levies on
individual properties are annually determined according to the amount of debt
service payments. Basically, a tax rate per $100,000 of assessed valuation (AV) is
determined to pay the annual debt service and each property is taxed accordingly:
In all.three options, a tax rate would be levied for the first issue and would increase
with each subsequent bond issue. Estimates per $.100,000 of valuationfor each
option are provided in Resource Impact section below.
The one-time costs of outfitting the expanded libraries with equipment and furniture
cannot be debt financed. It includes tables, chairs, computers, telephones,
audiovisual equipment, partitions, draperies, recreational equipment and other
fumishings and equipment with a useful life of less. than-the term of the bonds.
Staff has estimated the cost of fumishing each facility and has listed them in a
separate column in Attachment 1. The new fumishings and their importance in
inaugurating the .opening of each facility provide an ideal opportunity for private
fundraising. While funds for furnishings will not be needed until 2005 and later,
exploring private fundraising, building reserves through savings over the next five
years, or paying for these costs from a new revenue sourde are all possibilities.
Financing Ongoing Staffing and Operating Costs
Since bonds cannot pay for operating costs, another financing mechanism or
resource must be found to pay for the incremental staffing, program and collection,
and operating and maintenance costs. Both a short term and a long-term plan for
these costs are required.
CMR:219:02 Page 12 of 17
In the short term, one-time funding .in the amount of $2.9 million could be
reallocated from the Infrastructure Reserve to implement the immediate staffing
needs for library operations identified by the Simmons report. The money from the
Infrastructure Reserve represents funding identified in the original Infrastructure
Management Plan for rehabilitation of library facilities. This would require a
change in the Council policy for use of the Infrastructure Reserve. During this
short-term period (July 2002 to June 2004), staff would pursue the following
strategy in order to identi~ a long-term financing plan for library staffing and
operations:
¯Identification of offsetting expenditure reductions in other General Fund
services. This will require a careful prioritization of program priorities by the
community, Council, and staff. This effort could be folded into the forthcoming
staff initiative responding to Council direction to reduce City expenditures.
¯The General Fund is subsidizing Storm Drain operations at a cost of around $1.0
million annually. Should there be a successful effort at increasing storm drain
charges in the Spring of 2003, funds would be freed to partially staff and operate
the new library facilities.
If a funding gap still exists after the above strategies are employed, new revenue
sources such as a .parcel tax can be pursued. A parcel tax was recently passed by
residents for PAUSD to pay increased teacher salaries. This tax is basically a flat or
equal tax on all property owners and is not based on a property’sassessed value.
Parcel taxes, which must be passed by a two-thirds vote, are generally passed for a
specific period of time, have to reflect rising costs due to inflation, and are for
special purposes such as library, fire or park services.
Other potential new revenue sources that have been discussed for other General
Fund purposes are an increased Transient Occupancy Tax (each 1 percent increase
would generate around $.7 million given current revenue levels) and a new
Business License Tax (revenue levels dependent upon type and magnitude of tax).
It should be noted, however, that these taxes may be needed either as a backfill for
other potential revenue losses such as a structural change in the City’s sales tax base
(departure of automobile dealerships) or a State takeaway (Vehicle License Fee
reduction); or to pay for other new General Fund efforts such as traffic
improvements or a Police Building. ..
Other Financing Options
Another alternative is a different type of new tax that can fund both capital and
incremental operating costs. This financing vehicle is called a Community
Facilities District (CFD) or Mello-Roos District. Bonds issued by the CFD can
.finance facilities as well as fund ongoing services. A CFD tax to pay bonded debt
CMR:219:02 Page 13 of 17
service is considered a special tax that must be approved by a two,thirds vote of
registered voters or landowners within the district. This financing vehicle is
typically used in new developments where the cost of providing, roads, sidewalks
and parks by a developer are paid by new property owners. It has, however, been
used in older jurisdictions.
Instead of the ad valorem tax method GO bonds use, Mello-Roos bonds are payable
from and secured by special taxes, which are levied upon the property in the district
according to the rate and method of apportionment approved by the voters in the
district. The tax can be as simple as a flat parcel tax or can be based on a more
complex set. of factors such as density of development, square footage of
construction, acreage or zoning. Jurisdictions typically use more complicated
formulasto allocate taxes more equitably than under a parcel tax.
However, from public awareness and implementation perspectives, GO bonds are
more understandable and more efficient than Mello-Roos bonds. The latter bonds
may have more flexibility in developing a more equitable distribution of taxes, but
that benefit may well be offset by the complexity of agreeing on such a
methodology.
Staffing Requirements
Staff has developed a preliminary staffing approach in order to provide general
costing numbers for the purpose of this report. This staffing approach will require a
great deal more review and consideration, n6t only by staff but by the Library
Advisory Commission. The approach uses the NLP as the vision, i.e. that full
library service is provided, somewhat equally, through Resource Libraries in the
north and south areas of Palo Alto; and Neighborhood Libraries will transform into
popular reading libraries, staffed with paraprofessionals. In developing the short and
long term plans, the focus was first on the critical positions, a subset of the Baseline
Staffing Plan identified in the Simmons report; second on the. remaining Baseline
Staffing Plan positions; and finally on those that directly support expanded NLP
programs.
Short term plan: .July 2002 to June 2004
Between July 2002 and November 2002, the most critical staffing deficiencies
could be addressed immediately and without additional expense by closing each
library one day per week (except Terman Park, which has minimal service hours of
23 per week). Days of closure would be staggered so that four or five libraries
would remain open each day (except Sunday, when three would be open). This
would reduce Baseline Staffing requirements by 40%, from 19 to 11.5 FTE. "
CMR:219:02 Page 14 of 17
If the bond measure is successful in November, additional critical positions would
be phased in to begin implementation of the Neighborhood Library model,
improving staffing for public service and collection development oversight and
Children’s Library staff would be deployed to other libraries while it is closed
during construction. Staff estimates on a preliminary basis that the expense would
be $635,000 for a total of 7.25 employees for the 18-month period. This is the
period in which funding could be made available using the Infrastructure Reserve
...... (discussed above).
Long term plan-July 2004- 2012/13
Staff is recommending a long-term approach which gradually increases staffing
levels at all six libraries over an approximately six- to ten-year period, as expanded
space becomes operational. /i~ plan would take full advantage of the fact that
construction of expanded library buildings will occur without overlap but
continuously in this order: Children’s Library, Mitchell Park and Main Library.
Staff would be deployed at libraries which are closed during construction to other
libraries, thus postponing the need to increase staffing levels as long as possible.
The implementation of Neighborhood Library service concepts would occur
incrementally, as experience with the new model is gained, one branch at a time.
Staff’s recommended long-term plan would, provide alternatives to adding staffing
by adjusting service hours. The NLP .recommends service hour increases 31%
higher than today’s. Staff’s approach would represent a maximum hours increase of
9%. This plan would add 41 positions over the six- to ten-year period instead of 55.
The plan can be flexible and address whichever construction option Council selects.
Further review of the preliminary plan developed by Library staff for purposes of
cost estimating for this report is required by the Administrative Services and Human
Resources Departments. The Library Advisory Commission will need to carefully
review the draft plan and work with staff prior to a recommendation coming to the
Council before July.
RESOURCE IMPACT
Resource impacts to property owners and the City are chiefly dependent on the
option adopted, the ballot measures or phases approved by the voters in Options B
and C, and the financing vehicle(s) that are selected to fund operating costs. Total
estimated capital and operating costs for all four options are presented on
Attachment 1. All costs have been inflated by 3.5 percent per year up to the year of
implementation.
Based on the assumption that GO bonds will be used to fund capital expenditures, a
taxrate analysis per $100,000 of assessed value for property owners is provided
below. The analysis is shown by option and by bond issue within each option.
CMR:219:02 Page 15 of 17
City of Palo Alto General Obligation Bond Financing Program
Tax Rate Analysis
Option
2
3
4
Year of Issue
2003
2005
2005
2010
2003
2005
2010
2003
2005
Principal of
Bonds
$50,810,000
$40,710,000
$50,810,000
$48,790,000
$43,740,000
$28,590,000
$28,654,000
$47,250,000
$31,140,000
Project
Phase
Initial
Final/Total
Initial
Final/Total
Initial
Middle
Final/Total
Initial
Final/Total
Estimated Average Annual
Tax per $100,000 AV
Cumulated
$29~00
$49.00
$29.00
$54.00
$25.00
$38.00
$52.00
$27.00
$42.00
Assumptions:
*all bonds are assumed to have a 30 year amortization from issuance date
¯all bonds issued in 2003 are estimated at an average interest rate of 5.55 percent
(.5 percent over current market for AAA bonds)
¯all bonds issued in 2005, 2010 are estimated at an average interestrate of 5:84
percent
In Option. 1, voters would vote once and approve or disapprove an authorization of
$91.5 million. Since two series of bonds are planned, one in 2003 and one in 2005,
property.owners would pay an estimated $29 per $100,000 of AV in 2004-05 and
another $20 in 2005-06, for an estimated average annual payment of $4.9 per
$100,000. Hence, a house with an AV of $300,000 would pay $147 while a house
with an AV of $700,000 would pay $343.
In Option 2, two elections would occur, one in 2002 and one projected for 2010.
Two series of bonds would be issued. A favorable vote in the first election would
result in an estimated $29 per $100,000 of AV in 2004-05. Passage of the second
bond measure in 2010 would result in an additional tax of $25.
CMR:219:02 Page 16 of 17
Option 3 also results in 2 elections, but has three bond issues. Under this option,
there would be a phasing of projects over ten years. Assuming voter approval in
both elections, Option 1 and Option 2 have the same result in terms of community
facilities built, but would cost an estimated $91.5 and $100.9 million, respectively.
If all bond .issues are approved, property owners could expect estimated average,
incremental tax increases of $25, $13, and $14 for a total of $52 per $100,000 of
AV.
In Option 4, there would be one election and two bond issues. The total
authorization, if approved, would equal $78.5 million. Property owners could
expect estimated average, incremental tax increases of $27 for the first bond issue
and $15 for the second, for a total of $42 per $100,000 of AV.
It is important to understand that each bond issue has an assumed amortization of 30
years. Hence, the final phase amount shown in the table represents the maximum
estimated average amount when all bond payments are made simultaneously.
PREPARED BY:Emily Harrison, Assistant City Manager
Bob Morris, Senior Project Manager
Mary Jo Levy, Director of Libraries
Joe Saccio, Deputy Director of Administrative Services
CITY MANAGER APPROVAL
-Frank Benest, City Manager
Attachment 1 - Community Facilities
CMR:219:02 Page 17 of 17
Opzz~
o
°°°°° N ~°°°°
0 0 0 0 0 0 0 00 0 0 0 0 0 0 0
0 0 (::)0 0 0 0 0
0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0
~0 0 0 0 0 ~ 0 0 0
~-~0 0 0 0 C:)0 0 0
~0 0 0 0 0 O O ~0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 000000000 0 0 0
......o_ o°.
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 {=~
_I -I
o 0 0
o 0 0
uJ z
.~_
o_No ,,,I-, ~_0
o "