HomeMy WebLinkAbout2003-12-16 City Council (2)City of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
ATTENTION: FINANCE COMMITTEE
FROM:CITY MANAGER DEPARTMENT: ADMINISTRATIVE
SERVICES
DATE:DECEMBER 16, 2003 CMR: 540:03
SUBJECT:2002-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM
PROJECTS STATUS REPORT
This is an informational report and no Council action is required.
BACKGROUND
This report provides information on the status of the City’s Capital Improvement Program
(CIP) projects as of the end of fiscal year 2002-03. In the attached matrix (Attachment A),
all City departments have submitted information on their projects and commented on any
issues that might cause a change in the scope or timing of the projects. Information in this
report is intended to keep Council abreast of progress on all CIP projects that were open at
the beginning of the 2002-03 fiscal year and on those projects that were added or completed
during the same fiscal year.
DISCUSSION
The attached matrix categorizes CIP projects into minor projects (projects which can be
completed within a one-year period) and multi-year projects (projects which have multi-year
budgets and!or complex implementation schedules with identifiable phases). The project
status portion of the matrix identifies the phase the project was in at fiscal year-end.
Information on phases is intended to give Council a perspective on how much progress was
made on a project. Three distinct phases are utilized, as follows:
CMR: 540:03 Page 1 of 3
Phase:Activities:
Pre-Design
Design
Construction
o Preparation of feasibility study
o Development of a master plan
o Definition of a project scope
o Preparation of an Environmental Impact Report
o Hiring a design consultant
o Completion of project design
o Soliciting bids or proposals
o Acquisition of major equipment
o Installation
o Implementation of a project
The comment section of the matrix provides Council with information clarifying the status of
certain projects.
In the attached matrix, projects are listed by department for the General Fund and by fund for
the Enterprise and Internal Service Funds. Within each department or fund, the projects are
ordered by project number, which includes the year of Council approval (year of approval is
shown by the second two digits of the 5-digit project number or the first two digits of a 4-
digit project number). The matrix also includes information on the total or accumulated
budget for projects, the remaining budget as of the beginning of the fiscal year, and the fiscal
year expenditures through June 30, 2003 including commitments (encumbrances).
The matrix does not include "continuous" projects. These projects, such as water meter
replacement, have no definitive beginning or end dates and receive ongoing funding to reflect
continuing replacement cycles or commitments. During fiscal year 2002-03, progress was
made on all of the City’s "continuous" projects (Attachment B).
At year-end, all completed CIPs (after settlement of encumbrances) and CIPs where no
activity is planned in the near future were closed and the remaining balances transferred to
the Budget Stabilization Reserve for General Fund projects; to Retained Earnings for Internal
Service Funds; and for Utility Fund projects, to the appropriate Rate Stabilization Reserve.
CMR: 540:03 Page 2 of 3
A separate analysis of all Infrastructure Management Plan (IMP) projects has been prepared.
At June 30, 2003, the status of IMP projects was:
Total Adjusted Budget FY 2002/03
Less:
Actual expenditures as of 6/30/03
Encumbered Balance as of 6/30/03
Projects not yet started
Projects in design
Projects to be closed as of 6/30/03
Projects delayed
Project bids were too high - to be rebid or
project scope adjusted
Project needed larger amounts of funding
Projects ongoing
$18,046,300
(6,408,299)
(3,220,766)
(341,800)
(4,200,174)
(563,837)
(1,438,872)
(367,166)
(299,354)
(1,206,032)
$0
ATTACHMENTS
Attachment A:
Attachment B:
PREPARED BY:
Year-end Capital Improvement Projects Status Matrix
List of Continuous Projects
Staff Accountant
F. JACK(]~ AGUST~
Staff Accountant
DEPARTMENT HEAD APPROVAL:
CITY MANAGER APPROVAL:
CARL YE¢S - --"
Director, ldministrative Services
"- " ~LY HARRISON
Assistant City Manager
CMR: 540:03 Page 3 of 3
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
ADMINISTRATIVE SERVICES DEPARTMENT Attachment A
10106 Enterprise Backup
Solution
10107 City Network
Hardware
Redundancy
10108 Systems Management
10109 Acquisition Crime
Analysis Soft\vare
10110 Map Printing Plotter
10111 Vehicle Routing
Application
10112 IT Disaster Recovery
Plan
i10225 Cable Television
Broadcasting
Equipment
Minor $70,000 $70,000
Minor $57,500 $0 $0
Minor $320,000 $149,294 $137,141
Minor $75,000 $45,173 $45,150
Minor $50,000 $2,414 $2,200
Minor $50,000 $26,050 $26,050
Minor $270,000 $270,000 $0
Minor $50,000 $36,014 $1,178
$0 $70,000 Design
$0 Complete
$12,153 Design
$23 Complete
$214 Complete
$0 Complete
$270,000 Design
S34,837 Construction
JunO5
Dec 04
Jun 05
Jun 05
Evaluating vendor solutions and awaiting
the completion of the Computer Room
remodelling.
Tolal budget of $57,500 transferred to
CIP #10216 thru a FY 02-03 BAO.
Testing software is needed however, this
cannot be pursued until City. SAP is
completed.
Evaluating strategic approaches to
disaster recovery.
Continuing equipment improvements for
the cable booth.
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
ADMINISTRATIVE SERVICES DEPARTMENT
19516 Permit Information Multi-Year $890,000 $264,416
Tracking System
$105,761 $158,655 Construction Iun04 Code enforcement is being implemented.
Various other departments still need to be
addressed. This funding is also for the
Accela automation software license. As
the permit tracking needs to be assessed
for replacement by SAP functionality, the
;oftxvare licensing and funding for such
may need to be extended further.
19711 Citywide Network Multi-Year $410,000
Improvements
$0 S0 $0 Complete Adjusted budget of $26,901 transferred to
CIP #10216 thru a FY 02-03 BAO.
0021 / Ne,v Phone System Multi-Year $730,000 $728,968
2201
$4,223 $724,745 Design Jun 06 Continuing evaluation of developing
technolo~. A test site has been installed
at 1003 Elwell Court. Also researching
an Open System IP PBX.
0027 Renovations and Multi-Year $800,000 $754,004
Up~ades to Data
Management
0212 DesktopAutomation Multi-Year S55.000 $55,000
S744,629 $9,376 Complete
$683 $54,317 Design Jun 04 Currently evaluating desktop automation
software for web updates.
0213 Institutional Network Multi-Year $I,000,000 $1,000,000
(I-Net)
$40,000 $960,000 Construction Jun 06 In preparation to connect to the l-Net the
City made fiber optic connections to nine
sites: Fire Stations 1-5, Cubberley,
Mitchell Park, Lucie Stem and the Main
Library/Art Center campuses. After a
delay in 2003, Comcast is nearing
completion of the I-Net. Once completed,
the implementation phase of I-Net \~11 be
initiated in the first half of 2004. The
implementation phase requires the
~urchase of additional 1-Net equipment.
0214 eGov - Web
Infrastructure and
Application
Multi-Year $400,000 $354,166
0215 Cib~vide GIS Data Multi-Year $768,530 $625,248
Infrastructure and
Applications
S0 $354,166 Pre-design Jun 06
$305,006 $320,242 iConstruction Jun 04
Currently laying the foundation for eGov
with ERP and some other related projects.
0216 Enterprise Resource Multi-Year $3,059,726 $2,966,908
Planning
12200 Acquisition of New Multi-Year $150,000 $150,000
Computers
$2,964,369 $2,539 ~’onstruction Mar 04
$106,675 $43,325 Construction JunO4
FY 02,03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
COMMUNITY SERVICES DEPARTMENT
19901
19905
10113
10224
10301
10305
Robles Park Irrigation $649
Improvements
Cubberley Athletic Minor $30,000 $16,267
Field Irrigation
El Camino Median Minor $1,527,000 $1,449,000
Landscape
Children’s Theatre Minor $210,000 $210,000
Light & Sound
Systems Upgrade
Wildhorse Valley Minor $160,000 $160,000
Vehicle Bridge
Replacement
Lucie Stem Minor $45,000 $45,000
Community Theatre
Stage Floor
Replacement
$646
$1,840
$15,380
$1,244
$101
$o
$3
514,427
$1,433,620
$208,756
S159,899
545,000
Complete
Complete
Design
Construction
Design
Design
Jan 04
Oct 03
Sep 04
Jan 04
Phase 1 median landscaping.
19414
19418
"1’9801
19803
19812
19910
19911
Park Irrigation and
Backflow
Improvements
Multi-Year $1,708,000 $112,431
Libmr3’ Automation Multi-Year $1,286,751 5712,519
Service
School Site Irrigation Multi-Year $691,000 $203,491
Mitchell Park Multi-Year $2,382,644 $1,350,141
Facilities
Arastradero Preserve Multi-Year $339,800 $261,897
Gateway
Community Theater Multi-Year S891,000 $69,934
Renovation
Cubberley Theater Multi-Year $120,000 $3,280
Improvement
$107,441
S43,331
$46,063
$478,573
532,786
$67,227
$3,279
S4,989
$669,188
$157,427
$871,568
$229,110
52,708
$1
Construction
Design
Design
Design
Design
Complete
Complete
Jan 04
Jun 04
Sep 04
Nov 04
Jun 05
Jordan Middle School
Phase 2
Final construction drawings
are being prepared.
FY 02-.03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
COMMUNITY SERVICES DEPARTMENT
10001 Park Trails Multi-Year $88t,000 $648,433 $369,783 $278,650 Design Jun04 Phase 2
10002 Open Space Lakes & Multi-Year $110,000 $21,739 $21,739 $0 Complete
Ponds Maintenance
10003 Bayland Parking and Multi -Year $897,000 $679,321 $60,272 $619,050 Design Nov 04 In bid process.
Site Improvements
10009 Medians, Islands and Multi-Year $468,000 $439,466 $9,987 $429,479 Design Jun 05 Re-landscaping all medians
Planters Renovation and island on San Antonio
Projects Road.
10010 Park Facilities Multi-Year $1,755,450 $646,989 $144,811 $502,178 Design
Improvements
New play.L, rounds at three
parks in design phase with
an estimated completion date
Dec 03. Baylands Athletic
Center electricals design due
for completion Apr 04.
10114 Community Services Multi-Year $334,000 $319,217 $19,863 $299,354 Design Feb 04 Main Libra,, and Art Center.
Facilities Lighting Lucie Stem Parking Lot and
Enhancements Golf Course Parking Lot.
10218 Palo Alto SOFA Park Multi-Year $236,000 $221,616 $1,365 $220,251 Design Dec 04 Interim park construction.
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
FIRE DEPARTMENT
10211
10302
~rSCBA
Apparatus Floor
Lockers for Fire
Stations #1,3,4,5,7 &
Additional Fire
Frequency
19312 Fire Communications
Computer Systems
10015 Fire Station Driveway
Modification and
Wstallation of
Oil!Water Separator
System
$40,000
$40,000
$95,000 $95,000
$15,413
$0 Complete
$40,000 Ongoing ~Mar 04
Jan 04 Channel partially operational.
Additional equipment in bid
Multi-Year $485,050 i $196,383
Multi-Year $171,000 $3,975
$185,223
$3.857
$11,161 Construction Feb 04
$119
Vendor work scheduled Jan 04.
Project deferred until FY 034)5 due
to the bottom line expenditm-e
reduction plan.
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND NAME: GENERAL FUND/STREET IMPROVEMENT FUND (SIF)
PLANNING DEPARTMENT
19524 Bikeway System Minor $51,200 549,600
Improvement (SIF)
10116 Sheridan Sidewal "ks Minor $31,000 $31,000
10205 El Camino Re~/Minor $61,000 $61,000
Vantura Avenue Traffic
Si~anat
0206 Traffic Sig.nal San Minor S280,800 S280,800
Amonio/Hwy 101
10223 Mastar Schematic Minor $288,000 S150,333
Design
$2,636
SO
$0
$150,333!
$31,000
$61,000
S280,800
sol
Design
Closed
Desi_ma
Consti’uction
Pre-Design
Dee 05
Dec 04
Mar04
Reappropriation in the amount of
$49,000 was approved by Council
an Janua.D" 13,2003. Projects will
be implemented in conjunction witl"
Bicycle Plan recommendations.
No antivity for more than 2 years,
Caltrans is the lead agency for this
project. Caltrans indicated that the
will fund the project in FY 04-05.
Caltrans is the lead agency for this
project. City’s share for this project
is estimated to be $280,800. City
will execute cooperative agr_ eement
with Caltrans in Aug 03 who will
implement this project.
Draft Plan was completed and
endorsed by the Planning and
Transportation Commission in
Mar 03. A study session with the
City Council will be held in early
2004 Cattrans Distinct 4 has
l applied for _m-ant funds to install
improvements at Stanford Avenue
and El Camino Real consistent with
ithe 6-lane option in the Draft Plan
19310 ]Embarcadero Pedestriar
i Bike Bridge Path
Extension (SIF)
El Camino Real
Improvements (SIF)
Multi-Year $2,024,555 $1,741,391
Multi-Year $212,750 S 17,745
$1,232,141
$16,218
$509,250
S1,527
Construction
Complete
Mar04 The project is being managed by
Public Works Engineering.
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND NAME: GENERAL FUND/STREET IMPROVEMENT FUND (SIF)
PLANNING DEPARTMENT
19813 School Commute Safety Multi-Year $300,000 S141,364
Improvements (SIF)
19814 Residential Arterial
Traffic Calming (SIF)
10026 Local and
Neighborhood
Collector Street Traf~c
Calming Program
10117 El Camino
Real/Churchill Avenue
$24,501 S116,864 Design Dec 04 The remaining projects include
into-section modifications at
Stanford Avenue and El Camino
Real which must be coordinated
with Calmms.
Multi-Year S125,000 $16,029 SO S16,029 Complete
Muhi-Year $320,000 S287,451 $227,245 $60,206 Construction TBD Since the formal start of the
Neighborhood Traffic Calming
Program in Apr 01, 13 projects have
been initiated, two of which are
~hase two of the original project.
Five of these have been on collector
streets and the remainder on the
local streets. Trials have been
Implemented for 7 of the I l
projects. Two trials have been
successfully completed and are
waiting for permanent approval
Two trial were not successful. One
project is nearing a possible trial ant
one project is just starling Three of
the eleven projects ended with no
action. Several other qualified
projects are on the implementation
waiting lisL
M ulti-Yeas S 100,000 S 100,000 SO SlO0,O00 TBD Project has been postponed
indefinitely due to the bottom line
expenditure reduction plan
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
POLICE DEPARTMENT
10217 Public Safety Mobile
Data Computer
19109 Police Computer
Systems
19913 Police Records
Management
Minor $75,000
Multi-Year $1,133,762
Multi-Year 5526,435
$75,000
$34,004
$375,518
$0
$338,183
$75,000 Construction Jan 04
534,004 Complete
$37,335 Construction Jan 04
FY 02~3 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
PUBLIC WORKS DEPARTMENT
19820 Public Safety Building Minor $765.028 $343.158
10004 Dowmown Library Roof Minor 5103.000 $24.680
Replacement and Exterior
10005 MSC Bui|ding A. Emergency Minor $100.000 $89,803
Generator Replacement
10007 Art Center Plumbing Minor $32.000 $31.966
Replacements
10008 Mezzanine Heating - Ventilation. Minor $100,000 $84,494
Air Condition (HVAC) System
improvements
1~17 Adobe Creek Pedestrian/Bike Minor $100,000 S93.446
Undercrossing and Highway 101
Pedes~aofBike Overpass
Lighting Improvements
10018 Sand Hill Road Bridge Minor $83,000 $78,475
’~101 " Children Theater Extarior Minor $45,000 $44.931
10119 Baylands Bike Trail Minor $100.000 $I00.000
Replacement
~’0204 " ILibrary Master Plan Project Minor $977,550 $157,162
iDefinition Study
10208 Miranda Avenue Street Minor $100,000 S0
improvements
10219 Fire Station Seismic Evaluation Minor 5125,000 S105.818
10220 Golf Course Maintenance Shop Minor $60,000 $58,559
Improvements
~ 0226 Mitchell Park Library Expansion Minor $85.000 $83,250
10304 Roth Building Wings Demolition Minor $1,235,350 51,235,350
10306 Animal Service Protective Minor $160,000 SI60,000
Holding Kennels
$342.258
$0
$76,035
S5,553
S0
$0
$7,055
$23,526
536,437
5126,087
$0
$46,001
$58,559
$83,151
$197,687
5900
$24,680
$13,768
$26,413
$84,494
$93,446
$7t,420
521.405
$63.563
$31,075
$o
$59,817
$o
$99
$1,037,663
$160.000
Design
Complete
Complete
Complete
Complete
Complete
Design
Complete
Complete
Complete
Complete
Complete
Complete
Complete
Closed
Apr 04
Sep 04
Feb 04
Conceptual designs, site evaluations and
funding options will be presented to
Council for direction.
Project will bid and ready for construction
after June 15, 2004. Due to Fish & Game
regnlations there is a small window of time
that we can do construction in or near San
Francisquito Creek.
Staff negotiated an agreement with
Summerhill Homes whereby Summerhill
will do the demolition of the Roth Building
wings.
This project will be incorporated into
PE-04014 - Animal Shelter Expansion and
Renovation
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
PUBLIC WORKS DEPARTMENT
185081 Public Buildings Smactura];
19906 Current Projects are College
Terrace and Children’s Library,
MSC Study
Multi-Year $6,958,297 $563,992
18918 Harbor Improvements Multi-Year $2,139,000 $115,093
19102 Arastradero Lake Dam Multi-Year 5280,000 $35,313
19406 Rinconada Pool Site Multi-Year $1,755,000 $44,599
Improvements
19505 Revenue Collection Remodel Multi-Year $85,000 $57,470
19512 Civic Cemer Plaza Multi-Year 5250,000 $178,084
Waterproofing
19514 Facilities Roof Replacemants:Multi-Year $1,128,000
Mitchell Park Comm Ctr. &
Library, Station 5
$174,299
6900 Downtown Parking Structure Multi-Year $39,986,753 535,881,68I
Indirect Cst P
19608 Downtown Urban Design Multi-Year $1,220,349 $105,149
Improvements
16624 Golf Course Improvements Multi-Year $6,284,228 $105,257
19704 Traffic Control Safety Devices Multi-Year $320,000 $284.161
$12,305 $551,688 Pre-design ]un 04
$43,758 $71,335 Complete
$0 $35,313 Complete
$35,004 $9,595 Complete
$56,727 $743 Complete
5168 5177,916 Design Dec03
$0 $174,299 Complete
$27,894,101 $7,987,579 Construction Dec03
$442 5104,708 Complete
$0 $105,257 Complete
5188,175 $95,986 Complete
Staffhas requested that CIP #18508 be
closed and has requested new individual
projects be opened for College Terrace and
Children’s Library in 03-05 Capital
Improvement Project budget process.
CIP #19906 is in pre..design phase.
Feasibility study is in prograss and once the
study is complete, findings and
recommendations will be presented to
Council.
Mandatory monitoring required.
Staffwill hire additional consultant to
conduct further investigation and analysis ir
order to make recommendations for future
repair and seek alternatives to a costly
replacemem
Project consists of CIP numbers - 19530,
10122, 10123 and 10124
Phase 1 complete.
19707 Fire Station Emergent’Multi-Year $415,000 5369,148
Generator Replacement
19815 Arastradero Rd. Bike Lane Multi-Year 5455,000 5353,349
Improvements (SlF)
19907 San Marco Drive Bridges Multi-Year $ I 18,000 $ t 04,567
19922 3rd Fir - Civic Center Multi-Year $481,934 565,413
5356.t00 $13,048 Complete
$338,101 S15,248 Complete
50 $104,567 Construction Jan 04
S0 565,413 Complete
Fit).’ of Menlo Park staned construction in
Fall 2003
10
FY 02~3 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
GENERAL FUND
PUBLIC WORKS DEPARTMENT
’10923 Page Mil!Pdanover Multi-Year $850,000 $776,696
’10006 Roofing Replacement Multi-Year $180,000 583,567
10019 Inspection and Testing for Multi-Year $75,000 $10,377
Hazardous Materials
10020 Office Space Renovation and Multi-Year $882,934 $143,052
Reallocation
10102 Civic Cantar In frastructure Multi-Year $1,372,000 $1,317,986
lmprovemants
10103 Electrical Systems lmprovement~ Multi-Year $115,000 $114,697
$30 $776,666 iDesign Jun 04
$323 $83,244 !Ongoing ~ar04
$0 $10,377 Complete
Staffis finalizing design and will bid in
Spring 2004. Construction funding is
budgeted in FY 0405.
Project delayed due to issues with
Purchasing that are now resolved. Projects
to be completed in FY 03-04 are the
Baylands Interpretive Center, Baylands
Athletic Center, and Lucie Stern
Community Theatre Scene Shop
10104 Fire Shafion Improvements Multi-Year $174,000 $174,000
10105 Lucie Stern Community Center Multi-Year $5t,000 $50.975
Improvements
10121 Homer Avenue Undercrossing Multi-Year $2,800,000 $2,396,958
10210 New Vehicles Multi-Year $190,000 $29,823
5113,731 $29,321 Ongoing Dec03
$309,945 $1,008,041 Design Jan 04
$12,087 $102,611 Ongoing JunO4
$4,000 $170,000 Design Dec 04
$0 $50,975 Design Mar04
$216,088 S2,180,870 Design Dec03
$0 $29,823 Complete
Sixth floor renovation will be completed in
FY 03-04.
Currently working on design phase for the
elevator upgrades.
Rinconada Pool Boiler replacement and
Park restroom electrical upga’ades will be
completed in FY 03-04.
Project combined "~,’ith seismic upgrade of
fire stations.
Project re-assigned to Public Works
Engineering then returned to Facilities
Division due to staffing changes.
Design completed. Construction conh--act
will be awarded in Jut 03.
10222 Facility Interior Finishes iMulti-Year $100,000 $99,100
~0300 Foothills Park Interpretive Multi-Year $20,000 $20,000
Center Mechanical Upgrades
$34,700 S64,400 Construction Dec 03
$5,182 S14,818 Design Dec03
Project delayed due to Purchasing issues
that are now resolved. Sixth floor
renovation will be completed in FY 03-04
Design completed. Contractor selected.
Contract documents being prepared.
11
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
INTERNAL SERVICE FUND
GENERAL FUND
PUBLIC WORKS DEPARTMENT
10022 1 MSC Fuel Sturage Tank/Svc Minor $900,000 $740,350
81101 Island Replacement
10023 1 MSC Equipment Washing Minor $300,000 $274,214
81102 Facility Up_m’ade
81100 MSC Equipment Maintenance Minor
Facility Mezzanine Storage Area
$85,000 $78,000
81105 Wireless Vehicle Management Minor $25,000 $25,000
System
181106 Fuel Storage Tanks Up_made Minor $25,000 $25,000
19205 Fuel Tank Storage/Upgrade Multi-Year
19521 Wireless Vehicle Management Multi-Year
System
$37,568
$36,699
$65,740
521,992
$0
$702,782 Design Sep 04
$237,514 Design Sep 04
$12,260 Design Apt04
$3,008 Construction
$25,000 TBD
5291.000 550,062 SO S50.062 TBD
5205.000 $27.711 S23.385 S4,327 Construction Jun04
Design complete. Permitting process
delayed the project. Bid for construction by
Dec 03.
Design 50% complete. Major changas are
required as original plan for washwater
treatment is not feasible. Bid for
construction by Jan 03.
Design 50% complete. Permitting process
delayed the project and required major
additions to scope. Re-design will be
completed by Dec 03.
Stationary infrastructure is in place. Vehicle
outfitting is ongoing.
Project on hold until MSC Fuel Storage and
MSC Wash Facility are bid for construction.
Will purchase fixed components by Dec 03.
Project on hold until b, tSC Fuel Storage and
MSC Wash Facility are bid for constroction.
Will pm chase fixed components by Dec 03.
Stationary. infrastrocture in place. Vehicle
outfitting is ongoing.
81103 GolfCourse Equipment Multi-Year $145,000 58t.849 $78,590 $3,259 Complete
Replacement
:81104 New Vehicles Multi-Year S208.000 $208.000 5161,538 $46A62 Design Jun 04 All vehicles have been delivered, however.
one did not fit the intended application.
Vehicle will need to be re-ordered.
12
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
~UND NAME: ELECTRIC FUND
DEPARTMENT NAME: UTILITIES DEPARTMENT
$350,002
Replacement
0125 New Vehicles ¢linor $149,60~
0121 Natural Gas Back-Up ¢Iinor $4,982,739
Generator
0216 New Vehicles dinor $30,00C
$20,761
$521
$605,431
$1,08C
$0
$0
$359,969
$o
$20,761 Complete
$521 Complete
$245,462 .Construction
$1,08~2 Construction
Ju104
Ju103
Construction complete except for
metering and SCADA installation.
9250 Alma St 12KV Addition Aulti-Year $1,640,00~
9904 East Meadow UG Systems Multi-Year $400,0013
Rebuild
9916 Fiber to Home Trial Multi-Year $1,005,00~
9611 Embarcadero/Middlefield Multi-Year $5,360,00(3
UG Conversion District #37
9804 Oregort/Colorado/Cowper Multi-Year $2,790,0013
UG Conversion District #38
9901 Stanford West Under~ound Multi-Year $ !,700,0013
Extension
9902 Stanford Shopping Ctr 4- Multi-Year $500,000
12kV Conversion
$49,376
$6,932
$19,537
$582,18C
$2,554,677
$214,336
$93,105
$0
$0
$2,000
$15,184
$308,691
$1,2311
$49,376 Construction
$6,933 Complete
$17.537 Complete
$566,996 Complete
TBD
$2,245,986 Consmaction Dec. 04
$213,105 Construction
$93,105 Complete
Jul 03
Project is complete pending decision
on Alma Substation relocation.
Design complete. Construction on hold
due to SBC.
Construction complete except for the
senior housing complex.
13
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: ELECTRIC FUND
DEPARTMENT NAME: UTILITIES DEPARTMENT
Stanford Park UG Cable
Rebuild
0006 Park Boulevard Substation Multi-Year $2,755,0013 $2,618,083
Bus Re-arrangement
0010 City/pacs/Syst Upgrade Multi-Year $190,00(3 $163,748
Electric Vehicles
0103 Underground Multi-Year $ 1,000,00(]$975,486
Cable/Equipment
Replacement
0115 West Bayshore UG System Multi-Year $450,00C $214,783
Rebuild
0116 Downtown Street Light Multi-Year $579,00C $511,233
System Upgrade
0117 Upgrade Traffic Signal Multi-Year $1,905,00($1,878,954
Control System
0102 North/South Hampton UG Multi-Year $1,700,0(E $1,578,491
System Rebuild
0209 Baylands Underground Multi-Year ]$500,00C $499,88~
0210 SCACA System Upgrades Multi-Year ]$400,00($200,37C
0211 Electric Utiliw GIS Data Multi-Year I $162,50C $146,625
0305 Sherman/El Camino/Page Multi-Year $95,01X $95,00C
Mill/Park UG Conversion
District #39
0313 Utilities Estimating System Multi-Year $250,00~$250,00C
0314 Edgex~od Drive Multi-Year $50,00($50.00C
Underground Conversion
District #40
$152,222
$~
$178,97~
Consuxlction
$2,465,861 Construction
$163,748 Complete
$796,510 Complete
First two phases are complete. Third
Design complete. Construction
contract has been awarded.
$210,747
$430,32(
$205,16~
$699,394
$44,77~
$84,01(
$43,72~
$7,76~
Jul 05
Dec 04
$4,036 Construction Jul 04 Construction complete.
$5-~
$80,913 Complete
$1,673,79~3 Construction Jun 04
$879,097 Construction Dec 03
$455,107 Construction Dec 03
$116,36~3 Construction Jul 04
$102,897 Construction Jul 05
$87,232 Design Dec 05
$249,948 Design Jul 04
S50,0013 Design TBD
Construction in progress.
Construction in progress.
Construction in progress.
Phase 1 of construction is complete.
Layering standards are complete.
Formation of the District xvill start in
Nov 03.
Second bid package is being prepared.
Project is on hold pending
participation from SBC and Comcast.
14
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: GAS FUND
OEPARTMENT NAME : UTILITIES DEPARTMENT
9911
01t8
0120
0213
0310
0311
Gas Station Number Three
All Weather Amstmdem
Gas Main Directional
Directional Boring Machine
CNG Sequential Fuel
System
New Vehicle
0011 Compress Natural Gas
Station
0119 Global Positioning System
0307 Directional Boring
Equipment
0308 Polyethylene Fusion
Equipment
Minor $70,000 $55,548
Minor 5275,000 5251,575
Minor $47,500 $2,725
Minor $126,000 $47,094
Minor $75,000 $75,000
Minor $27,000 $27,000
$52,363
$237,619
$1,403
$700
$o
$27,000
S3,185
$13,956
$1,322
$46,394
$75,000
$0
Complete
Complete
Complete
Construction
Design
Complete
Jan 04
Oct 04
Remaining balance will purchase chassis for
vaccum excavation equipment to support
directional boring operations.
Planning permits approved, preliminary plans
completed. Project to bid in Jan 04.
Multi-Year $440,000 $379,929
Multi-Year $381,000 $320,157
Multi-Year $47,500 $47,500
Multi-Year $25,000 $25,000
$0
$80,132
$17,576
$23,158
$379,929
$240,025
$29,924
$1,842
Design
Construction
Construction
Complete
Oct 04
Jun 04
Jan 04
Planning permits approved, preliminary plans
completed. Project to bid in Jan 04.
GPS Base Station installed on top of Ci .ty Hall.
Roviag data collection unit purchased. Three
more on order. Stafftmining in Feb/Mar 03.
Blanket order established v, Sth local equipment
supplier.
15
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: REFUSE FUND
DEPARTMENT NAME: PUBLIC WORKS DEPARTMENT
9701 Environmental Services
Center
Minor
]
$115,000
Multi-Year $2,287,722
$115,000
$1,876,172
$I 15,000
$381’6611
$0]Complete
$1,494,51 Pre-Design
I
Jun 10 Project delayed until
completion of study to
discover all existing
Baylands Policies.
16
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: STORM DRAINAGE FUND
DEPARTMENT NAME: PUBLIC WORKS DEPARTMENT
17
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: WASTEWATER COLLECTION FUND
DEPARTMENT NAME : UTILITIES DEPARTMENT
18
~;=Y 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: WASTEWATER TREATMENT FUND
~DEPARTMENT NAME: PUBLIC WORKS DEPARTMENT
0215
Effluent Line Modification
500 KW Emergency
Generator
9504 Interceptor Maintenance
Cleaning and Repair
9707 Wastewater Solids
Disposal Project
Minor
$150,000
$150,000
$43,784
$41.181
$0
$0
$43,784 Complete
$41.181 Complete
Multi-Year $1,750,000
Multi-Year $7,641,706
$105,79E
$277.952
$48,913
$151,793
$56,88:: Construction Dec 03
$126,15~ Construction Jun 04 Checklist items and warranty work
still needs to be done. Mid-year BAO
submitted for $141,706.
19
FY 02-33 YE.aJ:~-END GAPITAL !~’JPROVEI~,~ENT PROGRAI’~ PROJECTS STATUS
DEPARTMENT NAME : UTILITIES DEPARTMENT
’ "~2.;~~.,~ ... ~ ~ ~ ~;~-,.-;~-,-i-~--- ~---~ .............................~;;;~;; ..............~?~~ ............................................;. ........2 ........
010~Mayfield Reservoir R~x~f
Repairs
0113 Irrigation Meter Installation
0114 Land Acquistion for a
reservoir, a well and pump
station.
0217 Water Bott]L~ Equip
0312 New Vehicles
8749 IWaterReservoir Improv.
9704 IWater System Study
0108 IFoothilts PRV Installation
o11o
o111
Improvements
Distribution System Water
Qualiky Enhancement
Minor $290,000 $16,908
Minor $60,000 $59,335
Minor $2,000,000 $1,999,055
Minor $25,000 $24,430
.Minor $50,000 $50,000
$1,95[$14,950 Complete
$01 $59,335 Pre-Desi_ma
$0 $1,999,055 Pre-Design
$0 $24,430 Pre-Desi_ma
S50,000 $0 Complete
TBD
Jan 05
Jun04
Having ditlqculty with cmtomers taking
advantage of prograrn benefits.
Multi-Year Not.available
Multi-Year S275,01N
Multi-Year $236,00C
Multi-Year S1,360,00C
Mu t -Year $457,00(
$63,294
$-40,598
$235,150
$1,359,055
S456,055
$56,792
$39,705
S225,500
$407,210
$121,041
$6,502 Complete
$893 Complete
$9,65C Construction
$951,845 Desi£m
$335,0t-1 Design
Jun 04
Sep04
Sep 04
Design of the Foothills PRV continues.
Three additional PRV installations, Lytton,
Page bfill and .~rastradero have been
completed.
oCarollo Engineeting submitted 65 % desi~ma
of booster station improvements has been
submitted for review.
Carollo Engineenng submitted 65% desi_ma
of reservoir water rnkxmg systems for staff
re’dew.
20
Booster Station Multi-Year $205,000 $204,05.<
I" 0205
Existing Well Rehab Multi-Year $950,000 $949,40C
El ~maino Park Reservoir Multi-Year $1,700,00($1,699,81C
and Pump Station
0206 E1 Can~o Park Well Multi-Year $280,00($279,737
0207 Middlefield Road Well Site Multi-Year $280,00($279,737
0208 Eleanor Pardee Pasak Well Multi-Year $280,00C $279,452
$62,8!6 $141,239 Design
$0 $949,400 Pre-Design
$1,466,948
S266:622
$232,862 Design
S13,ll/ Design
$0 $279,73"J Pre-Design
$0 S279,457 ] Pre-Design
oct o~
Jan 05
Jan 05
Jan 05
Jan 05
Carollo Engineering submitted 65% design
ofboostar station pump systems. Staff
review has started.
Carollo Engineering is prepanng
CEQA/EIR documentation for all Water
Study Project Design.
Carollo Engin_’ eering is prepanng
CEQ.~ffEIR documentation for all Water
Study Project Design.
Carollo Engineenng is prepanng
CEQA/EIR documentation for all Water
Study Project Desigv_
Carollo E ~ngineering is preparing
CEQA!EIR documentation for all Water
Study Project Design.
Carullo Engineering is prepanng
CEQA/EIR doca.unentation for all Water
Study Project Desigr~
21
FY 02-03 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS
FUND TYPE: ENTERPRISE
FUND NAME: MULTI FUNDS
DEPARTMENT NAME: UTILITIES/PUBLIC WORKS
Utilities Customer Info.
System
$695,539 $264,749 Construction IJun 05
$4,666,553 $900,029 $150,573 $749,456 Construction Jun 07
Upgrades have been done to
DOC 1 application, eBPP
functionali~ is now being
researched.
Major upgrade of software was
completed in Apr 02. The TCP
contract was upgraded to a 7x24
support contract. New server
upgrades are in the plan for 03-04.
The CWA project is completed.
Further Banner upgrades are bein
22
Attachment B
LIST OF CONTINUOUS PROJECTS
Administrative Services
18614
18822
19618
19914
Financial Database Upgrade
Computer Aides Mapping
GIS Application
New Computer Acquisitions
Community Services
18617
19415
Art in Public Places
Park Facilities Improvements
Public Works
GeneralFund
18903
18971
18670
19018
19101
19309
Sidewalk Improvements
Street Improvements (Utility Users Tax)
Street Improvements (Street Improvement Fund)
Cubberley Building Code Modification
Tank Investigation and Removal
ADA Compliance
8870
Storm Drainage Fund
Collection System Improvements
8021
8022
Wastewater Treatment
RWQCP Plant Equipment Replacement
RWQCP System Flow Metering
Utilities
8928
8930
8931
8938
8944
9354
9703
9801
9802
9803
Electric Fund
Customer Design and Connection Services
Traffic Signals Upgade
Communication System Improvements
Substation Protection Improvements
Substation Facility Improvements
Street Light Replacements
Underground Cable and Equipment Replacement
Fiber Optics Ring System Improvements
Fiber Optics Customer Design and Connection Services
Electric Distribution System Reconstruction and Improvements
Gas Fund
8017
8019
9230
8018/9912/0002/0104/0201/0302
0309
Gas System Extensions
Gas Meters and Regulators
Natural Gas Vehicle Conversions and Purchases
Gas Main Replacements
Unreimbursed System Extensions
Wastewater Collection
8020 Sewer System Extensions
9913/9914/0003/0105/0202/0303 Sewer System Rehabilitation and Augmentation
Water Fund
8013
8014
8015
8016/9915/0004/0106/0203
0214/0304
Water System Extensions
Service and Hydrant Replacements
Water Meters
Water Main Replacements
Water-Gas Wastewater Utilities GIS Data