HomeMy WebLinkAbout2003-12-08 City CouncilCity of Palo Alto
City Manager’s Report
10
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: UTILITIES
DATE:
SUBJECT:
DECEMBER 8, 2003 CMR:512:03
PUBLIC HEARING AND ADOPTION OF ORDINANCE
ESTABLISHING UNDERGROUND UTILITY DISTRICT NO. 39
(SHERMAN/EL CAMINO REAL/PAGE MILL/PARK BLVD)
RECOMMENDATION
Staff recommends that Council adopt the attached Ordinance to create Underground
Utility District No. 39 and thereby amend section 12.16.020 of Chapter 12.16 of Title 12
of the Palo Alto Municipal Code.
BACKGROUND
At its meeting of October 27, 2003, the Council passed Resolution of Intent No. 8350 to
establish Underground Utility District No. 39. The Council meeting of December 8,
2003, has been set as the date of the Public Hearing on the matter. Notices announcing
the meeting with a description of the project and a copy of the Resolution were mailed to
all property owners in the proposed district on November 6, 2003.
The Electric Utility’s undergrounding project areas are selected and recommended to
SBC and Comcast based on the age and maintainability of the existing overhead electric
system. SBC and Comcast determine whether the recommended area meets the criteria
for undergrounding, based on the guidelines established by the California Public Utility
Commission (CPUC). The attached Exhibit "C" shows the existing and planned
underground districts. Underground Utility District No. 39 meets the City’s and CPUC’s
guidelines for undergrounding overhead utility lines.
Cost-sharing of underground utility district projects has been determined by Agreement
between the City, SBC, and Comcast. The cost for joint trench bid items is determined
using a space/cost allocation formula, which divides the minimum trench area required
for each trench occupant, individually, by the sum of the minimum trench areas for all
occupants.
CMR:512:03 Page 1 of 4
DISCUSSION
This underground project will result in the removal of 40 poles. All of the poles are
located along the streets. Completion of this project will result in higher reliability and
improved aesthetics.
If an underground district is created, the Utilities Department will prepare plans and
specifications and obtain bids for installation of the underground substructure
construction. Underground substructure construction consists of the installation of
conduits, vaults, pads and boxes. The Utilities Department will then install the electric
distribution cables, transformers and switches upon completion of the substructure
installation. After the new underground system (cable, transformers, switches, etc.) has
been tested and energized, the property owners will be notified that they have 60 days to
connect to the new underground system. Upon completion of the new connections,
Utility crews will remove the overhead power lines, and telephone crews will complete
the project by removing the remaining telephone and CATV facilities and poles.
RESOURCE IMPACT
The total cost of the project is estimated at $1,315,000. The majority of the cost will be
for the substructure installation for underground facilities ($750,000). The remaining
money will be utilized for design engineering ($150,000), electric equipment & cables
($250,000), and removal of overhead facilities ($100,000). SBC and Comcast will
reimburse approximately $375,000 to the City for the installation of telephone and CATV
conduits and boxes in accordance to an agreement with the three parties (discussed
above). Funds for the construction and installation of this project have been budgeted in
the 2003-2004 Electric Fund Capital Improvement Program.
The cost of the required service conversions on private property is to be borne by the
individual owners in accordance with Utility Rule and Regulation No. 17. The total cost
for the property owners requiring service conversions from overhead to underground has
been estimated at $65,000. The property owners have been offered the option of
financing their service conversion costs over a period of ten years in accordance with the
procedure given in Section 12.16.090 through 12.16.096 of the Palo Alto Municipal
Code.
POLICY IMPLICATIONS
This recommendation is consistent with the Council-approved Utilities Strategic Plan to
invest in utility infrastructure to deliver reliable service. The project furthers Program L-
CMR:512:03 Page 2 of 4
80 (the continuation of citywide undergrounding of utility wires) and L-81(the use of
compact and well-designed utility elements) of the Comprehensive Plan.
TIMELINE
Once the public hearing is completed and if Council decides to proceed with the project,
then the following will occur as proposed:
Date
December 8, 2003*
Action
Introduction and first reading of Ordinance
Establishing Project Area as Underground Utility
District No. 39
Second reading and adoption of Ordinance.
Award of construction contract and Joint Construction
Agreement with SBC/Comcast.
Substructure (conduits, vaults, etc.) installation by
Contractor
Installation of underground facilities (cable, switches,
etc.)
Resolution determining properties electing to pay
service conversion cost over a period of 10 years
Service conversion work by property owners
Pole removal and project completion
2.December 15, 2003*
3.July 2004*
4.July 2004 through November 2004
5.January 2005 through April 2005
6.April 2005*
7.May 2005 through August 2005
8.September 2005 through December
2005
*DenotesCouncilAction
ENVIRONMENTAL REVIEW
This project is categorically exempt from the California Environmental Quality Act under
Section 15302.
ATTACHMENTS
A: Ordinance
B: Underground Utility District No. 39 Boundary Map
C: Underground Conversion Projects
CMR:512:03 Page 3 of 4
PREPARED BY:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
~In THOMPStON
Senior F~ectric Pro2[ec~ Engineer/t3((
~cto~ of Utilities
Assistant City Manager
CMR:512:03 Page 4 of 4
***NOT YET APPROVED***
ORDINANCE NO.
ORDINANCE OF THE COUNCIL OF THE CITY OFPALO ALTO
AMENDING SECTION 12.16.020 OF CHAPTER12.16 OF
TITLE 12 OF THE PALO ALTO MUNICIPAL CODE BY
ESTABLISHING UNDERGROUND UTILITY DISTRICT NO.39
The Council of the City of Palo Alto does ORDAIN as
follows:
SECTION i. Findings and Declarations.
finds and declares as follows:
The City Council
(a) This Council, on October 27, 2003, adopted
Resolution No. 8350, declaring its intention to amend Section
12.16.020 of Chapter 12.16 of Title 12 of the Palo Alto Municipal
Code by establishing Underground Utility District No. 39 in the
City and by such Resolution appointed Monday, December 8, 2003, at
the hour of 7:00 p.m., in the Council Chambers, City Hall, at 250
Hamilton Avenue, Palo Alto, California, as the time and place of
hearing protests and receiving evidence for and against the
proposed action and notice of direction.
(b) Notice was given of the time and place therein
stated in the manner provided by law, as appears from the
affidavits on file in the office of the City Clerk.
(c) This matter came on regularly for hearing at the
time therein fixed.
(d) All written protests and other written
communications were publicly read at this meeting and evidence duly
taken and all persons desiring to be heard were fully heard.
(e) The public necessity, health and safety require the
removal of poles and overhead lines and associated overhead
structures from that certain area described in Resolution No. 8350.
SECTION 2. Section 12.16.020 of Chapter 12.16 of Title 12
of the Palo Alto Municipal Code is hereby amended by adding
Subsection (39) thereto to read as follows:
~(39) District No. 39. All of the area in the County
of Santa Clara, City of Palo Alto, encompassing the
areas contiguous with portions of
Sherman/Grant/Sheridan/Page-Mill/Park Blvd./Birch/Ash
and E1 Camino Real all as more particularly described
on that certain map entitled "Sherman/El Camino
Real/Page Mill/Park Blvd. Underground Utility
District Number 39," on file in the office of the
City Clerk."
031202 cl 0072339
1
***NOT YET APPROVED***
SECTION 3. The "Underground Utility District Maps" referred
to in Section 12.16.020 shall be amended to add to the areas shown
on the map those referred to in Resolution No. 8350.
SECTION 4. The City Council hereby finds that the adoption
of this ordinance constitutes the approva! of a project that is
categorically exempt from environmental review under the California
Environmental Quality Act.
SECTION 5. This ordinance shall become effective upon the
expiration of thirty (30) days from its passage.
INTRODUCED:
PASSED:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
ATTEST:
City Clerk
APPROVED AS TO FORM:
Mayor
APPROVED:
Senior Asst. City Attorney City Manager
Director of Utilities
031202 cl 0072339
LEGEND
PROJECT BOU_~A_RY
231 270
/
2500 -2516
385 t’ 300-362
~-_4ZLS399
231
360
398
...........STREET ’
~~ 4__Q04
I --
-~408 425
425425 ~
445 444 P 455 410 5
451 456 -64453470 -78
466 4
APPROVED 24 MAR 03
TOMM MARSHALL
ENGR.MANAGER
I
ENGR I
GJ
DRA.WN PD
CHECKEDI JT
UNDERGROUND CONVERSION
DISTRICT NO. 39
BOUNDARY MAP
~\l/&.. Cffy of Palo Alto
~\~ California~UTIU’[IES. ELECTRIC ENGINEERING
IREVi DATE
SCALE
DESCRIIPTION
I APPR
WORK ORDER DRAWING NO.
i"=200’22072 .,9-,.,M-S