HomeMy WebLinkAboutStaff Report 6416
City of Palo Alto (ID # 6416)
City Council Staff Report
Report Type: Informational Report Meeting Date: 1/25/2016
City of Palo Alto Page 1
Summary Title: Update on Second Transmission Line
Title: Update on Progress Towards Building a Second Electric Transmission
Interconnection Between the City, Stanford National Accelerator Laboratory
and Stanford University
From: City Manager
Lead Department: Utilities
Executive Summary
The purpose of this report is to update Council on progress towards a new 60kV electric
transmission line between the City of Palo Alto (City), the Department of Energy (DOE), SLAC
National Accelerator Laboratory (SLAC), and Stanford University (Stanford). The proposed 60kV
transmission line (the Project) would provide an interconnection between two existing
transmission corridors - the 230 kilovolt (kV) line in the west serving SLAC and the 115kV line in
the east serving the City. The new 60kV line would provide SLAC, Stanford and the City
transmission service reliability improvements and potential cost savings.
Since four parties are involved in this Project (City, DOE, SLAC and Stanford), detailed feasibility
studies have been conducted and reviewed by all participants to analyze the Project’s reliability
and cost implications, which the City and Stanford have jointly funded. The DOE and SLAC are
particularly concerned with any incremental power quality issues that may result from a more
integrated system and they have identified a number of betterments they require to their
existing system before they will participate, the funding for which remains to be resolved.
Stanford remains a critical party to enable this Project to move forward and the parties’ current
focus is on possible business models to allow Stanford to access the new line over Palo Alto’s
distribution system. At this stage, none of the parties have committed to actual construction
and funding of the Project. Council will have full opportunity for review and approval prior to
any commitment for construction and funding.
Background
The City of Palo Alto’s electric distribution system is connected to Pacific Gas and Electric
Company’s (PG&E) transmission grid via three 115 kV transmission lines. Although three lines
would normally provide redundancy and back-up power delivery to the City, all three lines run
in a common corridor on the bay side of the City, a corridor that is in close proximity to the Palo
City of Palo Alto Page 2
Alto Airport. The common corridor and proximity to an airport means that the City’s power
supply is susceptible to single events that can affect all three lines, as happened in February of
2010 when a small aircraft hit the power lines resulting in a city-wide power outage for over 10
hours. To minimize these possibilities, it is in the City’s interest to find a physically diverse
connection for power supply to the City. Staff has been investigating options for an alternative
connection to the transmission grid for numerous years.
Following the February 2010 plane crash and subsequent city-wide outage, Council included the
goal to evaluate alternative electric transmission line sources in its priorities for 2011 (Staff
Report No. 1497, March 21, 2011). Further in March 2011, Council adopted a guideline and
implementation plan item to evaluate interconnection options to the City to increase service
reliability and lower delivery costs. Council adopted this guideline and implementation plan as
part of the City’s updated Long-term Electric Acquisition Plan (LEAP) (Resolution 9152, Staff
Report No. 1317). The relevant portion of the applicable LEAP Strategy #8 is as follows: 8.
Transmission and Reliability – Pursue the reliability of supply at fair and reasonable
transmission and delivery costs by: c. Evaluating interconnection options to the City to increase
service reliability and lower delivery costs.
Staff has provided updates on the evaluation of interconnection options in the Utilities
Quarterly reports to the Utilities Advisory Commission (UAC) since Council’s approval of LEAP.
Over the past three years, staff concluded that the optimal interconnection option is a
connection between the City’s Quarry electric substation and the SLAC substation. This Project
has the added advantage of also providing redundant back-up service to SLAC, providing
Stanford an alternative connection and reducing transmission costs for the City’s electric
ratepayers.
Implementing the Project will require a multiparty effort including Stanford--the land owner
and potential Project participant, and SLAC and DOE--Project participants and the owners of the
transmission assets to which the new transmission line would connect. This effort has required
several feasibility studies, as each participant has explored the reliability and cost implications
of the Project. Utilities Department appropriated funds (the “Feasibility Study Funds”) from the
Electric Fund – Capital Improvement Program (CIP) EL-06001 - 230 kV Electric Intertie and its
consulting budgets to conduct these evaluations.
Summary of Feasibility Studies
Load Flow Study – Although no new electric customer loads would be added to the regional
electric grid as a result of the Project, the City and Stanford commissioned an updated Load
Flow Study to determine potential Project impacts on PG&E’s system. The Load Flow Study
analyzed various normal and fault condition scenarios. The results of the study showed that the
proposed Project would be able to deliver power while improving regional power reliability and
quality.
City of Palo Alto Page 3
230 kV Overhead Line Assessment – Stanford commissioned a study of the existing DOE-owned
230 kV transmission line to determine if it has capacity to carry additional load. This study
evaluated the maximum load (temperature) at which the line could operate in compliance with
California Public Utilities Commission’s General Order 95 (overhead electric line rules regarding
ground and structure clearance) and identified spans that could require additional work to
meet current GO 95 criteria if the Project proceeds.
Routing Study – Stanford commissioned a Routing Study which analyzed various route options
for a potential underground 60kV line between SLAC and the City’s Quarry substation, with a
focus on route alternatives that best meet environmental and engineering constraints.
Transient Analysis – The City commissioned this study to determine whether the combined
system would be as reliable and stable as the current system. The study concluded that the
Project would create a reduction in voltage fluctuations overall, with generally positive impacts
on the magnitude of voltage depressions.
SLAC Studies – SLAC commissioned their own transient and steady state analyses for an
independent review of the impacts to their power quality and reliability. Their studies indicated
that while the Project would mitigate SLAC’s exposure to some PG&E faults there was an
additional exposure to faults on the City’s 60kV system. Although the City’s occurrence of faults
is extremely low--2 or 3 events in the past 10 years -- and notwithstanding the reduction in
magnitude of the PG&E fault impact, SLAC has determined that they need mitigation measures
in place at a cost of between $5M-$23M, depending on the level of correction they want from
both their existing exposure and their perceived risk from connecting to the City’s system.
SLAC’s steady state analysis concluded the Project would not add much value to the backup
service provided to SLAC, but SLAC is still interested in having a fully redundant system
designed into and funded through the Project.
Next Steps
Although the studies to date indicate that the proposed interconnection is feasible, would
strengthen the local transmission system, could be designed and operated to maintain and
improve power quality, and could provide for the participants’ current and forecasted electric
load, much work remains to move the Project forward.
In particular:
(a) The successful completion of the Project will require additional joint evaluation of various
issues, including, but not limited to, the method by which the City can provide electric
transmission service to Stanford; land use and environmental analysis under the California
Environmental Quality Act (CEQA); siting issues and easement acquisition; and possibly the
negotiation of separate agreements with other parties such as PG&E, the Western Area Power
Administration (WAPA), and the United States DOE.
City of Palo Alto Page 4
(b) Preliminary design of the proposed Project could entail substantial expenditure of funds by
both the City and Stanford.
(c) The completion of the Project may be infeasible if the City, Stanford, SLAC and DOE cannot
resolve contractual issues and execute and deliver mutually acceptable agreements pertaining
to this Project.
Project Timeline
A project of this magnitude will take between three to four years to complete once an
agreement is in place amongst the parties. An estimated duration of each task follows:
Project scope and environmental review would take from six months to one year.
Design contracting and the actual design would take approximately one year.
Construction contracting, construction, and project commissioning would take between
one year and one and a half years.
Alternatives
There is an alternative to the SLAC 230kV connection that will provide redundant transmission
service to the City. The alternative is a PG&E project that would connect the Adobe Creek
Substation near San Antonio Road with PG&E’s Ames Substation in Mountain View. Although
the PG&E alternative would provide the redundant service and come at minimal cost to the
City, it does not provide the same level of local system benefits or offer the opportunity for the
City to avoid any transmission access charges. This alternative has been proposed by PG&E to
the California Independent System Operator and is currently on hold pending the results of the
City’s negotiations on the SLAC project.
Resource Impact
The City has borne expenditures related to transmission-level interconnection studies
beginning in 2005. More recently the load flow study was updated and the three new studies
were conducted, as described above, to be used as the basis for the study and analysis
summary for SLAC and the DOE. The City’s portion of the load flow study update and three new
studies is $123,000. This includes:
$85,000 for the City’s share of the overhead line assessment and routing study to be
reimbursed to Stanford under a cost sharing agreement executed in December 2013.
The total cost of these two studies was $217, 000, with $132,000 paid by Stanford.
$27,000 for the City’s share of the updated load flow analysis paid to Flynn Resources
Consultants, Inc. under its existing consulting agreement with the City. The total cost of
the load flow analysis was split 50/50 with Stanford; and
$11,000 for the City’s share of the transient analysis, paid to Flynn Resources
Consultants, Inc. under its existing consulting agreement with the City.
This Project is also consuming 0.25 FTE in Utilities Engineering who is responsible for managing
the meetings with the various parties and consultants. Staff will be recommending the
contracting of additional resources to offset the staff time dedicated to this Project.
City of Palo Alto Page 5
Additional estimated costs if the City, Stanford and SLAC agree to proceed with the next steps
of project evaluation will include:
$40,000 for PG&E to perform a study assessing the impacts of the interconnection to its
system, which would include laying the groundwork for additional electrical protection
requirements required as a result of the proposed Project; and
$5-7 million for the detailed evaluation, negotiations and contract drafting, and
preliminary design described above in “Next Steps”.
In the event the City, Stanford and SLAC/DOE proceed with the Project, the total construction
cost is estimated at $50-90 million. Completing the required land use, legal and environmental
analysis and regulatory approvals will also impact that estimate.
The City’s share of the costs for the next phase of studies and construction has yet to be
determined. The allocation of these costs will be addressed in the terms of agreements yet to
be executed between the parties.
Staff will include estimates of the City’s share of the cost of the next phase of evaluation and
design for approval in Fiscal Years (FYs) 2017 and 2018 operating and CIP budgets for the
Electric Fund. Appropriation of these funds will only occur if and when agreements are signed
between the City, Stanford and SLAC/DOE to proceed with the next phase. Staff will continue to
report on the Project’s status to the UAC and Council in the Utilities Quarterly reports.