HomeMy WebLinkAbout2004-12-14 City Council (3)City of Palo Alto C ty Manager’s Report TO:HONORABLE CITY COUNCIL ATTENTION:FINANCE COMMITTEE FROM:CITY MANAGER DEPARTMENT: ADMINISTRATIVE SERVICES DATE:DECEMBER 14, 2004 CMR: 507:04 SUBJECT:2003-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS REPORT This is an informational report and no Council action is required. BACKGROUND This report provides information on the status of the City’s Capital hnprovement Program (CIP) projects as of the end of fiscal year 2003-04. In the attached matrix (Attachment A), all City departments have submitted information on their projects and commented on any issues that might cause a change in the scope or timing of the projects. Information in this report is intended to keep Council abreast of progress on all CIP projects that were open at the begi~ming of the 2003-04 fiscal year and on those projects that were added or completed during the same fiscal year. DISCUSSION The attached matrix categorizes CIP projects into minor projects (projects which can be completed within a one-year period) and multi-year projects (projects which have multi-year budgets and/or complex implementation schedules with identifiable phases). The project status portion of the matrix identifies the phase the project was in at fiscal year-end. Information on phases is intended to give Council a perspective on how much progress was made on a project. Three distinct phases are utilized, as follows: CMR: 507:04 Page 1 of 3 Phase:Possible Activities: Pre-Design Design Construction o Preparation of feasibility study o Development of a master plan o Definition of a project scope o Environmental Review o Hiring a design consultant o Completion of project design o Soliciting bids or proposals o Acquisition of major equipment o Installation o Implementation of a project Tlle comment section of the matrix provides Council with information clarifying the status of certain projects. Inthe attached matrix, projects are listed by department for the General Fund and by fund for the Enterprise and Internal Service Funds. The matrix also includes information on the total budget from inception for the project, the available budget as of the beginning of the fiscal year,the fiscal year expenditures tl~’ough June 2004, including commitments (encumbrances), the remaining balance in the project budget as of year-end, and the percentage of completion for the project. The matrix does not include "continuous" projects. These projects, such as water meter replacement, have no definitive beginning or end dates and receive ongoing funding to reflect continuing replacement cycles or commitments. During fiscal year 2003-04, progress was made on all of the City’s "continuous" projects (Attachment B). At year-end, all completed CIPs (after settlement of encumbrances) and CIPs where no activity is planned in the near future were closed and the remaining balances transferred to the Budget Stabilization Reserve for General Fund projects; to Retained Earnings for Internal Service Funds; and for Utility Fund projects, to the appropriate Rate Stabilization Reserve. A separate analysis of all Infrastructure Management Plan (IMP) projects has been prepared. At June 30, 2004, the status of IMP projects was: CMR: 507:04 Page 2 of 3 Total Adjusted Budget FY 2003/04 Less: Actual expenditures as of 6/30/04 Encumbered balance as of 6/30/04 Projects in pre-design stage Projects in design stage Projects in bid award stage Projects in construction stage Projects completed Projects that are ongoing Project bids were too high - to be rebid $18,220,405 (6,209,114) (6,986,121) (75,826) (2,725,555) (173,593) (389,949) ( 7,689) (1,405,375) (247,183) $.0 ATTACHMENTS Attachment A: Year-end Capital Improvement Projects Status Matrix Attachment B: List of Continuous Projects PREPARED BY: HARTMANN Staff Accountant F. JA~<;KIE AGUS~IN Staff Accountant DEPARTMENT HEAD APPROVAL: CITY MANAGER APPROVAL: HARRISON Assistant City Manager CMR: 507:04 Page 3 of 3 FY 03-04 YEAR-END CAPITAL I~IPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND ADMINISTI~kT1VE SERVICES DEPARTMENT Attachment A TE-01006 Enterprise Backup Minor $70,000 $70,000 $0 Solution (10106) TE-01008 Systems Management Minor $357,180 $37,180 $31,476 (10108) TE-01012 IT Disaster Recovery Minor $330,000 $330,000 $0 Plan (10112) TE-02025 Cable Television Minor $50,000 $34,837 Broadcasting Equipment (10225) TE-95016 Permitlnformation Tracking System (19516) TE-00010 Telephone System Replacement ( 82201) TE-00021 NewPhone System 10021) 1"E-00027 Renovations and Upgrades to Data Management (10027) rE-02012 Desktop Automation (10212) $70,000 $5,704 0% Design Dec 05 98% Design Jun 05 $330,000 0% Design Jun 06 $0 $34,837 30% Construction Jun 05 Staff is continuing to evaluate software vendor solutions. These funds were used for SAP training. The remaining balance will be used for any SAP software tools. Staff is continuing to evaluate strategic options. Work is continuing on upgrading the equipment in the cable booth and video equipment in the Council Chambers and Council Conference Room. RFP for equipment maintenance and equipment upgrades has been issued. Multi-Year $890,000 $201,868 Multi-Year $650,000 $650,000 Multi-Year $180,000 $174,745 Multi-Year $800,000 $58,569 Multi-Year]$80,000 $79,317 $111,195 $0 $0 $4,167 $0 $90,673 90% Construction $650,000 0% Design $174,745 $54,402 $79,317 3% Design 93% Complete I% Design Jun 06 9ec 06 Dec06 Jun 04 The City has implemented the following modules of the Accela System. Building, Code Enforcement and Planning. Code Enforcement was completed Feb 04 and Planning will be completed Aug 04. Fire; Police and Public Works ~ermits to be implemented in FY04-05. Staff is continuing to evaluate developing technology. 1003 Elwell Court continues to be a test site for ~ telephony. Staff is continuing to evaluate developing technology. 1003 Elwell Court continues to be a test site for IP telephony. Staff is also continuing research on an Open System IP PBX. Purchasing software for survey automation and web updates. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND ADMIN1STI~A_TIVE SERVICES DEPARTMENT Institutional Network (I-Net) (10213) eGov - Web Infrastructure and Application (10214) Infrastructure and Applications (10215) Enterprise Resource Planning (10216) Acquisition of New Computers (82200) $1,000,000 $400,000 $1,027,162 $5,018,476 $256,500 $56,564 $0 $141,119 $l,976,849 $54,451 $943,436 $354,166 $525~114 $136,345 $95;374 Construction Pre-Design Construction Pre-closure Jun 06 Jun 06 Jun 06 Mar 05 Jun 05 A settlem~’nt agreement \vith Comcast is pending. Once finalized, the agreement will allow the I-Net to progress. Palo Alto installation of fiber optic cable to connect to I-Net is continuing. facilities will be connected in FY04-05. On hold until SAP future direction is established. Siaff is in the final phase of this project, focusing on trouble- shooting and ensuring that users’ needs are met., Remaining funds are required for the final phase. Researching equipment needs for CSD’s request for a new PC. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND COMMUNITY SERVICES DEPART~IENT OS-99005 Cubberley Athletic Minor Field Irrigation (19905). PG-01013 El Camino Median Minor Landscape (10113) MinorChildren’s Theatre Light & Sound Systems Upgrade (10224) Minor Community Theatre Stage Floor Replacement (10305) Minor Children’s Theatre Stage Floor PG-04010 Athletic Field Minor Artificial Turf & Lighting Projects PG-94014 Park Irrigation and Multi-Year Backflow Improvements (19414) Library Automation Multi-Year Service ( 19418) School Site Irrigation Multi-Year (19801) PG-98003 Mitchell Park Muiti-’~ear !Facilities (19803) AC-99010 Community Theater Multi-Year Renovation (19910) $30,000 $1,577,000 $210,000 $45,000 $108,705 $155,000 $1,708,000 $1,286,751 $816,000 $2,382,6~4 $891,000 $14,427 $535,620 $208,756 $45,000 $108,705 $155,000 $4,989 $702,310 $173,I71 $406,269 $58,734 $14,427 $220,219 $208,756 $42,168 $103,705 $347 $222 $393,747 $24,560 $53,374 $56,026 $0 100% Complete $315,401 " 80% Complete $0 100% Construction $2,832 94% Construction $5,000 95% Construction $154,653 0% Design $4,767 I00% Construction $308,563 76%1 Ongoing $148,611 82% Design $352~895 85% Design $2,708 100% Complete Feb 05 Dec 04 Nov 04 Jun 06 Dec 04 Dec 04 Sep 04 Dec 04 Phase 1. FY 03-04 YEAR-END CAPITAL IMPROVE~,iENT PROGRAM PROJECTS STATUS GENERAL FUND COMMUNITY SERVICES DEPARTMENT OS-00001 ’"" Park Trails (10001) Multi-Year $1,009,000 $457,365 OS-00002 Open Space Lakes & Multi-Year $t50,000 $40,000 Ponds Maintenance (10002) OS-00003 Bayland Parking and Multi -Yeal $1,089,163 $838,103 Site Improvements (10003) $67,754 $389,611 61% Ongoing Jun 05 $19,575 $20,425 86% Ongoing Nov 05 $538,152 $299,951 72% Ongoing Jun 05 Phase 1 Completed Oct 03. Phase 2 Work at Pearson Arastradero Preserve will commence Oct 04. Annual pond weed clearing completed. "Annual maintenance is being maintain to keep Boranda lake free of invasive weeds. Pha~e 1 - B~,xbee Park Hills and Sailing Station parking lots completed. Phase 2 - Evans Parking Lot to be rebuilt May 05. PG~00009 PG-00010 Medians, Islands and Multi-Year $624,000’$132,601 Planters Renovation Projects (10009) :Park Facilities Multi-Year $2,828,450 $1,571,630 Improvements (10010) $16,375 $116,226 81% Design Nov 04 $250,416 $1,321,214 53% Ongoing Dec 04 CA-01014 PG-02018 Community Services Multi-Year $424,000 $357,925 Facilities Lighting Enhancements (10114) Palo Alto SOFA Park Multi-Year $236,000 $221,011 (10218) $226,896 $131,029 69% Construction Dec 04 $946 $220,065 7% Design Sep 04 Construction contract out to bid Jun 04. Eleonorand Hoover play areas - contract to Council for approval Jun 04. Briones, Cameron, Weisshaar and Mayfield in design phase. FY 03-04 ~T~AR-END CAPITA][, IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND FIRE DEPARTMENT Emergency Notification System (19821) Apparatus Floor Lockers for Fire Stations #1,3,4,5,7 & (10302) Minor $172,000 $57,781 $0 Minor $40,000 $40,000 $0 / 8 1 $57,781 $40,000 66% Closed 0% Ongoing Jun 05 FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND NAME: GENERAL FUND/STREET IMPROVEMENT FUND (SIF) PLANNING DEPARTMENT PL-95024 PL-OIO16 PL-02005 PL-02006 PL-02023 PL-04010 Bikeway System Improvement (SIF) 19524) Sheridan Sidewalks (10116) E1 Camino Real/ Ventura Avenue Traffic Signal (10205) Traffic Signal San Antonio/Hwy 101 (10206) Master Schematic Design (10223) Bicycle Boulevards Implementation Project Minor Minor Minor Minor Minor Minor $51,200 $31,000 $61,000 $280,800 $288,000 $50,000 $46,964 $31,000 $61,000 $280,800 $10,360 $50,000 $7,467 $0 $280,800 $0 $39,497 $31,000 $61,000 $0 $10,360 $50,000 23% Design 0% Closed 0% Delayed 100% Construction 96% Pre-Design 0% Pre-Design Jun 05 Dec 05 Dec 04 Jun 05 Jun 05 Louis/Ch.arleston median island was modified to provide improved bike access across intersection. Additional projects will be implemented including tmprovements along Park Blvd. The project balance of $61,000 was returned to reserves as of ’ Jun 04. This project is being implemeuted by Caltrans and is scheduled for FY 04-05. Staffi.’ expecting to receive cooperative agreement from Caltrans in Fall 2004 and will pursue just-in-tirol budgetin~ to reactivate project. Caltrans project under :onstruction. Draft Plan was completed and endorsed by Pla~ming and Transportation Commission in Mar 03. Caltrans District 4 has applied for grant funds to install ’improvements at Stanford Avenue and E1 Camino Real consistent with the 6-lane option in the Draft Plan. Sfaffheld a neighborhood and working group meetings with neighborhood, school and bike representatives to develop conceptual design for Maybell- Donald bike boulevard route. Staff and PABAC are collaborating on the design for the Park Blvd. Bike boulevard design expected to be completed by Dec 04 with installation in Spring 05. FY 03-04 YEAR-END CAPITAL I~IPROVEMENT PROGRAM PROJECTS STATUS FUND NAME: GENERAL FUND/STREET I~IPROVEbIENT FUND (SIF) PLANNING DEPARTMENT PL-95023 El Camino Real Multi-Year $212,750 $1,527 Intersection Improvements (SIF) (19523) $0 $1,527 99% Closed PL-98013 School Commute Multi-Year $300,000 $117,549 $679 $116,870 61% Design Inn 05 Safety Improvements (SIF) (19813) PL-00026 Local and Multi-Year $470,000 $306,840 $236,854 $69,986 85% On-going Neighborhood Collector Street Traffic Calming Program (10026) PL-O1017 E1 Camino Multi-Year $100,000 $100,000 $0 $100,000 0% Pre-Design Dec 05 Real/Churchill Avenue (10117) Funds will be used to fund projects identified in the South Palo Alto School Commute Safety Study and to implemeut other safety and operational unprovements, such as enhatlced crosswalks along school commute routes. Since the formal start of the Neighborhood Traffic Cahning Program in Apt 01, eleven projects have been initiated. During the past year, project have been implemented on Channing Avenue, Waverley Street, Ross Road and Moreno and Indian Drives. Project on Pepper Avenue is in design. This project was delayed indefinitely due to relocation of staff resources to the Homer Avenue Undercrossing. Staff plans to request that this project move for~vard in FY 04-05. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND POLICE DEPARTMENT PD.02017 PD-03003 iPD-04010 PD-04011 PD-93012 PD-99013 Public Safety Mobile Data Computer (10217) Additional Fire Frequency (10303) Fire Portable Radio Replacement Civic Center Parking Fire Communication~ Computer Systems (19312) Police Records Management (19913) Minor Minor Minor Minor Multi-Year Multi-Year $163,596 $95,000 $245,584 $75,000 $485,050 $526,435 $163,596 $95,000 $245,584 $75,000 $89,502 $57,335 $163,596 $0 $130,639 $0 $55,174 $95,000 $114,945 $75,000 $34,328 $57,335 IO0°A Construction May 05 0% Construction Feb 05 53% Construction Dec 05 0% Construction Nov 05 93% Construction May 05 89% Construction May 05 Currently testing 5 vehicles. Developed transition plan. Equipment procurdd. Equipment procured. In final phase of installation and training. Equipment back ordered. Delayedby vendor. . Work flow analysis under~vay. Implementation to coincide ~vith Mobile Data Computer ’,PD-02017) roll out. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT PE-98020 PE-00017 PE-00018 PE-01019 PE-02004 PE-02019 PE-03004 PE-03005 PO-03006 PE-04011 PE-04013 PF-04011 PF-04012 Public Safety Bnilding (19820) Adobe Creek Pedestrian/Bike Undercrossing and Highway i 01 Pedestrian/Bike Overpass Lighting Improvements (10017) Sand Hill Road Bridge (10018) Baylands Bike Trail Replacemenl (10119) Library Master Plan Project Definition Study (10204) Minor $765,028 Minor $100,000 Minor Minor Minor Fire Station Seisnric Evaluation Minor (10219) Roth Building Wings De~nolition Minor (10304) Wildhorse Valley Vehicle Bridge Minor Replacement (10301) Animal Service Protective Holding Kem~els (10306) Minor Cambridge Parking Structure Minor Improvements Fire Stations 3 & 4 Replacement Minor Feasibility Study Junior Museum Fire Sprinkler Minor Installation Cnbberley Building 1 Air Minor Conditioning Replacement $150,036 $100,000 $977,55O $125,000 $1,265,350 $172,000 $172,000 $65,589 $I00,000 $127,500 ~$175,000 $267,456 $93,446 $144,696 $63,563 $31,075 $59,817 $1,161,185 $173,899 _ $160,000 $65,589 $100,000 $127,500: $175,000 $267,456 $0 $106,614 $o $0 $1,074,132 $44,686 $0 $65,589 $92,382 $79,012 $6,444 $0 $93,446 $38,082 $63,563 $31,075 $59,817 $87,053 $129~213 $160,000 $0 $7,618 $48,488 $168,556 100% Pre-Design 7% Closed 75%Construction 36~Closed 97%Closed 52% Closed 93% Construction 25% Constn~ction 7°A Design 100°/, Complete 920A Pre-Design 62~ Construction 4oA Design Apr 05 Nov 04 Sep 04 Nov 04 Apr 06 Mar 05 Nov 04 Jan 05 Staffis going to Council in Dec 04 for direction. Design phase in FY 05-06. Bid opening date Nov 04; constnlction phase to be completed Jan 05. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT PE-99006 PE-89004 PE-93010 PF-95005 PE-95012 PE-95030 PE-96008 PO-97004 PE-98015 PE-99007 MSC Feasibility Study (19906) Harbor Improvements (18918) Embarcadero Pedestrian Bike Bridge Path Extension (SIF) (19310) Revenoe Collection Remodel 09505) Civic Center Plaza Waterproofing (19512) Downtown Parking Stnmture Indirect CstP (6900) (19530) Downtown Urban Design Improvements (19608) Traffic Control Safety Devices (19704) Arastradero Rd. Bike Lane Improvements (SIF) (19815) San Mateo Drive Bridges (19907) Multi-Year $6,958,297 Multi-Year $2,139,000 Multi-Year $1,819,555 Multi-Year $85,000 Multi-Year $250,000 Multi-Year $40,136,753 Multi-Year $1,220,349 Multi-Year $320,000 Multi-Year $455,000 Multi-Year $118,000 $137,995 $99,705 $1,241,380 $743 $177,916 $17,972,083 $0 $116,605 $81,576 $104,567 $6,284 $28,797 $1;209,297 $0 $114,861 $8,956,824 $0 $0 $66,427 $94,239 $131,711 $70,908 $32,083 $743 $63,O55 $9,015,259 $0 $116,605 $15,149 $10,328 98% 97% 98% 99% 75% 78% 100% 64% 97% 91% Pre-Design Complete Construction Closed Construction Construction Complete Closed Closed Complete Jun 05 J~n 05 Dec 04 Dec 05 This is maintenance repair, larger design phase scheduled FY 06-07. Phase 2 will commence FY 06-07. I0 FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS GENERAL FUND PUBLIC WORKS DEPARTMENT ’E-99023 Page Mill/Hanover (19923)Multi-Year $1,068,000 $994,666 $17,874 $976,792 9°A Design Sep 04 ’F-00006 Roofing Replacement (10006) Multi-Year $298 000 $216,244 $212,669 $3,575 99~ Ongoiag Complete for FY 03-04. ’O-00015 Fire Station Driveway Multi-Year $235 000 $67,945 Modification and Installation of Oil/Ware(Separator System ~10015) ’F-00020 Office Space Renovation and Multi-Year $882 934 $39,748 Reallocation (10020) ’F-01002 CCQB Infrastructure Multi-Year $2,492,000 $2,283,857 Construction (10102) $52,304 $15,641 93°A Corn flete $9,744 $30,004 97°A Corn ilete $1,964,566 $319,291 87°A Construction Jul 05 ’F-01003 Building Systems Improvement Multi-Year $117 000 ’$109,611 Construction (10103) ’F-01004 Fire Station Improvements Multi-Year ’ $822,000 $818,000 (10104) ’F-01005 Lucie Stern Community Center Mnlti-Year $379 000 $378,975 Improvements (10105) $109,287 ;324"100% Corn flete $644,677 $173,323 79% Design Jun 05 $67,579 $311,396 18% Design Apr 05 ’E-01021 Homer Avenue Undercrossing Multi-Year $5,216,510 $4,772;454 (10121) ’F-02022 Facility Interior Finishes (10222) Multi-Year $152 400 $152,400 $4,772,454 $0 100% Construction Dec 04 $152,400 $0 100% Ongoing ’F-03000 Foothills Park Interpretive Center Multi-Year $92,000 $91,818 Mechanical Upgrades (10300i $77,536 $14,282 84% Complete ’E-04010 Children’s Library Improvements Multi-Year $300,000 $300,000 & Expansion E-04012 Mitchell Park Library &Multi-Year $290,000 $290,000 Community Center Improvements E-04014 Animal Sh,elter Expansion &Multi-Year $415,00.0 $415,000 Renovation $46,161 $253.839 15% Design Mar 05 $271,279 $18,721 94% Pre-Design Jan 05 $408,965 $6,035 99% Design A ir 06 Construction phase for elevator upgrade. This projecl will be phased over multiple ~ears. Coastn~ction to start Oct 04. Bid opening date Nov 04; ,reliminat2 construction scheduled Spring 05. Complete for FY 03-04. F-04010 Cubbertey Mechanical &Multi-Year $425,000 $425,000 $359,731 $65,269 85% Design Electrical Upgrades Dec 04 E-05300 Arastradero Preserve Gateway Multi-Year $551,605 $551,605 $537,175 $14,430 97% Cansiruction Mar05 FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS INTERNAL SERVICE FUND GENERAL FUND PUBLIC WORKS I)EPARTMENT MSC Fuel Storage Tank ¯ Replacement (81101) MSC Equipment Washing Facility Upgrade ( 10023/81102) MSC Equipment Maintenance Facility Mezzanine Storage Area (81100) MSC Fuel Storage Tank/Svc Island Replacement (10022) New Vehicles Fuel Tank Storage/Upgrade (19205/81106) Wireless Vehicle Management System (19521/81105) Golf Course Equipment Replacement (81103) New Vehicles(81104) CNG Vehicle Maintenance Facility Upgrades Compressed Natural Gas Refueling Station Relocation Minor $225,000 Minor $300,000 Minor $85,000 Minor $775,000 Minor $108,000 $100,000 $255,703 $64,972 $707,547 $108,000 Multi-Year $341,000 $100;062 Multi-Year $245,000 $33,277 Multi-Year $145,000 $4,152 Multi-Year $208,000 $46,462 Multi-Year $85,000 $85,000 Multi-Year $50,000 $50,000 $2,643 I $44,929 $61,962 $42,011 $107,077 $0 $29,950 $0 $26,996 $43,227 $0 $97,357 $210,774 $3,010 $665,536 $923 $100,062 $3,327 $4,152 $19,466 $41,773 $50,000 57% Design 30%Design 96%Design 14%Design 99%Pre-Design 71%On-hold 99%Complete 97%Closed 91~ Design 51~, Pre-Design 0% Pre-Design Sep 05 Jun 05 Feb 05 Sep 05 Jun 05 TBD Dec 04 Jun 05 Dec 05 Original design is undergoing Changes which should be conipleted Jan 05. Design will be submitted for bidding by Mar 05. Project delayed un!il completion of new fueling station (VR-0000 t ). Project has been delayed due to pen~itting issues. Coustruction to start Jall 05. Original design is undergoing changes which should~ be completed Jan 05. Design will be submitted for bidding by Mar 05. One vehicle project remains to be completed. Delay due to change in plans by end-user. Design is complete. Project on hold until VR-00001 ~a~d VR-01000 are complete. Awaiting delivery Phase 1 - dynamometer installation and training complete. Project on hold until VR-00001 and VR-01000 complete. the compressed natural gas (CNG) equipment that is going to be relocated in VR-04011 will not be available until the new CNG facility (VR-00001 ) is complete. 12 FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: ELECTRIC FUND DEPARTMENT NAME: UTILITIES DEPARTMENT EL-99016 EL-96011 EL-98004 EL-99001 EL-990!~3 EL=00006 EL-01003 EL-OIO15 EL-01016 EL-01017 EL-01002 Generator (0121) Foothills System Rebuild Rhodes/Edgewood 2.4/4 kV Conversion Fiber to Home Trial (9916) Embarcadero/Middlefield UG Conversion District #37 (9611) Oregon/Colorado/Cowper UG Conversion District #38 (9804) Stanford West Underground Extension (9901) Stmaford Park UG Cable Rebuild (9903) Park Boulevard Substation Bus Re-arrangement (0006) Underground Cable/Equipment Replacement (0103 ) lWest Bayshore UG System Rebuild (0115) Downtown Street Light System Upgrade (0116) Upgrade Traffic Signal Control System (0117) North/South Hampton UG System Rebuild (0102) Multi-Year $1,005,000 $I8,537 Multi-Year $5,360,00C $100,000 Molti-Year $2,875,00C $33 $245,600 95% Construction Jul 05 $107,038 $742,962 13% Construction Jul 05 $150,000 $0 100% complete $0 $18,53~98% Complete $100,000 $~100% Complete $2,485,716 $2,187,744 $297,97]90% Construction Dec 05 Multi-Year $1,700,00~$100,000 Multi-Year $4,575,00C $1,451,058 Multi-Year $2,755,001~$2,552,091 Multi-Year $1,000,00C $67,850 Multi~Year $450,00C Multi-Year $579,00C Multi-Year $2,140,00C Multi-Year $1,700,000 $100,000 $~100.% Complete $618,632 $832,42(82% Construction Jul 05 $2,094,414 $457,677 83% Construction Dec 04 $67,850 $C I00% Complete $1,576 $1,576 $13 100% Complete $74,749 $74,7491 $~3 100% Complete $1,953,473 $1,880,41($73,063 97% Construction $972,045 $956,44~c $15,596 100% Co~nplete Dec 04 Construction complete except for metering and SCADA installation Construction in progress. Design complete. Substructnre construction completed. First two phases are complete. Third phase in construction. Design complete. Construction contract has been awarded. Construction in progress. 13 FY 03-04 MID-YEAR CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: ELECTRIC FUND DEPARTMENT NAME: uTILITIES DEPARTMENT EL-02009 BaylandS Underground Multi-Year $500;000 (0209) EL-02010 SCACASystem Upgrades Mnlti-Year $400,000 (0210) EL-02011 Electric Utility GIS Data Multi-Year $212,500 (o2ll) EL-03005 She~nan/El Camino/Page Multi-Year $2,995,000 Mill/Park UG Couversion District #39 (0305) EL-03013 Utilities Estimating System Multi-Year $300,000 (0313) EL-03014 Edgewood Drive Multi-Year Undergronnd Conversion District #40 (0314) $150~0013 $144,87~$5~124 99°A ConstructiOn Dee04 ~ $184,948 $70,78~$114,159 71~ Constraction Dec05 $51,229 $51,22~$0 100~ Construction Jul 05 $2,987,232 $355,901 $2,631,331 12°A Design Dec05 COnstruction in progress. Phase i of c0nstraction is Complete. $299,848 $50,00~3 $249,848 17°A Design Dec 04 $350,000 $350,000 Layering standards are complete. Design 90% cmnplete. Third proposal reqnest being evaluated. EL-04005 i Holly Oak and Christine UG Multi-Year $100,000 $100,000 System Rebuild EL-04006 Welch Road Underground Multi-Year $100,000 $100,000 System Rebuild EL-04007 Holly Oak and Christine UG Multi-Year $100,000 $100,000 System Rebuild EL-04012 Utility Site Security Multi-Year $80,000 $80,000 Improvements EL-04013 Foothills Commuuication Multi-Year $250,000 $250,000 hnprovement Plan $39,725 $310,275 11°/, Design Jul 05 Design 90% complete. $14,300 $85,700 14~ Design Jul 05 Design in progress. $0 $~00;000 0°A Design lnl 05 $0 $100,000 0% Design Ju105 $927 $79,073 1% Design Dec 05 Initial scoping and design in 9rogress. $73,888 $176,1t2 30% Construction Ju105 Automated Meter Reading System $10~Design Dec 05 14 FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE; ENTERPRISE FUND NAME: GAS FUND DEPARTMENT NAME : UTILITIES DEPARTMENT GS-99011 GS-01018 GS-01020 GS-02013 GS-03010 i GS-O~OIO GS-00011 GS-01019 GS-03007 GS-03008 Gas Station Number Three (99ll) All Weather Arastradero (0118) Gas Main Directional (0120) Directional Boring Machine (0213) CNG Seqnential Fuel System (0310) Gas and Water Facility Security Fencing Compress Natural Gas Station (0011) Global Positioning Syste~n 0119) Directional Boring !Equipment (0307) Polyethylene Fusion Equipment (0308) Minor $70,00C Minor ’$275,00C Minor $47,50C Minor $126,00C Minor $75,000 $3,185 $97,792 $1,322 $46,394 $75,000 Minor $199,000 $199,000 Multi-Year $440,000 Multi-Year $381,000 Mnlti-Year $47,500 Multi-Year $25,000 $379,929 $251,198 $43,830 $5,123 $1,537 $97,792 $0 $19,310 $35,138 $198,849 $160,069 $141,712i $27,89fi $5,123 $1,648 $0 $1,322 $27,084 $39,862 $151 $219,86( $109,48( $15,932 $C 98% 100% 97% 79% 47% 10o% 50% 71% 66% 190% Complete Complete Complete Constmction Jun 05 Design Dec 05 Complete Design Dec 05 Constructiou Jnn 05 Construction Jun 05 Complete Remaining balance will purchase chassis for vacumn excavation equipment to support directional boring operations. Redesigning Project PIans. New permits reqnired. Project to bid in Mar 05. Redesigning Project Plans. New permits reqnired. Project to bid in Mar 05. 2rid GPS Base Station installed on tog of UCC1. Roving data collection units in service. Staff training continues. Blanket ~rder established \vith local equipment supplier. 15 . FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: REFUSE FUND DEPARTMENT NAME: PUBLIC WORKS DEPARTMENT Leachate Extraction System Repair and Replacement Landfill Gas Collection and Emission Control Sys Repair and Replace Environmental Services Center (9701) $150,000 $300,000 $150,000 0% Design May 05 $50,000 added during CIP process last year. Contract awarded. $300,000 " 0% Des gn May 05 Contract awarded. $596,531 Jun 10 EIR scheduled to be awarded Nov 15, 2004. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: ~VASTEV~’ATER COLLECTION FUND DEPARTMENT NAME : UTILITIES DEPARTMENT WC-01022 Wastewater Collection System Minor $400,000 $131,697 Master Plan (0122) WC-04013 New Vehicle - Video Truck Minor $130,000 $130,000 WC-04015 New Vehicle - Hydro Minor $275,000 $275,000 Flusher/~acuum Truck $129,519 $130,000 $238,816 $2,178 $0 $36,184 99% Complete 100% Construction Mar 05 87% Complete Purchase order completed. Expected delivery Mar 05~ FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROG1L, kM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: WASTEWATER TREATMENT FUND DEPARTMENT NAME: PUBLIC WORKS DEPARTMENT WQ-98005 Effluent Line Modification (9805) WQ-02150 500 KW Emergency Generator (0215) WQ-04012 Landfill Gas Incineration WQ-95040 Interceptor Maintenance Cleaning and Repair (9504) WQ-97070 Wastewater Solids Disposal Project (9707) WQ-04010 Replacement of Existing Reclaimed Water Pipes WQ-04011 Facility Condition Assessment and Retrofit Minor $150 00($43 784 $0 $43,784 71°A Complete Minor $150,00($41,181 $0 $41,181 "73°A Complete Minor $500,00($500,000 $500,000 $C 100% Constnlction Jnn 05 Multi-Year $1,750,00C $68,713 $35,654 $33,059 ’ 98% Complete Multi-Year $7,641,706 $189,374 $96,876 $92,498 99% Complete At~erbumer replacement and piping construction on schedule. Multi-Year $800;00C ~800,000 $299,763 $500,237 37% Pre-Design Jun 07 Applied for St’ate Grant of $4 million to help finance pipeline to Mr. View. Multi-Year $I50,0013 $150,000 $149,974 $26 100% Pre-Design Jun 07 Completed phase I and beginning phase II. FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: \VATER FUND DEPARTMENT NAME: UTILITIES DEPARTMENT Mayfield Reservoir Roof Repairs (0109) WS-01013 Irrigation Meter Installation Program (0113) WS-01014 Land Acquisition for a reservoir, a well and pump station. (0114) WS-02017 Water Bottling Equip (0217) WS-04016 New Vehicles W1-87049 Water Reservoir Improv. (8749) WS-97004 Water System Study (9704) WS-01008 Foothills PRV Installation (0108) WS-01010 Reservoir Booster Improvements (0110) WS-01011 Distribution System Water Quality Enhaucement (0111) Minor $60,000 $59,335 Minor $2,000,000 $1,999,055 Minor $25,000 $24,43( Minor $100,000 $100,00( Multi-Year Not $6,50] Availabh Mnlti-Year . $275,000]$40,59£ Malti-Year $236,00($235,151~ Multi-Year $1,360,00C $1,284,327 Multi-Year .$457,00C $434,279 $0 $0 $14 $0 $18,474 $1,961 $155 $202,006 $554,17Z $163,644 $59,335 $1,999,041 $24,43C $81,526 $4,541 $40,443 $33,144 $730,150 $270,635 Complete 1~ Pre-Design 0°A Pre-Design 2~ Pre-Design 18~ Design Complete 85N Complete 86°/~ Construction 46% Construction 41% Constnmtion TBD Jan 09 Jun 05 Jun 05 Aug 05 Aug 05 Aug 05 Having difficulty with customers taking advantage of program benefits. EIR report in progress for new reservoir Carollo Engineering design of booster station improvements has been completed. Construction Contract to be awarded Nov 04. Carollo Engineering design of booster station improvements has been completed. Constmction Contract to be awarded Nov 04¯ Carollo Engineering design of booster station improvements has been completed. Constn~ction Contract to be a~varded Nov 04. 19 FY 03-04 MID-YEAR CAPITAL IMPROVEMENT PROGRAM PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: WATER FUND DEPARTMENT NAME: UTILITIES DEPARTMENT WS-01012 Booster Station (0112) WS-02004 Existing Well Rebab (0204) WS-02005 E1 Camino Park Reservoir and Pump Station (0205) WS-02006 El Camino Park Well (0206) WS-02007 Middlefield Road Well Site (0207) Multi-Year $205,000 $193,310 Multi-Year $3,160,000 $3,159,400 Multi-Year $1,700,000 $t,634,745 Multi-Year $280,000 $213,659 Multi-Y~ar $930,000 $929,73~ WS-02008 Eleanor Pardee Park Well Multi-Year $930,00~$929,451 (0208) WS-04004 Mayfield Pnmp Station Mnlti-Year $545,00($545,00C $85,83~ $35,261 $453,866 $44,923 $117,959 $62,742 $34,355 $107,471 $3,124,139 $1,180,879 $168,736 $811,778 $866,710 $510,6451 48% Design 1% Pre-Design 31% Pre-Design 40% Pre-Design 13% Pre-Design 7% Pre-Design 6°A Pre-Design Aug 05 Jun 05 Jun 05 Jun 05 Jun 05 Jan 05 Jun 07 Carotto Engineering design of booster station improvements has been completed. Construction Contract to be awarded Nov 04. Carollo Engineering is preparing CEQA/EIR documentation for all Water Stndy Project Design. Carollo Engineering is preparing CEQA/EIR documentation for all Water Study Project Design. Carollo Engineering is preparing CEQA]EIR documentation for all Water Study Project Design. Carollo Engineering is preparing CEQA]EIR docnmentation for all Water Study Project Design. Carotlo Engineering is preparing CEQMEIR documentation for all Water Study Project Design. Carollo Engineering is preparing CEQA/EIR documeutation for all Water Study Project Design. Design will be tart of Phase III. 2O FY 03-04 YEAR-END CAPITAL IMPROVEMENT PROG1L~,M PROJECTS STATUS FUND TYPE: ENTERPRISE FUND NAME: MULTI FUNDS DEPARTMENT NAME: UTILITIES/PUBLIC WORKS EL-99005 Utilities Bill Print Design (9905) EL-93057 Utilities Customer Info. System (9357) Multi-Year $845,539 $435,508 $0 $435,508 48% Construction Jun 06 Multi-Year $5,366,553 $1,452,990 $315,498 $1,137,492 79%Construction Jun07 eBPP enhancements are being ~ursued. Bill format is being reviewed and revmnped, Streamlining initiatives are being ~ursued. This could entail tool ~urchases and trai,ning for those tools. Server upgrades and CIS upgrades are on-hold due !o the pursuit of SAP’s Utility module. We will be researching and positioning for the mssible move to SAP. Archiving and purge software tools are being researched and an RFP is being developed. The timing of the SAP Utilities study will determine the need for the actual ~mplementation of an archive and nlrge filnction for our current CIS. 21 Attachment B LIST OF CONTINUOUS PROJECTS Administrative Services TE-86014 (18614) TE-96018 (19618) TE-99014 (19914) Financial Database Upgrade GIS Application New Computer Acquisitions Community Services AC-86017 (18617)Art in Public Places PG-94015 (19415)Park Facilities Improvements Public Worlcs General Fund PO-89003 (18903) PE-86070 (18670) PF-90018 (19018) PE-91001 (19101) PF-93009 (19309) Sidewalk Improvements Street Improvements (Street hnprovement Fund) Cubberley Building Code Modification Tank Investigation and Removal ADA Compliance Storm Drainage Fund SD-88070 (8870)Collection System Improvements Wastewater Treatment WQ-80021 (8021) WQ-80022 (8022) RWQCP Plant Equipment Replacement RWQCP System Flow Metering Utilities Electric Fund EL-89028 (8928) EL-89030 (8930) EL-89031 (8931) EL-89038 (8938) EL-89044 (8944) EL-93054 (9354) EL-97003 (9703) EL-98001 (9801) EL-98002 (9802) EL-98003 (9803) Customer Design i~nd Connection Services Traffic Signals Upgrade Communication System Improvements Substation Protection Improvements Substation Facility Improvements Street Li~t Replacements ¯ Underground Cable and Equipment Replacement Fiber Optics Ring System Improvements Fiber Optics Customer Design and Connection Services Electric Distribution System Reconstruction and Improvements Gas Fund GS-80017 (8017) GS-80019 (8019) GS-92030 (9230) GS-04003 Gas System Extensions Gas Meters and Regulators Natural Gas Vehicle Conversions and Purchases Gas Main Replacements Wastewater Collection WC-80020 (8020) WC-04002 Water Fund WS-80013 (8013) WS-80014 (8014) W8-80015 (8015) WS-02014 (0214) WS-04001 Sewer System Extensions Sewer System Rehabilitation and Augmentation Water System Extensions Service and Hydrant Replacements Water Meters Water-Gas Wastewater Utilities GIS Data Water Main Replacements