HomeMy WebLinkAbout2004-12-06 City Council (4)City of Palo Alto
City Manager’s Report
TO:
FROM:
HONORABLE CITY COUNCIL
CITY MANAGER
4
DEPARTMENTS: PUBLIC WORKS,
PLANNING & COMMUNITY ENVIRONMENT
DATE:DECEMBER 6, 2004 CMR:498:04
SUBJECT:REQUEST FOR COUNCIL DIRECTION TO PROCEED WITH
CONCEPTUAL DESIGN AND INITIATE A COMBINING ZONING
DISTRICT FOR THE CIVIC CENTER POLICE (PUBLIC SAFETY)
BUILDING PROJECT- CAPITAL IMPROVEMENT PROGRAM PROJECT
PE-98020
RECOMMENDATION
Staff recommends that the Council direct staff to proceed with conceptual design and initiate a
combining zoning district for the Civic Center Police (Public Safety) Building Project, Capital
Improvement Program Project PE-98020.
BACKGROUND
The 1997 feasibility study prepared by Ekona Architecture and Planning identified numerous
deficiencies with the current police facility. In addition to a lack of space, the building does not
conform with current State legal standards and codes, is operationally deficient; and it does not meet
many programmatic needs including property and evidence, detention, facility support and warehouse
functions. The study confirmed that the Police Department was in violation on a number of codes
and was unable to comply with certain standards relating to prisoner processing (keeping minors and
adults separated) and evidence processing, handling, and storage. A May 2004 report by the Santa
Clara County Civil Grand Jury confirmed the deficiencies, including the lack of storage space for
evidence items and proper ventilation for narcotics and other evidence. The study also found that the
existing electrical service and infrastructure was inadequate, has no capacity for expansion, and would
have great difficulty accommodating new technologies. In the event of a major earthquake, it could
render the current facility inoperable, including the City’s Emergency Operations Center (EOC) and
9-1-1 Dispatch Center.
On July 29, 1997 Council authorized staffto initiate the formal process needed for site selection and
construction of a new public safety building (CMR:342:97). In response to this Council direction
staff did extensive public outreach, identified a short list of four potential sites, did preliminary
environmental assessments and economic analysis of the four sites, looked at a split facility option,
prepared building diagrams and a developed and refined an architectural program for this project. In
CMR:498:04 Page 1 of 7
November 2001, Council approved a contract amendment #3, with Ross/Drulis/Cusenbery Architects
(RDC) for conceptual design that included the following tasks:
assess the current police facility at the Civic Center site
evaluate four building scenarios at the Civic Center site
evaluate utility infrastructure
evaluate communications and life safety systems
develop seismic design criteria meeting essential facility standards
complete an environmental assessment and certification
complete the conceptual design of the preferred option
continue to meet with the community
obtain the necessary approvals from the various City commissions and boards
In July, 2002 (CMR 314:02), staffpresented information to the council on the four potential options
for the expansion and renovation of the current police facility including the conceptual drawings, cost
estimates, and a preliminary environmental assessment. Staff and the consultant determined that the
most operationally efficient and cost effective building at the Civic Center site would be a four story
building. This option would entail the demolition of the existing structure, removal of the council
chambers roof, the expansion of the first floor and mezzanine levels and the addition of a second and
third floor. This option is the least expensive alternative when compared to the other sites in the City.
Construction cost estimates provided to Council in 2002 dollars ranged from $38 to $45 million. It is
important to note that initial projections at the beginning of this project included space needs of over
66,000 square feet. Staff has reduced the space needs to approximately 50,000 square feet, the
minimum amount of space that would meet the full programmatic requirements of the department for
the next 20 to 30 years.
DISCUSSION
Conceptual design work to-date has consisted of:
¯a preliminary needs analysis
¯development of a preliminary environmental assessment
¯preparation of cost estimates
~,development of massing diagrams
¯development of green building design alternatives
Dimensions such as building height, setbacks and floor area ratios (FAR) require further verification
during this conceptual design phase (see Attachments A and B). The projected building height is
approximately 60 feet above the surrounding sidewalk. Staff is prepared to proceed with the
completion of the concept design for this project upon Council direction.
The Civic Center Building, constructed in 1970, is located in the Public Facilities (PF) Zoning
District. The Civic Center administration, including the police building, is a permitted use in the PF
Zone. The Civic Center parking structure is considered an accessory use to the Civic Center. The
last major update to the PF zoning district in Title 18 (Zoning Ordinance) of the Palo Alto Municipal
Code was in 1978. The PF zoning district addresses many public facility uses and sites throughout
the City of Palo Alto, which are less intense in building size, height and massing than the existing
CMR:498:04 Page 2 of 7
Civic Center Building. Therefore, the development standards for the PF zoning district that were
primarily developed after the Civic Center was built are more restrictive than what currently exists on
the Civic Center site. Table A, below, illustrates the existing PF standards with the Civic Center
building as well as the proposed police building expansion and comparison with the surrounding
Downtown Commercial (CD) zoning district. The existing PF development standards need to be
modified for the Civic Center site in order to address:
the current and future programmatic needs
the operational and technological deficiencies
the inability to meet current codes and standards required for a police building
Staff is proposing that the City Council initiate the preparation of a Civic Center Combining District
that would be applied as an overlay zone to the PF zoning to accommodate the police building
expansion concept plan. The Civic Center Combining District would only be applicable to the Civic
Center site and no other PF facility in the City, including the Downtown Library. The Combining
District would allow specific flexible development standards, including Floor Area Ratio (FAR),
building height, building setbacks and parking, as follows:
Floor Area Ratio. FAR represents the total (gross) floor area of all buildings on site in relation
to the site area. It is the method used in the Zoning Ordinance to describe the bulk or mass of
building volume on a specific site. The higher the FAR ratio of the building to the site (i.e., 1.0
to 1.0) oiten results in more massing and scale as it relates to the height of the building. The
proposed FAR for the Civic Center Combining district would be 1.5:1. The PF zone currently
allows a maximum FAR of 1.0:1. However, the Civic Center building has an existing FAR of
1.11:1. The increase in FAR for the police building would not substantially increase the massing
or bulk of the entire Civic Center buildings relative to the site because of the existing high-rise
tower element on the site.
Building Height. The proposed combining district would allow the building height for the
proposed police building to be increased to a maximum of 60 feet. Although the existing mid-
rise portion of the Civic Center is approximately 35 feet in height and the high-rise portion is
approximately 130 feet in height, the PF zone allows a maximum building height of 50 feet.
Therefore, although still substantially less than the height of the existing Civic Center, this
flexible development standard would provide for the expansion of the police building. In
addition to the maximum building height of 50 feet, the PF zone also has a building height
standard of 35 feet for any portion of a site that is within a 150 foot radius of any low density,
multi-family or applicable Planned Community (PC) zoning district. The Civic Center site,
specifically the police building, is within 150 feet of two multifamily zoning sites; a Multi-Family
(RM-30) and a PC zone, (see Attachment A). Both multi-family sites are located on opposite
comers of streets (Bryant Street/Forest Avenue and Ramona Street/Forest Avenue) and are
three story buildings.
Building Setbacks. The existing Civic Center building including the parking podium wall is
essentially built out to the back of the sidewalk with some limited landscaped buffers. The PF
zoning, however, requires a minimum of a 20-foot setback from property line. Insofar as the
CMR:498:04 Page 3 of 7
existing building does not meet this setback requirement, and both the Civic Center and
sidewalk public right-of-way are City-owned properties, the proposed Civic Center Combining
¯ District would provide no requirements for setbacks for the police building expansion.
Although the architectural analysis does include setbacks for landscaped buffers at some
locations, the maximum 20-foot setback requirement could not be met. It should also be noted
fhat the CD district that adjoins three sides of the Civic Center site has no requirements for
building setbacks. The anticipation is to design the faoility with a 15-foot landscape buffer for
the main building. However, the main entrance will require this element to be set at the
property line. Considerations for landscaping and buffers will be addressed through the
Architectural Review Board (ARB) process.
Parking. Staff is anticipating adding a parking development standard to the Civic Center
Combining District because the project does not propose to add new parking. However, this
item is still being analyzed. The central issue for parking requirements is how to determine the
most efficient parking needs for the police building. The existing PF zone would require a
parking ratio of one space for each 250 s.f. for the new police building. A joint use facility may
have the parking requirement reduced by up to 20% of the total parking requirement.
The police building represents a unique use with respect to parking requirements. Based on a
program use, it may result in less parking than required for the PF zone. Two examples to illustrate
this are: 1) the uses of some of the building area for property and evidence processing and storage,
detention facility, locker and workout rooms, and the City’s Emergency Operations Center and the
Emergency 9-1-1 Dispatch Center; and 2) staffing rotates on a 24 hour period rather than the typical
employee hours of an administrative office. Therefore, staff is still analyzing the most efficient
application of parking standards to be included in the Civic Center Combining District and programs
that would address any new parking requirements.
CMR:498:04 Page 4 of 7
Table A - ZONING SITE DEVELOPMENT REGULATIONS
COMPARISON TABLE :
SITE
DEVELOPMENT
REGULATIONS
FAR
Height mid,rise
Height within 150’
of RE,R-1,R-2,
RM, PC/SF or MF
Setbacks as
applicable
Parking
EXISTING
CONDITIONS
1.11
35
35
Back of sidewalk
Civic Center
Garage Joint Use
PUBLIC
FACILITIES
(PD
1.0
50 feet
35 feet
20 feet from
adjoining streets
1 space/250
gross sfwith
20% reduction
for joint use
facilities
COMMERCIAL
DOWNTOWN
(CV)
1.0
50 feet
Equal the most
restrictive
residential district
No Requirement,
except 10 ft if
opposite RE, R-l,
R-2, RM, PC/SF or
1 space/250 gross sf
CONCEPTUAL
PROJECT CIVIC
CENTER
COMBINING
DISTRICT
(CCCD)
1.5 ¸
(Proposed project
FAR is
approximately
1.46)
60 feet
60 feet
No Requirement
(ARB review for
landscaping and
buffer design)
None provided.
In-lieu parking
fees for additional
sf as determined
by: 1 space/250
gross sfplus 20%
reduction, or as
determined by
increased program
use, whichever is
less.
CMR:498:04 Page 5 of 7
Due to the project delay over the last two years, the current scope of services with RDC will require a
consultant amendment next spring to cover fee increases, and additional studies necessary to certify
the environmental assessment. These studies were not initially required, but will be necessary and will
include a shadow study, a parking study, a temporary staff relocation plan and a traffic study
evaluating adjacent signalized intersections. The project conceptual design and environmental
certification is expected to be complete by late next year. Staffanticipates the initiation and approval
of the combining zoning district will not delay the project schedule as the approval process will run
concurrently with the environmental review process.
RESOURCE IIVIPACT
In 1998 Council approved a BAO for CIP PE-98020 police building project, in the amount of
$275,000 (CMR 261:98). In 1999, Council approved a BAO for a consultant contract amendment #1
to provide fiscal analyses of four sites and a split-facility study in the amount of $90,028
(CMR:256:99). In 2000, Council approved a BAO for consultant amendment #2 to provide a
detailed analysis on the potential use of the Downtown Library site in the amount of $74,000 (CMR
319:00). In 2001, Council approved a contract amendment #3 for Conceptual Design, Phase 2 inthe
amount of $380,000 (CMR 375:01). Current total expenditures are $819,028. In April 2004, staff
updated Council on the project, informing them that progress had been suspended due to the
economic downturn the City was experiencing. A consultant amendment is anticipated in Spring
2005 to complete this conceptual design phase.
Currently there is no funding plan for the proposed police building project. As this facility is
considered new infrastructure, current Council policy is that "new facilities require new funding
sources." Staff is reviewing several potential funding options which include working with a newly
formed resident group, the Palo Alto Police Foundation, analyzing potential new revenue sources
such as a 911 service fee, a business license tax or an increase in the transient occupancy tax. Other
potential sources could include issuance of new City Hall Renovation Certificates of Participation
(COPs) using rents for leased space as a funding source. Staffis planning to proceed with the work
needed to achieve a 30 percent design that will be used to determine the level of funding required for
the police building project. Staffwill return with specific funding plan options at the time.
PROJECT REVIEW ’
1. This project was initially funded in FY 1996-97.
2. This project has been reviewed various times as noted in Attachment C.
POLICY IMPLICATIONS
This request is consistent with existing City policies.
ENVIRONMENTAL ASSESSMENT
The project is subject to the requirements of the California Environmental Quality Act (CEQA). An
Initial Study will be completed during this conceptual design phase. Initial environmental analysis
indicates that a Mitigated Negative Declaration would be required for the proposed project. Areas of
potential impacts that would be analyzed include sun/shadow impacts, short-term construction
(including noise), visual and traffic impacts and the temporary relocation of the Police Department.
CMR:498:04 Page 6 of 7
ATTACHMENTS
Attachment A:Police Building Site plan
Attachment B:Police Building Sections
Attachment C:Police Building Project Timeline
PREPARED BY:
DEPARTMENT HEAD:
DEPARTMENT HEAD:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
ELIZABETH AMES, Senior Engineer
Chief of Police
GLENN S. ROBERT~.~S~
/ STEVE #MSLIg -/
Director of Planning and Community
Environment
Assistant City Manager
CMR:498:04 Page 7 of 7
ATTACHMENT C
POLICE BUILDING PROJECT TIMELINE
1985 First needs assessment completed.
1996 Second needs assessment was initiated. EKONA Associates hired to complete
assessment.
July 28, 1997 (CMR:342:97) Preliminary needs assessment completed by EKONA
Architecture and Planning. Council directs staff to formally initiate the process for site
selection and construction of a new public safety building and to further explore the
alternative of expanding the current facility.
October 20,1997 (CMR:431:97) Council approves scope of services for consultant
assistance with site evaluation and selection, project development, and concept designs
and direct staff to issue RFP.
December 8, 1997 (CMR:490:97) Council approves revised scope of services for
consultant assistance with site evaluation and selection, project development, and concept
designs and direct staff to issue RFP.
June 8, 1998 (CMR:261:98) Council approves: 1) BAO for $275,000 to fund project
development, Phase 1, for Public Safety Building CIP 19820; 2) contract for $240,700
with Ross/Drulis Architects and Planners; 3) authorize City Manger to execute change
orders not to exceed $24,000.
September 22, 1998 (CMR:364:98) Informational report no Council action taken.
Report details plans for a significant public outreach process. Through the City
Manager-appointed Advisory Committee which included members of neighborhood
associations, ARB, Planning Commission, Chamber of Commerce, CAADA, and others
along with representatives from Planning, Police, Fire, Public Works, and ASD were
instrumental developing the public outreach process. Community outreach included one
general meeting cablecast over local channel, three subsequent meetings, and a fifth
community meeting to obtain feedback on the 4 potential sites on the short list ......
December 1, 1998 (CMR:422:98) Finance Committee INTEGRATION OF NEW AND
EXISTING INFRASTRUCTURE NEEDS.
March 1, 1999 (CMR:151:99) Council approves staff proposal to proceed with ....
conceptual designs, cost estimation, and environmental assessments on the following
potential sites for a public safety building, identifying creative and cost effective
opportunities to deal with current site deficiencies (split-facility) and performing a cost
analysis of the options: Sites included: 1) Existing Police Building; 2) City Parking Lot 6,
251 Sheridan; 3) 2747 and 2785 Park Blvd. The fourth site, at the Downtown Library,
270 Forest Avenue was removed from the list. In its place the site at the comer of Page
Mill and E1 Camino Real was added.
May 24, 1999 (CMR:256:99) Council approved BAO for $90,028 to cover costs
associated with a split-facility study, fiscal impact of four sites; and additional public
outreach meetings.
June 12, 2000 (CMR:279:00) Report to Council at study session on results of Phase 1
associated with four sites under consideration for a new public safety building. Report
summarized findings, provided a summary of advantages and disadvantages of each site
and the split-facility concept. In light of significant cost estimates of the four sites, the
Downtown Library at 270 Forest Ave was to be reconsidered as a possible location.
Additionally, staff agreed to look at reducing program and size of project to result in
lower costs.
July 17, 2000 (CMR:319:00) Council approved BAO of $74,000 with (Ross Drulis
Cusenbery Architects (RDC) for contract amendment #2 to include additional work
associated with Phase 1 of Public Safety Building. Funds will cover costs associated
with analysis of the potential use of the Downtown Library site and a program reduction
study to determine further potential decreases in Police Department space and area
requirements.
July 2, 2001 (CMR:291:01) Council approved in concept the current building site at 275
Forest Avenue for a facility expansion/modemization project and directed staff to
proceed with the conceptual design. After further study, staff had concluded that the
Downtown Library should be removed from the list of potential sites and focused on
reducing space needs requirements. Staff identified four potential options for
modernization/expansion and will analyze each option and return with a
recommendation. Funds of $400,000 are included in the 2002-04 CIP to cover costs
associated with the conceptual design phase of the project.
November 13, 2001 (CMR:375:01) Council approves: 1) contract amendment #3 with
RDC in the amount of $380,000 for the Public Safety Building Project Conceptual
Design phase CIP 19820; 2) authorize City Manger to execute change orders not to
exceed $20,000 .................
July 15, 2002 (CMR:314:02) Informational report and no Council action required. This
report analyzed the four potential options for expansion and renovation of the current
facility, including seismic evaluations, operational and logistical reviews, cost estimates
and potential environmental impacts. After review of the information on each, only one
option met the programmatic needs of the Police Department, which tumed out to be the
lease costly of the four. Staff announced that it was going to proceed with the schematic
design of the selected option in order to determine the level ~f--actually required for the
project.
April 19, 2004 (CMR:224:04) Informational report and no Council action required.
General update on project was presented. In fall of 2002, staff had decided to halt
progress on project until City’s financial condition improved or new funding sources
were identified. In early 2004, due to recently identified potential funding options, staff
resumed the conceptual design phase of the project. Staff announced that it is planning to
hold a study session with ARB and provide information to the Planning and
Transportation Commission and Council within six months.