HomeMy WebLinkAboutStaff Report 8231City of Palo Alto (ID # 8231)
City Council Staff Report
Report Type: Action Items Meeting Date: 8/28/2017
City of Palo Alto Page 1
Summary Title: Finding Palo Alto Fire Station No.3 Substantially Complex
Title: PUBLIC HEARING: Adoption of Finding That the Fire Station No. 3
Replacement Project (CIP PE-15003) is "Substantially Complex" Under Public
Contract Code Section 7201 and Direction to Increase the Retention Schedule
From 5 Percent to 10 Percent
From: City Manager
Lead Department: Public Works
Recommendation
Staff recommends that Council consider the following motions:
1.Find the proposed Fire Station No.3 Replacement Project “substantially
complex” under Public Contract Code Section 7201 based on the reasons
set forth in the staff report, and
2.Allow this project to be advertised for bid with a retention amount of ten
percent.
Executive Summary
State law limits the City to five percent retention on public works projects unless
City Council makes a formal finding that the project is “substantially complex.”
This finding must be made before the project can be advertised for bid. Staff is
preparing to issue the formal Invitation for Bids (IFB) for the Fire Station No.3
Replacement Project. The IFB is expected to be released in September 2017.
Background
Public Contract Code Section 7201 requires public agencies to limit contract
retention on public works projects to 5%, unless the project is found to be a
“substantially complex project”. Retention is a contractual withholding of money
by the City to cover any unexpected expenses, such as liens or poor workmanship,
City of Palo Alto Page 2
that may occur before the project is completed and accepted. The standard
procedure is to return the retention once the following occurs: work is
completed, the contractor provides the maintenance bond, the City accepts the
project, and the lien period expires.
Public Contract Code Section 7201(b) states, “retention proceeds withheld from
any payment by a public entity from the original contractor…shall not exceed 5
percent of the payment” and “…in no event shall the total retention proceeds
withheld exceed 5 percent of the contract price.” However, Section 7201(b)(4)
provides that an awarding agency may withhold in excess of five percent (5%) on
specific projects where the governing body has approved a finding during a
properly noticed and normally scheduled public hearing and prior to bid that the
project is substantially complex and therefore requires a higher retention amount
than 5 percent. Section 7201(5) further provides that any finding by a public
entity that a project is substantially complex “shall include a description of …why
it is a unique project that is not regularly, customarily, or routinely performed by
the agency or licensed contractors.”
The awarding entity must include both this finding and the actual retention
amount in the bid documents.
Discussion
The Fire Station No. 3 Replacement Project is part of the Council Infrastructure
Plan.Funding for the Project was approved in Fiscal Year 2017 Adopted Capital
Budget, and is available in the Capital Improvement Program project PE-15003 in
the amount of $7.2 million.
The existing Fire Station No.3, located at 799 Embarcadero Road in Palo Alto is a
one-story,wood-framed structure built in 1958 and has had minimal
improvements over the past 59 years. The new Fire Station No.3 will replace the
aging station and be built as an Essential Services Facility in accordance with the
Essential Service Building Seismic Safety Act. The new two-story, 6,663 square
foot fire station will meet current California Building Codes, Americans with
Disabilities Act, National Fire Protection Association codes and standards,follow
Environmental, Health, Safety guidelines,and comply with OSHA laws and
regulations.
City of Palo Alto Page 3
The Architectural Review Board recommended approval of this project, and the
Director of Planning and Community Environment approved the project in March
2017. The plans include site integration features that relate with the surrounding
environment. The main materials to be used on the project are a red/orange terra
cotta and zinc metal paneling which will be installed using rain screen application
to maximize energy performance as well as indoor air quality. The roof will
contain a photovoltaic array and be screened with high parapets. The station will
be a wood-framed structure with supporting steel elements on a structural mat
foundation.The station will include a pedestrian plaza, a bicycle queuing area,
public art, landscaping that will incorporate protected trees, new regional
indigenous drought resistant plant material,and a stormwater collection system
integrated with a cobblestone dry steam bed. All these features and more will
allow for a Silver Certification in Leadership in Energy and Environmental Design
(LEED).Additionally the new station will incorporate an alarm and communication
system essential for fire and medic response to the neighborhood served by Fire
Station No. 3.
The construction of New Fire Station No. 3 will require the station to be relocated
to an interim facility located at 2000 Geng Road. The temporary facility will
accommodate the station’s three on-duty personnel and two apparatus (the
engine, and medic car) for a span of approximately 18 months while the existing
site is demolished and the new fire station is constructed.
The construction cost is estimated to be $5.5 million and is expected to be
completed at the end of 2018. The contractor will be required to subcontract for
numerous specialties including abatement of asbestos-containing material,
building envelope, fire alarm and communication systems. The project will require
the coordination of multiple construction disciplines while maintaining right-of-
way access within a heavily used intersection of Newell and Embarcadero Roads.
City staff has determined and recommends that Council find the Fire Station No. 3
Replacement Project to be “substantially complex”based on the large amount of
work required, the various disciplines and trades involved in the construction,the
measures to obtain LEED certification, and the work associated with Essential
Services construction.The Essential Services Buildings Seismic Safety Act requires
the facility be “constructed to minimize fire hazards and to resist…the forces
generated by earthquakes, gravity, and winds.” The City Clerk has published the
City of Palo Alto Page 4
required notice of this hearing in the Palo Alto Weekly starting on August 18,
2017.
The retention will be released as described in the City of Palo Alto’s standard
contract General Conditions Section 9.8.1 which states, “Upon receipt of notice
from Contractor that the Work is ready for final inspection, City will make such
inspection. The City will file a Notice of Completion (NOC) with the County Clerk
within ten (10) days after Acceptance by the City. Thirty-five (35) Days after filing
the NOC, the City may release the final retention provided the requirements in
this paragraph are met.”
Timeline
Staff plans to issue an IFB for the project in September. Fire Station No. 3 will be
relocated to the temporary site at 2000 Geng Road in October 2017. Demolition
and construction of Fire Station No. 3 is expected to begin shortly after relocation
to Geng Road and completion anticipated in early 2019.
Resource Impact
There are no resource impacts associated with finding the project “substantially
complex”.Funding for the Fire Station No.3 Replacement Project including the
temporary station is available in Capital Improvement Program (CIP) Project PE-
15003.
Policy Implications
The proposed action is consistent with City policy.
Environmental Review
This project is categorically exempt from the provisions of the California
Environmental Quality Act (CEQA) under Section 15302 of the CEQA Guidelines as
“Replacement or Reconstruction of Existing Structures”and no further
Environmental review is necessary. A notice of CEQA exemption was filed in early
March 2017.