REQUEST TO PRELIMINARILY APPROVE
REAPPROPRIATION REQUESTS
2003-04
RECOMMENDATION
The Finance Committee recommends that the Council preliminarily approve the 2003-04
reappropriations (Attachment 1).
COMMITTEE REVIEW AND RECOMMENDATIONS
The Finance Comnai~ee recommends approval of the 2003-04 reappropriation requests with
the following qualifications:
1)The reappropriation of $86,600 for Downtown North and Lytton neighborhood
traffic cahning expenditures may only be used for devices already authorized by City
Council.
2)The reappr0priation of $43,000 for the Parking District Educational Brochure not be
approved. Staff is requested to report back to Council on discussions with the
Chamber of Commerce and the Planning and Transportation Commission on the
need for parldng educational materials. In addition, it was requested that the impact
of the downtown parking plan, specifically the hourly parking limit, on sales tax
revenues be reviewed. Staff believes the information contained in the July 12, 2004
(CMR:341:04) Status Report on Downtown and California Avenue Parking
addresses the Finance Committee’s concerns on the need for parking educational
materials, and will also be prepared to provide information regarding the Chamber’s
recommendation at the Council meeting.
ATTACHMENTS
Attachment I:CMR 357:04
CMR:406:04 Page 1 of 2
PREPARED BY:
MARY DIVINSKI
Sr. Financial Analyst
DEPARTMENT HEAD APPROVAL:
CARL YEATS
Director,Services
CITY MANAGER APPROVAL:
HARRISON
Assistant City Manager
CMR:406:04 Page 2 of 2
ATTACHMENT 1
of
Manager’s Repor
TO:HONORABLE CITY COUNCIL
ATTENTION:FINANCE COMMITTEE
FROM:CITY MANAGER DEPARTMENT:ADM][N][STRATIVE
SERVICES
DATE:
SUBJECT:
JULY 20, 2004 CMR: 357:04
REQUEST TO PRELIMINARILY
REAPPROPRIATIONS REQUESTS
"RECOMMENDATION
Staff recommends that the Finance
reappropriations (Attachment 1).
Committee preliminarily
APPROVE 2003-04
approve the 2003-04
BACKGROUND
As a par~ of the typical year-end process, depamnent staff world with the Administrative
Services Depamnent (ASD) to review outstanding financial obligations as of year-end. In
the course of regular operations, these items span two fiscal years m the p~ocessing--
planning in one fiscal year and actual payment in the next. This necessitates carrying
forward both encumbered and budgeted amounts. Council approves these carry forward
items in the year-end closing ordinance, once the accounting books are closed. Staff
utilizes the reappr0priation process if base funding in the followfng fiscal 3’ear cannot
accommodate the expense. ASD staff works with departments to minimize the need for
reappropriation and ultimately rejects requests that lack merit.
In 1995, the Fiscal Procedures Chapter of the Municipal Code (Chapter 2.28) was
amended to implement mission driven budgeting and the 2-year budget process
(CMR:212:95; CMR:155:95). Section 2.28.090 governing reappropriations was
amended to allow Council to preliminarily authorize reappropriations of non-capital
appropriations at the beginning of the fiscal year with final authorization to be made at
the time of adoption of the budget closing ordinance. The purpose of this was to ease
difficulties experienced by the departments caused by the late final approval of the
reappropriations where the reappropriation was justified and sufficient funds from the
prior year are Clearly available. With ASD oversight, preIiminary approval allows the
CiVf1<:357:04 Page 1 of 3
department to continue with normal operations and spend the funds as .of the Council’s
prelimina~3~ approvai date rather than the year-end ordinance approva! date.
To this point, the City has not been able to utilize the preliminary reappropriation process
because of delays involved with the IFAS financial system, which required the manual
entry ofreappropriation amounts into the new year’s budget. The standard practice was to
post the reappropriations after the Council approved the close of the fiscal year. Final
Council approval would occur in January, resulting in at least a 7-month !ag-time for
these carry-forward items to be posted in the system.
DISCUSSION
With the implemep2ation of SP~P, there is an opportunity to take adva.~Xage of system
efficiencies by allowing the system to automatically post the previous year’s
reappropriations with the other encumbered carry-forwards as of the beginning of the
new fiscal year. As noted above, the City of Palo Alto Municipal Code (Section 2.28.090)
allows the "preliminary" approval of reap.propriations, as .long as final approval is
included with the normal year-end closing ordinance. The preliminary reappropriation
action allows for an early review of unconwnitted funds in a just-concluded fiscal year for
possible carry-forward into the next. Attachment 1 identifies those reappropriation
requests that ASD recommends for preliminary approval. Final approval will be
requested by Council after the books are closed.
RESOURCE IMPACT
Staff has determined that sufficient uncommitted budgeted funds do exist to allow for the
preliminary approval of the attached 2003-04 reappropriations list (Attachment !).
General Fund proposed reappropriations total $444,322 along with $44,123 within a
housing Special Revenue Fund. For comparative purposes, Council approved a similar
operating amount ($311,67!) in 2002-03.
POLICY IMPLICATIONS
This recolmaendation is consistent with adopted Council policy.
ENVIRONMENTAL REVIEW
The action recommended is not
Environmental Quality Act.
a project for the purposes of the California
ATTAC2’-iMENT
Attachment 1:2003-04 Reappropriations List
CMR:357:04 Page 2 of 3
PREPARED BY:
DEPARTMENT HEAD APPROVAL:
~ P
MARY DIVNSKI
Senior Financial Analyst
CARL YEATS /
Director, Adm]ffistrative Services
CITY M~_NAGE.2
HARP so
Assistant City Manager
CMR:357:04 Page 3 of 3
Attachment 1
REAPPROPPdATION REQUESTS
$
Planning Department
$60,000
$68,700
$86,600
Zoning Ordinance
Update
Stanford _/!-!_yatt Serfior
Housing Project
Downtown North &
l..~ytLOIl
This reappropriation is.being requested in order
to utilize public outreach, including focus
groups, website access and study sessions to
ensure ongoing community input of changes
being proposed. These funds were left unspent
in 2003-04, in order to match outreach effort
timing to presentation of each phase of the
zoning code as it has been completed.
This reappropriation is being requested in order
to provide the services for which the City has
already been paid. The FY 2003-04
expenditures were carefully timed to meet the
project requirements, resulting in a balance at
year-end. This project will continue into FY
2005-06
This reappropriation is being requested because
the trial of traffic calming devices and
community discussion of alternatives
continued well into FY 2003-04. Remaining
funds will be used to continue the trial of
traffic calming devices in the area and rrfitigate
impacts in the Lytton neighborhood.
Recommended $60,000. There is
sufficient balance in the 2003-04
budget that can be reappropriated.
Recommended $68,700. There is
sufficient balance in the 2003-04
budget that can be reappropriated.
Recommended $86,600, There is
sufficient baia~ce in the 2003-04
budget that can be reappropriated.
Planning Department, continued
$75,000 " Traffic Calmin~ and This reappropriation is being requested because
’ Alternative Me~hods due to other ~vork priorities, these projects
Police Department
were not initiated until late in FY 2003-04.
These projects will be implemented in FY
2004-05 and will be fully reimbursed with
grant funding. The City will be reimbursed
in full with TDA grants of $25,000 and
$so, ooo.
Recommended $75,000. There is
sufficient balance in the 2003-04
budget that can be reappropriated.
$43,000 Design, development,This reappropriation is being requested because Recommended $43,000. There is
and printing of a public,recently Cou~acil directed staff to work with the Sufficient balance in the 2003-04
education brochure Chamber of Commerce to study and examine budget that can be reappropriated.
encompassing a!!changes to the downtown parking
parking changes in the configuration. Some changes have been made
downtown area and a resolution reflecting those changes as
well as a separate informational report will be
going to Council in the next few weeks. St’aft
is waiting for final direction before developing ~
and printing brochures. The General Fund
monies for this project are reimbursed from the
University Avenue Par’king District Fund.
$111,022 Integration of the City’s This reappropriation is being requested because Recommended $111,1)22. There is
GIS and CAD systems .as this was a multi-phase project (CIP PD-sufficient balance in the 2003-04
02017), it has been necessary to deploy and budget that can be reappropriated.
fully test other deliverables in the project prior
to implementing these changes. In addition,
the department has had to rely upon
cooperation from outside wireless service
providers to meet federally mandated
technoiogy changes to ensure a seamless
transition. Delays associated with those
vendors and internal competing priorities
contributed to the delay. The Project is
currently scheduled and the contracts are
pending. It is anticipated that this work’ will be
completed by the Fall of 2004
Planlt, iltg Department - BMR Fttnd
$44,143 BMR Unit
Preservation
Pro~am
This reappropriation is being requested because staff
and Palo Alto Housing Corporation (our BMR program
administrator) were able to take other effective actions
to avoid the need for the City to directly acquire any
BMR units to prevent their loss due to problems with
the resale process. The City was also able to avoid
paying for urgent repairs needed to get units resold by
strong enforcement against the sellers. However, these
unused funds need to be reappropriated to add to the
$20,000 budgeted for this purpose. The nature of this
fund is to address emergencies that could result in the
loss of BMR units and all monies set aside in the fund
for this purpose need to be available to meet any
possible emergency. The total available for these needs
will then be $64,143 ($20,000 already in the budget
plus $44,143 reappropriated).
Recommended $44,143. There is
sufficient balance in the 2003-04
budget that can be reappropriated.