HomeMy WebLinkAboutStaff Report 200-05City of Palo Alto
City Manager's Report
TO: . HONORABLE CITY COUNCIL
FROM: CITY MANAGER DEPARTMENT: UTILITIES
DATE: APRIL 25, 2005 CMR:200:05
SUBJECT: RESOLUTION OF INTENT TO ESTABLISH UNDERGROUND UTILITY
DISTRICT NO. 41 COLORADO AVE/MIDDLEFIELD ROAD/OREGON
EXPRESSWAY/COWPER STREET AND SETTING A PUBLIC
HEARING ON JULY 11, 2005
RECOMMENDATION
Staff recommends that Council adopt the attached Resolution of Intent to amend Section
12.16.02 of Chapter 12.16 of Title 12 of the Palo Alto Municipal Code by establishing
Underground Utility District No. 41.
BACKGROUND
The Electric Utility's undergrounding project areas are selected and recommended to SBC and
Comcast based on the age and maintainability of the existing overhead electric system. SBC and
Comeast determine whether the/recommended area meets their criteria for undergrounding based
on guidelines established by the California Public Utility Commission (CPUC). The attached
Exhibit "A" shows the existing, current, and future underground districts. Theareanow
proposed as Underground Utility District No. 41 meets the City and CPUC guidelines for
undergrounding overhead utility lines.
DISCUSSION
This underground project will result in the removal of 80 poles and provide underground service
to 185 commercial and residential properties. Completion of this project will eliminate overhead
distribution lines in an area borclered bY' existing underground districts and enhance reliability of
the electric distribution system while improving aesthetics.
Once the underground district is created, the Utilities Department will design and obtain bids for
the installation of the underground substructure required prior to placing the electric, telephone,
cable TV (CATV), street light and City communication facilities underground. After the new
underground systems (cable, transformers, switches, etc.) have been installed, the property
owners will connect to the new underground system, utilizing their own contractors. City crews
CMR:200:05 Page 1 of3
will then remove the overhead power lines, and telephone crews will complete the project by
removing the remaining telephone and CATV overhead facilities and the poles.
The City staff is currently in discussion with SBC concerning the allocation of costs and
responsibilities for joint trench applications. Since both parties agree that joint participation on
projects is mutually beneficial, these discussions should not have an impact on the timeline of the
project. The discussions are on-going, but staff does not foresee a significant change in cost
allocation for projects with joint trench participation with SBC.
On February 16, 2005, a letter was sent to the property owners in the proposed district
introducing the project and inviting them to a meeting. During the meeting (attended by 12
property owners) on March 10, 2005, staff explained the details of the project and answered
questions from the property owners. A questionnaire, which was included with the letter, was
used to determine the level of support for the project. Staff has received completed
questionnaires from 70 property owners, 42(60%) of whom are in favor of the project, 20(29%)
of whom are not in favor of the project, and 8(11 %) having no preference.
RESOURCE IMPACT
Funds for this project are included in the FY 2004/05 Utilities Department Electric CIP budget.
The only cost to the property owners will be that of replacing the overhead service drops to their
buildings with underground service. It is estimated that the average cost per property owner will
be approximately $4,500. Property .owners will be offered the option of financing their service _
conversions under Section 12.16.091 of Palo Alto Municipal Code. In that case, customers
borrow fundsJrom the City and repay the loan and administrative costs, which are added to their
property tax bills, over a ten year period, at an interest rate approved by the Council.
POLICY IMPLICATIONS
The resolution of intent does not represent any changes to existing City policy and is consistent
with the Council-approved Utilities Strategic Plan to invest in utility infrastructure to deliver
reliable service.
TIMELINE
The first step in the establishment of the district is Council adoption of a Resolution of Intent to
establish Underground Utility District No. 41. The Resolution defines the district boundaries
and sets a time and place for a public hearing on the matter. The public hearing has been
tentatively scheduled for the City Council meeting on July 11, 2005. At the public hearing, the
property owners will have an opportunity to comment on the project. The adoption of the
Resolution of Intent will also serve as a formal action that is required by SBC and Comcast prior
to starting engineering design. .
CMR:200:05 Page 2 of3
.'
The first Council action required to initiate the procedure will be adoption of the Resolution of
Intent to establish Underground District No. 41. Below is the tentative project schedule:
Action Date
1. Resolution of Intent to establish Underground District No. 41 April 11 , 2005*
2. Public Hearing June 6, 2005*
3. Award of construction contract and Joint Construction January 2006*
Agreement with SSC/Comcast
4. Substructure (conduits, vaults, etc.) installation by Contractor February 2006 through July 2006
5. Installation of underground facilities (cable, switches, etc.) August 2006 through October
2006
6. Resolution determining properties electing to pay service April 2006*
conversion cost over a period of 10 years
7. Service conversion work by property owners October 2006 through January
2007
8. Pole removal and project completion February 2007 through May 2007
* Denotes Council Action
ENVIRONMENTAL REVIEW
This project is categorically exempt from CEQA under Section 15302.
ATTACHMENTS
A: Resolution
B: Underground Conversion Projects
C: Underground Utility District No. 41 Boundary Map
PREPARED BY: .
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
Assistant City Manager
CMR:200:05 Page 3 of3
***NOT YET APPROVED***
RESOLUTION NO.
RESOLUTION OF THE COUNCIL OF THE CITY OF PALO
ALTO DECLARING ITS INTENTION TO AMEND SECTION
12.16.020 OF CHAPTER 12.16 OF TITLE 12 OF THE
PALO ALTO MUNICIPAL CODE BY ESTABLISHING
UNDERGROUND UTILITY DISTRICT NUMBER 41
The Council of the City of Palo Alto does RESOLVE as
follows:
SECTION 1. In its opinion, the public necessity, health
and safety require, and it is the intention of the Council,
pursuant to Section 12.16.040 of Chapter 12.16 of Title 12 of the
Palo Alto Municipal Code ("Code"), to amend Section 12.16.020 of
Chapter 12.16 of the Code, by ordering the establishment of an
Underground Utility District ("District") and to prohibit the
construction in and require the removal from the proposed District
of all poles. and overhead lines and associated overhead structures
used or useful in supplying electric, communication or similar and
associated services.
SECTION 2. The number of the proposed District is
Underground Utility District Number 41 of the City of Palo Alto,
commonly known as Colorado Avenue/Middlefield Road/Oregon
Expressway/Cowper Street.
SECTION 3. The description of the area comprising the
District is as follows:
All of the area in the County of Santa Clara, City
of Palo Al to, encompassing the areas contiguous
with 'portions of Colorado Avenue/Middlefield
Road/Oregon Expressway/Cowper Street. Underground
Utility District Number 41," on file in the office
of the City Clerk.
SECTION 4. From and after the effective date of the
establishment of the proposed District, no person or utility shall
erect or construct within the District any pole, overhead lines or
associated overhead structure used or useful in supplying electric,
communication or similar associated services.
SECTION 5. Within ninety (90) days from the date of the
completion and acceptance of the proposed underground facilities
within the District to be constructed by the 'City of Palo Alto and
the Pacific Bell Company doing business as SBC California, all
poles and overhead lines and associated structures used or useful
in supplying electric, communication or similar and associated
1
050421 c1 0072528
***NOT YET APPROVED***
services in the proposed District shall be removed, and from and
after the date no person or utility shall use or maintain such
facilities within the proposed District. Additional notice shall
be given after the completion date has been precisely determined.
SECTION 6. NOTICE IS HEREBY GIVEN that Monday, the 11th
day of July, 200S, at the hour of 7:00 p.m., in the regular meeting
place of its City Council, Civic Center, Palo Alto, California, is
hereby fixed as the time and place when and where the Council shall
hear all protests and receive evidence for and against the action
herein proposed, and when and where the Council shall consider and
finally determine whether the public necessity, health and safety
require,the establishment of the District and the removal of poles,
overhead wires, and associated overhead structures, and the
underground installation of wires and facilities for supplying
electric, communication and similar or associated services in the
District hereinabove described.
SECTION 7. At the public hearing, all persons interested
shall be given an opportunity to be heard. The hearing may be
continued from time to time as determined by the Council.
SECTION 8. The Electrical Engineering Manager, Department
of Utilities, City of Palo Alto, is hereby designated as the person
to answer inquiries regarding the protest proceedings, to be had
herein and may be contacted during regular office hours at
1007 Elwell Court, Palo Alto, California, 94303, or by calling
(650) 566-4506.
II
II
II
II
II
II
II
II
II
II
2
050421 cl 0072528
/
***NOT YET APPROVED***
SECTION 9. The Clerk of the City shall give notice of the
public hearing by publishing notice of the public hearing and the
director of utilities shall mail copies of this resolution to all
property owners within the proposed District as shown on the last
equalized tax roll of the City, and to all utilities supplying
electric, communication or similar or associated services within
the proposed District, the mailing to be completed at least thirty
(30) days prior to the date of the public hearing. The Clerk is
authorized to include in the notice to be mailed a statement to the
effect that any affected property owner has the option of paying
the cost of converting his or her or their service connection to
underground locations over a period of years. Such notice shall
conform to Section 12.16.092 of Chapter 12.16 of Title 12 of the
Code ..
INTRODUCED AND PASSED:
AYES:
NOES:
ABSENT:
ABSTENTIONS:
ATTEST:
City Clerk Mayor
APPROVED AS TO FORM: APPROVED:
Senior Asst. City Attorney City Manager
Director of Utilities
3
050421 clOO72528
'i
UNDERO
PROPOSED UNDRRCROUND D1STRIr:I1!;
(lOlII!lI'tiI-~ lJQlIm''''-~ llI:IlII!11m-~ ,IJOJ.:/TM-~ rclltfrH6-~
"'_01---..,...,. .. --_. ..,-.. ---. "_H--_ "'_ .. --.., .. _ .. ---",,.,,,,n--.., .. _ .. ---......... ---I» II1T 111-.. ""-,.---......... --tm ......... --tm ... IIIJHH--_ ""-"'--"'" .. _ .. ---"''''''Ifr--'''' "_",--rm
.. _ .. --... .. ........ --." "''''''at--_ """IU--"" .. _ .. ---"'''''IU--_ .. _ ... ---.......... ---"".."."'---"" ...... ---"'..,. ... ---r."_,,,--_ ""S""--_ "'_m--_ "' ....... --. """1""--_ ...... _---..... "'--"" Iial6!llm-_
ATTACHMENT B
S1J:1':_AVV\rl..u"""IICI\T"'c....~A"''''' ••
Attachment C
= = -OREGON EXPRESSWAY
,1I1t"---__t1-2420 ~ 2425
2440 Ul 2435
11I1-----'iIro----tIOIIl----1
2450 ~ 2451
H-----lII!l'IlIllI---........ ---1I :;0
2466 m 2465 r-,--~II~~IIIt~~~,-~II:~III-----1 2479 I------.-----l
2670 8
__ ~~682 ~'''~---l mil" ~ ~ (J'1 __ .-,....2_6_9_0 --l;;lJ 2695 ..... :::.: ::t
(J'1
())
(J'1
__ ~2_6_9_8--l~~~~~~~~~
2702 fg'~~~~~~r~~~1I
__ -'[ 2712 ~ g ~ ~ ~
---I":2:l7~24~Ur.....l....,~~}»0 2717 .. 2708 (J)
pr~::~::a~ 1
"'0 2727
i--------:r 2718 ~ 1----1 2737
1----. 2728 8 I-~--l
C 2757 1----I-~2~73:81 ?:l f------l
2767
2758
1111-----11 277
2777
2787
OJ 8
OJ 0> ..... .... N ())
APPROVED 15 Mar 2005
Patrick Valath
Underground District No. 41
SR. ENGINEER / MANAGER
ENGR. PEV
DRWN POD
CHKO. PEV
Boundary Map
City of Palo Alto
California
UTILITIES, ELECTRIC ENGINEERING
~
'-------'---ill I Cl II~---l Cl
2502
2518
2534
11\\----'-1 2560
2576
'REV. 'DATE APPR.
MAP# CKT#, SCALE
r mlll----l
!! m 1------+ r °111 __ --+
;;0
~ 111-----1
Cl
SAP 4000 2540
, DESCRIPTION
W.O.#/DRAWING#
22187 NTS t--==-~--==---:---t SHEET OF 1