HomeMy WebLinkAboutStaff Report 209-10TO: HONORABLE CITY COUNCIL
FROM: CITY MANAGER
DATE: APRIL 12, 2010
13
DEPARTMENT: ADMINISTRATIVE
SERVICES
CMR:209:10
SURJECT: (1) Library Construction and Bond Issuance Update, (2) Confirmation of
Approval of Use of Available General Obligation Bond Proceeds to Pay for
Temporary Facility Costs for Mitchell Park Library and Community
Center; and (3) Preliminary Direction Regarding a Temporary Main
Library
RECOMMENDATION
Staff recommends that:
1. Council confirm its December 7, 2009 approval to use available General Obligation (GO)
Bond proceeds to pay for temporary facility costs associated with providing a temporary
Mitchell Park Library and Community Center at the Cubberley Community Center.
2. Council provide input on making available a temporary Main Library at a location yet to
be determined, and using available GO Bond proceeds to pay for those additional
temporary facility costs.
BACKGROUND
On November 4, 2008, City voters passed Measure N which gave the City the authority to issue
bonds in an amount up to $76.0 million for library and community center capital improvements.
On March 2, 2009, Council adopted a "Resolution Declaring Intention to Reimburse
Expenditures from the Proceeds of Bonds to be Issued by the City" for expenses incurred for the
library and community center capital projects (CMR: 149:09) -Attachment A. On the same date,
Council approved the capital projects and the funding necessary to move ahead with Measure N
improvements. This marked the beginning of the more detailed design development phase.
In the March 2 report (CMR: 149:09 -Attachment A) staff stated that proceeds from future bond
sales would be used to: "reimburse the Infrastructure Reserve for the design work funding
requested in this report and all costs incurred up to the time bonds are issued; construction of a
new and expanded Mitchell Park Library and Community Center; renovation and expansion of
the Main Library; and renovation of the Downtown Library."
On December 14,2009 the Council approved additional funding for the temporary Mitchell Park
Library and Community Center (MPLCC) facilities at Cubberley (CMR:463:09). In this report,
staff listed the temporary facility costs that could be covered by bond proceeds. The Library
Bond Oversight Committee has encouraged staff to confirm with Council its intent that bond
proceeds be used to cover eligible costs for temporary facilities. To date all costs, those
CMR209:1O Page 1 of5
considered bondable (covered by bond proceeds) and those considered non-bondable (not
covered by bond proceeds) have been funded using General Fund Infrastructure Reserve
resources. Bondable costs may be reimbursed from bond proceeds when the first series of bonds
is issued in June. TIle final section of this report provides an update on the timeline for bond
issuance.
DISCUSSION
1. Temporary Mitchell Park Facilities
In order to maintain adequate service levels during the construction for the new Mitchell Park
Library and Community Center (MPLCC), the Cooncil approved construction of temporary
facilities at the CubberJey Community Center. The temporary facility is currently under
construction at the Cubberley Community Center, and is budgeted at $600,000.
The December 14, 2009 staff report regarding the construction contract for these facilities made
clear that many costs could be covered by bond proceeds, explaining:
" ... staff directed bond counsel to further research the issue of construction costs
for the temporary facilities. The bond counsel determined that, because the
temporary library costs are necessitated by the project itself those costs can in fact
be bondable (covered by bond proceeds) as a site improvement related to the
greater library bond projects. Therefore, these construction costs can be
recovered at the time of the bond sale for the MPLCC in the spring or summer of
20 I 0, although items such as furniture, fixtures, and similar equipment for the
temporary library remain non-bondable."
The report further detailed the temporary facility expenses that were eligible to be covered by
bond proceeds, including construction, design, certain shelving, and security infrastructure.
Thus, the report strongly implied, and may have even been the Council's understanding III
approving the contract, that the listed costs would be covered by bond proceeds.
The Library Bond Advisory Committee subsequently reviewed the issue on January 26, 2010
noting that Measure N is silent on whether temporary facility costs would be paid with bond
proceeds. The Committee encouraged staff to request full and clear direction from the Council
on whether bond funds should be used for these facilities. The Committee did not, however, take
any position on whether these costs should in fact be covered by bond proceeds as such decisions
are outside their scope of review.
The text of Measure N was limited to 75 words and necessarily could not include each and every
component of the project. In addition to the opinion from bond counsel that these costs are
eligible, stafrs research confirms that use of bond proceeds to cover temporary storage and
facility expenditures incurred while constructing or renovating new or existing buildings is
common for such projects. In the City of San Jose, for example, temporary storage facilities for
community libraries undergoing construction were covered by GO bond proceeds. In addition,
the City of Millbrae paid for temporary facility costs with bond proceeds. Therefore, staff is
recolrunending that the Council confirm its approval of bond funds for the temporary Mitchell
Park facilities.
CMR209:10 Page 2 of5
2. Temporary Main Library Faeilities
Council has not yet approved construction of a separate temporary facility during the closure of
Main Library. Staff is in the early stages of estimating costs for a temporary Main facility, so
costs cited in this report are extremely tentative. There are two options that may be available in
order to provide a temporary Main Library. One is to design, renovate, and provide construction
management services for a leased retail space of approximately 8,500 square feet for 18 months.
Costs for this option are preliminarily estimated at $685,000. A second option would be to lease
trailers and install site utilities on City-owned property at an estimated at $960,000. The costs
for either temporary facility could increase or decrease depending on the size and condition of
leased facilities and availability of on-site utilities necessary for the trailers. Other variables that
could push the costs for a temporary facility higher include: parking needs, accessibility
requirements, seismic requirements, and modifications for lighting or circulation. The 18-month
time frame includes the time needed to renovate the leased space or to install trailer utilities; to
move staff and equipment into and later out of the temporary facility; and for additional time in
the event the opening of the renovated Main Library is delayed.
Like the temporary Mitchell facilities, many of these temporary costs for Main may be covered
by bond proceeds. Although additional costs such as operational expenses and certain equipment
cannot be covered by GO bonds (e.g., non fixed equipment such as chairs and desk top
computers), those costs are relatively minor and can be covered by using existing shelving,
computers, and furniture from the libraries undergoing construction, as well as the Library's
operating budget.
Temporary library facilities will allow the City to maintain service during construction of the
permanent facilities. Staff is requesting Council input on providing a separate temporary library
during the Main Library renovations. It is staff's intent to return to Council at a later date when
costs are more clearly defined and Council can make an informed decision on whether to move
forward with a Main temporary facility. Once again, given the current economic milieu and the
competitive nature of the construction industry, staff anticipates that construction bids will be
under projected estimates. How much will not be known until construction awards are made.
Should (his oceur, there may be flexibility to cover temporary facility costs within the funding
authority provided by the voters.
3. Next Steps
In concert with the City's financial and legal consultants, a schedule for issuing bonds in mid
June has been prepared. This schedule is in keeping with Council's desire to pursue an
advantageous construction cost environment and the goal of eliminating any capitalized costs for
property owners. This timeline facilitates placing the costs of the first series of two bond issues
on the property tax rolls for next fiscal year. 'The current schedule is as follows:
May 10,2010
May 11,2010
May 25, 2010
CMR209:IO
City Council Action on Financing Documents to Issue Bonds
Ratings Presentation to S&P and Moody's
Ratings Received
Page 3 of5
May 26, 2010
May 27, 2010
June 8, 2010
June 29, 2010
July 19,2010
Late July
Bond Sale Notices Published
Preliminary Official StatementlUnderwriter Bid Form Finalized and
Circulated
Bond Bids Received, Bonds Priced, and Bonds Awarded to Winning
Bidder
Close Bond Issue and Receive Bond Proceeds
City Council Action on Establishing Tax Levy
Send Property Assessments to County
In terms of construction bids and schedules, staff anticipates the following:
May 4, 2010 Bid Due Date for Downtown Library work
June 7, 2010 Council Awards Construction Contract for Downtown Library Work
June 8, 2010 Bid Due Date for Mitchell Park Facilities
June 21, 2010 Council A wards Construction Contract for MPLCC
June 28, 2010 Downtown Construction Begins
July 12, 2010 MPLCC Construction Begins
In order to meet the County's early August requirement for property assessment information,
staff must completc the bond sale in early June. To sell the bonds in early June, staff will be
returning to Council on May 10 for approval of the financing documents and a "not to exceed
amount" on the first series bond issue. In selecting the not to exceed amount, staff will rely on
what it believes are reliable design and construction estimates for Mitchell Park work.
Proceeds for the first bond series will cover funds advanced by the City for these projects to date
(including or excluding, depending on Council direction on temporary library costs for Mitchell)
as well as construction costs for the Downtown Library, and estimated costs for Mitchell Park
facilities. It is important to note that if bond proceeds from the first series of bonds are in excess
of costs, they will be carried forward for the Main Library project and could potentially reduce
the amount issued in the second bond series.
RESOURCE IMPACT
Council approval of use of bond funds for the temporary library at the Cubberley Community
Center would result in a return of approximately $600,000 to the Infrastructure Reserve. Based
on the current cost estimates, using bond proceeds for an additional temporary Main Library
would translate into a tax of approximately $0.21-$.34 per $100,000 of assessed value (A V) for
property owners. The original estimate for all projects that was placed on the Measure N ballot
was $27 per $100,000 of AV.
CMR 209: 10 Page 4 of5
It is critical to note that in the unlikely event pennanent facility design and construction costs
should consume bond proceeds or that available proceeds fall short of actual temporary facility
costs, the City's Infrastructure Reserve or GF would have to absorb the temporary facility
expenditures.
POLICY IMPLICATIONS
Although temporary library costs were not considered in initial project estimates, covering such
costs is legal and consistent with General Obligation Bond coverage practice.
TIMELINE
See Discussion section
ENVIRONMENTAL REVIEW
On July 21, 2008, the Council confinned the Director of Planning and Community
Environment's (PCE) approvals of a Mitigated Negative Declaration (MND) for the Mitchell
Park Library and Community Center and a 2007 Addendum to the 2002 final Environmental
Impact Report (EIR) for Main Library. The Downtown Library project was detennined to be
exempt from CEQA review pursuant to Section 15301, "existing fucilities."
ATTACHMENTS
Attachment A: CMR:149:09 "Adoption of (1) Resolution Declaring Intention to Reimburse
Expenditures from the Proceeds of Bonds to be Issued by the City .... "
Attachment B: CMR: 463:09 "Adoption of a Budget Amendment Ordinance in the Amount of
$381,583 for Costs Related to Constructing a Temporary Library and Teen Center at the
Cubberley Community Center .... "
PREPARED BY:
ty Directo , Administrative Services
DEPARTMENT HEAD APPROVAL: ---."L-, __ ±--_::;;.L'-------
Director, Administrative Services
CITY MANAGER APPROVAL: -----t.--ro~-l.---'--+-'------
CMR209:IO Page 5 of5
ATTACHMENT A
TO: HONORABLE CITY COUNCIL
FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE: MARCIl 2, 2009 CMR:149:09
REPORT TYPE: CONSENT
SUBJECT: Adoption of (I) Resolution Declaring Intention to Reimburse
Expenditures from the Proceeds of Bonds to be Issued by the City; and (2)
Ordinance Amending the Budget for Fiscal Year 2009 to Establish Capital
Improvement Program Project Number PE-09005, Downtown Library
Improvements, and to Provide an Appropriation in the Amount of
$411,056; Establish Capital Improvement Program Project Number PE-
09006, Mitchell Park Library and Community Center New Construction,
and to Provide an Appropriation in the Amount of $3,390,309; Establish
Capital Improvement Program Project Number PE-09010, Library and
Community Center Temporary Facilities, and to Provide an Appropriation
in the Amount of $79,525; and Approval of Contract C09130744 with
Group 4 Architecture, Research + Planning, Inc., in a total amount not to
exceed $3,827,280 for Architecture and Engineering Design Services for
the Mitchell Park Library and Community Center, DOwntown Library and
Library and Community Center Temporary Facilities
EXECUTIVE SUMMARY
Attached for approval is a design contract with Group 4 Architecture that will allow for the
completion of construction documents for the Downtown Library, the Mitchell Park Library and
Community Center; and Library and Community Center Temporary Facilities. This work is
consistent with the work approved by voters as part of the Library bond measure, Measure N, in
November 2008.. In order to fund this work, and to provide staff with the resources for
miscellaneous small contracts, a BAO is also included for adoption. Since approval for this
work is being requested outside of the normal budget adoption process, new Capital
Improvement Project numbers need to be created to budget the funds provided by the BAO.
Aqoption of the Resolution of Intention to Reimburse Expenditures will allow the City to l'eCOUp,
from bond proceeds, project funds that will be advanced by the Infrastructure Reserve (IR) for
the library and community center projects as described in this report. All design costs incurred
prior bond issuance will be bome by the IR. Based on the project schedule, City staff intends to
issue two series of bonds. The City intends to time the issuance of the bonds in order to ensure
that the best bond market conditions exist. The first series, for an estimated $57.1 million, would
CMR:149:09 Page I of8
be issued before construction begins in spring 2010. The second series, estimated at $18.9
million, would be issued in winter 2012. These estimates include future design, contract,
construction, and issuance costs.
RECOMMENDATION
Staff recommends that Council:
1. Adopt a Resolution Declaring Intention to Reimburse Expenditures from the Proceeds of
Bonds to be Issued by the City (Attachment A) ;
2. Approve the creation of a new Capital Improvement Project (CIP) PE-09005 for the
Downtown Library (Attachment B);
3. Approve the creation of a new Capital Improvement Project PE-09006 for the Mitchell
Park Library and Community Center (Attachment C);
4. Approve the creation of a new Capital Improvement Project PE-09010 for Library and
Community Center Temporary Facilities (Attachment D);
5. Adopt a Budget Amendment Ordinance (Attachment E) in the total amoont of
$3,880,890. Of this amount, $3,827,280 is to be distributed to the various CIPs as
outlined under Item 6 below as well as $3,000 to CIP PE-09005, Downtown Library, for
miscellaneous small contracts and $12,000 to CIP PE-09006, Mitchell Park Library and
Community Center for miscellaneous small contracts. Additionally, $38,610 will be
distributed to the various CIPs as outlined further below for plan check services.
6 Approve and authorize the City Manager to execute contract C09130744 with Group 4
Architecture, Research + Planning, Inc. (Attachment F) in a amount not to exceed
$3,827,280 for architectural and engineering design services for the Mitchell Park
Library and Community Center and for the Downtown Library, including a total of
$3,483,080 for basic services and $344,200 for additional services. The funding shall be
allocated in the fullowing proportions:
-Downtown Library
Design Fee = $367,206
Additional Services = $37,000
Total CIP PE-09005= $404,206
-Mitchell Park Library and Community Center
Design Fee = $3,043,549
Additional Services = $300,000
Total CIP PE-09006 = $3,343,549
-Library and Community Center Temporary Facilities
Design Fee = $72,325
Additional Services = $7,200
Total CIP PE-09010 = $79,525
CMR:149:09 Page 2 ofS
BACKGROUND
A General Obligation bond measure for library and eommunity center improvements, Measure
N, was passed by City voters on November 4, 2008. This Measure approved a maximum
amount of $76.0 million in bonds. Proeeeds from future bond sales. will be used to: reimburse
the 'Infrastructure Reserve for the design work funding requested in this report and all ()osts
incurred up to the time bonds are issued; construction of a new and expanded Mitchell Park
Library and Community Center; renovation and expansion of the Main Library; and renovation
of the Downtown Library. It is important to note that design work to date (which includes the
feasibility study and preliminary design by Group 4 Architecture) has been paid (approximately
$1.5 million) by the General Fund and these monies will not be reimbursed from bond proceeds.
Detailed history of the design development can be found in past City Manager's Reports to
Council, CMR:286:02, CMR: 119:06,CMR:343:06, CMR:434:06; CMR:225:07,
CMR:32 I :08and a December IS, 2008 Informational CMR:473 :08,
http://yrww.cityofpaloalto.org/knowzonelre.portslcmrs.asp
The various site improvements are summarized as follows:
-Downtown Library
The progranunatic evaluation by Group 4 Architecture, Research + Planning (Group 4
Architecture) found that the existing services at this library adequately serve its service
population and significant capital improvements are not recommended. By relocating
technical services to the new Mitchell Park library, much of the current technical staff
area will become public space as a result of interior reconfiguration. A small program
room is planned. Systems upgrades, such as improved lighting and mechanical systems
will also be provided.
-Mitchell Park Library and Community Center
The Mitchell Park Library and Community Center will be a joint facility, designed to the
Leadership in Energy and Environmental Design level of Gold (CMR:309:08). The
existing Mitchell Park Library is about 10,000 square feet and will be replaced with a
new facility of 36,000 square feet. The new library will be two stories to accommodate
an enlarged eollection, a children's area, an aeoustically separated teen area, group study
rooms, staff areas and a program room. Increases in collection, seating, eomputers,
children's area and programming space are planned to serve the needs of the projected
population. Technical Services staff, currently locatcd at the Downtown Library, would
be relocated to the Mitchell Park Library in order to facilitate the increased intake of new
materials for the entire Ii brary system.
The existing Mitchell Park Community Center is approximately 10,000 square feet and
will be replaced with a new facility of 15,000 square feet. Similar to the existing
eommunity center, the new building will be a one-story building attached to the new
library. By sharing activity space, the joint facility will be smaller in size than two
independent buildings and will create a more efficient use of the Iibrary/eommunity
center site.
CMR:149:09 Page 3 of8
-Main Library
The Main Library improvements include small group study rooms that are acoustically
separated from the rest of the existing building and a new program space that seats 100
people. To accommodate the new program space, the Main Library will expand by
approximately 4,000 square feet from the current 21,000 square feet on the ground floor
of the building (CMR:434:06). The interior of the existing library will also be
reconfigured to make better use of areas that are vacated by reloeating certain materials
into the new building. Lighting and other building systems will also be upgraded. All of
the improvements will be made with consideration for the historic nature of the existing
building.
DISCUSSION
New Capital Improvement Projects
Approval of Measure N by votera in allowed the library design to begin before the mid-year
budget approval, which is scheduled for April 2009. Approval of new CIPs for the Mitchell
Park Library and Community Center, the Downtown Library, and Library and Community
Center Temporary Facilities are needed in order to begin design work. This separation will
allow funding to be properly allocated and tracked from the beginning of the project. A CIP for
the Main Library will be presented as part of the normal Fiscal Year 2010·2012 budget process
as construction is not expected to begin until 2012. Attachments B through D include the
descriptions of the CIPs that are being requested for creation and approval.
Funding for design work will be provided by the Infrastructure Reserve upon Council approval
of a Budget Amendment Ordinance (Attachment E). This funding will be apportioned (see table
below) into the new CIPs to pay for the design of each particular facility. This allocation will
allow for clear tracking of all costs associated with each building. All funds expended in these
projects will be reimbursed to the Infrastructure Reserve shortly after bond proceeds are
received. A new CIP also is proposed for temporary library and community center facilities
(Attachment D). Bond proceeds carmot be used to fund temporary faoilities, equipment or
furnishings so funding from the Infrastructure Reserve will have to be identified to cover these
costs. This may require a reallocation of funding from other existing or planned projects. Staff
will be evaluating the impact of these costs as part of the Fiscal Year 2010-2012 budgefprocess.
pesign Contract
Conceptual designs for the three sites are now 35 percent complete and have been reviewed by
the Library Advisory Commission (LAC), the Parks & Recreation Commission (PRC), the
Architectural Review Board (ARB), the Historic Resources Board (HRB) and City Council.
They were also presented to the community as part of the Measure N outreach efforts.
The contract with Group 4 Architecture (Attachment F) will complete the design of the
Downtown Library and the Mitchell Park Library and Community Center f!'Om the current 35
percent completion stage to final construction documents. The contract does not yet include
funding for the construction administration phase of the project, which would be included for
approval along with the construction contracts. A contract for the design of the Main Library
will be presented in the fall of 2010 as that library is not scheduled to begin design until early
201l. The Downtown Library would be the first library advertised for construction bids, likely
CMR:149:09 Page 4 of8
in the spring of 2010, followed shortly thereafter by the Mitchell Park Library and Community
Center. '
In addition to design fees, staff is requesting a total of $15,000 be included in the BAO to be
used for any miscellaneous unforeseen small contracts, printing costs, hazardous materials
testing, and other incidentals that might. arise through the duration of thc project. Of this amount
$3,000 would be used for the Downtown Library and $12,000 would be used for the Mitchell
Park Library and Community Center.
The City will also be entering into a contract with West Coast Code Consultants to provide plan
check services for the Mitchell Park Library and Community Center and for the Downtown
Library, which will help expedite the project. This contract will total approximately $38,000 and
is within the City Manager's contract award authority. These costs are also reimbursable from
bond proceeds and were included in the original budget estimates.
Temporary Faci1itie~
The contract with Group 4 Architecture also includes design services for temporary facilities
needed during construction of the libraries and community center. Temporary facilities cannot
by law be funded by bond proceeds. The overall budget for temporary facilities that was
established prior to the passage of the Measure N bond was $600,000, which would come from
General Fund monies. In order to reduce the demand on General rood monies, staff is proposing
to use existing spaces at the Cubberley Community Center Auditorium in Heu of leasing trailers
or other spaces while the Mitchell Park library and community center is under construction.
Improving existing City spaces instead of leasing trailers or other facilities would also help
reduce future budget demands as the money for temporary facilities would be used to improve
the Auditorium for library use (upgraded lighting, new paint, etc.). The estimated cost to
improve the Auditorium and pay for associated moving and storage costs is $150,000. However,
this cost will be refined as the design improvements are better developed.
The Auditorium would be used as temporary space for Downtown Library Technical Services
staff and would function as a temporary Mitchell Park Library, including a "homework help"
area. The Teen Center, currently located at the Mitchell Park Community Center, would be
given priority use of the Cubberley gyrrmasium for special events but would otherwise not
require additional space. Staff intends to continue to provide similar services and programs to
library patrons and teens during this interim period. Lease contracts currently in effect for the
Auditorium will tenninate December 31, 2009, which wiD enable the needed improvements to be
completed prior to the start of construction on the Downtown Library in the spring of 2010.
There are currently eight primary users of the Auditorium. Staff is working with these users to
identifY possible new locations at Cubberlcy that would be suitable to their programs or space at
other City sites. Lost revenue for the Auditorium would be $80,000 per year. This lost revenue
is less than the cost of leasing other temporary facilities even when combined with necessary
improvement costs of$150,000.
The Library Administrative Services section, which is currently located at the Downtown
Library, will likely be placed in the lower level of the Lucie Stem Center. This area is already
furnished with carpeting, desks, phones and other office equipment so improvement costs will be
CMR:149:09 Page 5 of8
minor. The use and location of temporary facilities during the construction of the Main Library
is still under discussion and findings will be presented at a later date.
Outreach
Staff has been working to develop an implementation strategy and structure for the projects that
will facilitate the flow of information between staff, the community and key stakeholders
(CMR:473:08). Three committees will be established for this effurt: the Technical Team (staff
from multiple departments and Group 4 Architecture), the Stakeholders Committee (staff,
community stakeholders and representatives from various boards and commissions) and an
independent Citizen Bond Oversight Committee to provide financial oversight of the project.
The Bond Oversight Committee was a specific requirement of Measure N.
The Technical Team has recently completed their formal review of the 35 percent complete plans
so that Group 4 Architecture can quickly begin incorporating any needed revisions. An initial
Stakeholders Committee is planned for March 12,2009, to review the project to date and identity
joint goals and objectives for outreach efforts during the constrtlction of the bond projects.
Recommendations fur the composition and goals of the Citizen Bond Oversight Committee will
be presented to Council as a separate item on or about March 16, 2009.
RESOURCE IMPACT
To complete design for the Mitchell Park and Downtown projects, a BAO in the amount of
$3,880,890 is needed. The distribution of these funds is shown in the table below:
Bond Funding Genera I)'nnd
Bondable
Mitchell Temporary &
Downtown Park Library & Facility General
Library Community Center Bondable Design Fnnd
PE·09005 PE.09006 Subtotal PE-09010 I!!m!
Group 4
Architecture $404,206 $3,343,549 $3,747,755 $79,525 $3,827,280
West Coast Code
Consult. $3,850 $34,760 $38,610 $38,610
Miscellaneuus
Small Contracts $3,000 $12,000 $15,000 $15,000
$3,801,366 . $3,880,890
Later, in the summer or fall of 2009, a contract for construction management services to
supplement existing staff levels will be forthcoming. These later contracts will also be funded
through the Infrastructure Reserve (IR) at the time that they are presented to Council for
approval and will be reimbursed later from bond proceeds.
Based on the proposed project schedule, it is optimal to issue two series of bonds. The first
series of bonds would be issued just prior to the beginning of construction in the spring of201O.
This issue would cover the design and contract costs cited above as well as the construction costs
for the Downtown and Mitchell Park libraries and the Community Center. These project costs
CMR:149:09 Page 6 ofB
are estimated at $54.9 million. Together with the costs associated with issuing the bonds (e.g.,
underwriter, legal fees, and capitalized interest), the current estimated total fur the first bond
issue is $57.1 million.
The second series of bonds would be issued just prior to work on the Main Library in the winter
of 2012. Current estimated costs for this project are $18.0 million. Including issuance costs, the
second series of bonds is estimated at $18.9 miUion. The first and second series of bonds total
$76.0 million.
It is important to note that the costs cited above are still estimates and that project costs may
ehange based on construction bids and other factors. While the City has the authority to issue up
to $76 million in bonds, it will only issue an amount based on actual design and construction bid
costs. Issuance costs are somewhat dependent on the principal amount required for the projects
and will be determined primarily at the time of the bond sale. Interest costs on the bonds sold
also will be known at the time of the bond sale.
Since the first series of bonds is expected to be issued prior to the beginning of construction in
the spring of 201 0, property owners can expect their first General Obligation bond assessment on
their 2010-20n property tax statement. When the next series of bonds are issued some time in
the winter of 2012, another ineremental and final assessment will be added to each property
owner's tax bill. Measure N indicated that the estimated, total assessment (after all bonds are
issued) would equal $27 per $100,000 of assessed value. At this time, staff believes this remains
a realistic estimate. As stated in previous reports, this amount is subject to change based on the
fmal amount of bonds issued and the interest rate incurred at the time of the bond sale. In order
to make the bond issuance process clear and transparent, staff intends to have the City's
Financial Advisor and Bond Counsel available at future meeting(s) as appropriate.
Funding nceds for temporary facilities, equipment or furnishings are estimated at $150,000.
Since these expenses cannot be covered by the bonds, they must be paid by the Infrastructure
Reserve. In addition, all incremental operating and maintenance expenses resulting from the
new fucilities and any new programs will have te be funded by the General Fund. Staff is
working to identify funding plans for these items.
POLICY IMPLICATIONS
The projects discussed in this update are consistent with Council's prior policy direction and
consistent with the establishment of the Library Facility Plan as a Top 4 priority for 2008.
TIMELINE
The consultant will begin design of the Downtown and Mitchell Park projects shortly after
approval of the design contract. The approximate project schedule is as follows:
• Approve eonsultant contract to provide construction management services for the
Downtown and Mitchell Park libraries. Summer/Fall 2009
• Approve construction contract for temporary facilities in preparation for the remodel of
the Downtown Library late 2009, early 2010
• Approve construction contract for Downtown Library &
Mitchell Park Library and Community Center Spring 2010
CMR:149:09 Page? ofB
• Approve construction contract for temporary facilities in preparation for the remodel of
the Downtown Library late 2009, early 20 I 0
• Approve construction contract fur Downtown Library &
Mitchell Park Library and Community Center Spring 2010
• Appruve consultant design contract for Main Library
• Approve construction contract for Main Ubrary
late 20 I 0, early 20 II
late 2012, early 20\3
These timelines are only rough estimates at this point and will be refined as the design
progresses.
ENVIRONMENTAL REVIEW
On July 21, 2008, the Council confirmed the Director of Planning and Community
Environment's (PCE) approvals of a Mitigated Negative Declaration (MND) fur the Mitchell
Park Library and Commwilty Center and a 2007 Addendum to the 2002 final Environmental
Impact Report (EIR) for Main Library. The Downtown Library project was determined to be
exempt from CEQA review pursuant to Section 15301, "existing facilities."
ATTACHMENTS
Attachment A: Resolution ofintent
Attachment B: Description of New CIP PE·09005, Downtown Library
Attachment C: Description of New CIP PE-09006, Mitchell Park Library & Community Center
Attachment 0: Description of New CIP PE-09010, Library & Community Center Temporary
Facilities
Attachment E: Budget Amendment Ordinance
Attachment F: Contract, Group 4 Architecture
PREPARED BY: ..i.~-~ ... ~
Senior Engineer
PREPARED BY:
DEPARTMENT HEAD:
ROBERTS
Dir ctor of Public Works
CITY MANAGER APPROVAL:
CMR:149:09 Page 8 ofB
ATTACHMENT B
TO: HONORABLE CITY COUNCIL
FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE: DECEMBER 14,2009 CMR:463:09
REPORT TYPE: CONSENT
SUBJECT: Adoption of a Budget Amendment Ordinance in the Amount of
$381,583 for Costs Related to Constructing a Temporary Library and
Teen Center at the Cubb'erley Community Center; Approval of a
Contract with Johnstone Moyer, Inc., in a Total Amount Not to
Exceed $227,463 to Convert the Cubberley Community Center
Auditorium into a Temporary Library to Replace the Mitchell Park
Library (Capital Improvement Program Project PE-09010)
RECOMMENDATION
Staff recommends that Council:
1. Adopt a Budget Amendment Ordinance (Attachment A) in the amount of $381,583 for
remodeling the Cubberley Community Center auditorium into a temporary Mitchell Park
Library, for future security alarm, telecommunications, shelving and other small contracts
related to the temporary library and for upgrades to a classroom used as a temporary Teen
Center during construction of the Mitchell Park Library Community Center.
2. Approve and authorize the City Manager to execute a contract (Attachment B) with
Johnstone Moyer, Inc" in the amount of $227,463 for construction of improvements at
the Cubberiey Community Center auditorium that will convert it into a temporary library
facility to serve as a replacement for the Mitchell Park Library during its upcoming
construction. The construction bid includes the price of bid alternates I through 4 that
total $3,911.
3. Authorize the City Manager or his designee to negotiate and execute one or more change
orders to the contract with Johnstone Moyer, Inc., for related, additional but unforeseen
work which may develop during the project, the total value of which shall not exceed
$34,120.
BACKGROUND
On July 7, 2008, Council directed staff to proceed with placing on the November 2008 ballot a
library/community center bond measure. Measure N, whieh passed on November 4, 2008,
includes funding for construction of a new and expanded Mitchell Park Library and Community
Center (MPLCC), renovation and expansion of the Main Library and renovation of the
Downtown Library. During construction of the Downtown Library and the MPLCC, staff and
CMR:463:09 Page I of6
books would be moved into a temporary library that will be located at the remodeled auditorium
of the Cubberley Community Center.
Funding for a temporary library had been approved in Fiscal Year 2010 as CIP PE-09010, with
an initial funding amount of $75,000. On March 2, 2009, Council approved a contract with
Group 4 Architecture in the amount of $79,525 to identify a location for a temporary library and
Teen Center and to provide conceptual layouts and costs (CMR:149:09). On September 14,
2009, staff and Group 4 Architecture updated Council on the Measure N library bond measure
projects and prescnted design and construction management contracts for approval
(CMR:368:09). At that meeting, Contract Amendment No.1 with Group 4 Architeeture in the
amount of $92,034 was approved to complete the final design of the temporary library and to
provide construction administration services (CMR:368:09). Incorporated into the Council's
motion to approve the staff recommendations was an amendment directing Library staff and the
Library Advisory Commission (LAC) to readdress some elements of the design tor the
Downtown Library. As a result of this direction and after review by the LAC, shelving height
was increased from 66" to 84", four additional 84" high shelves were added, along with two
additional computer stations. It was also determined that Library Administration staff should
remain at the Downtown Library (CMR:409:09).
DISCUSSION
Measure N Library Project Update
Construction documents for the Downtown Library are approximately 90 percent complete and
have been submitted to the Building Division for a building code compliance review. The design
development plans (which outline the general design concept and details) for the Mitchell Park
Library and Community Center (MPLCC) are 100 percent complete and have been reviewed by
the Library Advisory Commission (LAC), the Parks & Recreation Commission (PARC), the
Architectural Review Board (ARB) and the Art Commission. Plans were also presented to
citizen focus groups, teen groups and to the community, the latest being a community meeting
for the MPLCC on October 28th. Review by these committees will continue through at least
January 2010 and additional community meetings will be seheduled for 2010, prior to the start of
constructi on.
Project Description
Group 4 Architecture was initially contracted to study alternative locations and design options
for a temporary MPLCC. Working with staff from the Public Works, Library and Community
Services Departments, the Cubberley Community Center Auditoriunl was identified as the best
location for a temporary library while a new Mitchell Park Library was being constructed. The
auditorium is currently rented by various community groups whose rental agreements will expire
on December 31, 2009. Staff has been able to accommodate these renters in other rooms of the
Cubberley Community Center.
An approximately 5,090 square foot temporary library with books, computer terminals and
seating will be located in the main auditorium area. The Mitchell Park Library currently has
approximately 83,000 volumes in the collection. The temporary library will accommodate
approximately 45,000 volumes, 28 reader table seats, 10 study carrel seats, 18 computers and
associated seats and 10 lounge seats. Used shelving and furniture will be taken from the
Downtown and Mitehell Park Libraries and re-used in the temporary library whenever possible.
Shortly after completion of the temporary library, some furniture and Technical Services staff
currently located at the Downtown Library will be moved into what is now the kitchen area at
the back of the auditorium. Once the Technical Services staff has been relocated to the
auditorium, construction on the Downtown Library can begin. Later, when construction on the
new MPLCC is ready to begin, additional furniture, books and shelving will be moved into the
auditorium. Once the books from the MPLCC have been moved in the summer of 2010, the
temporary library will be opened to the public and construction on the new MPLCC library will
begin. Any remaining books not housed in the temporary library will be stored elsewhere.
Technical Services staff will remain in the temporary library at the Cubberley Community
Center until their new spaces at the MPLCC have been completed. Library Administration staff
currently located at the Downtown Library will be moved to the Main Library for the duration of
the Downtown Library renovation and moved back to the Downtown Library when that work is
completed. The Teen Center now at the MPLCC will be relocated to a classroom at the
Cubberiey Community Center just prior to demolition of the existing MPLCC.
Bid Process
A notice inviting formal bids for the Temporary Library project was sent to twenty-three
contractors. 111e bidding period was 15 working days. Bids were received from 16 contractors
on November 17, 2009, as listed on the attached bid summary (Attachment B). Bids ranged from
a total low bid of $244,349 to a high of $450,444, which includes the cost of five bid alternates.
Bid alternates 1 through 3 are for the removal and replacement of overhead lamps that contain
small amounts of hazardous materials, bid alternate 4 is for the addition of overhead fans for
summer cooling and bid alternate 5 is for painting the rooms and trim. Staff recommends that
bid alternates I through 4 be approved, at a total cost of $3,911 and that bid alternate 5 be
deferred until the temporary library is closed and furnishings removed.
ummarvo 1 S fB'dP rocess
Bid NameINumber IFB 134408 II!ll:1porary Library Improvements Project ...........
Proposed Length of Pro' eet 4 months
Number of Bids 23
Contractors
Number of Bids Mailed to Builder's 12
Exchanges
Total Days to Respond to Bid 15
Pre-Bid Meeting? Yes
. Number of Company Attendees at 18
• Pre-Bid Meeting
mumber of Bids Received: 16
Bid Price Range (inc!. 5 Bid Alts)* $244,349 to $450,444
"Bid summary proVided III Attachment C.
Staff has reviewed all bids submitted and recommends that the bid of $227,463 submitted by
Johnstone Moyer, Inc., for the base bid plus Bid Alternates 1 through 4 be accepted and that
Johnstone Moyer, Inc., be declared the lowest responsible bidder. The bid is fifty percent below
the engineer's estimate of $568,000 dollars. Staff contacted Group 4 Architecture in an effort to
determine why the engineer'S estimate was significantly higher than even the highest bid
CMR:463:09 Page 3 of6
received. The estimating subconsultant used by Group 4 Architecture does not typically e~1imate
small scale projects such as the temporary library. That, combined with the economy which has
spurred some contractors to bid jobs at-cost, resulted in a conservative engineer's estimate. Staff
is working with Group 4 Architecture to negotiate a reduced construction administration contract
that reflects the lower construction cost.
A contingency amount of 15 percent is requested because renovations of older buildings tend
involve more unforeseen conditions due to incomplete archival blue prints, as well as dry rot and
termite damage which may be uncovered during construction.
Staff confirmed with the Contractor's State License Board that the contractor has an active
license on file. Staff checked references supplied by the contractor for previous work performed
and found no significant complaints.
RESOURCE IMPACT
A BAO in the amount of $381,583 (Attachment A) is requested to provide funding for
construction of the temporary library and to provide for future small contracts for a security
system and related electrical and teleeommunications work and for new shelving and modular
furnishings to supplement existing furnishings that will be relocated from the Mitchell Park and
Downtown Libraries. It also includes an allowance to upgrade (add partitions, extend electrical
and data for computer connections) a classroom formerly used by the JCC that will serve as a
temporary Teen Center.
Staff has been meeting internally and with bond counsel and the external auditor to detennine the
most advantageous time for a bond sale, and the best way to eoordinate the sale of bonds with
the construction schedule and funding. Staff has also been working with bond counsel to
establish guidelines and a decision-making process to determine items for which bond funds may
be appropriately used. In addition, at the October 27,2009, Library Bond Oversight Committee
meeting, a question was asked as to whether costs for the temporary library were bondable costs.
As a result of that query, staff directed bond counsel to further research the issue of construction
costs for the temporary facilities. The bond counsel determined that, because the temporary
library costs are neeessitated by the project itself those costs can in fact be bondable as a site
improvement related to the grcater library bond projects. Therefore, these construction costs can
be recovered at the time of the bond sale for the MPLCC in the spring or summer of 2010,
although items such as furniture, fixtures, and similar equipment for the temporary library
remain non-bondable. Based on the newly developed framework, staff plans to complete similar
analysis as other new and unique cost issues arise. Costs for non-bondable expenses such as
furnishings will be funded through the Infrastructure Reserve. Bondable expenses will be
reimbursed to the Infrastructure Reserve at the time of the first bond sale in the spring or summer
of2010.
Bond Council has reviewed the following specific items related to the temporary spaces:
Bondable Costs
Temporary Library construction cost -Johnstone Moyer, Inc.
Contingency (15%)
Subtotal:
CMR:463:09
$227,463
$34,120
$261,583
Page 4 of6
Temporary Library -Mise Contracts, Estimated Costs
Security Systems & Access Card Readers -Infrastructure installation
(conduit, wire, security keypads and panels)
Library Shelving -Relocating and re-using certain shelving from
Mitchell Park Library, leasing additional shelving units as-needed,
seismically anchoring and removing all shelving when the temporary
library is disestablished
Telephone and computer data -Purchasing and installing new
panels/switchboards for the telephone/data systems (OPX)
Interior furnishings for Technical Services -Remove Pivot office
panels at the Downtown Library and reinstall at the Temporary.
Library. Purchase new Pivot panels and parts, if necessary
Teen Center -Misc Contract, Estimated Cost
Installing conduit and cables for telephone and computers
Subtotal:
Total Bondable Costs, PE-0901O:
Non-Bondable Costs-Estimates
Temporary Library
Telephone -Purchasing new telephones compatible with the OPX
phone system
Subtotal
Total Non-Bondable Costs, PE-09010:
Total BAO:
POLICY IMPLICATIONS
Approval of this contract is consistent with City policies.
TIMELINE
$25,000
$30,000
$25,000
$30,000
$5,000
$115,000
$376,583
$5,000
$5,000
$5,000
$381,583
Construction on the temporary library will start shOlily after contract approval and is anticipated
to be complete with staff within four months (approximately early May of 2010). The
Downtown Library can begin construction after completion of the temporary library.
ENVIRONMENTAL REVIEW
This project is an interior renovation and is therefore categorically exempt.
ATTACHMENTS
Attachment A: Budget Amendment Ordinance
Attachment B: Construction Contract
Attachment C: Bid Summary
CMR:463:09 Page 5 of6
PREPARED BY:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
KAREN BENGARD
Seni or Engineer
GLENN S. ROBERTS
Director of Public Works
JAMES KEENE
city Manager
r;;:;m:A.<1:oq------------------------Page 6 of6 -CMR:463:09