Loading...
HomeMy WebLinkAboutStaff Report 122-10TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PLANNING AND COMMUNITY ENVIRONMENT DATE: JANUARY 25, 2010 CMR: 122:10 REPORT TYPE: ACTION ITEM SUBJECT: Monthly Update on City Activities Related to High Speed Rail Project and Authorization to Expend up to $88,000 from the Council Contingency Account for the Proposed Resources Plan for FY 2010 RECOMMENDATION Staff recommends that Council: 1. Review the quarterly update on City activities related to the California High Speed Train (HST) project. 2. Authorize the City Manager to expend up to $88,000 from the Council Contingency account to fund the proposed Resources Plan in FY2010 related to the Council High Speed Rail Ad Hoc Committee review of the High Speed Rail project, including the following: a) Additional engineering consultant services to perform a peer review of the Alternatives Analysis for the San Francisco to San Jose HST project. Estimated cost: $18,000. b) Outside expert consultant services for peer review of HST ridership, HST fiscal and economic issues, and general environmental issues. Estimated cost: $30,000. c) A Sacramento Legislative Liaison consultant to represent the City's interests to the Legislature. Estimated cost: $25,000. d) A one -day High Speed Rail symposium (Teach -In) on financing of HST alternatives and a potential HST station in Palo Alto. Estimated cost: $15,000. BACKGROUND Since passage of Proposition lA in November 2008, approving funds for the High Speed Rail connection from Los Angeles to San Francisco, the High Speed Rail Authority (HSRA) has initiated environmental and engineering studies for implementation of the train system statewide. The HSRA consulting team for the San Francisco to San Jose Project Level Environmental Impact Report (EIR) began work in early 2009. On May 18th 2009, the City Council adopted Guiding Principles to provide direction to the City's High Speed Rail Ad Hoc Committee. The Ad Hoc Committee has been working closely with the Peninsula Cities Consortium (PCC) to develop public outreach and education efforts, CMR: 122:10 Page 1 of 7 monitor and evaluate HST activities, and to explore urban design solutions that consider community values for the high speed train project. On August 3, 2009, the Council approved a transfer of Council Contingency in the amount of $70,000 to fund the a HST symposium (or Teach -in) in September, a two-day design workshop in October and retention of outside expertise to provide peer review and analysis of technical documents including the HST project alternatives analysis. As reported in the last HSR update report in November 2009, the California HSRA team had initiated the alternatives analysis for the San Francisco to San Jose HST project and was revising the 2008 system -wide Business Plan. The updated Business Plan was released in December, but the Alternatives Analysis is delayed until March 2010. DISCUSSION This report provides an update regarding activities related to the High Speed Rail project that have been undertaken at the State and City levels since the last report in November 2009 and provides a Resources Plan for the balance of FY 2010 for outside consulting services, proposed community outreach and internal staffing to provide Council with the necessary technical analysis of the San Francisco to San Jose HST Project Level EIR and other HSRA reports. HSRA Activities Update Litigation and Status of Bay Area to Central Valley Program EIR In August 2008, a group of petitioners filed a lawsuit in Sacramento County Superior Court claiming the Authority's Final Bay Area to Central Valley Program EIR violated the California Environmental Quality Act (CEQA) in numerous ways. (Town of Atherton, et al., v. California High -Speed Rail Authority, et al). In August 2009, the Court issued a ruling that the program EIR required revision and recirculation in the several areas to comply with CEQA related to the San Jose to Gilroy section and vibration impacts, etc. On December 3, 2009, the Authority approved resolution rescinding the 2008 certification of the Program EIR and related approvals and directed Authority staff to prepare the necessary revisions to the EIR and circulate them in accordance with CEQA for public comment. The Authority will consider the revised Program EIR and the entire record of material before making a new decision to certify the revised Final Program EIR. The Authority will also make a new decision on a network alternative, preferred alignments, and preferred station locations for further study in Project EIR as stated in the 2009 Business Plan update. However, HSRA staff have indicated that the rescission of the Program EIR has not affected the project -level analysis schedule. State Senate HSR Information Hearing State, Senator Joe Simitian hosted a State Senate Transportation Subcommittee informational hearing with State Senator Alan Lowenthal on high speed rail on January 21st in the Palo Alto Council Chambers. Staff will provide a verbal report on the meeting to the Council on January 25th. CMR:122:10 Page 2 of 7 HSRA Business Plan The 2009-10 State Budget mandated that the HSRA submit an updated Business Plan to the Legislature by December 15, 2009 (see Attachment B, HSRA Business Plan Fact Sheet). The document was prepared and submitted in mid -December. The report updates the cost of the project's Phase 1 into years of construction dollars (rather than current year dollars) and provides an updated financing plan that takes into account Proposition 1A, ARRA stimulus funding, and other funding sources that were not known last year. The Plan also includes discussion of community outreach plans, system details, cost, financing, a working timeline, risks and threats to project completion, project development, proposed levels of service, ridership, system capacity, operational plans, staffing, and a history of expenditures and accomplishments to date. The new Business Plan projects approximately 30% lower system ridership by 2035, higher construction costs, and higher passenger fares based on 83% of the cost of air travel rather than 50% cost. On January 12, 2010 the Legislative Analyst's Office (LAO) released comments to the Assembly Transportation Commission on the 2009 Business Plan (See Attachment C). The LAO found the report substantially lacking in detail and cited the lack of information on risk management, including the risk of incorrect ridership forecasts and the financial risks associated with a flawed funding plan. The LAO further found the timelines very general and potentially inconsistent and identified a potential violation of state law associated with the funding plan. The Senate Transportation and Housing Committee scheduled a hearing on the Business Plan on January 19th San Francisco to San Jose HST Project Alternatives Analysis Currently HSRA staff is working on the Alternatives Analysis (AA) Report to be completed and ready for circulation in early March for presentation to the HSRA Board on March 4. The AA is an important part of the EIR/EIS as it will incorporate conceptual engineering information, identify and compare the alternatives, and will explain why some alternatives will be retained while others will be dropped from further study in the EIR/EIS. The AA evaluation will be based on planning and engineering at a 2% to 4% level of engineering design. This level of detail may be enough to understand if an alternative can feasibly be constructed and if the alternative might encounter significant environmental, community, and construction -related impacts. The AA will describe the alternatives based on alignment and vertical profile, that is, whether the alignment will be below ground, at -grade, or elevated. Staff anticipates that the Ad Hoc Committee and Council will need independent peer review of technical conclusions in the AA, such as tunneling feasibility and other below grade options, costs, and railroad operations. As a result, the City is in the process of retaining outside expertise as technical documents are released by HSRA staff. Once the document is released, cities and the public will have 45 days to review the report and submit comments on the document. Attachment D is a HSRA handout that discusses common questions and answers related to the AA for High Speed Rail. Attachment E is the Technical Memorandum on the Alternatives Analysis methodology for the Project Level EIR/EIS that will be employed by HSRA. Site specific alignment and station alternatives will be developed for the project level AA. CMR:122:10 Page 3 of 7 Ad- Hoc Committee Activities The Council Ad Hoc Committee continues to meet every two weeks and will focus much of its efforts on working with the other peninsula communities that are potentially impacted by high speed rail. Mayor Burt has appointed Council Members Klein, Price and Shepherd to serve with him on the committee this year. The Peninsula Cities Consortium (PCC) also continues to engage various community groups organized around the potential impacts of high speed rail to coordinate local, statewide and national legislation. The Committee sent a letter to the HRSA staff in December (Attachment F) reiterating the City's request that the Alternatives Analysis included an alternative that ends HST service at San Jose and provides connecting service to San Francisco via enhanced Caltrain service. City staff has also continued to receive support of volunteer resources from the Californians Advocating Responsible Rail Design (CARRD) that have provided comprehensive legislative summaries. Staff will continue to post these periodic updates on its High Speed Rail website as they become available at www.citvofpaloalto.org/cahsr. Updates on upcoming PCC events and copies of reports/presentations can be viewed at the following website http://www.peninsularail.ord/. City Resources Plan In August, the Council approved a transfer of $70,000 from the Council Contingency to fund the HSR Teach -In ($5,000) Design Workshop ($15,000) and technical consulting services related to the City review of the San Francisco to San Jose Project EIR ($50,000). The technical consulting services were specifically targeted to an engineering consultant who could perform independent peer review of technical conclusions such as tunneling feasibility and other engineering matters. The Teach -In budget was $5,000 and the actual expenses were $11,000, therefore this budget was exceeded by $6,000. The Design Workshop budget was $15,000 with actual expenses of $33,000 which caused the budget to be exceeded by $18,000. The cities of Menlo Park and Atherton will be billed their prorate share of the Design Workshop totaling approximately $16,000. This total reimbursement will be added to the remaining HSR budget balance of $26,000 to arrive at the new balance of $42,000. This $42,000 amount would be earmarked for the Engineering Peer Review of Alternative Analysis consultant. In order to proceed with the next steps in the Ad Hoc Committee and Council review of the San Francisco to San Jose High Speed Train Project EIR/EIS, staff has prepared a proposed Resources Plan (Attachment A) that identifies the need for funding of approximately $88,000 for the following four activities: 1. Peer Review of HST Alternatives Analysis The estimated cost of the peer review of the Alternatives Analysis that will be released in March for the San Francisco to San Jose High Speed Train HST project is $60,000. An additional $18,000 is needed to supplement the current remaining budget of $42,000 that is reserved for this purpose. CMR:122:10 Page 4 of 7 2. Additional Peer Review consultant services for peer review analysis Staff proposes to expand outside consultant services resources, as needed, for peer review of the engineering alternatives and potential urban design impacts of the HST project. The consultants would critique or validate the assumptions and conclusions of the HSRA engineering and environmental consultants including ridership forecasting methodologies and ridership projections and for the system and potential Palo Alto station, and other technical issues including but not limited to: train operations, fiscal/economic (Business Plan critique), environmental consultant (noise, vibration, geology, visual, traffic, etc.). The estimated consultant services cost is $30,000 for the remainder of this fiscal year. 3. Sacramento Legislative Liaison Consultant Staff believes it would be in the City's interest to retain a knowledgeable, well-connected legal and legislative consultant who could represent the City's interests before the High Speed Rail Authority and monitor proposed legislation affecting the HSR Project. Over the past year, a significant number of bills relating to HSR have been introduced in the Legislature. While the City has benefited from the detailed monitoring of the legislation by members of the citizen group CARRD (Californians Advocating Responsible Rail Design), a professional representing the City's interests in Sacramento could meet with legislators and their staffs on the City's behalf, attend CHSRA meetings and provide briefings to the staff and Ad Hoc Committee. It is estimated that a consultant contract would be approximately $5,000 per month for Palo Alto. Staff proposes that such a consultant be hired for five months at $25,000 and then the value of the contract reassessed. Alternately, if all the PCC cities were agree to participate in a shared contract for a legislative liaison, the estimate cost would rise to $10,000 per month. In that scenario, Palo Alto's share on a per capita basis would be approximately $3,900 per month. This issue, however, has not been formally discussed with the PCC as a whole. The City will continue to rely upon the Van Scoyoc Associates to advocate for the City's high speed rail and other transportation priorities before federal legislators in Washington, DC. 4. HST Financial Workshop Staff proposes that another workshop be held this spring, similar to the September high speed rail teach -in event, focusing on the financing scenarios and land use alternatives for funding the optimal HST alignment within Palo Alto. Staff estimates the cost of the workshop would be approximately $15,000. In addition to the above, the HSR activities would continue to be staffed by the Deputy City Manager, City Attorney, and Senior Deputy City Attorney on an as needed basis and contract transportation planner. Next Steps/Planned Activities The schedule for local PCC and City Couhcil meetings is provided as Attachment G. The next milestones for the Project are: CMR:122:10 Page 5 of 7 Alternatives Analysis Report —early March 2010 Draft EIR/EIS — First Quarter of 2011 Final EIR/EIS — End of 2011 RESOURCE IMPACT Funding for the HSR Ad Hoc committee was not included in the City's FY 2010 Adopted Budget. The annual appropriation or the City Council Contingency Account is $250,000. A transfer of $70,000 from the Council Contingency was previously approved by the City Council in August 2009 to fund Ad Hoc Committee review of high speed rail activities. Staff is requesting that Council approve an additional transfer from the Council Contingency in the amount of $88,000 in funding for FY 2010 to fund the three activities discussed in this report. This transaction will reduce the City Council's Contingency account from $173,500 to $85,500. Because of the importance of this project and the need for the City to be responsive new information released from the HSRA, staff will be preparing a budget proposal for the FY 2010- 2011 operating budget that will document the direct staff costs and non -salary expenses that will be required to support the City Council and Ad Hoc Committee HSR oversight activities. POLICY IMPLICATIONS The recommendations in this report are consistent with existing Council policy direction related to the California High Speed Rail Project. ENVIRONMENTAL REVIEW The recommendations in this report do not constitute a project requiring environmental review under the California Environmental Quality Act. ATTACHMENTS A. Proposed City Resources Plan Summary B. HSRA Fact Sheet on 2009 Business Plan Report to the Legislature C. Legislative Analyst Report on 2009 High Speed Rail Business Plan D. HSRA Handout on Common Questions and Answers for Alternatives Analysis E. HSRA Technical Memorandum re Alternatives Analysis Methods for Project Level EIR/EIR F. Ad Hoc Committee letter to HSRA dated December 15, 2009 G. Palo Alto High Speed Rail 2010 Schedule PREPARED BY: APPROVED BY: Aj_ GAYLE Manage STEVE EM LIE Deputy City Manager CMR:122:10 Page 6 of 7 CITY MANAGER APPROVAL: S KEENE Manager CMR:122:10 Page 7 of 7 DRAFT City of Palo Alto Reso urces Plan for High Speed Rail Project Evaluatio n and Monitoring FY 2009/2010 Item Palo Alto Only All PCC Cities Estimated B udget Estimated Budget* Funded Consultant Expertise Engin eering Peer Review of Alternative Analysis $42,000 U nfunded Consultant Expertise A dditional Funding for Engineering Peer Review of A ltern ativ es A nalysis $60,000 Less previou s Council Contingen cy Transfer -$42,000 Total Additional Fun din g Required $18,000 A dditional Con sultant for Peer R eview as needed $30,000 of ridership projections, and other technical issues in clu ding but not limited to: Train operations ex pert Fiscal/economic (Business Plan critique), Env ironmental con sultant Sacramento Lobbyist consulta nt (5 months @ $10,000/mo. for PCC Or For Palo Alto without PCC participation Public O utreach Event Financial Teach -In Event at Cubberley Total A dditional Fu nding Request $19,500 (PA share of PCC expense) Or $25,000 $180,000 $100,000 $ 50,000 $15,000 $ NA $82,500-$88,000 $330,000 * Costs to each participating city would be a pportioned on a per capita basis: Palo A lto (39%), Menlo Park (20%), Bur linga me (19%), Belmont (17%), an d A therton (5%) ATTACHMENT B FACT SHEET: December 2009 Business Plan Report to the Legislature THE REPORT ADDRESSES EVERY ITEM OUTLINED IN THE BUDGET BILL The High -Speed Rail Authority's revised business plan was submitted on time to the Legislature, and satisfies the language of the 2009 Budget Act. It addresses: community outreach plans, system details, cost, financing, a working timeline, risks and threats to project completion, project development, proposed levels of service, ridership, system capacity, operational plans, staffing, and a history of expenditures and accomplishments to date. THE REPORT DESCRIBES THE UNPRECEDENTED MOMENTUM BEHIND CALIFORNIA'S HIGH-SPEED RAIL PROJECT > Proposition 1A was approved by the voters in November 2008. o President Obama publicly supports the development of high-speed rail corridors in the United States. o He included $8 billion for high-speed rail in the American Recovery and Reinvestment Act. o He expressed a desire for an annual appropriation for high-speed rail. > Congress approved $2.5 billion for high-speed rail in the annual transportation bill. > Private entities are interested in investing in California's high-speed rail project. CALIFORNIA'S HIGH-SPEED TRAIN PROJECT IS ON TRACK Environmental reviews are taking place, the project is moving toward construction, outreach to communities is being improved, interest is increasing from private partners. THE AUTHORITY IS GEARING UP FOR CONSTRUCTION AND HAS AN ORGANIZATIONAL PLAN TO GET THERE The Authority is transforming from an entity focused only on planning to one that must oversee the construction of a large public infrastructure project. > The Board elected a new Chairman, Mayor Curt Pringle. > The Authority conducted an organizational assessment to guide its growth. The Authority will begin the process in 2010 to seek a construction management team and financial partners. THE HIGH-SPEED TRAIN PROJECT WILL CREATE JOBS The high-speed train system will generate 600,000 construction -related jobs over the life of construction (one-year, full- time equivalents over approximately 8 years). Nearly 130,000 of those would be directly related to ARRA funding if California's request is fully funded. Rough estimates show job creation by region/rail section to be: San Francisco —San Jose: 105,000 San Jose — Merced: 112,000 Merced — Bakersfield: 135,000 Bakersfield — Palmdale: 81,000 Palmdale — Los Angeles: 125,000 Los Angeles — Anaheim: 92,000 TODAY'S PROGRESS — IN THE ENVIRONMENTAL STAGE, HEADING TOWARD DESIGN AND CONSTRUCTION The path from where California's high-speed train project stands today to initial revenue passenger service can be divided into three categories of major milestones: planning, implementation, and revenue service. The report to the Legislature illustrates that the project is on track to: ... begin completing environmental reviews in 2011, ... enter construction in 2012, ... begin opening sections for passenger service 2017 or earlier, and ... complete the initial system from Anaheim to San Francisco by 2020. OUTREACH ACTIVITIES ARE RAMPING UP Along with increased momentum and significant project progress comes the need for increased outreach and information. The Authority has: hired a Deputy Executive Director for Communications and Public Outreach; brought on a new communications and outreach contractor, begun building partnerships with partner agencies, local governments, and community groups to better focus on outreach. A CREDIBLE COST ESTIMATE BETTER EXPRESSED IN TERMS OF YEARS OF CONSTRUCTION RATHER THAN TODAY'S DOLLARS Previously, the cost of the project had been described in terms of the current year. But since we are not building it in the current year, that does not accurately reflect the cost for the project in the years in which we will build it. Now, for the first time, the project's cost is expressed in years -of -expenditure (YOE) dollars, providing a much more credible estimate. In 2008, the cost of the Anaheim -to -San Francisco system was estimated at $33.6 billion (in 2008 dollars). > Updated cost estimate (also in 2008 dollars) is $34.9 billion; due to changes in track alignment and structural needs. > Using year -of -expenditure dollars to account for inflation and more accurately reflect the financing needs of the project over the life of when it will actually be constructed, the updated cost estimate for the San Francisco -to - Anaheim initial high-speed rail system is $42.6 billion in year -of -expenditure dollars. A VIABLE FINANCE PLAN TO FUND THE PROJECT'S CONSTRUCTION Bolstered by the unanticipated American Recovery and Reinvestment Act, the state bond dollars approved by California voters, and a new President publicly eager to help build high-speed rail networks in this country, the financial plan lays out a realistic scenario for paying for the system with a combination of state, federal, local, and private funds. State funding: $9 billion from Proposition 1A (used to leverage additional investment) Federal funding: $17-19 billion (ARRA, other federal loan programs, transportation appropriations) Local funding: $4-5 billion (in right-of-way, parking fees, transit -oriented developments, contributions) Private funding: $10-12 billion (public -private partnerships, vendor financing, availability payments, etc.) Total: $45 billion RIDERSHIP SCENARIO THAT SHOWS PROFITABILITY Through its environmental review the Authority is pursuing a scenario of lower ticket fares and larger ridership in order to study the broadest possible environmental impacts. For the purposes of this business plan, we look at a scenario that: > Sets average ticket prices at 83 percent of airfares over the same distances > Projects 41 million riders per year in 2035 > Shows annual revenue of $2.87 billion in 2035 Sooner, in the first year of planned operation, 2020, the scenario projects: > 13.5 million riders > Revenue of nearly $1 billion ($950 million) HIGH-SPEED TRAIN PROJECT HAS MUCH OVERSIGHT AND SCRUTINY The High -Speed Rail Authority and the high-speed train project are overseen by a large number of entities. These include: > The Authority's Board and appointees of the Senate, Assembly, and Governor's Office > Legislation that requires routine reporting ➢ Proposition 1A, and the reporting, oversight requirements contained within it > Budgetary oversight by legislative committees, Department of Finance, and Governor's Office ➢ Legislative policy oversight, including Assembly and Senate transportation committees, others ➢ Peer review board set up within Proposition 1A and whose members are appointed by a variety of control agencies and constitutional officers > Program Management Oversight contractor hired to scrutinize the overall management of the project > Local agreements with regional entities > Recovery Act oversight required by the federal government and the state Inspector General WHAT HIGH-SPEED RAIL MEANS All -electric power and fully separated from automobile traffic, California's high-speed train will provide a new transportation option available to more than 90 percent of the residents of the state. The system is being designed to carry more than 100 million passengers a year. NEED EXISTS FOR A TRANSPORTATION ALTERNATIVE By 2030, the state's population will grow to 50 million people, which will nearly double interregional travel to one billion trips per year. A high-speed rail system will alleviate the need to build thousands of additional miles of new freeway and dozens of new airport departure gates and runways. ATTACHMENT C i5 '!cA2� OF SERVICE January 11, 2010 The 2009 High -Speed Rail Business Plan LEGISLATIVE ANALYST'S OFFICE Presented to: Assembly Transportation Committee Hon. Mike Eng, Chair January 11, 2010 63 YEARS OF SERV[CE 2008 High -Speed Rail Business Plan Requirement. Chapter 267, Statutes of 2008 (AB 3034, Gal- giani), required the High -Speed Rail Authority to submit a busi- ness plan for the high-speed train system to the Legislature by September 1, 2008. The plan was released on November 7, 2008. Plan Lacked Specifics. Information provided in the plan was very general and did not provide specifics that are included in typical business plans. The figure below summarizes our review of the 2008 plan. (See 2009-10 Budget Analysis Series: Trans- portation, page TR-47.) 2008 Business Plan Fails to Provide Many Details. u eme isstn Deal Description of the anticipated system Forecast of patronage, operating, and capital costs Estimate of necessary federal, state, and local funds Proposed construction timeline for each segment Discussion of risks and mitigation strategies • What are the expected service levels, by segment? • What is the assumed train capacity? • How are the ridership estimates projected? • What is the operating break-even point? • How will costs be distributed by route segment? • How would funds be secured? • What level of confidence is there for receiving each type of funding? • What is the proposed schedule, by segment, for completing design/ environmental clearance? • For beginning/completing construction? • How would each type of risk impact the project? • What specific mitigation strategies are planned to be deployed? LEGISLATIVE ANALYST'S OFFICE 1 January 11, 2010 2OC9 10 Budget Requires 65 YEARS OF SERVICE Business Plan Revision 2009-10 Budget Requirement. The current year budget direct- ed the authority to submit a revised business plan to the Joint Legislative Budget Committee by December 15, 2009. Required Elements. The revised plan must include, at a mini- mum: ■ A plan for a community outreach component to cities, towns, and neighborhoods affected by the project. ■ Further system details, such as route selection and alterna- tive alignment considerations. ■ A thorough discussion describing the steps being pursued to secure financing. ® A working timeline with specific, achievable project mile- stones. ■ The strategies the authority would pursue to mitigate different risks and threats. ® Additional information related to funding, project development , schedule, proposed levels of service, ridership, capacity, op- erational plans, cost, private investment strategies, staffing, and a history of expenditures and accomplishments to date. LEGISLATIVE ANALYST'S OFFICE 2 January 11, 2010 L 65 YEARS OF SERVICE Revised Business Plan Improved Revised Plan More Informative in Some Areas. The revised plan includes at least some description of all the elements re- quired by the 2009-10 budget. The plan also provides more information than the previous version in certain areas. ■ Community Outreach. Though the authority only recently obtained their public relations consultant, the plan contains a summary description of a community outreach plan. ■ System Details. The plan includes: — General route selection and various alternative align- ments. — Updated cost estimates using year -of -expenditure dollars. — Forecasted ridership, revenues, and proposed levels of service. — Projected operating and equipment replacement costs. ■ Funding. Descriptions of various types of financing available and possible funding sources for the project are included. ■ Authority Operations. The plan provides a short discussion of necessary future staffing for the authority as well as his- toric levels of funding. LEGISLATIVE ANALYST'S OFFICE 3 January 11, 2010 1 J. a 63 YEARS OF SERVICE Some Significant D.taiis Still MM11ssin inINIIMINIMMEGICLUNIMEILEffek Inadequate and Incomplete Discussion of Risk. The plan's discussion of risk management is significantly inadequate, lack- ing any description of mitigation processes or detailed consider- ation of many key types of risk. Uninformative Timeline. Few deliverables or milestones are identified in the plan against which progress can be measured. Also, inconsistencies in the proposed order of events create some uncertainty. LEGISLATIVE ANALYST'S OFFICE 4 January 11, 2010 L 65 YEARS OF SERVICE Risk Discussion incomplete and Inadequate No Risk Management Strategy. The plan contains no discus- sion of the authority's plans or processes to (1) identify poten- tial threats or (2) manage, respond, and mitigate those threats. The plan only states that the authority "believes it is aware of all existing threats and is taking the appropriate steps to prevent or mitigate those threats." Unknown Confidence in Projections. The plan does not pro- vide any numerical ranges nor confidence intervals for projec- tions contained in the plan (such as cost, revenues, or ridership). Without this information, the risk of not realizing the forecasted ridership, revenues, or costs is unknown. Inadequate Discussion of Key Types of Risks. The plan con- tains no detailed discussions or consideration of even the most significant risks to the project, such as ridership and funding. LEGISLATIVE ANALYST'S OFFICE 5 January 11, 2010 r : Discussion of Risk -Two Examples 65 YEARS OF S RVLCE Ridership Risk. The plan addresses the risk of incorrectly forecasted ridership with one sentence, stating the risk "would be mitigated by policies that continue to draw people to reside in California and encourage high-speed rail as an alternative mode of transportation." Funding Risks. The plan identifies the following types of finan- cial risks, and how these risks would be addressed: ■ Credit Approval Risk. To avoid the risk of failing to win credit approval from investors, the authority's strategy is "to clearly communicate the project and obtain up-to-date feed- back." ■ Overall Market Risk. To mitigate the risk that financial mar- kets shut down and stop lending, the authority "has to contin- ually monitor the market and develop strong back-up strate- gies such as project segmentation." ■ Government Funding Risk. The authority plans to avoid the risk that governments are not able to follow through on their commitments "by carefully assessing how each government funding source affects the build -out of each segment." LEGISLATIVE ANALYST'S OFFICE 6 65 YEARS OF SERVICE January 11, 2010 Timelines Very General and Potentially Inconsistent Uninformative Timeline. The program management and proj- ect delivery timelines contained in the plan are very general and provide little opportunity for increased accountability. There are few deliverables or milestones included against which progress can be measured. Inconsistent Order of Events. Because the timelines in the plan are so general, it is unclear in what order various events will occur. For example, regulatory approvals are expected by 2018 but procurement is scheduled to be complete by 2014. This could mean the train technology and rolling stock will be pro- cured before regulatory agencies approve their use. LEGISLATIVE ANALYST'S OFFICE 7 65 YEARS OF SER.ViCE January 11, 2010 Funding Plan Uncertain; Appears to Violate Law Operating Subsidy Necessary for Private Funding. The Proposition 1A bond measure explicitly prohibits any public op- erating subsidy. However, the plan expects the following items to be funded by the private sector. ■ Revenue Guarantee. The plan assumes some form of revenue guarantee from the public sector to attract private in- vestment. This generally means some public entity promises to pay the contractor the difference between projected and realized revenues if necessary. The plan does not explain how the guarantee could be structured so as not to violate the law. • Operations Insurance. The plan anticipates the cost of insurance for operating the system would not be borne by the private operator. If the public sector pays for insurance, that would constitute an operating subsidy in violation of Proposi- tion 1A. Federal Funding Expectations Highly Uncertain. The plan assumes between $17 billion and $19 billion from federal funds by 2016, or nearly $3 billion per year for the next six years. In comparison, over the past five years California has received roughly $3 billion per year of formula funding for the state's entire highway system, which is primarily funded through federal gas tax collected in the state LEGISLATIVE ANALYST'S OFFICE 8 ATTACHMENT D September 2009 Common Questions and Answers related to the Alternatives Analysis for the San Francisco to San Jose High -Speed Train Section What is an Alternatives Analysis? The Alternatives Analysis (AA) is a methodical process to provide the California High -Speed Rail Authority (Authority) and the Federal Railroad Administration (FRA) with sufficient information and documentation of the evaluation process used to identify and define a range of reasonable, practicab/e, and feasible project study alternatives. The AA will incorporate conceptual engineering information and will identify feasible and practicable alternatives to carry forward for review and evaluation in the project Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for the San Francisco to San Jose section of the California High -Speed Train Project (CHSTP). The AA will provide information that highlights and compares the alternatives, and will explain why some alternatives will be retained while others will be dropped from further study in the EIR/EIS. The Authority and the FRA will make the results of the AA available for public input. Where do the alternatives come from? The alternatives will take into account previous work conducted for the Statewide Program EIR/EIS. For the San Francisco to San Jose section, the program document identified the Caltrain right-of-way as the CHSTP route, with stations in San Francisco, Millbrae, and San Jose. Optional stations will be considered in Redwood City, Palo Alto, and Mountain View. In addition, the Authority and FRA will consider public and agency comments provided during a series of public scoping meetings held this past spring. In addition, input received from the community more recently will also be considered. How detailed are the alternatives? The AA evaluation will consider preliminary project features based on planning and engineering at a 2% to 4% level of engineering design. This level of detail is enough to understand if an alternative can feasibly be constructed and if the alternative might encounter significant environmental, community, and construction -related impacts. In the San Francisco to San Jose section, with the proposed use of the Caltrain right-of-way, the AA will describe the alternatives based on alignment and "vertical profile;" that is, whether the alignment will be below ground, at -grade, or elevated. How will the EIR/EIS study alternatives be identified? The Authority has established a ten -step process to identify practicable and feasible alternatives for study in the EIR/EIS. The steps are illustrated in the chart below and described in greater detail on the next page. In the gray boxes below, the following abbreviations are used: PMT = Program Management Team, providing guidance on the design of the overall HST system and to each of the regional planning and engineering teams on behalf of the Authority; CHSRA = California High -Speed Rail Authority; FRA = Federal Railroad Administration; and AG = California Attorney General's Office. Alternatives Analysis Process Initki I Development of Alternatives Revised Definition of Alternatives Agency cy. Public/ akethckl utriach. Fine Alternat ves Analysis ." Report Draft Alternatives Analysis _= Report Acre i Publicf takeholdr utreac1'i Project Description 2009 AUGUST SEPTEMBER OCTOBER OVEMBER ` DECEMBER JANUARY FEBRUARY': 2010 September 2009 Step .1: Initial Development of Alternatives (August 2009) Using the selected program -level corridor alignments and station locations, the planning and engineering team will develop site -specific project alternatives considering existing conditions and constraints as well as information gathered during the scoping process. It is essential to start with the selected program alternatives as these were identified as likely to contain the Least Environmentally Damaging Practicable Alternative (LEDPA) with concurrence by the U.S. Environmental Protection Agency and the U.S. Army Corps through the Clean Water Act Section 404 alternatives analysis process. Apresentation will be made to the PMT/Authority/FRA on the initial alternatives developed for further consideration through the AA process based on: • the program -level selected alternatives, alignment routes, and station locations, and consideration of purpose and need/project objectives; • public and agency input received during and after scoping; and • further analysis of the study area to identify alternatives and/or variations and design options that are practicable and feasible. Step 2: Ear/y Outreach to Agencies, Public, and Stakeholders (September/October 2009) The alternatives identified for further consideration will be presented informally to the local and regional planning agencies, transportation agencies, and environmental resource agencies in meetings. A similar effort will be conducted to inform the public. Coordination with Cooperating Agencies will also be conducted at this time. Step 3; Revise Definition of Alternatives (October/November 2009) Based on information and feedback received from early outreach, the Initial Project Alternatives may be revised and then resubmitted to the Program Management Team (PMT)/Authority/FRA for review. Step 4; PMT/Authority/FRA Project Alternatives Workshop (November2009) A workshop will be conducted by the planning and engineering team with the PMT/Authority/FRA to review the details and information regarding all alternatives studied to date. This will include discussion of severe design constraints or conflicts, and environmental impacts and benefits for each alternative. The purpose of the workshop is to get direction from the Authority and FRA on further investigation of alternatives, to identify alternatives requiring no further analysis, and to evaluation conclusions. Step 5; Alternatives Analysis (AA) Draft Report (December 2009) An AA Draft Report will be prepared that presents the results of the AA process to this point. Step 6; PMT/Authority/FRA/AG Review (December 2009/January 2010) The AA Draft Report will be reviewed by the PMT/Authority/FRA. When approved for release, the AA Draft Report will be posted to the Authority's website. Step 7.• Presentation to CAHSR4 Board (December 2009/January 2010) The results of the AA Draft Report will be presented to the Board as an information agenda item. Step 8; Outreach to Agencies, Public, and Stakeholders on the 44 Draft Report (January 2010) U.S. Department of Transportation Federal Railroad Administration Page 2 September 2009 The alternatives identified for inclusion in the EIR/EIS will be presented to the local and regional planning agencies, transportation agencies, and environmental resource agencies through a series of meetings. A similar effort will be conducted to inform the public. Coordination with cooperating agencies will also be conducted at this time. Step 9: Alternatives Analysis (44) Final Report (February 2010) The AA Draft Report will be finalized and will include the results of outreach meetings and consultation with cooperating and other agencies. The AA Final Report will be reviewed by the PMT/Authority/FRA and posted to the Authority's website when approved for release. Step 10: Prepare Draft Project Description (February 2010) Based on the Final AA report, a project description will be prepared that will identify a preferred alternative. The project description will include information about the CHSTP for the San Francisco to San Jose section including the horizontal and vertical alignment, the stations, other facilities such as sites for maintenance, and the operating schedule for the trains. Design options to the preferred alternative, if any, will also be identified. Options may include variations to a vertical alignment, to a station location or layout, or to any other feature of the design and operation of the HST system that need to be studied to provide the Authority, FRA, and the public with reasonable choices to make an informed decision about the project. The EIR/EIS will evaluate how the preferred alternative changes existing baseline conditions and how significant the changes are. How are the number and range of alternatives to be narrowed? Broad sets of criteria have been defined to help explain the goals of the HST system. Then, specific measures have been developed to evaluate and compare the project alternatives. The first goal focuses on meeting the purpose and need. Project Goal Criteria Measure Purpose and Need Travel time 30 minutes San Jose to San Francisco (Express Service) Intermodal connectivity (Stations) Connections with other transit services and airports Operations and maintenance costs Relative measure (None, Low, Medium, High) relative to one -another The following criteria and measures seek to expand on HST goals to be supportive of local land use plans, be feasible from an engineering perspective, minimize disruption to neighborhoods and communities, minimize impacts to environmental resources, and minimize impacts to the natural environment. Project Goal Criteria , Measure Land Use Planning Support Sites within 1/2 mile available for significant Transit Oriented Development Acres suited to redevelopment/revitalization within 1/2 mile Consistent with existing plans and policies Review of existing zoning , redevelopment and general plans U.S. Department of Transportation Federal Railroad Administration Page 3 September 2009 Constructability Vertical profile feasibility, compatibility with adjacent segments Vertical control points, grades, length of curves, combined vertical and horizontal curves, vertical profile of adjacent segments Horizontal clearance through existing structures (columns, bents, etc.) Locations of existing columns, bents and width of structures Major utility relocations Existence of major utilities requiring relocation Ability to maintain Caltrain operations during construction Qualitative assessment of High, Medium, Low Ability to maintain critical traffic operations during construction Qualitative assessment of High, Medium, Low Construction costs Relative measure (None, Low, Medium, High compared to one another) Neighborhood Compatibility Property displacements — acquisitions (full and partial) Number of full or partial residential acquisitions Properties with access affected Number of properties with changes in access Local traffic effects Street closures/un- resolvable capacity constraints Development/construction foot print (stations) Property acquisitions/relocation to accommodate station (residential/commercial) Protection of Environmental Resources and Natural Environment Waterways/wetlands/sensitive species habitat Potential jurisdictional wetlands and habitat for listed species Cultural resources (historic, archaeological, paleontological) Listed historic resources/known archaeological/known paleontological sites Parklands Existing parklands/community facilities that provide recreation (Section 4(f)) Noise and vibration Sensitive receptors (schools, hospitals, convalescent homes, daycare) within FRA screening distance �ALIPORMA U.S. Department of Transportation Federal Railroad Administration Page 4 September 2009 Protection of Environmental Resources and Natural Environment (Continued) Visual/scenic Obstruction of designated view corridors and scenic resources by elevated structures Geologic/soils Soil and slope constraints (high landslide susceptibility), seismic constraints (very strong groundshaking, cross active faults) Hazardous materials Known hazardous materials/wastes sites from database lists What might be reasons to not advance an alternative for further study? The AA identifies the alternatives evaluation process. Not all alternatives will be evaluated in the EIR/EIS. Reasons that could provide a rationale to exclude an alternative from further consideration include: • Alternative does not meet the purpose and need and project objectives. • Alternative has environmental or engineering issues that would make approvals infeasible. • Alternative is not feasible or practical to construct. • Alternative does not reduce or avoid adverse environmental impacts. U.S. Department of Transportation Federal Railroad Administration Page 5 ATTACHMENT E Ca orn a eed Tr hi Project TECHNICAL EMO NDU Alternatives Analysis Methods For Project -Level ETR/ EIS Prepared By: Checked By: Approved By: Released By: Reviewed By: Accepted tay: Steven rilyn Duffey Steven Wolf, Environ / At al armor puty Director, GSRA le di Morshed, Execu rector, CHSI Nov 08 Nov Nov 08 Dec 08 [_Revision 0 Date Oesription J 16 M 08 initial Release . l' 1 11 June 08 PMT Review 2 8 July 08 PMT Comments Incorporated .�._.. ._ __ . t6 Sept o8 ,LFRA 02 ec 08 X23 Cher 08 Comments incorporated _._ CAA & Atirthori Comments Incorporated Authority & FRA Comments Incorporated California High Speed Train Project Alternatives Analysis Methods TABLE OF CONTENTS 1.0 PURPOSE 1 1.1 INTRODUCTION 1 1.2 APPLICABILITY 1 1.3 OVERVIEW 1 1.4 ADDITIONAL INFORMATION,. 2 2.0 LEVEL OF EFFORT 2 2.1 APPROACH 2 2.2 COORDINATION 4 3.0 ASSESSMENT / ANALYSIS 4 3.1 ALTERNATIVES EVALUATION 4 3.2 SCOPE OF ANALYSIS 4 4.0 EVALUATION MEASURES 5 4.1 CHSTP DESIGN OBJECTIVES 5 4.2 PRELIMINARY ALTERNATIVES ANALYSIS CRITERIA 5 5.0 DOCUMENTATION 7. 5.1 LEVEL OF IMPACT 7 5.2 ALTERNATIVES COMPARISON 7 6.0 REFERENCES 8 6.1 .INFORMATION FOR INCLUSION 8 :A41FgRN14 Page C4i/FOLVG Mg SPEED R O.A(7Y.OUry California High Speed Train Project Alternatives Analysis Methods 1.0 .PURPOSE 1.1 Introduction This memorandum serves as a guide to the regional teams in preparing California High -Speed Train (HST) project -level Alternatives Analysis (AA) Reports for sections of the HST system. The AA Reports will incorporate conceptual engineering information and will identify feasible and practicable alternatives to carry forward for environmental review and evaluation in Environmental Impact Reports/Environmental Impact Statements (EIR/EIS) for sections of the California HST Project (CHSTP). In developing the AA Reports the regional teams will begin analysis with the alternatives selected with the previously prepared statewide and Bay Area prograrn EIRs/E1Ss. After identifying initial project alternatives; alignment plans, profiles, and sections will be developed and used for the preliminary evaluation of the alternatives. The AA evaluations will be used to assist the HSRA and the FRA in identifying the range of potentially feasible alternatives to analyze in the draft project. EIR/EIS. The guidelines contained in this memorandum are designed to maintain consistency among the regional teams in identifying an appropriate range of alternatives to analyze in each EIR/EIS, conducting a preliminary analysis, applying evaluation criteria, and documenting the evaluation process, while still allowing. flexibility to account for consideration of regional differences. 1.2 Applicability The AA Reports are intended to provide the California- High Speed Rail Authority (Authority) and the Federal Railroad Administration (FRA) with sufficient information and documentation to provide a clear understanding of the evaluation process used to identify and define a range of reasonable, practicable and feasible project alternatives. The Authority and the FRA expect to make the AA Reports available for public input. The alternatives evaluation will support decisions guiding the project design and environmental review process, including specifically the identification of reasonable alternatives to be further considered in the project -level environmental analysis and the identification of alternatives that will not be studied in the EIR/EIS analysis.• The Authority and the FRA will make these decisions, considering agency and public input. The AA reports will provide the basis for drafting the Alternatives Chapter in the Draft Project EIR/EIS. This memorandum applies to the initial review and analysis process to be used by each of the regional teams in identifying the full range of HST project alternatives and station sites for preliminary review in order to support decisions determining the reasonable and feasible alternatives to carry forward for further engineering and environmental review.. Each regional team is to use the engineering CAHST Basis of Design Technical Memo in their evaluation efforts, but will have flexibility if needed, to identify additional evaluation criteria that are specific to their region. This memorandum is consistent with the guidelines developed for the project environmentalreview phase, as defined by the CAHST Project Environmental Analysis Methodologies Report, and will help to ensure a consistent level of documentation of the analytic process for determining the alternatives to be analyzed in a project -level EIR/EIS. 1.3 OVERVIEW Whereas the program EIR/EISs analyzed alternative corridors and station location alternatives, site -specific alignment and station alternatives will be developed for the project -level AA Reports. In the statewide program EIR/EIS, No Project, Modal, and HST Alternatives were considered. The Authority and FRA selected the HST Alternative and selected corridor alternatives and station location options for further analysis, and identified needs for HST system cleaning and maintenance facilities. The Bay Area to Central Valley HST Program EIR/EIS supported Authority and FRA selection of corridor alternatives and station location Page 1 December 2008 ['tfffeinai FF1f./FSP141'daILKG'1fWer r California High Speed Train Project Alternatives Analysis Methods options for further analysis in the Bay Area and Central Valley regions. The program -level environmental reviews were integrated with early steps in the Clean Water Act Section 404 alternatives analysis process. The evaluation conducted for each of the AA reports will be based on preliminary alignments and will reflect a level of detail that considers preliminary project features at a 2% to 4% engineering design, but does not focus on the details of design. The analysis of alternatives will take into account previous work conducted for the Program EIRs/EISs. In some locations, program -level decisions narrowly defined the HST corridor, while in other locations a broader area was defined as the corridor for further evaluation. In addition, each of the regional teams will consider public and agency comments in response to the project -level EIR/E1S scoping processes and direction from the Authority and FRA. Input during the agency involvement process will also be Considered a key part of the alternatives analysis process to identify reasonable and feasible alternatives to carry forward for environmental review. The AA reports will fully document how each of the alternatives meets the Purpose and Need for the project, and how evaluation criteria was used to determine which alternatives would be carried forward for environmental analysis and which alternatives did not meet the evaluation criteria and were screened from further analysis. After the AA Reports have been finalized and reasonable and feasible HST location and design alternatives have been identified, a separate report that provides a detailed definition of alternatives will be prepared to describe each of the alternatives carried forward for environmental review. This report, the Alternatives Definition Report, will describe all design features and assumptions for the alternatives to support environmental evaluation and preliminary engineering design to 15%. 1.4 Additional Information Additional information and resources on HST system background, technical guidance, and evaluation criteria as well as previous Authority and FRA decisions can be found in the following locations. http://www:cahiohspeedraii.ca.govi Final Program EIR/EIS, Volumes 1 through 3, August 2005; the Authority's Certification and Decision on the Final Program EIR/EIS (Resolution No. 05-01); FRA Record of Decision for California High -Speed Train.. System, November 18, 2005,including the Mitigation Monitoring and Reporting Plan, the Summary of Public Comments from CEQA Certification, and the Errata for the Final Program EIR/EIS. Final Bay Area to Central Valley High -Speed Train Program EIR/EIS; Volumes 1 through 3, May 2008, including the Mitigation Monitoring and Reporting Plan, the Summary of Public Comments from CEQA Certification, and. the Errata for the Final EIR/EIS; the Authority's Certification and Decision on the Final Program EIR/EIS (Resolution No. 08-01); and FRA Record of Decision,. December 2, 2008. https://ww2.prolectsolve2.com/eRoom/SFOF/CAHSRProoramMemt http://www.fra.dot.gov/Downloads/RRdev/corridor planning.pdf 2.0 LEVEL OF EFFORT 2.1 APPROACH The AA Reports will document the initial process of defining and evaluating project alternatives for sections of the HST system. The process will begin with the alignment and station information provided in the relevant program EIR/EIS, which with additional information Page 2 December 2008 , vmz a rnan.urfnMI{ dunwwn• California High Speed Train Project ,alternatives Analysis Methods gathered by the section design team and information gathered during scoping will be used by the team to identify preliminary project alternatives. These alternatives will include alignment alternatives, station site alternatives, alternative sites for the cleaning, maintenance and storage facilities, and power supply facility alternatives needed for the HST system section. As the Alternative Analysis process continues, the alternatives will be revised using CHSTP design criteria for trackwork geometries, civil and structures design, systems design, and train operations. The AA Reports are to provide sufficient detail to document the evaluation process used to identify reasonable and feasible project alternatives that would meet the Purpose and Need for the project and are consistent with the Basis of Design Report as well as to identify those alternatives where environmental issues (severe conflicts or constraints) or engineering challenges may justify dropping them from further analysis. The AA Reports are to provide comparative information and data that highlight and compare similarities and differences between alternatives by using project design criteria. Each Regional Team will evaluate preliminary location and design alternatives against existing conditions, project -related changes, applicable state and federal standards, environmental impact criterion, design criteria, construction and operating factors, to support identification and selection of the reasonable range of practicable and feasible alternatives for project environmental review. The process will include the following steps: 1. Initial Project Alternatives — Using the selected program -level corridor alignments and station locations, develop site -specific project alternatives considering current contextual conditions and constraints as well as information gathered during the scoping process. It is essential to start with the selected program alternatives as these were identified as likely to contain the Least Environmentally Damaging Practicable Alternative (LEDPA) with concurrence by the U.S. Environmental Protection Agency and the U.S. Army Corps through the Clean Water Act Section 404 alternatives analysis process. 2. PMT, Authority and FRA review of initial project alternatives. 3. Initial Screening Prepare an initial evaluation for each alternative based on project - level existing conditions, future development plans, and other environmental studies prepared within the study area to identify alternatives likely to have severe constraints, conflicts with existing. conditions, or approved future development in the study area. 4. Compare alternatives that are similar and determine which are best to carry forward for further evaluation. 5. Assess Environmental and Right -of -Way Constraints - Using the project alternative evaluation measures presented in Section 4.2 of this memo prepare a comparative analysis of the alternatives. 6. Project Alternatives Workshop - Conduct a workshop with the Authority and FRA to discuss the Draft Alternatives Analysis Report, severe design constraints or conflicts, and environmental impacts and benefits for each alternative. Purpose of the workshop is to get direction from the Authority and FRA on further investigation of alternatives, and to discuss alternatives to be identified for no further analysis, evaluation conclusions, and material to present to the public. 7. Draft. Alternatives. Analysis Report — Develop a preliminary definition of the project alternatives using the Basis of Design Report and applicable Technical Memoranda. Submit to the Authority and FRA for approval. Page 3 December 2008 C4U'w, iiliic adranu&W a, maxim California High Speed Train Project Alternatives Analysis Methods 8. Public & Agency Outreach - Present evaluation process for preliminary alternatives to environmental, local, and transportation agencies and public and private stakeholders for input. 9. Refine Preliminary Definition of Project Alternatives — Based on comments and input received from the Public Outreach revise the project alternatives, as needed. 10. Final Alternatives Analysis Report — Finalize the report and submit to the Authority and FRA for approval. The Final Alternatives Analysis Report will document the alternatives to be carried forward through the environmental analysis process and alternatives not to receive further analysis. 2.2 COORDINATION Each Regional Team will coordinate their efforts with the project management team (PMT), Authority and FRA. Preliminary information including the initial project alternatives as well as initial alternatives screening and evaluation shall be presented to the PMT, Authority and FRA using diagrams, drawings, memoranda, and presentations that effectively communicate the informationwhile minimizing preparation time and effort. The AA reports will be initially reviewed by the. PMT, revised and submitted to the Authority and FRA for their review and comment. In addition, each AA Report will contain a discussion of the coordination and consultation efforts related to alternatives analysis and opportunities for agency and public input in the process. Coordination among regional teams is required at shared project limits where the end points would connect at common stations (example; Union Station for Anaheim to LA and LA to Palmdale sections). 3.0 ASSESSMENT / ANALYSIS 3.1 ALTERNATIVES EVALUATION The AA evaluation will be conducted using standardized criteria so that each of the alternatives can be compared with each other in an effort to identify feasible and reasonable alternatives and those that should be eliminated from further consideration due to environmental or engineering issues that would make approvals or implementation infeasible; that would not reduce or avoid adverse environmental impacts, that would not meet purpose and need and project objectives, or would not be feasible or practicable to construct. Each AA Report will assess preliminary alignments and station sites appropriate to the section of the HST system being studied, using the evaluation measures discussed in Section 4.0; however, each of the regional teams will have the flexibility to weight evaluation criteria differently to reflect the relative importance of issues in their region. Each report will include a brief discussion that characterizes key constraints or concerns in the region and explains criteria weighting. Specific evaluation criteria to be used in addition to criteria listed in Section 4.0 below must be discussed with and approved in advance by the PMT, Authority, and FRA. Applicable evaluation, discussion, and conclusions from the program EIRs/EISs should be incorporated as appropriate into the AA Reports. 3.2 SCOPE OF ANALYSIS Whereas the Program EIR/EIS evaluated the potential impacts various system alternatives would have ata planning level of detail, the AA Reports will assess preliminary project alignments, station sites and related facilities sites at a site -specific level of detail. The. AA Reports will document literature review; database queries, and field reconnaissance and will include a discussion of potential environmental constraints related to short-term and long-term effects. Short-term impacts will include construction and implementation issues. Long-term impacts will consider the direct and indirect effects of construction and daily operations of the project. The AA Reports are to describe the physical effects of the location and design Page 4 December 2008 eu uvA•u 11(CASPFEIQ RG d lR NORM California High Speed Train Project Alternatives Analysis Methods alternatives as well as consistencies with federal, and sta.?. environmental standards and future planned development. The AA Reports are to describe a range of typical measures or engineering designs that could be considered to avoid, minimize, or mitigate potential impacts and an assessment of the reasonableness and feasibility of these measures. Appropriate measures and engineering designs to be considered should be identified first from the mitigation monitoring and reporting programs approved for the two Program EIRIEISs, and then should be further defined and refined to apply to the site -specific and regional issues. 4.0 EVALUATION MEASURES 4.1 CHSTP DESIGN OBJECTIVES Project alternatives shall be evaluated using system performancecriteria that address design differences and qualities. Alignment. and station performance objectives and criteria are: Objective Criteria Maximize ridership/revenue potential Travel time Route length. Maximize connectivity and accessibility Intermodal connections Minimize operating and capital costs Operations and maintenance issues and costs 4.2 PRELIMINARY ALTERNATIVES ANALYSIS CRITERIA In addition to the CHSTP objectives and criteria above, further measures to evaluate and compare the project alternatives have been described below. Where it is possible to quantify the effects, estimates are to be provided, and where it is not possible to quantify effects, qualitative evaluation should be provided. A. Land use supports transit use and is consistent with existing, adopted local, regional, and state plans; and is supported by existing or future growth areas as measured by: Measurement Method Source Development potential for Transit Oriented Development (TOD) within walking distance of station Sites within 1i2 -mile of station compare potential of different stationsites; note location(s) with highest potential for TOD development Regional and local planning documents and land use analysis and input from local planning agencies Consistency with other planning efforts and adopted plans Qualitative - General analysis of applicable planning and policy documents Land use analysis and input from planning agencies Page 5 December 2008 CALIFORNI OGI/SPEED w¢.ionmarr California High Speed Train Project Alternatives Analysis Methods B. Construction of the alternative is feasible in terms of engineering challenges and right-of- way constraints as measured by: Measurement Method Source Constructability, access for construction; within existing transportation ROW Extent of feasible access to alignment for construction Plans and maps C. Minimize disruption to neighborhoods and communities — extent to which an alternative minimizes right-of-way acquisitions, minimizes dividing an established community and minimizes conflicts with community resources as measured by: Measurement Method Source Displacements. Number of residences and businesses displaced, size of properties and magnitude of property value of displaced (ranked as least, .most # displaced; # acres) Identified using concept drawings and aerial photographs Properties with Access Affected Number of properties whose access would be permanently disrupted Number of properties disrupted by construction Estimated off concept plans and aerial photographs Local Traffic Effects around stations Potential increase in traffic congestion or LOS at critical intersections Existing traffic LOS from local jurisdictions D. Minimize impacts to environmental resources — extent to which an alternative minimizes impacts on natural resources as measured by: Measurement Method Source Waterways and wetlands and nature preserves or biologically sensitive habitat areas affected Number of new bridge crossings required; rough estimate of acres of wetlands; linear feet of waterways; acres and species of T&E habitat affected; acres of natural areas affected Measured off concept plans and GIS layers; Section 404(b)1 analysis. Cultural resources Number and type of historic. architecturalproperties and archaeological sites directly impacted Basedonconcept plans and GIS layers; Section 4(f) studies and cultural resource records search and surveys Parklands Number and acres of wildlife refuges and parks directly and indirectly affected Based on concept plans and GIS layers; Section 4(f) studies.. Agricultural lands Acres of prime farmland, farmland of statewide importance, unique farmland, and farmland of local importance within preliminary limits of disturbance Based on concept plans and GIS layers GfwwOR94 A47F0/iNf.A 1.1117110M RUI;,i,'rnoRtn' Page 6 December 2008 California `nigh Speed Train Project Alternatives Analysis Methods E. Extent to which an alternative minimizes impacts on the natural environment as measured by: Measurement Method Source NoiseNibration effects an sensitive receivers Number of and types of receivers with projected noise levels and vibration levels above FRA impact threshold Results of screening level assessment: inventory of potential receivers from site survey and aerial maps Change in visual/scenic resources Number of view corridors and scenicivisual resources affected; extent of elevated structures in scenic areas and shadows on sensitive resources (parks) Results of general assessment; survey of alignment corridors and planning documents from local and regional agencies Maximize avoidance of areas with geologic and soils constraints Soils/slope constraints Seismic constraints (proximity to earthquake zones) USGS maps Maximize avoidance of areas with potential hazardous materials Hazardous materials/waste constraints Data from records search of hazardous materials locations and generators. 5.0 DOCUMENTATION 5.1 LEVEL OF IMPACT Each preliminary alternative should be evaluated individually under each objective and criterion at a preliminary level of analysis sufficient to identify potentially severe constraints and to provide an overall comparative analysis of the potential 'levels of impact' for the alternatives in a summary format. This information is expected to support determination of the feasible alternatives to be analyzed in the Draft Project EIR/EIS and the alternatives dismissed from further consideration. Starting with the Authority's adopted program -level Mitigation Monitoring and Reporting Plans, the Regional Team should identify practical mitigation measures, design considerations or avoidance techniques to address ways to minimize or avoid potentially significant impacts for consideration in the EIR/EIS: The measures should illustrate a general approach versus describing specific mitigation measures which would be addressed in the EIR/EI.S. The measures should account for cause, effect, resolution and follow an "if this", "then that" format. Consideration should be given to estimated costs and likely ability to mitigate different ROW and environmental impacts. 5.2 ALTERNATIVES COMPARISON The primary purpose of the AA Reports is to clearly describe the relative differences between preliminary alternatives based on a consistent set of evaluation criteria applied to each alternative. The AA Reports will summarize the attributes, potential design issues and environmental impacts and benefits for each alternative in matrix format. Alternatives identified to be dropped from further analysis should be included in the matrix and reasons for dropping the alternative should be described in the summary, A4iFPRNIA" -CaL!}i7RV'.ti Mai iPEEDIL dUTTttMIli Page 7 December 2008 California High Speed Train Project Alternatives Analysis Methods 6.0 REFERENCES 6.1 INFORMATION FOR INCLUSION All references will follow the format guidelines provided for the CHSTP. All sources must be referenced, including text, data, graphics, base maps, etc. Full referencing is also required in the text of the document in a footnote at the end of the sourced text. For tables, references will be listed as sources at the bottom of the table. For graphics, references, including base mapping, will be listed as sources in the legend. ALIFQRNIA C LIFOR' ,lfG7fSPE&DR11L , l7,o,YIri Page 8 December 2008 ATTACHMENT F Cityof Palo Alto Office of the Mayor and City Council " December 15, 2009 Mehdi Morshed, Executive Director California High Speed Rail Authority 925 L Street, Suite 1425 Sacramento, CA 95814 RE: Alternatives Analysis for San Francisco to San Jose Project EIR Dear Mr. Morshed: The Alternatives identified to date for study in the Project EIR for the San Francisco to San Jose Project include two elevated alignments (berm or elevated structure) and two below grade options (open trench or tunnel). The No Build project stops the HST service in San Jose without a HST alternative extending north to San Francisco. Palo Alto wishes to reiterate the following comments provided in the City's March 30 scoping comments letter to the Authority with regard to inclusion of an alternative that ends HST service at San Jose and provides connecting service to San Francisco via enhanced Caltrain service: "Evaluate an alternative that would end HST at San Jose and rely on upgraded electrified and grade -separated Caltrain connections to/from San Francisco, including facilitating improved Caltrain access and speeds and possible reduction in the number of tracks required in the Caltrain corridor. The Palo Alto station is the second busiest on the Caltrain line and as such serves approximately 3,700 hoardings per day. Caltrain's future 2025 Plan provides for electrification and an increase in the current 96 daily trains up to 172 trains. The EIR/EIS should evaluate whether Caltrain could provide the frequency, capacity and speed for the connecting service between San Jose and San Francisco in lieu of HST service." Palo Alto thus requests that the alternatives for the San Francisco to San Jose section be expanded to include this alternative. Thank you for considering this request, and please let us know as soon as possible whether these items can be incorporated into your project. If you or others have questions, please feel free to contact me or Deputy City Manager Steve Emslie at 329-2354 or steve.emslie@cityofpaloalto.org. Thank you for your assistance with this matter. Sincerely, Palo to City Council by City Council Subcommittee Chair for High Speed Rail P.O. Box 10250 cc: Robert Doty, Peninsula Corridor Joint Powers Boasd Alto, CA 94303 City Council 650.329.2477 James Keene, City Manager 650.328.3631 fax Printed with soy -based inks on 100% recycled paper processed without chlorine. ATTACHMENT G HIGH SPEED RAIL 2010 SCHEDULE OF MEETINGS All Dates Subject to Change Peninsula Cities Consortium (PCC) Meetings: (8:15-9:45 a.m.): PCC meetings rotate between the Cities of Palo Alto, Menlo Park, Atherton, Belmont, and Burlingame on a quarterly basis. Menlo Park January 8 & 22 February 5 & 19 March 5 & 19 Venue TBD April 2, 16, & 30 May 14 & 28 June 11 & 25 Venue TBD July 9 & 23 August 6 & 20 September 3 & 17 Venue TBD October 1, 15, & 29 November 12 & 26 December 10 & 24 Palo Alto City Council January 25 March 1 April 19 June 7 July 19 August September 13 October 25 December 6 HSRA Board Meetings: January 7 February 4 March 4 April 1 May 6 June 3 July 1 August 5 Council Committee Report Council Study Session Council Committee Report Council Committee Report Council Study Session Break Council Committee Report Council Committee Report Council Study Session 915 I Street Sacramento, CA 95814 at 10:00 am September 2 October 7 November 4 December 2 Peninsula High Speed Rail Technical Advisory Committee (TAC) & Policv Advisory Committee (PAC): February May August November Alternatives Analysis Report: March Draft EIR/EIR: December