HomeMy WebLinkAboutStaff Report 260-06City of Palo Alto
City Manager’s Report
TO:
FROM:
DATE:
SUBJECT:
HONORABLE CITY COUNCIL
CITY MANAGER DEPARTMENT: PUBLIC WORKS
JUNE 12, 2006 CMR:260:06
REQUEST FOR COUNCIL DIRECTION ON PROPOSED MITCHELL
PARK LIBRARY EXPANSION,SPACE REQUIREMENTS AND
PROJECTED COSTS
9
RECOMMENDATION
Staff recommends that the City Council a) approve the recommended project timeline and
methodology for determining the potential size and costs of the new Mitchell Park Library; and
b) approve deferring work on the Roth Building or the College Terrace infrastructm-e upgrades to
give staff the necessary time to work on this project.
BACKGROUND
In December 2004, the City Council directed the Library Advisory Commission (LAC) to
"recommend a strategy for creating a Nil-service library at the existing site or another site, a
strategy to include maintaining neighborhood facilities and distributed services; to maintain
collection services, and to direct the LAC to recommend a redefinition of branch services."
The Library Advisory Commission returned to the Council on May 15, 2006 to present an
interim report on its work-in-progress, the Library Service Model Analysis and
Recommendations ~SMAR), and to ask for Council feedback and direction. The Council gave
conceptual approval to several key concepts in the draft report, including maintaining all current
library locations; expanding and/or improving access to services; seeking further efficiencies;
and upgrading Mitchell Park library services from branch library resource levels without
downgrading the Main Library.
Among other points, the Council directed the LAC and staff to "Determine how big Mitchell
Park Library would need to be," and "prepare preliminary cost models/projections/estimates for
capital needs." Staff was directed to return to Council with this information for inclusion in the
LAC’s final report by September 11, 2006 (Schedule A).
The Council made it clear that existing General Fund revenues would not be used to cover the
added costs associated with the Library plan, and that additional funding would need to come
from a tax measure or other new source.
CMR:260:06 _.Page 1 of 5
DISCUSSION
A three-part study is needed to determine a) the potential maximum size of the new Mitchell
Park Library building; b) the estimated square footage requirements for the proposed building as
envisioned by the LAC; and c) cost estimates for building and operating the new library. An
architectural consultant with expertise in public library facilities will be required.to make these
determinations.
Given that the new library facility must not encroach on park land, available sites are very
limited. There seem to be three potentia! sites: a) the footprint of the exi~ing libra.ry building; b)
the footprint of the existing library and community center (in which case the proposed new
building would need to provide sufficient space for the community center, unless the community
center operations could be relocated elsewhere, such as to Cubberley; or c) the parking area to
the south of the comrnurfity center, rneaning the access road and parking would be shifted to
where the existing buildings are located. The consultant might identify other feasible sites.
Because potential sites for the new library seem few in number, the amount of space to
adequate!y provide for library services for the next twenty to forty years is limited as wel!.
Moreover, a larger building will trigger the need for more parking. If resistance to an
underground structure dictates, a large amount of the !imited available space will need to be
allocated to surface parking, the space availability for the library building, and its capacity for
meeting identified needs such as expanded collections, adequate public spaces for different uses,
and flexibility for as-yet-unforeseen services and programs will be severely limited.
It is advisable to secure a consulting team that has familiarity with trends and best practices in
public librap~, construction, so that it can accurately project space requirements for optimal
application of new technologies, self-service options, automated materials handling, ergonomic
work areas, and other critical program elements. Attachment A is a scope of work for consultant
services that will be needed for this project. This scope of work differs from that included in the
contracts exceeding $85,000 duNng the 2006-07 budget process (C~-~/hR:228:06) in that it does not
include environmental assessment work.
At least two important issues will need to be considered as the Council moves forward with this
project:
Staffing for this project
The impact of this project on already scheduled work at the Mitchell Park Library and
Community Center.
It is important to note that despite Council guidance to focus on maintaining existing
infrastructure, this project and others such as the Public Safety building and the Roth Building
require staffing resources originally designated for projects to rehabilitate existing infrastructure
to be redirected to planning for and design of new facilities. Staff is over ful! capacity with the
combination of FY05/07 budgeted projects and additional priorities which have been added by
Council during the past 12 months. Those new projects include the Police Building BRTF, the
advanced schedule for Charleston-Arastradero, the MSC - auto dealers study, Roth Building
renovations, and the CAADA California Avenue streetscape master plan project. Staff has
CMR:260:06 Page 2 of 5
literally worked on evenings, weekends, and holidays to ensure that the schedules for those
additional priorities would be met. No further capacity to take on additional work remains.
This additional work cannot be taken on without deferring something else. It is recommended
that the Roth Building or the College Terrace Library improvements be deferred for six months
to allow for this project to take priority. Delaying one of these two projects will free up enough
stafftime to apply to the successful completion of this project.
The Mitchell Park Library and Community Center have been slated for important infrastructure
improvements since 1998. These improvements include electrical, mechanical, seismic and
accessibility upgrades at both buildings. The work was deferred pending the Library bond issue
of 2002, and when that measure failed, it was rescheduled tbr design in 2005. An assessment of
necessary upgrades, including a projected budget, was conducted prior to design, and the
assessment revealed that the cost of doing the necessary upgrades on both buildings would be in
excess of $2.4 million. Further work on infrastructure has been put on hold pending completion
of the Children’s Library and outcomes from the Library Advisory Commission’s planning
process. Public Works recommends prompt attention to the critical infrastructure upgrades,
particularly at the !ibrarj, despite the possibility of construction of a new library building or a
new combined community center/library. Realistically, a new building is at least six years away,
and the existing systems are long past their functional life. Once some key parameters for the
new Mitchell Park Library have been established, staff will need to return to the Council for
further direction on the implementation of some or all of the in_frastructure upgrades to the
existing buildings.
RESOURCE IMPACT
Effective July 1, 2006 pending Council’s approval of the 2006-07 proposed budget there will be
$4007000 in the Capital Improvement Program (CEP) (PE-07011) for design and other initial
costs associated with the Library Advisory Commission’s rgcommendations. Work can beNn
prior to July 1 to secure the consultant and finalize the contract. It should be noted that there is
some cormnunity and perhaps Council interest in a bifurcated library project, consisting of a new
Mitchell Park Library building and a possible expansion renovation of the Main Library, rather
than focusing exclusively at Mitchell Park. This may become even more necessary if space
limitations at Mitchell Park preclude the construction of a building of adequate size. If so, this
budget would need to cover initial costs at both locations.
Costs for the scope of work as described in the first paragraph under "Discussion", above, will
likely be between $150,000 and $250,000.
POLICY IMPLICATIONS
This recornmendation is consistent with Council’s direction to the LAC in May, and consistent
with the establishment of the Library as a Top 3 priority for 2006.
TIMELINE
Two possible timelines are presented for the Council’s consideration. The first, Schedule A, is
extremely aggressive, and may not provide the information desired by Council by Council’s
deadline of September 11, 2006. The second allows for all the required steps in the procurement
CMR:260:06 Page 3 of 5
process and is more realistic given current workloads in Purchasing, Public Works, the
Attorney’s Office and the Library. Staff will make every effort to fulfill the Council’s
expectations and complete this project as swiftly as possible.
i Prepare request for proposals
Pursue sole source contract
Response period for RFP
Evaluate responses
Finalize contract
Council award contract
Project fulfillment
Report to LAC
LAC develop report to Council
Total weeks
Schedule A
Meet Sept 11 deadline
(numerals represent number
of weeks per task)
1
Skip
Skip
3
1
4
1
12
(September 11)
Schedule B
Based on actual practice
(numerals represent number
of weeks per task)
2
skip
4
2
6
1
11
1
2
29
(December 22)
It shotfld be noted that Schedule B still complies with the recently approved Top-3 Priority
milestones for the Library as the consultant selected for this effort would likely be considered for
the follow-on design work needed to get a potential library measure on the ballot by June 2008.
EI~WIRON~IENTAL REVIEW
This limited-scope project is statutorily exempt from CEQA.
ATTACHMENTS
Attachment A: Outline Scope of Work for consultant services
Assistant Director
DEPARTMENT HEAD:/.~--- ....
GLENN S. ROBERTS
Director of Public Works
CMR:260:06 Page 4 of 5
CITY MANAGER APPROVAL;
PAULA SIMPSON
Library Director
EMILY HARRISON
Assistant City Manager
CMR:260:06 Page 5 of 5
ATTACHMENT A
Scope of Work
Mitchell Park Library Space Study
1.General Information
The City of Palo Alto is requesting proposals from Consukants to prepare a study to
evaluate the space available to renovate or replace the existing Mitchell Park Library
located at 3700 Middlefield Road, Palo Alto. Design and construction cost estimates
should also be prepared for the proposed improvements.
Mitchell Park is a community parking serving the entire city of Palo Alto. The park
is located in a residential area with surrounding land uses that include several schools,
churches a senior complex and other educational facilities. The approximately 22
acre Mitchell Park is comprised of an 18 acre outdoor recreational park with surface
parking and an adjoining 3.2 acre area that contains the library, community center and
surface par-king area. The library and community center are not on dedicated park
land. The site is shown on Attachment A.
Palo Alto’s public library system is comprised of five libraries. The City has a high
library item per capita circulation rate and recent studies by the Library Commission
have shown the Mitchell Park Library to be the most space-constrained.
2. Proiect Description
The Library was designed by Edward Durell Stone and built in July of 1958. It has
been used exclusively as a library since construction. The Library was expanded in
1974 to its current size of 10,984 square feet. The City wishes to determine the cost
and compare the benefits of, building a new library on the existing site or renovating
and expanding the existing library.
The project site, which is shared by the Library and Community Center, includes two
surface parking lots immediately adjacent to the Library and Community Center
buildings. The parking lots have a total of 264 parking stalls.
3. Scope of Work
S cenario s:
a)
b)
The three scenarios to be evaluated are as follows:
Demolish the existing library and construct a new library without
adversely impacting the Community Center.
Construct a new library on the surface parking lot south of the community
center and add surface parking where the Community Center currently
stands.
c)Demolish the existing Library and Community Center and construct acom
combined facility on the site.
Site Constraints and Assumptions
a) No parkland will be considered in the expansion
b) All work, whether remodel or rebuild scenario, must fit onto the
existing site.
c) In the "demolish and rebuild" scenario, it is possible, and may even be
desirable, to relocate the existing parking onto the other side of the
site. This may allow removal of an existing signal and allow better
access to both Library- and Community- Center parking and to 1Vfitchell
Park.
Reference Materials: The following studies were prepared for this site and will be
available for review:
1) Draft "Mitchell Park Library and Community Center, Design Development
Study Report", December 2005
2) "Mitchell Park Library and Community Center, Initial Study", April 2002
Task A Site Assessment
The Consultant shall meet with City staffto review the existing Library and Community
Center site. The Consultant shall interview Library staffto identify what technology and
programs are currently used in the program and what upgrades would be desirable.
These needs may need to be scaled back as needed to fit into any new Libraw.
The Consultant shall review existing reports listed above under "Reference Material" and
review existing site plans.
Task B Conceptual Space Availability
For scenarios a), b) and c) above:
Evaluate the existing site and identify opportunities for, and cost of, expansion.
Include any related code upgrades that might be required. Prepare massing diagram and
pertinent report for: expandability of the existing building; human, vehicular and material
flow patterns; analysis of operating functions; adjacency and parking demand and
adequacy.
No design renderings or elevations will be needed for this Task. The purpose is to
identify how much space could be made available and which functions could occupy that
space.
Task C Cost Estimate
For scenarios a), b) and c) above:
Prepare cost estimates for the expansion and any needed relocation of existing
services. Cost estimates shall be prepared by a firm specializing in construction cost
estimating. Costs shall be presented in current-year dollars, but inflation projections shall
be given for the anticipated construction year, which will be provided by City. The
estimate should include the cost to design, construct and commission a LEED-certified
building.
For financing purposes, costs shall be broken into two categories: 1) ’hard costs’
to include design, consWaction, testing, construction management and hazardous material
testing and removal and 2) ’soft costs’ such as furniture, equipment and moving costs.
Furniture and equipment will be re-used as much as possible.
Due to the schematic nature of the workscope, a detailed cost estimate is not
required and per-square foot costs may be used. The numbers used should be
conservative in order to reflect the conceptual nature of the design.
Task C Meetings
¯ Meet as needed with City staff
¯ Consukant shall prepare presentation materials for 1 meeting with the Library Advisory
Commission. Consultant shall budget each meeting at up to two hours (this includes the
’waiting time’ as well as presentation time) and shall include travel time and the cost of
any presentation materials.
¯ Consultant shall prepare presentation materials for 1 meeting with the Parks and
Recreation Commission. Consultant shall budget each meeting at up to two hours (this
includes the ’waiting time’ as well as presentation time) and shall include travel time and
the cost of any presentation materials.
¯ Consultant shall prepare presentation materials for, and attend 1 meeting with the City
Council. Consultant shall budget each meeting at up to four hours (this includes the
’waiting time’ as well as presentation time) and shall include travel time and the cost of
any presentation materials.
Task D Reimbursables
¯ The Consukant shall prepare a report summarizing the findings and costs for the 3
scenarios listed above. The report shall include massing diagrams showing adjacency,
circulation and parking. The design and construe’don costs shall be presented in a table
format so that each Scenario can be easily compared to the other.
¯ Consultant shall submit a preliminary and final copy of the report for review and revise
as needed based on staff or advisory board comments. Consultant shall provide 2
unbound copies of each report and 2 reproducible copies of schematic plans associated
with the report.
The cost of travel and meals shall be included in Task C, Meetings.
The mark-up on subconsultants, printing and related tasks shall not exceed 10 percent.
Task E Additional Services
If approved by the City Project Manager in advance and in wMting, additional services
may include but are not limited to: additional meetings, study scenarios or cost estimates.