Loading...
HomeMy WebLinkAboutStaff Report 221-06City of Palo Alto Manager’ Report 2 TO:HONORABLE CITY COUNCIL FROM:CITY 5~LNAGER DEPARTMENT: UTILITIES DATE: SUBJECT: MAY 15, 2006 CMR: 221:06 ADOPTION OF A RESOLUTION APPROVING THE FACILITIES STUDY AGREEMENT WITH PACIFIC GAS AND ELECTRIC COMPANY IN AN AMOUNT NOT TO EXCEED $220,000 TO DETERSfiNE THE FEASIBILITY AND DEVELOP A COST ESTIMATE OF CONVERTING THE PALO ALTO TO RAVENSWOOD ELECTRICAL TRANSMISSION LINE FROM 115 KV TO 230 KV RECOMMENDATION Staff recommends that the City Council adopt the Resolution approving the Facilities Study Agreement with Pacific Gas and Electric Company (PG&E) in an amount not to exceed $220,000 to determine the feasibility and develop a cost estimate of converting the Palo Alto to Ravenswood electrical transmission line from 115 kV to 230 kV, including the amount of $200,000 for the study and $20,000 for unforeseen additional services. BACKGROUND The electrical transmission charge assessed by the California Independent Systems Operator (CASIO) for the use of the electrical transmission grid is based on the voltage at which electricity is delivered to the City. At present the City pays a Transmission Access Charge (TAC) of approximately $6 for every Megawatt-hour (MWh) of electricity delivered to the City. This is equivalent to an annual cost of approximately $6 million. If the City upgrades the connection voltage from the present 115 kV level to the 230 kV level, the annual TAC cost to the City is expected to drop from $6 million/year to approximately $3 million/year. CMR:221:06 Page 1 of 3 DISCUSSION The connection voltage upgrade from 115 kV to 230 kV will require PG&E to upgrade its 115 kV double circuit transmission line from PG&E’s Ravenswood substation to a PG&E-owned substation adjacent to the City’s Colorado substation. In order to study the upgrade of the line and undertake the necessary reconfigurations, the City and PG&E have developed a Facilities Study Plan (Attachment C). The Study Plan has the following elements: 1. Assessment of the feasibility of converting the lines. 2.Cost estimates and work scope for converting the lines from 115 kV to 230 kV. 3.Cost estimates and work scope for modifying PG&E’s Ravenswood Substation to accommodate the new 230 kV lines and for removing PG&E’s Palo Alto Switching Station. 4.Cost estimates and work scope to maintain reliable transmission service during the conversion. 5. Construction schedule. Terms and conditions for the City’s electrical interconnection with PG&E are outlined in the NCPA/City Interconnection Agreement with PG&E (CMR:298:02 of July 15, 2002). The Facilities Study Agreement will be governed by terms and conditions outlined in this Federal Energy Regulatory Commission ~ERC)-approved Interconnection Agreement. Staff is also studying an alternative to this project by evaluating the potential of connecting to the 230 kV electrical grid on the west side of town through the 230 kV substation at the Stanford Linear Accelerator Center (SLAC). A contract to study this option will be brought to Council in the coming months. RESOURCE IMPACT The estimated cost of the study is $200,000 and this amount has been included in the Utilities Department budget (Capital Improvement Program Project EL-06001). The full $200,000 payment will be made to PG&E upon Council approval of the agreement. Since it is a cost- based study, if the actual cost incurred by PG&E in conducting this study is less than $200,000, the unspent amount will be returned to the City. There is also a possibility that actual costs may be higher. An additional $20,000 to cover such unforeseen events has also been included in the project budget. The decision whether or not to implement the upgrade will depend on the study assessment of the cost of the upgrade versus the cost of the SLAC alternative upgrade, compared with a potential cost savings of $3 million per year. CMR:221:06 Page 2 of 3 POLICY IMPLICATIONS This study supports Strategy 1 of the Utilities Strategic Plan, to ensure a high level of system reliability in a cost effective and timely manner. EI~,WIRONMENTAL REVIEW Execution of the Agreement does not constitute a project for the purposes of the California Environmental Quality Act (CEQA). ATTACHMENTS A: Resolution Approving the Facilities Agreement with Pacific Gas and Electric Company B: Facilities Study Agreement with PG&E C: Facilities Study Plan PREPARED BY:Debra Lloyd, Resource Planner Tom Finch, Senior Power EnNneer Shiva Swaminathan, Senior Resource Planner DEPARTMENT HEAD: CITY MANAGER APPROVAL: CARL YEATS Director Services EMILY HARRISON Assistant City Manager CMR:221:06 Page 3 of 3 ****NOT YET APPROVED**** ATTACHMENT A RESOLUTION NO. RESOLUTION OF THE COUNCIL OF THE CITY OF PALO ALTO APPROVING THE FACILITIES STUDY AGREEMENT WITH PACIFIC GAS AND ELECTRIC COMPANY IN AN AMOUNT NOT TO EXCEED $220,000 TO DETERMINE THE FEASIBILITY AND DEVELOP A COST ESTIMATE OF CONVERTING PALO ALTO TO RAVENSWOOD ELECTRICAL TRANSMISSION LINE FROM 115 KV TO 230 KV WHEREAS, the City of Palo Alto ("City"), a municipal utility and a chartered city, is electrically interconnected to the transmission system owned by Pacific Gas and Electric Company (PG&E) under terms and conditions of the September 2002 Interconnection Agreement ("IA"); WHEREAS, to continue to reliably serve the electrical load of the City at a reasonable cost, the City wishes to study the feasibility of upgrading the 115 kV line from the City’s Colorado substation to PG&E’s Ravenswood substation; WHEREAS, the City has negotiated with PG&E to conduct a Facilities Study Plan and to enter into a Facilities Study Agreement ("Agreement") under the terms and conditions established in the IA; NOW, THEREFORE, the Council of the City of Paio Alto hereby RESOLVE as follows: SECTION i. The Council hereby approves the Facilities Study Agreement with PG&E, in an amount not to exceed $220,000 to determine the feasibility and develop a cost estimate of converting the Pa!o Alto to Ravenswood electrical transmission line from 115 kV to 230 kV, including the amount of $200,000 for the study and $20,000 for unforeseen additional services. SECTION 2. The Council finds that the adoption of this resolution does not constitute a project under the California Environmental Quality Act and no environmental assessment is required. INTRODUCED AND PASSED: AYES: 060509 cs 00727 ****NOT YET APPROVED**** NOES: ABSENT: ABSTENTIONS: ATTEST: City Clerk APPROVED AS TO FORM: St. Assistant City Attorney Mayor APPROVED: City Manager Director of Utilities Director of Administrative Services 060509 cs 0072710 2 ATTACHMENT Facilities Study Agreement The City of Palo Alto (City) and Pacific Gas and Electric (PG&E) have reviewed the study plan for the conversion of PG&E’s Ravenswood - Palo Alto 115 kV Lines to 230 kV service, at the request of Palo Alto. PG&E shall perform the tasks and PG&E and the City shall abide by the terms and conditions set forth in the Facilities Study Plan, attached hereto and incorporated by reference. This Study is being undertaken within provisions established under the September 2002 Interconnection Agreement between PG&E and the Northern California Power Agency ..... fCITY OF PALO ALTO:",,\. PACIFIC ELECTRIC: BY: FRANK BENEST, City Manager APPROVED AS TO FORM: GRANT KOLLING, Senior Assistant City Attorney APPROVED BY: ’ (Name#l, Title) Title) EMILY HARRISON, Assistant City Manager APPROVED BY:MAILING ADDRESS: CARL YEATS, Director of Administrative Services MAILING ADDRESS: City of Palo Alto - Utilities Department Attn: Girish Balachandran, Assistant Director 250 Hamilton Avenue. Palo Alto, CA 94303 Dated this __ day of 2006. Dated this __ day of 2006. ATTACHMENT C Facilities Study Plan City of Palo Alto WE DELIVER ENERGY. May 15, 2006 2. 3. 4. 5. 6. 7. 7.2 7.3 7.4 8. Table of Contents Introduction ...........................................................................................................................1 Study Fee ..............................................................................................................................1 Facilities Study Schedule ......................................................................................................1 Cost Estimates ......................................................................................................................2 Interconnection Costs ...............................................................................................................................2 Project Information and Interconnection Plan ......................................................................2 Facilities Study Assumptions ................................................................................................5 Facilities Study Scope ...........................................................................................................6 Feasibility Assessment .............................................................................................................................6 Substation Evaluation ...............................................................................................................................7 Transmission Line Evaluation ..................................................................................................................7 Construction Schedule .............................................................................................................................7 Deliverables ..........................................................................................................................7 !1 CITY OF PALO ALTO~ RAVENSWQOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31, 2006 At the request of the City of Palo Alto (City), Pacific Gas & Electric (PG&E) will perform a Facilities Study (FS) to determine the feasibility and develop a cost estimate to convert, as requested by Palo Alto, PG&E’s existing 115 kV double circuit tower line (DCTL) between PG&E’s Ravenswood and Palo Alto Substations from 115 kV to 230 kV. This FS will consist of the following Tasks: Assessment of the feasibility of converting the lines. Cost estimates and work scope for modifying PG&E’s Ravenswood Substation to terminate the new 230 kV lines, and feasibility and cost estimates to remove PG&E’s Palo Alto Switching Station. o Cost estimates and work scope for converting the lines from 115 kV to 230 kV and extending to Colorado Substation, including cost estimates and work scope to maintain reliable transmission service during the conversion. 4. Construction schedule This FS Study Plan will form the basis for the Facilities Study Agreement (FSA) by defining the scope, content, assumptions, and terms of reference of the FS. The Facilities Study will provide interconnection cost estimates, as specified in Section 4.1, to be used in a Special Facilities Agreement, should Pato Alto and PG&E agree to proceed with construction. PG&E has estimated a study fee of $200,000 for performing this FS. PG&E will suspend work on the FS in the event that the final cost is expected to exceed $200,000, at which time PG&E will provide the City with a revised budget and will not resume work on the FS until such time as the City accepts the revised budget (City will inform PG&E of decision within 60 days). tn the event that the City does not accept the increase in budget, PG&E will provide the City with the FS results to date and will return the balance of study fee to the City within 60 days. The final cost to complete this FS will be based on actual cost. PG&E will provide the City a record of actual costs for performing this FS within 60 days of completion of the FS. PG&E will bill the City the remaining balance if the actual cost is higher than the estimated $200,000 and the City was informed of and accepted the revised budget. If the actual cost is less than the estimated study fee, or if the FS is terminated on completion of Task 1, the Feasibility Assessment, PG&E will return the balance to the City within 60 days of delivery of the final FS Report. CITY OF PALO ALTO RAVENSWOOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31, 2006 Establish study commencement date based on receipt of FSA. PG&E and City to agree on transmission arrangement to be assumed during the period of construction for the Feasibility Assessment. City to provide proposed Colorado Substation layout. ’ Completion of Feasibility Assessment Issue Initial Report on Feasibility Assessment results and budget status to City City reviews Initial Report and determines whether to continue or terminate the FS. Completion of Substation Cost Estimates, Transmission Line Cost Estimates, and Construction Schedule Issue final FS Report June 1,2006 TBD 12 Weeks from date of agreement on transmission arrangement during the period of construction. 30 Days after receipt of Initial Report 9 Weeks after City gives notice to continue FS + any delay from suspension of FS due to cost increase and time to restart work after notification All costs provided will be estimates only. Charges for implementing this interconnection and facility modifications, if the City decides to proceed, will be made based upon the actual costs incurred. 4.1 Interconnection Costs A decision quality engineering cost estimate (with a theoretical confidence level of +/- 25%) will be provided. Cost estimates will include any substation and transmission line facilities required to interconnect the City at 230 kV. The interconnection costs will include PG&E required 115 kV and 230 kV line protection, and removal of facilities in PG&E’s Palo Alto Switching Station. The estimate will not include any facilities constructed, owned, and operated by the City. 2 CITY OF PALO ALT(~ ~ RAVENSWQQD - PALQ ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31,2006 The City is presently interconnected to PG&E’s transmission system at PG&E’s Palo Alto Switching Station. There are three 115 kV lines that connect the Palo Alto Switching Station to the rest of PG&E’s transmission grid. A simplified one-line of the existing system is shown in Figure 5-1. A diagram showing the location of the existing facilities is shown in Figure 5-2. Ravenswood Cooley Landing PG&E Ownership 230 kV 115 kV Existing Ties Between City of Palo Alto & PG&E Transmission Systems Palo Alto Ownership PG&E Palo Alto Switching Station Pa,o Alto Colorado Switching Station Figure 5-1: Simplified One-line of Existing System 3 CITY OF PALO ALTO RAVENSWOOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31, 2006 Owner:. PGE ~lS ID: 71~ ®East Paio A Figure 5-2: Location of Transmission Facilities The City has requested that PG&E determine the feasibility and costs of converting the Palo Alto - Ravenswood 115 kV DCTL to 230 kV operations. This existing DCTL is about 4.3 miles long. After the conversion, the system would be similar to the simplified one-line shown in Figure 5-3. 4 CITY OF PALO ALTO~ RAVENSWOOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31,2006 Ravenswood J-,- J,-, Cooley Landing 230 kV 115 kV Assumptions for Palo Alto Switching Station and Colorado Substation to be a~eed upon prior to start of Facilites Study. Figure 5-3: Simplified One-line of Proposed System PG&E will conduct the FS using the following assumptions: As part of the FS, PG&E and City staff will meet, study, and mutually agree on the transmission arrangement to be assumed for service to Colorado Substation during the period of construction, including operation of the existing Cooley Landing - Palo Alto 115 kV circuit. ¯The Ravenswood - Palo Alto 1 !5 kV Lines will be converted to 230 kV operation, to the 230 kV takeoff structures within Palo Alto’s Colorado Substation. The City will provide the takeoff structures. The 115 kV connection from Cooley Landing Substation to Colorado Substation will be maintained and operated normally open for use as a back-up circuit after the Ravenswood-Palo Alto 115 kV circuits are converted to 230 kV operation. The City will engineer, procure, construct, own, and maintain its project facility. CITY OF PALO ALTO RAVENSWOOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31, 2006 The feasibility study and cost estimates will include the interconnection of the two lines at Ravenswood 230 kV bus and the conversion of the two lines from Ravenswood Substation to the takeoff structures at Colorado Substation. ¯Prior to the start of the feasibility assessment, the City will provide their proposed Colorado Substation layout for the construction period and for when construction is complete. ¯The cost estimates will include removal of any PG&E facilities such as the Palo Alto Switching Station. ¯The FS will provide complete 115 kV and 230 kV protection requirements including the line circuit breakers at Colorado Substation. The FS will focus on the feasibility, cost estimates and work scope for facilities required to convert PG&E’s Palo Alto - Ravenswood 115 kV Lines to 230 kV operations. The study will include the interconnection of the converted lines to PG&E’s 230 kV bus at Ravenswood. The study will also include cost estimates for at the removal of PG&E’s Palo Alto Switching Station. The study will not include any facilities requiring conversion or modification at the City’s Colorado Substation. The following tasks will be included in the study: 7.1 Feasibility Assessment The Feasibility Assessment would include the following: []Determine feasibility of interconnecting two additional 230 kV Lines at Ravenswood Substation. []Feasibility of installing agreed upon transmission arrangement to Colorado Substation during conversion. []Reviewof Land Rights. []Assessment of Right of Way (ROW), including feasibility of widening ROW for 230 kV operation []Area preliminary report on the biology to assess land acquisition and construction hurdles. ¯Transmission Line report on conversion using same alignment including likely tower replacement. ¯Assessment of clearance issues including issues with the proposed transmission arrangement during the conversion. ¯Drive and/or Fly the lines to assess constructability. CITY OF PALO ALTORAVENSWOOD - PALO ALTO 115 KV LINE CONVERSION TO 230 KV FACILITIES STUDY PLAN MAY 31, 2006 Determination of permitting requirements, including EIR/Regulatory requirements. 7.2 Substation Facilities Cost Estimates The Substation Estimates would include the following: ¯Determine preliminary protection requirements. ¯Develop costs for interconnection of two new 230 kV lines at Ravenswood Substation. ¯Develop costs for removal of PG&E’s Palo Alto Switching Station. 7.3 Transmission Line Facilities Estimates The Transmission Line Evaluation would include the following: ¯Cost estimate to modify or replace towers for 230 kV operation. ¯Cost estimate to reconductor lines for 230 kV operation. ¯Cost estimate to prepare and file a Certificate of Public Necessity and Convenience (CPCN). Cost estimate to obtain additional Right of Way. Cost estimate to provide transmission arrangement to Colorado Substation during the period of construction as agreed by the City while the Ravenswood - Palo Alto Lines are being converted to 230 kV. 7.4 Construction Schedule The construction schedule would include the following: ¯Schedule to remove Palo Alto Switching Station. ¯Schedule to convert the Ravenswood - Palo Alto 115 kV lines to 230 kV. ¯Estimated date of operation for the 230 kV interconnection. The deliverables shall include the following: ¯An initial FS Report detailing findings of the Feasibility Assessment as defined in Section 7.1 and budget status. ¯A final FS Report detailing findings of the Study as defined in Sections 7.1 through 7.4. 7