HomeMy WebLinkAboutStaff Report 202-06City of Palo Alto
City Manager’s Repor
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: PLANNING AND
COMMUNITY ENVIRONMENT
DATE:APRIL 24, 2006 CMR: 202:06
SUBJECT: COLLEGE TERRACE TRIAL TRAFFIC CALMING PROJECT
RECOMMENDATION
This is an information report; no Council action is required.
BACKGROUND
In November 2004, the City Council directed staff to implement a trial of the College Terrace
Traffic Calming Plan. The plan includes five traffic circles in the interior of the neighborhood,
on Cambridge Street and on College Avenue, and a total of six speed tables on the perimeter
streets, California Avenue and Stanford Avenue. (See Exhibit A). The project is scheduled to be
implemented this summer for a one year trial.
Staff has completed the bid documents and is prepared to issue the request for bids by the end of
April and to award the construction contract in late May. Construction is scheduled to begin in
June and be completed by August.
Staff has reviewed and discussed the construction schedule for the trial traffic calming project
with Public Works and Utilities staff to identify other projects scheduled in the College Terrace
neighborhood over the next 3 years and to determine any conflicts or conditions that would need
to be addressed in the scheduling of or bid documents for the traffic calming project. Staff
believes that this project can proceed as scheduled.
DISCUSSION
The Utilities Department has scheduled a major gas main replacement project in the College
Terrace neighborhood in summer 2007. This project will occur on the segments of Yale Street,
College Avenue, and Stanford Avenue where all of the traffic circles and one of the six speed
tables will be located. At the conclusion of the gas main project, the Public Works Department
plans to overlay all the streets in the College Terrace neighborhood. This work will occur
beginning in 2008, depending upon the duration of the gas main project, and take several years to
complete.
Utilities staff will not begin the detailed design of the project until this fall, but the method of
construction is to be directional boring rather than open trench, which will minimize the impact
on the roadway or surface features such as the traffic circles. The traffic circles are typically 23
feet in diameter and are constructed of a 2-foot wide concrete ring which is doweled into the
CMR:202:06 Page 1 of 3
street below with reinforcing bars. Staff believes the presence of the traffic circles will not
restrict or impede the design work for the Utilities project. Even if Utilities needed to locate a
bore pit in the concrete sections of the traffic circles, the work could proceed and the section of
the traffic circle could be reconstructed at minimal cost.
Temporary traffic circles will need to be removed prior to resurfacing the College Terrace
streets. If the trial is successful and permanent traffic circles are recommended, they will be
installed after the street resurfacing work is completed.
The design issues for these projects can be addressed in the plans and specifications for the
College Terrace traffic calming project and through coordination with Utilities staff as the design
of the gas main project proceeds. Given that the College Terrace neighborhood has awaited the
installation of the traffic calming features since 2004, and that the Utilities and Public Works
projects could extend through summer 2008, staff plans to move ahead with implementation of
the College Terrace trial traffic calming project this summer as scheduled.
RESOURCE IMPACT
Funding of $150,000 is provided in CIP Project PL-05003
calming proj ect.
for the College Terrace traffic
Public Works Department staff has consistently raised the concern that the existing roadways
and traffic control devices cannot be maintained to the level that is needed with existing contract
and staff resources. The cumulative impact of the addition of new roadway features adds to this
deficit in maintenance resources. Additional operational costs of maintaining these structures
would need to be included in the annual operating budget. Public Works will be able to quantify
this impact once the permanent traffic calming project is determined. This information will be
included in the evaluation report to the City Council at the conclusion of the trial phase.
POLICY IMPLICATION
This project is consistent with City Council policy.
ATTACHMENTS
A. College Terrace Traffic Calming Plan Map
COURTESY COPIES
Traffic Advisory Committee of the College Terrace Residents’ Association
Jean Snider, Stanford Management Company
CMR:202:06 Page 2 of 3
PREPARED BY:
Acting Chief Transportation Official
APPROVED BY:
.,STEVE F~’VI S LIE
Director of Planning and Community Environment
CITY MANAGER APPROVAL: .
EM~[LY HARRISON
Assistant City Manager
CMR:202:06 Page 3 of 3
ATTACHMENT A
(Physical Traffic Calming Devices)
~x ~E .-
II
Driveway
Legend
Traffic Signal
Slop Sign
TrafficCirde
Speed Table
Cornell
Princeton
Escondido
Driveway
Obedin
I
Escondido
School
Bowdoin
Harvard
LL Hanover
Dartmouth ~I~L
I
i C°’umb’a1,3L 1
Odveway
Driveway
i~Hanover
Driveway
Plan also includes signal timing modification at CambridgelECR and pavement legend improvements
Source: Kimley-Hom and Associales, Inc.