HomeMy WebLinkAboutStaff Report 122-08City of Palo Alto
City Manager’s Report
5
TO:
FROM:
DATE:
SUBJECT:
HONORABLE CITY COUNCIL
CITY MANAGER DEPARTMENT: UTILITIES
JANUARY 22, 2008 CMR: 122:08
UTILITIES ADVISORY COMMISSION RECOMMENDATION TO
UTILIZE THE ELECTRICSUPPLY RATESTABILIZATION RESERVE
TO COVER INCREASEDSUPPLY COST IN FISCAL YEAR 2007-08
INSTEAD OF A MID-YEAR RATE INCREASE
RECOMMENDATION
Staff and the Utilities Advisory Conwnission (UAC) recommend utilizing the Electric Supply
Rate Stabilization Reserve (E-SRSR) to cover increased supply cost in Fiscal Year (FY) 2007-08
instead of a mid-year rate increase. The incremental amount to be withdrawaa from the E-SRSR
will be determined as part of the mid-year Budget Amendment Ordinance process in March
2008.
BACKGROUND
As part of the FY 2007-08 budget process, staff developed a 5-year Financial Plan (Plan) in
December 2006 which showed costs steadily increasing over the next five years as a result of
higher commodity, renewable energy, transmission, regulatory, and distribution costs. Further,
retail revenue was projected to be insufficient to cover costs and the Plan included a series of rate
increases designed to recover costs.
In accordance with the Plan, on June 18, 2007, Council approved a five-percent electric retail
rate increase, or $4.4 million in additional revenue, effective July 1, 2007, to cover distribution-
related expenses; and an in-concept 10-percent electric retail rate increase, ($9.2 million in
additional revenue), for FY 2008-09 [CMR 202:07] to cover distribution-and supply-related
expenses. The need for a rate increase in FY 2007-08 to cover supply-related expenses was not
warranted as the projected end of FY 2007-08 E-SRSR was expected to be above the minimum
g~ideline level.
CMR: 122:08 Page 1 of 4
DISCUSSION
Supply Proi ections and Cost
Projections developed during the FY 2007-08 budget process (prior to updated hydrologic
conditions being available) assumed hydroelectric supply from the Western Base Resource and
the Calaveras hydroelectric project would be average for FY 2007-08 and FY 2008-09. The
adopted budget for FY 2007-08 calls for a drawdown of the E-SRSR of $11 million in FY 2007-
08 and $8.4 million in FY 2008-09.
Given the dry conditions actually experienced, generation from both hydroelectric resources is
now projected to be below average and a total of ")""_~ ~ Gigawatt-hour of hydroelectric supply will
need to be replaced. The cost increase over budget associated with the dry conditions is
estimated at $7.5 million in FY 2007-08 and $8 million h~ FY 2008-09.
Alternatives to Address Increased Costs
Staff evaluated and presented to the UAC several alternatives to address the impact of the
increased drought-related costs on the electric fund as discussed briefly below.
FY 2007-08 Mid-Year rate increase option
Implementing a 10 percent rate increase, effective February 1, 2008, would provide
additional revenues of $3.6 million for FY 2007-08. This rate increase, along with the
approved-in-concept 10 percent electric retail rate increase for FY 2008-09, effective July 1,
2008, would put the E-SRSR above the minimum guidelines level by the end of FY 2008-09.
2.Drawdown of the E-SRSR and higher future rate increases
The expected supply cost increases would increase the E-SRSR drawdown necessary to
cover operating expenses to $19 million and $16.6 million in FY 2007-08 and FY 2008-09,
respectively. Given both the City’s policy to set rates to recover costs and the reserve
guidelines, staff would need to consider a rate increase ~eater than the 10 percent approved-
in-concept rate increase for FY 2008-09.
Drawdown of Calaveras Reserve
The Calaveras Reserve was established in 1996 as part of the City’s effort to prepare for
deregulation of the electric industry and the possibility of losing customers to retail
competition. The Calaveras Reserve was set to cover the difference between the cost of City-
owned assets and long-term contracts, and the market value of those assets, otherwise known
as stranded cost. In 1999, the Calaveras Reserve was fully funded at $71 million and Council
approved a schedule of Calaveras Reserve drawdowns to be used to offset power costs for
future ratepayers through FY 2031-32 [CMR: 222:99].
Staff’s preliminary assessment shows that approximately $10 to $20 million could be drawn
from the Calaveras Reserve without adversely impacting the competitiveness of the electric
utility. Such a drawdown could be a single transfer to the E-SRSR or could be a transfer
over multiple years. Staff is not recormnending drawing down the Calaveras Reserve for FY
2007-08. However, this alternative may be considered in the furore, if the E-SRSR is
insufficient to cover costs.Any change to the drawdown schedule will need Council
approval.
CMR: 122:08 Page 2 of 4
To address the increased supply costs, staff considered implementing a 10 percent mid-year rate
increase effective February 1, 2008. However, with the concurrence of the UAC, staff
recommends foregoing a mid-year rate increase and instead utilizing the E-SRSR based on the
following:
1.The ending E-SRSR for FY 2007-08 with the increased supply cost is estimated at
approximately $42 million, sufficiently above the minimum reserve guideline level of $29.3
million.
2.Hydrologic uncertainty for FY 2007-08 is reduced as a dry hydro scenario is included in the
expected cost and the E-SRSR is sufficient to cover the remaining cost uncertainties in FY
2007-08.
3.Use of the E-SRSR to fund the increased cost associated with reduced hydroelectric
generation is consistent with the purpose for which the reserve is intended.
COMMITTEE REVIEW AN~ RECOMMENDATIONS
At its December 5, 2007 meeting, the UAC voted 4-1 to "recommend to Counci! to utilize funds
from the Electric Supply Rate Stabilization Reserve, instead of a mid-year rate increase, to offset
electric supply cost increases in FY 2007-08." Commissioner Melton voted against the motion
arguing that a mid-year rate increase would send the proper signal to ratepayers that there are
costs associated with dry hydrologic conditions and that a delay will result in a larger rate
increase in July 2008. Commissioner Dawes countered that a mid-year increase is not warranted
given the reserve level forecasts for June 2008.
Further, the UAC advised staff that in addition to considering the use of the Calaveras Reserve to
offset future rate increases, staff should evaluate use of the Calaveras Reserve to 1) invest in
other capital projects; and 2) pay off some of the Calaveras and!or California Oregon
Transmission Project debt.
RESOURCE IMPACT
Utilization of the E-SRSR to fund the increased cost in FY 2007-08 will require approval from
Council in the form of a budget amendment ordinance. The exact amount to be drawn from
reserves will be determined through the mid-year budget process in March 2008.
POLICY IMPLICATIONS
Use of the E-SRSR to fund changes in cost associated with hydroelectric generation supply is
consistent with the E-SRSR guidelines (CMR:467:03) and supports the Utilities Strategic Plan
objective of providing competitive rates to customers. This recommendation does not represent
a change in current City policies.
ENWIRONMENTAL REVIEW
The utilization of the E-SRSR to fund charges in cost associated with hydroelectric generationsupply does not meet the definition of a project pursuant to Section 21065 of the California
Environmental Quality Act (CEQA), thus, environmental review is not required.
CMR: 122:08 Page 3 of 4
ATTACHMENTS
A. UAC Minutes from November 7, 2007 meeting
B. UAC Minutes from December 5, 2007 meeting
PREPARED BY:MONICA PADILLA
Resource Planner
DEPARTMENT APPROVAL:
VALE ONG
Director of Utihtles
CITY MANAGER APPROVAL:
EMILY HARRISON
Assistant City Manager
CMR: 122:08 Page 4 of 4
FINAL
ATTACHMENT A
UTILITIES ADVISORY COMMISSION
MINUTES OF NOVEMBER 7, 2007
CALL TO ORDER
Chairman Rosenbaum called to order at 7:05 P.M. the scheduled meeting of the Utilities Advisory
Commission.
Present: Commissioners George Bechtel, Dexter Dawes, Marilyn Keller, John Melton, Dick Rosenbaum
ORAL COMMUNICATIONS
NONE
APPROVAL OF THE MINUTES
The minutes from the September 5, 2007, were unanimously approved.
AGENDA REVIEW
The order of the agenda items was changed so that Item 3 - Utilities Water, Gas and Electric Efficiency
Programs and Services for FY 2007-09 would be discussed before Item 2 - Quarterly Risk Management
Report.
REPORT FROM COMMISSION MEETINGS/EVENTS
Commissioner Bechtel attended the Northern California Power Agency (NCPA) Annual Meeting in Monterey,
California, and commented that the focus was on compliance with Assembly Bill 32, the "Global Warming
Solutions Act of 2006," and how to reduce greenhouse gas emission. He noted that the costs to comply are
potentially very high and that there is much uncertainty with regards to the rules and regulations that will be put
into place at both the state and federal levels.
UTILITIES DIRECTOR REPORT
Valerie Fong, Utilities Director, noted the passage of two ballot measures:
Emergency Water Supply Project, and the vote on the Transient Occupancy Tax.
the advisory vote on the
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 1 of 8
Fong then introduced two new employees: Joyce Kinnear, the new Manager of Utility Marketing Services, who
was most recently with Silicon Valley Power, and Marites Ward, the new Administrative Assistant, who was
most recently with Alameda. Fong also acknowledged Bruce Lesch for his excellent work as Interim Utilities
Services Manager, and Jennie Castelino and Melody Vega as Interim Administrative Assistants.
Resource Adequacy Capacity: Fong gave an update on of the California Independent-System
Operator’s (CAISO) - Market Redesign and Technology Update tariff and the Local Resource
Adequacy Capacity requirement which staff estimates to be roughly $4 million per year. Fong noted
that during the evaluation process of local generation, the long-term costs of capacity-only products
were incorporated. Fong also noted that the PLUG-IN local cogeneration incentive program
incorporated elements of long-term capacity costs into the buy-back rates, and that these costs were
further included in the evaluation of renewable energy projects. Fong noted that staff is in the process
of purchasing the capacity-only product from other NCPA members, especially Alameda (14 MW at
$40/kW-year), and has registered the emergency generators with the CAISO as local capacity. Fong
recognized the efforts of Electric Systems Supervisor Norm Brown, his team in Operations, and Shiva
Swaminathan in getting the generators CAISO-registered.
Fong gave a quick update on Assembly Bill 1470, the "Solar Water Heating and Efficiency Act of
2007," which requires that all retail gas utilities in the state, including municipal gas utilities like Palo
Alto, implement and finance a solar water heating system incentive program, with the goal of installing
200,000 solar water heating systems by 2017 at a program cost of $250 million. Fong remarked that
implementation of a gas utility funded solar heating program was already included in the Ten-Year
Energy Efficiency Portfolio Plan and identified Palo Alto’s proportionate share of the statewide goal to
be approximately 500 systems.
Fong gave a quick update on the issuance of $1.5 million in "Clean Renewable Energy Bonds"
(CREBs), which had been allocated by the IRS to Palo Alto to finance its portion of the cost of the
solar photovoltaic demonstration project with an effective ten-year zero interest loan. Fong recognized
the efforts of Nancy Nagel and Joe Saccio from the Administrative Services Department.
UNFINISHED BUSINESS
NONE
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 2 of 8
NEW BUSINESS
ITEM 1: INFORMATION ITEM:
Utilities Report
Water Report:
Commissioner Keller asked about the nature of the comments on the Draft Program Environmental Impact
Report (PEIR) on San Francisco Public Utilities Commission’s (SFPUC’s) Water System Improvement
Program (WSIP). Jane Ratchye, Assistant Director - Resource Management, responded that although there
is broad support for completing the seismic improvements, the overwhelming comment is to stop any
additional diversions from the Tuolumne River.
Commissioner Melton asked what San Francisco will do. Ratchye explained that San Francisco’s Planning
Commission (Planning Commission) is scheduled to certify the Final PEIR, which will contain the responses to
the comments submitted on the Draft PEIR, in May 2008. Any appeals to the Planning Commission’s actions
will be considered by the San Francisco Board of Supervisors. After the Final PEIR is certified, the SFPUC will
adopt the Water System Improvement Program (WSIP), including level of service goals. Then remaining
planning, design, and construction on the projects can proceed. At this time, we do not know exactly what
projects will be built and how any other arrangements such as agreements with Modesto or Turlock Irrigation
Districts wil! proceed.
Commissioner Bechtel asked how the 70 shutdowns will affect Utilities operations. Ratchye replied that the
shutdowns are designed to not result in any loss of service, however, the system will be losing redundancy,
and, therefore, be vulnerable to unplanned emergencies, during the shutdowns.
Melton asked about the timeline for the City’s Emergency Water Supply and Storage project. Fong stated that
the project is anticipated to be completed in 2012 with construction forecast to take about two years, following
a project design phase estimated to take 18 to 24 months.
Chairman Rosenbaum asked about the status of any agreements with Stanford on the lease for the reservoir
project. Fong said that staff is working on this, but there is nothing to report at this time.
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 3 of 8
Gas Report:
Rosenbaum asked why the gas meter exchanges are below the goals for each month of the fiscal year. Tom
Auzenne, Assistant Director Administrative Services, noted that manpower issues have slowed the ability to
meet the monthly goal, but that staff is working to improve performance in this area.
Electric Report:
Bechtel asked whether staff believes that the transmission cost upgrade will be as expensive as estimated.
Fong acknowledged that high cost and noted the preliminary nature of the estimate. Fong indicated that staff is
continuing to work with PG&E to refine the cost estimate which may or may not reduce with refinement.
Rosenbaum asked why the costs for the NCPA Green Power Poo! (NGPP) were so high. Tom Kabat, Senior
Resource Originator, responded that the cheapest projects are done and that it’s now a seller’s market,
possibly due to the state Renewable Portfolio Standard (RPS) mandate. Rosenbaum remarked that the City
may want to re-evaluate the standard in light of the fact that costs of electric supply are an issue as will be
discussed later.
Commissioner Dawes asked whether the increased costs associated with generation capacity could be
applied to the incentives for local generation, and whether that would provide a greater incentive for projects to
be more likely to happen.
Karl Knapp, Senior Resource Planner, stated that the generation capacity and associated market design costs
are included in the electric buyback rates, and would be adjusted in response to the costs facing the utility.
The potential to recoup some of the fixed costs through a capacity charge that reflects those high costs would
be likely to push some projects into economic feasibility that may not otherwise be economic, which would
reduce the risk associated with the initial capital cost.
Financial Report:
Dawes asked whether the fiber project has repaid the electric fund for the initial start-up funds and whether the
City pays for the fiber it uses. Auzenne replied that loan has not been paid back yet, but it will likely be repaid
in FY 08-09 and that yes, the City does pay for use of fiber at its facilities - about 22% of the fiber revenues
are from the City itself.
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 4 of 8
ITEM 3: INFORMATION ITEM:
Utilities Water, Gas and Electric Efficiency Pro,qrams and Services for FY 2007-09
Staff presented the Utilities Water, Gas and Electric Efficiency Programs and Services informational report for
FY 2007-2009 to the UAC. Auzenne stated that this was a report providing supporting detail to the Council-
approved "Ten Year Energy Efficiency Portfolio Plan." There was no presentation, but staff could be asked
clarifying questions.
Keller asked whether portables at the school district were included in the efficiency programs, if schools were
considered to be commercial or residential customers, how the City was working with the schools to ensure
trees could be watered (paving was cutting off trees from water sources), and whether irrigation programs
were available to City facilities. Auzenne replied that: 1) portables are included in efficiency programs, they
are often inefficient, but staff is working with the school district to ensure new structures are efficient; 2)
schools are "commercial customers" for rebates; 3) CPAU staff works with both the school district and the city
to make buildings as water and energy efficient as possible; and 4) irrigation programs were available to
schools, and CPAU would look into the water accessibility problem for tree locations at schools. Keller also
requested clarification on the definition of "negawatts," which Auzenne explained was another way of having
third parties bid to provide energy and demand savings at customer sites.
Dawes requested definition for "evapotranspiration" controller for watering and why the utilities are working
with the Santa Clara Valley Water District (SCVWD) on these water efficiency programs. Auzenne explained
that an evapotranspiration, or ET or ETO, controller senses ground moisture to prevent overwatering. He also
explained that the SCVWD partners with the Utilities to co-fund water efficiency services as part of their
county-wide services. Ratchye explained that the City gets good value for its money on the water efficiency
programs through the SCVWD, as the district delivers programs and pays half the costs of administering and
delivering the programs, while the City only has to reimburse the district for half the cost of the customer
programs. Dawes remarked that he wanted to make sure that the City was not just paying for the SCVWD to
deliver programs that the utilities would not otherwise deliver. With no further comments, Rosenbaum moved
to the next item on the agenda.
ITEM 2: INFORMATION ITEM:
Quarterly Risk Manaqement Report
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 5 of 8
Energy Risk Manager, Karl Van Orsdol, presented his quarterly risk management report.
Dawes asked if the negative mark-to-market value of the Calaveras project included the subsidy provided from
the Calaveras Reserve. Van Orsdol explained that the mark-to-market of the project did not include that
reserve transfer, but was only the total costs (debt service and variable and fixed O&M charges)less the
market value of the energy produced.
Rosenbaum remarked that he liked the appendix with all the transaction details that has appeared in past
reports. Van Orsdol promised to include the detailed appendix in the report on a twice per year basis.
ITEM 4: ACTION ITEM:
Recommendation to Not Increase Electric Rates until FY 2008-09 in keeping with the Impact of Current
Drought On the Five-Year Electric Supply Cost, Rates and Reserve Projections
Resource Planner, Monica Padilla presented her report on cost increases to the electric supply fund due to the
current drought compared to the budgeted costs for FY 2007-08, conceptual budget for FY 2008-09, and the
5-year Financial Plan developed in January 2007. Since that time, reduced estimates for hydroelectric
supplies have necessitated purchases from the market resulting in costs being over budget by $11 million for
FY 2007-08 and $8.4 million for FY 2008-09. Given the retail rate projections contained in the 5-year Financial
Plan, the ending balance of the Electric Supply Rate Stabilization Reserve (E-SRSR) is expected to be below
minimum guideline levels as of June 30, 2009. If dry conditions continue, the reserve could be exhausted by
June 30, 2009.
Padilla showed that planned rate increases would bring the E-SRSR balance above minimum by
FY 2011-12.
Padilla noted that staff considered alternatives, including:
1. A 10% mid-year rate increase effective February 1, 2008, which would bring revenues more
quickly in line with costs and let reserves climb above minimum levels by FY 2011-12.
2.Re-evaluation of the 5-year Financial Plan and possible recommendation of an increase higher
than the 10% approved-in-concept rate increase effective July 1,2008.
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 6 of 8
Utilization of the Calaveras Reserve, which was established to recover "stranded costs" and
subsidize rates through FY 2031-32 to reduce rate increases.
Implementation of a rate adjustor that could be applied with supply cost increases or decreases to
more quickly reflect the impacts of dry or wet hydro conditions.
Padilla reviewed Staff’s recommendation as follows:
1.No mid-year rate increase for FY 2007-08.
2.Modifications to the 5-year Financial Plan in the FY 08-09 budget and rate setting process.
3.Evaluation/recommendation of funding levels for the Electric reserves, including the Calaveras
("stranded cost") Reserve.
4.Implementation of an automatic rate adjustor mechanism only after the billing system upgrade is
complete.
Padilla noted that staff plans to return to the UAC in December with an assessment of and recommendations
for use of the electric reserves; in February, 2008 with an updated 5-year Financial Plan; and in March, 2008
with a rate increase proposal as part of the FY 08-09 budget process.
Melton noted that the information staff presented made a compelling case for a mid-year rate increase, and
that without a mid-year increase, the increase that may be needed in July 2008 could be very large. Fong
responded that staff believes it has an obligation to look at all resources and reserves closely before
recommending an electric rate increase outside of the normal budget and rate setting process.
Dawes agreed with Melton on the need for an interim increase noting that a decision to forego an increase
now makes him very nervous. Dawes cautioned that without a mid-year increase, revenues could get too far
behind costs resulting in the need for a series of dramatic increases as happened with gas costs and rates in
2001. Dawes noted that the high cost of renewable resources also increases cost pressures.
Bechtel commented that he generally agreed with Melton and Dawes and questioned whether the 5-year
Financial Plan needs to be updated in order to make a decision on rates in the short-term due to cost
increases caused by the drought. Bechtel indicated his understanding of the need for more analysis, but
advised it was still possible to implement an increase effective in February 2008 if analysis is brought to the
UAC in December. He noted that a 5-year forecast is not needed to make a decision on rates now.
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 7 of 8
Dawes commented on the need to re-look at the Calaveras debt service and the need for the money in the
Calaveras Reserve.
Melton noted that the Calaveras Reserve can’t be changed before FY 2008-09, but also noted that
implementing a rate increase in February 2008 doesn’t mean an automatic rate increase in July 2008. Prior to
the budget process, Melton posed that there would be more information on the status of hydro conditions, and
a wet hydro year could mean no additional rate increase in July, 2008.
Rosenbaum supported staff’s recommendation. He noted that requesting a mid-year rate increase indicates
an emergency, which is not the case.
Melton moved that the UAC recommend that Council approve a 10% electric rate increase effective February
1,2008. The motion died for lack of a second.
Bechtel asked why this report was prepared as an action item instead of an informational report. Fong noted
that staff wanted a mechanism to show the Council the information and to give it a heads-up that the July 2008
may be higher than projected last year.
The UAC chose to take no action and make no recommendation to Council. Staff will return to the UAC with a
new recommendation and analysis of the reserves at the December 5, 2007, meeting.
Rosenbaum requested that staff compare Palo Alto’s rates to Roseville’s and Silicon Valley Power’s and not
just PG&E’s. He expressed concern over costs rising at a fast rate due to Palo Alto’s reliance on Western
hydro power. Rosenbaum also noted that a rate adjustor mechanism can be quite simple if adjusted annually
based on hydro year conditions, and that a drought reserve could be maintained at a certain level with the
adjustor raised or lowered to maintain a balance in the reserve.
Meeting adjourned at 8:55 P.M.
Respectfully submitted,
Marites Ward
City of Palo Alto Utilities
Utilities Advisory Commission Minutes from: Approved on: December 5, 2007 Page 8 of 8
FINAL
ATTACHMENT B
UTILITIES ADVISORY COMMISSION
MINUTES OF DECEMBER 5, 2007
CALL TO ORDER
Chairman Rosenbaum called to order at 7:00 P.M. the scheduled meeting of the Utilities Advisory
Commission.
Present: Commissioners George Bechtel, Dexter Dawes, Marilyn Keller, John Melton, Dick Rosenbaum, and
Council Liaison, Beecham
ORAL COMMUNICATIONS
NONE
APPROVAL OF THE MINUTES
The minutes from the November 7, 2007, were unanimously approved.
AGENDA REVIEW
Chairman Rosenbaum requested that item 1 - Climate Protection Plan be moved to after the other four
agenda items to accommodate Commissioner Bechtel who had to leave early and wanted to be there for item
4, an action item.
REPORT FROM COMMISSION MEETINGS/EVENTS
There were no reports.
UTILITIES DIRECTOR REPORT
Jane Ratchye, Assistant Director for Resource Management, conveyed the regrets of Valerie Fong, Director of
Utilities, who couldn’t be here tonight. Ratchye provided the UD report summarized below:
Council adopted the Climate Protection Plan at its December 3 meeting, which will be presented as Item 1.
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 1 of 9
Palo Alto received notification on December 3 that the City successfully completed the California Climate
Action Registry’s greenhouse gas inventory certification process for 2006, earning the registry’s "Climate
Action Leader" status for the second year in a row. The emissions inventory is for all municipal government
operations, and is available to the general public on the Registry’s website.
At a December 4 ceremony yesterday, the Alma substation was electrically disconnected. The equipment will
be decommissioned in the coming weeks and the property will be vacated before the end of the year.
The City is in the process of negotiating two contracts to meet City’s share of the Local Capacity for calendar
year 2008,
The market for renewables has moved to prices that exceed the $70/MWh price cap in the original NCPA
Green Power Pool (NGPP) agreement, To improve chances of success and customized participation, the
NCPA Commission on November 29 approved a resolution to amend the NGPP agreement with four changes:
1) Removal of the $70/MWh price cap; 2) Project by project opt out provisions so members can opt out of
projects in which they are not interested; 3) Clean up of accounting language to make opt out provisions clear;
and 4) Clarification of language related to development activities where NCPA may develop the renewables.
For the amendment to be effective, all NGPP participants must have it approved by their Councils by January
31, 2008. Palo Alto’s Council will consider a resolution approving execution of the amended NGPP agreement
on December 18. The Palo Alto resolution has an average new renewable price cap provision of $118/MWh
set to keep the retail price impact of meeting the additional 13% of our portfolio needs within the one half
cent/kWh Council-approved rate impact cap for attaining 33% renewables by 2015.
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 2 of 9
NCPA’s Annual Strategic Planning Meeting will be held in Sacramento on January 23-25. CMUA’s Capitol
Day will be held on Monday, January 14 in Sacramento. This meeting starts with a legislative briefing in the
morning followed by visits to legislators and their staff in the afternoon. Utilities encourages one or two UAC
Commissioners to attend these meetings.
Staff changes in the Resource Management Division include: 1) Ipek Connolly is the new Senior Resource
Planner responsible for rate making - taking over these duties after Lucie Hirmina’s retirement; 2) Nicolas
Procos is a new Senior. Resource Planner joining Palo Alto last week. Nico will be focusing on water issues
and also will be involved in other gas and electric resource planning activities; and 3) Debbie Lloyd was
promoted to a Senior Resource Planner in October and will continue in her role as the point person on
legislative and regulatory issues for the department.
UNFINISHED BUSINESS
NONE
NEW BUSINESS
Jane Ratchye explained that items 2, 3, and 4 would be taken together and discussed in a combined
presentation.
ITEM 2: INFORMATION ITEM: Update of Utility Reserves: Refer to Item 4.
ITEM 3: INFORMATION ITEM: Strateqies to Mana.qe the Calaveras Reserve: Refer to Item 4.
ITEM 4: ACTION ITEM: Recommendation to Utilize Funds from the Electric Supply Rate Stabilization to
Reserve, Instead of a Mid-Year Rate Increase, to Offset Electric Supply Cost Increases in FY 2007-08
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 3 of 9
Shiva Swaminathan, Senior Resource Planner, made a combined presentation to cover agenda Items 2, 3 and
4. He presented the balances for the Utilities reserves funds as of June 30, 2007. Anticipated changes to the
reserves in FY 07-08 include budgeted draw downs and mid-year changes which will leave reserves within
Council-approved reserve guidelines by June 30, 2008.
The Calaveras Reserve was established by Council in 1996 to prepare the City for competitive retail electric
markets by pre-collecting above market costs of the Calaveras hydroelectric project, the California Oregon
Transmission Project (COTP), and the Seattle City Light (SOL) contract. Forward market costs at the time
were between 2¢ and 4C/kWh over 30 years and the Calaveras reserve was fully funded in 1999 at $71
million. At that time, Council approved a drawdown schedule allowing the reserve to be fully depleted in 2032
when the Calaveras debt is due to be paid-off. Over the next 15 years, the transfers from the Calaveras
Reserve are $5-6 million/year, which effectively reduces retail rates by 0.5C/kWh, or by 5%.
Staff conducted a preliminary assessment of stranded costs with updated electric forward prices over the next
25 years of between 7¢ and 13C/kWh. The estimated stranded cost at these prices is about $24 million, of
which $3 million is for the Calaveras project, $20 million is for COTP, and $1 million is for the SCL contract.
The stranded cost estimate is highly sensitive to market prices. For example, if market prices fall by 25%, then
stranded cost would double - to $48 million. If market prices fall by 25% and long-term hydroelectric
production falls by 10% (perhaps due to effects of climate change), then the stranded cost estimate is about
$57 million.
Options to manage the Calaveras Reserve include: 1) do nothing - maintain the 1999 Council approved
schedule to deplete reserves by 2032; 2) deplete Reserves More Quickly than Scheduled - either through a
one-time transfer to electric SRSR (e.g. $20M) or withdrawal over a period of time (e.g. $5M/year over 4
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 4 of 9
years); and 3) borrow from (and repay to) Calaveras Reserve to cover extreme events (e.g. multi-year drought,
natural disaster) so that the reserve acts as a secondary buffer to the E-SRSR.
Drawing down ahead of the schedule from the Calaveras Reserve has pros and cons. The pros include that it:
provides the ability to have more gradual rate increases, returns money to customers earlier- customers who
contributed towards the fund in 1996-99, and so that customers enjoy a lower retail rate in the short-term. The
cons of early drawdown include that it: reduces competitiveness of electric rate in the long run, eliminates a
secondary reserves buffer to cover higher cost in the event of a prolonged drought, reduces financial flexibility
in the future (e.g. potential to fund major capital expenditure, natural disaster), and has the potential to
adversely affect the City’s credit rating.
Based on the information provided, staff recommends that the E-SRSR be used to cover increased supply
costs in FY 07-08 due.to the drought instead of a mid-year rate increase. Staff will return to the UAC to
discuss the 5-year financial forecast in February and to request approval of the FY 08-09 retail rates in March.
Those discussions will include recommendations for the use of the Calaveras Reserve.
Following the presentation, Commissioner Dawes suggested an evaluation of utilizing the surplus Calaveras
reserves towards other Utilities capital projects such as local generation. He characterized the Calaveras
Reserve as a capital reserve tied to bond repayment as opposed to an operating reserve. Staff also
mentioned that the City’s financial advisors had recommended that the City look at the feasibility of paying
down Calaveras debt with the surplus funds. Commissioner Melton, supported Commissioner Dawes’ ideas
and expressed reluctance to utilize the Calaveras reserve to pay operating expenses under the present
circumstances.
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 5 of 9
Council Member Beecham asked how reserves are really managed - for example, if a reserve is established
for drought and the drought occurs, does the money get used, or does the reserve just get replenished
immediately. If the latter is the case, then what’s the use of the reserve? Beecham also commented that he
generally would like to see reserves returned to ratepayers and, more specifically, to those ratepayers who
paid into the reserve.
Rosenbaum suggested that staff evaluate the stranded cost reserve at an appropriate price level and
mentioned 5C/kWh as an example, midway between prices in 1999 and today. He also suggested that staff
explore the possibility of using the surplus reserves to set up a new reserve dedicated to cover hydro
production risks. Rosenbaum also suggested that a separate reserve could be established specifically for
drought. Staff noted that the E-SRSR is maintained for uncertainties including drought.
Bechtel requested staff look at two additional options when developing a recommendation for alternate uses of
the Calaveras Reserve: 1) investment in other capital projects; and 2) pay off some of the Calaveras or COTP
debt.
Dawes does not support subsidizing the current operating expenses with the Calaveras Reserve. He noted
that price increases projected are moderate and we should "tough it out" and re-evaluate its use next year
when money is still in the E-SRSR. Melton agreed that it is too early to move Calaveras Reserve funds in to
the E-SRSR.
Dawes moved and Bechtel seconded the motion to "Recommend to Council to utilize funds from the Electric
Supply Rate Stabilization to Reserve, instead of a mid-year rate Increase, to offset electric supply cost
increases in FY 2007-08." Melton opposed the motion arguing that a mid-year rate increase would send the
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 6 of 9
proper signal to ratepayers that there are costs associated with dry hydro conditions. Dawes countered that a
mid-year increase is not warranted given the reserve level forecasts for June 2008.
The Commission voted 4-1 to approve the motion, with Melton in opposition and reiterating that a delay will
result in a larger rate increase in July 2008.
ITEM 1: INFORMATION ITEM:
Climate Protection Plan
Karl Van Orsdol, Energy Risk Manager and Karl Knapp, Senior Resource Planner, presented a summary of
Palo Alto’s Climate Protection Plan, which had been approved by Council on Monday, December 3, 2007. The
presentation by Van Orsdol was essentially the same information presented at the Council study Session on
November 26, and Knapp added several slides to highlight the utilities’ chapter in particular.
Van Orsdol described the community-wide greenhouse gas emissions inventory that was conducted for 2005,
and the rationale for the emissions reduction goals, with the key long-term goal to achieve 15% reductions
from 2005 levels community-wide by mid-2019. Cost-effectiveness of a number of proposed actions were
reviewed, grouped into short-term, medium-term, and longer-term potential. Van Orsdol summarized with a list
of exactly what it was that Council approved.
Knapp highlighted the utilities chapter of the plan, which consists largely of existing programs, but tied together
with the common theme of climate protection. The proposed actions, primarily energy efficiency, renewable
energy, and cogeneration have the potential to reduce carbon dioxide emissions associated with electricity and
natural gas use by approximately 50% from 2005 levels by 2020. Knapp summarized the emissions reduction
potential of each major category and their associated costs per ton of emissions reduced, with an expanded
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 7 of 9
slide illustrating the cost-effectiveness evaluation of photovoltaics (which was corrected the next day to show
that the Utility Rate Perspective should be a $165/ton cost instead of a $35/ton savings). Knapp concluded
with a list of items yet to be evaluated, which may have additional potential for utilities and its customers to
address climate protection.
Keller asked staff to clarify how the implementation of the plan actually happens, including who one calls at
City hall to find out about trees or solar panels. Van Orsdol explained that a key part of the overall plan is to
engage the community, and in particular the school district. Knapp described the importance of having
champions for different initiatives throughout the City, and that some of the tasks will take a while to get going.
Van Orsdol followed up by explaining that the city’s sustainability website will be including a lot of the
information in the plan, and that the longer-term plan is also to replace the four half-time team members with
one full-time dedicated individual to champion the plan, but pointed out that it will still be everyone’s
responsibility to make good on the plan, not just the Environmental Coordinator.
Dawes commented that the municipal hydro energy recovery project sounded promising, and asked for an
explanation of how the $20/ton greenhouse gas adder worked. Knapp responded that the adder is intended for
long-term energy purchases that are not being purchased at a premium for some other reason, such as for
PaloAItoGreen or the renewable portfolio standard. The adder is a placeholder that reflects the financial risk
associated with taking on a long-term potential emissions liability, and will be replaced with the actual costs of
allowance or credits once the state settles on a cap and trade system design. For now, the adder is used to
compare energy purchases from two different sources; if one emits 1000 Ibs of CO2 per MWh and another
emits zero, the low or zero carbon resource would be selected as long as its price is no more than $10/MWh
higher.
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 8 of 9
Beecham added that some of the least expensive opportunities are right now, and that perhaps taking a
longer-term view of reducing total carbon over a long time horizon might work out to be far more cost-effective
to invest in offsets right now rather than waiting for a decade or two when they could be very expensive. Staff
agreed that such an approach is worth evaluating when looking at potential reduction projects and offsets.
Meeting adjourned at 9:20 P.M.
Respectfully submitted,
Marites Ward
City of Palo Alto Utilities
Utilities Advisory Commission Minutes from: Approved on: January 9, 2008 Page 9 of 9