HomeMy WebLinkAboutStaff Report 308-09TO: HONORABLE CITY COUNCIL
FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE: JULY 13, 2009 CMR:308:09
REPORT TYPE: CONSENT
SUBJECT: Approval of a Contract With Granite Rock Company DBA Pavex
Construction Division, in an Amount not to Exceed $1,493,356 for the
2009 Street Maintenance Program Asphalt Overlay Capital
Improvement Project PE-86070
RECOlVIMENDATION
Staff recommends that Council:
1. Approve and authorize the City Manager or his designee to execute the attached contract
with Granite Rock Company DBA Pavex Construction Division (Attachment A) in an
amount not to exceed $1,493,356 for the Street Maintenance Program Asphalt Overlay
Capital Improvement Project PE-86070; and
2. Authorize the City Manager or his designee to negotiate and execute one or more change
orders to the contract with Granite Rock Company DBA Pavex Construction Division,
for related, additional but unforeseen work which may develop during the project, the
total value of which shall not exceed $149,336.
BACKGROUND
The Public Works Engineering Division manages construction contracts for concrete pavement
repair, preventative maintenance, resurfacing and reconstruction of various City streets on an
annual basis. The candidate streets are surveyed biannually by Public Works Engineering staff
and then rated by a computerized pavement management system. The annual budget for these
past contracts averaged approximately $2.1 million and included all phases of the project. Since
2003, the Public Works Engineering Division has implemented multi-phased resurfacing projects
by bidding one phase for concrete repairs and preparation, a second phase for preventative
maintenance and a third phase for asphalt concrete resurfacing. This method of phasing has
proved more cost effective by avoiding the typical 15% markup on concrete work and
preventative maintenance work previously included in asphalt resurfacing contracts because the
work was subcontracted out.
DISCUSSION
Project Description
The project focuses on the placement of asphalt concrete overlays on the older Portland Cement
Concrete (PCC) base streets that have a low Pavement Condition Index (PCI) score. These
CMR:308:09 Page 1 of4
streets are all high priorities on the City's resurfacing backlog and have been coordinated
through monthly project coordination meetings between the Public Works Engineering, Public
Works Operations, and the Utilities Departments. The purpose of these meetings is for each
department to present their anticipated schedules for upcoming projects and make sure the
planned work does not conflict with the schedule of another department. Streets in this contract
include Waverley Street along the Gamble Garden Center, five blocks of the Bryant Street Bike
Boulevard, California A venue from E1 Camino Real to the Caltrain Station, and several streets in
the College Terrace Targeted Work Zone (TWZ). The work to be performed under this contract
will also include Portland Cement concrete base repairs, asphalt milling, placement of interlayer
membranes on PCC cold joints, crack filling, driveway, curb and gutter, and sidewalk repair,
installation of ADA compliant pedestrian ramps, catch basin replacements, raising of manholes
and utility vaults to the new pavement elevations, traffic calming devices, new pavement striping
and inert recycling on 5.4 lane miles of streets. The project work locations are identified on the
project list of streets (Attachment B). Much of the sidewalk, driveway, and concrete base repairs
for these streets have already been completed as part of a separate concrete contract. This work
was separated out to save approximately 15 percent in overhead and administration fees typically
charged by contractors on large resurfacing/overlay contracts. Separating the contracts will also
enable the asphalt contractor to begin milling the existing asphalt concrete immediately upon the
execution ofthis contract.
Certain elements of the comprehensive California Avenue Streetscape Improvement Project are
included in this contract. The paving of California A venue includes the installation of colored
crosswalks, and the restriping of the roadway down from two lanes to one lane in each direction.
This will create a pedestrian and bicycle friendly two-lane road configuration. New trees, tree
grates, benches, trash cans, and bike racks will be installed under a separate CIP PE-07005 later
this year. Public Works held several meetings with the California A venue Area Development
Association (CAADA) while developing the scope of work for these projects and coordinating
the schedule of activities with the Utilities Department for the improvements on California
Avenue.
Extensive coordination was also involved with the portion of this contract located in the College
Terrace neighborhood. The Public Works and Utilities Departments worked together to
accelerate all of the needed utility work to take place before street resurfacing. Upon completion
of this contract, 40% of the College Terrace neighborhood will have been resurfaced. The
remaining 60% will be resurfaced in phases over the next two years. The tentative College
Terrace Target Work Zone (TWZ) Resurfacing Schedule is included with this report as
Attachment D. All three of the add alternate streets recommended in this contract are located in
the College Terrace TWZ. Upon approval by Council on August 3, 2009, the installation of
traffic calming devices in the College Terrace TWZ will be incorporated into this project. Th~ .
original and <trial project traffic circles along College Avenue will be removed while pedestrian
refuge islands and several speed humps will be installed in their place. One additional speed
table will be installed on California Avenue between Dartmouth and Columbia as well. It is
expected that these new traffic calming features will be more effective than the trial project
traffic circles. The traffic calming devices were designed by the Transportation Division and are
funded through College Terrace Traffic Calming Capital Improvement Program (CIP PL-05003).
Page 2
Bid Process
On May 21, 2009, a notice inviting formal bids for the 2009 Street Maintenance Program
Asphalt Overlay Project was posted at City Hall, and was sent to 11 builder's exchanges and 12
contractors I subcontractors. The bidding period was 19 calendar days. Bids were received from
six qualified contractors on June 9, 2009 as listed on the attached Bid Summary (Attachment C).
ummaryo 1 S fB'd P rocess
Bid NamelNumber Asphalt Overlay Proiect I IFB #131632
Proposed Length of Project 130 calendar days
Number of Bids Mailed to 12
Contractors
Number of Bids Mailed to Builder's 11
Exchanges
Total Days to Respond to Bid 19
Pre-Bid Meeting? No
Number of Bids Received: 6
Bid Price Range (Base bid plus four From a low of$I,660,886 to a high of$I,917,413.
alternates
Bids ranged from a high of $1,917,413 to a low bid of $1,660,886 and ranged from 3 % over to
11% under the engineer's estimate. The engineer's estimate of$1,861,512 was decreased based
on the low bids received for similar work last year and is reflective of the continued deflated
construction market. The number of contractors bidding the project and lower construction bids
are also indicative of the current construction market in this economic downturn. Staff has
reviewed all bids submitted and recommends that the base bid and the first three add alternates
totaling $1,493,356 submitted by Granite Rock Company DBA Pavex Construction Division be
accepted and that Granite Rock Company DBA Pavex Construction Division be declared the
lowest responsible bidder. The change order amount of $149,336, which equals 10 percent of
the total contract, is requested for related, additional but unforeseen work which may develop
during the project. Current funding does not allow for the recommendation to award the fourth.
add alternate. The fourth add alternate was to repave Cornell Street in College Terrace. This
work will be completed as part the 2010 Street Maintenance Project.
The lowest responsible bidder, Granite Rock Company DBA Pavex Construction Division, has
worked with the City on previous paving projects and staff found no significant complaints.
Staff also checked with the Contractor's State License Board and found that the contractor has an
active license on file.
RESOURCE IMPACT
Funds for this project are included in the FY 2009-10 CIP Street Maintenance project, PE-86070.
Funds for the modification of traffic calming measures on College Avenue are included in the
CIP project PL-05003 College Terrace Traffic Calming.
This project is not funded in any part by Federal stimulus funds, The stimulus funds are reserved
for projects on collector or arterial streets only and the funds allocated to the City of Palo Alto
will be used on San Antonio Avenue, Lytton Avenue, and Alma Street later this year. The State
CMR:308:09 Page 3 of 4
of California is currently proposing withholding payment of Gas Tax funds to local governments
for street maintenance. This proposal would put future street maintenance projects in jeopardy by
significantly reducing the annual budget for street maintenance during the term of this non-
payment
ENVIRONMENTAL REVIEW
This project is categorically exempt from the California Environmental Quality Act (CEQA)
under Section 15301c of the CEQA Guidelines as repair, maintenance andlor minor alteration of
the existing facilities-and no further environmental review is necessary.
ATTACHMENTS
Attachment A: Contract
Attachment B: List of Streets
Attachment C: Bid Summary
Attachment D: College Terrace Targeted Work Zone Resurfacing Schedule
PREPARED BY:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
MATT BRID'lNINGS
Engineer
GLENN S. ROBERTS
Director of Public Works
Page 4