HomeMy WebLinkAboutStaff Report 257-09TO: HONORABLE CITY COUNCIL
FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE: JUNE 1,2009
REPORT TYPE: CONSENT
CMR:257:09
SUBJECT: Approval of a Change Order to the Contract with AJF Builders, Inc. to
Add $89,447 for a Total Contract Amount of $623,698 for Fire Stations
5 and 8 Improvements -Capital Improvement Program Project PF -
01004
RECOMMENDATION
Staff recommends that Council:
I. Approve and authorize the City Manager or designee to execute the attached contract
change order with AJF Builders, Inc., to add $89,447 to the contrlIDt for It total contract
amount of $623,698 for Fire Station 5 and 8 Improvements -Capital Improvement
Program ProjectPF -01004.
2. Authorize the City Manager or his designee to negotiate and execute one or more change
orders to the contract with AJF Builders, Inc., in an additional amount not to exceed
$14,000 for related, additional but unforeseen work that may develop during the project.
DISCUSSION
Background
Council approved a contract with AJF Builders, Inc. on December 8, 2008 (CMR:455:08). The
work performed under this contract provided for the renovation and seiamic upgrade of Fire
Stations 5 and 8.
proj ect Description
During the course of construction, extensive unforeseen damage was discovered at both fire
stations. At Fire Station 5, following the tear-off of the roof, additional dry rot was found
beyond that determined in the design phase. Due to these unforeseen conditions, additional
repairs were required including beam replacement and repair of rafter tails, eave boards, and glue
laminated beams. Within the interior of the structure, there were various concealed conditions
that were addressed during construction including plumbing and electrical in walls, and conduit
in the slab.
During Fire Station 8 demolition, the contractor found animal damage and infestation, and dry
rot and mold in the walls. Removal of gypsum board in selected areas, kitchen cabinets, and
restroom fixtures was required to determine the cause of the mold problem. Limited mold
remediation was completed by an environmental contractor, and further investigation was
completed to determine the probable cause. The architect determined that the non-conventional
construction method originally used was probable cause for the conditions found. Various
improvements to mitigate the potential for future problems Were recommended. These include
the installation of exterior paper and siding; replacement of windows and trim; removal of
viscuine, insulation and gypsum board; and installation of new insulation and gypsum board.
The Qriginal contract contingency funds in the amount of $69,700 were used to address the issues
identified at Station 5, and to address limited demolition and cleanup at Station 8. As Station
No. 8 is not staffed until July 1, priority was placed on completion of Station 5 to allow
occupancy as soon as possible. Additional funds in the amount of $89,447 are now requested for
the completion of work at Station 5 and the wark recommended above for Station 8 to allow
occupancy before the summer fire season begins. Additional contingency funds of $14,000 are
requested for further unforeseen conditions such as dry rot or mold.
RESOURCE IMPACT
Funds for this work are available in Capital Improvement Program Project PF-OI004 -Fire
Station Improvements.
POLICY IMPLICATIONS
This recommendation does not represent any change to existing City policies.
ENViRONMENTAL REVIEW
This project is categorically exempt from California Environmental Quality Act under Section
15301 as an alteration to an existing facility and no further environmental review is necessary.
ATTACHMENTS
Attachment A: Change Order
PREPARED BY:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL
KAREN SMITH
Manager, Facilities Maintetlance & Projects
I:£j,~ ..
GLENN S. ROBERTS
Director of Public Works
ATTACHMENT A
-------------~ .... -.-.-------------~ ...
Project Title: Fire Station 5 &8lmp rovements -Construction Project Number: NIA Phase --_ ... _-._---...
Contract Number: C1l9129264 Data: 06101109 ....... _--,---
Contractor: AJF Builders Change Order CPACOt#24 Number: , Inc.
--
Description of Change Order
Background Information:
Change Order Justification:
During the course of construction, ext
-,.-----,,-_._.......---
ensive unforeseen damage was discovered at
both Fire Stations 5 and B. Additional repairs were required at Stalion 5 including
lails, eave boards, and glue laminated beams.
e were various concealed conditions thai were
g plumbing and electrical in walis, and conduit !
beam replacement and repair of rafter
Within the intenor of the structure, ther
addressed during construction includin
in the slab.
, During Fire Station 8 demolition, the co ntractor found animal damage and infestation, i
Removal of gypsum board in selected areas, : : and dry rot and mold in the walls.
kitchen cabinets, and restroom fixture S was required to determine the cause of the ,
mined that the non-conventional construction
e cause for the conditions found. Various
al for future problems were recommended.
lOr paper and siding; replacement of windows
on and gypsum board; and Installation of new
: mold problem. The architect deter
, method originally used was probabl
improvements to mitigate the potenti
These include the installation of exter"
and trim; removal of viscuine, insulati
.i.nsulation and 9l'l1sum board ._-----
Increase contract with AJF Builders, In C. for the repair of concealed and unforeseen
conditions in the amount of $89,447.
roeacrlpj.ion of Work to be Station B exterior siding, windows, inte rior insulalion and drywall, restroom
. Performed: renovation, and replacement of kitchen cabinets. Station 5 replacement of apparatus
, bay light fixtures, plumbing and electric
~-----~-----
: Incorporates Field Order Work is described in contractor's pendi
al connec:tlons for extractor/d.-!.ry..;,e..;,r. ____ -I
ng change order requests #3,4,5,11, 12,24R3,
Number(s): . 25 and 26,
,--~---.. ._-----..
Cost Time
Change order will: This Change order will:
0 Not change cost a Not change time
!
X Increase contract and contingency by $89,447. X Increase time by 48 days
a Decrease cost by $ 0 Decrease time by days !
The date of completion liS of this change order is -._--...
Note GIL account number (s) here (see GIL #'s below): July 3, 2009.
-,-
ApPEllolX 8-CONTRACT CHANGE OI!llER PAGE 1 OF3
Contract Change Order
City of Palo Alto
Department: Public Works Facilities Management
Contract Number: C09129624
Basis for change in
Cl Unit price(s)
X lump sum
1:1 Cost plus %
1:1 Other:
-~~" .. ~--
Contract Change Order Form -continued
... __ ..... ... __ .....
The undersigned Contractor approves this Change Order as to the ebunges, if any, in the contract price specified for each Line Item
and as to the extension oftime allowed, if any, for completion oftha entire work on account of each Line Item, and agrees to furnish
all labor and materials and perform all work necessary to complete any additiooal work specified therein, for the cOIk,ideration stated
therein. It is understood that the lime and cosl adj1lstments set forth in this Change Order include full compensation fur any impacts
or &Iays asSQciated with-the Line Items addressed in this Change Order.
... --.. ,-
Accepted for Contractor: Accepted for City of Palo Alto: .•....... ~
By: Anthony Franceschini By: Karen Smith .. ~-~ .... -
Title: President, AJF Builders, Inc. Title: Manager, Facilities Maintenance and Projects
. -~
Date: Date: 611/2009
~ .. ---.-
Summary of Amounts Payable Under Contract (For Intemel Purposes Only)
Amount of Original Contract $ 464,551,00
Net affect of all Change Orders $ lSI},147.00
Revised Contract Total: $ 623,6911.00
Compare to: I
Original Contract Amount: $ 464,551.00
Add: Contract and $ 173,147.00 Contingency:
Total Authorized Funding: $ 637,6911.00
Change orders shall not be initiated tor Council-approved contracts If the revised contrect total
exceeds the totel authorized funding amount.
PAGE20F3 APl'ENlllJ( S...comRACT CIlAHGE OIIDE.
Document Preparation
By: Karen Smith
Title: Manager, Facilities Maintenance and Projects
Date : 5/\9/09
City Approval -Required on all change ordere
By: Karen Smith
Title: Manager, Facilities Maintenance and Projects
Date : 06/01109
City Approval-Department Head signature required when any Individual
Change Order exceeds $10,000.
By: Glenn Roberts
TItle: Director ofPnblic Works
Date: 06/01109
i\Pl'ENDIX B-CONTRACT CHANGE ORDER