HomeMy WebLinkAboutStaff Report 244-09TO: 9." HONORABLE CITY COUNCIL-B~
FROM: CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE: MAY 18,2009 CMR:244:09
REPORT TYPE: CONSENT
SUBJECT: Adoption of a Resolution to Establish a Pledge of Revenue as a
Financial Assurance Mechanism for Post Closure Maintenance of the
Palo Alto Landfill and Approval of a Pledge of Revenue Agreement
with the California Integrated Waste Management Board for Post
Closure Maintenance of the Palo Alto Landfdl
RECOMMENDATION
Staff recommends that Council:
1. Adopt a resolution (Attachment A) establishing a pledge of revenue assurance for 30
years of post closure maintenance costs in an amount of $5.1 million (plus annual
inflation adjustments) that would provide for performing maintenance, monitoring and
reporting for the Palo Alto Landfill after the landfill is closed in accordance with the
California Integrated Waste Management Board (CIWMB) requirements; and
2. Authorize the City Manager or designee to approve the pledge of revenue agreement
(Attachment B) made and entered into by and between the City of Palo Alto and the
California Integrated Waste Management Board (CIWMB) that will pledge future
revenues to be received from refuse rate payers through utility billings to pay for the
costs to perform these post closure maintenance activities for 30 years after the landfill
closes.
BACKGROUND
In 1990, the City responded to new State requirements by approving a Resolution (No. 6919)
that formally established a landfill closure/post closure maintenance reserve within the Refuse
Enterprise Fund in accordance with State regulations. The purpose of establishing the reserve
was to demonstrate to the State that the City could provide a source of funding that would
ultimately fund the landfill's closure construction and 30 years of post closure maintenance
activities.
In 1993, the City approved Resolution No. 7192 that repealed Resolution No. 6919 eliminating
the closure/post closure maintenance reserve and established a liability to recognize the costs to
perform these activities. All of the funds in the reserve remained in the Refuse Fund in order to
fully fund the liability (CMR:325:93). The change was made in response to the Governmental
Accounting Standards Board requirement that all costs associated with the operation of a landfill
CMR:244:09 Page 1 of3
must be recognized as a liability and that the total costs for closure/post closure maintenance
activities must be fully captured by the time the landfill reaches its full capacity. The CIWMB
accepted the City's liability assurance method as an equivalent Enterprise Fund method as long
as it provided for funding that equals or exceeds the CIWMB funding requirements.
Since 1993, the landfill has been filled to approximately 98 percent of its permitted capacity and
in every year, funds have been added to the closure/post closure maintenance liability account to
reflect the percentage of the landfill filled along with an inflation adjustment factor provided by
the State.
Recently, staff has contracted with a consultant who has prepared a final closure/post closure
maintenance plan and cost estimate in response to Title 27 regulations requiring a final plan be
prepared and submitted no later than two (2) years prior to closure. The post closure
maintenance cost estimate for 30 years increased from $3.4 million to $5.1 million reflecting
updated regulatory requirements mostly related to landfill gas collection, monitoring and
reporting.
DISCUSSION
Title 27 of the California Code of Regulations, contains the regulations that specify standards for
financial mechanisms of solid waste landfills. A financial assurance mechanism is an
arrangement whereby a party facing a potential or certain liability pledges or deposits funds so
that: 1) all anticipated costs will be covered; 2) all funds will be secure over time; and 3) all
funds will be available when needed. Public Resources Code Section 43501 mandates that
landfill operators establish "a trust fund or equivalent financial arrangement" as evidence of
financial ability to pay for the costs of closure/post closure maintenance for their respective
facilities. There are several mechanisms allowed for government entities to provide financial
assurance. The City has chosen an enterprise fund for both the landfill's closure/post closure
maintenance and corrective action. For an enterprise fund to provide proper financial protection,
the fund (or a specific portion of the fund) must be dedicated to the closure/post closure
maintenance and/or corrective action of a specific landfill, and the amount deposited must be tied
to the cost estimates for that facility. To provide security over time and ensure funds are readily
available, on each anniversary of the establishment of the fund, the balance must be increased by
at least the amount determined by Section 22225(a) of the Regulations. In response to State
requirements, staff recommends changing the landfill's post closure maintenance financial
assurance mechanism from the Enterprise Fund account to a Pledge of (future) Revenues
mechanism for the following reasons:
1) The primary advantage to changing to a Pledge of Revenue mechanism is that the City
will not need to have all of the funds available in the Refuse Fund to cover the long-term
liability of post closure maintenance prior to the landfill closure. In the current
Enterprise Fund account mechanism, the City is required to annually certify to the State
that all of the funds are available for the 30 year post closure maintenance costs.
Changing to a Pledge of Revenue Mechanism will allow the City to collect post closure
maintenance costs over a 30 year time period and will have a lesser impact on the rate
payers. Post closure maintenance costs are expected to begin after certification of the
closure in early 2013; and
CMR:244:09 Page 2 of3
, 2) The process of reimbursement for post closure maintenance activities would be
simplified. Currently with the Enterprise Fund mechanism, City staff is required to
request approval from the State to withdraw fimds from the Refuse Fund for closure and
post closure maintenance activities. With the Pledge of Revenue Assurance, the City
would not need State approval.
Once the attached resolution has been adopted, the City will need to enter into an agreement with
the CIWMB to assure that adequate fimds are available to carry out the post closure maintenance
of the Palo Alto Landfill.
RESOUR<;E IMPACT
The current "Enterprise Fund" financial assurance mechanism requires that the :full amount of
the post closure maintenance liability be available ($5.1 million). Changing the post closure
maintenance financial assurance mechanism to a Pledge of Revenue mechanism will allow the
Refuse fimd time to produce revenue to obtain the funds necessary to cover this long term
liability.
POLICY IMPLICATIONS
The recommendation does not represent changes to existing City policies.
ENVIRONMENTAL REVIEW
Adoption of this resolution and entering into an agreement with the State is not a Project under
Section 2lO65 of the California Environmental Quality Act (CEQA) because the activity will not
cause either a direct physical change or a reasonably foreseeable indirect physical change in the
environment.
ATTACHMENTS
Attachment A: Resolution
Attachment B: Agreement
PREPARED BY:
DEPARTMENT HEAD:
CITY MANAGER APPROVAL:
CMR:244:09
RON~
Manager, Environmental Control Programs
/jL 1. KL}-
GLENN S. ROBERTS
Director of Public Works
Page 3 of3
ATTACHMENT A
NOT YET APPROVED
Resolution No. ---Resolution of the Council of the City of Palo Alto to Establish
a Pledge of Revenue as a Financial Assurance Mechanism for
Post Closure Maintenance of the Palo Alto Landfill
WHEREAS, the City of Palo Alto owns and operates the Palo Alto Landfill, a solid waste
landfill, in conformance with the findings, conditions, prohibitions and requirements contained in
Solid Waste Facilities Permit No. 43-AM-000I issued by, the County of Santa Clara,
Department of Environmental Health serving as Local Enforcement Agency for the California
Integrated Waste Management Board (CIWMB); and
WHEREAS, Public Resources Code sections 43500 through 43610.1 and Title 27,
California Code of Regulations (Regulations), Division 2, Subdivision 1, Chapter 6, require
operators of solid waste landfills to demonstrate the availability of financial resources to conduct
closure, post closure maintenance, and corrective action activities; and
WHEREAS, on June 7, 1993 the City Council adopted Resolution No. 7192 which in
part established the Landfill Closure and Postclosure Maintenance Liability account within the
Refuse Enterprise Fund to demonstrate the City's availability of financial resources through an
Enterprise Fund; and
WHEREAS, sections 22228 and 22245 of the Regulations specify a Pledge of Revenue
as an acceptable mechanism to demonstrate financial responsibility for financing post closure
maintenance costs of a solid waste landfill; and
WHEREAS, the City now desires to change this mechanism to a Pledge of Revenue.
NOW, THEREFORE, the Council of the City of Palo Alto does RESOLVE as follows:
1. The portion of the Landfill Closure and Postclosure Maintenance Reserve Liability
account currently set aside for post-closure maintenance is hereby released and
Resolution 6919 is hereby repealed to the extent it requires a separate liability
account for Postclosure maintenance.
2. In place of the Postclosure Maintenance Reserve Liability account, the City of Palo
Alto shall establish a Pledge of Revenue to demonstrate financial responsibility for
post closure maintenance of the Palo Alto Landfill in accordance with sections 22228
and 22245 of the Regulations. The pledged revenue shall consist of refuse utility
billings designated as net sales in the Refuse Budget.
3. Disbursement of funds for post closure maintenance shall be in accordance with the
final closure plan, as approved by the CIWMB.
4. In the event the CIWMB determines that the City of Palo Alto has failed, or is failing,
to perform post closure maintenance as required by law, the CIWMB may direct the
090226 jb 0130439
NOT YET APPROVED
Director of Administrative Services (Treasurer) to pay to the Director of Public
Works (City Engineer) from the pledged revenues sufficient funds to ensure post
closure maintenance, who then shall be obligated to use such funds for post closure
maintenance in accordance with the directives of the CIWMB.
5. The Director of Public Works is directed to produce an annual report for transmittal
to the CIWMB, containing, as appropriate, a revised post closure maintenance cost
estimate, prepared as specified by section 21840 of the Regulations concerning the
Palo Alto landfill.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSENT:
ABSTENTIONS:
ATTEST:
City Clerk
APPROVED AS TO FORM:
Senior Assistant City Attorney
090427 jb 0130439
2
APPROVED:
Mayor
City Manager
Director of Administrative
Services
ATTACHMENT B
PLEDGE OF REVENUE AGREEMENT FOR
POSTCLOSURE MAINTENANCE OF THE
PALO ALTO LANDFILL
This AGREEMENT is entered into this day 2009, by and between
the CITY OF PALO ALTO, a California chartered municipal corporation ("CITY"), and the
California Integrated Waste Management Board ("CIWMB") to establish a Pledge of Revenue to
assure that adequate funds are available to carry out the Postclosure Maintenance of the Palo Alto
Landfill.
RECITALS:
A. WHEREAS, the City of Palo Alto owns and operates the Palo Alto Landfill, a
solid waste landfill, in conformance with the findings, conditions, prohibitions and requirements
contained in Solid Waste Facilities Permit No. 43-AM-000I issued by, the County of Santa
Clara, Department of Environmental Health serving as Local Enforcement Agency for the
California Integrated Waste Management Board (CIWMB); and
B. WHEREAS, Public Resources Code sections 43500 through 43610.1 and Title
27, California Code of Regulations (Regulations), Division 2, Subdivision 1, Chapter 6, require
operators of solid waste landfills to demonstrate the availability of fmancial resources to conduct
closure, postclosure maintenance, and corrective action activities; and
C. WHEREAS, on June 7, 1993 the City Council adopted Resolution No. 7192
which in part established the Landfill Closure and Postc1osure Maintenance Enterprise Fund
Account within the Refuse Enterprise Fund to demonstrate the City's availability of fmancial
resources through an Enterprise Fund; and
D. WHEREAS, sections 22228 and 22245 of the Regulations specify a Pledge of
Revenue as an acceptable mechanism to demonstrate financial responsibility for fmancing
postclosure maintenance costs of a solid waste landfill; and
E. WHEREAS, the City of Palo Alto intends to pledge revenues from refuse rate
payer fees paid monthly by residents and business within Palo Alto deposited into the Palo Alto
Refuse Enterprise Fund; and
F. WHEREAS, the City of Palo Alto has determined that projected net revenues
from the refuse rate payer fees during the thirty (30) year period of postclosure maintenance
shall, during each year of this period, be greater than the yearly monitoring and postclosure
maintenance costs contained in the most recent Cost Estimate for the Palo Alto Landfill, which
has been submitted to the CIWMB in accordance with section 21840 of the Regulations.
NOW THEREFORE, the City of Palo Alto and the CIWMB do agree as follows:
SECTION 1. The City of Palo Alto hereby establishes a pledge of revenue to
demonstrate financial responsibility for postclosure maintenance costs of the Palo Alto Landfill
in accordance with sections 22228 and 22245 of the Regulations.
1 0312009
SECTION 2. The City of Palo Alto agrees to pledge net revenues from refuse rate payer
fees as described herein.
SECTION 3. The amount of the pledged revenue shall be equal to $168,655 per year for
the 30 year period of postclosure maintenance, representing the most recent monitoring and
postclosure maintenance cost estimate for the Palo Alto Landfill. It is agreed that the amount of
this pledge may increase or decrease to match any adjustment to the identified cost estimate,
which is mutually agreed to by the City of Palo Alto and the CIWMB.
SECTION 4. If the City of Palo Alto ceases at any time to retain control of its ability to
allocate the pledged revenue as identified herein to pay postclosure maintenance costs, the City
of Palo Alto shall notify the CIWMB and the local enforcement agency and shall obtain alternate
coverage within sixty (60) days after the control of funds lapses, pursuant to section 22245 of the
Regulations.
SECTION 5. In the event that CIWMB, RWQCB or LEA staff determines that the City
of Palo Alto has failed, or is failing, to perform postclosure maintenance as required by law, the
CIWMB, RWQCB and/or LEA staff shall confer with the City of Palo Alto and attempt to
resolve the alleged violation. If no agreement is reached, the matter shall be presented to the
CIWMB which shall give reasonable notice, hold a public hearing, and consider the testimony
and documentation submitted by the CIWMB and/or LEA staff, the City of Palo Alto, and any
interested parties, prior to making a determination in the matter. In the event the CIWMB then
determines that the City of Palo Alto has failed, or is failing, to perform postclosure maintenance
as required by law, the CIWMB may direct the Director of Administrative Services to pay the
Public Works Director from the pledged revenues sufficient funds to ensure postclosure
maintenance, who then shall be obligated to use such funds for postclosure maintenance in
accordance with the directives of the CIWMB and RWQCB.
II
II
II
II
II
II
II
II
II
II
II
2 0312009
SECTION 6. This Agreement shall become effective immediately, and is made and
entered into by and between the City of Palo Alto and the California Integrated Waste
Management Board (CIWMB).
STATE OF CALIFORNIA
California Integrated
Waste Management Board
By: __________ _
Authorized Officer of the CIWMB
APPROVED AS TO FORM
By: __________ _
Authorized Counsel of the CIWMB
3
CITY OF PALO ALTO
By: __________ _
City Manager
ATTEST:
By: __________ _
City Clerk
APPROVED AS TO FORM:
By: __________ _
Sr. Assistant City Attorney
0312009