HomeMy WebLinkAbout1999-04-19 City Council (19)City of Palo Alto
City Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT:ADMINISTRATIVE
SERVICES
DATE:APRIL 19, 1999 CMR:199:99
SUBJECT:APPROVAL OF AN ORDINANCE TO AMEND THE MUNICIPAL FEE
SCHEDULE TO INCREASE FEES BY $369,517 TO COVER COSTS
ASSOCIATED WITH THE DEVELOPMENT CENTER, INCLUDING
FEES CONTAINED IN TABLE 1A OF THE 1997 UNIFORM
BUILDING CODE
RECOMMENDATION
Staff recommends that the City Council
Approve revisions to the Municipal Fee Schedule (Attachment C) to implement the
changes detailed below. (The impact of these changes to individuals using the
Development Center is shown on Attachment A.)
Adopt the fee levels includeffas Fee Table 1A in the 1997 Uniform Building
Code (UBC), which is projected to increase Development Center Revenues by
12 percent, or $228,552 in 1999-00. (UBC fee increases were last
implemented in January 1996.)
Implement a change in the minimum permit fee from $25 to $40, which is
projected to increase revenues by $22,000 in 1999-00.
Co Implement an increase for new residential construction electrical, plumbing,
and mechanical permits, from a per-unit charge to a fiat rate of five cents per
square foot for each. This is projected to increase revenues by $44,000 in
1999-00.
CMR:199:99 Page 1 of 3
Go
Implement an increase for new commercial construction electrical, plumbing,
and mechanical permits from a per-unit charge to a fiat rate of four cents per
square foot for each. In addition, implement an increase for tenant
improvement reconstruction electrical and mechanical permits, and for
laboratory, medical and restaurant plumbing permits from a per-unit charge to
a flat rate of four cents per square foot for bach. This is projected to increase
revenues by $55,000 in 1999-00.
Increase the fees for excavating, grading, and fill permits. This is projected to
increase revenues by $5,000 in 1999-00.
Increase the Certificate of Compliance fee from $335 to $600. This is
projected to increase revenues by $6,625 in 1999-00.
Increase encroachment permit fees. This is projected to increase revenue by
$8,340 in 1999-00.
Approve the Budget Amendment Ordinance (Attachment B) to increase revenue.by
$369,517.
DISCUSSION
In CMR: 175:99, staff recommended fee increases associated with the Development Center,
Which are estimated to raise $294,552 in revenues in 1999-00, covering 82 percent of the
ongoing costs associated with the creation of the Development Center. In addition, staff
identified other fee increases, which are estimated to raise an additional $74,965 in revenue
in 1999-00. In response, the Finance Committee recommended that the City Council
implement all of the Development Center fee increases proposed in CMR: 175:99, to raise
a total of $369,517 in 1999-00, which would fully cover ongoing costs associated with the
creation of the Development Center. This report implements the Finance Committee
direction. (CMR: 175:99, without attachments, is included as Attachment D.)
RESOURCE IMPACT
The implementation of the proposed revisions to the Municipal Fee Schedule would result
in annual revenue increases to the City of $369,517.
POLICY IMPLICATIONS
The revenue from these fee changes, if implemented, would be consistent with Council
direction with regards to cost recovery for development-related services.
CMR:199:99 Page 2 of 3
Implement an increase for new commercial construction electrical, plumbing,
and mechanical permits from a per-unit charge to a flat rate of four cents per
square foot for each. In addition, implement an increase for tenant
improvement reconstruction electrical and mechanical permits, and for
laboratory, medical and restaurant plumbing permits from a per-unit charge to
a flat rate of four cents per square foot for each. This is projected to increase
revenues by $55,000 in 1999-00.
Increase the fees for excavating, grading, and fill permits. This is projected to
increase revenues by $5,000 in 1999-00.
Increase the Certificate of Compliance fee from $335 to $600. This is
projected to increase revenues by $6,625 in 1999-00.
Increase encroachment permit fees. This is projected to increase revenue by
$8,340 in 1999-00.
Approve the Budget Amendment Ordinance (Attachment B) to increase revenue by
$369,517.
DISCUSSION
In CMR: 175:99, staffrecommended fee increases associated with the Development Center,
Which are estimated to raise $294,552 in revenues in 1999-00, covering 82 percent of the
ongoing costs associated with the creation of the Development Center. In addition, staff
identified other fee increases, which are estimated to raise an additional $74,965 in revenue
in 1999-00. In response, the Finance Committee recommended that the City Council
implement all of the Development Center fee increases proposed in CMR: 175:99, to raise
a total of $369,517 in 1999-00, which would fully cover ongoing costs associated with the
creation of the Development Center. This report implements the Finance Committee
direction. (CMR: 175:99, without attachments, is included as Attachment D.)
RESOURCE IMPACT
The implementation of the proposed revisions to the Municipal Fee Schedule would result
in annual revenue increases to the City of $369,517.
POLICY IMPLICATIONS
The revenue from these fee changes, if implemented, would be consistent with Council
direction with regards to cost recovery for development-related services.
CMR:199:99 Page 2 of 3
TIMELINE
Upon approval of these recommendations by the City Council, the fee adjustments will take
effect after a 60-day period, on July 1, 1999.
ENVIRONMENTAL REVIEW
This is not a project for the purposes of the California Environmental Quality Act Review.
ATTACHMENTS
Attachment A:
Attachment B:
Attachment C:
Attachment D:
Attachment E:
Attachment F:
The Effect of Increasing the UBC and Selected Fees on Users
Ordinance to Amend the Municipal Fee Schedule
Proposed Revisions to the Municipal Fee Schedule
CMR: 175:99 (without attachments)
Cost Recovery at the Development Center
Budget Amendment Ordinances Impacting General Fund Reserves
Approved to Date in 1998-99
PREPARED BY: Shannon Gaffne¥, Senior Financial Analyst
DEPARTMENT HEAD APPROVAL:
Director, Administrative Services
CITY MANAGER APPROVAL:
cc."
Manager
Susan Frank, Palo Alto Chamber of Commerce
Carl Guardino, Silicon Valley Manufacturing Group
Randy Okamura, Pacific Bell
Hal Mickelson, Hewlett-Packard
John Northway, Stoecker & Northway, Architects
Kathleen Gwynn, Senior Coordinating Council
Tony Carrasco, Carrasco & Associates
Katherine Strehl, Lockheed Martin
Mark Johnson, Varian Associates
Brad Lopacinski, Varian Associate
CMR:199:99 Page 3 of 3
ATTACHMENT B
ORDINANCE NO.
ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO TO
AMEND THE 1998-99 MUNICIPAL FEE SCHEDULE FOR SERVICES
PROVIDED AT THE DEVELOPMENT CENTER
WHEREAS, pursuant to the provisions of Section 12 of Article
III of the Charter of the City of Palo Alto, the Council on June
22, 1998 did adopt a budget for fiscal year 1998-99; and
WHEREAS, the City Council has directed staff to implement fee
increases for services offered at the Development Center; and
WHEREAS, the Municipal Fee Schedule needs to be amended to
implement these changes; and
WHEREAS, City Council authorization is needed to amend the
1998-99 Municipal Fee Schedule as hereinafter set forth.
NOW, THEREFORE, the Council of the City of Palo Alto does
ORDAIN as follows:
SECTION I. The Municipal Fee Schedule is hereby amended to
reflect the changes shown in Attachment C, which is attached hereto
and incorporated herein by reference.
SECTION 2. In accordance with Section 66016 of the California
Government Code, this ordinance was considered by the Council at a
noticed public hearing, and at least I0 days prior to the hearing,
data indicating the amount of the cost, or estimated cost, required
to provide the services for which these fees were proposed, and the
revenue sources anticipated to provide the services, were made
available to the public.
SECTION 3.
reserves.
This transaction will have no impact on 1998-99
SECTION 4. As specified in Section 2.28.080(h) of the Palo
Alto Municipal Code, a majority vote of the City Council is required
to adopt this ordinance.
SECTION 5. The Council of the City of Palo Alto hereby finds
that this is not a project under the California Environmental
Quality Act and, therefore, no environmental impact assessment is
necessary.
SECTION 6. As provided in Section 2.04.350 of the Palo Alto
Municipal Code, this ordinance shall become effective upon adoption;
ATTACHMENT B
provided, that the fees herein adopted, shall be effective July i,
1999.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
ATTEST:APPROVED:
City Clerk Mayor
APPROVED AS TO FORM:City Manager
Senior Asst. City Attorney Director of
Services
Administrative
o
o o
0
i
ATTACHMENT D
City of Palo Alto
City Manager’s Report
TO:
ATTENTION:
HONORABLE CITY COUNCIL
FINANCE COMMITTEE
FROM:
DATE:
CITY MANAGER
MARCH 16, 1999
DEPARTMENT:ADMINISTRATIVE
SERVICES
CMR:175:99
SUBJECT:AMENDMENT TO THE MUNICIPAL FEE SCHEDULE TO
INCREASE FEES BY $294,552 TO COVER COSTS
ASSOCIATED WITH THE DEVELOPMENT CENTER,
INCLUDING IMPLEMENTING FEE TABLE 1A OF THE 1997
UNIFORM BUILDING CODE AND APPROVAL OF A BUDGET
AMENDMENT ORDINANCE
REPORT IN BRIEF
In CMR: 135:99, and in response to earlier Council direction, staffproposed implementing
fee changes to increase revenue associated with the Development Center by $294,552. At
that time, the City Council directed staffto return with information as to how the full amount
of the ongoing costs associated with the Development Center could be recovered (an
additional $63,408). This report responds to that direction. It contains proposed revisions
to the Municipal Fee Schedule to increase the revenues associated with the Development
Center by $294,552 and identifies additional fee changes which could be implemented to
generate the additional revenues needed to fully cover the ongoing costs of the Development
Center.
CMR:175:99 Page 1 of 5
RECOMMENDATION:
Staff recommends that the City Council
Approve revisions to the Municipal Fee Schedule to implement the changes detailed
below. (The impact of these changes to individuals using the Development Center is
shown on Attachment A.)
°
mo
Bo
Implement the Fee Table 1A in the 1997 Uniform Building Code (UBC),
which is projected to increase Development Center revenues by 12 percent or
$228,552 in 1999-00. (UBC fee increases were last implemented in January
1996.)
Implement a change in the minimum permit fee from $25.00 to $40.00, Which
is projected to increase revenues by $22,000 in 1999-00.
Co Implement an increase for new residential construction for electrical,
plumbing, and mechanical permits, from a per-unit charge to a flat rate of five
cents per square foot for each. This is projected to increase revenues by
$44,000 in 1999-00.
Approve the Bridget Amendment Ordinance (Attachment B), which amends the
Municipal Fee Schedule to increase revenue by $294,552. The proposed changes to
the Municipal Fee Schedule are shown on Attachment C.
Provide staff with feedback regarding any additional fee changes, as detailed in
Attachment D, the Committee would like to be forwarded to the Council for action.
BACKGROUND
In CMR: 135:99, Council approved several fee increases which would increase Development
Center revenues by $294,552, covering 82 percent of the ongoing Development Center costs.
Council directed staff to return with revisions to the Municipal Fee Schedule with the 1998-
99 Midyear Report to implement these fee increases. At that time, staff proposed
undertaking an update of the 1990 User Fee Study in 1999-00, specifically for the fees that
will be charged at the Development Center, prior to making the additional fee increase.s
needed to fully cover the ongoing costs of the Development Center. In addition, staff
recommended revisiting the issue of cost recovery levels citywide, returning to Council with
revised cost recovery proposals, which would include the appropriate level at which cost
recovery should be sought (by major activity, functional area, department, or citywide), and
an improved methodology for calculating cost recovery for all fees charged by the General
Fund. The Council directed staffto return with the 1998-99 Midyear Report, instead of in
1999-00, with a plan as to how additional revenue of $63,408 could be generated to fully
cover the ongoing costs of the Development Center.
CMR:175:99 Page 2 of 5
DISCUSSION
This report includes the revisions to the Municipal Fee Schedule which are necessary to
increase fees by $294,552. In addition, as directed by the City Council, staffhas identified
ways to raise additional revenues associated with the Development Center, which are
discussed below. The total estimated additional revenue projected to be raised by the
changes discussed below would be $74,965 in 1999-00, which is slightly more than the
shortfall of $63,408. The fee changes themselves are shown in an amended Municipal Fee
Schedule, Attachment D.
Change the charge for new commercial construction for electrical, plumbing and
mechanical permits from a per-unit charge to a flat rate of four cents per square foot
for each. In addition, change the charge for tenant improvement reconstruction for
electrical and mechanical permits, and for laboratory, medical, and restaurant
plumbing permits from a per-unit charge to a flat rate of four cents per square foot for
each. These changes are projected to increase revenue by $55,000 in 1999-00.
This approach mirrors the change being recommended for new residential
construction. The per square foot charge is less because commercial projects tend to
be much larger in terms of square footage, and thus each project would be expected
to raise more revenue than residential projects.
Increase the fees for excavating, grading and fill permits as shown on Attachment D.
This is projected to increase revenue by $5,000 in 1999-00.
Based upon a preliminary survey of the fees other communities charge for excavation,
grading, and fill permits, the City ofPalo Alto’s fees are considerably lower. This
change would make Palo Alto’s fees moreconsistent with those of other
communities.
°
o
Increase the Certificate of Compliance fee from $335 to $600. This is projected to
increase revenue by $6,625 in 1999-00.
Based upon a preliminary survey of the fees charged by other communities for
certificates of compliance, Palo Alto’s fee is on the low end of the scale. This
adjustment would place Palo Alto closer to the middle, and would allow staffto more
closely cover the costs of such certificates.
Adjust encroachment permit fees as shown on Attachment D. This is projected to
increase revenue by $8,340 in 1999-00.
CMR:175:99 Page 3 of 5
Based upon a preliminary survey of the fees charged by other communities, Palo
Alto’s fees for encroachment permits are generally consistent with those charged in
other communities. The increases shown on Attachment D are therefore not dramatic.
ALTERNATIVES TO STAFF RECOMMENDATION
As an alternative to increasing the fees above immediately, Council could consider delaying
these increases. By deferring further fee changes, staff would be able to hire a consultant to
more completely analyze the current levels of cost recovery at the Center, examine how Palo
Alto development fees compare to those in other communities, and analyze the allocation of
citywide overhead to the Development Center. As can be seen on Attachment E, staff is
confident that none of the proposals will put the Development Center in the position of
recovering more than the cost of services provided. However, conducting a study woufiJ
allow staff to spend more time ensuring that the City’s Development Center fees remain
competitive. Funding is already available to hire a consultant to do this analysis associated
with the Development Center, and staff could return to Council next winter with further
recommendations regarding cost recovery. Initial estimates indicate that the cost of the study
would be under $25,000.
RESOURCE IMPACT
The implementation of the proposed revisions to the Municipal Fee Schedule would result
in annual revenue increases to the City of $294,552, covering 82 percent of the ongoing
Development Center costs.
POLICY IMPLICATIONS
The revenue from these fee changes, if implemented, would be consistent with the current
Council direction with regards to cost recovery.
TIMELINE
Upon approval of these recommendations by the City Council, the fee adjustments will take
effect after a 60-day period, on July 1, 1999, to coincide with the implementation of the
California Model Codes, as required by State law.
ENVIRONMENTAL REVIEW
This is not a project for the purposes of California Environmental Quality Act Review.
CMR:175:99 Page 4 of 5
ATTACHMENTS
Attachment A:
Attachment B:
Attachment C:
Attachment D:
Attachment E:
Attachment F:
The Effect of Increasing the UBC and Selected Fees on Users
Budget Amendment Ordinance
Proposed Revisions to the Municipal Fee Schedule
Possible Other Revisions to the Municipal Fee Schedule
Cost Recovery at the Development Center
Budget Amendment Ordinances Impacting General Fund
Approved To Date in 1998-99
Reserves
PREPARED BY: Shannon Gaffney, Senior Financial Analyst
DEPARTMENT HEAD APPROVAL:
CARL YEATS
Director,Services
CITY MANAGER APPROVAL:
Susan Frank, Palo Alto Cham[
Carl Guardino, Silicon Valley Manufacturing Group
Randy Okamura, Pacific Bell
Hal Mickelson, Hewlett-Packard
John Northway, Stoecker & Northway Architects
Kathleen Gwynn, Senior Coordinating Council
Tony Carrasco, Carrasco & Associates
Katherine Strehl, Lockheed Martin
Mark Johnson, Varian Associates
Brad Lopacinski, Varian Associates
CMR:175:99 Page 5 of 5
ATTACHMENT F
Budget Amendment Ordinances Impacting General Fund Reserves Approved To Date in 1998-99
Estimated Beginning Budget Stabilization Reserve (BSR)
Balance
Adopted Budget Addition to BSR
Reduction in Rental Income from Utilities Due to Relocation of
Utilities Engineering and Creation of Capital Improvement Project
19921, Relocation / Consolidation of Level A Storage
Increase in the City’s Annual Rental Payment to the Palo Alto
Unified School District for Lease and Covenant Not to Develop for
an Extended Day Care Center at the New Hoover School Site
Salary and Benefit Increases Retroactive to May 1, 1998 for
Classified Personnel (SEIU) *
Salary and Benefit Increase Retroactive to July 1, 1998 for Police
Personnel
Addition of Five Full-Time Positions and Associated Resources to
the Planning and Community Environment Department
Interim Historic Inventory Consultant
Interim Historic Regulations Administration
Phase 1 - San Francisquito Creek Bank Stabilization and
Revegitation Study
Reclassification of CDBG Position to Senior Planner Position
Acquire Leased Space and Cover Associated Support Costs for a
One-Stop Development Center at 285 Hamilton Avenue
Recruitment Assistance
Formation of Library Advisory Commission
Golf Course Clubhouse and Related Improvements
Salary and Benefit Increases Retroactive to July 1, 1998 for
Management and Confidential Employees
Emergency Rep.airs (Basements, Creek, Arastradero Pres.)
Council Chambers Refurbishing Capital Project Number 19625
Emergency Management Plan Implementation
Automatic Public Toilets
Legal Contract Services
$19,050,591
$1,378,606
($231,700)($231,700)($221,000)
($34,792)($34,792)($36,000)
($260,000)($260,000)($702,000)
($182,200)($182,200)($265,000)
($488,364)$300,000 ($188,364)($410,743)
($437,400)($437,400)
($269,600)($269,600)
($112,500)($112,500)
($7,400)($7,400)
($506,979)($506,979)($370,000)
($60,000)($60,000)
($22,500)($22,500)
$33,430 $33,430 ($14,280)
($334,000)($334,000)($624,900)
($142,895)($142,895)
($238,000)($238,000)
($308,500)$200,000 ($108,500) $294,000
($106,000)($106,000)$140,000
($50,000)($50,000)
BSR Balance After BA 0 ’s S17,169,797
S: ASD~udget\1998-99 Budget\99BAO\BAO99
* The estimated increase for the SEIU agreement in 1999-2000 is the cumulative increase beyond the 1998-99 Adopted Budget.
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT:ADMINISTRATIVE
SERVICES
DATE:APRIL 19, 1999 CMR:199:99
SUBJECT:APPROVAL OF AN ORDINANCE TO AMEND THE MUNICIPAL FEE
SCHEDULE TO INCREASE FEES BY $369,517 TO COVER COSTS
ASSOCIATED WITH THE DEVELOPMENT CENTER, INCLUDING
FEES CONTAINED IN TABLE 1A OF THE 1997 UNIFORM
BUILDING CODE
RECOMMENDATION
Staff recommends that the City Council
Approve revisions to the Municipal Fee Schedule (Attachment C) to implement the
changes detailed below. (The impact of these changes to individuals using the
Development Center is shown on Attachment A.)
A°
Co
Adopt the fee levels included as Fee Table 1A in the 1997 Uniform Building
Code (UBC), which is projected to increase Development Center Revenues by
12 percent, or $228,552 in 1999-00. (UBC fee increases were last
implemented in January 1996.)
Implement a change in the minimum permit fee from $25 to $40, which is
projected to increase revenues by $22,000 in 1999-00.
Implement an increase for new residential construction electrical, plumbing,
and mechanical permits, from a per-unit charge to a fiat rate of five cents per
square foot for each. This is projected to increase revenues by $44,000 in
1999-00.
CMR:199:99 Page 1 of 3