HomeMy WebLinkAbout1999-01-09 City CouncilTO:
FROM:
City of Palo Alto
Manager’s Report
HONORABLE CITY COUNCIL
CITY MANAGER DEPARTMENT: PUBLIC WORKS
DATE:JANUARY 19, 1999 CMR:125:99
SUBJECT:RECOMMENDATION TO INCORPORATE THE HEATING,
VENTING AND AIR-CONDITIONING UNIT FOR THE LUCIE
STERN COMMUNITY CENTER THEATRE INTO THE
INFRASTRUCTURE MANAGEMENT PROGRAM SCHEDULE
REPORT IN, BRIEF
This report recommends that Council incorPorate the Lucie Stem Community Center Theatre
heating, venting and air conditioning (HVAC) system into the Int~astrueture Management
Program (IMP) schedule as a fully integrated project which includes all IMP work at the
Community Theatre. This would mean that the study phase of the project would be initiated
in Fiscal Year (FY) 1999-2000, with estimated project completion in FY 2000-2001. The
alternative, a stand-alone HVAC project, is not recommended since the integrated project
provides construction and design efficiencies and the better ability to identify and deal with
historical, architectural and neighborhood concerns all at one time.
CMR:125:99 Page 1 of 5
.RECOMMEr~IDATION
Staff recommends that Council incorporate the Lucie Stern Community C~nter Theatre
heating, venting and air conditioning (HVAC) system into the Infrastructure Management
Program (IMP) schedule as a fully integrated project which includes all IMP work at the
Community Theatre. This would mean that the study phase of the project would be initiated
in Fiscal Year (FY) 1999-2000, with estimated project completion in FY 2000-2001. The
alternative, a stand-alone HVAC project, is not recommended since the integrated project
provides construction and design efficiencies and the better ability to identify and deal with
historical, architectural and neighborhood concerns all at one time.
BACKGROUND
On April 21, 1998, the infrastructure management trmancing and prioritization plan
(CMR: 191:98) was presented to Council. On June 22, 1998, Council approved the FY 1998-
99 Capital Improvement Program Budge~, which included the Lucie Stern Community
Theatre (Theatre) Renovations, CIP #19910 (Attachment A). The project document
identifies two sources of funding: the General Fund, and a David and Lucille Packard
Foundation grant of $150,000. The following is the scope of work and time line for the
original project as part of FY 1998-99 Capital Improvement Budget:
FY 1998-99 - Reu_pholster seats and replace the stage curtain in the Theatre for the
estimated cost of $133,000. The seats are being reupholstered in this fiscal year, and
the stage curtain replacement will be scheduled to coincide with the HVAC system.
installation.
FY 1999-00 -Design and install an HVAC system, necessary infrastructure, and
Americans with Disabilities Act (ADA) improvements.
On July 20, 1998, Council approved the financing and prioritization methodology for the
IMP (April 21, 1998 CMR:191:98). During the same meeting, Council directed staff to
explore the possibility of expediting the installation of the HVAC system for the Theatre and
return with the information.
DISCUSSION
An initial assessment of the existing ventilation system indicated that the cost of a new,
stand-alone HVAC system would be approximately $500,000. However, there may be
additional unforseen costs due to the historical nature of the building, physical constraints
affecting the installation of the system, architectural design features required to conceal the
compressor for the system, asbestos concerns, assessment of existing systems, and noise
considerations inside the Theatre and within the neighborhood.
The IMP has identified that, within the next ten years, the Theatre will need repair,
replacement, or upgrade of the electrical system, tile, flooring, interior and exterior painting,
and roofing for an estimated cost of $394,000. This amount does not include the cost of the
CMR:125:99 Page 2 of 5
new HVAC system ($500,000), and ADA improvements ($40,000). Also within the next ten
years, the IMP has identified that the Community Center and the Children’s Theatre will
need an estimated $207,000 and $353,000, respectively, for infrastructure improvements.
The construction of ADA improvements is estimated to cost $70,000 for the Center and
$10,000 for the Children’s Theatre. Attachment B lists all of the Community Center IMP-
related improvements over the next ten years for a total cost of $1,574,000 in 1996 dollars.
The Theatre HVAC system could either be installed as a stand-alone-project or combined
with the other infrastructure and ADA improvements to gain various project efficiencies. The
following is staff’s evaluation of each option.
.Option 1: New HVAC System as a Stand-Alone-Project
The scope of work for. this option includes replacing the existing fan unit in the basement,
upgrading the existing ducts to carry the new air flows, upgrading the electrical system
serving the HVAC, installing the compressor unit outside the building, and installing related
ADA improvements. This project will require associated Building Code upgrades within the
area served by the HVACsystem. Since the condensing.unit for the HVAC system must be
located outside the building, it will raise historical, architectural and neighborhood impact
issues.
The historical and architectural issues will be particularly significant since the building is on
the National Register of Historical Places. That designation will require a protracted review
and approval process for any changes to the appearance or exterior elevation of the building,
which will almost certainly preclude this project option from being implemented in FY 98-99
or even FY 99-00. Additionally, the Theatre programs and performances will need to be
coordinated beforehand to allow for timely rescheduling of these activities. It is anticipated
that these issues will require a significant amount of time to resolve, which may result in the
project schedule being virtually the same as the recommended fully integrated project
alternative.
Adding the new HVAC system to, the current workload in FY 1998-99 would delay work on
other scheduled projects. Some of the larger projects that could be impacted are the
Municipal Service Center Permanent Seismic Upgrade, Wilkie Way Bicycle Bridge, 1999
Street Resurfacing Project, Arastradero Road Bike Lane Improvements, and Page
Mill/Hanover Street Intersection Improvements.
Should the stand-alone-project go forward, the Theatre would be disrupted a second time
when the remaining Theatre infrastructure and ADA improvements are constructed in
approximately four years. Based on the combined reasons noted, including process and
schedule requirements, disruption to the facility on a repetitive basis, and impact to other
currently scheduled projects, staff concludes that the stand-alone-project scenario is neither
desirable nor viable.
CMR:125:99 Page 3 of 5
Option 2: Fully Integrated Project for New HVAC System. Infrastructure Maintenance, and
ADA Improvements
The major advantages of combining the new HVAC system with the other Theatre
improvements as one fully integrated comprehensive project include:
Minimal disruption to the public and Theatre staff by constructing all the
infrastructure components, ADA improvements, and HVAC system at one time;
Elimination of any duplicative effort by constructing all the improvements at one
time;
Lower design and project coordination costs, by employing one consultant instead of
two separate consultants (one for the stand-alone-project, and one for the remaining
infrastructure/ADA improvements project);
A schedule that will allow staff adequate time to meet and address at one time the
historical, architectural, and neighborhood concerns for all the improvements; and
-A schedule that will allow time for the completion of the IMP staffing study to
address the present staffing constraints prior to implementing the IMP and the fully
integrated project.
The fully integrated project alternative would require more time to complete than the stand-
alone project. The project schedule would be adjusted to start in FY 1999-00 and would
proceed in three phases: study, design, and construction. The project is estimated to take
approximately two years to complete, depending upon the degree of process required due to
the historical nature of the building, physical constraints, architectural design features, noise
considerations and neighborhood or other public involvement.
Attachment D is the project time line for both alternatives and Attachment E shows the
project location.
Staff recommends proceeding with the fully integrated project alternative. It provides for
lower cost, least disruption, and most efficient process to complete the scheduled
infrastructure improvements for the Lucie Stem Community Center Theatre, including the
addition of the new HVAC system.
POLICY IMPLICATIONS
This action is in accordance with the Infrastructure Management Program and prior Council
direction that the implementation of the IMP be o~i an integrated project basis to the greatest
extent possible.
RESOURCE IMPACT
Attachment C, the Stand-Alone-Project option, identifies the cost breakdown for the initial
project ($570,000 in FYs 1998-99 and 1999-00), and the additional project that would
complete the infrastructure and ADA improvements ($434,000 between FY 2004-05 and
CMR: 125:99 Page.4 of 5
FY 2008-09). The total estimated cost for this alternative is $1,004,000. The FY 1998-99
Capital Improvement Budget is a one year budget and funds are not yet allocated for the
proposed Theatre HVAC system improvements in subsequent years.
Attachment C, the Fully Integrated Project option, lists the cost breakdown for the initial
project ($892,000 in FY 1999-00 and FY 2000-01), and the additional costs to complete the
infrastructure improvements ($79,000 between FY 2004-05 and FY 2008-09). The total
estimated project cost for this alternative is $971,000.
ENVIRONMENTAL REVIEW
An environmental assessment will be necessary for the installation of the HVAC system.
ATTACHMENTS
Attachment A:
Attachment B:
Attachment C:
Attachment D:
Attachment E:
CIP #19910, Community Theatre Renovations, FY 1998-99 Budget
Document
Lucie Stem Community Center IMP Improvement Costs
Lucie Stem Community Theatre IMP Improvement Costs
(Options 1 & 2)
Lucie Stem Community.Theatre Project Time Line
Location Map
PREPARED BY: Alice Stoner, Assistant Director of Public Works
DEPARTMENT HEAD:
GLENN S. ROBERTS
CITY MANAGER APPROVAL:
City Manager
CMR:125:99 Page 5 of 5
ATTACHMENT A
PROJECT DESCRIPTION
This project reupholsters seats and replaces stage curtains at the Lucie Stem Community Theatre. It may also
provide’for an.air conditioning system for the.entire facility in the future, once necessary infrastructure work is
completed and dependent on total cost. : .’"
PROJECT JUSTIFICATION
The David and Lucile Packard Foundation has awarded TheatreWorks a grant in the amount of $150,000, to be
matched by the City of Palo Alto, for the purpose of air conditioning the theatre and rehabilitating the aging seats
and stage drapes and curtains. In response to this grant, the City is conducting a feasibility study in 1997-98 to
investigate the costs of air conditioning the facility. It will include an assessment of the existing duct work, asbestos
concerns, and overall estimated cost of the project, including any Americans with Disabilities Act work which may
be necessary. In the interim, in 1998-99, the work on.the curtains and seats will be done.
FUTURE FINANCIAL REQUIREMENTS
FISCAL YEAR
PYBudget
1998-99
1999-00
2000-01
2001-02
2002-03
AMOUNT
$133,000
TDB
COMPONENTS
Replacement of seat upholstery and stage curtains.
Design and installation of air conditioning, along with any necessary
infrastructure work and Americans with Disabilities Act work.
Sources of Funding: General Fund ($66,500) and the David and Lucile Packard Foundation ($66,500).
IMPACT AND SUPPORT ANALYSIS ’
Environmental:
Design Elements:
Operating:None.
Telecommunications:None.
For seats and curtains work, categorically exempt from CEQA under Section 15301,
minor change to existing facility. For air conditioning work, an environmental
assessment may be necessary.
None.
COMPREHENSIVE PLAN
The Comprehensive Plan contains no policies or procedures directly related to this project.
ATTACHMENT B
LUCIE STERN COMMUNITY CENTER
Infrastructure Management Program Improvements
Community Theatre
Theatre HVAC
ADA
Subtotal
Infrastructure Improvements
Electrical
Interior Paint and Tile
Dressing
Floor
Exterior
Roofnag
Subtotal Infrastructure Improvements
Total Community Theatre
$500,000
540,000
$210,000
$28,000
$25,000
$63,000
$5o,ooo
$18.000
$394,000
$540,000
$394,000
$934,000
¯ Lucie Stern Community Center
ADA
Infrastructure Improvements
Electrical
Floor
Exterior
Interior Paint and Tile
Subtotal Infrastructure Improvements
Total Lucie Stem Community Center
$70,000
$103,000
$46,000
$38,000
$20.000
$207,000
$277,000
Children’s Theatre
ADA
Total
Infrastructure Improvements
Exterior (seal leaks)
Electrical
Interior Paint and Tile
Floor
Subtotal Infrastructure Improvements
Children’s Theatre
$45,000
$236,000
$22,000
$353,000
$363,000.
TOTAL ESTIMATED COST (1996 IMP Dollars)$1,574.000
ATTACHMENT C
LUCIE STERN COMMUNITY THEATRE
OPTION 1
HVAC SYSTEM - STAND-ALONE-PROJECT
Fiscal Years 1998-00
Theatre HVAC
ADA
Infrastructure Improvements, Electrical Only
Total Fiscal Year 1998-00
$500,000
$20,000
$50.000
$570,000.
Fiscal Years 2004-09
ADA
Infrastructure Improvements
Electrical
Interior Paint and Tile
Dressing
Floor
Exterior
Roofing
Subtotal Infrastructure Improvements
Total Fiscal Year 2004-09
Adjusted for Inflation (5 years @ 3 %)
TOTAL STAND ALONE PROJECT
$20,000
$160,000
$28,000
$25,000
$63,000
$50,000
$18.000
$344,000 $344.000
$364,000
$1,004,000
OPTION 2
FULLY INTEGRATED PROJECT (Recommended)
Fiscal Years 1999-01
Theatre HVAC
ADA
Subtotal.
Infrastructure Improvements
Electrical
Interior Paint and Tile
Dressing
Floor
Subtotal Infrastructure Improvements
Total Fiscal Year 1999-01
Adjusted for Inflation (1 years @ 3 %)
$500,000
$40.000
$540,000
$210,000
$28,000
$25,000
$63.000
$326,ooo
$866,000
Fiscal Years 2004-09.
Infrastructure Improvements
Exterior
Roofing
Total Fiscal Year 2004-09
Total Community Theatre
Adjusted for Inflation (5 years @ 3 %)
$50,000
$68,000
$934,000
TOTAL INTEGRATED PROJECT $97!,000
ATTACHMENT D
8 ONIN~: