HomeMy WebLinkAbout1996-12-03 City Council (6)City of Polo Alto City Manager’s Report TO:HONORABLE CITY COUNCIL ATTENTION: FINANCE COMMITTEE FROM:CITY MANAGER DEPARTMENT: ADMINISTRATIVE SERVICES AGENDA DATE: DECEMBER 3, 1996 CMR:471:96 SUBJECT:1995-96 YEAR-END CAPITAL IMPROVEMENT PROJECTS STATUS MATRIX REQUEST This is an informational report and no Council action is required. EXECUTIVE SUMMARY This report provides the Finance Committee with information on the status of the City’s Capital Improvement Program (CIP) projects as of the end of fiscal year 1995-96. In the attached matrix, all City departments have submitted information on their projects and commented on any issues which might cause a change in the scope or timing of the projects. Information in this report will keep Council abreast of progress on all open CIP projects and on those projects which have been completed during the fiscal year. Earlier this year, Council received two Midyear CIP Status Reports (CMR:174:96 and CMR:251:96). The format of this new Year-end Report reflects input received from Council on both Midyear CIP reports. The attached matrix categorizes CIP’s into minor projects (projects which can be completed within a one-year period) and multi-year projects (projects which have multi-year budgets and/or complex implementation schedules with identifiable phases). Information in the project status portion of the matrix has been changed to identify the phase the project is in at the end of the fiscal year. Information on phases will give Council a better perspective on how much progress has been made on a project. Three distinct phases have been utilized, as follows: CMR:471:96 Page 1 of 3 Phase: Pre-Design Design Construction May Include: o Preparation of feasibility study o Development of a master plan o Definition of project scope o Preparation of Environmental Impact Report o Hiring a design consultant o Completion of project design o Soliciting bids or proposals o Acquisition of major equipment o Installation o Implementation of a project (e.g., computer application) A comments section has also been added to the matrix to inform Council of the reasons for substantial project delays or changes in the scope or cost of a project. In the attached matrix, projects are listed by department for the General Fund and by Fund for the Enterprise and Internal Service Funds. Within each department or fund, the projects are ordered by project number, which includes the year of Council approval (year of approval is shown by the second two digits of 5-digit project numbers or the first two digits of 4-digit project numbers). Staff has also incorporated information on the total or accumulated budget for projects, the remaining budget as of the beginning of the fiscal year, and the fiscal year expenditures, including commitments (encumbrances). While a project’s accumulated budget is provided as a reference point, information on the project’s budget balance and on expenditures during the fiscal year is detailed to provide another measurement of a project’s status. It is important to note that the total or accumulated budget was not readily available for a number of multi-year Enterprise Fund projects. The attached report does not include "continuous" projects. These projects, such as water meter replacement, have no definitive beginning or end dates and receive ongoing funding to reflect continuing replacement cycles or commitments. Staff, however, plans to provide Council with information on any "continuous" project where no progress has been made during the year. During fiscal year 1995-96, progress was made on all of the City’s "continuous" projects; a listing of these projects is provided for Council’s reference (Attachment A). All completed CIP’s will be closed and the remaining balances transferred to the Budget Stabilization Reserve for General Fund projects; and for Utility Fund projects, to the appropriate Rate Stabilization Reserves. CMR:471:96 Page 2 of 3 ATTACHMENT: Attachment A: List of Continuous Projects PREPARED BY:Linda Craig, Senior Financial Analyst Melissa Cavallo, Assistant Director, Administrative Services DEPARTMENT HEAD APPROVAL: Emil?) Harrison Deputy City Manager, Administrative Services CITY MANAGER APPROVAL: CC: n/a Fleming Manager CMR:471:96 Page 3 of 3 ATTACHMENT A List of Continuous Projects Administrative Services 18614 Financial Database Upgrade 19618 GIS Application 19711 City Network Improvements Community Services 19415 Park Facilities Improvements 18617 Art in PuNic Places Public Works 18903 18971/ 18670/ 19610 19101 19309 General Fund Sidewalk Improvements Street Improvements (Utility Users Tax) Street Improvements (Street Improvement Fund) Street Improvements (General Fund) Tank Investigation and Remova! ADA Compliance Storm Drainage Fund 8870 Collection System Improvements Utilities 8928 8930 8931 8938 8944 9354 Electric Fund Underground Improvements, customer design and connection services Traffic Signals Communications System Improvements Substation Protection Improvements Substation Facility Improvements Street Light Replacements 8013 8014 8015 8016 Water Fund Water System Extensions Sen, ice & Hydrant Replacements Water Meters Water Main Replacements 8020 9173 Wastewater Collection Sewer System Extension Sewer System Rehabilitation and Augmentation 8017 8018 8019 Gas Fund Gas System Extensions Gas Main Replacements Gas Meters & Regulators ~zn I& I0 LU 0 0 jr" 0 ~ i0 I0 I~ oo °iZ~u I.U o tO ZLU Io ~,~ "5" c o ~ ~>.~t- ~ 0 o,,,~- ~zzn ~ Z ~ZZ~