HomeMy WebLinkAbout1996-10-15 City Council (23)City
City of Palo Alto
Manager’s Report 5
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: Public Works
DATE:OCTOBER 15, 1996 CMR:427:96
SUBJECT:PALO ALTO HARBOR-MARSH RESTORATION
COOPERATIVE AGREEMENT WITH SAN FRANCISCO
INTERNATIONAL AIRPORT -BUDGET AMENDMENT
ORDINANCE.
REQUEST
This is a request for approval of a cooperative agreement with San Francisco International
Airport for funding marsh restoration at Palo Alto’s Harbor Point. It also recommends
approval of a Budget Amendment Ordinance for receipt of funds from the Airport.
RECOMMENDATIONS
Staff recommends that Council:
o
Approve and authorize the Mayor to execute the attached agreement with the
Airports Commission of the City and County of San Francisco (Commission) for
the creation of 7.2 acres of wetland habitat at Harbor Point in substantially the form
set forth in the attached agreement.
Authorize the City Manager or her designee to negotiate and amend the agreement.
Approve the attached Budget Amendment Ordinance for receipt of funds from the
Commission.
POLICY IMPLICATIONS
Approval of this agreement is consistent with the Council’s direction to proceed with
obtaining funds from other agencies or private parties to reduce or eliminate the City’s
cost for Phase II of the marsh restoration at Harbor Point.
CMR:427:96 Page 1 of 4
EXECUTIVE SI JMMARY
In 1981, the San Francisco Bay.Conservation and Development Commission (BCDC),
issued a permit to the City to perform a final marina dredging in the Palo Alto Harbor.
The permit required the City to develop four acres of marsh and seven acres of public
access improvements to mitigate the dredging. In 1992, BCDC amended the City’s
original 1981 permit, to provide the City with the option of developing the remaining
seven acres of Harbor Point as marsh rather than public access improvements. The four
acre marsh was completed in 1993.
On March 6, 1995, staff discussed the project timing and cost with the Finance Committee.
Staff indicated to the Committee that an additional one-year time extension was being
requested from BCDC to implement the remaining seven acres of marsh restoration. This
would allow time to pursue obtaining funds from a developer or agency, thereby reducing
or eliminating the City’s cost for the work. Since then, BCDC has granted a time
extension and staff was able to pursue several possible funding sources. One such source,
the San Francisco International Airport, proved to be the most viable option due to the
timing and type of project involved.
San Francisco International Airport is currently embarking on a major expansion of its
international airport to meet growing aviation transportation demands. In order to
implement the airport’s master plan, the Airport Commission must fill approximately 17
acres of wetlands to provide for runway safety zones, taxiway alignments, road widening,
new detention pond and public parking. The Army Corps of Engineers requires
landowners to mitigate for wetland fills by creating compensatory wetlands in other
locations.
Staff has held several conversations with airport representatives over the last two months
about the City’s project. These discussions resulted in a memorandum of understanding
(MOU) outlining the Commission’s participation in Palo Alto’s marsh restoration at
Harbor Point for satisfying their Army Corps of Engineers requirements. The attached
agreement represents the terms of the MOU and includes the following points:
The Commission agrees to pay the City the sum of $96,268 to fully cover the City’s
past and future administrative, design, monitoring and engineering costs. Payments
for the costs will be made within four weeks of execution of the agreement. The
City agrees to provide all necessary design and engineering for the project.
The Commission agrees to pay for the cost of construction based on the lowest
responsible bid, plus a 15 percent construction contingency and 10 percent bidding
CMR:427:96 Page 2 of 4
contingency. The current estimate for the work is $664,789 including the
contingencies.
3.The City a~;ees to manage the project.
The City agrees to be responsible for any expense incurred in the investigation and
appropriate remediation of any pre-existing contamination at the site. (The soil has
been tested and was found to be suitable as cover material for a local landfill site).
The City agrees to provide the Commission’s project manager with a copy of the
plans .and specifications and any required change orders for review and approval.
o The City agrees to hold the Commission harmless for any damage or liability
occurring in connection with any work; and the agreement also provides for defense
and indemnity for all claims, suits or actions.
The City’s and the Commission’s project managers agree to consult with each other
to determine the next appropriate steps if the lowest bid exceeds the estimated cost
for the project.
Because of conflicting agenda dates and the need to meet Palo Alto’s project and permit
schedules, it will not be possible for the City to obtain a pre-signed agreement as part of
this action. Both parties have instead agreed to respectively request approval on the basis
that the agreement has been approved by authorized Commission and City staff. (See
attached Commission letter) The City Attorney has reviewed the agreement.
FISCAL IMPACT
Funds for the past and future administrative, design, monitoring and engineering costs will
be paid by the Commission to Palo Alto within four weeks of execution of this project.
The City will pay for all construction costs from CIP 18918 and will be reimbursed by the
Commission on a monthly basis, based on the contractor’s work progress. The attached
Budget Amendment Ordinance provides for receipt of funds anticipated from the
Commission for FY 1996-97. Staff will budget for expected reimbursement for FY 1997-
98 in the 1997-98 budget.
ENVIRONMENTAL ASSESSMENT
The project will have no significant environmental effect for the purpose of the California
Environmental Quality Act, as shown in the mitigated negative declaration for the project
CMR:427:96 Page 3 of 4
approved by the Council on March 18, 1991 (Negative Declaration No. 91-EIA-1) No
further review is necessary.
STEPS FOLLOWING APPROVAL
Staff will return in the fall of 1996 with a request to approve a contract with a general
contractor to construct the seven acre marsh restoration project. Work is expected to be
completed next year.
ATTACHMENTS
Commission letter
Agreement
Budget Amendment Ordinance
PREPARED BY:
DEPARTMENT HEAD REVIEW:
George Bagdon, Assistant Director of Public Works
GLENN S. ROBERTS
Director of Public Works
CITY MANAGER APPROVAL:
FLEMING
Manager
CMR:427:96 Page 4 of 4
Airports
Commission
C,ty and County
cf San Francisco
Wiliie L. Brown, Jr.
Mayor
Henry E. Berman
President
Marie K. BrooV, s
Vice President
Michael S Strunsky
Roland A. Quan
Larry Mazzola
JOHN L. MARTIN
Director of Airporls
San Francisco Internatio~ al Airport
O,~TEWAY TO THE PACIFIC
October 8, 1996
Jim Harrington
Public Works Department
City of Palo Alto
Civic Center
250 Hamilton Avenue
Palo Alto, CA 94301
Subject: Approval of Cooperative Agreement
Dear Jim:
I am separately transmitting to you the hard copy of the Cooperative Agreement
between the San Francisco International Airport (SFIA) and the City of Palo Alto
(Palo Alto) regarding the Harbor Point Wetland Restoration Project. SFIA staff
are in full concurrence with the agreement and it will be presented to the Airports
Commission for its approval at the meeting of November 5, 1996. Please return
the signed copy to me as soon as it is executed by the City.
We look forward to the mutual benefits that will result from this project.
Very truly yours,
T. Calerdine
Environmental Planning Manager
John Costas
BPE Chron
BPE B.06.15
X:LL52q~,WETLANDS’ffLARRIN G. LTR(10/8/96)
SAt.,’, FR&HCiSO0 IHTERI’i~TiON&L A!R’~ORT P0 BO× 8097 SAH FRAHCISCO CALIFORNia, 94128. TELEPHONE (415} 794-5008 F:=.)t415 794-5~05
Cooperative Agreement
COOPERATIVE AGREEMENT
This AGREEMENT, entered into on , is between THE CITY AND COUNTY OF SAN
FRANCISCO through its AIRPORT COMMISSION (COMMISSION), and the CITY OF PALO
ALTO, (PALO ALTO), a municipal corporation in the County of Santa Clara, California.
RECITALS
(1) PALO ALTO proposes to create 7.2 acres of wetland habitat on property within
and owned by PALO ALTO at Harbor Point for purposes of environmental enhancement (PROJECT).
Harbor Point is a former boat harbor that PALO ALTO is restoring as a tidal wetland. The location
of the property is shown in Attachment 1.
(2) COMMISSION proposes to fill 17.2 acres of wetlands and other waters of the
United States at the San Francisco International Airport (SFIA) in order to implement its Master Plan
of landside improvements.
(3) The fill of such wetlands by COMMISSION will require the approval of the U.S.
ARMY CORPS OF ENGINEERS (CORPS) under Section 404 of the Clean Water Act, and a permit
application is presently pending before the CORPS.
(4) The CORPS requires landowners to mitigate for wetland fills by creating
compensatory wetlands in other locations.
(5) COMMISSION has applied for a Section 404 permit from the CORPS for
placement of fill at SFIA, and has identified the PROJECT as a proposed mitigation site (additional
mitigation sites will also be required). The CORPS has circulated a Public Notice describing the
proposed wetland fill at SFIA and identifying PROJECT as proposed partial mitigation. Approval
of the permit by CORPS is anticipated by COMMISSION in December, 1996. Approval will also
be required from the California Regional Water Quality Contro! Board (RWQCB) and potentially
the California Department of Fish and Game.
(6) COMMISSION and PALO ALTO desire COMMISSION to fund the construction
of PROJECT in exchange for COMMISSION receipt of mitigation credits that result from such
construction. Such credits will be used by COMMISSION to partially offset the impacts of wetland
fills by the COMMISSION, as required by CORPS.
(7) PALO ALTO has prepared a cost estimate for the PROJECT of $761,057, identified
in Section II, including a 15% construction contingency.
X:kLYN~WETLANDSkAGREE.WPD(10/8196)
Cooperative Agreement
(8) PALO ALTO and COMMISSION intend to define herein the terms and conditions
under which PROJECT is to be developed, designed and financed.
(9) This AGREEMENT supercedes any provisions of the prior Memorandum of
Understanding relating to the PROJECT where said provisions conflict with this AGREEMENT.
TERMS OF AGREEMENT
PALO ALTO and COMMISSION do hereby agree as follows:
I. TRANSFER OF MITIGATION CREDITS
Within one month after the award of a construction contract for the PROJECT, PALO ALTO
will inform the CORPS and other such agencies that may have jurisdiction over wetlands and
waters of the United States that 7.2 acres of wetlands created by PROJECT may be utilized
by COMMISSION as mitigation for wetland impacts resulting from construction projects
at SFIA.
II.ESTABLISHMENT OF BUDGET
In exchange for mitigation credits provided to COMMISSION by Palo Alto, COMMISSION
will fund PALO ALTO’s design and engineering, construction, monitoring per the
requirements of the San Francisco Bay Conservation and Development Commission (BCDC),
maintenance and administrative costs up to the maximum budget established below:
Design and Engineering $
(including environmental review
and permitting)
Construction $
Construction Bid Potential Over-$
run (10%)
Construction Contingency (15%)$
Mitigation Monitoring and Main-$
tenance
Administrative Costs $
Total $
59,439
525,526
52,552
86,711
22,685
14,144
761,057
X :kLYN~W ETL ANDSL~.GREE .WPD(10/8/96)2
Cooperative Agreement
Any expenditures in excess of the total budget listed above will require approval by
the COMMISSION.
III.PRIg-CONSTRUCTION ACTIVITIES
COMMISSION and PALO ALTO shall each appoint a Project Manager for the
duration of the PROJECT construction. The Project Managers shall be the single point
of contact for construction administration and PROJECT related activities on behalf
of each agency. Formal written notice shall be given to the addresses listed below
of any change in Project Manager by either agency.
COMMISSION shall seek approval from CORPS and other regulatory bodies with
jurisdiction over wetland fills to utilize the PROJECT as mitigation for proposed
wetland fills at SFIA.
PALO ALTO shall provide all necessary design and engineering for PROJECT,
including the preparation of PROJECT plans, specifications and estimates (PS&E),
utility identification and location, and preparation of contract documents, and will
obtain all necessary permits and environmental review for the PROJECT. The final
PROJECT PS&E shall include, as a separate item, a construction contingency (15%
of estimated construction amount) and the costs for landscape maintenance of the
PROJECT for at least three months.
o At its own expense, PALO ALTO shall perform the identification and investigation
of all hazardous materials on the site and shall comply with all remediation standards
and requirements imposed by applicable laws and regulatory agencies.
o At least two weeks prior to PROJECT advertisement for bidding, PALO ALTO will
provide COMMISSION’s Project Manager with a copy of the PROJECT PS&E for
review and approval.
The COMMISSION’s Project Manager shall review PROJECT PS&E within two
weeks of the submittal of the PROJECT plans by PALO ALTO, and shall indicate,
in writing, its acceptance or rejection of the PROJECT PS&E. The COMMISSION’s
acceptance or rejection of the PROJECT PS&E shall be based solely on whether the
final cost estimate and construction contingency amount exceeds the limits set forth
in Section II above. If the COMMISSION’s Project Manager does not approve the
final PROJECT PS&E, then PALO ALTO and COMMISSION shall work in good
faith to resolve the dispute as follows:
PALO ALTO and COMMISSION shall use best efforts to agree to design
changes to meet the COMMISSION’s concerns.
X:kLYNkWETLANDSkAGREE.WPD(10/8/96)
b)
c)
Cooperative Agreement
PALO ALTO and COMMISSION shall use best efforts to agree to other
reasonable and prudent steps, such as partial or phased construction, to
facilitate development of the PROJECT as they may deem appropriate at the
time. Any such actions which have the effect of reducing wetland creation
credits to the COMMISSION or increasing the PROJECT’s budget will require
the separate approval of the COMMISSION.
COMMISSION can withdraw from the PROJECT funding and terminate the
AGREEMENT, at which time PALO ALTO will inform the CORPS that the
AGREEMENT has been terminated and that no mitigation credits should be
granted to COMMISSION as a result of this PROJECT.
IV. BIDDING AND CONTRACT AWARD ACTIVITIES
Upon approval of the PROJECT PS&E by COMMISSION’s Project Manager, PALO
ALTO will proceed to advertise the PROJECT for bids using normal PALO ALTO
bidding procedures.
Upon receipt of bids, PALO ALTO will review all bids received with the COMMIS-
SION’s Project Manager.
o PALO ALTO will determine the lowest responsible bidder for the PROJECT in
accordance with PALO ALTO’s contract awarding procedures.
PALO ALTO will award the contract to the lowest.responsible bidder if the low bid
is less than or equal 110% of the construction budget listed in Section II above
(excluding construction contingencies).
PALO ALTO will consult with COMMISSION’s Project Manager to determine the
next appropriate steps if the low bid exceeds 110% of the construction budget adopted
in Section II above, as follows:
PALO ALTO and COMMISSION agree to rebid the PROJECT with or
without design changes to reduce the PROJECT’s cost.
b)The COMMISSION’s Project Manger can recommend to the COMMISSION
to proceed with the PROJECT based upon the low bid price. It is understood
that a decision to proceed to construct the PROJECT at a cost in excess of
110% of the COMMISSION approved budget will require approval by the
COMMISSION. If the COMMISSION determines not to approve the increase
in budget for the PROJECT then one of the following steps will be taken:
X:’~LYN~WETLAND SkAGRE E. WPD(10/8/96)4
Cooperative Agreement
(i)ALO ALTO and COMMISSION will take prudent steps, including
redesign of the PROJECT as appropriate, to bring it within the adopted
budget, and rebid the PROJECT; or
(ii)PALO ALTO and COMMISSION can mutually agree to other
reasonable and prudent steps, such as partial or phased construction,
to facilitate development of the PROJECT. Any such actions which
have the effect of reducing wetland creation credits to the COMMIS-
SION or increasing the PROJECT’s budget will require the separate
approval of the COMMISSION.
(iii)COMMISSION can withdraw from the PROJECT funding and
terminate the AGREEMENT, at which time PALO ALTO will inform
the CORPS that the AGREEMENT has been terminated and that no
mitigation .credits should be granted to COMMISSION.
V. CONSTRUCTION ACTIVITIES
Upon written concurrence of the parties that the PROJECT bid price is consistent with
the terms of this AGREEMENT, PALO ALTO will authorize the construction to
commence on PROJECT.
o PALO ALTO’s contractor will provide the management, labor, materials, tools and
equipment to build the PROJECT, and to cause it to be constructed in accordance with
the construction documents approved by the COMMISSION as part of its PROJECT
PS&E approval.
o PALO ALTO will report progress on the construction of the PROJECT to the
COMMISSION on a monthly basis, or as requested by COMMISSION.
If, during the course of construction, PALO ALTO determines that a contract change
order is appropriate for additional work by the contractor, then PALO ALTO shall
seek the written approval of the COMMISSION’s Project Manager prior to approval
of the contract change. The COMMISSION’s Project Manager shall review the
proposed change in good faith to determine if development of the mitigation
PROJECT requires the approval of the change order; such approval shall not be
tmreasonably withheld. If the COMMISSION’s Project Manager approves the change,
and the cumulative total cost of such changes is within the approved construction
contingency (15% of the awarded contract amount), then PALO ALTO shall pay the
contractor for the change with the funds allocated for construction contingencies. If
COMMISSION determines, in good faith, that the requested change is not necessary
for the implementation of the PROJECT, then COMMISSION shall not be obligated
X:kLYI~W ETLAN DSL~.GRE E .WPD(10/8/96)
Cooperative Agreement
to authorize payment for the change; however, PALO ALTO may proceed with the
change at its own cost. In no case shall the cumulative cost of such change orders
exceed the budget listed in Section II above for construction contingencies without
the prior written approval of the COMMISSION.
VI.PAYMENT AND BILLING PROCEDURES
Any payment by COMMISSION to PALO ALTO for construction of PROJECT shall
be based upon approval by CORPS of PROJECT as 7.2 acres of partial mitigation
for COMMISSION’s proposed wetland fill. Payment shall also be contingent upon
same approvals by other agencies as may have jurisdiction over the proposed wetland
fill at SFIA (i.e., California Regional Water Quality Control Board and potentially
the California Department ofFish and Game).
Within four weeks of the award of the construction contact, and subject to approval
of PROJECT as mitigation site by the CORPS and other regulatory agencies with
jurisdiction, COMMISSION shall pay PALO ALTO for PALO ALTO’s past and
current administrative, design, and monitoring costs incurred in connection with the
PROJECT. PALO ALTO shall provide documentation to COMMISSION to
substantiate such costs. The combined total of the administrative, design and
monitoring costs shall not exceed the budget for such items adopted in Section II
without the separate approval of the COMMISSION.
o PALO ALTO shall invoice the COMMISSION on a monthly basis for work performed
by the general contractor to cover progress payments to the general contractor
matching the payment schedule contained in the bid documents of the general
contractor. Invoice’s shall be directed to the attention of the COMMISSION’s Project
Manger. Invoices may also include ongoing administrative costs incurred during the
billing period (within the budget for such expenses). Invoices shall, as a minimum,
(i) be mechanically accurate, (ii) include vouchers or invoices from the general
contractor that are properly supported with satisfactory backup documentation
approved by COMMISSION’s Project Manager; and (iii) be in a form acceptable to
PALO ALTO’s Manager of Accounting and the Controller for the City and County
of San Francisco. All amounts paid by the City and County of San Francisco to PALO
ALTO shall be subject to audit by the City.
o Upon completion of the PROJECT, PALO ALTO will provide COMMISSION with
a detailed statement of accounting for actual costs of construction. COMMISSION
will have the right to reasonable review of all PROJECT-related costs.
o Any obligation of COMMISSION to pay invoices for the PROJECT is subject to the
underlying costs meeting the following requirements:
X:kLYI~WETLAND S’,.AGRE E.WPD (10/8/96)6
Cooperative Agreement
a)conform with the awarded scope of work and all other terms of this
AGREEMENT;
b)are, in the reasonable judgment of PALO ALTO, necessary in order to
accomplish the scope of work and reasonable for the services provided; and
c)are actual net costs to PALO ALTO (i.e., the price paid minus any refunds,
rebates, or other items of value received by PALO ALTO that have the effect
of reducing the costs actually incurred).
PALO ALTO or its consultants will maintain all books, documents, papers, accounting
records, and other evidence pertaining to this AGREEMENT, including but not limited
to, all costs, completion dates and schedules, and the costs of administering this
AGREEMENT, for a period of at least five (5) years following termination or
completion of the PROJECT under this AGREEMENT. PALO ALTO’s books,
records, and documents that are pertinent to the AGREEMENT shall be made
available to the COMMISSION as may be required for audit and examination
purposes. Monthly records ofPALO ALTO’s consultants’ personnel costs, consultant
costs, and reimbursable expenses shall be kept by PALO ALTO’s consultants on a
generally recognized accounting basis. These documents and records shall be
available to COMMrSSION upon request at reasonable times and places.
PALO ALTO may, at its own risk, proceed to prepare plans and/or construct
PROJECT prior to approval .of PROJECT as mitigation site by CORPS and other
regulatory agencies with jurisdiction. In such case, payments to PALO ALTO by
COMMISSION will not be made until the PROJECT is approved as mitigation by
the CORPS and other agencies. Upon approval of PROJECT as mitigation by CORPS
and agencies, PALO ALTO will then invoice COMMISSION for expenses incurred
to date as described above. No payments wil! be made if CORPS or other regulatory
agencies do not approve PROJECT as mitigation.
POST-CONSTRUCTION ACTIVITIES
Following completion of the PROJECT, PALO ALTO will maintain the property as
a restored wetland for the period of time specified by the CORPS in their permitting
of the PROJECT.
PALO ALTO shall provide a ten year monitoring program of the 7.2 acre site in
accordance with BCDC permit condition H.5, which is incorporated herein by
reference.
X ALYN~WETLANDSkAGREE.WPD(10/8196)7
o
Cooperative Agreement
At the completion of construction, PALO ALTO shall invoice the COMMISSION
in a single lump sum amount for all future monitoring activities. Monitoring costs
shall be equal to or less than the budget adopted in Section II above. Any changes
in subsequent monitoring costs (positive or negative) shall be absorbed by PALO
ALTO.
VIII. PALO ALTO AND COMMISSION MUTUALLY AGREE:
All obligations of COMMISSION under the terms of this AGREEMENT are subject
to the budget and fiscal provisions of the Charter of the City and County of San
Francisco and any required approvals by the City and County of San Francisco Board
of Supervisors. Charges will accrue only after prior written authorization by the
Controller, and the amount of the City’s obligation hereunder will not at any time
exceed the amount certified for this purpose and period stated in such advance
certification.
o Except as otherwise provided by this AGREEMENT, the PROJECT site shall remain
under the ownership of PALO ALTO and PALO ALTO shall retain all the rights and
responsibilities of the property owner.
This AGREEMENT may be terminated or provisions contained herein may be altered,
changed or amended by the mutual consent of the parties thereto.
4.PALO ALTO shall defend, indemnify and hold harmless the COMMISSION, the City
and County of San Francisco Board of Supervisors, its officers, agents and employees
from all claims, demands, suits, loss damages, injury and liability, direct or indirect,
incurred by reason of any act, failure to act, error or omission of PALO ALTO, its
officers, agents, employees, or consultants, or any of them arising out of or in
conjunction with the PROJECT under this AGREEMENT; andPALO ALTO agrees
at its own cost expense and risk to defend any and all claims, actions, suits, or other
legal proceedings brought or instituted against COMMISSION, the City and County
of San Francisco Board of Supervisors, its officers, agents and employees, or any of
them, arising out of or in conjunction with the PROJECT under this AGREEMENT
and pay and satisfy any resulting judgements.
Except as otherwise provided for above, this AGREEMENT shall terminate on the
completion of the monitoring period for the PROJECT as required by BCDC, or on
December 31, 2007, whichever is earlier in time.
All notices hereunder shall be given in writing and mailed, postage prepaid, by
certified mail, addressed as follows:
X:kLYN~WETLANDSkAGREE.WPD (October 2, 1996)8
To PALO ALTO:(Sffice of the City Clerk
City of Palo Alto
P.O. Box 10250
Palo Alto CA 94301
Cooperative Agreement
Copy to:James M. Harrington
Public Works Department
City of Palo Alto
P.O. Box 10250
Palo Alto CA 94301
To COMMISSION:
Copy To:
John L. Martin
Director of Airports
San Francisco International Airport
P.O. Box 8097
San Francisco, CA 94114
John Costas
Deputy Director, Planning and Environmental Affairs
San Francisco International Airport
P.O. Box 8097
San Francisco, CA 94114
X:kLYN~WETLANDSLAGREE.WPD (October 2, 1996)9
Cooperative Agreement
AIRPORT COMMISSION OF THE CITY
AND COUNTY OF SAN FRANCISCO
JOHN L. MARTIN,
MRPORT DIRECTOR
CITY COUNCIL OF THE CITY OF
PALO ALTO, CALIFORNIA
By By
Director of Airports
Approved as to form
Louise H. Renne
City Attorney
Mayor
Attest:
Melba Yee
Deputy City Attorney
Airport Commission
Approved as to Form
Senior Assistant Attorney
Approved
City Manager
Deputy City Manager
(Administrative Services)
Director of Public Works
Attachment 1 :
X:kLYN~WETLANDS~AGREE.WPD (October 2, 1996)10
Attachment 1
PROJECT SITE
MIN.
VIEW
PURPOSE:
PROVIDE PUBLIC ACCESS,
CREATE WETLANDS AND
CREATE SAILING STATION
DATUM: NGVD
ADJACENT PROPERTY OWNERS:
CITY OF-PALO ALTO
STREET MAP
~C.~L£
PALO ALTO HARBOR IMPROVEMENTS
IN: MAYFIELD SLOUGH
COUNTY: SANTA CLARA
STATE: CALIFORNIA
APPLICATION BY:
CITY OF PALO ALTO
SHEET 2 OF 5. DATE 1-24-95
ORDINANCE NO.
ORDINANCE OF THE COUNCIL OF THE CITY OF PALO ALTO
AMENDING THE BUDGET FOR THE FISCAL YEAR 1996-97 TO
ALLOCATE REVENUE FROM THE AIRPORTS COMMISSION OF THE CITY
AND COUNTY OF SAN FRANCISCO TO BE USED FOR MARSH
RESTORATION AT HARBOR POINT
WHEREAS, pursuant to the provisions of Section 12 of Article
III of the Charter of the City of Palo Alto, the Council on June
24, 1996 did adopt a budget for fiscal year 1996-97; and
WHEREAS, Capital Improvement~ Project 18918, Harbor
Improvements, has been funded through prior and current year
appropriations from the Budget Stabilization Reserve; and
WHEREAS, the Harbor Improvements CIP (Number 18918) was
established pursuant to an agreement with the San Francisco Bay
Conservation and Development Commission (BCDC) to develop marsh at
Harbor Point; and
WHEREAS, the Airports Commission of the City and County of San
Francisco (Commission) has a master plan to expand the San Francisco
International Airport which will require them to develop new
wetlands; and
WHEREAS, BCDC and US Army Corps of Engineers has allowed the
Commission’s Marsh requirements to be fulfilled by funding part of
the Harbor CIP 18918; and
WHEREAS, in order to meet its requirement to develop new
wetlands, the Commission has agreed to a one-time payment of $96,268
to fully cover the City’s past and future administrative, design,
monitoring and engineering costs; and
WHEREAS, in addition, the Commission has a~reed to reimburse
the City for the costs of construction, on a monthly basis, for a
total of $612,237, $306,119 to be received in 1996-97 and $306,118
to be received in 1997-98; and
WHEREAS, City Council authorization is needed to amend the
1996-97 budget as hereinafter set forth.
NOW, THEREFORE
ORDAIN as fol!ows:
the Counci! of the City of Palo Alto does
SECTION i. The sum of Four Hundred Two Thousand Three Hundred
Eighty Six ($402,386 is hereby added to revenue in the Public Works
Department budget in the Genera! Fund and the General Fund Budget
Stabilization Reserve is corresponding increased.
SECTION 2. This transaction will increase the
Stabilization Reserve from $16,111,391 to $16,513,777.
Budget
SECTION 3. The City Council certified a mitigated negative
declaration (91-EIA-I) on March 18, 1991, for the project. No
further review is necessary.
SECTION 4. As provided in Section 2.04.350 of the Palo Alto
Municipal Code, this ordinance shal! become effective upon adoption.
INTRODUCED AND PASSED:
AYES:
NOES:
ABSTENTIONS:
ABSENT:
ATTEST:APPROVED:
City Clerk Mayor
APPROVED AS TO FORM:City Manage~
Senior Asst. City Attorney Deputy City
Administrative
Department
Manager,
Services
Director of Public Works