HomeMy WebLinkAbout1996-04-18 City Council (23)C ty
BIIDGET 1996-98
City of Palo Alto
Manager’s Report
TO:HONORABLE CITY COUNCIL
FROM:CITY MANAGER DEPARTMENT: ADMINISTRATIVE
SERVICES
DATE:APRIL 18, 1996 CMR:211:96
SUBJECT:BUDGET ISSUE: NEW POSITION REQUESTS
RECOMMENDATIONS
This is an informational report, and no Council action is required. This staff report provides
Council with background information about new position requests that are addressed in the
1996-98 Budget, for discussion at the Council study session on budget issues.
EXECUTIVE SUMMARY
The 1996-98 Budget includes 9.5 new General Fund position requests, 1.0 new Utility Fund
position request, and 2.0 temporary-to-permanent conversions. Of the General Fund
positions, 3.6 would be entirely reimbursed by the Utility Funds. The positions provide for
a number of service enhancements, including permanent graffiti prevention and removal
services; a comprehensive tree program that includes tree protection, trimming, planting and
removal services; improved parking adjudication services; personal computer support to
accommodate the growth of computer usage citywide; leadership of the City’s GIS program;
in-house programming expertise for the new Utilities Customer Information System and
improved Utilities computer applications support; improved inventory control and receipt
inspection; improved contract administration; and financial support for the growing City
investment portfolio and debt financing projects. The cost of these service enhancements has
been incorporated into the 1996-98 Budget and totals $344,882 for the General Fund and
$378,387 for the Utility Funds. This amount does not include one-time costs associated with
these positions (e.g., computers, equipment, furniture, training, etc.) that has been budgeted
in 1996-97. The positions are summarized in the table below. Following the table, each
position request is discussed in more detail.
CMR:211:96 Page 1 of 12
SERVICE/NEED POSITIONS REQUESTS
Permanent Graffiti Program
Implement Tree Task Force
Recommendations
Implement Tree Protection
Ordinance
Improved Parking Adjudication
Services
Improved Citywide Personal
Computer Support
Improved GIS Support
Programming Support for the
Utilities Customer Information
System
Improved Computer
Applications Support
Improved Inventory Control
and Receipt Inspection at the
MSC
Improved Contract
Administration
Financial Support for
Investments and Debt Financing
Projects
.5 Office Assistant (new)
.5 Office Assistant (temporary to
permanent conversion)
.5 Traffic Control Maint II (new)
.5 Traffic Control Maint II
(temporary to permanent
conversion)
1.0 Coordinator Public Works
Projects (new)
1.0 Arborist (new)
.5 Parking Examiner (temporary to
permanent conversion)
.5 PC Technician (new)
.5 PC Technician (temporary to
permanent conversion)
1.0 Systems Analyst (new)
1.0 Senior Programmer Analyst
(new)
1.0 Utility System Technician
(new)
1.0 Storekeeper (new)
2.0 Contract Managers (new)
COST~UNDING SOURCE
$8,105 General Fund
$11,400 Utility Funds
$73,088 General Fund
$73,650 General Fund
4,808 General Fund
$43,405 General Fund
$47,989 General Fund
$31,993 Utility Funds
$75,723 Utility Funds
65,558 Utility Funds
1.0 Senior Financial Analyst (new)
$46,992 Utility Funds
$63,183 General Fund
$96,775 Utility Funds
$30,654 General Fund
$49,946.Utility Funds
CMR:211:96 Page 2 of 12
PERMANENT GRAFFITI PROGRAM
Staffis requesting to convert two half-time temporary positions (Office Specialist and Traffic
Control Maintenance worker) in the Public Works Department to two full-time permanent
positions, in order to continue successful graffiti removal and prevention efforts. The current
program resulted in response to about 1,100 calls during calendar year 1995. Services
include a 24-hour hotline for reporting graffiti; a hotline coordinator who responds to and
logs calls, generates work orders, and tracks data on the program; and the actual field work
of removing graffiti. By converting these positions to permanent full-time positions, staff
will also be able to expand the program to provide cleaning and maintenance activities at the
22 County bus shelters in Palo Alto. The County discontinued this service when Palo Alto
opted not to participate in a proposed shelter advertising program.
IMPLEMENT TREE TASK FORCE RECOMMENDATIONS
In order to effectively implement increased trimming, planting and removal services in
support of the City’s Tree Program, staff recommends the addition of a Coordinator of Public
Works Projects position. This position would be responsible for identifying dying trees for
removal; preparing and administering removal contracts; identifying sites for planting of new
trees and selecting the appropriate species for the site; inspecting and purchasing trees and
preparing planting contracts; and assisting with the inspection and administration of
clearance and shade tree (ash and elm) pruning. This employee would also serve as liaison
with the nonprofit tree group’s planting and pruning activities. This position has been
recommended in reports from both the Tree Task Force and the Hughes-Heiss Organizational
Review.
IMPLEMENT TREE PROTECTION ORDINANCE
On August 8, 1995, the Policy and Services Committee directed the City Attorney’s Office
to lead an interdepartmental effort to draft a tree protection ordinance. Staff plans to bring
the ordinance to Council for approval in 1996-97. After studying the staffing needed in other
communities to properly enforce and administer such an ordinance, staff has concluded that
a full-time arborist position is required to implement the ordinance. Should this ordinance
be adopted, staff is requesting Council approval of an arborist position in the Planning
Department. The final position classification will be determined by the Human Resources
Department. The arborist would be responsible for minimizing harm and damage to trees
on private property in the City, including education and community outreach efforts; issuing
permits for certain categories of tree removal, which would result in the protection of
significant trees that should not be removed; monitoring replacement of trees that are
removed; and coordinating appeals for removal permits that have been denied.
CMR:211:96 Page 3 of 12
IMPROVED PARK]NG ADJUDICATION SERVICES
The responsibilities of this position were mandated by State Assembly Bill 408 (AB408) that
went into effect July 1, 1993. This legislation decriminalized parking offenses, removed
parking citation processing from the court system and established a system of administrative
adjudication. Since 1993, when this legislation was enacted, a temporary employee served
as the parking adjudicator. The 1,000-hour limitation on the number of hours that temporary
employees can work each year, in order to comply with retirement system regulations, has
resulted in delays in adjudicating parking citations. Additionally, a recently-adopted State
law requires a significant amount of professional training for parking adjudicators. Each
year, the adjudicator has exceeded the 1,000-hour limit in order to prevent lengthy delays in
scheduling hearings. Since the work associated with this position is part of an ongoing
program, staff is recommending converting this to a permanent half-time position. This
would ensure fair, impartial and speedy hearings for everyone who contests parking citations
and would maintain qualified staff.
The City issues approximately 40,000 parking citations each year, the third highest in the
County. In addition, the City averages approximately 1,000 hearings annually. The City of
Mountain View and the Mid-Peninsula Open Space District are under contract and use the
City adjudicator services, adding an additional 30 to 50 hearings each year:
IMPROVED CITYWIDE PERSONAL COMPUTER SUPPORT
The City’s increased dependency on personal computers, software, application sharing, and
data networking has placed greater requirements on the staff who install, maintain and
implement these technologies. The City utilizes more than 650 personal computers. In
addition, there are the peripherals and communications devices which form the data network.
These functions are supported by two full-time personal computer technicians in Information
Technology, as well as a half-time contract employee performing personal computer support
solely for the Police Department. The 1996-98 Budget recommends increasing computer
support by converting the half-time contract employee in the Police Department to one full-
time regular employee, and contracting for additional citywide support.
The Police Department has unique support requirements, including laptop computers
installed in the police cars and radio connectivity to various data bases. Virtually all Police
employees, reserve officers, and volunteers utilize computers in their daily work, from
inquiring into in-house, Federal, State and County data bases, to writing, processing, storing
and retrieving reports on-line. The Fire Department is also adding laptop computers to its
fleet of fire trucks. These computer resources are critical to the Departments’ ability to
provide quality public safety programs. Currently, there is no ongoing maintenance program
in place, due to unavailability of staff. The expanded use of personal computers in the Police
and Fire Departments necessitates the increase of the half-time contract employee to a full-
CMR:211:96 Page 4 of 12
time position, to ensure the timely exchange of information which is essential in the law
enforcement and public safety environments.
Due to the desire to centralize computer resources, the position is recommended to be
assigned to the Information Technology Division of the Administrative Services Department.
Complete support of the Police Department’s personal computers, hardware, sotb,vare, and
networking, as well as support for the new Fire Department laptops, would be added to the
responsibilities of Information Technology. The requested increase to the Information
Technology budget is $61,308; the Police Department budget would be decreased by
$17,903.
To accommodate the growth of computer usage citywide, Information Technology has
requested funding of $50,000 to contract with an outside organization for personal computer
support. Contracting for this service will eliminate the immediate need for added full-time
employees, and provide experienced support without the training required for regular
personnel. This support will allow the existing technicians to pursue critical projects (such
as an automated PC inventory, improved problem management and help desk support, and
improved networking for printing, file sharing and application sharing), which cannot
progress due to the number of requests for personal computer-related service. A formal
Request for Proposal process will be followed to determine the requirements, contractor
skills, costs, and level of service.
IMPROVED GEOGRAPHIC INFORMATION SYSTEM (GIS) SUPPORT
A Systems Analyst is requested to provide coordination for the Geographic Information
System (GIS) program. The position will be responsible for working with the GIS Steering
Committee to establish short- and long-term GIS strategic plans; directing and overseeing
the coordination of GIS with City information systems; assisting departments in the
specification of GIS needs; and basic coordination of the development efforts, hardware and
software installations, and network requirements. Positioning a staff member to handle all
matters of GIS is critical to the success of the project, in lieu of having the responsibilities
spread across several City staffmembers and outside consultants. The Interdepartmental
Steering and Technical Committees defined the requirements for the position. The
Coordinator will lead the project, as it heads into the new phase of application development
to allow City staff and the public to gain access to the data stored within the GIS system.
Although the City’s initial intent was to add a GIS Systems Analyst in the 1995-96 fiscal
year by converting a software training position, a critical need arose in the area of network
support, and the open position was converted to a network engineer. The requirement to
maintain the connectivity between the users of personal computers and applications
processing on the HP9000’s had expanded, and three City facilities were added to the City’s
CMR:211:96 Page 5 of 12
local and wide area network. At that time, the GIS project efforts were focused on
development, input and verification of the graphical data. As GIS transitions to the use and
interfacing of this data with citywide systems, and making the data available to the public,
the GIS Coordinator becomes essential. The position will be located in the Information
Technology Division of Administrative Services.
PROGRAMMING SUPPORT FOR THE UTILITIES CUSTOMER INFORMATION
SYSTEM (CIS)
Council received a status report and funding request for the Utilities CIS in December, 1995
(CMR:510:95). That report indicated that, in addition to contracted consulting services, staff
would return during the 1996-98 budget process with a recommendation for permanent
staffing. One Senior Programmer Analyst is recommended to support CIS system
development and maintenance in the Information Technology Division of Administrative
Services. The employee would assume responsibility for the long-term maintenance of, and
future enhancements to, the CIS application upon successful system implementation. This
would provide the City with in-house programming expertise for the continuity of the CIS
project.
IMPROVED UTILITIES COMPUTER APPLICATIONS SUPPORT
The onset of deregulation is changing the environment in which utilities are operating and
elevating the importance of information.technology. In the past, utilities used technology
only to automate or improve the reliability of technical and business processes. Now, it is
viewed as a critical element of their strategy for surviving in this increasingly competitive
environment. The City’s Utility Department is currently developing and.implementing
several new information systems applications. These new systems applications include Load
Research, Traffic Control System, Computer Aided Design, Gas Nomination System, and
Water-Gas-Storm and Electric SCADA Systems. The Utilities Department is, therefore,
requesting a Systems Technician position to support the growing number of information
systems applications. This position will enable Utilities to effectively maintain existing
systems and support the implementation and maintenance of the new information system
applications.
IMPROVED INVENTORY CONTROL AND RECEIPT INSPECTION AT THE
MUNICIPAL SERVICE CENTER (MSC) WAREHOUSE
For a number of years, the Utilities Department has maintained a stock of materials and
supplies separate from the City’s central inventory. This practice began because Utility
Operations stafffound that materials in the City’s central inventory were not always available
when needed. Staff has a number of concerns regarding this practice. These materials and
CMR:211:96 Page 6 of 12
supplies are of considerable dollar value (several hundred thousand dollars) and are not
adequately secured, nor are they monitored as closely as the City’s central inventory. In
addition, they are not tracked on the City’s inventory system and, as a result, the materials
are not available if needed to support other City needs (e.g. Public Works projects). Lastly,
this practice makes it difficult to determine annual usage and may negatively impact
procurement activities. For example, this practice prevents Purchasing from establishing
annual contracts to lock in prices and often results in expensive emergency orders when
stock-outs occur.
In 1995-96, Administrative Services and Utilities Departments staff developed a plan to
transfer these materials back to the City’s central inventory. Staff has jointly reviewed
appropriate stock levels, economic order quantities and reorder points. Administrative
Services staff has developed a process to provide Utilities staff access to the materials after
hours and on weekends. However, in order to effectively support the increased levels of
inventory, an additional storekeeper position will be required in the City’s central warehouse.
With this position, Utility Operations will be able to get the materials it needs, while ensuring
proper security and accountability for the City’s assets. This position would also enhance the
service levels provided to Utilities by the addition of a more thorough receipt inspection of
incoming materials, and the capability to conduct materials testing and perform quality
control reviews of materials received.
IMPROVED CONTRACT ADMINISTRATION
At the present time, the City’s contracting process is decentralized. Each City department
is responsible for ensuring that it complies with City bidding and contracting policies and
procedures. More specifically, City departments lead the effort to develop bid and proposal
specifications, evaluate responses and, ultimately, select the most responsible contractor or
vendor. The City’s Purchasing organization ensures that policies and procedures are in place
to guide departments through this process, along with supporting many of the administrative
steps involved in the contracts process (e.g. advertising bids, assembling bid packages, etc.).
With this current structure, there is no central ownership and accountability for the
contracting process and, as a result, a number of concerns have surfaced.
In early 1994, Council shared with staff its concerns about the City’s procurement process.
Council was concerned that the City may not have adequate numbers of bidders, so that the
products and services purchased are of high quality at the lowest possible prices; that the
City’s bid process may not be competitive; and that the purchasing process may not be
honest, open and efficient.
In September 1995, the City Auditor completed an audit of the City’s contracting process,
identifying a number of areas in need of improvement. The Auditor found instances where
CMR:211:96 Page 7 of 12
City departments did not comply with established contracting policies and procedures. The
Auditor also identified that the Purchasing Section was not involved in a pro-active manner
in procurement decisions. Among other things, the Auditor pointed out that bid evaluations,
selection decisions and negotiated changes to scope and price were not properly documented
and reviewed by Purchasing. In addition, the Auditor identified that Purchasing did not
review City Manager’s Reports to ensure that contracts complied with City policies and
procedures before going to Council for approval.
Although staff agreed with the Auditor that improved oversight by Purchasing would add
objectivity and value to the selection process, staffing levels did not allow the time
commitment that this would require. As a result, staff agreed to evaluate Purchasing’s role
in the City organization and to provide Council with a plan to address the need for change
in the City’s procurement operation with the 1996-98 Budget.
Organization and Process Changes Required for Purchasing: In October 1995, staff hired a
new Purchasing Manager and set out to review the costs and benefits associated with
-providing the controls recommended by the Auditor. Staff concluded that the benefits that
could be obtained through increasing Purchasing’s involvement and assistance to departments
would far outweigh the costs. As such, staff has formulated a plan to address the required
organizational and process changes that includes five major elements: 1) the creation of new
positions in Purchasing (Contract Managers) responsible for overseeing the contracts
process; 2) the assignment of Contract Liaisons within each department to support
contracting efforts; 3) a process reengineering study and implementation of resulting
improvements, including enhanced purchasing policies and procedures and training for
project managers.
Purchasing Contract Managers: Staffis proposing a reorganization of the Purchasing Section
with the 1996-98 Budget that will require the addition of two Contract Managers, with
related non-salary costs. Staff also recommends restructuring several of the position
responsibilities in Purchasing to provide the proper focus on the City’s high dollar, high value
purchases.
These proposed changes will provide staff with three Contract Managers in the Purchasing
Section dedicated to the contracts process. Each of these three employees would be assigned
to specific City departments, providing each department with a single point of contact. They
would be knowledgeable about the unique purchase requirements of their assigned
departments, would be responsible for overseeing their contracting efforts and would act as
an interface with Purchasing for all of the other requirements of their customer departments.
They would have expertise in the development of specifications, eliminating the potential
for poorly drafted and restrictive specifications that limit competition. They would oversee
the contract evaluation and selection process, ensuring scope and price changes are
CMR:211:96 Page 8 of 12
reasonable, decisions are properly documented, and that the lowest responsible bidder or
proposer is selected. They would also have expertise in contract negotiations, providing staff
the oppommity to employ their skill to reduce the costs of purchased materials and services.
Through aggressive contract negotiations, the City can (conservatively) obtain cost savings
of 1 to 2 percent of total contract dollars annually (approximately $150,000 to $300,000),
more than offsetting the added cost of the two new positions. In addition, they would review
City Manager Reports to ensure that all relevant contract information is provided to Council.
Lastly, their single-point accountability will make departmental compliance with purchasing
procedures more effective, minimizing the potential for abuse or fraud.
Department Contract Liaisons: Staff recommends the assignment of individuals within each
department as Contract Liaisons. These responsibilities would be added to the duties of their
existing positions. The Contract Liaisons would have extensive training in contracting,
giving them the ability to answer questions and provide direction to project managers
regarding contract documentation needs. The Contract Liaisons would complement
Purchasing’s Contract Managers and would be available to provide Purchasing with a focus
group that could be used to identify citywide issues and concerns involving contracting.
Finally, the Liaisons would support the development of, and any future modifications to, the
purchasing Policies and Procedures Manual and would help to coordinate procurement
training sessions.
Process Reen~neering: To accomplish the reengineering of the purchasing process, staffhas
formed a citywide steering committee. The committee will identify ways to simplify and
speed .up the contracting process. Staff plans to utilize tools such as "flow charts" and
"benchmarking" to identify process improvement opportunities.
Staff is currently updating the Purchasing Policies and Procedures Manual to make it more
useful, understandable and to provide better guidance to departments, as well as to
incorporate recommendations made by the City Auditor. Staff plans to incorporate the
process changes resulting from the reengineering efforts into the new manual.
Staff will also develop and conduct training sessions, in cooperation with the City Attorney’s
Office. These sessions will effectively communicate the changing role of Purchasing and the
improvement made from reengineering the purchasing and contracting process.
FINANCIAL SUPPORT FOR INVESTMENTS AND DEBT FINANCING PROJECTS
One of the recommendations made during the recent organizational review process, and
approved by the Council in 1994-95, was the elimination of the Treasury Manager
position. That position became vacant shortly after the organizational review was
completed, and is scheduled for elimination July 1, 1996. As a result of Finance
CMR:211:96 Page 9 of 12
Committee concerns regarding the investment area prompted by the problems in Orange
County, staff was asked to come back to the Council with various options for supporting
the investment area, including a review of Treasury staffing. Staff is now requesting that,
as an alternative to eliminating the Treasury Manager position, the position be converted
to a lower level Senior Financial Analyst. Staff believes that this request is prudent, given
the major new debt financing projects planned over the next several years and the need to
safeguard the City’s growing investment portfolio.
The Treasury function is now staffed by one Investment Analyst, reporting to the Finance
Manager. The Investment Analyst manages the City’s bank contract, manages the City’s
cash flow needs, invests City funds, manages debt service payments, and ensures the
City’s continued compliance with bond covenant requirements. The Finance Manager
ensures that investments are made in compliance with City policy, helps guide investment
strategy, supervises the Investment Analyst, as well as the Senior Financial Analyst in
charge of the Revenue Collections Office, manages debt financing projects, administers
the real property transfer tax appeals process, and coordinates department wide projects
in the, Administrative Services Department.
Several major debt financing projects have been identified for the next several years that
were not foreseen during the organization review. They include: the Golf Course Master
Plan implementation, acquisition and development of the former Los Altos Treatment Plant
site, implementation of a General Fund Infrastructure Management Plan (if approved by
Council), a new Storm Drainage Fund issuance, and (potentially) a Wastewater Plant
expansion issuance in a few years. In contrast to these anticipated projects, only one debt
financing occurred over the last four years, for Storm Drainage improvements. Work in
support of these major debt projects will require a dedicated Senior Financial Analyst. The
intensive work required to support these projects is beyond the resources available with
current staffing, without jeopardizing the level of oversight and analysis considered
prudent for the City’s $195 million investment portfolio.
Support for debt financing projects includes intensive financial analysis, prior to the time
that the debt issuance process actually begins. Once a large funding need has been
identified, a variety of steps are then required, including verifying the size of the project
and of funding needs; weighing other options, such as reducing the scope of the capital
project, extending the time frame over which the improvements are planned, seeking
alternative funding or revenues to fmance the project; and then, fmally, recommending
an optimal fmancing size, given revenues and other budget considerations. Once all
options have been explored, the actual financing process begins. This includes obtaining
a financial advisor, managing the work of the financial advisor on behalf of the City,
coordinating efforts for legal issues with the City Attorney’s Office and outside bond
counsel, coordinating any issues raised by the financial advisor with the operating
CMl1:211:96 Page 10 of 12
department and/or Public Works staff involved in the project, and keeping management
abreast of the implications of the recommended financing method as it develops.
In addition to additional debt responsibilities facing the Treasury staff, the Orange County
investment problems have reinforced the importance of performing various analytical tasks
on an annual basis to ensure the continued safety of City investments. These tasks include
an annual review of approved brokers, institutions, and instruments the City utilizes for
investment. The existing Investment Analyst cannot perform these tasks on an annual basis
unless some of her existing workload is shifted. By hiring this new position, all of the
existing debt responsibilities could be transferred, providing the Investment Analyst the
time to perform these important tasks.
Finally, this new position will provide backup to the existing Investment Analyst. In
addition, by taking away some of the existing debt service requirements that the Investment
Analyst is now responsible for, time will be freed up to do more analysis related to
investment strategies. With more time, a more aggressive management of daily bank
account balances can occur (e.g. staff can spend time investing bank balances in overnight
mutual funds to earn more interest), some increase in portfolio yield should occur.
The City’s portfolio has grown substantially over the last five years, meaning that investment
oversight is both more important and more complex than it once was. In 1990, the City’s
portfolio was $114 million, while it is currently about $195 million, a growth of over 70
percent in five years.
The major reasons for the portfolio growth include:
The growth of the Electric Fund Rate Stabilization Reserve has contributed
about $17 million to the portfolio over five years;
A commitment to fund a more aggressive infrastructure spending program for
the Utilities has increased the year to year carryover of capital projects by
about $8 million;
An increase in reserves in the Water, Gas, and Wastewater Collection Funds
has contributed to an almost $20 million increase in Utility cash;
Changes in the regulatory environment have added about $6 million to fund
landfill closure and post closure care costs in the Refuse Fund;
CMR:211:96 Page 11 of 12
o
o
An effort to fully fund employee’s long-term sick leave and worker’s
compensation liabilities added about $2.3 million to the General Benefits
Internal Service Fund over five years;
The Public Employees Retirement System (PERS) retirement rebate from the
State added over $6 million to the City’s portfolio;
The City’s vehicle replacement fund retained earnings have increased over $4
million. It was this growth that caused City staff to recommend operating
budget reductions through lower vehicle replacement charges to departments
in the 1994-95 and 1995-96 budgets. It is possible that additional reductions
will become necessary in the future to reduce this reserve to a more prudent
level;
The General Fund’s budget stabilization reserve has increased about $8.5
million over five years, due to prudent budget reduction efforts in the face of
State budget revenue reductions, as well as due to an end to the recession and
year end budget savings by departments.
PREPARED BY: Melissa Cavallo, Assistant Director, Administrative Services
Jim Steele, Finance Manager
DEPARTMENT HEAD APPROVAL:~~, ~
Emi~ Harrison
Deputy City Manager,
Administrative Services
CITY MANAGER APPROVAL:
CC: n/a
CMR:211:96 Page 12 of 12